TWM535357U - Construction history monitoring management system guided by engineering planning - Google Patents

Construction history monitoring management system guided by engineering planning Download PDF

Info

Publication number
TWM535357U
TWM535357U TW105214122U TW105214122U TWM535357U TW M535357 U TWM535357 U TW M535357U TW 105214122 U TW105214122 U TW 105214122U TW 105214122 U TW105214122 U TW 105214122U TW M535357 U TWM535357 U TW M535357U
Authority
TW
Taiwan
Prior art keywords
project
progress
construction
engineering
management system
Prior art date
Application number
TW105214122U
Other languages
Chinese (zh)
Inventor
zhi-xin Wu
Original Assignee
Giei Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Giei Engineering Co Ltd filed Critical Giei Engineering Co Ltd
Priority to TW105214122U priority Critical patent/TWM535357U/en
Publication of TWM535357U publication Critical patent/TWM535357U/en

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)

Description

經由工程企劃引導的施工履歷監控管理系統 Construction history monitoring and management system guided by engineering planning

本創作係有關一種經由工程企劃引導的施工履歷監控管理系統,尤其是一種與營造機電配管線工程施作及工程管控技術有關,特別是建立程式化工程作業自動引導技術者。 This creation is related to a construction history monitoring and management system guided by engineering planning, especially related to the construction of electromechanical distribution pipeline engineering and engineering management and control technology, especially the establishment of automatic guidance technology for stylized engineering operations.

按,現今營造機電配管線工程業在無法自動化下人力為完成工程進度最重要環節之一,也是工程專案成敗最大變數。先前技術其施做程序為依業主端原設計圖面需求發包,再由承攬商乙方發展施工圖後,再發包至再承攬商丙方後投入人力執行或再發包至丁方執行現場配管線作業,由於工程代工業為人力密集產業,其成本以人力支出為大宗、因此管控施工人員之效率、產能即為本行業經營成敗之關鍵,依過去本行業之派工模式,為取得承攬契約後按承攬金額及依據業主工程專案表定完工時間,再按乙方提供之施工設計圖面及規劃與工進時程再配合土建進度調派人力施做,但工程進行中涉及相當多工程界面與工序配合,其人力支出(成本)會因業主設計變更、乙方物料 供給、施工圖面不明確、土建施工延遲、現場施作障礙所產生的協調、溝通程序等等因素,造成人力怠工成本之損耗,進而造成工程專案虧損,最後增加經營之風險。而各項工程作業中,如電氣工程中的配電盤控制箱的製作,機械電機工程的製造,各種機械設備安裝工程,營建工程中的給排水工程、中水工程、消防工程、配電工程、空調工程及各種設備裝修工程、都存在下列問題: According to the current construction of the electromechanical distribution pipeline engineering industry, it is one of the most important steps in the progress of the project, and it is also the biggest variable of the success or failure of the engineering project. In the prior art, the application procedure was based on the original design drawings of the owner, and then the contractor B developed the construction drawing, and then sent the package to the contractor C, and then put it into the manpower execution or re-issued the package to Dingfang to perform on-site pipeline operation. As the engineering industry is a manpower-intensive industry, its cost is based on manpower expenditure. Therefore, the efficiency and capacity of the construction and control personnel are the key to the success of the industry. According to the dispatch mode of the industry in the past, The amount of the contract and the completion time according to the owner's project plan, and then according to the construction design drawings and planning and work schedule provided by Party B, and the man-made construction schedule, and the project involves a considerable number of engineering interfaces and processes. Manpower expenditure (cost) will be changed due to the owner's design, Party B materials Factors such as unclear supply and construction drawings, delays in construction of civil works, coordination and communication procedures caused by obstacles on the site, etc., result in the loss of manpower completion costs, which in turn leads to loss of engineering projects and ultimately increases the risk of operation. In various engineering operations, such as the production of switchboard control boxes in electrical engineering, the manufacture of mechanical and electrical engineering, various mechanical equipment installation projects, water supply and drainage projects, water projects, fire engineering, power distribution engineering, air conditioning projects in construction projects and The following problems exist in various equipment renovation projects:

一、非計畫性施工因在執行設計圖說時並沒有計劃性進行施工前工程圖說與規範的施作分析確認,因此每個施作人員在無法了解工序執行及作業內容下施作產生錯誤所造成工時損耗。 1. The non-planned construction is confirmed by the analysis of the engineering drawings and specifications before the execution of the design drawings. Therefore, each of the implementers is not able to understand the execution of the procedures and the contents of the operations. Causes working hours loss.

二、因甲乙方管理人員指揮調度不當未按工程優先順序投入人力導致重覆施做的工時損耗。 Second, due to the improper command and dispatch of the management personnel of Party A and Party B, the manpower loss caused by repeated input of manpower according to the priority of the project resulted in repeated work.

三、人力需求之不確定性導至人力調度投入困難。 Third, the uncertainty of manpower demand leads to difficulties in manpower scheduling.

四、因乙方施工圖面供給不及的工時損耗。 4. The working hours lost due to the supply of Party B's construction drawings.

五、因乙方物料供給不及產生的工時損耗。 5. Working hours loss due to the inability of Party B's material supply.

六、因管理人員不足致使施工人員怠惰所產生的工時損耗。 6. The loss of working hours caused by the laziness of construction workers due to insufficient management personnel.

七、因管理人員查核不足致使施工人員掩飾施工不良造成查驗缺失重新施做所產生之工時損耗。 VII. Due to the lack of inspection by the management personnel, the construction personnel conceal the poor construction, resulting in the loss of working hours caused by the lack of inspection and re-applied.

八、無法有效掌握施工人員之出勤、虛報施工人員出勤 及虛報工程進度所產生的成本損耗。 8. It is impossible to effectively grasp the attendance of construction workers and falsely report the attendance of construction workers. And falsely report the cost loss caused by the progress of the project.

九、無法掌握工程高峰期之人員調度。 Nine, unable to grasp the personnel scheduling during the peak period of the project.

十、因管理不足無法量化掌控施工人員之效率、產能致使施工人員產能不佳,工程進度延宕,最後須以提高人力趕工補其工程進度所增加之人力成本。 X. Due to insufficient management, it is impossible to quantify the efficiency of the construction personnel, and the production capacity causes the construction workers to have poor productivity. The progress of the project is delayed. Finally, the manpower cost of manpower to make up the progress of the project must be increased.

十一、因甲乙方管理人員之不做為如圖面澄清、物料供給、障礙排除等等所產生怠工的工時損耗。 XI. Due to the failure of the management personnel of Party A and Party B as the clarification of the drawings, the supply of materials, the elimination of obstacles, etc., the lost working hours are completed.

十二、因施工人員偷工減料所造成重覆施做的工時損耗。 12. Working hours lost due to heavy work caused by construction workers cutting corners.

十三、因設計變更資訊遲緩導致重覆施做的工時損耗。 XIII. Loss of working hours due to delays in design changes due to delays in design changes.

十四、因甲乙方管理人員指示錯誤導致重覆施做的工時損耗。 14. The working hours lost due to repeated errors caused by the instructions of the management personnel of Party A and Party B.

是以,針對上述先前技術所存在之問題,如何開發一種更有效進行查核工程人力派遣、施工效率及產能之實用創作,實使用者所殷切企盼,亦係相關業者須努力研發突破之目標及方向。 Therefore, in view of the problems existing in the above prior art, how to develop a practical design for more effective manpower dispatching, construction efficiency and production capacity of the auditing project, the users are eagerly awaiting, and the relevant operators must strive to develop breakthrough goals and directions. .

創作人針對上述先前技術之問題,本創作主要目的係提供一種經由工程企劃引導的施工履歷監控管理系統,以預防施作錯誤所造成工時損耗,人力調度投入困難,施工圖面及物料供給不及,施工人員怠惰及查驗缺失重新施做的工時損耗,虛報施工人員出勤及虛報工程進度所產 生的成本損耗,工程高峰期之人員調度困難,施工人員產能不佳、工程進度延宕所增加之人力成本,管理人員之不做為所產生怠工的工時損耗,施工人員偷工減料及設計變更資訊遲緩導致重覆施做的工時損耗,管理人員指示錯誤導致重覆施做的工時損耗等問題;而其解決問題之技術特徵,係為: The creator is aiming at the above-mentioned problems of the prior art. The main purpose of this creation is to provide a construction history monitoring and management system guided by engineering planning to prevent the loss of working hours caused by misapplication, the difficulty of manpower scheduling, and the lack of construction drawings and materials. The construction workers are lazy and check the lost work hours, and the construction workers’ attendance and false report on the progress of the project The cost of production is lost, the personnel dispatching during the peak period of the project is difficult, the labor capacity of the construction personnel is not good, and the labor cost of the project is delayed. The management personnel do not use the lost working hours, and the construction workers cut the materials and design changes. The problem of man-hour loss caused by repeated application, the manager's indication of the error caused by repeated failures, and the technical characteristics of solving the problem are:

一、藉由用戶終端裝置以網際網路連結管控中心伺服器執行人力派工系統,整合當日出勤記錄提供即時、可用人員名單以進行迅速、高效率之人力調度解決虛報施工人員出勤及虛報工程進度所產生的成本損耗。 1. The user terminal device uses the Internet connection control center server to execute the manpower dispatching system, integrates the time and record records to provide a list of instant and available personnel for quick and efficient manpower dispatch to solve the false report of the construction workers' attendance and false report progress. The resulting cost loss.

二、藉由工作進度瀏覽系統提供透明施工資訊包含:施工圖面、工作項目及主要物料表以進行即時充分的物料及正確之施工圖供給,有效工程進度監控避免施作錯誤及停工待料所造成工時損耗。 2. Provide transparent construction information through the work progress browsing system: construction drawings, work items and main material tables for immediate and sufficient materials and correct construction drawings, effective project progress monitoring to avoid misuse and stoppage Causes working hours loss.

三、藉由工作進度瀏覽系統提供狀況回報以解決因設計變更、施作錯誤的工時損耗。 Third, through the work progress browsing system to provide status returns to solve the work loss due to design changes, implementation errors.

四、藉由人力派工系統提供預先派工以提供工作人員預覽施工圖面及準備主要物料以避免施工圖面及物料供給不及之缺失。 4. Providing pre-delivery by the manpower dispatching system to provide staff to preview the construction drawings and prepare the main materials to avoid the lack of construction drawings and material supply.

五、藉由人力派工系統提供當日派工以提供改派、問題回報以解決人員缺勤及工程高峰期之人員調度困難之缺失。 5. Providing the dispatch of workers on the same day to provide reassignment and problem returns to solve the lack of personnel dispatching difficulties during the peak period of the project.

六、藉由驗收檢核及進度監控管理系統提供工程進度監控圖點選各工程區段即迅速、清楚顯示該工程之工程項目及各區段之主要物料數量避免施工及備料錯誤導致工時損耗。 6. Providing project progress monitoring chart by inspection and inspection and progress monitoring management system Clicking on each project section will quickly and clearly show the project's engineering project and the main material quantity of each section to avoid construction loss due to construction and stock errors. .

七、藉由驗收檢核及進度監控管理系統提供工程進度監控圖,建置完工照片,以顏色區分及完工照片顯示完工區段以解決施工人員偷工減料、怠惰及查驗缺失導致重新施做的工時損耗。 7. Providing project progress monitoring maps by inspection and inspection and progress monitoring management system, establishing completed photographs, coloring and finishing photographs showing completed sections to solve the man-hours of re-applying by construction workers for cutting corners, laziness and missing inspections loss.

八、藉由驗收檢核及進度監控管理系統分析工程進度以解決工程進度延宕所增加之人力成本及施工人員怠惰及查驗缺失重新施做的工時損耗。 8. Analyze the progress of the project by means of the inspection and inspection and progress monitoring management system to solve the increase in manpower costs and the laziness of the construction staff and the loss of man-hours for the re-applied work.

藉此創新獨特設計,使本創作對照先前技術而言,大致可達到如下功效:由於本創作經由工程企劃引導的施工履歷監控管理系統,藉由用戶終端裝置連結網際網路系統執行人力派工系統,整合當日出勤記錄提供即時、可用人員名單以進行迅速、高效率之人力調度解決虛報施工人員出勤及虛報工程進度所產生的成本損耗;藉由工作進度瀏覽系統提供透明施工資訊包含:施工圖面、工作項目及主要物料表以進行即時充分的物料及正確之施工圖供給,有效工程進度監控避免施作錯誤及停工待料所造成工時損耗;藉由工作進度瀏覽系統提供狀況回報以解決因設計變更、施作 錯誤的工時損耗;藉由人力派工系統提供預先派工以提供工人預覽施工圖面及準備主要物料以避免施工圖面及物料供給不及之缺失;藉由人力派工系統提供當日派工以提供改派、問題回報以解決人員缺勤及工程高峰期之人員調度困難之缺失;藉由驗收檢核及進度監控管理系統提供工程進度監控圖點選各工程區段即迅速、清楚顯示該工程之項目及各區段之主要物料數量避免施工及備料錯誤導致工時損耗;藉由驗收檢核及進度監控管理系統提供工程進度監控圖,建置完工照片,以顏色區分及完工照片顯示完工區段以解決施工人員偷工減料、怠惰及查驗缺失導致重新施做的工時損耗。藉由驗收檢核及進度監控管理系統分析工程進度以解決工程進度延宕所增加之人力成本及施工人員怠惰及查驗缺失重新施做的工時損耗之實用進步性功效。 With this innovative and unique design, this creation can achieve the following effects in comparison with the prior art: since the creation is based on the construction history monitoring management system guided by the engineering planning, the user terminal device is connected to the Internet system to execute the manual dispatching system. Integrate when the Sunrise Record provides a list of immediate and available personnel for rapid and efficient manpower dispatch to solve the cost loss caused by false reporting of construction personnel attendance and false reporting of the project progress; transparent construction information provided by the work progress browsing system includes: construction drawing , work items and main material tables for immediate and sufficient materials and correct construction drawings, effective project progress monitoring to avoid misuse and stoppages caused by work stoppages; work progress browsing system to provide status returns to solve the problem Design change, implementation Wrong working hours loss; provide pre-delivery by the manpower dispatching system to provide workers with a preview of the construction drawings and prepare the main materials to avoid the lack of construction drawings and material supply; provide the same day dispatch by the manpower dispatch system Provide reassignment, problem return to solve the lack of staff scheduling difficulties during the peak period of the project; provide the progress monitoring chart by the inspection and inspection and progress monitoring management system. Select each project section to quickly and clearly display the project. The number of major materials in the project and each section avoids the loss of working hours caused by construction and stock errors; the project progress monitoring chart is provided by the inspection and inspection and progress monitoring management system, the completed photo is constructed, and the finished section is displayed by color and completed photo. In order to solve the man-hour loss caused by the construction workers to cut corners, slack and check the lack of work. The progress of the project is analyzed by the inspection and inspection and progress monitoring management system to solve the increase in labor costs and the laziness of the construction staff and the practical and progressive effect of checking the lost work time.

1‧‧‧終端裝置 1‧‧‧ Terminal devices

2‧‧‧網際網路 2‧‧‧Internet

3‧‧‧管控中心伺服器 3‧‧‧Control Center Server

30‧‧‧施工履歷監控管理系統程式 30‧‧‧ Construction history monitoring management system program

31‧‧‧人力派工系統 31‧‧‧Manpower Distribution System

311‧‧‧上下班打卡系統 311‧‧‧Working and Punching System

3111‧‧‧QR CODE條碼打卡 3111‧‧‧QR CODE barcode punch

3112‧‧‧輸入ID打卡 3112‧‧‧Enter ID punch

312‧‧‧工作進度瀏覽系統 312‧‧‧Work progress browsing system

3121‧‧‧瀏覽預期人力 3121‧‧‧View expected manpower

3122‧‧‧預計工作天數 3122‧‧‧Expected working days

3123‧‧‧預計開始日期 3123‧‧‧Expected start date

3124‧‧‧實際人力 3124‧‧‧ Actual manpower

3125‧‧‧實際開始日期 3125‧‧‧ Actual start date

3126‧‧‧實際結束日期 3126‧‧‧ Actual end date

3127‧‧‧狀況回報 3127‧‧‧Return of status

313‧‧‧預先派工系統 313‧‧‧Pre-delivery system

3131‧‧‧預期人力 3131‧‧‧Expected manpower

3132‧‧‧預計工作天數 3132‧‧‧Expected working days

3133‧‧‧預計開始日期 3133‧‧‧Expected start date

3134‧‧‧實際人力 3134‧‧‧ Actual manpower

3135‧‧‧實際開始日期 3135‧‧‧ Actual start date

3136‧‧‧欲派名單 3136‧‧‧ want to send a list

313A‧‧‧開啟工作進度表 313A‧‧‧Open work schedule

313B‧‧‧選取日期後自動列出未完成的工作項目 313B‧‧‧Automatically list unfinished work items after date

313C‧‧‧點選派工項目自動列出可用工人名單 313C‧‧‧Selected work items automatically list the list of available workers

313D‧‧‧選取欲指派的工人 313D‧‧‧Select the workers to be assigned

313E‧‧‧確認後完成預先派工 313E‧‧‧After confirmation, complete pre-delivery

314‧‧‧當日派工系統 314‧‧‧Day delivery system

3141‧‧‧預期人力 3141‧‧‧Expected manpower

3142‧‧‧預計工作天數 3142‧‧‧Expected working days

3143‧‧‧預計開始日期 3143‧‧‧Expected start date

3144‧‧‧實際人力 3144‧‧‧ Actual manpower

3145‧‧‧實際開始日期 3145‧‧‧ Actual start date

3146‧‧‧欲派名單 3146‧‧‧ want to send a list

314A‧‧‧開啟工作進度表 314A‧‧‧Open work schedule

314B‧‧‧點選「工作項目」 314B‧‧‧Click on "Work Items"

a‧‧‧改派 A‧‧‧reassigned

a1‧‧‧自動列出要改派的工人名單 A1‧‧‧Automatically list the list of workers to be reassigned

a2‧‧‧選取要改派的工人 a2‧‧‧Select workers to be reassigned

a3‧‧‧確認後完成派工 A3‧‧‧After confirmation, complete delivery

b‧‧‧問題回報 B‧‧‧ Problem return

b1‧‧‧輸入問題描述及所需協助 B1‧‧‧ Enter the description of the problem and the assistance required

b2‧‧‧確認後完成回報 B2‧‧‧Complete return after confirmation

c‧‧‧完成回報 c‧‧‧Complete return

c1‧‧‧點選完成回報 C1‧‧‧Click to complete the return

c2‧‧‧確認後完成回報 C2‧‧‧Complete return after confirmation

32‧‧‧驗收檢核及進度監控管理系統 32‧‧‧ Acceptance check and progress monitoring management system

321‧‧‧工程進度監控圖 321‧‧‧Project progress monitoring chart

3211‧‧‧工程區段 3211‧‧‧Engineering section

32111‧‧‧工程項目 32111‧‧‧Project

32112‧‧‧主要物料表 32112‧‧‧Main material list

32113‧‧‧施工完成照片 32113‧‧‧ Construction completed photos

322‧‧‧工程進度 322‧‧‧Project progress

32a‧‧‧建置工程進度監控圖於雲端資料庫 32a‧‧‧ Construction project progress monitoring map in the cloud database

32b‧‧‧開啟工程進度監控圖為背景 32b‧‧‧Opening the project progress monitoring chart as background

32c‧‧‧畫出各工程區段的工程線段 32c‧‧‧Draw the engineering line segments of each engineering section

32d‧‧‧定義各工程區段的工程項目 32d‧‧‧Defining engineering projects for each project section

32e‧‧‧建置各工程區段的主要物料表 32e‧‧·Main material list for each project section

32f‧‧‧依實際完成之工程點選完成工程進度之區段後儲存 32f‧‧‧Save after the completion of the project according to the actual completion of the project

32g‧‧‧輸入區段物料剩餘數量 32g‧‧‧ Input section material remaining quantity

32h‧‧‧上傳完工工程照片 32h‧‧‧ Upload completed project photos

f 32i‧‧‧檢核進度達成率若100%則進行下一步驟,否則回到步驟 f 32i‧‧‧ If the completion rate of the check progress is 100%, proceed to the next step, otherwise return to the step

32j‧‧‧結束工程進度監控管理 32j‧‧‧End project progress monitoring management

4‧‧‧用戶 4‧‧‧Users

40‧‧‧雲端資料庫 40‧‧‧Cloud database

41‧‧‧管理者 41‧‧‧Manager

42 42’‧‧‧一般使用者 42 42’‧‧‧General users

50‧‧‧訊息主機 50‧‧‧Message Host

60‧‧‧分析主機 60‧‧‧Analysis host

第1圖:係本創作之實施例基本架構圖。 Figure 1: The basic architecture of the embodiment of the present creation.

第2圖:係本創作之人力派工系統圖。 Figure 2: This is the diagram of the manpower dispatch system of this creation.

第3圖:係本創作之上下班打卡系統圖。 Figure 3: This is the diagram of the punching system on the top of this creation.

第4圖:係本創作之工作進度瀏覽系統圖。 Figure 4: A diagram showing the progress of the work of this creation.

第5圖:係本創作之預先派工系統圖。 Figure 5: A diagram of the pre-delivery system of this creation.

第6圖:係本創作之當日派工系統圖。 Figure 6: The system map of the day of the creation of this creation.

第7圖:係本創作之驗收檢核及進度監控管理系統圖。 Figure 7: Diagram of the acceptance check and progress monitoring management system of this creation.

第7A圖:係本創作之工程進度監控圖 Figure 7A: The progress monitoring diagram of the project

第8圖:係本創作之預先派工流程圖。 Figure 8: The pre-delivery flow chart for this creation.

第9圖:係本創作之當日派工流程圖。 Figure 9: The flow chart of the day of the creation of this creation.

第10圖:係本創作之工程進度監控管理流程圖。 Figure 10: Flow chart of the project progress monitoring management of this creation.

請參閱第1圖所示,係本創作之實施例基本架構圖,惟此等實施例僅供說明之用,在專利申請上並不受此結構之限制。 Please refer to FIG. 1 for the basic architecture diagram of the embodiment of the present invention. However, these embodiments are for illustrative purposes only and are not limited by this structure.

茲為使能進一步瞭解本創作之架構及技術,謹配合圖式再予深入說明於後:請參閱第1圖,為本創作之實施例基本架構圖,本創作經由工程企劃引導的施工履歷監控管理系統,其主要係藉由終端裝置1以網際網路2與管控中心伺服器3進行連結,藉以進行查核工程人力派工、施工效率及產能之整合創新系統,其係包含:至少一用戶4,其係該施工履歷監控管理系統使用者,包含管理者41及一般使用者4242’;一管控中心伺服器3,其係包含施工履歷監控管理系統程式30、雲端資料庫40、訊息主機50及分析主機60,該雲端資料庫40包含工程圖及工程進度監控圖,該訊息主機係傳遞進度異常及會議訊息,該分析主機60係分析比對工程進度比率,該用戶4藉由終端裝置1(平板電腦、智慧型手機、個人電腦)以網際網路2與管控中心伺服器3進行連結執行施工履歷監控管理。 In order to further understand the structure and technology of this creation, we will further explain it in detail with the following diagram: Please refer to Figure 1 for the basic architecture diagram of the embodiment of the creation. The construction history monitoring guided by the project planning The management system is mainly connected to the control center server 3 by the terminal device 1 by the Internet device 2, thereby performing an integrated innovation system for checking the manpower dispatching, construction efficiency and productivity of the project, and the system includes: at least one user 4 The user is the user of the construction history monitoring management system, including the manager 41 and the general user 4242', and the control center server 3 includes the construction history monitoring management system program 30, the cloud database 40, the message host 50, and The host computer 60 is configured to include a drawing and a project progress monitoring map. The message host transmits a schedule abnormality and a conference message. The analysis host 60 analyzes the comparison progress rate, and the user 4 uses the terminal device 1 ( The tablet computer, the smart phone, and the personal computer are connected to the control center server 3 via the Internet 2 to perform construction history monitoring and management.

請參閱第2圖,為本創作之人力派工系統圖,本創作經由工程企劃引導的施工履歷監控管理系統,其中 之施工履歷監控管理系統程式30包含:一人力派工系統31,其係包含上下班打卡系統311、工作進度瀏覽系統312、預先派工系統313及當日派工系統314。 Please refer to Figure 2, which is the diagram of the manpower dispatching system of this creation. The construction history monitoring and management system guided by the project planning, The construction history monitoring management system program 30 includes a manpower dispatching system 31 including a commuting punching system 311, a work progress browsing system 312, a pre-delivery system 313, and a day dispatching system 314.

請參閱第3圖,為本創作之上下班打卡系統圖,該上下班打卡系統311藉由QR CODE條碼打卡3111或輸入ID打卡3112建立員工上班出勤記錄。 Please refer to FIG. 3 , which is a diagram of the above-mentioned work punching system. The commuting punching system 311 establishes an employee attendance record by QR CODE barcode punch 3111 or input ID punch 3112.

請參閱第4圖,為本創作之工作進度瀏覽系統圖,該工作進度瀏覽系統312藉由瀏覽預期人力3121、預計工作天數3122、預計開始日期3123、實際人力3124、實際開始日期3125、實際結束日期3126及狀況回報3127以監控工程進度。 Please refer to FIG. 4 , which is a work progress browsing system diagram of the present work. The work progress browsing system 312 ends by browsing the expected manpower 3121, the estimated working days 3122, the estimated start date 3123, the actual manpower 3124, the actual start date 3125, and the actual end. Date 3126 and status return 3127 to monitor the progress of the project.

請參閱第5圖,為本創作之預先派工系統圖,該預先派工系統313藉由預期人力3131、預計工作天數3132、預計開始日期3133、實際人力3134、實際開始日期3135及欲派名單3136以實施預先派工作業。 Please refer to FIG. 5, which is a pre-delivery system diagram of the creation. The pre-delivery system 313 is based on the expected manpower 3131, the estimated working days 3132, the estimated start date 3133, the actual manpower 3134, the actual starting date 3135, and the wish list. 3136 to implement pre-dispatch work.

請參閱第6圖,為本創作之當日派工系統圖,該當日派工系統314藉由預期人力3141、預計工作天數3142、預計開始日期3143、實際人力3144、實際開始日期3145及欲派名單3146以實施當日派工作業。 Please refer to Figure 6 for the day-to-day delivery system diagram of the creation. The day delivery system 314 is based on the expected manpower 3141, the estimated number of working days 3142, the estimated start date 3143, the actual manpower 3144, the actual start date 3145, and the list of desires. 3146 to implement the day of the work industry.

請參閱第7及7A圖,為本創作之驗收檢核及進度監控管理系統及工程進度監控圖,該驗收檢核及進度監控管理系統32係包含建置工程進度監控圖321、建置工程區段3211、建置工程項目32111、建置主要物料表32112、建置施工完成照片32113及分析工程進度322;其係依原始工程 圖建置一工程進度監控圖321於該雲端資料庫40(第1圖)中以顏色區分顯示完成區段及未完成區段,藉由終端裝置1讀取工程進度監控圖321作為背景畫面進行工程區段3211拆解並定義各工程區段3211工程項目32111,建置各工程區段3211的主要物料表32112,依實際完成之工程進度於工程進度監控圖321點選各工程區段3211(完成區段以不同顏色顯示)後儲存,並回報工程區段物料剩餘數量及上傳施工完成照片32113,依工程進度監控圖321顯示最新工程進度比率進行工程進度322分析。 Please refer to Figures 7 and 7A for the acceptance check and progress monitoring management system and project progress monitoring chart of the creation. The acceptance check and progress monitoring management system 32 includes the construction progress monitoring chart 321 and the construction project area. Section 3211, construction project 32111, construction of main material table 32112, construction completion photo 32113 and analysis project progress 322; Figure Build a project progress monitoring map 321 in the cloud database 40 (Fig. 1) to display the completed segment and the unfinished segment by color, and the terminal device 1 reads the project progress monitoring map 321 as a background image. The engineering section 3211 disassembles and defines the 3211 project 32111 of each engineering section, and builds the main material table 32112 of each engineering section 3211, and selects each engineering section 3211 according to the actual progress of the project in the project progress monitoring diagram 321 ( After the completion section is displayed in different colors, it will be stored, and the remaining quantity of materials in the engineering section will be returned and the construction completion photo 32113 will be uploaded. According to the progress monitoring diagram 321 shows the latest project progress ratio and the project progress 322 is analyzed.

請參第8圖,為本創作之預先派工流程圖,本創作經由工程企劃引導的施工履歷監控管理系統,其中該預先派工流程包含:A.開啟工作進度表313A;B.選取日期後自動列出未完成的工作項目313B;C.點選派工項目自動列出可用工人名單313C;D.選取欲指派的工人313D;E.確認後完成預先派工313E。 Please refer to Figure 8 for the pre-delivery flow chart of the creation. The creation of the construction history monitoring and management system guided by the project planning, wherein the pre-dispatching process includes: A. Opening the work schedule 313A; B. After selecting the date The unfinished work item 313B is automatically listed; C. The selected work item automatically lists the available workers list 313C; D. selects the worker 313D to be assigned; E. confirms the pre-delivery 313E.

請參第9圖,為本創作之當日派工流程圖,本創作經由工程企劃引導的施工履歷監控管理系統,其中該當日派工流程包含:A.開啟工作進度表314A;B.點選「工作項目」314B後自動列出「改派a」、「問題回報b」及「完成回報c」選項; 點選「改派a」;a1.自動列出要改派的工人名單a1;a2.選取要改派的工人a2;a3.確認後完成派工a3;點選「問題回報b」;b1.輸入問題描述及所需協助b1;b2.確認後完成回報b2;點選「完成回報c」;c1.點選完成回報c1;c2.確認後完成回報c2。 Please refer to Figure 9 for the flow chart of the day of the creation. The creation of the construction history monitoring and management system guided by the project planning, the day dispatching process includes: A. Open the work schedule 314A; B. Click " Work item "314B" automatically lists the "Reasue a", "Problem return b" and "Complete return c" options; Click on "Reassign a"; a1. Automatically list the list of workers to be reassigned a1; a2. Select the worker a2 to be reassigned; a3. Complete the assignment a3 after confirmation; click "Question return b"; b1. Enter the problem description and required assistance b1; b2. Complete the return b2 after confirmation; click “Complete return c”; c1. Click to complete the return c1; c2. Confirm the return and complete the return c2.

請參第10圖,為本創作之工程進度監控管理流程圖,本創作經由工程企劃引導的施工履歷監控管理系統,其中該工程進度監控管理流程包含:a.建置工程進度監控圖於雲端資料庫32a;b.開啟工程進度監控圖為背景32b;c.畫出各工程區段的工程線段32c;d.定義各工程區段的工程項目32d;e.建置各工程區段的主要物料表32e;f.依實際完成之工程點選完成工程進度之區段後儲存32f;g.輸入區段物料剩餘數量32g;h.上傳完工工程照片32h; i.檢核進度達成率若100%則進行下一步驟,否則回到步驟f 32i;j.結束工程進度監控管理32j。 Please refer to Figure 10 for the flow chart of the project progress monitoring management of this creation. The construction history monitoring and management system guided by the project planning, the project progress monitoring management process includes: a. Construction project progress monitoring map in the cloud data Library 32a; b. Open the project progress monitoring map as the background 32b; c. draw the engineering line segment 32c of each engineering section; d. define the engineering project 32d of each engineering section; e. build the main materials of each engineering section Table 32e; f. According to the actual completion of the project, select the section after completing the progress of the project and store 32f; g. input the remaining amount of material in the section 32g; h. upload the completed project photo 32h; i. If the check progress achievement rate is 100%, proceed to the next step, otherwise return to step f 32i; j. End the project progress monitoring management 32j.

上述實施例所揭示者係藉以具體說明本創作,且文中雖透過特定的術語進行說明,當不能以此限定本新型創作之專利範圍;熟悉此項技術領域之人士當可在瞭解本創作之精神與原則後對其進行變更與修改而達到等效之目的,而此等變更與修改,皆應涵蓋於如后所述之申請專利範圍所界定範疇中。 The disclosures of the above embodiments are used to specifically explain the present creation, and although the descriptions are made through specific terms, the scope of patents of the novel creation cannot be limited thereby; those skilled in the art can understand the spirit of the creation. Changes and modifications are made to the equivalent of the principles, and such changes and modifications are to be included in the scope of the patent application as described later.

1‧‧‧終端裝置 1‧‧‧ Terminal devices

2‧‧‧網際網路 2‧‧‧Internet

3‧‧‧管控中心伺服器 3‧‧‧Control Center Server

30‧‧‧施工履歷監控管理系統程式 30‧‧‧ Construction history monitoring management system program

4‧‧‧用戶 4‧‧‧Users

40‧‧‧雲端資料庫 40‧‧‧Cloud database

41‧‧‧管理者 41‧‧‧Manager

42 42’‧‧‧一般使用者 42 42’‧‧‧General users

50‧‧‧訊息主機 50‧‧‧Message Host

60‧‧‧分析主機 60‧‧‧Analysis host

Claims (6)

一種經由工程企劃引導的施工履歷監控管理系統,其主要係藉由用戶終端裝置以網際網路與管控中心伺服器進行連結,藉以進行查核工程人力派工、施工效率及產能之整合創新系統,其係包含:至少一用戶,其係該施工履歷監控管理系統使用者,包含管理者及一般使用者;一管控中心伺服器,其係包含施工履歷監控管理系統程式、雲端資料庫、訊息主機及分析主機,該雲端資料庫包含工程圖及工程進度監控圖,該訊息主機係傳遞進度異常及會議訊息,該分析主機係分析比對工程進度比率,該用戶藉由終端裝置以網際網路與管控中心伺服器進行連結執行施工履歷監控管理。 A construction history monitoring and management system guided by engineering planning, which is mainly connected with a server and a control center server by a user terminal device, thereby performing an integrated innovation system for checking manpower dispatching, construction efficiency and productivity of the project, The system includes: at least one user, which is a user of the construction history monitoring management system, including a manager and a general user; and a control center server, which includes a construction history monitoring management system program, a cloud database, a message host, and an analysis The host computer, the cloud database includes a drawing and a project progress monitoring map, the message host transmits the progress anomaly and the conference message, and the analysis host compares the progress ratio of the project, and the user uses the terminal device to connect to the Internet and the control center. The server performs connection and performs construction history monitoring and management. 如請求項1所述之經由工程企劃引導的施工履歷監控管理系統,其中之施工履歷監控管理系統程式包含:一人力派工系統,其係包含上下班打卡系統、工作進度瀏覽系統、預先派工系統及當日派工系統,其中該上下班打卡系統藉由QR CODE條碼打卡或輸入ID打卡,該工作進度瀏覽系統藉由瀏覽預期人力、預計工作天數、預計開始日期、實際人力、實際開始日期、實際結束日期及狀況回報以監控工程進度,該預先派工系統藉由預期人力、預計工作天數、預計開始日期、實際人力、實 際開始日期及欲派名單以實施預先派工作業,該當日派工系統藉由預期人力、預計工作天數、預計開始日期、實際人力、實際開始日期及欲派名單以實施當日派工作業;一驗收檢核及進度監控管理系統,係包含建置工程進度監控圖、建置工程區段、建置工程項目、建置主要物料表、建置完工照片及分析工程進度;其係依原始工程圖建置一工程進度監控圖於該資料庫中以顏色區分顯示完成區段及未完成區段,藉由用戶終端裝置讀取工程進度監控圖作為背景畫面進行工程區段拆解並定義各工程區段工程項目,建置各工程區段的主要物料表,依實際完成之工程進度於工程進度監控圖點選各工程區段後儲存,並回報工程區段物料剩餘數量及上傳施工完成照片,依工程進度監控圖顯示最新工程進度比率進行工程進度分析。 The construction history monitoring and management system guided by the engineering plan described in claim 1, wherein the construction history monitoring management system program comprises: a manpower dispatching system, which includes a commuting and punching system, a work progress browsing system, and a pre-delivery work. The system and the day dispatching system, wherein the commuting punching system punches the card by QR CODE barcode or enters the ID, and the work progress browsing system browses the expected manpower, estimated working days, estimated starting date, actual manpower, actual starting date, The actual end date and status report to monitor the progress of the project. The pre-dispatched system is based on expected manpower, estimated working days, estimated start date, actual manpower, and actual The date of commencement and the list of parties to be implemented to implement the pre-dispatched work. The day-to-day delivery system will implement the day-to-day work by the expected manpower, estimated working days, estimated start date, actual manpower, actual start date and wish list. The inspection and inspection and progress monitoring management system includes the progress monitoring map of the construction project, the construction project section, the construction project, the construction of the main material list, the completion of the construction photo and the analysis of the progress of the project; Establishing a project progress monitoring map in the database to display the completed segment and the unfinished segment by color, and the user terminal device reads the project progress monitoring map as a background image to disassemble the engineering segment and define each project area For the section project, the main material list of each project section will be built. According to the actual progress of the project, the project sections will be selected and stored in the project progress monitoring map, and the remaining quantity of materials in the project section will be returned and the photo of the construction completion will be uploaded. The project progress monitoring chart shows the latest project progress rate for project progress analysis. 如請求項1或2所述之經由工程企劃引導的施工履歷監控管理系統,其中該終端裝置為平板電腦、智慧型手機或個人電腦者。 The construction history monitoring and management system guided by the engineering plan according to claim 1 or 2, wherein the terminal device is a tablet computer, a smart phone or a personal computer. 如請求項2所述之經由工程企劃引導的施工履歷監控管理系統,其中該預先派工系統實施步驟包含:A.開啟工作進度表;B.選取日期後自動列出未完成的工作項目; C.點選派工項目自動列出可用工作人員名單;D.選取欲指派的工作人員;E.確認後完成預先派工。 The construction history monitoring and management system guided by the engineering plan as described in claim 2, wherein the pre-dispatching system implementation step comprises: A. opening a work schedule; B. automatically listing unfinished work items after the date is selected; C. Select the dispatched project to automatically list the available staff; D. Select the staff to be assigned; E. Complete the pre-delivery after confirmation. 如請求項2所述之經由工程企劃引導的施工履歷監控管理系統,其中該當日派工系統實施步驟包含:A.開啟工作進度表;B.點選「工作項目」後自動列出「改派」、「問題回報」及「完成回報」選項;點選「改派」;a1.自動列出要改派的工作人員名單;a2.選取要改派的工作人員;a3.確認後完成派工;點選「問題回報」;b1.輸入問題描述及所需協助;b2.確認後完成回報;點選「完成回報」;c1.點選完成回報;c2.確認後完成回報。 The construction history monitoring and management system guided by the engineering plan as described in claim 2, wherein the day delivery system implementation step comprises: A. opening a work schedule; B. automatically selecting "reassigned" after clicking "work item" , "Problem Return" and "Complete Return" options; click "Reassign"; a1. Automatically list the list of staff to be reassigned; a2. Select the staff to be reassigned; a3. Complete the assignment after confirmation Click "Question Return"; b1. Enter the problem description and required assistance; b2. Complete the return after confirmation; click "Complete Return"; c1. Click to complete the return; c2. Confirm the return. 如請求項2所述之經由工程企劃引導的施工履歷監控管理系統,其中該驗收檢核及進度監控管理系統實施步驟包含:a.建置工程進度監控圖於雲端資料庫; b.開啟工程進度監控圖為背景;c.劃出各工程區段的工程線段;d.定義各工程區段的工程項目;e.建置各工程區段的主要物料表;f.依實際完成之工程點選完成工程進度之區段後儲存;g.輸入區段物料剩餘數量;h.上傳完工工程照片;i.檢核進度達成率是否100% 32i,是則進行下一步驟,否則回到步驟f;j.結束驗收檢核及進度監控管理。 The construction history monitoring and management system guided by the engineering plan described in claim 2, wherein the implementation steps of the acceptance check and progress monitoring management system comprise: a. constructing a project progress monitoring map in the cloud database; b. Open the project progress monitoring map as the background; c. Draw the engineering line segments of each engineering section; d. Define the engineering projects of each engineering section; e. Establish the main material table of each engineering section; f. The completed project is selected and completed after the section of the project progress; g. Enter the remaining quantity of the material; h. Upload the completed project photo; i. Check whether the progress rate is 100% 32i, then proceed to the next step, otherwise Go back to step f; j. End the inspection and inspection and progress monitoring management.
TW105214122U 2016-09-13 2016-09-13 Construction history monitoring management system guided by engineering planning TWM535357U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW105214122U TWM535357U (en) 2016-09-13 2016-09-13 Construction history monitoring management system guided by engineering planning

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW105214122U TWM535357U (en) 2016-09-13 2016-09-13 Construction history monitoring management system guided by engineering planning

Publications (1)

Publication Number Publication Date
TWM535357U true TWM535357U (en) 2017-01-11

Family

ID=58400118

Family Applications (1)

Application Number Title Priority Date Filing Date
TW105214122U TWM535357U (en) 2016-09-13 2016-09-13 Construction history monitoring management system guided by engineering planning

Country Status (1)

Country Link
TW (1) TWM535357U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109002952A (en) * 2017-06-07 2018-12-14 株式会社日立制作所 The system of operation and management
CN109726457A (en) * 2018-12-17 2019-05-07 深圳市中行建设工程顾问有限公司 A kind of overall process intelligence engineering supervisory information managing and control system
CN110264168A (en) * 2019-07-26 2019-09-20 梧州市城建投资发展集团有限公司 A kind of Engineering Project Construction duration monitoring system and method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109002952A (en) * 2017-06-07 2018-12-14 株式会社日立制作所 The system of operation and management
CN109726457A (en) * 2018-12-17 2019-05-07 深圳市中行建设工程顾问有限公司 A kind of overall process intelligence engineering supervisory information managing and control system
CN110264168A (en) * 2019-07-26 2019-09-20 梧州市城建投资发展集团有限公司 A kind of Engineering Project Construction duration monitoring system and method
CN110264168B (en) * 2019-07-26 2023-05-02 梧州市城建投资发展集团有限公司 Engineering project construction period monitoring system and method

Similar Documents

Publication Publication Date Title
Zhai et al. An Internet of Things-enabled BIM platform for modular integrated construction: A case study in Hong Kong
Ko et al. Making formwork construction lean
Zhou et al. Customization of on-site assembly services by integrating the internet of things and BIM technologies in modular integrated construction
CN105023201B (en) Assembled architecture Deepen Design and construction method based on BIM and big data
JP6057607B2 (en) Production management system and method
CN109559379B (en) Panorama house-seeing method and device based on assembly type building platform
US11805170B2 (en) Fire service and equipment inspection test and maintenance system
KR102064490B1 (en) System for managing manufacturing and production process
KR20140058732A (en) System and method for manageing defect of construction site
JP2008299762A (en) Production management program
CN109360123B (en) Multi-professional construction management method and system based on room
CN107886287A (en) A kind of decoration construction work Self management system and its control method
TWM535357U (en) Construction history monitoring management system guided by engineering planning
JP7376309B2 (en) Work performance analysis server, work performance analysis method, and work performance analysis program
CN109558412A (en) The data growing method and device of assembled architecture construct platform
Tsai et al. Workflow re-engineering of design-build projects using a BIM tool
KR102370134B1 (en) Process management system and method using smart construction platform
Sahin et al. A simulation case study on supply chain management of a construction firm adopting cloud computing and RFID
CN117391640A (en) Engineering construction project construction period management method and system based on BIM and GIS
CN110019435A (en) Data processing method and system based on assembled architecture platform
Peiris et al. Digitalising modular construction: Enhancement of off-site manufacturing productivity via a manufacturing execution & control (MEC) system
Desai et al. Value stream mapping as a lean construction tool–a case study
Sanchez Gomez et al. Perth Children's Hospital-case study report
JP2020129312A (en) Building performance management method and performance management system
KR20090000285A (en) A process control system and a method thereof