CN110490975A - A kind of overall construction site plan production method based on orthography data - Google Patents

A kind of overall construction site plan production method based on orthography data Download PDF

Info

Publication number
CN110490975A
CN110490975A CN201910787092.5A CN201910787092A CN110490975A CN 110490975 A CN110490975 A CN 110490975A CN 201910787092 A CN201910787092 A CN 201910787092A CN 110490975 A CN110490975 A CN 110490975A
Authority
CN
China
Prior art keywords
data
control point
orthography
construction
image
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910787092.5A
Other languages
Chinese (zh)
Other versions
CN110490975B (en
Inventor
谢显龙
文舟
郭书涛
胡光全
何寿海
崔宇
熊峰
钟杰
廖正华
龚建伟
李国栋
梁旋
阮忠栎
黄俊峰
周磊
曹文
唐佳俊
袁恩培
原菊星
周莉
郭梅
刘衍君
李永康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Erju 1st Engineering Co Ltd
Original Assignee
China Railway Erju 1st Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Erju 1st Engineering Co Ltd filed Critical China Railway Erju 1st Engineering Co Ltd
Priority to CN201910787092.5A priority Critical patent/CN110490975B/en
Publication of CN110490975A publication Critical patent/CN110490975A/en
Application granted granted Critical
Publication of CN110490975B publication Critical patent/CN110490975B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F18/00Pattern recognition
    • G06F18/20Analysing
    • G06F18/25Fusion techniques
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • G06T17/05Geographic models
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T7/00Image analysis
    • G06T7/10Segmentation; Edge detection
    • G06T7/12Edge-based segmentation

Abstract

The present invention provides a kind of overall construction site plan production method based on orthography data, merge more information element, to improve total figure to the expressivity of project integral layout, it is preferably construction production service, it is higher and higher to solve to develop with construction trade information, construction information is delivered and the problem of the integrated level also the next high, and existing total figure has been unable to meet use demand.Be particularly suitable for project in construction construction general plan application, can true, intuitive, high definition show geometry site of the construction main structure at the scene in environment, belong to building engineering field.

Description

A kind of overall construction site plan production method based on orthography data
Technical field
The present invention relates to a kind of overall construction site plan production methods based on orthography data, are particularly suitable for building item Mesh is constructed general plan application, can true, intuitive, high definition show that geometric position of the construction main structure at the scene in environment is closed System, belongs to building engineering field.
Background technique
Currently, to improve, construction management of project is horizontal and management philosophy, each project in construction can make a construction General arrangement plan, for show the construction repair of this project, Design of Construction Organization, arrangement and method for construction, construction speed, The main contents such as resource planning, it can be seen that always flat figure production quality and depth directly affect item construction management to project construction It is horizontal.Currently, the production method of domestic construction main flat graph mainly has: first is that directlying adopt designing institute provides grating map as total Figure, the designed lines of the figure main presentation engineering project cannot check the geographical environment on route periphery;Second is that with the satellite of downloading Figure is used as map, is superimposed designed lines figure, the data changed plan with satellite image mostly several years ago, cannot grasp live ground very well The case where environment such as object, landforms, so that its expression effect is unsatisfactory;Third is that the involvement element of total figure is less, most total figures are only The position for having incorporated route red line, having faced facility greatly, can not intuitively express very much project applies a group arrangement.With construction row Industry information development is higher and higher, delivers construction information and the integrated level also the next high, and existing total figure has been unable to meet to use and need It asks, needs to merge more information element, be preferably construction production clothes to improve total figure to the expressivity of project integral layout Business.
Summary of the invention
The present invention provides a kind of overall construction site plan production method based on orthography data, to solve to apply with building Industrial and commercial bank's industry information development is higher and higher, delivers construction information and the integrated level also the next high, existing total figure, which has been unable to meet, to be made The problem of with demand.
To solve the above problems, such a overall construction site plan production method based on orthography data of proposed adoption, The specific method is as follows:
1) unmanned plane field acquisition image:
2) aerophotogrammetry data is handled:
3) realize that satellite image is merged with unmanned plane orthography;
The orthography of the satellite image of downloading and unmanned aerial survey production is saved under same file respectively, hereinafter referred to as Total map file;
Cutting edge processing is carried out to unmanned orthography using global mapper first, the underproof number in edge is carried out It deletes;
Data set is inlayed in arcgis creation, dataset name, the identical coordinate system of setting and pixel class are inlayed in input Type gets up two data fusions, and exports;
4) DOM and design drawing fusion
Design drawing is edited in CAD software, unwanted atural object data is deleted, retains required boundary lines of roads, Main structure line is saved into total figure file;
In global mapper, according to red line figure and main structure coordinate that designing institute provides, setting and orthography Identical coordinate system carries out geographical calibration to design drawing;
By after calibration image and design drawing imported into cad simultaneously, according to coordinate matching by DOM data and design drawing into Row association integrates, and the ratio of the two data is 1:1;
5) face building for facility BIM model greatly
Building model in conjunction with the case where live construction land, needed for being established by revit software partitioning;
6) Enhanced expressing of multisource data fusion
The BIM Model Fusion of facility will be faced greatly into total figure;In conjunction with the deployment at scene, drafting road changes shifting, sidewalk is planned, Construction red line information;Using the mobilization of mind map combing project, it is integrated into total figure in the form of highly concentrated contract drawing; It is arranged according to applying group, classifying rationally work area;
In preceding method, unmanned plane field acquisition image specific requirement is as follows:
Weather, surrounding enviroment in conjunction with construction site select the flight optimization period to carry out aerophotogrammetric field work;
According to the size for surveying area, Reasonable Arrangement photo control point, photo control point is laid alternate using 500mm*500mm black-white colors Navigation mark measures the coordinate of each photo control point as land marking;
Aerial survey task is set, place relatively gentler for city or topography, around without high-voltage line, large-scale wireless base station, Signal tower, image is acquired using full-automatic flight;Mountain area is acquired using manual offline mode.
In preceding method, it is as follows that aerophotogrammetry data handles detailed process:
Aerophotogrammetry data pretreatment, checks whether aerial images have underproof image, and unqualified image is deleted;It checks Whether the pos data of photo control point are qualified;The lower product of empty three mass is selected, is quickly pre-processed, entire survey area is detected Data whether all standing, if having cavity, garland situation;If there is above situation, carries out mending survey or resurvey;
After pretreatment is qualified, into aerophotogrammetry data process flow, raw video data and the pos data at control point are imported In aerial survey software, according to the coordinate system where pos data, coordinate parameters are set, it is ensured that image and pos data coordinates system One;
Control point is oriented, in empty trilete rays, according to the number at control point, successively control point is carried out at thorn point Reason, the crosshair centering of all images occurred in specially same control point to photo control point center.
Compared with prior art, the method for the invention has that image collection speed is fast, the with short production cycle, update cycle Fastly, image definition is high, really can intuitively the express major project positional relationship of environment, required at low cost, easy at the scene In promote and apply many advantages, such as, for the total figure of small scene, directlys adopt aerial survey of unmanned aerial vehicle technology and obtain high definition orthography As the basic data of total figure, project longer for route is merged using satellite image with unmanned plane orthography, really Protect large scene effective use, line midline and the mode for facing the displaying of Facilities Construction position high definition greatly.Company is multiple at present Application, the highly recognition for obtaining construction unit, establishing unit and designing unit, the construction to engineering project are carried out in project General arrangement and deployment have important directive significance and promotional value.
Detailed description of the invention
Fig. 1 is flow chart of the invention.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, the present invention is made into one below in conjunction with attached drawing The detailed description of step, it should be understood that described herein specific examples are only used to explain the present invention, is not used to limit this hair It is bright.
Embodiment
Referring to Fig.1, the present embodiment provides a kind of overall construction site plan production method based on orthography data, specific sides Method is as follows:
1) unmanned plane field acquisition image:
Weather, surrounding enviroment in conjunction with construction site select the flight optimization period to carry out aerophotogrammetric field work;
According to the size for surveying area, Reasonable Arrangement photo control point, photo control point is laid alternate using 500mm*500mm black-white colors Navigation mark measures the coordinate of each photo control point as land marking;
Aerial survey task is set, place relatively gentler for city or topography, around without high-voltage line, large-scale wireless base station, Signal tower, image is acquired using full-automatic flight;Mountain area is acquired using manual offline mode.
2) aerophotogrammetry data process flow:
The production of the present embodiment orthography selects pix4d mapper aerial survey software to be handled, which has processing speed The advantages that degree is fast, precision is high, automatic processing;
Aerophotogrammetry data pre-processes first, in order to ensure aerophotogrammetry data process flow smoothly completes, needs to do following inspection: one It is to check whether aerial images have underproof image, such as fuzzy pictures, sky, is accordingly to be regarded as substandard product, needs to delete;Two It is to check whether the pos data of photo control point are qualified;Third is that selecting the lower product of empty three mass, quickly pre-processed, is detected The entire data for surveying area whether all standing, if having situations such as cavity, garland.If there is three cases above, mended It surveys or resurveys;
After pretreatment is qualified, into aerophotogrammetry data process flow, raw video data and the pos data at control point are imported In aerial survey software, according to the coordinate system where pos data, coordinate parameters are set, it is ensured that image and pos data coordinates system One;
Control point is oriented, in empty trilete rays, according to the number at control point, successively control point is carried out at thorn point Reason, the crosshair centering of all images occurred in specially same control point to photo control point center.
According to construction demand, the DOM data of suitable accuracy and required digital product is selected to be produced;
3) realize that satellite image is merged with unmanned plane orthography;
The orthography of the satellite image of downloading and unmanned aerial survey production is saved under same file (hereinafter referred to as respectively Total map file) in;
Cutting edge processing is carried out to unmanned orthography using global mapper first, the underproof number in edge is carried out It deletes;
Data set is inlayed in arcgis creation, dataset name, the identical coordinate system of setting and pixel class are inlayed in input Type gets up two data fusions, and exports;
4) DOM and design drawing fusion
Design drawing is edited in CAD software, unwanted atural object data is deleted, retains required boundary lines of roads, Main structure line is saved into total figure file;
In global mapper, according to red line figure and main structure coordinate that designing institute provides, setting and orthography Identical coordinate system carries out geographical calibration to design drawing;
By after calibration image and design drawing imported into cad simultaneously, according to coordinate matching by DOM data and design drawing into Row association integrates, and the ratio of the two data is 1:1, measures convenient for the geometry in later period;
5) face building for facility BIM model greatly
According to owner and the requirement of company's temporary engineering standardized construction, the establishment of integration project personnel, using revit software Building model needed for piecemeal establishes project management department, mixing station, reinforcement yard etc.;
Face the case where building construction land in conjunction with scene, project guard station, mix will will be built by revit on-link mode (OLM) respectively It stands, the threedimensional model of reinforcement yard;
6) Enhanced expressing of multisource data fusion
The BIM Model Fusion of facility will be faced greatly into total figure;
In conjunction with the deployment at the scene at scene, draws road and change the information such as shifting, sidewalk planning, construction red line;
Using the mobilization of mind map combing project, it is integrated into total figure in the form of highly concentrated contract drawing;
It is arranged according to applying group, classifying rationally work area.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (3)

1. a kind of overall construction site plan production method based on orthography data, which is characterized in that the specific method is as follows:
1) unmanned plane field acquisition image:
2) aerophotogrammetry data is handled:
3) realize that satellite image is merged with unmanned plane orthography;
The orthography of the satellite image of downloading and unmanned aerial survey production is saved under same file respectively, hereinafter referred to as total figure File;
Cutting edge processing is carried out to unmanned orthography using globalmapper first, the underproof number in edge is deleted;
Data set is inlayed in arcgis creation, dataset name, the identical coordinate system of setting and type of pixel are inlayed in input will Two data fusions are got up, and are exported;
4) DOM and design drawing fusion
Design drawing is edited in CAD software, unwanted atural object data is deleted, retains required boundary lines of roads, main body Structure lines are saved into total figure file;
In globalmapper, according to red line figure and main structure coordinate that designing institute provides, it is arranged identical as orthography Coordinate system, to design drawing carry out geographical calibration;
It by the image and design drawing after calibration while importeding into cad, is closed DOM data with design drawing according to coordinate matching Connection integrates, and the ratio of the two data is 1:1;
5) face building for facility BIM model greatly
Building model in conjunction with the case where live construction land, needed for being established by revit software partitioning;
6) Enhanced expressing of multisource data fusion
The BIM Model Fusion of facility will be faced greatly into total figure;In conjunction with the deployment at scene, draws road and change shifting, sidewalk planning, construction Red line information;Using the mobilization of mind map combing project, it is integrated into total figure in the form of highly concentrated contract drawing;According to Apply a group arrangement, classifying rationally work area.
2. a kind of overall construction site plan production method based on orthography data according to claim 1, which is characterized in that Unmanned plane field acquisition image specific requirement is as follows:
Weather, surrounding enviroment in conjunction with construction site select the flight optimization period to carry out aerophotogrammetric field work;
According to the size for surveying area, Reasonable Arrangement photo control point, photo control point lays the navigation mark alternate using 500mm*500mm black-white colors As land marking, and measure the coordinate of each photo control point;
Aerial survey task is set, for city or the relatively gentler place of topography, around without high-voltage line, large-scale wireless base station, signal Tower, image is acquired using full-automatic flight;Mountain area is acquired using manual offline mode.
3. a kind of overall construction site plan production method based on orthography data according to claim 1, which is characterized in that It is as follows that aerophotogrammetry data handles detailed process:
Aerophotogrammetry data pretreatment, checks whether aerial images have underproof image, and unqualified image is deleted;It checks as control Whether the pos data of point are qualified;The lower product of empty three mass is selected, is quickly pre-processed, the entire data for surveying area are detected Whether all standing, if having cavity, garland situation;If there is above situation, carries out mending survey or resurvey;
After pretreatment is qualified, into aerophotogrammetry data process flow, raw video data and the pos data at control point are imported into aerial survey In software, according to the coordinate system where pos data, coordinate parameters are set, it is ensured that image and pos data coordinate system are unified;
Control point is oriented, in empty trilete rays, according to the number at control point, thorn point processing successively is carried out to control point, The crosshair centering of all images occurred in specially same control point is to photo control point center.
CN201910787092.5A 2019-08-25 2019-08-25 Construction general plane graph manufacturing method based on orthographic image data Active CN110490975B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910787092.5A CN110490975B (en) 2019-08-25 2019-08-25 Construction general plane graph manufacturing method based on orthographic image data

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910787092.5A CN110490975B (en) 2019-08-25 2019-08-25 Construction general plane graph manufacturing method based on orthographic image data

Publications (2)

Publication Number Publication Date
CN110490975A true CN110490975A (en) 2019-11-22
CN110490975B CN110490975B (en) 2022-11-01

Family

ID=68553772

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910787092.5A Active CN110490975B (en) 2019-08-25 2019-08-25 Construction general plane graph manufacturing method based on orthographic image data

Country Status (1)

Country Link
CN (1) CN110490975B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111260563A (en) * 2020-03-15 2020-06-09 国科天成(北京)科技有限公司 Video acquisition and transmission system based on orthographic technology
CN112150626A (en) * 2020-08-25 2020-12-29 金华送变电工程有限公司 Three-dimensional modeling method and system for temporary construction
CN112258157A (en) * 2020-10-22 2021-01-22 上海建科工程咨询有限公司 Novel urbanization construction management system
CN112862966A (en) * 2021-02-20 2021-05-28 中煤航测遥感集团有限公司 Method, device and equipment for constructing three-dimensional model of earth surface and storage medium
CN114782619A (en) * 2022-01-26 2022-07-22 中交二公局第三工程有限公司 BIM technology-based visual safety facility circulation management method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009116806A (en) * 2007-11-09 2009-05-28 Hitachi-Ge Nuclear Energy Ltd Progress management method, program and progress management apparatus
CN106952023A (en) * 2017-03-01 2017-07-14 广东中建普联科技股份有限公司 Construction project Fast Quasi construction method and system
CN107679820A (en) * 2017-08-30 2018-02-09 深圳市易联智道科技有限公司 Construction Schedule management method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009116806A (en) * 2007-11-09 2009-05-28 Hitachi-Ge Nuclear Energy Ltd Progress management method, program and progress management apparatus
CN106952023A (en) * 2017-03-01 2017-07-14 广东中建普联科技股份有限公司 Construction project Fast Quasi construction method and system
CN107679820A (en) * 2017-08-30 2018-02-09 深圳市易联智道科技有限公司 Construction Schedule management method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张颖秋: "无人机航空摄影测量在地形图测绘中的应用", 《中国非金属矿工业导刊》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111260563A (en) * 2020-03-15 2020-06-09 国科天成(北京)科技有限公司 Video acquisition and transmission system based on orthographic technology
CN111260563B (en) * 2020-03-15 2020-12-01 国科天成(北京)科技有限公司 Video acquisition and transmission system based on orthographic technology
CN112150626A (en) * 2020-08-25 2020-12-29 金华送变电工程有限公司 Three-dimensional modeling method and system for temporary construction
CN112258157A (en) * 2020-10-22 2021-01-22 上海建科工程咨询有限公司 Novel urbanization construction management system
CN112862966A (en) * 2021-02-20 2021-05-28 中煤航测遥感集团有限公司 Method, device and equipment for constructing three-dimensional model of earth surface and storage medium
CN112862966B (en) * 2021-02-20 2024-01-26 中煤航测遥感集团有限公司 Method, device, equipment and storage medium for constructing surface three-dimensional model
CN114782619A (en) * 2022-01-26 2022-07-22 中交二公局第三工程有限公司 BIM technology-based visual safety facility circulation management method

Also Published As

Publication number Publication date
CN110490975B (en) 2022-11-01

Similar Documents

Publication Publication Date Title
CN110490975A (en) A kind of overall construction site plan production method based on orthography data
CN103884321B (en) A kind of remote sensing image becomes figure technique
CN106651609B (en) Mineral resource development environment remote sensing monitoring auxiliary information system and method
CN111724477A (en) Method for constructing multi-level three-dimensional terrain model through multi-source data fusion
CN110728752A (en) Construction method of three-dimensional terrain scene model of road
CN108921943A (en) A kind of road threedimensional model modeling method based on lane grade high-precision map
CN109902332A (en) A kind of power matching network system based on Three-dimension
CN103136789A (en) Traffic accident road base map information processing method based on topographic map and image
CN104679822A (en) Geographic national condition field investigation and plotting method
CN104281746A (en) Method for generating traffic safety road characteristic graphs on basis of point-cloud
CN107167815A (en) The automatic creation system and method for a kind of highway road surface line number evidence
CN112733247A (en) Large project field planning method
Aringer et al. Bavarian 3D building model and update concept based on LiDAR, image matching and cadastre information
CN107102339A (en) A kind of automatic generation method of above-ground route data
CN112729259A (en) Intelligent mapping method for three-dimensional model of strip mine
Akob et al. Deployment of GIS+ BIM in the construction of Pan Borneo Highway Sarawak, Malaysia
KR102424571B1 (en) Automatically conversion system of GIS data
CN102495879A (en) Industrial overhead pipeline measurement method based on ground LIDAR (Light Detection And Ranging)
CN103700063A (en) Integrated topographic map quick forming method based on high-definition satellite image
Alshaiba et al. Automatic manhole extraction from MMS data to update basemaps
CN107085219A (en) A kind of automatic creation system of above-ground route data
CN110490788A (en) A kind of quick earth clearance method based on orthography data
CN115375864B (en) Unmanned aerial vehicle-based high-speed railway completion acceptance method
CN106772433A (en) Building line picture generation method based on airborne laser radar data
CN115628720A (en) Intelligent three-dimensional topographic map surveying and mapping method and system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant