CN107067160A - A kind of assembled architecture allocation of the labour force method based on BIM - Google Patents

A kind of assembled architecture allocation of the labour force method based on BIM Download PDF

Info

Publication number
CN107067160A
CN107067160A CN201710145144.XA CN201710145144A CN107067160A CN 107067160 A CN107067160 A CN 107067160A CN 201710145144 A CN201710145144 A CN 201710145144A CN 107067160 A CN107067160 A CN 107067160A
Authority
CN
China
Prior art keywords
assembled architecture
labour
bim
method based
region
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710145144.XA
Other languages
Chinese (zh)
Inventor
徐宁
王广斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongji University
Original Assignee
Tongji University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongji University filed Critical Tongji University
Priority to CN201710145144.XA priority Critical patent/CN107067160A/en
Publication of CN107067160A publication Critical patent/CN107067160A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063116Schedule adjustment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The present invention relates to a kind of assembled architecture allocation of the labour force method based on BIM, comprise the following steps:1) position of on-site personnel is obtained by way of the positioning of scene;2) threedimensional model of assembled architecture is set up according to assembled architecture drawing;3) position of real-time update on-site personnel and draw movement track and show in the three-dimensional model;4) the three-dimensional installation process simulation of prefabricated member is carried out using BIM softwares;5) operating personnel's movement track is installed with prefabricated member three-dimensional and matched, the statistics of assembled architecture labour's operation resource is obtained in real time;6) obtained according to statistics and show labour intensive region and the region of manpower shortage;7) labour in labour intensive region and the region of manpower shortage is reallocated respectively, makes Work types balanced.Compared with prior art, the present invention have the advantages that real-time Simulation, dynamically associate, rationally accurately.

Description

A kind of assembled architecture allocation of the labour force method based on BIM
Technical field
The present invention relates to assembled architecture construction field, more particularly, to a kind of assembled architecture labour based on BIM Concocting method.
Background technology
Assembled architecture installs the advantage such as quick, duration shortening, energy-saving with it, at this stage by wide popularization and application. In fabricated construction construction, labour's operation resource is general to carry out cloth according to construction planning and field condition and progress status Put, intersecting intensive and flowing water section due to assembled arthitecutral structure process divides less, and builder often concentrates on specific region Another region is arrived after completion task again and carries out continuous productive process, the not enough situation of working face is caused, fails to have given play to construction operation class The maximum efficiency of group personnel, seriously limits assembled architecture construction speed.
The content of the invention
It is an object of the present invention to overcome the above-mentioned drawbacks of the prior art and provide a kind of real-time Simulation, dynamic Association, the rationally accurate assembled architecture allocation of the labour force method based on BIM.
The purpose of the present invention can be achieved through the following technical solutions:
A kind of assembled architecture allocation of the labour force method based on BIM, comprises the following steps:
1) position of on-site personnel is obtained by way of the positioning of scene;
2) threedimensional model of assembled architecture is set up according to assembled architecture drawing;
3) position of real-time update on-site personnel and draw movement track and show in the three-dimensional model;
4) the three-dimensional installation process simulation of prefabricated member is carried out using BIM softwares;
5) operating personnel's movement track is installed with prefabricated member three-dimensional and matched, assembled architecture work is obtained in real time The statistics of masterpiece industry resource;
6) obtained according to statistics and show labour intensive region and the region of manpower shortage;
7) labour in labour intensive region and the region of manpower shortage is reallocated respectively, makes labour point Balancing.
Described step 4) in, the actual progress and prefabricated member for being installed prefabricated member using BIM softwares are three-dimensional Installation process is associated, and makes up to the requirement of 4D displayings.
Described step 5) in, the composition of operating personnel is classified, the required work post of component installation procedure is determined, The process that operating personnel after classification is installed with component is associated.
Described step 1) specifically include following steps:
11) positioning chip is set in the on-site personnel safety cap of assembled architecture labour's operation field;
12) multiple positioning websites are arranged around assembled architecture, the signal that positioning website is launched is covered building Each corner of thing;
13) by positioning the data cube computation of website and positioning chip in safety cap, the position of whole on-site personnels is obtained Put.
Described step 11) in, multiple positioning websites position the position of on-site personnel by WIFI.
Described step 6) in, judge the threshold value of labour intensive region and manpower shortage for 3m per capita2
Compared with prior art, the present invention has advantages below:
This method is simulated to assembled architecture construction area operating personnel, and correspondence associates and is illustrated in three-dimensional visualization On model, assembled architecture human resources are reasonably allocated by dynamic data, and then raising field operation efficiency, Even in the assembled architecture job site that the duration is tighter, also can rationally, accurately and timely to labour's operation resource it carry out real Allotment is applied, accelerates assembled architecture construction paces.
Brief description of the drawings
Fig. 1 is flow chart of the method for the present invention.
Embodiment
The present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings.
Embodiment
As shown in figure 1, the present invention provides a kind of engineering material stacking method based on BIM, specifically include
Positioning chip is set in step 1, at the scene labour operating personnel safety cap, and operating personnel is by regulation safe wearing Cap carries out constructing operation to scene;
Step 2, the side of assembled architecture four arrange several location equipments, and lay WiFi network, launch location equipment Signal can cover each corner of building;
Step 3, assembled architecture threedimensional model is set up according to drawing;
Step 4, the data cube computation by setting up positioning chip in building periphery location equipment and safety cap, record scene Movement track of the operating personnel in assembled architecture typical floor plan;
Step 5, the movement track of on-site personnel is shown in the three-dimensional model in real time;
Step 6, operation BIM softwares carry out prefabricated member three-dimensional and install Whole Process Simulation, by actual progress and assembled Components three-dimensional installation process is associated, and reaches 4D displaying requirements;
Step 7, in this Modular building member planar, operating personnel's movement track is entered with prefabricated member installation steps Row matching, obtains assembled architecture labour's operation resource statistics, the composition of operating personnel is classified in real time, it is determined that Work post composition when component is installed, the process then installed again with component is associated;
Step 8, threedimensional model emphasis displaying density are concentrated and the inadequate region of working face, and such as density calculation formula standard is this Region 3 ㎡ per capita, after person works' density is less than 3 ㎡, then red display is marked in the region;
Step 9, calculating flood labour's work intensity, and be identified with different colours, need are lifted according to three-dimensional structure Will, manual adjustment is carried out to labour intensive region, 3 ㎡ are larger than, scheduling job resource to specified clear area is carried out simultaneously Row operation.

Claims (6)

1. a kind of assembled architecture allocation of the labour force method based on BIM, it is characterised in that comprise the following steps:
1) position of on-site personnel is obtained by way of the positioning of scene;
2) threedimensional model of assembled architecture is set up according to assembled architecture drawing;
3) position of real-time update on-site personnel and draw movement track and show in the three-dimensional model;
4) the three-dimensional installation process simulation of prefabricated member is carried out using BIM softwares;
5) operating personnel's movement track is installed with prefabricated member three-dimensional and matched, assembled architecture work masterpiece is obtained in real time The statistics of industry resource;
6) obtained according to statistics and show labour intensive region and the region of manpower shortage;
7) labour in labour intensive region and the region of manpower shortage is reallocated respectively, makes Work types equal Weighing apparatus.
2. a kind of assembled architecture allocation of the labour force method based on BIM according to claim 1, it is characterised in that institute The step 4 stated) in, the actual progress for being installed prefabricated member using BIM softwares is entered with the three-dimensional installation process of prefabricated member Row association, makes up to the requirement of 4D displayings.
3. a kind of assembled architecture allocation of the labour force method based on BIM according to claim 1, it is characterised in that institute The step 5 stated) in, the composition of operating personnel is classified, the required work post of component installation procedure is determined, will be made after classification The process that industry personnel install with component is associated.
4. a kind of assembled architecture allocation of the labour force method based on BIM according to claim 1, it is characterised in that institute The step 1 stated) specifically include following steps:
11) positioning chip is set in the on-site personnel safety cap of assembled architecture labour's operation field;
12) multiple positioning websites are arranged around assembled architecture, the signal that positioning website is launched is covered building Each corner;
13) by positioning the data cube computation of website and positioning chip in safety cap, the position of whole on-site personnels is obtained.
5. a kind of assembled architecture allocation of the labour force method based on BIM according to claim 1, it is characterised in that institute The step 11 stated) in, multiple positioning websites position the position of on-site personnel by WIFI.
6. a kind of assembled architecture allocation of the labour force method based on BIM according to claim 1, it is characterised in that institute The step 6 stated) in, judge the threshold value of labour intensive region and manpower shortage for 3m per capita2
CN201710145144.XA 2017-03-13 2017-03-13 A kind of assembled architecture allocation of the labour force method based on BIM Pending CN107067160A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710145144.XA CN107067160A (en) 2017-03-13 2017-03-13 A kind of assembled architecture allocation of the labour force method based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710145144.XA CN107067160A (en) 2017-03-13 2017-03-13 A kind of assembled architecture allocation of the labour force method based on BIM

Publications (1)

Publication Number Publication Date
CN107067160A true CN107067160A (en) 2017-08-18

Family

ID=59621973

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710145144.XA Pending CN107067160A (en) 2017-03-13 2017-03-13 A kind of assembled architecture allocation of the labour force method based on BIM

Country Status (1)

Country Link
CN (1) CN107067160A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111915152A (en) * 2020-07-10 2020-11-10 中铁第四勘察设计院集团有限公司 Task allocation method and system applied to intelligent contact network construction site
CN114997739A (en) * 2022-07-18 2022-09-02 深圳市奇果物联科技有限公司 Electronic student identity card information management system and method based on Internet of things

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104329120A (en) * 2014-10-17 2015-02-04 成都四为电子信息股份有限公司 Tunnel construction safety monitoring and management system and tunnel construction safety monitoring and management method
CN104599063A (en) * 2015-01-16 2015-05-06 苏州彼慕建筑设计咨询有限公司 Paperless digital building system
CN104680318A (en) * 2015-02-13 2015-06-03 上海同筑信息科技有限公司 BIM-based engineering personnel control system and method
CN104965964A (en) * 2015-08-06 2015-10-07 山东建筑大学 Building personnel distribution model establishment method based on surveillance video analysis
CN106127412A (en) * 2016-07-05 2016-11-16 重庆交通大学 A kind of engineering quality supervision and management method and device
CN106228208A (en) * 2016-07-21 2016-12-14 重庆工程职业技术学院 Control system based on BIM and method
CN106295745A (en) * 2016-08-11 2017-01-04 广联达科技股份有限公司 Location scan method and device, information processor and communication system
CN106296473A (en) * 2015-05-28 2017-01-04 上海宝冶集团有限公司 A kind of construction project progress real-time control method based on BIM technology

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104329120A (en) * 2014-10-17 2015-02-04 成都四为电子信息股份有限公司 Tunnel construction safety monitoring and management system and tunnel construction safety monitoring and management method
CN104599063A (en) * 2015-01-16 2015-05-06 苏州彼慕建筑设计咨询有限公司 Paperless digital building system
CN104680318A (en) * 2015-02-13 2015-06-03 上海同筑信息科技有限公司 BIM-based engineering personnel control system and method
CN106296473A (en) * 2015-05-28 2017-01-04 上海宝冶集团有限公司 A kind of construction project progress real-time control method based on BIM technology
CN104965964A (en) * 2015-08-06 2015-10-07 山东建筑大学 Building personnel distribution model establishment method based on surveillance video analysis
CN106127412A (en) * 2016-07-05 2016-11-16 重庆交通大学 A kind of engineering quality supervision and management method and device
CN106228208A (en) * 2016-07-21 2016-12-14 重庆工程职业技术学院 Control system based on BIM and method
CN106295745A (en) * 2016-08-11 2017-01-04 广联达科技股份有限公司 Location scan method and device, information processor and communication system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111915152A (en) * 2020-07-10 2020-11-10 中铁第四勘察设计院集团有限公司 Task allocation method and system applied to intelligent contact network construction site
CN111915152B (en) * 2020-07-10 2022-10-18 中铁第四勘察设计院集团有限公司 Task allocation method and system applied to intelligent contact network construction site
CN114997739A (en) * 2022-07-18 2022-09-02 深圳市奇果物联科技有限公司 Electronic student identity card information management system and method based on Internet of things
CN114997739B (en) * 2022-07-18 2022-10-28 深圳市奇果物联科技有限公司 Electronic student identity card information management system and method based on Internet of things

Similar Documents

Publication Publication Date Title
CN105554976B (en) Outdoor work field lighting analogy method based on BIM technology
CN105888248B (en) A kind of construction method based on BIM technology tutorial message prefabricated components
CN104680318A (en) BIM-based engineering personnel control system and method
CN107256005A (en) A kind of reinforcing steel bar numerical control processing method and equipment based on BIM technology
CN106910009A (en) Construction manpower management system based on BIM technology and its method for manpower management of constructing
CN107993000A (en) The method of construction main flat face dynamic coordinate management based on BIM
CN107067160A (en) A kind of assembled architecture allocation of the labour force method based on BIM
CN110528881A (en) A kind of quick turnover method of assembled architecture support system based on BIM
CN110978204A (en) BIM-based intelligent concrete pouring method and related product
CN109255145B (en) BIM-based three-dimensional scene steel truss bridge simulation construction method
CN112907389A (en) Land, air and space integrated intelligent construction site system and management method
CN106897453A (en) Engineering BIM progresses model and on-site supervision control methods
CN104809663A (en) Power professional technique service assurance surveillance system and method
CN115439099A (en) Construction project cooperative supervision system based on BIM model
CN107248045A (en) A kind of intelligent management, apparatus and system evaluated and conserve active service bridge
CN109356018A (en) A kind of steel-structure box girder analogy method
CN104484751A (en) Dynamic optimization method and device for production planning and resource allocation
CN103628483B (en) The concrete dam pouring mechanically combining that puts in storage builds simulation and optimum method
CN109598085A (en) One kind being based on artificial intelligence construction project time management method
CN210072621U (en) BIM management-based deepened transformation system for vehicle section with ultra-large cover body
CN108876082A (en) A kind of construction site emergency management and rescue management system and method based on BIM
CN105421298B (en) The gate control method shown based on multi-screen
CN109162459A (en) A kind of big section rings beam construction method of hyperbolic bonded prestress
CN105261253B (en) A kind of universal heat power plant simulation training automatic scoring evaluation system and method
CN111126691B (en) Project management method and related products

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170818

RJ01 Rejection of invention patent application after publication