CN107516161A - A kind of project progress management-control method based on BIM - Google Patents

A kind of project progress management-control method based on BIM Download PDF

Info

Publication number
CN107516161A
CN107516161A CN201710657013.XA CN201710657013A CN107516161A CN 107516161 A CN107516161 A CN 107516161A CN 201710657013 A CN201710657013 A CN 201710657013A CN 107516161 A CN107516161 A CN 107516161A
Authority
CN
China
Prior art keywords
engineering
progress
bim
project
dimensional surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710657013.XA
Other languages
Chinese (zh)
Inventor
黄劲超
陆本燕
彭云林
侯聚玲
彭俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fifth Engineering Bureau Co Ltd
Original Assignee
China Construction Fifth Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fifth Engineering Bureau Co Ltd filed Critical China Construction Fifth Engineering Bureau Co Ltd
Priority to CN201710657013.XA priority Critical patent/CN107516161A/en
Publication of CN107516161A publication Critical patent/CN107516161A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063114Status monitoring or status determination for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063116Schedule adjustment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Geometry (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Computer Hardware Design (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Mathematical Analysis (AREA)
  • Pure & Applied Mathematics (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Computational Mathematics (AREA)
  • Data Mining & Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Civil Engineering (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Computer Graphics (AREA)
  • Software Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of project progress management-control method based on BIM, comprise the following steps:The first step:According to project development engineering two dimensional surface schedule, and create engineering BIM models;Second step:Engineering two dimensional surface actual progress is worked out according to engineering project actual progress;3rd step:The engineering two dimensional surface schedule and engineering two dimensional surface actual progress input progress simulation softward;4th step:The engineering BIM models are attached to the data three-dimensional dynamic analog engineering actual progress in the data source of the progress simulation softward and in the data source;5th step:The analog video of the Three Dimensional Dynamic Simulation engineering actual progress is generated, works out engineering actual progress analysis report;For the present invention by the way that plane schedule is combined with threedimensional model, allowing model to carry out Dynamic Display with the plan of engineering actual progress can be by schedule and actual progress;Output progress analog video, is played out at the scene, is easy to workmen's understanding.

Description

A kind of project progress management-control method based on BIM
Technical field
The present invention relates to a kind of project progress management-control method, a kind of combination BIM of specific design carries out project progress management and control Method.
Background technology
BIM (Building Information Modeling) is related with the items of construction-engineering project Basis of the information data as model, carries out the foundation of BUILDINGS MODELS, by possessed by digital information analogue simulation building Real information.It has visualization, harmony, simulation, optimization property and five big feature of figure can be gone out.BIM technology is initially main Apply to architectural design, rear gradually to expand to construction management field, the former is realized by calculation amount and valuation software, and with engineering Based on item data management, the Cost Management of overall process is extended to;The latter is mainly by three-dimensional modeling work compound and virtual Construction, detect between each component with the presence or absence of conflict or inconsistent, eliminate hard collision hidden danger, and check that each structure part was being constructed Journey, in hoisting process, it whether there is soft collision between other components or equipment, so as to assist the management of construction progress, enter And reduce doing over again caused by the uncontrollability at scene and the complexity of operation and be lost.
Project is a well-known Common item management tool software, and the software inherits many ripe project pipes Modern theory and method are managed, is usually used in engineering plane Schedule management, project administrator is helped in the form of exporting Gantt chart Realize time, resource, the plan of cost, control.
During Engineering Project Construction, in order that project implementation result is without departing from plan, the important set of project management It is exactly project progress management and control into part, and the schedule performance form that Project makes is single, it is not vivid to tell somebody what one's real intentions are, can not be fast Speed contrasts schedule variance, and directiveness is limited;BIM creates threedimensional model, it is impossible to directly reflects project progress.Therefore, how Realize that it is this area urgent problem to carry out three-dimensional display to project progress.
The content of the invention
It is an object of the invention to for above-mentioned technical problem propose it is a kind of based on BIM can be with dynamic tracing display engineering The project progress management-control method of progress.
Technical scheme is used by the present invention solves above-mentioned technical problem:A kind of project progress management and control side based on BIM Method, comprise the following steps:
The first step:According to project development engineering two dimensional surface schedule, and create engineering BIM models;
Second step:Engineering two dimensional surface actual progress is worked out according to engineering project actual progress;
3rd step:The engineering two dimensional surface schedule and the input progress simulation of engineering two dimensional surface actual progress are soft Part;
4th step:The engineering BIM models are attached in the data source of the progress simulation softward and according to the data source In data three-dimensional dynamic analog engineering actual progress;
5th step:Generate the analog video of the Three Dimensional Dynamic Simulation engineering actual progress, establishment engineering actual progress point Analysis report.
In the present invention, the 4th step include set Three Dimensional Dynamic Simulation project progress at the beginning of between, the end time And progress shifts to an earlier date display mode and progress hysteresis display mode.
In the present invention, the engineering two dimensional surface schedule, engineering two dimensional surface actual progress task names and Engineering BIM model file titles are consistent.
In the present invention, the engineering two dimensional surface schedule and engineering two dimensional surface actual progress are special according to engineering Industry, plane subregion are worked out.
In the present invention, the engineering BIM models are carried out according to the level of detail of the engineering two dimensional surface schedule Create.
In the present invention, the engineering BIM models comprise at least:Component name, component material, scantling and component Construction information.
In the present invention, the component material comprises at least:Material Name, material model and material specification.
In the present invention, the component construction information comprises at least:Component unit in charge of construction, component commencement date, component are tested Receive date and component inspection unit.
In the present invention, the 5th step includes exporting the analog video to mobile terminal playing out.
In the present invention, the mobile terminal includes mobile phone, tablet personal computer or notebook computer.
The present invention establishes the project progress based on BIM technology by the way that plane schedule is combined with threedimensional model Management-control method, implementation model change with the propulsion of schedule, allow model to carry out Dynamic Display with the plan of engineering actual progress, The project progress at exact date efficient and convenient can be checked, there can be deviation by schedule and actual progress, quick lookup progress Position, carry out progress correction;Simulated by different majors progress, the interspersed construction that can be marched into the arena to different majors carries out decision-making, keeps away Exempt from the irrationality of practice of construction;Output progress analog video, is played out at the scene, is easy to workmen's understanding.
Brief description of the drawings
Fig. 1 is a kind of schematic flow sheet of project progress management-control method based on BIM of the present invention.
Embodiment
In order to illustrate more clearly of technical scheme, below in conjunction with drawings and Examples, to the technology of the present invention Scheme is further elaborated, it should be apparent that, description below is only some embodiments of the present invention, for this area For those of ordinary skill, on the premise of not paying creative work, it can also be obtained according to these embodiments other real Apply example.
A kind of reference picture 1, project progress management-control method based on BIM, comprises the following steps:
The first step:According to project development engineering two dimensional surface schedule, and create engineering BIM models;Wherein, create The engineering BIM models built save as nwc formatted files
Second step:Engineering two dimensional surface actual progress is worked out according to engineering project actual progress;
3rd step:The engineering two dimensional surface schedule and the input progress simulation of engineering two dimensional surface actual progress are soft Part;Schedule and the actual progress of engineering are simulated by progress simulation softward, is follow-up Three-Dimensional Dynamic project progress Simulation provides basic data;Wherein, progress simulation softward typically uses navisworks softwares;
4th step:The engineering BIM models are attached in the data source of the progress simulation softward and according to the data source In data three-dimensional dynamic analog engineering actual progress;BIM models are attached in the data source of progress simulation softward, passed through Relevant parameter is set to realize the Three Dimensional Dynamic Simulation of project progress;
5th step:Generate the analog video of the Three Dimensional Dynamic Simulation engineering actual progress, establishment engineering actual progress point Analysis report.Construction program and actual progress are directly shown by visual video mode, can easily carry out work The establishment of journey actual progress analysis report, progress correction is carried out by engineering actual progress analysis report, the progress of next stage is determined Plan, and can be used for instructing site operation.Preferably, the engineering actual progress analysis report includes construction program and engineering After actual progress compares, the position with hysteresis in advance of appearance, the reason for project progress and the loss thereby resulted in are influenceed.It is logical The correction that engineering actual progress analysis report carries out project progress is crossed, adjusts the construction organization of next step.Carrying out progress decision-making When, it is necessary to formulate the schedule in different majors and different operating face, it is ensured that whole work progress does not conflict, not collided, preceding Linking is reasonable afterwards.
In one embodiment, between at the beginning of the 4th step is including setting Three Dimensional Dynamic Simulation project progress, tie Beam time and progress shift to an earlier date display mode and progress hysteresis display mode.Between at the beginning of by setting Three Dimensional Dynamic Simulation and The progress section of simulation shows required for end time is selected, accurately some construction node of whole engineering can be entered Row control, actual progress and the schedule of engineering relatively have three states:1st, actual progress matches unanimously with schedule;2、 Actual progress shifts to an earlier date than schedule;3rd, actual progress lags than schedule;Need to set different display modes to represent Different states;It is clear intuitively to show current engineering typically by selecting to set the different state of different color expressions The actual conditions of progress.
In one embodiment, data identification matching, the engineering two dimensional surface progress are carried out automatically for ease of system Plan, the task names of engineering two dimensional surface actual progress are consistent with engineering BIM model file titles, and system passes through progress task The data of title and file name automatic identification matching separate sources.
In one embodiment, the engineering two dimensional surface schedule and engineering two dimensional surface actual progress are according to specially Industry, subregion are worked out;Such as can be divided into foundation, agent structure, building decoration, building roof, building water supply and drainage and Heating, architectural electricity, intelligent building, heating ventilation and air-conditioning, elevator, energy-conservation etc. are worked out.The schedule of engineering two dimensional surface with And engineering two dimensional surface actual progress is worked out using project softwares, wherein, the schedule of engineering two dimensional surface needs Worked out before construction task starts, engineering two dimensional surface actual progress is worked out after construction task terminates.Engineering two The level of detail of dimensional plane schedule and engineering two dimensional surface actual progress is configured according to specialty and subregion (segmentation), To adapt to the demand of different majors and different Work sectors.
In one embodiment, the engineering BIM models are according to the detailed journey of the engineering two dimensional surface schedule Degree is created.Needed the schedule of engineering two dimensional surface, engineering two dimensional surface actual progress and engineering BIM moulds in the later stage The data of type, which combine, to be carried out in Three Dimensional Dynamic Simulation, and the data structure of three needs to keep matching consistent, therefore, engineering The level of detail of BIM models needs to be consistent with the schedule of engineering two dimensional surface, engineering two dimensional surface actual progress, to protect Demonstrate,prove the accuracy of later stage Three Dimensional Dynamic Simulation.
In one embodiment, the engineering BIM models comprise at least:Component name, component material, scantling with And component construction information.Wherein, the component material comprises at least:Material Name, material model and material specification;The structure Part construction information comprises at least:Component unit in charge of construction, component commencement date, component date of inspection and receipt and component inspection unit.It is logical The essential information of target member, the detailed and involved construction Supervision list of associated materials can be rapidly found out by crossing above- mentioned information Position, complete reference information is provided for follow-up scheduling, is very easy to the development of follow-up scheduling work.
In one embodiment, the 5th step includes exporting the analog video to mobile terminal playing out. Because the process for carrying out Three Dimensional Dynamic Simulation needs to handle substantial amounts of data, generally require and high-performance computer is used in computer room Carry out the calculating of Three Dimensional Dynamic Simulation, therefore, the shape of the analog result video file of Three Dimensional Dynamic Simulation engineering actual progress Formula is exported, and the mobile terminal specified can be uploaded to by network, is directly directly played out in corresponding mobile terminal, can Constructed for on-the-spot guidance, reasonable arrangement resource input and progress construction organization;And the analog result is visual and understandable, use Told somebody what one's real intentions are in progress, it is acceptant to apply workmen person, reduces construction organization difficulty.Preferably, the mobile terminal includes conventional Mobile phone, tablet personal computer or notebook computer etc., facilitate onsite application.
The present invention establishes the project progress based on BIM technology by the way that plane schedule is combined with threedimensional model Management-control method, implementation model change with the propulsion of schedule, allow model to carry out Dynamic Display with the plan of engineering actual progress, The project progress at exact date efficient and convenient can be checked, there can be deviation by schedule and actual progress, quick lookup progress Position, carry out progress correction;Simulated by different majors progress, the interspersed construction that can be marched into the arena to different majors carries out decision-making, keeps away Exempt from the irrationality of practice of construction;Output progress analog video, is played out at the scene, is easy to workmen's understanding.
Described above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, under the premise without departing from the principles of the invention, some improvements and modifications can also be made, these improvements and modifications also should It is considered as protection scope of the present invention.

Claims (10)

1. a kind of project progress management-control method based on BIM, it is characterised in that comprise the following steps:
The first step:According to project development engineering two dimensional surface schedule, and create engineering BIM models;
Second step:Engineering two dimensional surface actual progress is worked out according to engineering project actual progress;
3rd step:The engineering two dimensional surface schedule and engineering two dimensional surface actual progress input progress simulation softward;
4th step:The engineering BIM models are attached in the data source of the progress simulation softward and according in the data source Data three-dimensional dynamic analog engineering actual progress;
5th step:Generate the analog video of the Three Dimensional Dynamic Simulation engineering actual progress, establishment engineering actual progress analysis report Accuse.
2. the project progress management-control method based on BIM as claimed in claim 1, it is characterised in that the 4th step includes setting Between putting at the beginning of Three Dimensional Dynamic Simulation project progress, end time and progress shift to an earlier date display mode and progress hysteresis display side Formula.
3. the project progress management-control method based on BIM as claimed in claim 1, it is characterised in that the engineering two dimensional surface Schedule, the task names of engineering two dimensional surface actual progress are consistent with engineering BIM model file titles.
4. the project progress management-control method based on BIM as claimed in claim 1, it is characterised in that the engineering two dimensional surface Schedule and engineering two dimensional surface actual progress are worked out according to specialty, subregion.
5. the project progress management-control method based on BIM as claimed in claim 1, it is characterised in that the engineering BIM model roots Created according to the level of detail of the engineering two dimensional surface schedule.
6. the project progress management-control method based on BIM as claimed in claim 1, it is characterised in that the engineering BIM models are extremely Include less:Component name, component material, scantling and component construction information.
7. the project progress management-control method based on BIM as claimed in claim 6, it is characterised in that the component material is at least Including:Material Name, material model and material specification.
8. the project progress management-control method based on BIM as claimed in claim 7, it is characterised in that the component construction information Comprise at least:Component unit in charge of construction, component commencement date, component date of inspection and receipt and component inspection unit.
9. the project progress management-control method based on BIM as claimed in claim 1, it is characterised in that the 5th step includes will The analog video, which is exported to mobile terminal, to be played out.
10. the project progress management-control method based on BIM as claimed in claim 9, it is characterised in that the mobile terminal includes Mobile phone, tablet personal computer or notebook computer.
CN201710657013.XA 2017-08-03 2017-08-03 A kind of project progress management-control method based on BIM Pending CN107516161A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710657013.XA CN107516161A (en) 2017-08-03 2017-08-03 A kind of project progress management-control method based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710657013.XA CN107516161A (en) 2017-08-03 2017-08-03 A kind of project progress management-control method based on BIM

Publications (1)

Publication Number Publication Date
CN107516161A true CN107516161A (en) 2017-12-26

Family

ID=60721875

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710657013.XA Pending CN107516161A (en) 2017-08-03 2017-08-03 A kind of project progress management-control method based on BIM

Country Status (1)

Country Link
CN (1) CN107516161A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109146120A (en) * 2018-06-25 2019-01-04 国网经济技术研究院有限公司 Three-dimensional model identification method for construction task progress state of power transmission and transformation project
CN109345195A (en) * 2018-09-13 2019-02-15 深圳市栋森工程项目管理有限公司 A kind of project supervision monitoring and managing method and system based on BIM
CN109377065A (en) * 2018-10-31 2019-02-22 广西路桥工程集团有限公司 One kind being based on three-dimensional visualization engineering construction progress control and cost control system
CN109977582A (en) * 2019-04-04 2019-07-05 中国十七冶集团有限公司 A kind of inorfil vacuum heat-insulation plate construction video based on BIM technology is told somebody what one's real intentions are method
CN110378670A (en) * 2019-07-17 2019-10-25 重庆大学 A kind of spatial network technology model and its construction method and application
CN110598260A (en) * 2019-08-16 2019-12-20 南京紫城工程设计有限公司 Municipal engineering design system based on BIM technology
CN110852696A (en) * 2019-10-08 2020-02-28 上海建工五建集团有限公司 Project progress monitoring method and system
CN110880097A (en) * 2019-11-21 2020-03-13 中国电力企业联合会电力建设技术经济咨询中心 Project progress simulation display method and device
CN113128961A (en) * 2021-04-16 2021-07-16 深圳市艾赛克科技有限公司 Wisdom building site management cloud platform
CN114444163A (en) * 2021-12-13 2022-05-06 中建五局安装工程有限公司 Electromechanical construction method and system based on BIM technology

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105512822A (en) * 2015-12-14 2016-04-20 国家电网公司 Construction progress management method based on visualization technology
CN106296473A (en) * 2015-05-28 2017-01-04 上海宝冶集团有限公司 A kind of construction project progress real-time control method based on BIM technology
CN106803150A (en) * 2017-01-20 2017-06-06 上海市地下空间设计研究总院有限公司 Municipal Engineering Construction progress msg management method and system based on BIM

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106296473A (en) * 2015-05-28 2017-01-04 上海宝冶集团有限公司 A kind of construction project progress real-time control method based on BIM technology
CN105512822A (en) * 2015-12-14 2016-04-20 国家电网公司 Construction progress management method based on visualization technology
CN106803150A (en) * 2017-01-20 2017-06-06 上海市地下空间设计研究总院有限公司 Municipal Engineering Construction progress msg management method and system based on BIM

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109146120A (en) * 2018-06-25 2019-01-04 国网经济技术研究院有限公司 Three-dimensional model identification method for construction task progress state of power transmission and transformation project
CN109345195A (en) * 2018-09-13 2019-02-15 深圳市栋森工程项目管理有限公司 A kind of project supervision monitoring and managing method and system based on BIM
CN109377065B (en) * 2018-10-31 2022-02-01 广西路桥工程集团有限公司 Project construction progress management and cost control system based on three-dimensional visualization
CN109377065A (en) * 2018-10-31 2019-02-22 广西路桥工程集团有限公司 One kind being based on three-dimensional visualization engineering construction progress control and cost control system
CN109977582A (en) * 2019-04-04 2019-07-05 中国十七冶集团有限公司 A kind of inorfil vacuum heat-insulation plate construction video based on BIM technology is told somebody what one's real intentions are method
CN110378670A (en) * 2019-07-17 2019-10-25 重庆大学 A kind of spatial network technology model and its construction method and application
CN110598260A (en) * 2019-08-16 2019-12-20 南京紫城工程设计有限公司 Municipal engineering design system based on BIM technology
CN110852696A (en) * 2019-10-08 2020-02-28 上海建工五建集团有限公司 Project progress monitoring method and system
CN110880097A (en) * 2019-11-21 2020-03-13 中国电力企业联合会电力建设技术经济咨询中心 Project progress simulation display method and device
CN110880097B (en) * 2019-11-21 2023-04-07 中国电力企业联合会电力建设技术经济咨询中心 Project progress simulation display method and device
CN113128961A (en) * 2021-04-16 2021-07-16 深圳市艾赛克科技有限公司 Wisdom building site management cloud platform
CN113128961B (en) * 2021-04-16 2022-03-11 深圳市艾赛克科技有限公司 Wisdom building site management cloud platform system
CN114444163A (en) * 2021-12-13 2022-05-06 中建五局安装工程有限公司 Electromechanical construction method and system based on BIM technology

Similar Documents

Publication Publication Date Title
CN107516161A (en) A kind of project progress management-control method based on BIM
US20190205484A1 (en) Systems and methods for construction planning
WO2022048156A1 (en) Pumped storage power station comprehensive management method, platform and system, device and medium
CN113360583B (en) Construction progress visualization method based on BIM model and monitoring image comparison
US8155928B2 (en) Method for generating data of plant construction simulation and system thereof
CN107679310A (en) The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology
CN107832498A (en) A kind of complicated construction technology based on BIM is told somebody what one's real intentions are method
CN108984832B (en) Method and system for loading BIM model by utilizing Unity3D in intelligent building operation and maintenance
EP1643335A2 (en) System and method for designing building structures with associated estimates and schedules
Ahmed et al. A brief discussion on augmented reality and virtual reality in construction industry
CN104680320A (en) BIM-based project management system and method
CN110276555A (en) Residential housing entity Life cycle analysis method based on internet and BIM
CN108563851A (en) A kind of mountain tunnel BIM modeling methods quickly refined
CN104679954A (en) Method and system for lightening BIM (Building Information Modeling) model
CN109033558A (en) External scaffolding model modelling approach based on Revit platform
CN108665172A (en) A kind of interactive building engineering construction quality control method
CN114528613A (en) Intelligent park digital twin system visual editing method
Begić et al. Digitalization and automation in construction project's life-cycle: a review.
CN108416076A (en) A kind of assembled architecture design method based on BIM technology
CN112765711A (en) BIM modeling method for green building simulation calculation
CN113987659A (en) Building design method based on BIM technology
CN116109042A (en) Engineering implementation visual management system and method based on BIM technology
CN105426601A (en) Diversity design scheme reporting method and system based on BIM (Building Information Modeling)
CN111242498A (en) Construction progress management system and management method based on building information model
CN111242497A (en) Construction cost management system and method based on building information model

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171226