CN109816263A - A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision - Google Patents
A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision Download PDFInfo
- Publication number
- CN109816263A CN109816263A CN201910103230.3A CN201910103230A CN109816263A CN 109816263 A CN109816263 A CN 109816263A CN 201910103230 A CN201910103230 A CN 201910103230A CN 109816263 A CN109816263 A CN 109816263A
- Authority
- CN
- China
- Prior art keywords
- bim
- construction
- equipment
- time
- personnel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 83
- 238000000034 method Methods 0.000 title claims abstract description 34
- 238000004458 analytical method Methods 0.000 claims abstract description 20
- 230000003993 interaction Effects 0.000 claims abstract description 15
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 10
- 238000012544 monitoring process Methods 0.000 claims abstract description 9
- 238000009430 construction management Methods 0.000 claims abstract description 8
- 238000011161 development Methods 0.000 claims abstract description 5
- 230000008569 process Effects 0.000 claims description 7
- 230000000694 effects Effects 0.000 claims description 4
- 238000005457 optimization Methods 0.000 claims description 4
- 238000012800 visualization Methods 0.000 claims description 4
- 238000009826 distribution Methods 0.000 claims description 3
- 238000011156 evaluation Methods 0.000 claims description 3
- 241000208340 Araliaceae Species 0.000 claims 1
- 235000005035 Panax pseudoginseng ssp. pseudoginseng Nutrition 0.000 claims 1
- 235000003140 Panax quinquefolius Nutrition 0.000 claims 1
- 235000008434 ginseng Nutrition 0.000 claims 1
- 230000006872 improvement Effects 0.000 description 9
- 238000007726 management method Methods 0.000 description 7
- 238000010422 painting Methods 0.000 description 5
- 229910000831 Steel Inorganic materials 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 230000005662 electromechanics Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 230000003068 static effect Effects 0.000 description 2
- 101100033673 Mus musculus Ren1 gene Proteins 0.000 description 1
- 238000009825 accumulation Methods 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 238000013070 change management Methods 0.000 description 1
- 238000007405 data analysis Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 239000003973 paint Substances 0.000 description 1
- 238000013439 planning Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision, specific steps are as follows: (1) BIM modeling of constructing;(2) progress control platform is established in BIM secondary development, realizes the data interaction at scene with BIM;(3) by BIM progress control platform, personnel, equipment real time kinematics track, work thermal map is had access to, BIM progress analysis and real-time video monitoring are integrated;(4) by the data in step (2), (3), further analysis determines the key parameter of project progress, including worker, equipment circulation matching, flowing water section construction order, progress execution controllability;(5) it according to the data in step (2), (3), carries out overall progress and analyzes forecast assessment, Optimizing construction management improves the efficiency of management, and manages interface by BIM and fed back;(6) construction teams and groups adjust in time according to BIM control interface, respond.The present invention assists administrative staff's optimum management by BIM, improves efficiency.
Description
Technical field
The invention belongs to Construction of Civil Engineering management, realize civil engineering site operation intelligence using Beidou GNSS and BIM
Change management, in particular to a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision.
Background technique
Due to can not collection site labor service worker and equipment teams and groups real-time working situation, be difficult by BIM to construct into
Degree is analysed scientifically and is assessed.So for a long time, civil engineering/building engineering construction management is by construction experience
Accumulation and primary data analysis effectively manage construction site.
Summary of the invention
Goal of the invention: the purpose of the present invention is to solve deficiency in the prior art, provide it is a kind of based on Beidou GNSS,
The labor service of BIM construction time, equipment dynamic supervision method, quickly position realization using the personnel based on Beidou GNSS and BIM, equipment
Construction site worker's labor service, the unification of equipment and virtual reality return worker's labor service, equipment working condition by BIM completion
It receives, analyze, assist administrative staff's optimum management, improve efficiency.
Technical solution: a method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision, including following step
It is rapid:
(1) construction BIM modeling, comprising it is all face set, personal information, facility information;
(2) progress control platform is established in BIM secondary development, and the integrated personnel based on Beidou GNSS and BIM, equipment quickly position
Function realizes the data interaction at scene with BIM;
(3) by BIM progress control platform, personnel, equipment real time kinematics track, work thermal map is had access to, BIM progress analysis is integrated
And real-time video monitoring, analyze personnel, the working region of equipment, working stage, working strength situation;
(4) by the data in step (2), (3), further analysis determines the key parameter of project progress, including worker, equipment
Matching, flowing water section construction order, the progress of circulating execute controllability;
(5) it according to the data in step (2), (3), carries out overall progress and analyzes forecast assessment, Optimizing construction management improves management
Efficiency, and interface is managed by BIM and is fed back;
(6) construction teams and groups adjust in time according to BIM control interface, respond.
A further improvement of the present invention is that: step (3), it is quickly fixed by personnel/equipment based on Beidou GNSS, BIM
Position method, realizes construction site and BIM model personnel/equipment data interaction and visualization.
A further improvement of the present invention is that: step (2), the content of data interaction include: the real-time three-dimensional of personnel, equipment
Motion profile, Cell and Time Distribution section activity thermal map, task object is specified and performance, construction quality;It further include in construction area
Safety work and early warning.
A further improvement of the present invention is that: the safety work and automatic early-warning of personnel, equipment in construction area pass through meter
Calculation personnel, device space position, with reference to BIM model temporary facility position, to the automatic early-warning for entering safety zone,
Wherein, the safety work and automatic early-warning of personnel, equipment in construction area, including personnel, equipment no signal feedback or long
Phase is static or regular move reaches 5mins automatic alarm.
A further improvement of the present invention is that: step (3) integrates BIM progress analysis and real-time video monitoring, including analysis
Personnel, the working region of equipment, working stage, working strength.
A further improvement of the present invention is that: in step (3), by worker, equipment working trajectory, work heat map data
Comparison, analysis, and combine actual progress, worker's average operation thermal map, average process circulation circulation time obtained, as evaluation
The basic foundation of the working efficiency of labor service teams and groups, equipment teams and groups.
A further improvement of the present invention is that: real-time tracking labor service teams and groups, equipment teams and groups worker's average operation thermal map,
On the basis of the average process circulation circulation time, is estimated by each flowing water section project amount that BIM is provided, calculate each flowing water section
Estimate construction speed, and then assess the progress of whole topic construction, be construction management decision service.
A further improvement of the present invention is that: the data interaction entirely managed passes through BIM control platform and completes, packet
It includes:
Manager is acquired by platform, analyzes worker's labor service, equipment working condition, and optimization instruction is assigned;
Labor service teams and groups, equipment teams and groups grasp teamwork situation by platform, adjust Construction State and scheme in time;
Worker grasps oneself and team mates working condition by platform, is mutually supervised.
A further improvement of the present invention is that: step (6), construction personnel can access this system by the pad that constructs, and inquiry is applied
Work plan, arrangement and method for construction, quality, safety-related requirement, are adjusted job-shop;If it was found that personnel's real work position in system
It is equipped with mistake, can be reported to system and is corrected in time.
Compared with prior art, provided by the invention a kind of based on the labor service of Beidou GNSS, BIM construction time, equipment dynamic prison
The method of pipe, at least realize it is following the utility model has the advantages that
The present invention using based on Beidou GNSS and BIM personnel, equipment quickly position realize construction site worker labor service, equipment and
The unification of virtual reality completes conclusion, analysis to labor service, equipment working condition by BIM, administrative staff is assisted to optimize pipe
Reason, labor service teams and groups, equipment teams and groups grasp teamwork situation by platform, adjust Construction State in time and scheme, worker pass through
Platform grasps oneself and team mates working condition, is able to carry out and mutually supervises, and improves efficiency.
Certainly, not specific needs are implemented any of the products of the present invention while reaching all the above technical effect.
Detailed description of the invention
It is combined in the description and the attached drawing for constituting part of specification shows the embodiment of the present invention, and even
With its explanation together principle for explaining the present invention.
Fig. 1 is flow chart of the invention.
Specific embodiment
The existing various exemplary embodiments of detailed description of the present invention.It should also be noted that unless specifically stated otherwise, otherwise at this
Component described in a little embodiments and the positioned opposite of step, numerical expression and numerical value do not limit the scope of the invention.
Be to the description only actually of at least one exemplary embodiment below it is illustrative, never as to the present invention
And its application or any restrictions used.
Technology, method and apparatus known to person of ordinary skill in the relevant may be not discussed in detail, but suitable
In the case of, the technology, method and apparatus should be considered as part of specification.
It is shown here and discuss all examples in, any occurrence should be construed as merely illustratively, without
It is as limitation.Therefore, other examples of exemplary embodiment can have different values.
Embodiment 1,
Central China Urban House project, this engineering basement one, six to ten seven layers on the ground, dwelling layer height is 2.9m.Frame
Shear structure, 113076.5 ㎡ of overall floorage, 9238.94 ㎡ of hypogee area.
In the project, the construction BIM model of the project, including civil engineering, electromechanics, Ground arrangement BIM mould have been initially set up
Type and associate people information and facility information.Civil engineering and electromechanical speciality and Ground arrangement establish model using Revit software.
The painting work that 6 people of teams and groups carries out 6 floor of the building 1# is painted in certain daily planning arrangement, and painting teams and groups take when entering construction site
The physical location of positioning device with the miniature high accuracy positioning of GNSS containing Beidou chip, painting teams and groups personnel on site is filled by the positioning
Offer is provided;By BIM secondary development, progress control platform is established, in the construction process, production manager can pass through BIM progress
Control platform has access to painting teams and groups, equipment real time kinematics track, work thermal map, and discovery only has 4 building Ren 1#, 6 floor, and there are also 2 people
In basement.Monitoring, which is had access to, by progress control platform finds that another 2 people carries out painting repairing work in basement;By correlation point
Analysis show that the plastering construction of 4 people progress 6 floor of the building 1# cannot complete this work in time, will lead to progress extension, passes through BIM then and manage
It is fed back at control interface;Class monitor and group leader increases according to BIM control interface in time upon receipt of a notification adjusts 2 construction personnel to paint.
Such as Fig. 1, a method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision, comprising the following steps:
(1) construction BIM modeling, comprising it is all face set, personal information, facility information;
(2) progress control platform is established in BIM secondary development, and the integrated personnel based on Beidou GNSS and BIM, equipment quickly position
Function realizes the data interaction at scene with BIM;
(3) by BIM progress control platform, personnel, equipment real time kinematics track, work thermal map is had access to, BIM progress analysis is integrated
And real-time video monitoring, analyze personnel, the working region of equipment, working stage, working strength situation;
(4) by the data in step (2), (3), further analysis determines the key parameter of project progress, including worker, equipment
Matching, flowing water section construction order, the progress of circulating execute controllability;
(5) it according to the data in step (2), (3), carries out overall progress and analyzes forecast assessment, Optimizing construction management improves management
Efficiency, and interface is managed by BIM and is fed back;
(6) construction teams and groups adjust in time according to BIM control interface, respond.
Based on the above embodiment, the present invention realizes construction site and BIM model by the data interaction at scene and BIM
The data interaction of personnel/equipment and visualization are completed by the management of BIM progress control platform to worker's labor service, equipment work
Conclusion, the analysis for making situation, assist administrative staff's optimum management, and teamwork situation can be grasped by platform, is adjusted in time
Construction State and scheme, worker grasp oneself and team mates working condition by platform, are able to carry out and mutually supervise, improve
Efficiency.
In order to which the present embodiment is explained further, it should be noted that step (3) passes through the people based on Beidou GNSS, BIM
Member/equipment method for rapidly positioning realizes construction site and BIM model personnel/equipment data interaction and visualization.
In order to which the present embodiment is explained further, it should be noted that step (2), the content of data interaction include: personnel,
The real-time three-dimensional motion profile of equipment, Cell and Time Distribution section activity thermal map, task object is specified and performance, construction quality;Also
Including the safety work and early warning in construction area.
In order to which the present embodiment is explained further, it should be noted that personnel, equipment are in the safety work of construction area and oneself
Dynamic early warning, by computing staff, device space position, with reference to BIM model temporary facility position, to the automatic of entrance safety zone
Early warning,
Wherein, the safety work and automatic early-warning of personnel, equipment in construction area, including personnel, equipment no signal feedback or long
Phase is static or regular move reaches 5mins automatic alarm.
In order to which the present embodiment is explained further, it should be noted that step (3) integrates BIM progress analysis and real-time video
Monitoring, including analyzing personnel, the working region of equipment, working stage, working strength.
In order to which the present embodiment is explained further, it should be noted that in step (3), by worker, equipment work rail
Mark, the comparison for the heat map data that works, analysis, and actual progress is combined, obtain worker's average operation thermal map, average process recycle stream
Turn the time, the basic foundation of the working efficiency as evaluation labor service teams and groups, equipment teams and groups.
In order to which the present embodiment is explained further, it should be noted that in the worker of real-time tracking labor service teams and groups, equipment teams and groups
Average operation thermal map on the basis of the average process circulation circulation time, is estimated by each flowing water section project amount that BIM is provided,
It calculates the construction speed of estimating of each flowing water section, and then assesses the progress of whole topic construction, be construction management decision service.
In order to which the present embodiment is explained further, it should be noted that the data interaction entirely managed is controlled by BIM
Platform processed is completed, comprising:
Manager is acquired by platform, analyzes worker's labor service, equipment working condition, and optimization instruction is assigned;
Labor service teams and groups, equipment teams and groups grasp teamwork situation by platform, adjust Construction State and scheme in time;
Worker grasps oneself and team mates working condition by platform, is mutually supervised.
A further improvement of the present invention is that: step (6), construction personnel can access this system by the pad that constructs, and inquiry is applied
Work plan, arrangement and method for construction, quality, safety-related requirement, to be adjusted job-shop;If it was found that the practical work of personnel in system
It is wrong to make position, can be reported to system and corrects in time.
Embodiment 2,
China shores of the lower Changjiang river city International Conference and Exhibition Center project.About 12.3 ten thousand square metres of overall floorage.Construction investment
About 1,400,000,000 yuan.
In the project, the construction BIM model of the project, including civil engineering, electromechanics, steel construction and place have been initially set up
Arrange BIM model.Civil engineering and electromechanical speciality and Ground arrangement establish model using Revit software, and steel construction profession uses
Tekla software establishes model, and curtain wall profession establishes model using rhinoceros software, finally using Revit software by four professions with
And the model assembly of Ground arrangement is into a model, and establishes the device models such as tower crane, construction elevator in a model, thus complete
The foundation of integral model.
In work progress, production manager has access to real time kinematics track, the work of 1# tower crane by BIM progress control platform
Thermal map, discovery 1# tower crane is in a little motionless always, and has the point of a large amount of construction personnel to show below tower crane, then transfers
Disagreement has played about lifting in associated monitoring video, discovery steel construction teams and groups and reinforcing bar teams and groups;Interface is managed by BIM immediately and allows two
A class monitor and group leader, which shows up, coordinates matters;Finally construction teams and groups increase in time according to BIM control interface adjusts a truck crane to solve the problems, such as.
It is through the foregoing embodiment it is found that provided by the invention a kind of dynamic based on the labor service of Beidou GNSS, BIM construction time, equipment
State supervision method, at least realize it is following the utility model has the advantages that
The present invention using based on Beidou GNSS and BIM personnel, equipment quickly position realize construction site worker labor service, equipment and
The unification of virtual reality completes conclusion, analysis to worker's labor service, equipment working condition by BIM, assists administrative staff's optimization
Management, labor service teams and groups, equipment teams and groups grasp teamwork situation by platform, adjust Construction State and scheme, Gong Rentong in time
It crosses platform and grasps oneself and team mates working condition, be able to carry out and mutually supervise, improve efficiency.
Although some specific embodiments of the invention are described in detail by example, the skill of this field
Art personnel it should be understood that example above merely to being illustrated, the range being not intended to be limiting of the invention.The skill of this field
Art personnel are it should be understood that can without departing from the scope and spirit of the present invention modify to above embodiments.This hair
Bright range is defined by the following claims.
Claims (9)
1. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision, which is characterized in that including following step
It is rapid:
(1) construction BIM modeling, comprising it is all face set, personal information, facility information;
(2) progress control platform is established in BIM secondary development, and the integrated personnel based on Beidou GNSS and BIM, equipment quickly position
Function realizes the data interaction at scene with BIM;
(3) by BIM progress control platform, personnel, equipment real time kinematics track, work thermal map is had access to, BIM progress analysis is integrated
And real-time video monitoring, analyze personnel, the working region of equipment, working stage, working strength situation;
(4) by the data in step (2), (3), further analysis determines the key parameter of project progress, including worker, equipment
Matching, flowing water section construction order, the progress of circulating execute controllability;
(5) it according to the data in step (2), (3), carries out overall progress and analyzes forecast assessment, Optimizing construction management improves management
Efficiency, and interface is managed by BIM and is fed back;
(6) construction teams and groups adjust in time according to BIM control interface, respond.
2. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 1,
It is characterized in that,
Step (3) realizes construction site and BIM model by the personnel based on Beidou GNSS, BIM/equipment method for rapidly positioning
The data interaction of personnel/equipment and visualization.
3. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 1,
It is characterized in that,
The step (2), the content of data interaction include: personnel, the real-time three-dimensional motion profile of equipment, Cell and Time Distribution section activity
Thermal map, task object is specified and performance, construction quality;It further include the safety work and early warning in construction area.
4. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 3, special
Sign is,
The safety work and automatic early-warning of the personnel, equipment in construction area pass through computing staff, device space position, ginseng
Examine BIM model temporary facility position, to enter safety zone automatic early-warning,
Wherein, the safety work and automatic early-warning of the personnel, equipment in construction area, including personnel, equipment no signal feedback
Or long inactivity or regular movement reach 5mins automatic alarm.
5. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 1,
It is characterized in that,
Step (3) integrates BIM progress analysis and real-time video monitoring, including analysis personnel, the working region of equipment, work rank
Section, working strength.
6. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 1,
It is characterized in that,
In step (3), by worker, equipment working trajectory, work heat map data comparison, analysis, and combine actual progress,
Obtain worker's average operation thermal map, average process circulation circulation time, the working efficiency as evaluation labor service teams and groups, equipment teams and groups
Basic foundation.
7. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 6,
It is characterized in that,
In real-time tracking labor service teams and groups, worker's average operation thermal map of equipment teams and groups, the basis of average process circulation circulation time
On, it is estimated by each flowing water section project amount that BIM is provided, calculates the construction speed of estimating of each flowing water section, and then assess whole
The progress of construction is inscribed, is construction management decision service.
8. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 1,
It is characterized in that,
The data interaction entirely managed passes through BIM control platform and completes, comprising:
Manager is acquired by platform, analyzes worker's labor service, equipment working condition, and optimization instruction is assigned;
Labor service teams and groups, equipment teams and groups grasp teamwork situation by platform, adjust Construction State and scheme in time;
Worker grasps oneself and team mates working condition by platform, is mutually supervised.
9. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 1,
It is characterized in that,
The step (6), construction personnel can access this system by the pad that constructs, inquire construction plan, arrangement and method for construction, quality, peace
Total correlation requirement, is adjusted job-shop;If being reported to system and timely it was found that personnel's real work position is wrong in system
Amendment.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910103230.3A CN109816263A (en) | 2019-02-01 | 2019-02-01 | A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910103230.3A CN109816263A (en) | 2019-02-01 | 2019-02-01 | A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109816263A true CN109816263A (en) | 2019-05-28 |
Family
ID=66605175
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910103230.3A Pending CN109816263A (en) | 2019-02-01 | 2019-02-01 | A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109816263A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112781567A (en) * | 2020-12-07 | 2021-05-11 | 广东建设职业技术学院 | Construction progress monitoring method based on small program, Beidou GNSS and BIM |
CN113882863A (en) * | 2021-09-29 | 2022-01-04 | 重庆建工第七建筑工程有限责任公司 | Construction method of underground complex frame shear structure based on BIM technology |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106910009A (en) * | 2017-01-24 | 2017-06-30 | 广西建工集团第五建筑工程有限责任公司 | Construction manpower management system based on BIM technology and its method for manpower management of constructing |
CN107679820A (en) * | 2017-08-30 | 2018-02-09 | 深圳市易联智道科技有限公司 | Construction Schedule management method |
CN107993000A (en) * | 2017-11-27 | 2018-05-04 | 中国十九冶集团有限公司 | The method of construction main flat face dynamic coordinate management based on BIM |
CN108053150A (en) * | 2018-01-09 | 2018-05-18 | 中建七局安装工程有限公司 | A kind of site operation personnel's intelligent management based on BIM |
CN108469752A (en) * | 2018-04-27 | 2018-08-31 | 中国建筑第二工程局有限公司 | A kind of security management and control system and method based on GPS positioning and BIM models |
CN108596423A (en) * | 2018-03-02 | 2018-09-28 | 重庆机电装备技术研究院有限公司 | A kind of trackways engineering construction progress msg management method based on BIM |
-
2019
- 2019-02-01 CN CN201910103230.3A patent/CN109816263A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106910009A (en) * | 2017-01-24 | 2017-06-30 | 广西建工集团第五建筑工程有限责任公司 | Construction manpower management system based on BIM technology and its method for manpower management of constructing |
CN107679820A (en) * | 2017-08-30 | 2018-02-09 | 深圳市易联智道科技有限公司 | Construction Schedule management method |
CN107993000A (en) * | 2017-11-27 | 2018-05-04 | 中国十九冶集团有限公司 | The method of construction main flat face dynamic coordinate management based on BIM |
CN108053150A (en) * | 2018-01-09 | 2018-05-18 | 中建七局安装工程有限公司 | A kind of site operation personnel's intelligent management based on BIM |
CN108596423A (en) * | 2018-03-02 | 2018-09-28 | 重庆机电装备技术研究院有限公司 | A kind of trackways engineering construction progress msg management method based on BIM |
CN108469752A (en) * | 2018-04-27 | 2018-08-31 | 中国建筑第二工程局有限公司 | A kind of security management and control system and method based on GPS positioning and BIM models |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112781567A (en) * | 2020-12-07 | 2021-05-11 | 广东建设职业技术学院 | Construction progress monitoring method based on small program, Beidou GNSS and BIM |
CN113882863A (en) * | 2021-09-29 | 2022-01-04 | 重庆建工第七建筑工程有限责任公司 | Construction method of underground complex frame shear structure based on BIM technology |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Zhang et al. | BIM-and 4D-based integrated solution of analysis and management for conflicts and structural safety problems during construction: 1. Principles and methodologies | |
Tam et al. | GA-ANN model for optimizing the locations of tower crane and supply points for high-rise public housing construction | |
CN109801038A (en) | A kind of versatility engineering construction method based on BIM technology application | |
WO2020056669A1 (en) | Control method and apparatus for unmanned aerial vehicle cruise based on prefabricated building platform | |
CN109523107A (en) | A kind of Construction Management System and method based on BIM | |
CN109856655A (en) | A kind of construction time personnel positioning based on Beidou GNSS and BIM, monitoring and managing method | |
CN108280281A (en) | A kind of construction cost control method and system based on BIM technology | |
CN109816263A (en) | A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision | |
CN112907389A (en) | Land, air and space integrated intelligent construction site system and management method | |
Yoo et al. | Genetic algorithm-based steel erection planning model for a construction automation system | |
CN115330253A (en) | BIM-based industrial base construction comprehensive management system and method | |
Wang et al. | Integrating building information modelling and firefly algorithm to optimize tower crane layout | |
Hu et al. | Estimating and visualizing the exposure to tower crane operation hazards on construction sites | |
CN111709081A (en) | Construction cost control system based on BIM technology | |
CN115329416A (en) | Building construction method based on BIM | |
CN109558606A (en) | BIM Tender System | |
Xu | Analysis of Safety Behavior of Prefabricated Building Workers’ Hoisting Operation Based on Computer Vision | |
CN117236892A (en) | Digital twin-based bridge steel web water transportation hoisting system and control method | |
CN114594697B (en) | Internet of things type intelligent climbing rack controller | |
Russell et al. | Assessing the quality of a construction schedule | |
Ezzeddine et al. | Singularity functions to enhance monitoring in the last planner system | |
Castro-Lacouture | Construction Automation and Smart Buildings | |
Balaguer | Nowadays trends in robotics and automation in construction industry: Transition from hard to soft robotics | |
Bagautdinov et al. | Feasibility study tool for semi-rigid joints design of high-rise buildings steel structures | |
CN107067160A (en) | A kind of assembled architecture allocation of the labour force method based on BIM |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190528 |