CN109636675A - A kind of management method and system of the construction site based on artificial intelligence - Google Patents

A kind of management method and system of the construction site based on artificial intelligence Download PDF

Info

Publication number
CN109636675A
CN109636675A CN201811519714.8A CN201811519714A CN109636675A CN 109636675 A CN109636675 A CN 109636675A CN 201811519714 A CN201811519714 A CN 201811519714A CN 109636675 A CN109636675 A CN 109636675A
Authority
CN
China
Prior art keywords
project amount
target
planned target
resources
reason
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811519714.8A
Other languages
Chinese (zh)
Inventor
刘威鑫
徐峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Hefu Artificial Intelligence Technology (group) Co Ltd
Original Assignee
Shanghai Hefu Artificial Intelligence Technology (group) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Hefu Artificial Intelligence Technology (group) Co Ltd filed Critical Shanghai Hefu Artificial Intelligence Technology (group) Co Ltd
Priority to CN201811519714.8A priority Critical patent/CN109636675A/en
Publication of CN109636675A publication Critical patent/CN109636675A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Educational Administration (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses the management method and system of a kind of construction site based on artificial intelligence, the method is the following steps are included: calculate the project amount target that corresponding buildings and resources are equipped with demand or can complete according to plan according to the calculating of existing buildings and resources according to existing project amount planned target;Actual performance and plan to project amount complete target and carry out analysis comparison;The analysis of causes and control are carried out according to the difference of the performance of project amount and planned target.It can accordingly be equipped with the buildings and resources of the project amount size by quantities calculation and how many project amount can be completed according to the calculating of existing buildings and resources;Entire construction process and each construction stage can be managed and the later period is to the rectifications of mistake and the retrospect of responsibility;The intelligent management to engineering is realized and then progress, quality, the cost to entire work progress are managed.

Description

A kind of management method and system of the construction site based on artificial intelligence
Technical field
The present invention relates to INTELLIGENT BUILDING TECHNIQUE field more particularly to a kind of pipes of the construction site based on artificial intelligence Manage method and system.
Background technique
It is many kinds of that the construction engineering project of building trade is related to field, and engineering is complicated, to entire project construction mistake Thread management is difficult.It is existing to be all that building constructor arranges construction personnel to march into the arena to start to construct after being connected to engineering project, but for The quantity of the trade categories of construction personnel and each work post construction personnel are by empirically determined or by first arranging People's construction, then mends construction personnel after according to construction speed;According to the size to each engineering project and it cannot plan Intelligentized calculating analysis is carried out at target, intelligent comparison point can not be carried out to entire work progress or each construction stage Analysis and rectification and Liability Retroact, are unfavorable for the intelligent management of engineering project and the progress of building trade.
Summary of the invention
It is an object of the invention to overcome the deficiencies of the prior art and provide a kind of construction sites based on artificial intelligence Management method and system, solve defect existing for now current construction-engineering project construction management.
The purpose of the present invention is achieved through the following technical solutions: a kind of construction site based on artificial intelligence Management method, the method the following steps are included:
Corresponding buildings and resources, which are calculated, according to existing project amount planned target is equipped with demand or according to existing buildings and resources Calculate the project amount target that can be completed according to plan;
Actual performance and plan to project amount complete target and carry out analysis comparison;
The analysis of causes and control are carried out according to the difference of the performance of project amount and planned target.
Buildings and resources include the human resources of construction, realize that the material resource of project amount needs and logistics are mating Resource.
The human resources of construction include the number of workers of building trades type and each work post;The material money Source includes the quantity of building material type and every kind of material;The logistics necessary resources include that worker's wearing is eaten material and matched Standby and equipment.
Calculating corresponding buildings and resources to be equipped with demand according to existing project amount target includes the following contents:
Need the process completed to split existing project amount planned target, calculate the building trades type of needs with And the building material number of species needed;
It is split according to workload of the project amount planned target to each process, calculates each process and need work post Number of workers and the material quantity for needing type;
Go out the matched task arrangement of logistics according to project amount planned target, human resources object and material Resource Calculation.
The method further includes splitting into multiple phase targets according to engineering phase to project amount planned target, then root It compares and audits with each phase targets according to the actual performance in project amount each stage, realize the construction to each stage It is managed.
Carrying out the analysis of causes and control according to the difference of the performance of project amount and planned target includes the following contents:
The reason of judgement is without completing planned target according to the analysis and contrast of the results;
To causing the reason of not completing planned target to carry out Liability Retroact;
The reason of no completion planned target, analyze and rectify and improve to the mistake of entire project amount work progress.
Include the following contents to causing the reason of not completing planned target to carry out Liability Retroact:
The comparison that progress and target advance are actually accomplished according to project amount judges the reason of delaying project progress, and to this Reason carries out Liability Retroact;
The comparison of quality and plan quality is completed according to project amount, judgement the process of construction quality occurs and completes the work The work post of sequence simultaneously carries out Liability Retroact;
According to the comparison of the Material Cost of project amount actual use and planning material cost, judgement exceeds planning material cost Process and complete the work post of the process and carry out Liability Retroact.
A kind of management system of the construction site based on artificial intelligence, it includes computing module, for according to existing Project amount planned target calculates corresponding buildings and resources outfit demand or according to plan can be complete according to the calculating of existing buildings and resources At project amount target;Contrast module completes target with plan for the actual performance to project amount and carries out analysis comparison; Management control module, for carrying out the analysis of causes and control according to the performance of project amount and the difference of planned target.
Computing module includes split cells and computing unit;
Split cells is used to need the process completed split and according to project amount existing project amount planned target Planned target splits the workload of each process;
Computing unit is used to calculate the quantity for needing work post and material kind according to existing project amount process split result Class quantity, and go out worker's demand of each process work post and the material requirement of type according to the workload computing of each process Amount.
Management control module includes reason trace-back unit, Liability Retroact unit and mistake rectification unit;
Reason trace-back unit is used for causing not reach planned target the reason of progress in entire project amount work progress Retrospect;
Liability Retroact unit is used to carry out the responsibility for not reaching planned target reason in entire project amount work progress Retrospect;
Mistake rectification unit is used to carry out the details for not reaching planned target in entire project amount work progress Analysis is summarized and is improved.
The beneficial effects of the present invention are: a kind of intelligent management method and system of construction site, can pass through work Journey amount calculate accordingly be equipped with the project amount size buildings and resources and according to existing buildings and resources calculating can complete how much Project amount;Entire construction process and each construction stage can be managed and rectification and duty of the later period to mistake The retrospect appointed;It is realized and then progress, quality, the cost to entire work progress are managed and the intelligence of engineering is managed Reason.
Detailed description of the invention
Fig. 1 is the flow chart of the method for the present invention.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.The present invention being usually described and illustrated herein in the accompanying drawings is implemented The component of example can be arranged and be designed with a variety of different configurations.
Therefore, the detailed description of the embodiment of the present invention provided in the accompanying drawings is not intended to limit below claimed The scope of the present invention, but be merely representative of selected embodiment of the invention.Based on the embodiments of the present invention, this field is common Technical staff's every other embodiment obtained without creative efforts belongs to the model that the present invention protects It encloses.
It should also be noted that similar label and letter indicate similar terms in following attached drawing, therefore, once a certain Xiang Yi It is defined in a attached drawing, does not then need that it is further defined and explained in subsequent attached drawing.
In the description of the present invention, it should be noted that the orientation of the instructions such as term " on ", "inner", "outside" or position are closed System for be based on the orientation or positional relationship shown in the drawings or the invention product using when the orientation usually put or position close System, is merely for convenience of description of the present invention and simplification of the description, rather than the device or element of indication or suggestion meaning must have Specific orientation is constructed and operated in a specific orientation, therefore is not considered as limiting the invention.
In the description of the present invention, it is also necessary to which explanation is unless specifically defined or limited otherwise, term " setting ", " installation ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integrally connect It connects;It can be mechanical connection, be also possible to be electrically connected;It can be directly connected, can also indirectly connected through an intermediary, it can To be the connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood with concrete condition Concrete meaning in the present invention.
Technical solution of the present invention is described in further detail with reference to the accompanying drawing, but protection scope of the present invention is not limited to It is as described below.
As shown in Figure 1, a kind of management method of the construction site based on artificial intelligence, the method includes following Step:
S1, corresponding buildings and resources outfit demand is calculated according to existing project amount planned target or is provided according to existing building Source calculates the project amount target that can be completed according to plan;
S2, analysis comparison is carried out to the actual performance and plan completion target of project amount;
S3, the analysis of causes and control are carried out according to the performance of project amount and the difference of planned target.
Buildings and resources include the human resources of construction, realize that the material resource of project amount needs and logistics are mating Resource.
The human resources of construction include the number of workers of building trades type and each work post;Material resource includes The quantity of building material type and every kind of material;Logistics necessary resources include worker wearing eat material be equipped with and transport match It is standby.
Calculating corresponding buildings and resources to be equipped with demand according to existing project amount target includes the following contents:
A1, it needs the process completed to split existing project amount planned target, calculates the building trades kind of needs The building material number of species of class and needs;
A2, it is split according to workload of the project amount planned target to each process, calculates each process and need work The number of workers of kind and the material quantity for needing type;
A3, the matched task arrangement of logistics is gone out according to project amount planned target, human resources object and material Resource Calculation.
Pass through acquisition preferably for the human resources of construction with the work of a certain number of construction personnel of each work post Make the average operation efficiency that each work post construction personnel is calculated based on efficiency;Then go out to complete according to average operation efficiency calculation Construction personnel's quantity that certain road engineering process needs, and then calculate and each of engineering project needs are completed according to planned target The manpower that the construction personnel's number and then clearly entire engineering project that work post needs need to put into;For material resource according to engineering The type (such as silt, cement, brick, stone, steel) for the construction material that the size and loss calculation of project need and The demand of every kind of material;The transport of logistics is calculated to building according to the planned target of project progress for logistics necessary resources Delivery arrangement (quantity and number, the quantity of haulage vehicle, type, row of such as daily transport material into construction site of material Journey arrangement of time etc.), the clothes of the construction in logistics necessary resources, peace are calculated according to construction personnel's quantity that engineering project needs The quantity of full cap and communication equipment, the daily food materials quantity of construction personnel, residential placement etc..
Preferably, calculating the project amount target that can be completed according to plan according to existing buildings and resources includes the following contents:
B1, the engineering process 1 completed is determined to according to existing construction material Resource Calculation and completes these engineerings The performance 1 of process 1;
B2, the engineering process 2 for being determined to complete is calculated according to existing work post and the quantity of each work post construction personnel And complete the performance 2 of these engineering process 2;
B3, judge 2 quantity of engineering process 1 and engineering process number, select the few engineering process of quantity;Judge engineering work The size of the performance 2 of the performance 1 and engineering process 2 of sequence 1, the performance for the engineering process for selecting performance small;
B4, according to the engineering process of selection and the performance of engineering process obtain based on existing buildings and resources can be complete At engineering.
Such as: 5 engineering process can only be done according to existing construction material resource, each engineering process can be only done 60%; And only have the construction personnel of 4 work posts that can only do 4 engineering process according to existing construction human resources, according to each The performance of how much each engineering process of work post construction personnel is 70%;Then completion can be calculated according to existing buildings and resources 4 engineering process, and the performance of each engineering process can only achieve 60% engineering.
The method further includes splitting into multiple phase targets according to engineering phase to project amount planned target, then root It compares and audits with each phase targets according to the actual performance in project amount each stage, realize the construction to each stage It is managed.
By carrying out interim fractionation available each stage to entire engineering project and quantities calculation target The phase targets of actual performance and each stage;Then according to the actual performance in project amount each stage and each stage Target compares, it will be able to obtain the difference of each stage actual performance and phase targets;Such as, some in some stage The schedule or completion quality of process do not reach the phase targets, then can be by determining that the work post for being responsible for the process be applied The working condition of worker person and each construction personnel are completed to the retrospect of responsibility and to follow-up phase work plan in turn It improves.
The performance in each stage can be audited, entirety is finally carried out after the completion to entire construction project Audit;By realizing audit stage by stage and finally audit to staged construction process, stage auditing result and entirety The management control of auditing result and the Liability Retroact of more convenient pair of problem.
Step S3 the analysis of causes carried out according to the difference of the performance of project amount and planned target and control include with Lower content:
The reason of S31, according to the analysis and contrast of the results judgement are without completion planned target;Main judgement is without completing plan mesh The reason of mark is building material resource or construction manpower reason i.e. construction personnel artificial origin;
It such as, is that insufficient or construction personnel's working efficiency is low leads to dragging for schedule because building material resource is equipped with Prolong;The problem of the problem of being because of building material sole mass or construction personnel's construction technology, causes completion quality not reach Mark.
S32, to causing the reason of not completing planned target to carry out Liability Retroact;
S33, analysis is carried out to the reason of no completion planned target and the mistake of entire project amount work progress is carried out Rectification.
By to cause actual performance with the analysis of the appearance difference reason of planned target, and the duty to the reason Retrospect is appointed to realize the construction such as project progress, quality and cost completed to entire construction project without target according to schedule It is required that carrying out intelligent management, engineering efficiency and construction quality are greatly improved, it is also further perfect that entire engineering is applied The management of work process is managed.
Step S32 includes the following contents to causing the reason of not completing planned target to carry out Liability Retroact:
S321, the comparison that progress and target advance are actually accomplished according to project amount judge the reason of delaying project progress, and Liability Retroact is carried out to the reason;
There is the process of construction quality and complete in S322, the comparison that quality and plan quality are completed according to project amount, judgement At the process work post and carry out Liability Retroact;
S323, the Material Cost according to project amount actual use and the comparison of planning material cost, judgement is beyond plan object Expect the process of cost and completes the work post of the process and carry out Liability Retroact.
It is that building material resource is equipped with and insufficient either applies e.g. preferably to causing the reason of not completing planned target Work person works' low efficiency leads to the delay of schedule;The problem of being building material sole mass either construction personnel's construction The problem of technology, causes to complete quality dissatisfaction;Progress responsibility defines and Liability Retroact.
A kind of management system of the construction site based on artificial intelligence, it includes computing module, for according to existing Project amount planned target calculates corresponding buildings and resources outfit demand or according to plan can be complete according to the calculating of existing buildings and resources At project amount target;Contrast module completes target with plan for the actual performance to project amount and carries out analysis comparison; Management control module, for carrying out the analysis of causes and control according to the performance of project amount and the difference of planned target.
Computing module includes split cells and computing unit;
Split cells is used to need the process completed split and according to project amount existing project amount planned target Planned target splits the workload of each process;
Computing unit is used to calculate the quantity for needing work post and material kind according to existing project amount process split result Class quantity, and go out worker's demand of each process work post and the material requirement of type according to the workload computing of each process Amount.
Management control module includes reason trace-back unit, Liability Retroact unit and mistake rectification unit;
Reason trace-back unit is used for causing not reach planned target the reason of progress in entire project amount work progress Retrospect;
Liability Retroact unit is used to carry out the responsibility for not reaching planned target reason in entire project amount work progress Retrospect;
Mistake rectification unit is used to carry out the details for not reaching planned target in entire project amount work progress Analysis is summarized and is improved.
The foregoing is merely the present invention/invention embodiments, are not intended to limit the present invention/invention the scope of the patents, all It is directly or indirectly to be transported using equivalent structure or equivalent flow shift made by the present invention/description of the invention and accompanying drawing content It similarly include in the present invention/invention scope of patent protection used in other related technical areas.

Claims (10)

1. a kind of management method of the construction site based on artificial intelligence, it is characterised in that: the method includes following Step:
Corresponding buildings and resources, which are calculated, according to existing project amount planned target is equipped with demand or according to the calculating of existing buildings and resources The project amount target that can be completed according to plan;
Actual performance and plan to project amount complete target and carry out analysis comparison;
The analysis of causes and control are carried out according to the difference of the performance of project amount and planned target.
2. a kind of management method of construction site based on artificial intelligence according to claim 1, it is characterised in that: The buildings and resources include the human resources of construction, realize material resource and the mating money of logistics that the project amount needs Source.
3. a kind of management method of construction site based on artificial intelligence according to claim 2, it is characterised in that: The human resources of the construction include the number of workers of building trades type and each work post;The material resource Quantity including building material type and every kind of material;The logistics necessary resources include that worker's wearing eats material outfit And equipment.
4. a kind of management method of construction site based on artificial intelligence according to claim 3, it is characterised in that: It includes the following contents that the basis, which has project amount target to calculate corresponding buildings and resources to be equipped with demand:
It needs the process completed to split existing project amount planned target, calculate the building trades type of needs and needs The building material number of species wanted;
It is split according to workload of the project amount planned target to each process, calculates the worker that each process needs work post Quantity and the material quantity for needing type;
Go out the matched task arrangement of logistics according to project amount planned target, human resources object and material Resource Calculation.
5. a kind of management method of construction site based on artificial intelligence according to claim 1, it is characterised in that: The method further includes splitting into multiple phase targets according to engineering phase to project amount planned target, then according to project amount The actual performance in each stage is compared and is audited with each phase targets, and realization carries out pipe to the construction in each stage Reason.
6. a kind of management method of construction site based on artificial intelligence according to claim 1, it is characterised in that: Described carries out the analysis of causes and manages to include the following contents according to the performance of project amount and the difference of planned target:
The reason of judgement is without completing planned target according to the analysis and contrast of the results;
To causing the reason of not completing planned target to carry out Liability Retroact;
The reason of no completion planned target, analyze and rectify and improve to the mistake of entire project amount work progress.
7. a kind of management method of construction site based on artificial intelligence according to claim 6, it is characterised in that: Described includes the following contents to causing the reason of not completing planned target to carry out Liability Retroact:
The comparison that progress and target advance are actually accomplished according to project amount judges the reason of delaying project progress, and to the reason Carry out Liability Retroact;
The comparison of quality and plan quality is completed according to project amount, judgement the process of construction quality occurs and completes the process Work post simultaneously carries out Liability Retroact;
According to the comparison of the Material Cost of project amount actual use and planning material cost, judgement exceeds the work of planning material cost It sequence and completes the work post of the process and carries out Liability Retroact.
8. a kind of management system of the construction site based on artificial intelligence, it is characterised in that: it includes computing module, is used for Corresponding buildings and resources, which are calculated, according to existing project amount planned target is equipped with demand or according to the calculating of existing buildings and resources based on Draw the project amount target that can be completed;Contrast module, for the actual performance and plan completion target progress to project amount Analysis comparison;Management control module, for the difference according to the performance of project amount and planned target carry out the analysis of causes with And control.
9. a kind of management system of construction site based on artificial intelligence according to claim 8, it is characterised in that: The computing module includes split cells and computing unit;
The split cells is used to need the process completed split and according to engineering existing project amount planned target Amount planned target splits the workload of each process;
The computing unit is used to calculate the quantity and material for needing work post according to existing project amount process split result Number of species, and go out worker's demand of each process work post and the material need of type according to the workload computing of each process The amount of asking.
10. a kind of management system of construction site based on artificial intelligence according to claim 8, feature exist In: the management control module includes reason trace-back unit, Liability Retroact unit and mistake rectification unit;
The reason trace-back unit be used for caused in entire project amount work progress the reason of not reaching planned target into Row retrospect;
The Liability Retroact unit be used for do not reach in entire project amount work progress the responsibility of planned target reason into Row retrospect;
The described mistake rectification unit be used for do not reach in entire project amount work progress the details of planned target into Row analysis is summarized and is improved.
CN201811519714.8A 2018-12-12 2018-12-12 A kind of management method and system of the construction site based on artificial intelligence Pending CN109636675A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811519714.8A CN109636675A (en) 2018-12-12 2018-12-12 A kind of management method and system of the construction site based on artificial intelligence

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811519714.8A CN109636675A (en) 2018-12-12 2018-12-12 A kind of management method and system of the construction site based on artificial intelligence

Publications (1)

Publication Number Publication Date
CN109636675A true CN109636675A (en) 2019-04-16

Family

ID=66073294

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811519714.8A Pending CN109636675A (en) 2018-12-12 2018-12-12 A kind of management method and system of the construction site based on artificial intelligence

Country Status (1)

Country Link
CN (1) CN109636675A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110111659A (en) * 2019-05-22 2019-08-09 蓝莓极客(武汉)智能科技有限公司 It is a kind of that system is constructed based on the teaching of electronic building blocks multifunction electronic module
CN110796335A (en) * 2019-09-18 2020-02-14 广东电网有限责任公司审计中心 Audit project implementation quality monitoring system and equipment based on data analysis
CN111027803A (en) * 2019-11-01 2020-04-17 国艺天成建设工程技术有限公司 Construction management method and construction management system
CN113283879A (en) * 2021-06-21 2021-08-20 华电重工股份有限公司 Method and device for determining construction amount, electronic equipment and readable storage medium
CN115511430A (en) * 2022-08-17 2022-12-23 福建永旺建设集团有限公司 Wisdom building site management platform based on thing networking
CN118378854A (en) * 2024-06-21 2024-07-23 江西省公路工程有限责任公司 Building construction management method and system based on two-dimension code
US12054160B2 (en) 2019-02-07 2024-08-06 2 Circle, Incorporated Reconstruction and assessment of proficiency in an integrated debrief by a server in a network

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106875159A (en) * 2017-02-17 2017-06-20 中国十七冶集团有限公司 The city integrated piping lane construction total management system of cast-in-place structural
CN107169747A (en) * 2017-06-19 2017-09-15 郑州航空工业管理学院 A kind of management system of various engineering of civil construction
CN107679820A (en) * 2017-08-30 2018-02-09 深圳市易联智道科技有限公司 Construction Schedule management method
CN108596423A (en) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 A kind of trackways engineering construction progress msg management method based on BIM

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106875159A (en) * 2017-02-17 2017-06-20 中国十七冶集团有限公司 The city integrated piping lane construction total management system of cast-in-place structural
CN107169747A (en) * 2017-06-19 2017-09-15 郑州航空工业管理学院 A kind of management system of various engineering of civil construction
CN107679820A (en) * 2017-08-30 2018-02-09 深圳市易联智道科技有限公司 Construction Schedule management method
CN108596423A (en) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 A kind of trackways engineering construction progress msg management method based on BIM

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US12054160B2 (en) 2019-02-07 2024-08-06 2 Circle, Incorporated Reconstruction and assessment of proficiency in an integrated debrief by a server in a network
CN110111659A (en) * 2019-05-22 2019-08-09 蓝莓极客(武汉)智能科技有限公司 It is a kind of that system is constructed based on the teaching of electronic building blocks multifunction electronic module
CN110796335A (en) * 2019-09-18 2020-02-14 广东电网有限责任公司审计中心 Audit project implementation quality monitoring system and equipment based on data analysis
CN110796335B (en) * 2019-09-18 2023-12-22 广东电网有限责任公司审计中心 Audit project implementation quality monitoring system and equipment based on data analysis
CN111027803A (en) * 2019-11-01 2020-04-17 国艺天成建设工程技术有限公司 Construction management method and construction management system
CN113283879A (en) * 2021-06-21 2021-08-20 华电重工股份有限公司 Method and device for determining construction amount, electronic equipment and readable storage medium
CN115511430A (en) * 2022-08-17 2022-12-23 福建永旺建设集团有限公司 Wisdom building site management platform based on thing networking
CN118378854A (en) * 2024-06-21 2024-07-23 江西省公路工程有限责任公司 Building construction management method and system based on two-dimension code

Similar Documents

Publication Publication Date Title
CN109636675A (en) A kind of management method and system of the construction site based on artificial intelligence
Ko et al. Making formwork construction lean
CN108022176B (en) Intelligent garden management system and method
CN107480912A (en) Hydraulic engineering construction comprehensive management system based on big data analysis and Internet of Things
CN107368951A (en) A kind of power grid enterprises' technological transformation Overhaul Quality management and control honesty Warning System and its operation method
CN109557934A (en) A kind of control method and device of the unmanned plane cruise based on assembled architecture platform
CN109558412A (en) The data growing method and device of assembled architecture construct platform
CN106997511A (en) Railway beam yard management system and railway beam yard management method based on BIM technology
CN108564306A (en) Prefabricated components information collection based on LoRa technologies and hanging method
CN104898084A (en) Electric energy metering device operation state monitoring method
CN109214679A (en) A kind of projects management system based on Building Information Model
CN109636183A (en) A kind of multiplexing kind recruitment coordinated management method and system based on big data
CN205581659U (en) Real -time dispatch system supplies water
CN104992285A (en) Enterprise budget cost controlling system
CN118052522B (en) Visual management method and system for construction operation progress
Lucko et al. Line-of-balance against linear scheduling: Critical comparison
CN115775068A (en) Nuclear power project progress monitoring method and system
CN116167582A (en) Intelligent construction progress monitoring system based on BIM technology
Zhanglin et al. Application of BIM technology in prefabricated buildings
Yang Application of BIM technology in construction cost management of building engineering
Van de Zande et al. Design and Evaluation of an Automatic Scheduling-Manual Operation Tool to Bring Precision Irrigation to Resource-Constrained Farmers
Desai et al. Value stream mapping as a lean construction tool–a case study
Xiaosheng et al. Precast concrete building construction process comparison
CN116385124B (en) Agricultural socialization integrated service cloud platform based on big data analysis traceability
Nissilä et al. BIM based schedule control for precast concrete supply chain

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190416