CN107516161A - A kind of project progress management-control method based on BIM - Google Patents
A kind of project progress management-control method based on BIM Download PDFInfo
- Publication number
- CN107516161A CN107516161A CN201710657013.XA CN201710657013A CN107516161A CN 107516161 A CN107516161 A CN 107516161A CN 201710657013 A CN201710657013 A CN 201710657013A CN 107516161 A CN107516161 A CN 107516161A
- Authority
- CN
- China
- Prior art keywords
- engineering
- progress
- bim
- project
- dimensional surface
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 25
- 238000004088 simulation Methods 0.000 claims abstract description 15
- 238000005094 computer simulation Methods 0.000 claims abstract description 14
- 238000004458 analytical method Methods 0.000 claims abstract description 8
- 238000011161 development Methods 0.000 claims abstract description 5
- 238000010276 construction Methods 0.000 claims description 22
- 239000000463 material Substances 0.000 claims description 16
- 238000007689 inspection Methods 0.000 claims description 5
- 238000007726 management method Methods 0.000 description 8
- 238000005516 engineering process Methods 0.000 description 5
- 238000012937 correction Methods 0.000 description 4
- 230000018109 developmental process Effects 0.000 description 3
- 230000008520 organization Effects 0.000 description 3
- 230000008569 process Effects 0.000 description 3
- 230000008859 change Effects 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 238000010438 heat treatment Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 230000000007 visual effect Effects 0.000 description 2
- 238000004378 air conditioning Methods 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 150000001875 compounds Chemical class 0.000 description 1
- 238000009430 construction management Methods 0.000 description 1
- 238000013523 data management Methods 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000004134 energy conservation Methods 0.000 description 1
- 230000014509 gene expression Effects 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 230000011218 segmentation Effects 0.000 description 1
- 238000009423 ventilation Methods 0.000 description 1
- 238000012800 visualization Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063114—Status monitoring or status determination for a person or group
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063116—Schedule adjustment for a person or group
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Strategic Management (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Entrepreneurship & Innovation (AREA)
- Economics (AREA)
- Geometry (AREA)
- Marketing (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Computer Hardware Design (AREA)
- Educational Administration (AREA)
- Development Economics (AREA)
- Game Theory and Decision Science (AREA)
- Mathematical Analysis (AREA)
- Pure & Applied Mathematics (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Computational Mathematics (AREA)
- Data Mining & Analysis (AREA)
- Mathematical Optimization (AREA)
- Civil Engineering (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Computer Graphics (AREA)
- Software Systems (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of project progress management-control method based on BIM, comprise the following steps:The first step:According to project development engineering two dimensional surface schedule, and create engineering BIM models;Second step:Engineering two dimensional surface actual progress is worked out according to engineering project actual progress;3rd step:The engineering two dimensional surface schedule and engineering two dimensional surface actual progress input progress simulation softward;4th step:The engineering BIM models are attached to the data three-dimensional dynamic analog engineering actual progress in the data source of the progress simulation softward and in the data source;5th step:The analog video of the Three Dimensional Dynamic Simulation engineering actual progress is generated, works out engineering actual progress analysis report;For the present invention by the way that plane schedule is combined with threedimensional model, allowing model to carry out Dynamic Display with the plan of engineering actual progress can be by schedule and actual progress;Output progress analog video, is played out at the scene, is easy to workmen's understanding.
Description
Technical field
The present invention relates to a kind of project progress management-control method, a kind of combination BIM of specific design carries out project progress management and control
Method.
Background technology
BIM (Building Information Modeling) is related with the items of construction-engineering project
Basis of the information data as model, carries out the foundation of BUILDINGS MODELS, by possessed by digital information analogue simulation building
Real information.It has visualization, harmony, simulation, optimization property and five big feature of figure can be gone out.BIM technology is initially main
Apply to architectural design, rear gradually to expand to construction management field, the former is realized by calculation amount and valuation software, and with engineering
Based on item data management, the Cost Management of overall process is extended to;The latter is mainly by three-dimensional modeling work compound and virtual
Construction, detect between each component with the presence or absence of conflict or inconsistent, eliminate hard collision hidden danger, and check that each structure part was being constructed
Journey, in hoisting process, it whether there is soft collision between other components or equipment, so as to assist the management of construction progress, enter
And reduce doing over again caused by the uncontrollability at scene and the complexity of operation and be lost.
Project is a well-known Common item management tool software, and the software inherits many ripe project pipes
Modern theory and method are managed, is usually used in engineering plane Schedule management, project administrator is helped in the form of exporting Gantt chart
Realize time, resource, the plan of cost, control.
During Engineering Project Construction, in order that project implementation result is without departing from plan, the important set of project management
It is exactly project progress management and control into part, and the schedule performance form that Project makes is single, it is not vivid to tell somebody what one's real intentions are, can not be fast
Speed contrasts schedule variance, and directiveness is limited;BIM creates threedimensional model, it is impossible to directly reflects project progress.Therefore, how
Realize that it is this area urgent problem to carry out three-dimensional display to project progress.
The content of the invention
It is an object of the invention to for above-mentioned technical problem propose it is a kind of based on BIM can be with dynamic tracing display engineering
The project progress management-control method of progress.
Technical scheme is used by the present invention solves above-mentioned technical problem:A kind of project progress management and control side based on BIM
Method, comprise the following steps:
The first step:According to project development engineering two dimensional surface schedule, and create engineering BIM models;
Second step:Engineering two dimensional surface actual progress is worked out according to engineering project actual progress;
3rd step:The engineering two dimensional surface schedule and the input progress simulation of engineering two dimensional surface actual progress are soft
Part;
4th step:The engineering BIM models are attached in the data source of the progress simulation softward and according to the data source
In data three-dimensional dynamic analog engineering actual progress;
5th step:Generate the analog video of the Three Dimensional Dynamic Simulation engineering actual progress, establishment engineering actual progress point
Analysis report.
In the present invention, the 4th step include set Three Dimensional Dynamic Simulation project progress at the beginning of between, the end time
And progress shifts to an earlier date display mode and progress hysteresis display mode.
In the present invention, the engineering two dimensional surface schedule, engineering two dimensional surface actual progress task names and
Engineering BIM model file titles are consistent.
In the present invention, the engineering two dimensional surface schedule and engineering two dimensional surface actual progress are special according to engineering
Industry, plane subregion are worked out.
In the present invention, the engineering BIM models are carried out according to the level of detail of the engineering two dimensional surface schedule
Create.
In the present invention, the engineering BIM models comprise at least:Component name, component material, scantling and component
Construction information.
In the present invention, the component material comprises at least:Material Name, material model and material specification.
In the present invention, the component construction information comprises at least:Component unit in charge of construction, component commencement date, component are tested
Receive date and component inspection unit.
In the present invention, the 5th step includes exporting the analog video to mobile terminal playing out.
In the present invention, the mobile terminal includes mobile phone, tablet personal computer or notebook computer.
The present invention establishes the project progress based on BIM technology by the way that plane schedule is combined with threedimensional model
Management-control method, implementation model change with the propulsion of schedule, allow model to carry out Dynamic Display with the plan of engineering actual progress,
The project progress at exact date efficient and convenient can be checked, there can be deviation by schedule and actual progress, quick lookup progress
Position, carry out progress correction;Simulated by different majors progress, the interspersed construction that can be marched into the arena to different majors carries out decision-making, keeps away
Exempt from the irrationality of practice of construction;Output progress analog video, is played out at the scene, is easy to workmen's understanding.
Brief description of the drawings
Fig. 1 is a kind of schematic flow sheet of project progress management-control method based on BIM of the present invention.
Embodiment
In order to illustrate more clearly of technical scheme, below in conjunction with drawings and Examples, to the technology of the present invention
Scheme is further elaborated, it should be apparent that, description below is only some embodiments of the present invention, for this area
For those of ordinary skill, on the premise of not paying creative work, it can also be obtained according to these embodiments other real
Apply example.
A kind of reference picture 1, project progress management-control method based on BIM, comprises the following steps:
The first step:According to project development engineering two dimensional surface schedule, and create engineering BIM models;Wherein, create
The engineering BIM models built save as nwc formatted files
Second step:Engineering two dimensional surface actual progress is worked out according to engineering project actual progress;
3rd step:The engineering two dimensional surface schedule and the input progress simulation of engineering two dimensional surface actual progress are soft
Part;Schedule and the actual progress of engineering are simulated by progress simulation softward, is follow-up Three-Dimensional Dynamic project progress
Simulation provides basic data;Wherein, progress simulation softward typically uses navisworks softwares;
4th step:The engineering BIM models are attached in the data source of the progress simulation softward and according to the data source
In data three-dimensional dynamic analog engineering actual progress;BIM models are attached in the data source of progress simulation softward, passed through
Relevant parameter is set to realize the Three Dimensional Dynamic Simulation of project progress;
5th step:Generate the analog video of the Three Dimensional Dynamic Simulation engineering actual progress, establishment engineering actual progress point
Analysis report.Construction program and actual progress are directly shown by visual video mode, can easily carry out work
The establishment of journey actual progress analysis report, progress correction is carried out by engineering actual progress analysis report, the progress of next stage is determined
Plan, and can be used for instructing site operation.Preferably, the engineering actual progress analysis report includes construction program and engineering
After actual progress compares, the position with hysteresis in advance of appearance, the reason for project progress and the loss thereby resulted in are influenceed.It is logical
The correction that engineering actual progress analysis report carries out project progress is crossed, adjusts the construction organization of next step.Carrying out progress decision-making
When, it is necessary to formulate the schedule in different majors and different operating face, it is ensured that whole work progress does not conflict, not collided, preceding
Linking is reasonable afterwards.
In one embodiment, between at the beginning of the 4th step is including setting Three Dimensional Dynamic Simulation project progress, tie
Beam time and progress shift to an earlier date display mode and progress hysteresis display mode.Between at the beginning of by setting Three Dimensional Dynamic Simulation and
The progress section of simulation shows required for end time is selected, accurately some construction node of whole engineering can be entered
Row control, actual progress and the schedule of engineering relatively have three states:1st, actual progress matches unanimously with schedule;2、
Actual progress shifts to an earlier date than schedule;3rd, actual progress lags than schedule;Need to set different display modes to represent
Different states;It is clear intuitively to show current engineering typically by selecting to set the different state of different color expressions
The actual conditions of progress.
In one embodiment, data identification matching, the engineering two dimensional surface progress are carried out automatically for ease of system
Plan, the task names of engineering two dimensional surface actual progress are consistent with engineering BIM model file titles, and system passes through progress task
The data of title and file name automatic identification matching separate sources.
In one embodiment, the engineering two dimensional surface schedule and engineering two dimensional surface actual progress are according to specially
Industry, subregion are worked out;Such as can be divided into foundation, agent structure, building decoration, building roof, building water supply and drainage and
Heating, architectural electricity, intelligent building, heating ventilation and air-conditioning, elevator, energy-conservation etc. are worked out.The schedule of engineering two dimensional surface with
And engineering two dimensional surface actual progress is worked out using project softwares, wherein, the schedule of engineering two dimensional surface needs
Worked out before construction task starts, engineering two dimensional surface actual progress is worked out after construction task terminates.Engineering two
The level of detail of dimensional plane schedule and engineering two dimensional surface actual progress is configured according to specialty and subregion (segmentation),
To adapt to the demand of different majors and different Work sectors.
In one embodiment, the engineering BIM models are according to the detailed journey of the engineering two dimensional surface schedule
Degree is created.Needed the schedule of engineering two dimensional surface, engineering two dimensional surface actual progress and engineering BIM moulds in the later stage
The data of type, which combine, to be carried out in Three Dimensional Dynamic Simulation, and the data structure of three needs to keep matching consistent, therefore, engineering
The level of detail of BIM models needs to be consistent with the schedule of engineering two dimensional surface, engineering two dimensional surface actual progress, to protect
Demonstrate,prove the accuracy of later stage Three Dimensional Dynamic Simulation.
In one embodiment, the engineering BIM models comprise at least:Component name, component material, scantling with
And component construction information.Wherein, the component material comprises at least:Material Name, material model and material specification;The structure
Part construction information comprises at least:Component unit in charge of construction, component commencement date, component date of inspection and receipt and component inspection unit.It is logical
The essential information of target member, the detailed and involved construction Supervision list of associated materials can be rapidly found out by crossing above- mentioned information
Position, complete reference information is provided for follow-up scheduling, is very easy to the development of follow-up scheduling work.
In one embodiment, the 5th step includes exporting the analog video to mobile terminal playing out.
Because the process for carrying out Three Dimensional Dynamic Simulation needs to handle substantial amounts of data, generally require and high-performance computer is used in computer room
Carry out the calculating of Three Dimensional Dynamic Simulation, therefore, the shape of the analog result video file of Three Dimensional Dynamic Simulation engineering actual progress
Formula is exported, and the mobile terminal specified can be uploaded to by network, is directly directly played out in corresponding mobile terminal, can
Constructed for on-the-spot guidance, reasonable arrangement resource input and progress construction organization;And the analog result is visual and understandable, use
Told somebody what one's real intentions are in progress, it is acceptant to apply workmen person, reduces construction organization difficulty.Preferably, the mobile terminal includes conventional
Mobile phone, tablet personal computer or notebook computer etc., facilitate onsite application.
The present invention establishes the project progress based on BIM technology by the way that plane schedule is combined with threedimensional model
Management-control method, implementation model change with the propulsion of schedule, allow model to carry out Dynamic Display with the plan of engineering actual progress,
The project progress at exact date efficient and convenient can be checked, there can be deviation by schedule and actual progress, quick lookup progress
Position, carry out progress correction;Simulated by different majors progress, the interspersed construction that can be marched into the arena to different majors carries out decision-making, keeps away
Exempt from the irrationality of practice of construction;Output progress analog video, is played out at the scene, is easy to workmen's understanding.
Described above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For member, under the premise without departing from the principles of the invention, some improvements and modifications can also be made, these improvements and modifications also should
It is considered as protection scope of the present invention.
Claims (10)
1. a kind of project progress management-control method based on BIM, it is characterised in that comprise the following steps:
The first step:According to project development engineering two dimensional surface schedule, and create engineering BIM models;
Second step:Engineering two dimensional surface actual progress is worked out according to engineering project actual progress;
3rd step:The engineering two dimensional surface schedule and engineering two dimensional surface actual progress input progress simulation softward;
4th step:The engineering BIM models are attached in the data source of the progress simulation softward and according in the data source
Data three-dimensional dynamic analog engineering actual progress;
5th step:Generate the analog video of the Three Dimensional Dynamic Simulation engineering actual progress, establishment engineering actual progress analysis report
Accuse.
2. the project progress management-control method based on BIM as claimed in claim 1, it is characterised in that the 4th step includes setting
Between putting at the beginning of Three Dimensional Dynamic Simulation project progress, end time and progress shift to an earlier date display mode and progress hysteresis display side
Formula.
3. the project progress management-control method based on BIM as claimed in claim 1, it is characterised in that the engineering two dimensional surface
Schedule, the task names of engineering two dimensional surface actual progress are consistent with engineering BIM model file titles.
4. the project progress management-control method based on BIM as claimed in claim 1, it is characterised in that the engineering two dimensional surface
Schedule and engineering two dimensional surface actual progress are worked out according to specialty, subregion.
5. the project progress management-control method based on BIM as claimed in claim 1, it is characterised in that the engineering BIM model roots
Created according to the level of detail of the engineering two dimensional surface schedule.
6. the project progress management-control method based on BIM as claimed in claim 1, it is characterised in that the engineering BIM models are extremely
Include less:Component name, component material, scantling and component construction information.
7. the project progress management-control method based on BIM as claimed in claim 6, it is characterised in that the component material is at least
Including:Material Name, material model and material specification.
8. the project progress management-control method based on BIM as claimed in claim 7, it is characterised in that the component construction information
Comprise at least:Component unit in charge of construction, component commencement date, component date of inspection and receipt and component inspection unit.
9. the project progress management-control method based on BIM as claimed in claim 1, it is characterised in that the 5th step includes will
The analog video, which is exported to mobile terminal, to be played out.
10. the project progress management-control method based on BIM as claimed in claim 9, it is characterised in that the mobile terminal includes
Mobile phone, tablet personal computer or notebook computer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710657013.XA CN107516161A (en) | 2017-08-03 | 2017-08-03 | A kind of project progress management-control method based on BIM |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710657013.XA CN107516161A (en) | 2017-08-03 | 2017-08-03 | A kind of project progress management-control method based on BIM |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107516161A true CN107516161A (en) | 2017-12-26 |
Family
ID=60721875
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710657013.XA Pending CN107516161A (en) | 2017-08-03 | 2017-08-03 | A kind of project progress management-control method based on BIM |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107516161A (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109146120A (en) * | 2018-06-25 | 2019-01-04 | 国网经济技术研究院有限公司 | Three-dimensional model identification method for construction task progress state of power transmission and transformation project |
CN109345195A (en) * | 2018-09-13 | 2019-02-15 | 深圳市栋森工程项目管理有限公司 | A kind of project supervision monitoring and managing method and system based on BIM |
CN109377065A (en) * | 2018-10-31 | 2019-02-22 | 广西路桥工程集团有限公司 | One kind being based on three-dimensional visualization engineering construction progress control and cost control system |
CN109977582A (en) * | 2019-04-04 | 2019-07-05 | 中国十七冶集团有限公司 | A kind of inorfil vacuum heat-insulation plate construction video based on BIM technology is told somebody what one's real intentions are method |
CN110378670A (en) * | 2019-07-17 | 2019-10-25 | 重庆大学 | A kind of spatial network technology model and its construction method and application |
CN110598260A (en) * | 2019-08-16 | 2019-12-20 | 南京紫城工程设计有限公司 | Municipal engineering design system based on BIM technology |
CN110852696A (en) * | 2019-10-08 | 2020-02-28 | 上海建工五建集团有限公司 | Project progress monitoring method and system |
CN110880097A (en) * | 2019-11-21 | 2020-03-13 | 中国电力企业联合会电力建设技术经济咨询中心 | Project progress simulation display method and device |
CN113128961A (en) * | 2021-04-16 | 2021-07-16 | 深圳市艾赛克科技有限公司 | Wisdom building site management cloud platform |
CN114444163A (en) * | 2021-12-13 | 2022-05-06 | 中建五局安装工程有限公司 | Electromechanical construction method and system based on BIM technology |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105512822A (en) * | 2015-12-14 | 2016-04-20 | 国家电网公司 | Construction progress management method based on visualization technology |
CN106296473A (en) * | 2015-05-28 | 2017-01-04 | 上海宝冶集团有限公司 | A kind of construction project progress real-time control method based on BIM technology |
CN106803150A (en) * | 2017-01-20 | 2017-06-06 | 上海市地下空间设计研究总院有限公司 | Municipal Engineering Construction progress msg management method and system based on BIM |
-
2017
- 2017-08-03 CN CN201710657013.XA patent/CN107516161A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106296473A (en) * | 2015-05-28 | 2017-01-04 | 上海宝冶集团有限公司 | A kind of construction project progress real-time control method based on BIM technology |
CN105512822A (en) * | 2015-12-14 | 2016-04-20 | 国家电网公司 | Construction progress management method based on visualization technology |
CN106803150A (en) * | 2017-01-20 | 2017-06-06 | 上海市地下空间设计研究总院有限公司 | Municipal Engineering Construction progress msg management method and system based on BIM |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109146120A (en) * | 2018-06-25 | 2019-01-04 | 国网经济技术研究院有限公司 | Three-dimensional model identification method for construction task progress state of power transmission and transformation project |
CN109345195A (en) * | 2018-09-13 | 2019-02-15 | 深圳市栋森工程项目管理有限公司 | A kind of project supervision monitoring and managing method and system based on BIM |
CN109377065B (en) * | 2018-10-31 | 2022-02-01 | 广西路桥工程集团有限公司 | Project construction progress management and cost control system based on three-dimensional visualization |
CN109377065A (en) * | 2018-10-31 | 2019-02-22 | 广西路桥工程集团有限公司 | One kind being based on three-dimensional visualization engineering construction progress control and cost control system |
CN109977582A (en) * | 2019-04-04 | 2019-07-05 | 中国十七冶集团有限公司 | A kind of inorfil vacuum heat-insulation plate construction video based on BIM technology is told somebody what one's real intentions are method |
CN110378670A (en) * | 2019-07-17 | 2019-10-25 | 重庆大学 | A kind of spatial network technology model and its construction method and application |
CN110598260A (en) * | 2019-08-16 | 2019-12-20 | 南京紫城工程设计有限公司 | Municipal engineering design system based on BIM technology |
CN110852696A (en) * | 2019-10-08 | 2020-02-28 | 上海建工五建集团有限公司 | Project progress monitoring method and system |
CN110880097A (en) * | 2019-11-21 | 2020-03-13 | 中国电力企业联合会电力建设技术经济咨询中心 | Project progress simulation display method and device |
CN110880097B (en) * | 2019-11-21 | 2023-04-07 | 中国电力企业联合会电力建设技术经济咨询中心 | Project progress simulation display method and device |
CN113128961A (en) * | 2021-04-16 | 2021-07-16 | 深圳市艾赛克科技有限公司 | Wisdom building site management cloud platform |
CN113128961B (en) * | 2021-04-16 | 2022-03-11 | 深圳市艾赛克科技有限公司 | Wisdom building site management cloud platform system |
CN114444163A (en) * | 2021-12-13 | 2022-05-06 | 中建五局安装工程有限公司 | Electromechanical construction method and system based on BIM technology |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107516161A (en) | A kind of project progress management-control method based on BIM | |
US20190205484A1 (en) | Systems and methods for construction planning | |
WO2022048156A1 (en) | Pumped storage power station comprehensive management method, platform and system, device and medium | |
CN113360583B (en) | Construction progress visualization method based on BIM model and monitoring image comparison | |
US8155928B2 (en) | Method for generating data of plant construction simulation and system thereof | |
CN107679310A (en) | The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology | |
CN107832498A (en) | A kind of complicated construction technology based on BIM is told somebody what one's real intentions are method | |
CN108984832B (en) | Method and system for loading BIM model by utilizing Unity3D in intelligent building operation and maintenance | |
EP1643335A2 (en) | System and method for designing building structures with associated estimates and schedules | |
Ahmed et al. | A brief discussion on augmented reality and virtual reality in construction industry | |
CN104680320A (en) | BIM-based project management system and method | |
CN110276555A (en) | Residential housing entity Life cycle analysis method based on internet and BIM | |
CN108563851A (en) | A kind of mountain tunnel BIM modeling methods quickly refined | |
CN104679954A (en) | Method and system for lightening BIM (Building Information Modeling) model | |
CN109033558A (en) | External scaffolding model modelling approach based on Revit platform | |
CN108665172A (en) | A kind of interactive building engineering construction quality control method | |
CN114528613A (en) | Intelligent park digital twin system visual editing method | |
Begić et al. | Digitalization and automation in construction project's life-cycle: a review. | |
CN108416076A (en) | A kind of assembled architecture design method based on BIM technology | |
CN112765711A (en) | BIM modeling method for green building simulation calculation | |
CN113987659A (en) | Building design method based on BIM technology | |
CN116109042A (en) | Engineering implementation visual management system and method based on BIM technology | |
CN105426601A (en) | Diversity design scheme reporting method and system based on BIM (Building Information Modeling) | |
CN111242498A (en) | Construction progress management system and management method based on building information model | |
CN111242497A (en) | Construction cost management system and method based on building information model |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171226 |