CN116167582A - An intelligent construction progress monitoring system based on BIM technology - Google Patents

An intelligent construction progress monitoring system based on BIM technology Download PDF

Info

Publication number
CN116167582A
CN116167582A CN202310132548.0A CN202310132548A CN116167582A CN 116167582 A CN116167582 A CN 116167582A CN 202310132548 A CN202310132548 A CN 202310132548A CN 116167582 A CN116167582 A CN 116167582A
Authority
CN
China
Prior art keywords
bim
plan
monitoring system
construction
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310132548.0A
Other languages
Chinese (zh)
Inventor
曾晋明
方晓正
张琦
钟贤煜
王传宝
邓正贤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Original Assignee
Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd filed Critical Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority to CN202310132548.0A priority Critical patent/CN116167582A/en
Publication of CN116167582A publication Critical patent/CN116167582A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063114Status monitoring or status determination for a person or group
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/90Details of database functions independent of the retrieved data types
    • G06F16/95Retrieval from the web
    • G06F16/953Querying, e.g. by the use of web search engines
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Databases & Information Systems (AREA)
  • Geometry (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • General Engineering & Computer Science (AREA)
  • Data Mining & Analysis (AREA)
  • Computer Hardware Design (AREA)
  • Primary Health Care (AREA)
  • Computational Mathematics (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Development Economics (AREA)
  • Structural Engineering (AREA)
  • General Health & Medical Sciences (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明公开了一种基于BIM技术的智能建造进度监控系统,属于工程管理技术领域,该智能建造进度监控系统系统部署于云服务器或自有机房,包括网络服务端和APP端两部分,网络服务端用于通过浏览器查看BIM及各类业务应用数据,APP端用于用户在移动手机上查看项目数据;其中,该智能建造进度监控系统还包括数据采集子系统、数据处理子系统、BIM数据子系统和功能应用子系统。本发明,基于BIM的计划进度管理,具有计划编制和进度填报功能,并把计划、进度与BIM模型关联绑定,实现BIM完工标识和BIM施工模拟功能,降低BIM智慧建造技术应用门槛,提高施工过程控制和安全监控水平,当出现计划无法按期完成时,能够尽早纠偏,采取措施,提升进度管控的效率。

Figure 202310132548

The invention discloses an intelligent construction progress monitoring system based on BIM technology, which belongs to the technical field of engineering management. The intelligent construction progress monitoring system is deployed on a cloud server or a self-owned machine room, and includes two parts: a network server and an APP. The network service The terminal is used to view BIM and various business application data through a browser, and the APP terminal is used for users to view project data on mobile phones; among them, the intelligent construction progress monitoring system also includes data acquisition subsystems, data processing subsystems, and BIM data Subsystems and Functional Application Subsystems. The present invention, based on BIM plan progress management, has the functions of plan preparation and progress reporting, and associates and binds the plan and progress with the BIM model, realizes the functions of BIM completion identification and BIM construction simulation, reduces the application threshold of BIM intelligent construction technology, and improves construction The level of process control and safety monitoring. When the plan cannot be completed on schedule, deviations can be corrected as soon as possible, and measures can be taken to improve the efficiency of progress control.

Figure 202310132548

Description

一种基于BIM技术的智能建造进度监控系统An intelligent construction progress monitoring system based on BIM technology

技术领域technical field

本发明属于工程管理技术领域,具体涉及一种基于BIM技术的智能建造进度监控系统。The invention belongs to the technical field of engineering management, and in particular relates to an intelligent construction progress monitoring system based on BIM technology.

背景技术Background technique

BIM技术是一种应用于工程设计、建造、管理的数据化工具,通过对建筑的数据化、信息化模型整合,在项目策划、运行和维护的全生命周期过程中进行共享和传递,使工程技术人员对各种建筑信息作出正确理解和高效应对,为设计团队以及包括建筑、运营单位在内的各方建设主体提供协同工作的基础,在提高生产效率、节约成本和缩短工期方面发挥重要作用。工程项目的管理,是一个复杂、艰巨的系统工程,涉及进度、质量、投资、合同、人员、风险、图纸文档等多方面的工作,大量的信息需要有效的管理,随着互联网技术以及无线通讯技术的发展,现代社会已逐步进入到信息时代,现有的项目管理系统,已经显得越来越吃力,需要寻找新的方法和工具。BIM technology is a digital tool applied to engineering design, construction and management. Through the integration of data and information models of buildings, it can be shared and transmitted in the whole life cycle of project planning, operation and maintenance, so that engineering Technicians make a correct understanding and efficient response to various building information, provide a basis for collaborative work for the design team and all parties including construction and operation units, and play an important role in improving production efficiency, saving costs and shortening the construction period . The management of engineering projects is a complex and arduous system engineering, involving work in progress, quality, investment, contracts, personnel, risks, drawings and documents, etc. A large amount of information requires effective management. With Internet technology and wireless communication With the development of technology, modern society has gradually entered the information age. The existing project management system has become more and more difficult, and new methods and tools need to be found.

现有的电力隧道项目进度监控管理方法中,工程人员一般是用横道图的方式通过收集实际数据来监控现场进度。此法比较平面化且不直观,并且项目各个参与方并不都是专业人士,很多项目参与人员很难快速看懂横道图显示的进展状况,每个人对横道图的理解程度也参次不齐,这会影响项目各参与方之间的交流讨论,特别是当现场各专业交错频繁、场地空间变换复杂时,大家很难从中获取准确一致的信息,从而无法快速知晓施工项目的进度并进行进度管控,进而影响到电力隧道工程的进展。In the existing monitoring and management methods for the progress of power tunnel projects, engineering personnel generally monitor the progress of the site by collecting actual data in the form of bar diagrams. This method is relatively flat and unintuitive, and all participants in the project are not professionals. It is difficult for many project participants to quickly understand the progress displayed by the bar chart, and everyone's understanding of the bar chart is also uneven. , which will affect the communication and discussion between the various participants of the project, especially when the on-site specialties are frequently intertwined and the site space changes complicatedly, it is difficult for everyone to obtain accurate and consistent information from them, so that they cannot quickly know the progress of the construction project and make progress. control, which in turn affects the progress of the power tunnel project.

发明内容Contents of the invention

本发明的目的在于提供一种基于BIM技术的智能建造进度监控系统,以解决上述背景技术中提出的问题。The purpose of the present invention is to provide an intelligent construction progress monitoring system based on BIM technology, so as to solve the problems raised in the above-mentioned background technology.

为实现上述目的,本发明提供如下技术方案:一种基于BIM技术的智能建造进度监控系统,该智能建造进度监控系统系统部署于云服务器或自有机房,包括网络服务端和APP端两部分,网络服务端用于通过浏览器查看BIM及各类业务应用数据,APP端用于用户在移动手机上查看项目数据;In order to achieve the above purpose, the present invention provides the following technical solutions: an intelligent construction progress monitoring system based on BIM technology, the intelligent construction progress monitoring system is deployed on a cloud server or its own computer room, including two parts: a network server and an APP, The web server is used to view BIM and various business application data through a browser, and the APP is used for users to view project data on mobile phones;

其中,该智能建造进度监控系统还包括数据采集子系统、数据处理子系统、BIM数据子系统和功能应用子系统;Among them, the intelligent construction progress monitoring system also includes a data acquisition subsystem, a data processing subsystem, a BIM data subsystem and a functional application subsystem;

数据采集子系统,用于采集电力隧道施工现场的实时数据信息,并将实时数据信息输送至数据处理子系统;The data acquisition subsystem is used to collect real-time data information on the power tunnel construction site, and transmit the real-time data information to the data processing subsystem;

数据处理子系统,用于对数据采集子系统上传的实时数据信息进行处理,以生成BIM实时模型;The data processing subsystem is used to process the real-time data information uploaded by the data acquisition subsystem to generate a BIM real-time model;

BIM数据子系统,其为智能建造进度监控系统系统的中央数据库,包含BIM计划模型和BIM实时模型,BIM计划模型集成BIM计划信息,BIM实时模型集成了施工过程中动态监测产生的有价值信息;BIM data subsystem, which is the central database of the intelligent construction progress monitoring system, includes BIM plan model and BIM real-time model. The BIM plan model integrates BIM plan information, and the BIM real-time model integrates valuable information generated by dynamic monitoring during the construction process;

功能应用子系统,其为智能建造进度监控系统所提供的信息的具体应用,用于实现电力隧道施工进度的可视化呈现、施工进度监测和施工成本监测。The functional application subsystem is a specific application of the information provided by the intelligent construction progress monitoring system, and is used to realize the visual presentation of the power tunnel construction progress, construction progress monitoring and construction cost monitoring.

进一步的,所述实时数据信息包括3D点云和深度图像;Further, the real-time data information includes 3D point cloud and depth image;

其中,3D点云通过3D激光扫描仪采集电力隧道施工现场已完成构筑物部分的3D坐标,并经过数据配准集成不同测站的数据生成;Among them, the 3D point cloud collects the 3D coordinates of the completed structures at the power tunnel construction site through a 3D laser scanner, and generates data from different stations through data registration;

深度图像至少包括构件形状和材料信息,利用摄像测量技术对现场拍摄获得。The depth image includes at least the shape and material information of the component, and is obtained by shooting on-site with photogrammetry technology.

进一步的,所述数据处理子系统对数据采集子系统上传的实时数据信息进行处理,以生成BIM实时模型的具体过程为:Further, the data processing subsystem processes the real-time data information uploaded by the data acquisition subsystem to generate a BIM real-time model. The specific process is as follows:

通过提取实时数据信息的深度图像和3D点云的信息,进行对象识别和匹配过程,并利用BIM计划模型提供的信息识别出模型构件,而后用计划模型中参数的对象替换点云生成BIM实时模型。By extracting the depth image and 3D point cloud information of real-time data information, the object recognition and matching process is carried out, and the information provided by the BIM plan model is used to identify the model components, and then the point cloud is replaced with the object of the parameters in the plan model to generate a BIM real-time model .

进一步的,所述BIM实时模型内包含施工节点管理,至少包含钢筋工程、模板工程、混凝土工程、砌体工程、防水工程、保湿工程、装饰装修工程、机电安装工程和外墙工程。Further, the BIM real-time model includes construction node management, including at least reinforcement engineering, formwork engineering, concrete engineering, masonry engineering, waterproof engineering, moisturizing engineering, decoration engineering, electromechanical installation engineering and exterior wall engineering.

进一步的,所述BIM计划信息包含总体计划、月计划和周计划三级,并且将月计划或周计划作为一个个施工任务,下达给相关的施工项目责任人。Further, the BIM plan information includes three levels of overall plan, monthly plan and weekly plan, and the monthly plan or weekly plan is assigned to the relevant construction project responsible person as each construction task.

进一步的,所述BIM计划信息为基于施工节点的施工计划,并作为关键节点进度跟踪考核。Further, the BIM plan information is a construction plan based on construction nodes, and is used as a key node progress tracking assessment.

进一步的,所述当相关的施工项目责任人被安排月度生产任务或者周生产任务后,需要每天/每周填报完成进度情况,保障计划执行情况的及时、动态更新。Further, when the person in charge of the relevant construction project is assigned a monthly production task or a weekly production task, he needs to report the completion progress every day/week to ensure timely and dynamic update of the plan implementation.

进一步的,所述智能建造进度监控系统根据计划和进度的对比,自动进行偏差分析,当任务完成量或完成百分比,与计划完成时间的比例相比出现滞后时,就需要进行预警提示,引起相关的施工项目责任人的重视。Further, the intelligent construction progress monitoring system automatically performs deviation analysis according to the comparison between the plan and the progress. When the task completion amount or completion percentage lags behind the planned completion time, an early warning prompt is required to cause related problems. The attention of the person in charge of the construction project.

与现有技术相比,本发明的有益效果是:Compared with prior art, the beneficial effect of the present invention is:

本发明基于BIM技术的智能建造进度监控系统,基于BIM的计划进度管理,具有计划编制和进度填报功能,并把计划、进度与BIM模型关联绑定,实现BIM完工标识和BIM施工模拟功能,降低BIM智慧建造技术应用门槛,提高施工过程控制和安全监控水平,当出现计划无法按期完成时,能够尽早纠偏,采取措施,提升进度管控的效率,尽可能减少工期滞后带来的成本损失,实现电网“智能、高效、可靠、绿色”的建设目标。The intelligent construction progress monitoring system based on BIM technology of the present invention, based on BIM plan progress management, has the functions of plan preparation and progress reporting, and associates and binds the plan and progress with the BIM model to realize the functions of BIM completion identification and BIM construction simulation, reducing the The application threshold of BIM smart construction technology can improve the level of construction process control and safety monitoring. When the plan cannot be completed on schedule, it can correct the deviation as soon as possible, take measures to improve the efficiency of progress control, and minimize the cost loss caused by the delay of the construction period. Realize the power grid The construction goal of "smart, efficient, reliable and green".

附图说明Description of drawings

图1为本发明一种基于BIM技术的智能建造进度监控系统的网络架构图。Fig. 1 is a network architecture diagram of an intelligent construction progress monitoring system based on BIM technology according to the present invention.

图2为本发明一种基于BIM技术的智能建造进度监控系统的BIM实时模型建模过程图。Fig. 2 is a BIM real-time model modeling process diagram of an intelligent construction progress monitoring system based on BIM technology according to the present invention.

图3为本发明一种基于BIM技术的智能建造进度监控系统的系统架构图。Fig. 3 is a system architecture diagram of an intelligent construction progress monitoring system based on BIM technology according to the present invention.

图4为本发明一种基于BIM技术的智能建造进度监控系统的移动终端硬件结构图。FIG. 4 is a hardware structure diagram of a mobile terminal of a smart construction progress monitoring system based on BIM technology according to the present invention.

具体实施方式Detailed ways

本发明的说明书和权利要求书及上述附图中的术语“第一”、“第二”、“第三”“第四”等(如果存在)是用于区别类似的对象,而不必用于描述特定的顺序或先后次序。应该理解这样使用的数据在适当情况下可以互换,以便这里描述的本发明的实施例能够以除了在这里图示或描述的那些以外的顺序实施。The terms "first", "second", "third", "fourth", etc. (if any) in the description and claims of the present invention and the above drawings are used to distinguish similar objects and not necessarily Describe a specific order or sequence. It is to be understood that the data so used are interchangeable under appropriate circumstances such that the embodiments of the invention described herein can be practiced in sequences other than those illustrated or described herein.

应当理解,在本发明的各种实施例中,各过程的序号的大小并不意味着执行顺序的先后,各过程的执行顺序应以其功能和内在逻辑确定,而不应对本发明实施例的实施过程构成任何限定。It should be understood that in various embodiments of the present invention, the sequence numbers of the processes do not mean the order of execution, and the execution order of the processes should be determined by their functions and internal logic, rather than by the implementation order of the embodiments of the present invention. The implementation process constitutes no limitation.

应当理解,在本发明中,“包括”和“具有”以及他们的任何变形,意图在于覆盖不排他的包含,例如,包含了一系列步骤或单元的过程、方法、系统、产品或设备不必限于清楚地列出的那些步骤或单元,而是可包括没有清楚地列出的或对于这些过程、方法、产品或设备固有的其它步骤或单元。It should be understood that in the present invention, "comprising" and "having" and any variations thereof are intended to cover a non-exclusive inclusion, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to Those steps or elements are not explicitly listed, but may include other steps or elements not explicitly listed or inherent to the process, method, product or apparatus.

应当理解,在本发明中,“多个”是指两个或两个以上。“和/或”仅仅是一种描述关联对象的关联关系,表示可以存在三种关系,例如,和/或B,可以表示:单独存在A,同时存在A和B,单独存在B这三种情况。字符“/”一般表示前后关联对象是一种“或”的关系。“包含A、B和C”、“包含A、B、C”是指A、B、C三者都包含,“包含A、B或C”是指包含A、B、C三者之一,“包含A、B和/或C”是指包含A、B、C三者中任1个或任2个或3个。It should be understood that in the present invention, "plurality" means two or more. "And/or" is just an association relationship describing associated objects, which means that there can be three kinds of relationships, for example, and/or B, which can mean: A exists alone, A and B exist at the same time, and B exists alone. . The character "/" generally indicates that the contextual objects are an "or" relationship. "Includes A, B and C", "Includes A, B, C" means that A, B, and C are all included, "includes A, B, or C" means includes one of A, B, and C, "Containing A, B and/or C" means containing any 1 or any 2 or 3 of A, B and C.

应当理解,在本发明中,“与A对应的B”、“与A相对应的B”、“A与B相对应”或者“B与A相对应”,表示B与A相关联,根据A可以确定B。根据A确定B并不意味着仅仅根据A确定B,还可以根据A和/或其他信息确定B。A与B的匹配,是A与B的相似度大于或等于预设的阈值。It should be understood that in the present invention, "B corresponding to A", "B corresponding to A", "A corresponding to B" or "B corresponding to A" means that B is associated with A, and according to A It is possible to determine B. Determining B from A does not mean determining B from A alone, B can also be determined from A and/or other information. The matching between A and B means that the similarity between A and B is greater than or equal to a preset threshold.

取决于语境,如在此所使用的“若”可以被解释成为“在……时”或“当……时”或“响应于确定”或“响应于检测”。Depending on the context, "if" as used herein may be interpreted as "at" or "when" or "in response to determining" or "in response to detecting".

下面以具体地实施例对本发明的技术方案进行详细说明。下面这几个具体的实施例可以相互结合,对于相同或相似的概念或过程可能在某些实施例不再赘述。The technical solution of the present invention will be described in detail below with specific embodiments. The following specific embodiments may be combined with each other, and the same or similar concepts or processes may not be repeated in some embodiments.

如图1-3所示,一种基于BIM技术的智能建造进度监控系统,该智能建造进度监控系统系统部署于云服务器或自有机房,包括网络服务端和APP端两部分,网络服务端用于通过浏览器查看BIM及各类业务应用数据,APP端用于用户在移动手机上查看项目数据;As shown in Figure 1-3, an intelligent construction progress monitoring system based on BIM technology, the intelligent construction progress monitoring system is deployed on the cloud server or its own computer room, including two parts: the network server and the APP end, and the network server uses It is used to view BIM and various business application data through a browser, and the APP terminal is used for users to view project data on mobile phones;

其中,该智能建造进度监控系统还包括数据采集子系统、数据处理子系统、BIM数据子系统和功能应用子系统;Among them, the intelligent construction progress monitoring system also includes a data acquisition subsystem, a data processing subsystem, a BIM data subsystem and a functional application subsystem;

数据采集子系统,用于采集电力隧道施工现场的实时数据信息,并将实时数据信息输送至数据处理子系统;The data acquisition subsystem is used to collect real-time data information on the power tunnel construction site, and transmit the real-time data information to the data processing subsystem;

数据处理子系统,用于对数据采集子系统上传的实时数据信息进行处理,以生成BIM实时模型;The data processing subsystem is used to process the real-time data information uploaded by the data acquisition subsystem to generate a BIM real-time model;

BIM数据子系统,其为智能建造进度监控系统系统的中央数据库,包含BIM计划模型和BIM实时模型,BIM计划模型集成BIM计划信息,BIM实时模型集成了施工过程中动态监测产生的有价值信息;BIM data subsystem, which is the central database of the intelligent construction progress monitoring system, includes BIM plan model and BIM real-time model. The BIM plan model integrates BIM plan information, and the BIM real-time model integrates valuable information generated by dynamic monitoring during the construction process;

功能应用子系统,其为智能建造进度监控系统所提供的信息的具体应用,用于实现电力隧道施工进度的可视化呈现、施工进度监测和施工成本监测。The functional application subsystem is a specific application of the information provided by the intelligent construction progress monitoring system, and is used to realize the visual presentation of the power tunnel construction progress, construction progress monitoring and construction cost monitoring.

本实施例中,所述实时数据信息包括3D点云和深度图像;In this embodiment, the real-time data information includes 3D point cloud and depth image;

其中,3D点云通过3D激光扫描仪采集电力隧道施工现场已完成构筑物部分的3D坐标,并经过数据配准集成不同测站的数据生成;Among them, the 3D point cloud collects the 3D coordinates of the completed structures at the power tunnel construction site through a 3D laser scanner, and generates data from different stations through data registration;

深度图像至少包括构件形状和材料信息,利用摄像测量技术对现场拍摄获得。The depth image includes at least the shape and material information of the component, and is obtained by shooting on-site with photogrammetry technology.

本实施例中,所述数据处理子系统对数据采集子系统上传的实时数据信息进行处理,以生成BIM实时模型的具体过程为:In this embodiment, the data processing subsystem processes the real-time data information uploaded by the data acquisition subsystem to generate a BIM real-time model. The specific process is as follows:

通过提取实时数据信息的深度图像和3D点云的信息,进行对象识别和匹配过程,并利用BIM计划模型提供的信息识别出模型构件,而后用计划模型中参数的对象替换点云生成BIM实时模型。By extracting the depth image and 3D point cloud information of real-time data information, the object recognition and matching process is carried out, and the information provided by the BIM plan model is used to identify the model components, and then the point cloud is replaced with the object of the parameters in the plan model to generate a BIM real-time model .

本实施例中,所述BIM实时模型内包含施工节点管理,至少包含钢筋工程、模板工程、混凝土工程、砌体工程、防水工程、保湿工程、装饰装修工程、机电安装工程和外墙工程。In this embodiment, the BIM real-time model includes construction node management, including at least reinforcement engineering, formwork engineering, concrete engineering, masonry engineering, waterproof engineering, moisturizing engineering, decoration engineering, electromechanical installation engineering, and exterior wall engineering.

本实施例中,所述BIM计划信息包含总体计划、月计划和周计划三级,并且将月计划或周计划作为一个个施工任务,下达给相关的施工项目责任人。In this embodiment, the BIM plan information includes three levels: overall plan, monthly plan and weekly plan, and the monthly plan or weekly plan is assigned to the relevant construction project responsible person as each construction task.

本实施例中,所述BIM计划信息为基于施工节点的施工计划,并作为关键节点进度跟踪考核。In this embodiment, the BIM plan information is a construction plan based on construction nodes, and is used as a key node progress tracking assessment.

本实施例中,所述当相关的施工项目责任人被安排月度生产任务或者周生产任务后,需要每天/每周填报完成进度情况,保障计划执行情况的及时、动态更新。In this embodiment, when the relevant construction project responsible person is assigned a monthly or weekly production task, he needs to report the completion progress every day/week to ensure timely and dynamic update of the plan implementation.

本实施例中,所述智能建造进度监控系统根据计划和进度的对比,自动进行偏差分析,当任务完成量或完成百分比,与计划完成时间的比例相比出现滞后时,就需要进行预警提示,引起相关的施工项目责任人的重视。In this embodiment, the intelligent construction progress monitoring system automatically performs deviation analysis according to the comparison between the plan and the progress. When the task completion amount or completion percentage lags behind the planned completion time, an early warning prompt is required. Attract the attention of relevant construction project responsible persons.

参见图4,是本发明实施例提供的一种移动终端的硬件结构示意图,该移动终端包括:处理器、存储器和计算机程序;其中,Referring to FIG. 4 , it is a schematic diagram of a hardware structure of a mobile terminal provided by an embodiment of the present invention. The mobile terminal includes: a processor, a memory, and a computer program; wherein,

存储器,用于存储所述计算机程序,该存储器还可以是闪存(flash)。所述计算机程序例如是实现上述方法的应用程序、功能模块等。The memory is used to store the computer program, and the memory may also be a flash memory (flash). The computer program is, for example, an application program, a function module, etc. for realizing the above method.

处理器,用于执行所述存储器存储的计算机程序,以实现上述方法中设备执行的各个步骤。具体可以参见前面方法实施例中的相关描述。The processor is configured to execute the computer program stored in the memory, so as to realize each step executed by the device in the above method. For details, refer to the related descriptions in the foregoing method embodiments.

可选地,存储器既可以是独立的,也可以跟处理器集成在一起。Optionally, the memory can be independent or integrated with the processor.

当所述存储器是独立于处理器之外的器件时,所述设备还可以包括:When the memory is a device independent of the processor, the device may further include:

总线,用于连接所述存储器和处理器。A bus for connecting the memory and the processor.

本发明还提供一种可读存储介质,所述可读存储介质中存储有计算机程序,所述计算机程序被处理器执行时用于实现上述的各种实施方式提供的方法。The present invention also provides a readable storage medium, wherein a computer program is stored in the readable storage medium, and when the computer program is executed by a processor, the computer program is used to implement the methods provided in the above various implementation manners.

其中,可读存储介质可以是计算机存储介质,也可以是通信介质。通信介质包括便于从一个地方向另一个地方传送计算机程序的任何介质。计算机存储介质可以是通用或专用计算机能够存取的任何可用介质。例如,可读存储介质耦合至处理器,从而使处理器能够从该可读存储介质读取信息,且可向该可读存储介质写入信息。当然,可读存储介质也可以是处理器的组成部分。处理器和可读存储介质可以位于专用集成电路(ApplicationSpecific Integrated Circuits,简称:ASIC)中。另外,该ASIC可以位于用户设备中。当然,处理器和可读存储介质也可以作为分立组件存在于通信设备中。可读存储介质可以是只读存储器(ROM)、随机存取存储器(RAM)、CD-ROM、磁带、软盘和光数据存储设备等。Wherein, the readable storage medium may be a computer storage medium, or a communication medium. Communication media includes any medium that facilitates transfer of a computer program from one place to another. Computer storage media can be any available media that can be accessed by a general purpose or special purpose computer. For example, a readable storage medium is coupled to the processor such that the processor can read information from, and write information to, the readable storage medium. Of course, the readable storage medium can also be a component of the processor. The processor and the readable storage medium may be located in an application specific integrated circuit (Application Specific Integrated Circuits, ASIC for short). Additionally, the ASIC may be located in the user equipment. Of course, the processor and the readable storage medium can also exist in the communication device as discrete components. The readable storage medium may be read only memory (ROM), random access memory (RAM), CD-ROM, magnetic tape, floppy disk, and optical data storage devices, among others.

本发明还提供一种程序产品,该程序产品包括执行指令,该执行指令存储在可读存储介质中。设备的至少一个处理器可以从可读存储介质读取该执行指令,至少一个处理器执行该执行指令使得设备实施上述的各种实施方式提供的方法。The present invention also provides a program product, which includes execution instructions, and the execution instructions are stored in a readable storage medium. At least one processor of the device may read the execution instruction from the readable storage medium, and the at least one processor executes the execution instruction so that the device implements the methods provided in the foregoing various implementation manners.

在上述移动终端的实施例中,应理解,处理器可以是中央处理单元(英文:CentralProcessing Unit,简称:CPU),还可以是其他通用处理器、数字信号处理器(英文:DigitalSignal Processor,简称:DSP)、专用集成电路(英文:Application Specific IntegratedCircuit,简称:ASIC)等。通用处理器可以是微处理器或者该处理器也可以是任何常规的处理器等。结合本发明所公开的方法的步骤可以直接体现为硬件处理器执行完成,或者用处理器中的硬件及软件模块组合执行完成。In the above-mentioned embodiment of the mobile terminal, it should be understood that the processor may be a central processing unit (English: Central Processing Unit, referred to as: CPU), and may also be other general-purpose processors, digital signal processors (English: DigitalSignal Processor, referred to as: DSP), Application Specific Integrated Circuit (English: Application Specific Integrated Circuit, referred to as: ASIC) and so on. A general-purpose processor may be a microprocessor, or the processor may be any conventional processor, or the like. The steps of the method disclosed in conjunction with the present invention can be directly implemented by a hardware processor, or implemented by a combination of hardware and software modules in the processor.

最后应说明的是:以上各实施例仅用以说明本发明的技术方案,而非对其限制;尽管参照前述各实施例对本发明进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分或者全部技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明各实施例技术方案的范围。Finally, it should be noted that: the above embodiments are only used to illustrate the technical solutions of the present invention, rather than limiting them; although the present invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: It is still possible to modify the technical solutions described in the foregoing embodiments, or perform equivalent replacements for some or all of the technical features; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the technical solutions of the various embodiments of the present invention. scope.

Claims (8)

1.一种基于BIM技术的智能建造进度监控系统,其特征在于,该智能建造进度监控系统系统部署于云服务器或自有机房,包括网络服务端和APP端两部分,网络服务端用于通过浏览器查看BIM及各类业务应用数据,APP端用于用户在移动手机上查看项目数据;1. An intelligent construction progress monitoring system based on BIM technology, characterized in that the intelligent construction progress monitoring system is deployed on a cloud server or its own machine room, including two parts, a network server and an APP end, and the network server is used to pass The browser is used to view BIM and various business application data, and the APP is used for users to view project data on mobile phones; 其中,该智能建造进度监控系统还包括数据采集子系统、数据处理子系统、BIM数据子系统和功能应用子系统;Among them, the intelligent construction progress monitoring system also includes a data acquisition subsystem, a data processing subsystem, a BIM data subsystem and a functional application subsystem; 数据采集子系统,用于采集电力隧道施工现场的实时数据信息,并将实时数据信息输送至数据处理子系统;The data acquisition subsystem is used to collect real-time data information on the power tunnel construction site, and transmit the real-time data information to the data processing subsystem; 数据处理子系统,用于对数据采集子系统上传的实时数据信息进行处理,以生成BIM实时模型;The data processing subsystem is used to process the real-time data information uploaded by the data acquisition subsystem to generate a BIM real-time model; BIM数据子系统,其为智能建造进度监控系统系统的中央数据库,包含BIM计划模型和BIM实时模型,BIM计划模型集成BIM计划信息,BIM实时模型集成了施工过程中动态监测产生的有价值信息;BIM data subsystem, which is the central database of the intelligent construction progress monitoring system, includes BIM plan model and BIM real-time model. The BIM plan model integrates BIM plan information, and the BIM real-time model integrates valuable information generated by dynamic monitoring during the construction process; 功能应用子系统,其为智能建造进度监控系统所提供的信息的具体应用,用于实现电力隧道施工进度的可视化呈现、施工进度监测和施工成本监测。The functional application subsystem is a specific application of the information provided by the intelligent construction progress monitoring system, and is used to realize the visual presentation of the power tunnel construction progress, construction progress monitoring and construction cost monitoring. 2.根据权利要求1所述的一种基于BIM技术的智能建造进度监控系统,其特征在于,所述实时数据信息包括3D点云和深度图像;2. A kind of intelligent construction progress monitoring system based on BIM technology according to claim 1, is characterized in that, described real-time data information comprises 3D point cloud and depth image; 其中,3D点云通过3D激光扫描仪采集电力隧道施工现场已完成构筑物部分的3D坐标,并经过数据配准集成不同测站的数据生成;Among them, the 3D point cloud collects the 3D coordinates of the completed structures at the power tunnel construction site through a 3D laser scanner, and generates data from different stations through data registration; 深度图像至少包括构件形状和材料信息,利用摄像测量技术对现场拍摄获得。The depth image includes at least the shape and material information of the component, and is obtained by shooting on-site with photogrammetry technology. 3.根据权利要求2所述的一种基于BIM技术的智能建造进度监控系统,其特征在于,所述数据处理子系统对数据采集子系统上传的实时数据信息进行处理,以生成BIM实时模型的具体过程为:3. A kind of intelligent construction progress monitoring system based on BIM technology according to claim 2, is characterized in that, described data processing subsystem processes the real-time data information that data acquisition subsystem uploads, to generate the BIM real-time model The specific process is: 通过提取实时数据信息的深度图像和3D点云的信息,进行对象识别和匹配过程,并利用BIM计划模型提供的信息识别出模型构件,而后用计划模型中参数的对象替换点云生成BIM实时模型。By extracting the depth image and 3D point cloud information of real-time data information, the object recognition and matching process is carried out, and the information provided by the BIM plan model is used to identify the model components, and then the point cloud is replaced with the object of the parameters in the plan model to generate a BIM real-time model . 4.根据权利要求1或3所述的一种基于BIM技术的智能建造进度监控系统,其特征在于,所述BIM实时模型内包含施工节点管理,至少包含钢筋工程、模板工程、混凝土工程、砌体工程、防水工程、保湿工程、装饰装修工程、机电安装工程和外墙工程。4. A kind of intelligent construction progress monitoring system based on BIM technology according to claim 1 or 3, it is characterized in that, the described BIM real-time model includes construction node management, at least includes reinforcement engineering, formwork engineering, concrete engineering, masonry Physical engineering, waterproofing engineering, moisturizing engineering, decoration engineering, mechanical and electrical installation engineering and exterior wall engineering. 5.根据权利要求4所述的一种基于BIM技术的智能建造进度监控系统,其特征在于,所述BIM计划信息包含总体计划、月计划和周计划三级,并且将月计划或周计划作为一个个施工任务,下达给相关的施工项目责任人。5. The intelligent construction progress monitoring system based on BIM technology according to claim 4, wherein the BIM plan information includes three levels of overall plan, monthly plan and weekly plan, and the monthly plan or weekly plan is used as Each construction task is assigned to the person in charge of the relevant construction project. 6.根据权利要求4所述的一种基于BIM技术的智能建造进度监控系统,其特征在于,所述BIM计划信息为基于施工节点的施工计划,并作为关键节点进度跟踪考核。6. The intelligent construction progress monitoring system based on BIM technology according to claim 4, wherein the BIM plan information is a construction plan based on construction nodes, and is used as a key node progress tracking assessment. 7.根据权利要求5所述的一种基于BIM技术的智能建造进度监控系统,其特征在于,所述当相关的施工项目责任人被安排月度生产任务或者周生产任务后,需要每天/每周填报完成进度情况,保障计划执行情况的及时、动态更新。7. The intelligent construction progress monitoring system based on BIM technology according to claim 5, characterized in that, after the relevant construction project responsible person is assigned monthly production tasks or weekly production tasks, daily/weekly production tasks are required. Fill in the completion progress and ensure the timely and dynamic update of the implementation of the plan. 8.根据权利要求7所述的一种基于BIM技术的智能建造进度监控系统,其特征在于,所述智能建造进度监控系统根据计划和进度的对比,自动进行偏差分析,当任务完成量或完成百分比,与计划完成时间的比例相比出现滞后时,就需要进行预警提示,引起相关的施工项目责任人的重视。8. The intelligent construction progress monitoring system based on BIM technology according to claim 7, characterized in that, the intelligent construction progress monitoring system automatically performs deviation analysis according to the comparison between the plan and the progress, and when the task is completed or completed When there is a lag compared with the proportion of the planned completion time, an early warning reminder is required to attract the attention of the responsible person of the relevant construction project.
CN202310132548.0A 2023-02-16 2023-02-16 An intelligent construction progress monitoring system based on BIM technology Pending CN116167582A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310132548.0A CN116167582A (en) 2023-02-16 2023-02-16 An intelligent construction progress monitoring system based on BIM technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310132548.0A CN116167582A (en) 2023-02-16 2023-02-16 An intelligent construction progress monitoring system based on BIM technology

Publications (1)

Publication Number Publication Date
CN116167582A true CN116167582A (en) 2023-05-26

Family

ID=86412907

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310132548.0A Pending CN116167582A (en) 2023-02-16 2023-02-16 An intelligent construction progress monitoring system based on BIM technology

Country Status (1)

Country Link
CN (1) CN116167582A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118018403A (en) * 2024-04-10 2024-05-10 中国电建集团市政规划设计研究院有限公司 Intelligent building site management method, device and system based on BIM and GIS
CN118246887A (en) * 2024-05-23 2024-06-25 成都建工第六建筑工程有限公司 Control method and control system for intelligent construction of building projects
CN119338535A (en) * 2024-10-16 2025-01-21 广东电网有限责任公司揭阳惠来供电局 A method for automatic settlement of engineering data based on the construction progress of power grid projects
CN119672505A (en) * 2025-02-20 2025-03-21 沸蓝建设咨询有限公司 A communication engineering construction site anomaly detection method and system based on visual recognition
CN119989461A (en) * 2024-12-18 2025-05-13 中建三局集团有限公司 A construction monitoring method and system based on BIM

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118018403A (en) * 2024-04-10 2024-05-10 中国电建集团市政规划设计研究院有限公司 Intelligent building site management method, device and system based on BIM and GIS
CN118018403B (en) * 2024-04-10 2024-06-11 中国电建集团市政规划设计研究院有限公司 Intelligent building site management method, device and system based on BIM and GIS
CN118246887A (en) * 2024-05-23 2024-06-25 成都建工第六建筑工程有限公司 Control method and control system for intelligent construction of building projects
CN119338535A (en) * 2024-10-16 2025-01-21 广东电网有限责任公司揭阳惠来供电局 A method for automatic settlement of engineering data based on the construction progress of power grid projects
CN119338535B (en) * 2024-10-16 2025-04-04 广东电网有限责任公司揭阳惠来供电局 A method for automatic settlement of engineering data based on the construction progress of power grid projects
CN119989461A (en) * 2024-12-18 2025-05-13 中建三局集团有限公司 A construction monitoring method and system based on BIM
CN119672505A (en) * 2025-02-20 2025-03-21 沸蓝建设咨询有限公司 A communication engineering construction site anomaly detection method and system based on visual recognition

Similar Documents

Publication Publication Date Title
CN116167582A (en) An intelligent construction progress monitoring system based on BIM technology
US12153445B2 (en) Method and apparatus for controlling cruise of unmanned air vehicle based on prefabricated construction platform
CN108470315B (en) BIM-based project progress supervision system
CN109557934B (en) Unmanned aerial vehicle cruise control method and device based on fabricated building platform
CN106595565A (en) BIM-based intelligent monitoring system
CN113656864B (en) Building construction method, system, computer device and storage medium based on BIM
CN104484524A (en) Method and system based on BIM (building information modeling) simulation model and in-site construction interaction
CN109214679B (en) Project engineering management system based on building information model
CN117852838B (en) BIM-based municipal engineering construction progress intelligent management platform
CN111476425A (en) Engineering project cost progress supervision system and method
CN106997511A (en) Railway beam yard management system and railway beam yard management method based on BIM technology
CN112907390A (en) Building full life cycle dynamic intelligent management system and method based on BIM
CN108595818B (en) Assembly type building management method and system based on BIM and cloud service
CN112990844A (en) Construction method and management system based on BIM
CN112464494A (en) Construction system is built to wisdom
CN115936546A (en) Assembly type building green construction management method and device based on digital twinning
CN106779585A (en) Method, system and mobile terminal for supervising construction projects
CN112417562A (en) Dynamo-based earthwork construction modeling method and device
CN116597108A (en) A BIM 3D reconstruction method for a steel structure workshop
CN116308128A (en) Method, equipment and medium for green construction management of assembled building
CN117350494A (en) Joint management and control method and system for prefabricated buildings based on BIM technology
CN116976700A (en) Construction progress and cost prediction method, device, equipment and storage medium
CN115936654A (en) Intelligent hydraulic engineering progress control method and system
CN111242497A (en) A construction cost management system and method based on building information model
CN114037403B (en) Method for efficiently sharing and managing light weight of BIM data

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination