CN109816263A - A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision - Google Patents

A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision Download PDF

Info

Publication number
CN109816263A
CN109816263A CN201910103230.3A CN201910103230A CN109816263A CN 109816263 A CN109816263 A CN 109816263A CN 201910103230 A CN201910103230 A CN 201910103230A CN 109816263 A CN109816263 A CN 109816263A
Authority
CN
China
Prior art keywords
bim
construction
equipment
time
personnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910103230.3A
Other languages
Chinese (zh)
Inventor
耿裕华
徐卓
张卫国
朱岭
穆小香
周昕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Sijian Construction Group Co Ltd
Original Assignee
Nantong Sijian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Sijian Construction Group Co Ltd filed Critical Nantong Sijian Construction Group Co Ltd
Priority to CN201910103230.3A priority Critical patent/CN109816263A/en
Publication of CN109816263A publication Critical patent/CN109816263A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision, specific steps are as follows: (1) BIM modeling of constructing;(2) progress control platform is established in BIM secondary development, realizes the data interaction at scene with BIM;(3) by BIM progress control platform, personnel, equipment real time kinematics track, work thermal map is had access to, BIM progress analysis and real-time video monitoring are integrated;(4) by the data in step (2), (3), further analysis determines the key parameter of project progress, including worker, equipment circulation matching, flowing water section construction order, progress execution controllability;(5) it according to the data in step (2), (3), carries out overall progress and analyzes forecast assessment, Optimizing construction management improves the efficiency of management, and manages interface by BIM and fed back;(6) construction teams and groups adjust in time according to BIM control interface, respond.The present invention assists administrative staff's optimum management by BIM, improves efficiency.

Description

A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision
Technical field
The invention belongs to Construction of Civil Engineering management, realize civil engineering site operation intelligence using Beidou GNSS and BIM Change management, in particular to a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision.
Background technique
Due to can not collection site labor service worker and equipment teams and groups real-time working situation, be difficult by BIM to construct into Degree is analysed scientifically and is assessed.So for a long time, civil engineering/building engineering construction management is by construction experience Accumulation and primary data analysis effectively manage construction site.
Summary of the invention
Goal of the invention: the purpose of the present invention is to solve deficiency in the prior art, provide it is a kind of based on Beidou GNSS, The labor service of BIM construction time, equipment dynamic supervision method, quickly position realization using the personnel based on Beidou GNSS and BIM, equipment Construction site worker's labor service, the unification of equipment and virtual reality return worker's labor service, equipment working condition by BIM completion It receives, analyze, assist administrative staff's optimum management, improve efficiency.
Technical solution: a method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision, including following step It is rapid:
(1) construction BIM modeling, comprising it is all face set, personal information, facility information;
(2) progress control platform is established in BIM secondary development, and the integrated personnel based on Beidou GNSS and BIM, equipment quickly position Function realizes the data interaction at scene with BIM;
(3) by BIM progress control platform, personnel, equipment real time kinematics track, work thermal map is had access to, BIM progress analysis is integrated And real-time video monitoring, analyze personnel, the working region of equipment, working stage, working strength situation;
(4) by the data in step (2), (3), further analysis determines the key parameter of project progress, including worker, equipment Matching, flowing water section construction order, the progress of circulating execute controllability;
(5) it according to the data in step (2), (3), carries out overall progress and analyzes forecast assessment, Optimizing construction management improves management Efficiency, and interface is managed by BIM and is fed back;
(6) construction teams and groups adjust in time according to BIM control interface, respond.
A further improvement of the present invention is that: step (3), it is quickly fixed by personnel/equipment based on Beidou GNSS, BIM Position method, realizes construction site and BIM model personnel/equipment data interaction and visualization.
A further improvement of the present invention is that: step (2), the content of data interaction include: the real-time three-dimensional of personnel, equipment Motion profile, Cell and Time Distribution section activity thermal map, task object is specified and performance, construction quality;It further include in construction area Safety work and early warning.
A further improvement of the present invention is that: the safety work and automatic early-warning of personnel, equipment in construction area pass through meter Calculation personnel, device space position, with reference to BIM model temporary facility position, to the automatic early-warning for entering safety zone,
Wherein, the safety work and automatic early-warning of personnel, equipment in construction area, including personnel, equipment no signal feedback or long Phase is static or regular move reaches 5mins automatic alarm.
A further improvement of the present invention is that: step (3) integrates BIM progress analysis and real-time video monitoring, including analysis Personnel, the working region of equipment, working stage, working strength.
A further improvement of the present invention is that: in step (3), by worker, equipment working trajectory, work heat map data Comparison, analysis, and combine actual progress, worker's average operation thermal map, average process circulation circulation time obtained, as evaluation The basic foundation of the working efficiency of labor service teams and groups, equipment teams and groups.
A further improvement of the present invention is that: real-time tracking labor service teams and groups, equipment teams and groups worker's average operation thermal map, On the basis of the average process circulation circulation time, is estimated by each flowing water section project amount that BIM is provided, calculate each flowing water section Estimate construction speed, and then assess the progress of whole topic construction, be construction management decision service.
A further improvement of the present invention is that: the data interaction entirely managed passes through BIM control platform and completes, packet It includes:
Manager is acquired by platform, analyzes worker's labor service, equipment working condition, and optimization instruction is assigned;
Labor service teams and groups, equipment teams and groups grasp teamwork situation by platform, adjust Construction State and scheme in time;
Worker grasps oneself and team mates working condition by platform, is mutually supervised.
A further improvement of the present invention is that: step (6), construction personnel can access this system by the pad that constructs, and inquiry is applied Work plan, arrangement and method for construction, quality, safety-related requirement, are adjusted job-shop;If it was found that personnel's real work position in system It is equipped with mistake, can be reported to system and is corrected in time.
Compared with prior art, provided by the invention a kind of based on the labor service of Beidou GNSS, BIM construction time, equipment dynamic prison The method of pipe, at least realize it is following the utility model has the advantages that
The present invention using based on Beidou GNSS and BIM personnel, equipment quickly position realize construction site worker labor service, equipment and The unification of virtual reality completes conclusion, analysis to labor service, equipment working condition by BIM, administrative staff is assisted to optimize pipe Reason, labor service teams and groups, equipment teams and groups grasp teamwork situation by platform, adjust Construction State in time and scheme, worker pass through Platform grasps oneself and team mates working condition, is able to carry out and mutually supervises, and improves efficiency.
Certainly, not specific needs are implemented any of the products of the present invention while reaching all the above technical effect.
Detailed description of the invention
It is combined in the description and the attached drawing for constituting part of specification shows the embodiment of the present invention, and even With its explanation together principle for explaining the present invention.
Fig. 1 is flow chart of the invention.
Specific embodiment
The existing various exemplary embodiments of detailed description of the present invention.It should also be noted that unless specifically stated otherwise, otherwise at this Component described in a little embodiments and the positioned opposite of step, numerical expression and numerical value do not limit the scope of the invention.
Be to the description only actually of at least one exemplary embodiment below it is illustrative, never as to the present invention And its application or any restrictions used.
Technology, method and apparatus known to person of ordinary skill in the relevant may be not discussed in detail, but suitable In the case of, the technology, method and apparatus should be considered as part of specification.
It is shown here and discuss all examples in, any occurrence should be construed as merely illustratively, without It is as limitation.Therefore, other examples of exemplary embodiment can have different values.
Embodiment 1,
Central China Urban House project, this engineering basement one, six to ten seven layers on the ground, dwelling layer height is 2.9m.Frame Shear structure, 113076.5 ㎡ of overall floorage, 9238.94 ㎡ of hypogee area.
In the project, the construction BIM model of the project, including civil engineering, electromechanics, Ground arrangement BIM mould have been initially set up Type and associate people information and facility information.Civil engineering and electromechanical speciality and Ground arrangement establish model using Revit software.
The painting work that 6 people of teams and groups carries out 6 floor of the building 1# is painted in certain daily planning arrangement, and painting teams and groups take when entering construction site The physical location of positioning device with the miniature high accuracy positioning of GNSS containing Beidou chip, painting teams and groups personnel on site is filled by the positioning Offer is provided;By BIM secondary development, progress control platform is established, in the construction process, production manager can pass through BIM progress Control platform has access to painting teams and groups, equipment real time kinematics track, work thermal map, and discovery only has 4 building Ren 1#, 6 floor, and there are also 2 people In basement.Monitoring, which is had access to, by progress control platform finds that another 2 people carries out painting repairing work in basement;By correlation point Analysis show that the plastering construction of 4 people progress 6 floor of the building 1# cannot complete this work in time, will lead to progress extension, passes through BIM then and manage It is fed back at control interface;Class monitor and group leader increases according to BIM control interface in time upon receipt of a notification adjusts 2 construction personnel to paint.
Such as Fig. 1, a method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision, comprising the following steps:
(1) construction BIM modeling, comprising it is all face set, personal information, facility information;
(2) progress control platform is established in BIM secondary development, and the integrated personnel based on Beidou GNSS and BIM, equipment quickly position Function realizes the data interaction at scene with BIM;
(3) by BIM progress control platform, personnel, equipment real time kinematics track, work thermal map is had access to, BIM progress analysis is integrated And real-time video monitoring, analyze personnel, the working region of equipment, working stage, working strength situation;
(4) by the data in step (2), (3), further analysis determines the key parameter of project progress, including worker, equipment Matching, flowing water section construction order, the progress of circulating execute controllability;
(5) it according to the data in step (2), (3), carries out overall progress and analyzes forecast assessment, Optimizing construction management improves management Efficiency, and interface is managed by BIM and is fed back;
(6) construction teams and groups adjust in time according to BIM control interface, respond.
Based on the above embodiment, the present invention realizes construction site and BIM model by the data interaction at scene and BIM The data interaction of personnel/equipment and visualization are completed by the management of BIM progress control platform to worker's labor service, equipment work Conclusion, the analysis for making situation, assist administrative staff's optimum management, and teamwork situation can be grasped by platform, is adjusted in time Construction State and scheme, worker grasp oneself and team mates working condition by platform, are able to carry out and mutually supervise, improve Efficiency.
In order to which the present embodiment is explained further, it should be noted that step (3) passes through the people based on Beidou GNSS, BIM Member/equipment method for rapidly positioning realizes construction site and BIM model personnel/equipment data interaction and visualization.
In order to which the present embodiment is explained further, it should be noted that step (2), the content of data interaction include: personnel, The real-time three-dimensional motion profile of equipment, Cell and Time Distribution section activity thermal map, task object is specified and performance, construction quality;Also Including the safety work and early warning in construction area.
In order to which the present embodiment is explained further, it should be noted that personnel, equipment are in the safety work of construction area and oneself Dynamic early warning, by computing staff, device space position, with reference to BIM model temporary facility position, to the automatic of entrance safety zone Early warning,
Wherein, the safety work and automatic early-warning of personnel, equipment in construction area, including personnel, equipment no signal feedback or long Phase is static or regular move reaches 5mins automatic alarm.
In order to which the present embodiment is explained further, it should be noted that step (3) integrates BIM progress analysis and real-time video Monitoring, including analyzing personnel, the working region of equipment, working stage, working strength.
In order to which the present embodiment is explained further, it should be noted that in step (3), by worker, equipment work rail Mark, the comparison for the heat map data that works, analysis, and actual progress is combined, obtain worker's average operation thermal map, average process recycle stream Turn the time, the basic foundation of the working efficiency as evaluation labor service teams and groups, equipment teams and groups.
In order to which the present embodiment is explained further, it should be noted that in the worker of real-time tracking labor service teams and groups, equipment teams and groups Average operation thermal map on the basis of the average process circulation circulation time, is estimated by each flowing water section project amount that BIM is provided, It calculates the construction speed of estimating of each flowing water section, and then assesses the progress of whole topic construction, be construction management decision service.
In order to which the present embodiment is explained further, it should be noted that the data interaction entirely managed is controlled by BIM Platform processed is completed, comprising:
Manager is acquired by platform, analyzes worker's labor service, equipment working condition, and optimization instruction is assigned;
Labor service teams and groups, equipment teams and groups grasp teamwork situation by platform, adjust Construction State and scheme in time;
Worker grasps oneself and team mates working condition by platform, is mutually supervised.
A further improvement of the present invention is that: step (6), construction personnel can access this system by the pad that constructs, and inquiry is applied Work plan, arrangement and method for construction, quality, safety-related requirement, to be adjusted job-shop;If it was found that the practical work of personnel in system It is wrong to make position, can be reported to system and corrects in time.
Embodiment 2,
China shores of the lower Changjiang river city International Conference and Exhibition Center project.About 12.3 ten thousand square metres of overall floorage.Construction investment About 1,400,000,000 yuan.
In the project, the construction BIM model of the project, including civil engineering, electromechanics, steel construction and place have been initially set up Arrange BIM model.Civil engineering and electromechanical speciality and Ground arrangement establish model using Revit software, and steel construction profession uses Tekla software establishes model, and curtain wall profession establishes model using rhinoceros software, finally using Revit software by four professions with And the model assembly of Ground arrangement is into a model, and establishes the device models such as tower crane, construction elevator in a model, thus complete The foundation of integral model.
In work progress, production manager has access to real time kinematics track, the work of 1# tower crane by BIM progress control platform Thermal map, discovery 1# tower crane is in a little motionless always, and has the point of a large amount of construction personnel to show below tower crane, then transfers Disagreement has played about lifting in associated monitoring video, discovery steel construction teams and groups and reinforcing bar teams and groups;Interface is managed by BIM immediately and allows two A class monitor and group leader, which shows up, coordinates matters;Finally construction teams and groups increase in time according to BIM control interface adjusts a truck crane to solve the problems, such as.
It is through the foregoing embodiment it is found that provided by the invention a kind of dynamic based on the labor service of Beidou GNSS, BIM construction time, equipment State supervision method, at least realize it is following the utility model has the advantages that
The present invention using based on Beidou GNSS and BIM personnel, equipment quickly position realize construction site worker labor service, equipment and The unification of virtual reality completes conclusion, analysis to worker's labor service, equipment working condition by BIM, assists administrative staff's optimization Management, labor service teams and groups, equipment teams and groups grasp teamwork situation by platform, adjust Construction State and scheme, Gong Rentong in time It crosses platform and grasps oneself and team mates working condition, be able to carry out and mutually supervise, improve efficiency.
Although some specific embodiments of the invention are described in detail by example, the skill of this field Art personnel it should be understood that example above merely to being illustrated, the range being not intended to be limiting of the invention.The skill of this field Art personnel are it should be understood that can without departing from the scope and spirit of the present invention modify to above embodiments.This hair Bright range is defined by the following claims.

Claims (9)

1. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision, which is characterized in that including following step It is rapid:
(1) construction BIM modeling, comprising it is all face set, personal information, facility information;
(2) progress control platform is established in BIM secondary development, and the integrated personnel based on Beidou GNSS and BIM, equipment quickly position Function realizes the data interaction at scene with BIM;
(3) by BIM progress control platform, personnel, equipment real time kinematics track, work thermal map is had access to, BIM progress analysis is integrated And real-time video monitoring, analyze personnel, the working region of equipment, working stage, working strength situation;
(4) by the data in step (2), (3), further analysis determines the key parameter of project progress, including worker, equipment Matching, flowing water section construction order, the progress of circulating execute controllability;
(5) it according to the data in step (2), (3), carries out overall progress and analyzes forecast assessment, Optimizing construction management improves management Efficiency, and interface is managed by BIM and is fed back;
(6) construction teams and groups adjust in time according to BIM control interface, respond.
2. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 1, It is characterized in that,
Step (3) realizes construction site and BIM model by the personnel based on Beidou GNSS, BIM/equipment method for rapidly positioning The data interaction of personnel/equipment and visualization.
3. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 1, It is characterized in that,
The step (2), the content of data interaction include: personnel, the real-time three-dimensional motion profile of equipment, Cell and Time Distribution section activity Thermal map, task object is specified and performance, construction quality;It further include the safety work and early warning in construction area.
4. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 3, special Sign is,
The safety work and automatic early-warning of the personnel, equipment in construction area pass through computing staff, device space position, ginseng Examine BIM model temporary facility position, to enter safety zone automatic early-warning,
Wherein, the safety work and automatic early-warning of the personnel, equipment in construction area, including personnel, equipment no signal feedback Or long inactivity or regular movement reach 5mins automatic alarm.
5. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 1, It is characterized in that,
Step (3) integrates BIM progress analysis and real-time video monitoring, including analysis personnel, the working region of equipment, work rank Section, working strength.
6. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 1, It is characterized in that,
In step (3), by worker, equipment working trajectory, work heat map data comparison, analysis, and combine actual progress, Obtain worker's average operation thermal map, average process circulation circulation time, the working efficiency as evaluation labor service teams and groups, equipment teams and groups Basic foundation.
7. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 6, It is characterized in that,
In real-time tracking labor service teams and groups, worker's average operation thermal map of equipment teams and groups, the basis of average process circulation circulation time On, it is estimated by each flowing water section project amount that BIM is provided, calculates the construction speed of estimating of each flowing water section, and then assess whole The progress of construction is inscribed, is construction management decision service.
8. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 1, It is characterized in that,
The data interaction entirely managed passes through BIM control platform and completes, comprising:
Manager is acquired by platform, analyzes worker's labor service, equipment working condition, and optimization instruction is assigned;
Labor service teams and groups, equipment teams and groups grasp teamwork situation by platform, adjust Construction State and scheme in time;
Worker grasps oneself and team mates working condition by platform, is mutually supervised.
9. a kind of method based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision according to claim 1, It is characterized in that,
The step (6), construction personnel can access this system by the pad that constructs, inquire construction plan, arrangement and method for construction, quality, peace Total correlation requirement, is adjusted job-shop;If being reported to system and timely it was found that personnel's real work position is wrong in system Amendment.
CN201910103230.3A 2019-02-01 2019-02-01 A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision Pending CN109816263A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910103230.3A CN109816263A (en) 2019-02-01 2019-02-01 A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910103230.3A CN109816263A (en) 2019-02-01 2019-02-01 A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision

Publications (1)

Publication Number Publication Date
CN109816263A true CN109816263A (en) 2019-05-28

Family

ID=66605175

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910103230.3A Pending CN109816263A (en) 2019-02-01 2019-02-01 A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision

Country Status (1)

Country Link
CN (1) CN109816263A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112781567A (en) * 2020-12-07 2021-05-11 广东建设职业技术学院 Construction progress monitoring method based on small program, Beidou GNSS and BIM
CN113882863A (en) * 2021-09-29 2022-01-04 重庆建工第七建筑工程有限责任公司 Construction method of underground complex frame shear structure based on BIM technology

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106910009A (en) * 2017-01-24 2017-06-30 广西建工集团第五建筑工程有限责任公司 Construction manpower management system based on BIM technology and its method for manpower management of constructing
CN107679820A (en) * 2017-08-30 2018-02-09 深圳市易联智道科技有限公司 Construction Schedule management method
CN107993000A (en) * 2017-11-27 2018-05-04 中国十九冶集团有限公司 The method of construction main flat face dynamic coordinate management based on BIM
CN108053150A (en) * 2018-01-09 2018-05-18 中建七局安装工程有限公司 A kind of site operation personnel's intelligent management based on BIM
CN108469752A (en) * 2018-04-27 2018-08-31 中国建筑第二工程局有限公司 A kind of security management and control system and method based on GPS positioning and BIM models
CN108596423A (en) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 A kind of trackways engineering construction progress msg management method based on BIM

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106910009A (en) * 2017-01-24 2017-06-30 广西建工集团第五建筑工程有限责任公司 Construction manpower management system based on BIM technology and its method for manpower management of constructing
CN107679820A (en) * 2017-08-30 2018-02-09 深圳市易联智道科技有限公司 Construction Schedule management method
CN107993000A (en) * 2017-11-27 2018-05-04 中国十九冶集团有限公司 The method of construction main flat face dynamic coordinate management based on BIM
CN108053150A (en) * 2018-01-09 2018-05-18 中建七局安装工程有限公司 A kind of site operation personnel's intelligent management based on BIM
CN108596423A (en) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 A kind of trackways engineering construction progress msg management method based on BIM
CN108469752A (en) * 2018-04-27 2018-08-31 中国建筑第二工程局有限公司 A kind of security management and control system and method based on GPS positioning and BIM models

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112781567A (en) * 2020-12-07 2021-05-11 广东建设职业技术学院 Construction progress monitoring method based on small program, Beidou GNSS and BIM
CN113882863A (en) * 2021-09-29 2022-01-04 重庆建工第七建筑工程有限责任公司 Construction method of underground complex frame shear structure based on BIM technology

Similar Documents

Publication Publication Date Title
Zhang et al. BIM-and 4D-based integrated solution of analysis and management for conflicts and structural safety problems during construction: 1. Principles and methodologies
Tam et al. GA-ANN model for optimizing the locations of tower crane and supply points for high-rise public housing construction
CN109801038A (en) A kind of versatility engineering construction method based on BIM technology application
WO2020056669A1 (en) Control method and apparatus for unmanned aerial vehicle cruise based on prefabricated building platform
CN109523107A (en) A kind of Construction Management System and method based on BIM
CN109856655A (en) A kind of construction time personnel positioning based on Beidou GNSS and BIM, monitoring and managing method
CN108280281A (en) A kind of construction cost control method and system based on BIM technology
CN109816263A (en) A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision
CN112907389A (en) Land, air and space integrated intelligent construction site system and management method
Yoo et al. Genetic algorithm-based steel erection planning model for a construction automation system
CN115330253A (en) BIM-based industrial base construction comprehensive management system and method
Wang et al. Integrating building information modelling and firefly algorithm to optimize tower crane layout
Hu et al. Estimating and visualizing the exposure to tower crane operation hazards on construction sites
CN111709081A (en) Construction cost control system based on BIM technology
CN115329416A (en) Building construction method based on BIM
CN109558606A (en) BIM Tender System
Xu Analysis of Safety Behavior of Prefabricated Building Workers’ Hoisting Operation Based on Computer Vision
CN117236892A (en) Digital twin-based bridge steel web water transportation hoisting system and control method
CN114594697B (en) Internet of things type intelligent climbing rack controller
Russell et al. Assessing the quality of a construction schedule
Ezzeddine et al. Singularity functions to enhance monitoring in the last planner system
Castro-Lacouture Construction Automation and Smart Buildings
Balaguer Nowadays trends in robotics and automation in construction industry: Transition from hard to soft robotics
Bagautdinov et al. Feasibility study tool for semi-rigid joints design of high-rise buildings steel structures
CN107067160A (en) A kind of assembled architecture allocation of the labour force method based on BIM

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190528