CN116109042A - Engineering implementation visual management system and method based on BIM technology - Google Patents

Engineering implementation visual management system and method based on BIM technology Download PDF

Info

Publication number
CN116109042A
CN116109042A CN202310382124.XA CN202310382124A CN116109042A CN 116109042 A CN116109042 A CN 116109042A CN 202310382124 A CN202310382124 A CN 202310382124A CN 116109042 A CN116109042 A CN 116109042A
Authority
CN
China
Prior art keywords
engineering
architecture
bim
database
framework
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202310382124.XA
Other languages
Chinese (zh)
Other versions
CN116109042B (en
Inventor
刘军
罗敏
于云港
逄淑华
魏广民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Rongtai New Housing Engineering Co ltd
Original Assignee
Qingdao Rongtai New Housing Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Rongtai New Housing Engineering Co ltd filed Critical Qingdao Rongtai New Housing Engineering Co ltd
Priority to CN202310382124.XA priority Critical patent/CN116109042B/en
Publication of CN116109042A publication Critical patent/CN116109042A/en
Application granted granted Critical
Publication of CN116109042B publication Critical patent/CN116109042B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/24Querying
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Quality & Reliability (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Operations Research (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Computational Linguistics (AREA)
  • Data Mining & Analysis (AREA)
  • Databases & Information Systems (AREA)
  • General Engineering & Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Stored Programmes (AREA)
  • Testing And Monitoring For Control Systems (AREA)

Abstract

The invention relates to the technical field of engineering implementation visual management, in particular to a BIM technology-based engineering implementation visual management system and a BIM technology-based engineering implementation visual management method, comprising an engineering database extraction module, a basic underlying architecture analysis module, an engineering architecture combination set construction module, a correlation value analysis module, a remote storage judgment module and a priority analysis early warning module; the engineering database extraction module acquires an engineering database recorded by BIM technology implementation; the basic underlying mechanism analysis module splits the model mapping project in the project database and outputs a basic underlying architecture; the engineering framework combination set construction module is used for analyzing the connection relation and outputting an engineering framework combination set; the association value analysis module analyzes and extracts the association values of the abnormal event and all the completed engineering frameworks before the abnormal event occurs; and the remote storage judging module stores the BIM structure model corresponding to the engineering architecture with the association value larger than or equal to the association value threshold value in different places.

Description

Engineering implementation visual management system and method based on BIM technology
Technical Field
The invention relates to the technical field of engineering implementation visual management, in particular to a system and a method for engineering implementation visual management based on BIM technology.
Background
Under the large trend of informatization and industrialization in the building industry, BIM technology is leading to the optimization and upgrading of a building mode due to the outstanding advantages of optimality, simulation, visualization, coordination and the like, and BIM application gradually becomes the main stream in the building industry; BIM can help project team understand the standards and regulations of complex space by analyzing the space in the building planning stage, thereby saving time and providing possibility of more value-added activities for team. Particularly, when customers discuss requirements, select and analyze optimal schemes, critical decisions can be made by means of BIM and related analysis data; the application result of the BIM in the building planning stage also helps an architect to check whether the preliminary design meets the requirements of owners at any time in the building design stage, and whether the preliminary design meets the design basis obtained in the building planning stage, and the huge waste of modification design when unqualified is found in the detailed diagram design stage in the future is greatly reduced through the continuous information transmission or traceability of the BIM;
however, in practical application, it is generally found that, due to different levels of engineers, the BIM database is not reasonably utilized in the construction of the early stage of the project, so that the project time is saved, and when the model information is inconsistent with the field information and needs to be modified, no safe platform is available for processing and storing the data so as to prevent interference to the historical safe data; meanwhile, the BIM engineer and the field engineer communicate in real time in different places in the model, so that the BIM engineer and the field engineer have the limitation that the two parties can not immediately use the same window to rotate the model to confirm that the discussion positions are identical, the difficulty degree of modifying the characteristics can not be determined, and the problems of accurate positioning and quick solution can not be realized.
Disclosure of Invention
The invention aims to provide a visual management system and a visual management method for engineering implementation based on BIM technology, which are used for solving the problems in the background technology.
In order to solve the technical problems, the invention provides the following technical scheme: a visual management method for engineering implementation based on BIM technology comprises the following analysis steps:
step S1: acquiring an engineering database recorded by BIM technology, wherein the engineering database refers to data recorded from the process of constructing a model of an original space structure by using the BIM technology to the process of finishing engineering by taking the original space structure as a unit; the engineering is completed, namely the BIM construction model is mapped onto the original space structure to form an actual engineering structure; splitting all model mapping projects recorded in the project database and outputting a basic underlying framework;
step S2: extracting engineering frameworks which have connection relation with the basic underlying framework in the engineering database, and outputting an engineering framework combination set;
step S3: acquiring an abnormal event stored in an engineering database in the actual construction of the engineering framework combination centralized engineering framework combination, wherein the abnormal event refers to an event that the length of time required for completing the actual engineering of the engineering framework combination is greater than or equal to a preset duration threshold value or the number of times of modifying a BIM structure model in the actual engineering is greater than or equal to a modification threshold value; analyzing and extracting association values of the abnormal event and all the completed engineering structures before the abnormal event occurs;
step S4: setting an association value threshold, and storing BIM structure models corresponding to engineering frameworks with association values larger than or equal to the association value threshold in different places; off-site storage refers to storing in a local database other than the engineering database; the local database is convenient to modify, and early warning is carried out on the structure involved in the abnormal event under the condition that the structure is similar to the engineering architecture combination set in the implementation process of the subsequent new engineering, so that the involved structure is possibly abnormal, a BIM engineer and a field engineer are reminded of paying attention, and the local database is convenient for the BIM engineer and the field engineer to modify so as to ensure that the data stored in the engineering database is the final data and is not easy to change;
step S5: extracting modification data of abnormal event records in a local database, wherein the modification data refers to data of communication modification records of BIM model architecture when a field engineer and a BIM engineer communicate in different places; and analyzing priorities corresponding to different modification data, and outputting early warning signals based on the priorities.
Further, in step S1, all model mapping projects recorded in the project database are split and a basic underlying architecture is output, including the following analysis steps:
the model mapping project refers to the process of correspondingly implementing the BIM structure model on the actual space structure, and the splitting refers to the fact that each project framework of the project database for planning construction is a splitting unit according to the finishing sequence of the actual construction process; constructing a structure data pair A, A { a } corresponding to the splitting unit 1 →a 2 (wherein a) 1 Representing a BIM model architecture corresponding to the splitting unit, and a2 represents an actual engineering architecture corresponding to the splitting unit;
extracting all structure data pairs contained in all projects recorded in the project database;
sequentially comparing BIM model architecture and actual engineering architecture of the structure data pairs in different projects, taking any structure data pair as a target structure data pair, extracting the number m of projects to which other structure data pairs in the engineering database which are completely the same as the target structure data pair belong, and utilizing the formula: f=m/M, calculating the universality ratio f of any structural data pair; wherein M represents the total number of recorded projects in the project database;
and extracting a target structure data pair corresponding to the maximum value max (f) of the pervasive ratio as a basic infrastructure.
In the engineering implementation recording process, structures of different engineering have the same points, because the analysis and comparison process of historical engineering is rarely carried out in the existing construction process, and meanwhile, analysis is also a relatively time-consuming engineering, engineers prefer to formulate a BIM model from scratch and also do not want to search for directly utilizing the existing model, and the application selects a basic framework suitable for most engineering modeling and an alternative combined framework by extracting a large amount of engineering data, so that the time cost of the engineer on structural design is saved, BIM technology is utilized more comprehensively and intelligently, and the universality of the BIM model is improved.
Further, step S2 includes the following analysis steps:
acquiring an engineering framework with a connection relation with a basic underlying framework, wherein the connection relation comprises a first connection relation and a second connection relation;
the first connection relationship refers to a connection relationship which is connected with the basic underlying framework in a space position and does not contain the basic underlying framework;
the second connection relationship refers to a connection relationship of a newly added architecture on the basic underlying architecture;
constructing an engineering tree with a first connection relation or a second connection relation corresponding to the engineering architecture as a child node by taking the basic underlying architecture as a root node; matching and combining different engineering trees and outputting a combined set which comprises all engineering trees as an engineering framework; the matching combination refers to that a first connection relation or a second connection relation exists between engineering frameworks contained in the combined engineering tree.
The engineering tree is constructed to clearly and rapidly extract a model diagram which can be utilized in the BIM model architecture.
Further, in step S3, the correlation values between the abnormal event and all the completed engineering structures before the abnormal event occurs are analyzed and extracted, which includes the following analysis steps:
marking the engineering architecture in the engineering architecture combination corresponding to the abnormal event as an objective architecture to be analyzed, and obtaining the number n of the objective architecture to be analyzed existing in the engineering tree 1 The engineering architecture recorded before the implementation of the target architecture to be analyzed is the investigation architecture, the investigation architecture changed when the target architecture to be analyzed carries out abnormal event processing is extracted to be the first investigation architecture, and the change times d corresponding to the first investigation architecture are marked 1 Using the formula:
G=k 1 [(n 1 /N)+(d 1 /D)]
k 1 =u 1 /u 2
calculating the association value G of the abnormal event and all the completed engineering structures before the abnormal event occurs; n represents the total number of engineering trees, D represents the total number of changes in an abnormal event;
wherein k is 1 Representing the first correlation coefficient, k 2 Representing a second correlation coefficient;
u 1 represents n 1 The target architecture to be analyzed in each engineering tree is the number of root nodes in the engineering tree, u 2 Representation ofn 1 The target architecture to be analyzed in each engineering tree is the number of sub-nodes in the engineering tree.
The method comprises the steps that the node relation of an engineering tree to which a target architecture to be analyzed belongs is confirmed to consider the influence degree of the target architecture to be analyzed in an abnormal event, and the influence degree is generally larger than that of a child node when the target architecture to be analyzed is a root node;
the analysis is based on the abnormal events in the engineering framework combination, because the engineering framework combination can be applied to other engineering, and the analysis of the abnormal events can be the early warning response of the subsequent implementation engineering when the engineering is executed to the same engineering link.
Further, step S5 includes the following analysis steps:
extracting the feature names of the engineering architecture corresponding to the modified data;
recording the regulation times y of the feature names in the BIM model architecture marked by the field engineers 1 The regulation and control refers to clicking, amplifying and rotating operations of a field engineer on the BIM model framework; acquiring the regulation and control times y of BIM engineers corresponding to the same feature name 2
Using the formula:
Z=|y 1 -y 2 |(y 1 /Y)
calculating a first regulating value Z corresponding to the feature name; wherein Y represents the total number of times of regulation and control of field engineers corresponding to all feature names;
extracting all feature names and first regulating and controlling values corresponding to the feature names of the abnormal event records, sequencing the feature names according to the sequence from the higher to the lower of the corresponding first regulating and controlling values to generate priorities, and outputting corresponding early warning signals.
The method and the system do not define the specific content of the modified data, only analyze the difficulty of the modified data, and sort the priority after extracting the feature names of the engineering frameworks corresponding to the modified data, so that when new construction projects exist and any engineering framework in the engineering framework combination set can be utilized, early warning is carried out on the framework features of the possible abnormal event, and after the problem occurs, detailed and proper data analysis and prompt are carried out on the different framework features according to the priority.
The project implementation visual management system comprises a project database extraction module, a basic underlying architecture analysis module, a project architecture combination set construction module, a correlation value analysis module, a remote storage judgment module and a priority analysis early warning module;
the engineering database extraction module is used for obtaining an engineering database recorded by the BIM technology, wherein the engineering database refers to data recorded from the process of constructing a model of an original space structure by the BIM technology by taking the original space structure as a unit;
the basic underlying architecture analysis module is used for splitting all model mapping projects recorded in the project database and outputting a basic underlying architecture;
the engineering framework combined set construction module is used for extracting engineering frameworks which have connection relation with the basic underlying framework in the engineering database and outputting an engineering framework combined set;
the association value analysis module is used for analyzing and extracting association values of the abnormal event and all the completed engineering frameworks before the abnormal event occurs;
the remote storage judging module is used for storing the BIM structure model corresponding to the engineering architecture with the association value larger than or equal to the association value threshold value in different places;
the priority analysis early warning module is used for analyzing priorities corresponding to different modification data and outputting early warning signals based on the priorities.
Further, the basic underlying framework analysis module comprises a structural data pair construction unit, a pervasive ratio calculation unit and a basic underlying framework output unit;
the construction unit of the structure data pair is used for taking each engineering framework of the planned construction as a splitting unit according to the sequence of the actual construction process in the engineering database; constructing a structure data pair corresponding to the splitting unit;
the universal ratio calculating unit is used for extracting the number of projects to which other structure data pairs belong in the engineering database which is completely the same as the target structure data pairs, and calculating the universal ratio;
the infrastructure output unit is used for extracting a target structure data pair corresponding to the maximum value of the pervasive ratio as an infrastructure.
Further, the association value analysis module comprises a target architecture output unit to be analyzed, a data extraction unit and an association value calculation unit;
the target architecture to be analyzed output unit is used for marking the engineering architecture in the engineering architecture combination corresponding to the abnormal event as the target architecture to be analyzed;
the data extraction unit is used for obtaining the number of the target architecture to be analyzed existing in the engineering tree and the change times corresponding to the first investigation architecture;
the association value calculating unit is used for calculating association values of the abnormal event and all the completed engineering frameworks before the abnormal event occurs based on the data corresponding to the data extracting unit.
Further, the priority analysis early warning module comprises a feature name extraction unit, a first regulation and control value calculation unit and a priority generation unit;
the feature name extraction unit is used for extracting feature names of engineering frameworks corresponding to the modified data;
the first regulation and control value calculation unit is used for recording the regulation and control times of the feature names in the BIM model architecture marked by the field engineers and the regulation and control times of the same feature names corresponding to the BIM engineers, and calculating the first regulation and control values corresponding to the feature names;
the priority generation unit is used for extracting all feature names and first regulating and controlling values corresponding to the feature names of the abnormal event records, sequencing the feature names according to the sequence from the high to the low corresponding to the first regulating and controlling values to generate priorities, and outputting corresponding early warning signals.
Compared with the prior art, the invention has the following beneficial effects: according to the method, the historical data recorded in the BIM system are analyzed, the engineering framework combination set capable of realizing effective utilization rate is extracted, the universality of the BIM model is improved, the time cost of structural design of engineers is saved, and the BIM technology is utilized more comprehensively and intelligently; meanwhile, the method analyzes the abnormal events existing in the engineering framework combination set from the data storage direction and the engineering modification direction, ensures the data safety of the data modification part in the engineering implementation process, and ensures the grasping degree of the model structure when engineers communicate in different places, and the system gives out the difficulty degree of the characteristic names in the framework so that the on-site engineers can effectively analyze and judge the information, thereby realizing the purposes of accurately positioning the problem and rapidly solving the problem.
Drawings
The accompanying drawings are included to provide a further understanding of the invention and are incorporated in and constitute a part of this specification, illustrate the invention and together with the embodiments of the invention, serve to explain the invention. In the drawings:
FIG. 1 is a schematic diagram of a visual management system for engineering implementation based on BIM technology.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
Referring to fig. 1, the present invention provides the following technical solutions: a visual management method for engineering implementation based on BIM technology comprises the following analysis steps:
step S1: acquiring an engineering database recorded by BIM technology, wherein the engineering database refers to data recorded from the process of constructing a model of an original space structure by using the BIM technology to the process of finishing engineering by taking the original space structure as a unit; the engineering is completed, namely the BIM construction model is mapped onto the original space structure to form an actual engineering structure; splitting all model mapping projects recorded in the project database and outputting a basic underlying framework;
step S2: extracting engineering frameworks which have connection relation with the basic underlying framework in the engineering database, and outputting an engineering framework combination set;
step S3: acquiring an abnormal event stored in an engineering database in the actual construction of the engineering framework combination centralized engineering framework combination, wherein the abnormal event refers to an event that the length of time required for completing the actual engineering of the engineering framework combination is greater than or equal to a preset duration threshold value or the number of times of modifying a BIM structure model in the actual engineering is greater than or equal to a modification threshold value; analyzing and extracting association values of the abnormal event and all the completed engineering structures before the abnormal event occurs;
step S4: setting an association value threshold, and storing BIM structure models corresponding to engineering frameworks with association values larger than or equal to the association value threshold in different places; off-site storage refers to storing in a local database other than the engineering database; the local database is convenient to modify, and early warning is carried out on the structure involved in the abnormal event under the condition that the structure is similar to the engineering architecture combination set in the implementation process of the subsequent new engineering, so that the involved structure is possibly abnormal, a BIM engineer and a field engineer are reminded of paying attention, and the local database is convenient for the BIM engineer and the field engineer to modify so as to ensure that the data stored in the engineering database is the final data and is not easy to change;
step S5: extracting modification data of abnormal event records in a local database, wherein the modification data refers to data of communication modification records of BIM model architecture when a field engineer and a BIM engineer communicate in different places; and analyzing priorities corresponding to different modification data, and outputting early warning signals based on the priorities.
In step S1, all model mapping projects recorded in the project database are split and a basic underlying architecture is output, and the method comprises the following analysis steps:
the model mapping project refers to the process of correspondingly implementing the BIM structure model on the actual space structure, and the splitting refers to the fact that each project framework of the project database for planning construction is a splitting unit according to the finishing sequence of the actual construction process; constructing a structure data pair A, A { a } corresponding to the splitting unit 1 →a 2 (wherein a) 1 Representing a BIM model architecture corresponding to the splitting unit, and a2 represents an actual engineering architecture corresponding to the splitting unit;
extracting all structure data pairs contained in all projects recorded in the project database;
sequentially comparing BIM model architecture and actual engineering architecture of the structure data pairs in different projects, taking any structure data pair as a target structure data pair, extracting the number m of projects to which other structure data pairs in the engineering database which are completely the same as the target structure data pair belong, and utilizing the formula: f=m/M, calculating the universality ratio f of any structural data pair; wherein M represents the total number of recorded projects in the project database;
and extracting a target structure data pair corresponding to the maximum value max (f) of the pervasive ratio as a basic infrastructure.
In the engineering implementation recording process, structures of different engineering have the same points, because the analysis and comparison process of historical engineering is rarely carried out in the existing construction process, and meanwhile, analysis is also a relatively time-consuming engineering, engineers prefer to formulate a BIM model from scratch and also do not want to search for directly utilizing the existing model, and the application selects a basic framework suitable for most engineering modeling and an alternative combined framework by extracting a large amount of engineering data, so that the time cost of the engineer on structural design is saved, BIM technology is utilized more comprehensively and intelligently, and the universality of the BIM model is improved.
Step S2 comprises the following analysis steps:
acquiring an engineering framework with a connection relation with a basic underlying framework, wherein the connection relation comprises a first connection relation and a second connection relation;
the first connection relationship refers to a connection relationship which is connected with the basic underlying framework in a space position and does not contain the basic underlying framework;
the second connection relationship refers to a connection relationship of a newly added architecture on the basic underlying architecture;
constructing an engineering tree with a first connection relation or a second connection relation corresponding to the engineering architecture as a child node by taking the basic underlying architecture as a root node; matching and combining different engineering trees and outputting a combined set which comprises all engineering trees as an engineering framework; the matching combination refers to that a first connection relation or a second connection relation exists between engineering frameworks contained in the combined engineering tree.
The engineering tree is constructed to clearly and rapidly extract a model diagram which can be utilized in the BIM model architecture.
The engineering architecture in the application is based on the spatial physical structure relation in the BIM, and does not relate to the attribute information about the structure, so that when different engineering needs to utilize the engineering tree, the attribute information contained in the architecture is not needed to be considered, and only the corresponding structure is needed to be extracted. And (3) if in the construction stage of the actual pre-buried pipeline, the water supply and drainage BIM model is directly positioned on the field. Guiding on-site slotting through corresponding scribing on the on-site by pipeline trend of the BIM; in this process, the drainage BIM model may be a root node, and the corresponding child node is a pipeline configured in the BIM model, belongs to the child node, and is a second connection relationship.
In step S3, the relevant values of the abnormal event and all the completed engineering structures before the abnormal event occurs are analyzed and extracted, which includes the following analysis steps:
marking the engineering architecture in the engineering architecture combination corresponding to the abnormal event as an objective architecture to be analyzed, and obtaining the number n of the objective architecture to be analyzed existing in the engineering tree 1 The engineering architecture recorded before the implementation of the target architecture to be analyzed is the investigation architecture, the investigation architecture changed when the target architecture to be analyzed carries out abnormal event processing is extracted to be the first investigation architecture, and the change times d corresponding to the first investigation architecture are marked 1 Using the formula:
G=k 1 [(n 1 /N)+(d 1 /D)]
k 1 =u 1 /u 2
calculating the association value G of the abnormal event and all the completed engineering structures before the abnormal event occurs; n represents the total number of engineering trees, D represents the total number of changes in an abnormal event;
wherein k is 1 Representing the first correlation coefficient, k 2 Representing a second correlation coefficient;
u 1 represents n 1 The target architecture to be analyzed in each engineering tree is the number of root nodes in the engineering tree, u 2 Represents n 1 The target architecture to be analyzed in each engineering tree is the number of sub-nodes in the engineering tree.
The method comprises the steps that the node relation of an engineering tree to which a target architecture to be analyzed belongs is confirmed to consider the influence degree of the target architecture to be analyzed in an abnormal event, and the influence degree is generally larger than that of a child node when the target architecture to be analyzed is a root node;
the analysis is based on the abnormal events in the engineering framework combination, because the engineering framework combination can be applied to other engineering, and the analysis of the abnormal events can be the early warning response of the subsequent implementation engineering when the engineering is executed to the same engineering link.
Step S5 comprises the following analysis steps:
extracting the feature names of the engineering architecture corresponding to the modified data;
recording the regulation times y of the feature names in the BIM model architecture marked by the field engineers 1 The regulation and control refers to clicking, amplifying and rotating operations of a field engineer on the BIM model framework; acquiring the regulation and control times y of BIM engineers corresponding to the same feature name 2
Using the formula:
Z=|y 1 -y 2 |(y 1 /Y)
calculating a first regulating value Z corresponding to the feature name; wherein Y represents the total number of times of regulation and control of field engineers corresponding to all feature names;
extracting all feature names and first regulating and controlling values corresponding to the feature names of the abnormal event records, sequencing the feature names according to the sequence from the higher to the lower of the corresponding first regulating and controlling values to generate priorities, and outputting corresponding early warning signals.
Because the precondition of the application is that engineers communicate in different places, the site engineers do not have the problems existing in the BIM engineers in quick and professional positioning actual space structure, deviation on BIM model operation exists, if the engineering architecture is simple in structure, the influence on the communication of the engineering architecture and the BIM engineers is small, and if the engineering architecture is difficult, larger deviation is generated; therefore, the modification difficulty of the feature structure to be modified can be judged by analyzing the deviation of the BIM model control;
the method and the system do not define the specific content of the modified data, only analyze the difficulty of the modified data, and sort the priority after extracting the feature names of the engineering frameworks corresponding to the modified data, so that when new construction projects exist and any engineering framework in the engineering framework combination set can be utilized, early warning is carried out on the framework features of the possible abnormal event, and after the problem occurs, detailed and proper data analysis and prompt are carried out on the different framework features according to the priority.
Recording modifications of the modification data as feature name 1, feature name 2, and feature name 3 in the abnormal event;
and the corresponding priority ranking is: feature name 2> feature name 3> feature name 1; the priority corresponds to that the modification difficulty is reduced in sequence according to the order of the priority;
the BIM system transmits a signal to prompt the engineer that the feature modification difficulty is the greatest when the feature name 2 is encountered during real-time construction.
The project implementation visual management system comprises a project database extraction module, a basic underlying architecture analysis module, a project architecture combination set construction module, a correlation value analysis module, a remote storage judgment module and a priority analysis early warning module;
the engineering database extraction module is used for obtaining an engineering database recorded by the BIM technology, wherein the engineering database refers to data recorded from the process of constructing a model of an original space structure by the BIM technology by taking the original space structure as a unit;
the basic underlying architecture analysis module is used for splitting all model mapping projects recorded in the project database and outputting a basic underlying architecture;
the engineering framework combined set construction module is used for extracting engineering frameworks which have connection relation with the basic underlying framework in the engineering database and outputting an engineering framework combined set;
the association value analysis module is used for analyzing and extracting association values of the abnormal event and all the completed engineering frameworks before the abnormal event occurs;
the remote storage judging module is used for storing the BIM structure model corresponding to the engineering architecture with the association value larger than or equal to the association value threshold value in different places;
the priority analysis early warning module is used for analyzing priorities corresponding to different modification data and outputting early warning signals based on the priorities.
The basic underlying framework analysis module comprises a structural data pair construction unit, a pervasive ratio calculation unit and a basic underlying framework output unit;
the construction unit of the structure data pair is used for taking each engineering framework of the planned construction as a splitting unit according to the sequence of the actual construction process in the engineering database; constructing a structure data pair corresponding to the splitting unit;
the universal ratio calculating unit is used for extracting the number of projects to which other structure data pairs belong in the engineering database which is completely the same as the target structure data pairs, and calculating the universal ratio;
the infrastructure output unit is used for extracting a target structure data pair corresponding to the maximum value of the pervasive ratio as an infrastructure.
The association value analysis module comprises a target architecture output unit to be analyzed, a data extraction unit and an association value calculation unit;
the target architecture to be analyzed output unit is used for marking the engineering architecture in the engineering architecture combination corresponding to the abnormal event as the target architecture to be analyzed;
the data extraction unit is used for obtaining the number of the target architecture to be analyzed existing in the engineering tree and the change times corresponding to the first investigation architecture;
the association value calculating unit is used for calculating association values of the abnormal event and all the completed engineering frameworks before the abnormal event occurs based on the data corresponding to the data extracting unit.
The priority analysis early warning module comprises a feature name extraction unit, a first regulation value calculation unit and a priority generation unit;
the feature name extraction unit is used for extracting feature names of engineering frameworks corresponding to the modified data;
the first regulation and control value calculation unit is used for recording the regulation and control times of the feature names in the BIM model architecture marked by the field engineers and the regulation and control times of the same feature names corresponding to the BIM engineers, and calculating the first regulation and control values corresponding to the feature names;
the priority generation unit is used for extracting all feature names and first regulating and controlling values corresponding to the feature names of the abnormal event records, sequencing the feature names according to the sequence from the high to the low corresponding to the first regulating and controlling values to generate priorities, and outputting corresponding early warning signals.
It is noted that relational terms such as first and second, and the like are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Moreover, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Finally, it should be noted that: the foregoing description is only a preferred embodiment of the present invention, and the present invention is not limited thereto, but it is to be understood that modifications and equivalents of some of the technical features described in the foregoing embodiments may be made by those skilled in the art, although the present invention has been described in detail with reference to the foregoing embodiments. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (9)

1. The engineering implementation visual management method based on the BIM technology is characterized by comprising the following analysis steps:
step S1: acquiring an engineering database recorded by BIM technology, wherein the engineering database refers to data recorded from the process of constructing a model of an original space structure by using the BIM technology to the process of finishing engineering by taking the original space structure as a unit; the engineering is completed by mapping the BIM construction model onto an original space structure to form an actual engineering structure; splitting all model mapping projects recorded in the project database and outputting a basic underlying framework;
step S2: extracting engineering frameworks which have connection relation with the basic underlying framework in the engineering database, and outputting an engineering framework combination set;
step S3: acquiring an abnormal event stored in an engineering database in actual construction of an engineering framework combination centralized engineering framework combination, wherein the abnormal event refers to an event that the length of time required for completing the actual engineering of the engineering framework combination is greater than or equal to a preset duration threshold value or the number of times of modifying a BIM structure model in the actual engineering is greater than or equal to a modification threshold value; analyzing and extracting association values of the abnormal event and all the completed engineering structures before the abnormal event occurs;
step S4: setting an association value threshold, and storing BIM structure models corresponding to engineering frameworks with association values larger than or equal to the association value threshold in different places; the off-site storage refers to a local database stored in a different engineering database;
step S5: extracting modification data of abnormal event records in a local database, wherein the modification data refers to data of communication modification records of a BIM model architecture when a field engineer and a BIM engineer communicate in different places; and analyzing priorities corresponding to different modification data, and outputting early warning signals based on the priorities.
2. The visual management method for engineering implementation based on the BIM technology according to claim 1, wherein the visual management method comprises the following steps: in the step S1, all model mapping projects recorded in the project database are split and a basic underlying architecture is output, and the method includes the following analysis steps:
the model mapping engineering refers to a process of correspondingly implementing a BIM structure model on an actual space structure, and the splitting refers to that each engineering framework of planned construction in an engineering database is a splitting unit according to the sequence of the completion of the actual construction process; constructing a structure data pair A, A { a } corresponding to the splitting unit 1 →a 2 (wherein a) 1 Representing a BIM model architecture corresponding to the splitting unit, and a2 represents an actual engineering architecture corresponding to the splitting unit;
extracting all structure data pairs contained in all projects recorded in the project database;
sequentially comparing BIM model architecture and actual engineering architecture of the structure data pairs in different projects, taking any structure data pair as a target structure data pair, extracting the number m of projects to which other structure data pairs in the engineering database which are completely the same as the target structure data pair belong, and utilizing the formula: f=m/M, calculating the universality ratio f of any structural data pair; wherein M represents the total number of recorded projects in the project database;
and extracting a target structure data pair corresponding to the maximum value max (f) of the pervasive ratio as a basic infrastructure.
3. The visual management method for engineering implementation based on the BIM technology according to claim 2, wherein the visual management method is characterized by comprising the following steps: the step S2 includes the following analysis steps:
acquiring an engineering framework with a connection relation with a basic underlying framework, wherein the connection relation comprises a first connection relation and a second connection relation;
the first connection relationship refers to a connection relationship which is connected with the basic underlying framework in a space position and does not contain the basic underlying framework;
the second connection relation refers to a connection relation of a newly added architecture on the basic underlying architecture;
constructing an engineering tree with a first connection relation or a second connection relation corresponding to the engineering architecture as a child node by taking the basic underlying architecture as a root node; matching and combining different engineering trees and outputting a combined set which comprises all engineering trees as an engineering framework; the matching combination means that a first connection relation or a second connection relation exists between engineering frameworks contained in the combined engineering tree.
4. A visual management method for engineering implementation based on BIM technology according to claim 3, wherein: in the step S3, the analysis and extraction of the correlation values between the abnormal event and all the completed engineering structures before the abnormal event occurs includes the following analysis steps:
marking the engineering architecture in the engineering architecture combination corresponding to the abnormal event as an objective architecture to be analyzed, and obtaining the number n of the objective architecture to be analyzed existing in the engineering tree 1 The engineering architecture recorded before the implementation of the target architecture to be analyzed is the investigation architecture, the investigation architecture changed when the target architecture to be analyzed carries out abnormal event processing is extracted to be the first investigation architecture, and the change corresponding to the first investigation architecture is markedNumber d of times 1 Using the formula:
G=k 1 [(n 1 /N)+(d 1 /D)]
k 1 =u 1 /u 2
calculating the association value G of the abnormal event and all the completed engineering structures before the abnormal event occurs; n represents the total number of engineering trees, D represents the total number of changes in an abnormal event;
wherein k is 1 Representing the first correlation coefficient, k 2 Representing a second correlation coefficient;
u 1 represents n 1 The target architecture to be analyzed in each engineering tree is the number of root nodes in the engineering tree, u 2 Represents n 1 The target architecture to be analyzed in each engineering tree is the number of sub-nodes in the engineering tree.
5. The visual management method for engineering implementation based on BIM technology according to claim 4, wherein the visual management method is characterized by comprising the following steps: the step S5 includes the following analysis steps:
extracting the feature names of the engineering architecture corresponding to the modified data;
recording the regulation times y of the feature names in the BIM model architecture marked by the field engineers 1 The regulation and control refers to clicking, amplifying and rotating operations of a field engineer on a BIM model framework; acquiring the regulation and control times y of BIM engineers corresponding to the same feature name 2
Using the formula:
Z=|y 1 -y 2 |(y 1 /Y)
calculating a first regulating value Z corresponding to the feature name; wherein Y represents the total number of times of regulation and control of field engineers corresponding to all feature names;
extracting all feature names and first regulating and controlling values corresponding to the feature names of the abnormal event records, sequencing the feature names according to the sequence from the higher to the lower of the corresponding first regulating and controlling values to generate priorities, and outputting corresponding early warning signals.
6. The project implementation visualization management system applying the project implementation visualization management method based on the BIM technology according to any one of claims 1-5 is characterized by comprising a project database extraction module, a basic underlying architecture analysis module, a project architecture combination set construction module, a correlation value analysis module, a remote storage judgment module and a priority analysis early warning module;
the engineering database extraction module is used for obtaining an engineering database recorded by implementing BIM technology, wherein the engineering database refers to data recorded from the implementation of an original space structure as a unit and the modeling of the original space structure by the BIM technology to the completion of engineering;
the basic underlying architecture analysis module is used for splitting all model mapping projects recorded in the project database and outputting a basic underlying architecture;
the engineering framework combined set construction module is used for extracting engineering frameworks which have connection relation with the basic underlying framework in the engineering database and outputting an engineering framework combined set;
the association value analysis module is used for analyzing and extracting association values of the abnormal event and all the completed engineering frameworks before the abnormal event occurs;
the remote storage judging module is used for storing the BIM structure model corresponding to the engineering architecture with the association value larger than or equal to the association value threshold value in different places;
the priority analysis early warning module is used for analyzing priorities corresponding to different modification data and outputting early warning signals based on the priorities.
7. The project implementation visualization management system of claim 6, wherein: the basic underlying framework analysis module comprises a structural data pair construction unit, a pervasive ratio calculation unit and a basic underlying framework output unit;
the structure data pair construction unit is used for constructing each engineering framework of the planning construction according to the sequence of the actual construction progress in the engineering database as a splitting unit; constructing a structure data pair corresponding to the splitting unit;
the universal ratio calculating unit is used for extracting the number of projects to which other structure data pairs in the engineering database which are completely the same as the target structure data pairs belong and calculating the universal ratio;
the infrastructure output unit is used for extracting a target structure data pair corresponding to the maximum value of the universal ratio to be the infrastructure.
8. The project implementation visualization management system of claim 7, wherein: the association value analysis module comprises a target architecture output unit to be analyzed, a data extraction unit and an association value calculation unit;
the target architecture output unit to be analyzed is used for marking the engineering architecture in the engineering architecture combination corresponding to the abnormal event as the target architecture to be analyzed;
the data extraction unit is used for obtaining the number of the target architecture to be analyzed existing in the engineering tree and the change times corresponding to the first investigation architecture;
the association value calculating unit is used for calculating association values of the abnormal event and all the completed engineering frameworks before the abnormal event occurs based on the data corresponding to the data extracting unit.
9. The project implementation visualization management system of claim 8, wherein: the priority analysis early warning module comprises a feature name extraction unit, a first regulation value calculation unit and a priority generation unit;
the feature name extraction unit is used for extracting feature names of engineering frameworks corresponding to the modified data;
the first regulation and control value calculation unit is used for recording the regulation and control times of the feature names in the BIM model architecture marked by the field engineers and the regulation and control times of the same feature names corresponding to the BIM engineers, and calculating the first regulation and control values corresponding to the feature names;
the priority generation unit is used for extracting all feature names and first regulation and control values corresponding to the feature names of the abnormal event records, sequencing the feature names according to the sequence from the high to the low corresponding to the first regulation and control values to generate priorities, and outputting corresponding early warning signals.
CN202310382124.XA 2023-04-12 2023-04-12 Engineering implementation visual management system and method based on BIM technology Active CN116109042B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310382124.XA CN116109042B (en) 2023-04-12 2023-04-12 Engineering implementation visual management system and method based on BIM technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310382124.XA CN116109042B (en) 2023-04-12 2023-04-12 Engineering implementation visual management system and method based on BIM technology

Publications (2)

Publication Number Publication Date
CN116109042A true CN116109042A (en) 2023-05-12
CN116109042B CN116109042B (en) 2023-07-28

Family

ID=86256505

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310382124.XA Active CN116109042B (en) 2023-04-12 2023-04-12 Engineering implementation visual management system and method based on BIM technology

Country Status (1)

Country Link
CN (1) CN116109042B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117786099A (en) * 2024-02-27 2024-03-29 中建安装集团有限公司 Engineering technical data informatization management system and method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20170035682A (en) * 2015-09-23 2017-03-31 현대건설주식회사 Construction work management system based on BIM and management method of the same
CN113377880A (en) * 2021-05-14 2021-09-10 华仁建设集团有限公司 Building model automatic matching method and system based on BIM
CN113626920A (en) * 2021-08-12 2021-11-09 浙江大学 Engineering monitoring management system based on BIM +5G technology
CN115187214A (en) * 2022-07-20 2022-10-14 中铁十一局集团有限公司 BIM-based three-dimensional visualization image progress system and manufacturing method
CN115270277A (en) * 2022-08-24 2022-11-01 深圳艺洲建筑工程设计有限公司 Building design method based on BIM
CN115358721A (en) * 2022-08-30 2022-11-18 中新华都国际工程咨询有限公司 Engineering supervision information supervision system and method based on big data
WO2022257099A1 (en) * 2021-06-09 2022-12-15 青岛理工大学 Prefabricated building intelligent drawing output method based on bim

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20170035682A (en) * 2015-09-23 2017-03-31 현대건설주식회사 Construction work management system based on BIM and management method of the same
CN113377880A (en) * 2021-05-14 2021-09-10 华仁建设集团有限公司 Building model automatic matching method and system based on BIM
WO2022257099A1 (en) * 2021-06-09 2022-12-15 青岛理工大学 Prefabricated building intelligent drawing output method based on bim
CN113626920A (en) * 2021-08-12 2021-11-09 浙江大学 Engineering monitoring management system based on BIM +5G technology
CN115187214A (en) * 2022-07-20 2022-10-14 中铁十一局集团有限公司 BIM-based three-dimensional visualization image progress system and manufacturing method
CN115270277A (en) * 2022-08-24 2022-11-01 深圳艺洲建筑工程设计有限公司 Building design method based on BIM
CN115358721A (en) * 2022-08-30 2022-11-18 中新华都国际工程咨询有限公司 Engineering supervision information supervision system and method based on big data

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
HIYAMA,K等: ""A new nethod for reusing building information models of past projects to optimize the default configuration for performance simulations"", 《ENERGY AND BUILDINGS》, vol. 73 *
王蒙蒙: "基于深度学习的BIM构件搭配推荐方法研究", 《中国优秀硕士学位论文全文数据库(工程科技Ⅱ辑)》, no. 2 *
郭红领;潘在怡;: "BIM辅助施工管理的模式及流程", 清华大学学报(自然科学版), no. 10 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117786099A (en) * 2024-02-27 2024-03-29 中建安装集团有限公司 Engineering technical data informatization management system and method
CN117786099B (en) * 2024-02-27 2024-04-26 中建安装集团有限公司 Engineering technical data informatization management system and method

Also Published As

Publication number Publication date
CN116109042B (en) 2023-07-28

Similar Documents

Publication Publication Date Title
CN114511202A (en) BIM-based full-period engineering project management method and platform
CN116109042B (en) Engineering implementation visual management system and method based on BIM technology
CN112258159B (en) BIM + GIS-based hydraulic structure management system and method
CN114626615A (en) Production process monitoring and management method and system
CN107516161A (en) A kind of project progress management-control method based on BIM
CN113760625B (en) Evaluation method and monitoring system for model predictive controller performance
CN115238430A (en) Infrastructure construction on-site monitoring system based on Internet of things
CN114896652B (en) Industrial building informatization control terminal based on BIM
CN116305797A (en) Construction risk assessment system based on BIM and multisource quality information fusion
CN115330180A (en) Engineering management and control method and device based on BIM (building information modeling)
CN115775068A (en) Nuclear power project progress monitoring method and system
CN113312736B (en) River network hydrodynamic simulation implementation method and system based on cloud platform
CN117151445B (en) Power grid dispatching knowledge graph management system and dynamic updating method thereof
CN114565312A (en) Power transmission and transformation project refined construction management method based on BIM
CN109447466A (en) A kind of overall process visualization managing and control system based on Distribution Network Communication network construction
Zhang et al. Research on construction schedule control based on critical chain method and BIM
CN115345078B (en) Cable management method and device based on cable iteration model
CN116071048A (en) Intelligent operation and maintenance management system and method
CN115952989A (en) Natural disaster emergency scheduling system based on digital twins
CN115861557A (en) Urban rail transit monitoring method, system and medium based on BIM + three-dimensional scanning assistance
CN112257165B (en) Power transformation engineering research and artificial intelligence auxiliary examination method
CN111852466A (en) Method for shale gas well scale production allocation and pipe network operation optimization
CN113986380A (en) Data processing method, device and system, electronic equipment and storage medium
CN112202861A (en) Hydropower engineering method management application system based on BIM
CN110555218A (en) Production model update system, apparatus, method, and computer-readable medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant