CN106296473A - A kind of construction project progress real-time control method based on BIM technology - Google Patents
A kind of construction project progress real-time control method based on BIM technology Download PDFInfo
- Publication number
- CN106296473A CN106296473A CN201510279327.1A CN201510279327A CN106296473A CN 106296473 A CN106296473 A CN 106296473A CN 201510279327 A CN201510279327 A CN 201510279327A CN 106296473 A CN106296473 A CN 106296473A
- Authority
- CN
- China
- Prior art keywords
- model
- progress
- bim
- control method
- level
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention relates to project schedule control method.A kind of construction project progress real-time control method based on BIM technology, comprises the following steps: step one, collects BIM model information and progress msg, corresponding relation correct between establishing model and operation;Step 2, input BIM model information and progress msg, carry out linking and arranging relevant parameter with the operation in progress by the BIM model component having had determined that corresponding relation;Step 3, is added as needed on out of Memory;Step 4, exports 4D model, forms benchmark 4D model file after confirmation;Step 5, collect actual progress data and update the progress status in 4D model, the 4D model file of output reference and actual contrast is also sent to related personnel and discusses and analyze, and updates 4D model file according to feedback opinion and be again sent to related personnel and confirm after receiving related personnel's feedback.The present invention can intuitively show project progress, facilitates the exchange of each specialty, in order to realizes the real-time control of project.
Description
Technical field
The present invention relates to project schedule control method, particularly relate to construction project progress real-time control method.
Background technology
In existing project schedule control method, engineering staff is usually and carrys out monitoring site progress by the mode of gunter drawing by collecting real data.This method compare planarization and the most directly perceived, and each participant of project is not necessarily all professional person, a lot of project participants are difficult to quickly understand the development situation that gunter drawing shows, the degree of understanding of gunter drawing is also joined secondary uneven by everyone, this can affect the communication and discussion between each participant of project, particularly when on-the-spot each specialty is staggered frequently, place spatial alternation complexity time, everybody is difficult to therefrom obtain precisely consistent information.Thus have influence on the progress of engineering.
Summary of the invention
It is contemplated that overcome the defect of prior art, it is provided that a kind of construction project progress real-time control method based on BIM technology.The present invention can intuitively show project progress, facilitates the exchange of each specialty, in order to realizes the real-time control of project.
In order to solve above-mentioned technical problem, a kind of construction project progress real-time control method based on BIM technology, it comprises the following steps:
Step one, collects BIM model information and progress msg, corresponding relation correct between establishing model and operation;A described corresponding relation that is operation is according to the corresponding one or more BIM model components of the content described by its title;If the level of detail LOD of model component is higher than the level of detail of operation in progress, then extract corresponding model according to the level of detail of operation in progress;If the level of detail LOD of model component is lower than the level of detail of operation in progress, then determines the level of detail of operation in progress according to the level of detail of model component and extract the model that operation is corresponding;
Step 2, input BIM model information and progress msg, carry out linking and arranging relevant parameter with the operation in progress by the BIM model component having had determined that corresponding relation;.
Step 3, is added as needed on out of Memory such as cost, manual resource, unartificial resource, material resources, explanation;
Step 4, exports 4D model, forms benchmark 4D model file after confirmation;
Step 5, collect actual progress data and update the progress status in 4D model, the 4D model file of output reference and actual contrast is also sent to related personnel and discusses and analyze, and updates 4D model file according to feedback opinion and be again sent to related personnel and confirm after receiving related personnel's feedback.
Described a kind of based on BIM technology construction project progress real-time control method, the display mode when relevant parameter described in step 2 refers to model countershaft moves at any time, the filter of path, custom field, model and operation of machinery, resource tree, animation.
Described a kind of based on BIM technology construction project progress real-time control method, the 4D model file of described step 4 kind output is video file and relevant chart and explanatory note adnexa;Described correlation graph and explanatory note include but not limited to that schedule diagram, resource use table, building block plan, model and projected conditions describe.
Described a kind of based on BIM technology construction project progress real-time control method, the progress data in described step 5 refers to as the actual time started of industry, Percent Complete, actual finish time, the impacted factor of operation;The benchmark of described output and the 4D model file of actual contrast are video file and relevant chart and explanatory note adnexa;Video has the view of benchmark 4D model and actual 4D model simultaneously, and contains other view simultaneously and include but not limited to job title display view, models show explanation view, date view, remarks view.
The present invention is complicated in structure, specialty is intersected many, place converts and uses during project construction frequently, 4D model is formed by the combination of model with plan, and the 4D model of plan and actual contrast is formed by collecting real data, intricate plan information is made to become visualization, understandable, relative to conventional way, 4D high efficiency in progress control can be embodied, it is easy to each participant of project mutually exchange and call for Votes, also allow for identifying the risk in following construction, work efficiency is improved in construction process, propelling progress, reduce risk aspect to play a significant role.
Detailed description of the invention
A kind of construction project progress real-time control method based on BIM technology of the present invention, it includes:
1) BIM model information and progress msg, corresponding relation correct between establishing model and operation are collected;A described corresponding relation that is operation is according to the corresponding one or more BIM model components of the content described by its title;If the level of detail of model component (LOD) is higher than the level of detail of operation in progress, then extract corresponding model according to the level of detail of operation in progress;If the level of detail of model component (LOD) is lower than the level of detail of operation in progress, then determines the level of detail of operation in progress according to the level of detail of model component and extract the model that operation is corresponding.
2) input BIM model information and progress msg, carry out linking and arranging relevant parameter with the operation in progress by the BIM model component having had determined that corresponding relation;Display mode (growth pattern of model, color, transparency etc.) when described relevant parameter refers to model countershaft moves at any time, the filter of path, custom field, model and operation of machinery, resource tree, animation etc..
3) out of Memory such as cost, manual resource, unartificial resource, material resources, explanation etc. it are added as needed on;
4) output 4D model, forms benchmark 4D model file after confirmation;The 4D model file of described output is video file and relevant chart and explanatory note adnexa;Described correlation graph and explanatory note include but not limited to that schedule diagram, resource use table, building block plan, model and projected conditions describe.
5) collect actual progress data and update the progress status in 4D model, the 4D model file of output reference and actual contrast is also sent to related personnel and discusses and analyze, and updates 4D model file according to feedback opinion and be again sent to related personnel and confirm after receiving related personnel's feedback;Described progress data refers to as the actual time started of industry, Percent Complete, actual finish time, the impacted factor of operation etc.;The benchmark of described output and the 4D model file of actual contrast are video file and relevant chart and explanatory note adnexa;Video has the view of benchmark 4D model and actual 4D model simultaneously, and contains other view simultaneously and include but not limited to job title display view, models show explanation view, date view, remarks view.
The present invention is that each professional provides a good intercommunion platform, improves work efficiency, reduces the risk of the project implementation.
Claims (4)
1. a construction project progress real-time control method based on BIM technology, it is characterised in that it comprises the following steps:
Step one, collects BIM model information and progress msg, corresponding relation correct between establishing model and operation;A described corresponding relation that is operation is according to the corresponding one or more BIM model components of the content described by its title;If the level of detail LOD of model component is higher than the level of detail of operation in progress, then extract corresponding model according to the level of detail of operation in progress;If the level of detail LOD of model component is lower than the level of detail of operation in progress, then determines the level of detail of operation in progress according to the level of detail of model component and extract the model that operation is corresponding;
Step 2, input BIM model information and progress msg, carry out linking and arranging relevant parameter with the operation in progress by the BIM model component having had determined that corresponding relation;.
Step 3, is added as needed on out of Memory and includes cost, manual resource, unartificial resource, material resources, explanation;
Step 4, exports 4D model, forms benchmark 4D model file after confirmation;
Step 5, collect actual progress data and update the progress status in 4D model, the 4D model file of output reference and actual contrast is also sent to related personnel and discusses and analyze, and updates 4D model file according to feedback opinion and be again sent to related personnel and confirm after receiving related personnel's feedback.
A kind of construction project progress real-time control method based on BIM technology the most according to claim 1, it is characterized in that, the display mode when relevant parameter described in step 2 refers to model countershaft moves at any time, the filter of path, custom field, model and operation of machinery, resource tree, animation.
A kind of construction project progress real-time control method based on BIM technology the most according to claim 1, it is characterised in that the 4D model file of described step 4 kind output is video file and relevant chart and explanatory note adnexa;Described correlation graph and explanatory note include but not limited to that schedule diagram, resource use table, building block plan, model and projected conditions describe.
A kind of construction project progress real-time control method based on BIM technology the most according to claim 1, it is characterised in that the progress data in described step 5 refers to as the actual time started of industry, Percent Complete, actual finish time, the impacted factor of operation;The benchmark of described output and the 4D model file of actual contrast are video file and relevant chart and explanatory note adnexa;Video has the view of benchmark 4D model and actual 4D model simultaneously, and contains other view simultaneously and include but not limited to job title display view, models show explanation view, date view, remarks view.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510279327.1A CN106296473A (en) | 2015-05-28 | 2015-05-28 | A kind of construction project progress real-time control method based on BIM technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510279327.1A CN106296473A (en) | 2015-05-28 | 2015-05-28 | A kind of construction project progress real-time control method based on BIM technology |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106296473A true CN106296473A (en) | 2017-01-04 |
Family
ID=57634833
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510279327.1A Pending CN106296473A (en) | 2015-05-28 | 2015-05-28 | A kind of construction project progress real-time control method based on BIM technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106296473A (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106384200A (en) * | 2016-09-27 | 2017-02-08 | 朱海涛 | BIM (Building Information Modeling) technology-based management and application method of construction multidimensional model |
CN106897453A (en) * | 2017-03-08 | 2017-06-27 | 朱海涛 | Engineering BIM progresses model and on-site supervision control methods |
CN106910009A (en) * | 2017-01-24 | 2017-06-30 | 广西建工集团第五建筑工程有限责任公司 | Construction manpower management system based on BIM technology and its method for manpower management of constructing |
CN107067160A (en) * | 2017-03-13 | 2017-08-18 | 同济大学 | A kind of assembled architecture allocation of the labour force method based on BIM |
CN107516161A (en) * | 2017-08-03 | 2017-12-26 | 中国建筑第五工程局有限公司 | A kind of project progress management-control method based on BIM |
CN107705100A (en) * | 2017-11-02 | 2018-02-16 | 港珠澳大桥管理局 | A kind of management system of Traffic Engineering Construction progress |
CN108596423A (en) * | 2018-03-02 | 2018-09-28 | 重庆机电装备技术研究院有限公司 | A kind of trackways engineering construction progress msg management method based on BIM |
CN109472539A (en) * | 2017-09-07 | 2019-03-15 | 上海嘉实(集团)有限公司 | Progress control method, system, device and the storage medium of live project |
CN109583772A (en) * | 2018-12-04 | 2019-04-05 | 上海宝冶集团有限公司 | Method for managing and monitoring, device, system and the readable storage medium storing program for executing of construction site |
CN110119774A (en) * | 2019-05-08 | 2019-08-13 | 中铁八局集团建筑工程有限公司 | A kind of contrast difference's method based on Building Information Model 4D progress Yu outdoor scene progress |
CN111160838A (en) * | 2018-11-07 | 2020-05-15 | 苏州微缔软件股份有限公司 | 3D visualization building project management system and method based on BIM technology |
CN112446937A (en) * | 2020-11-10 | 2021-03-05 | 上海宝冶集团有限公司 | Project progress three-dimensional visualization method based on BIM technology |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103440600A (en) * | 2013-09-13 | 2013-12-11 | 成都中铁隆工程集团有限公司 | BIM (Building Information Modeling) risk monitoring system and method of multilayer 4D (4-Dimensional) model |
CN103455878A (en) * | 2013-08-28 | 2013-12-18 | 哈尔滨工业大学 | Method and device for construction progress network diagram real-time adjustment based on internet of things technology |
US20130335413A1 (en) * | 2012-06-13 | 2013-12-19 | National Chiao Tung University | System and method for estimating construction duration |
CN103500371A (en) * | 2013-08-08 | 2014-01-08 | 机械工业第六设计研究院有限公司 | Change control method based on BIM |
-
2015
- 2015-05-28 CN CN201510279327.1A patent/CN106296473A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20130335413A1 (en) * | 2012-06-13 | 2013-12-19 | National Chiao Tung University | System and method for estimating construction duration |
CN103500371A (en) * | 2013-08-08 | 2014-01-08 | 机械工业第六设计研究院有限公司 | Change control method based on BIM |
CN103455878A (en) * | 2013-08-28 | 2013-12-18 | 哈尔滨工业大学 | Method and device for construction progress network diagram real-time adjustment based on internet of things technology |
CN103440600A (en) * | 2013-09-13 | 2013-12-11 | 成都中铁隆工程集团有限公司 | BIM (Building Information Modeling) risk monitoring system and method of multilayer 4D (4-Dimensional) model |
Non-Patent Citations (3)
Title |
---|
丁烈云等主编: "《BIM应用•施工》", 31 March 2015, 上海:同济大学出版社 * |
王婷 等: "BIM技术在4D施工进度模拟的应用探讨", 《图文学报》 * |
王雪青 等: "基于BIM实时施工模型的4D模拟", 《广西大学学报自然科学版》 * |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106384200A (en) * | 2016-09-27 | 2017-02-08 | 朱海涛 | BIM (Building Information Modeling) technology-based management and application method of construction multidimensional model |
CN106910009A (en) * | 2017-01-24 | 2017-06-30 | 广西建工集团第五建筑工程有限责任公司 | Construction manpower management system based on BIM technology and its method for manpower management of constructing |
CN106897453A (en) * | 2017-03-08 | 2017-06-27 | 朱海涛 | Engineering BIM progresses model and on-site supervision control methods |
CN107067160A (en) * | 2017-03-13 | 2017-08-18 | 同济大学 | A kind of assembled architecture allocation of the labour force method based on BIM |
CN107516161A (en) * | 2017-08-03 | 2017-12-26 | 中国建筑第五工程局有限公司 | A kind of project progress management-control method based on BIM |
CN109472539A (en) * | 2017-09-07 | 2019-03-15 | 上海嘉实(集团)有限公司 | Progress control method, system, device and the storage medium of live project |
CN107705100B (en) * | 2017-11-02 | 2022-04-26 | 港珠澳大桥管理局 | Management system for traffic engineering construction progress |
CN107705100A (en) * | 2017-11-02 | 2018-02-16 | 港珠澳大桥管理局 | A kind of management system of Traffic Engineering Construction progress |
CN108596423A (en) * | 2018-03-02 | 2018-09-28 | 重庆机电装备技术研究院有限公司 | A kind of trackways engineering construction progress msg management method based on BIM |
CN111160838A (en) * | 2018-11-07 | 2020-05-15 | 苏州微缔软件股份有限公司 | 3D visualization building project management system and method based on BIM technology |
CN109583772A (en) * | 2018-12-04 | 2019-04-05 | 上海宝冶集团有限公司 | Method for managing and monitoring, device, system and the readable storage medium storing program for executing of construction site |
CN110119774A (en) * | 2019-05-08 | 2019-08-13 | 中铁八局集团建筑工程有限公司 | A kind of contrast difference's method based on Building Information Model 4D progress Yu outdoor scene progress |
CN112446937A (en) * | 2020-11-10 | 2021-03-05 | 上海宝冶集团有限公司 | Project progress three-dimensional visualization method based on BIM technology |
CN112446937B (en) * | 2020-11-10 | 2023-07-14 | 上海宝冶集团有限公司 | Project progress three-dimensional visualization method based on BIM technology |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106296473A (en) | A kind of construction project progress real-time control method based on BIM technology | |
US20130335413A1 (en) | System and method for estimating construction duration | |
CN111861358A (en) | Building information integration platform based on BIM technology | |
CN107516161A (en) | A kind of project progress management-control method based on BIM | |
CN110008648A (en) | A kind of wisdom building site Integration Data Model method based on BIM model | |
CN109035060A (en) | A kind of structured processes management system and management method | |
CN104573254A (en) | Pre-construction technical disclosure method based on BIM | |
CN107993000A (en) | The method of construction main flat face dynamic coordinate management based on BIM | |
CN109034404B (en) | AR (augmented reality) -glasses-based multi-user cooperative maintenance system and method for thermal power plant and AR glasses | |
CN105388876B (en) | Obtain the method and device of the batch-type chemical production technology degree of conformity based on teams and groups | |
CN108596374A (en) | Construction schedule optimizes preparation method | |
KR101674101B1 (en) | Project management system based information and communication technology | |
CN108205735A (en) | A kind of workshop information physical monitoring management plateform system | |
CN111651818A (en) | BIM model rapid change method | |
CN107194112A (en) | The method being laid out based on BIM to garden landscape | |
CN111666619A (en) | BIM technology-based substation engineering implementation field digital management system | |
CN112307546A (en) | Decoration design method based on BIM | |
CN112307548A (en) | BIM-based rail transit construction visualization progress management method and system | |
CN115545664A (en) | Automated project management system and method based on WBS | |
DE102016105480A1 (en) | Method and system for installing, managing and / or maintaining components in a building complex | |
Fadoul et al. | Constructability assessment model for buildings design | |
KR20150096191A (en) | Project management system | |
TWM535357U (en) | Construction history monitoring management system guided by engineering planning | |
Tarar et al. | Impact of 4D modeling on construction planning process | |
CA2832806C (en) | Method for optimizing schedule compression in projects using accelerating and overlapping of activities |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170104 |
|
RJ01 | Rejection of invention patent application after publication |