CN106803150A - Municipal Engineering Construction progress msg management method and system based on BIM - Google Patents
Municipal Engineering Construction progress msg management method and system based on BIM Download PDFInfo
- Publication number
- CN106803150A CN106803150A CN201710041846.3A CN201710041846A CN106803150A CN 106803150 A CN106803150 A CN 106803150A CN 201710041846 A CN201710041846 A CN 201710041846A CN 106803150 A CN106803150 A CN 106803150A
- Authority
- CN
- China
- Prior art keywords
- bim
- construction
- progress
- module
- bim models
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063116—Schedule adjustment for a person or group
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/90—Details of database functions independent of the retrieved data types
- G06F16/904—Browsing; Visualisation therefor
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Theoretical Computer Science (AREA)
- Economics (AREA)
- Databases & Information Systems (AREA)
- Strategic Management (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Entrepreneurship & Innovation (AREA)
- Game Theory and Decision Science (AREA)
- Educational Administration (AREA)
- Development Economics (AREA)
- Data Mining & Analysis (AREA)
- General Engineering & Computer Science (AREA)
- Marketing (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention provides a kind of Municipal Engineering Construction progress msg management method based on BIM,When BIM models are set up,Urban geography position coordinates is converted to the position coordinates being mutually equal to project basic point in modeling software first,Then BIM models are set up under unified basic point,Therefore,BIM models are combined with the geographical position in city,More can intuitively reflect construction work overview,Coding numbering is carried out to BIM models,Establishment construction schedule,Construction schedule is divided into multiple operations and is numbered,And associated with the coding numbering of BIM models,So that it is determined that plan engineering time of each component in BIM models,By typing practice of construction progress,Practice of construction progress is contrasted with the construction speed of plan,And enter shape with various exhibition methods to show and analysis,The progress msg for comprehensively understanding construction work more directly perceived.
Description
Technical field
The invention belongs to Municipal Engineering Construction technical field, and in particular to a kind of Municipal Engineering Construction progress based on BIM
Approaches to IM and system.
Background technology
The construction project time management of engineering project is the important step of project management, and traditional progress control method information is stagnant
Afterwards, the features such as level of informatization is relatively low, the development of engineering constraint progress control level.BIM, abbreviation BIM
(building information modeling), BIM technology has the features such as informationization, visualization, the construction based on BIM
Application of the progress msg management mode in municipal works improves the whole of engineering to lifting the managerial skills of such engineering
Body value is significant.
In the prior art, although there is also some construction project time management methods, but these methods are for a certain spy
Determine the solution of engineering customization, engineering project can only be reflected in itself in scheme, actual city coordinate can not be combined.Due to
Municipal works are closely related with daily life, and the influence journey to daily life is should be taken into account in work progress
Degree, when construction plan is formulated, should formulate rational scheme, and energy according to the daily life of construction surrounding resident and pedestrian
It is enough intuitively to show, therefore, there is presently no the related public technology suitable for municipal works.Also, prior art is being based on
In the Municipal Engineering Construction progress msgization management of BIM, the establishment to BIM models, BIM models are associated with WBS can not be met
The requirement of municipal works progress control, and it is too single with analysis to information displaying, it is impossible to staff is met to construction work
The requirement of the information management of journey.
The content of the invention
The present invention is carried out to solve the above problems, it is therefore intended that is provided one kind and is entered suitable for Municipal Engineering Construction
Degree information management, and can intuitively, it is many analysis with displaying Municipal Engineering Construction progress the municipal works based on BIM
Construction speed approaches to IM and system.
The invention provides a kind of Municipal Engineering Construction progress msg management method based on BIM, it is characterised in that including
Following steps:Step 1, builds BIM models, comprises the following steps:
Step 1-1, project basic point unification, the geographical position coordinates in city is converted, with the item in BIM MBMs
Mesh basic point coordinate unification,
Step 1-2, BIM model creation, each Professional Model is created under unified basic point coordinate,
Step 1-3, model based coding is carried out to BIM models,
Step 2, works out construction schedule, and the BIM models that step 1 is set up are associated with construction schedule, described to apply
Work schedule is divided into multiple operations according to the task of engineering, and each operation is numbered, operation numbering with it is corresponding
BIM models model based coding be associated,
Step 3, the incidence relation between BIM models, construction schedule, BIM models and construction plan is stored,
Step 4, the actual progress of typing construction process, system is compared actual progress with construction schedule
Compared with,
Step 5, is respectively adopted vivid progress display, progress backtracking, Gantt chart and Report Server Management and construction speed information is entered
Row displaying and analysis.
Further, in the Municipal Engineering Construction progress msg management method based on BIM that the present invention is provided, can also have
There is such feature:Wherein, vivid progress display:Respectively with engineering project beginning and ending time and actual beginning and ending time as foundation,
On BIM models task and unfinished task have been completed with two kinds of color marks.
Further, in the Municipal Engineering Construction progress msg management method based on BIM that the present invention is provided, can also have
There is such feature:Wherein, the progress recalls the construction figure progress for checking any date, and the time is set comprising module
Axle, the module on time shaft can arbitrarily be dragged in construction period, by dragging the module on time shaft, can check any
The construction figure progress on date.
Further, in the Municipal Engineering Construction progress msg management method based on BIM that the present invention is provided, can also have
There is such feature:Wherein, Gantt chart is used to show the contrast situation of target advance and actual progress.
Further, in the Municipal Engineering Construction progress msg pipe physico-chemical method based on BIM that the present invention is provided, can be with
Have the feature that:Wherein, the list of engineering that progress report is completed comprising completed works inventory and next cycle planning.
Built according to above-mentioned Municipal Engineering Construction progress msg management method based on BIM present invention also offers a kind of
System, it is characterised in that:Including:Construction data initialization module, comprising:BIM MBMs, modular converter and coding module,
The BIM MBMs are used to build the BIM models of engineering, and the modular converter is used to convert the geographical position coordinates in city
It is to be used to enter on the BIM models that the BIM MBMs build with identical unit in BIM MBMs, the coding module
Row model based coding, the operation of construction schedule is numbered;Relating module, for by construction schedule and BIM models
It is associated;Input module, the actual progress for being input into construction schedule, input work progress;Memory module, for depositing
Store up the incidence relation between the BIM models, the construction schedule, the BIM models and construction schedule, constructed
The actual progress of journey;Display module, comprising:For having been completed task and not completed with two kinds of color marks on BIM models to appoint
The vivid progress display module of business, for check the progress backtracking module of the construction figure progress on any date in construction period,
For with the gunter module of gunter diagram form displaying target advance and the contrast situation of actual progress and for form
Pattern displaying has completed list of engineering and lower cycle planning completes the statement management module of inventory.
Advantages of the present invention is as follows:
According to the Municipal Engineering Construction progress msg management method based on BIM involved in the present invention, BIM models are being set up
When, urban geography position coordinates is converted to the position coordinates being mutually equal to project basic point in modeling software first, then in system
BIM models are set up under one basic point, therefore, BIM models are combined with the geographical position in city, more can intuitively reflect construction work
Journey overview, coding numbering is carried out to BIM models, works out construction schedule, and construction schedule is divided into multiple operations simultaneously
Numbering, and associate with the coding of BIM models numbering, so that it is determined that the plan engineering time of each component in BIM models, logical
Typing practice of construction progress is crossed, practice of construction progress is contrasted with the construction speed of plan, and use various exhibition methods
Enter shape displaying and analysis, the progress msg for comprehensively understanding construction work more directly perceived.Municipal works based on BIM of the invention
Construction speed approaches to IM suitable for Municipal Engineering Construction progress msg manage, and can intuitively, many analyses
With displaying Municipal Engineering Construction progress.
The present invention provide message tube physics and chemistry system, by essential information input system after, can intuitively, comprehensively will construction
The information of engineering shows staff, improves the managerial skills of engineering.
Brief description of the drawings
Fig. 1 is the flow chart of the Municipal Engineering Construction progress msg management method based on BIM in the present invention;
The flow chart of BIM models is built during Fig. 2 in the present invention;
Fig. 3 is the structural representation of information management system in the present invention.
Specific embodiment
In order that technological means, creation characteristic, reached purpose and effect that the present invention is realized are easy to understand, it is real below
Example combination accompanying drawing is applied to be specifically addressed Municipal Engineering Construction progress msg managementization method and system of the present invention based on BIM.
As shown in figure 1, in the present embodiment, the Municipal Engineering Construction progress msg management method based on BIM is comprising following
Step:
Step S1, builds BIM models, as shown in Fig. 2 comprising the following steps:
Step S1-1, the unification of project basic point, in BIM modeling softwares, each model, structure, position coordinates are measured with millimeter,
The geographical position coordinates in city are measured with km, therefore need to be converted the geographical position coordinates in city, it is modeled with BIM
Project basic point coordinate unification in module.
Step S1-2, BIM model creation, each Professional Model is created under unified basic point coordinate.The fineness that model splits
Meet the fineness requirement of Engineering Construction Management, the material of model meets difference requirement clearly demarcated, elegant in appearance.
Step S1-3, model based coding numbering is carried out to BIM models.By BIM models according to Engineering Speciality, section partition, work
Journey scale etc. carries out differentiation establishment, and uniqueness is respectively provided with comprising each numbering in numbering, and each numbering represents BIM models
In certain component, numbering is comprising position coordinates, element type etc..Numbering can as engineering foundation information, construction speed information,
The label of retrieval.
Step S2, establishment construction schedule (Work Break Structure, abbreviation WBS), step 1 is set up
BIM models are associated with WBS.Wherein, WBS is divided into multiple operations according to the task of engineering, and each operation is numbered, and gives
The working time of fixed each operation.The model based coding numbering numbered on unique, BIM models of each operation of WBS is unique, by work
Sequence is numbered to be associated with the model based coding numbering of corresponding BIM models, sets up logical relation.
Step S3, the incidence relation between BIM models, construction schedule, BIM models and construction plan is deposited
Storage.
Step S4, the actual progress of typing construction process, system is compared actual progress with construction schedule
Compared with.The actual progress of construction process is by Data Collection, data screening, data according to the progress msg to engineering site
Record obtains actual progress information.
Step S5, is respectively adopted vivid progress display, progress backtracking, Gantt chart and Report Server Management and construction speed information is entered
Row displaying and analysis.Using various displayings and analysis method, so that staff can more fully understand construction work
Information.
Vivid progress display:Respectively with engineering project beginning and ending time and actual beginning and ending time as foundation, on BIM models
Task and unfinished task have been completed with two kinds of color marks.Can intuitively show engineering in construction speed on threedimensional model
Progress under plan, and the progress in the case of practice of construction progress.
Progress recalls the construction figure progress for checking any date in construction period, with BIM models as object, comprising
Module sets time shaft, and the module on time shaft can arbitrarily be dragged in construction period, by dragging the module on time shaft,
The construction figure progress on any date can be checked.
Gantt chart is used to show the contrast situation of target advance and actual progress, can intuitively find out engineering actual development with
The difference of target advance.
The list of engineering that progress report is completed comprising completed works inventory and next cycle planning.According to progress report
Style, the list of engineering that generation is completed with the list of engineering for completing and next cycle planning.In the present embodiment, data in form
Classification statistics is carried out according to work area, element type.
A kind of message tube physics and chemistry system 100, including:Construction data initialization module 10, relating module 20, input module
30th, memory module 40 and display module 50.
Construction data initialization module 10 is included:BIM MBMs 11, modular converter 12 and coding module 13.BIM is modeled
Module 11 is used to build the BIM models of engineering.Modular converter 12 is used to be converted into the geographical position coordinates in city and BIM modelings
Identical unit in module.Coding module 13 is used to for the BIM models that BIM MBMs build to carry out model based coding, will construct
The operation of schedule is numbered.
Relating module 20 is used to be associated construction schedule with BIM models.
Input module 30 is used to be input into construction schedule, the actual progress of input work progress.
Memory module 40 is used to store the pass between BIM models, construction schedule, BIM models and construction schedule
The actual progress of connection relation, work progress.
Display module 50 is included:Vivid progress display module 51, progress backtracking module 52, gunter module 53, Yi Jibao
Table management module 54.
Vivid progress display module 51 is used on BIM models completed task and not completed with two kinds of color marks to appoint
Business.
Progress backtracking module 52 is used to check the construction figure progress on any date in construction period.
Gunter module 53 is used for the contrast situation with actual progress with gunter diagram form displaying target advance.
Statement management module 54 is used to complete list of engineering with the pattern displaying of form and lower cycle planning completes inventory.
Above-mentioned implementation method is preferred case of the invention, is not intended to limit protection scope of the present invention.
Claims (6)
1. a kind of Municipal Engineering Construction progress msg management method based on BIM, it is characterised in that comprise the following steps:
Step 1, builds BIM models, comprises the following steps:
Step 1-1, project basic point unification, the geographical position coordinates in city is converted, with the project base in BIM MBMs
Point coordinates is unified,
Step 1-2, BIM model creation, each Professional Model is created under unified basic point coordinate,
Step 1-3, model based coding is carried out to BIM models,
Step 2, works out construction schedule, and the BIM models that step 1 is set up associate with construction schedule, it is described construct into
Degree plan is divided into multiple operations according to the task of engineering, and each operation is numbered, and operation is numbered and corresponding BIM
The model based coding of model is associated,
Step 3, the incidence relation between BIM models, construction schedule, BIM models and construction plan is stored,
With construction schedule be compared actual progress by step 4, the actual progress of typing construction process, system,
Step 5, is respectively adopted vivid progress display, progress backtracking, Gantt chart and Report Server Management and construction speed information is opened up
Show and analysis.
2. the Municipal Engineering Construction progress msg management method based on BIM according to claim 1, it is characterised in that:
Wherein, the vivid progress display:Respectively with engineering project beginning and ending time and actual beginning and ending time as foundation, in BIM
On model task and unfinished task have been completed with two kinds of color marks.
3. the Municipal Engineering Construction progress msg management method based on BIM according to claim 1, it is characterised in that:
Wherein, the progress recalls the construction figure progress for checking any date, and time shaft, time shaft are set comprising module
On module can arbitrarily be dragged in construction period, by dragging the module on time shaft, applying for any date can be checked
Work image progress.
4. the Municipal Engineering Construction progress msg management method based on BIM according to claim 1, it is characterised in that:
Wherein, the Gantt chart is used to show the contrast situation of target advance and actual progress.
5. the Municipal Engineering Construction progress msg management method based on BIM according to claim 1, it is characterised in that:
Wherein, the list of engineering that the progress report is completed comprising completed works inventory and next cycle planning.
6. a kind of structure of the Municipal Engineering Construction progress msg management method based on BIM according to claim 1 to 5 is
System, it is characterised in that including:
Construction data initialization module, comprising:BIM MBMs, modular converter and coding module, the BIM MBMs are used
In build engineering BIM models, the modular converter be used for by the geographical position coordinates in city be converted into in BIM MBMs
Identical unit, the coding module is used to for the BIM models that the BIM MBMs build to carry out model based coding, will construct
The operation of schedule is numbered;
Relating module, for construction schedule to be associated with BIM models;
Input module, the actual progress for being input into construction schedule, input work progress;
Memory module, for store the BIM models, the construction schedule, the BIM models and construction schedule it
Between incidence relation, the actual progress of work progress;
Display module, comprising:For having completed task with two kinds of color marks on BIM models and abortive image is entered
Degree display module, for checking the progress backtracking module of the construction figure progress on any date in construction period, for gunter
Diagram form shows target advance with the gunter module of the contrast situation of actual progress and for the pattern displaying with form
Complete list of engineering and lower cycle planning completes the statement management module of inventory.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710041846.3A CN106803150A (en) | 2017-01-20 | 2017-01-20 | Municipal Engineering Construction progress msg management method and system based on BIM |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710041846.3A CN106803150A (en) | 2017-01-20 | 2017-01-20 | Municipal Engineering Construction progress msg management method and system based on BIM |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106803150A true CN106803150A (en) | 2017-06-06 |
Family
ID=58986942
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710041846.3A Pending CN106803150A (en) | 2017-01-20 | 2017-01-20 | Municipal Engineering Construction progress msg management method and system based on BIM |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106803150A (en) |
Cited By (50)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107368972A (en) * | 2017-07-25 | 2017-11-21 | 中建安装工程有限公司 | It is a kind of that work platform and its application method are sent based on BIM technology |
CN107516161A (en) * | 2017-08-03 | 2017-12-26 | 中国建筑第五工程局有限公司 | A kind of project progress management-control method based on BIM |
CN107563703A (en) * | 2017-09-22 | 2018-01-09 | 熊志军 | A kind of method and system of material information management |
CN107679310A (en) * | 2017-09-26 | 2018-02-09 | 华北电力大学 | The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology |
CN107688908A (en) * | 2017-09-06 | 2018-02-13 | 北京城乡建设集团有限责任公司 | Study and judge the method and device of construction safety risk |
CN107798194A (en) * | 2017-10-30 | 2018-03-13 | 毕埃慕(上海)建筑数据技术股份有限公司 | The analogy method and device of engineering construction |
CN107818430A (en) * | 2017-12-15 | 2018-03-20 | 武汉理工大学 | A kind of building engineering construction progress msg management method and system based on BIM |
CN108009758A (en) * | 2018-01-09 | 2018-05-08 | 中建七局安装工程有限公司 | A kind of site operation material intelligent management based on BIM |
CN108229923A (en) * | 2018-01-29 | 2018-06-29 | 联合建管(北京)国际工程科技有限责任公司 | The methods of exhibiting and device of continuous type project schedule plan |
CN108256213A (en) * | 2018-01-16 | 2018-07-06 | 中铁局集团有限公司 | Depot of urban railway transit vehicles modular construction analogy method based on VR and BIM |
CN108537462A (en) * | 2018-04-17 | 2018-09-14 | 万翼科技有限公司 | Confirmation method, device, computer readable storage medium and the system of project process |
CN108681879A (en) * | 2018-05-24 | 2018-10-19 | 广州市建筑科学研究院有限公司 | A kind of filling pile construction management method and system based on BIM technology |
CN109190962A (en) * | 2018-08-24 | 2019-01-11 | 北京中联环建设工程管理有限公司 | Project process supervision control system |
CN109360123A (en) * | 2018-10-22 | 2019-02-19 | 上海建工四建集团有限公司 | A kind of multi-specialized execution management method therefor and system based on room |
CN109446668A (en) * | 2018-10-31 | 2019-03-08 | 广西路桥工程集团有限公司 | A kind of component Schedule monitoring system and method based on threedimensional model |
CN109522661A (en) * | 2018-11-23 | 2019-03-26 | 上海蓝色星球科技股份有限公司 | A kind of Building Information Model component and work breakdown structure (WBS) correlating method and system |
CN109685479A (en) * | 2018-12-29 | 2019-04-26 | 中铁十九局集团第六工程有限公司 | A kind of methods of exhibiting, computer installation and the computer readable storage medium of construction tunnel progress |
CN109872127A (en) * | 2019-02-01 | 2019-06-11 | 重庆工商职业学院 | Building intelligence builds progress control method |
CN109886838A (en) * | 2019-01-29 | 2019-06-14 | 杭州凌望建筑科技有限公司 | Smart city operation management platform based on CIM |
CN110084526A (en) * | 2019-05-05 | 2019-08-02 | 广西路桥工程集团有限公司 | A kind of visualization project management monitoring system based on BIM+WBS |
CN110119565A (en) * | 2019-05-08 | 2019-08-13 | 中铁八局集团建筑工程有限公司 | A method of quick association and displaying based on BIM model and project programme |
CN110428176A (en) * | 2019-08-05 | 2019-11-08 | 中国电力企业联合会电力建设技术经济咨询中心 | Project progress checking method and system |
CN110505452A (en) * | 2019-08-26 | 2019-11-26 | 广东电网有限责任公司 | A kind of capital construction power transmission engineering Schedule monitoring method and monitoring system |
CN110555661A (en) * | 2018-05-31 | 2019-12-10 | 西安海平方网络科技有限公司 | information display method, device and equipment of building element and readable storage medium |
CN110580267A (en) * | 2019-09-23 | 2019-12-17 | 重庆渝高科技产业(集团)股份有限公司 | engineering information display control method for urban engineering management |
CN110599027A (en) * | 2019-09-09 | 2019-12-20 | 中铁建设集团有限公司 | Method for automatically acquiring progress data of BIM platform by using weighbridge weighing system |
CN110598260A (en) * | 2019-08-16 | 2019-12-20 | 南京紫城工程设计有限公司 | Municipal engineering design system based on BIM technology |
CN110852696A (en) * | 2019-10-08 | 2020-02-28 | 上海建工五建集团有限公司 | Project progress monitoring method and system |
CN110942239A (en) * | 2019-11-21 | 2020-03-31 | 中国电力企业联合会电力建设技术经济咨询中心 | Automatic inspection method and device for actual engineering progress |
CN110968751A (en) * | 2019-11-29 | 2020-04-07 | 中国电力企业联合会电力建设技术经济咨询中心 | Dynamic display method and device for engineering project capital curve |
CN111080239A (en) * | 2019-11-29 | 2020-04-28 | 中国电力企业联合会电力建设技术经济咨询中心 | Real-time dynamic tracking method and device for construction cost |
CN111429097A (en) * | 2020-03-24 | 2020-07-17 | 上海捷规建筑工程咨询有限公司 | BIM-based automatic matching method and system for field progress and model |
CN111506949A (en) * | 2020-04-10 | 2020-08-07 | 中国电建集团昆明勘测设计研究院有限公司 | BIM-based visualization method for road soft foundation treatment construction progress |
CN111754138A (en) * | 2020-07-07 | 2020-10-09 | 天津水泥工业设计研究院有限公司 | Engineering construction progress plan management and control system and method based on BIM model |
CN111815235A (en) * | 2020-07-01 | 2020-10-23 | 中国电建集团华东勘测设计研究院有限公司 | Engineering material management and control method and device based on BIM, storage medium and computer equipment |
CN111899343A (en) * | 2020-07-02 | 2020-11-06 | 广州市第一市政工程有限公司 | Traffic dispersion method in municipal engineering based on BIM technology |
CN111967837A (en) * | 2020-07-16 | 2020-11-20 | 译筑信息科技(上海)有限公司 | BIM-based assembly type component construction process control method and system |
CN112100725A (en) * | 2020-09-18 | 2020-12-18 | 中国电建集团华东勘测设计研究院有限公司 | Engineering whole-element process information display method based on BIM (building information modeling) model and crosswalk diagram |
CN112488663A (en) * | 2020-12-14 | 2021-03-12 | 广西路桥工程集团有限公司 | Progress management system based on WBS |
CN112486613A (en) * | 2020-11-27 | 2021-03-12 | 东南大学 | Engineering project Web end construction progress management method and device and readable storage medium |
CN112541733A (en) * | 2020-12-12 | 2021-03-23 | 中冶天工集团有限公司 | Engineering construction stage management control method based on BIM |
CN112581030A (en) * | 2020-12-29 | 2021-03-30 | 基建通(三亚)国际科技有限公司 | Bridge BIM model component level progress display method and device and storage medium |
CN112613109A (en) * | 2021-01-04 | 2021-04-06 | 中国铁道科学研究院集团有限公司电子计算技术研究所 | Construction progress and cost management method and device of railway BIM system based on web real-time modeling |
CN113538661A (en) * | 2021-07-06 | 2021-10-22 | 万翼科技有限公司 | Information display method based on building model and related device |
CN113609550A (en) * | 2021-07-05 | 2021-11-05 | 江苏徐工工程机械研究院有限公司 | BIM-based construction process planning management method and system |
CN113673899A (en) * | 2021-08-28 | 2021-11-19 | 江苏苏科建设项目管理有限公司 | Road engineering progress management method based on supervision cloud system |
CN114282909A (en) * | 2022-01-04 | 2022-04-05 | 中广核工程有限公司 | Nuclear power facility installation progress monitoring method and system, electronic equipment and nuclear power project progress monitoring method |
CN114418279A (en) * | 2021-12-07 | 2022-04-29 | 中国电建集团华东勘测设计研究院有限公司 | BIM model-based visual management method for progress and cost of whole construction process |
CN115878872A (en) * | 2023-02-08 | 2023-03-31 | 一智科技(成都)有限公司 | Construction progress visualization method and system |
CN118194399A (en) * | 2024-03-15 | 2024-06-14 | 中交三航局第九工程有限公司 | Overpass bridge construction progress management method based on illusion engine BIM technology |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104766182A (en) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | Intelligent monitoring system for building design construction based on BIM |
CN105335559A (en) * | 2015-10-28 | 2016-02-17 | 上海同筑信息科技有限公司 | Engineering standardized construction process control method and system on basis of BIM (building information modeling) |
KR101648027B1 (en) * | 2016-01-04 | 2016-08-17 | (주) 한길아이티 | Building information modeling design collaboration device |
CN105976089A (en) * | 2016-04-27 | 2016-09-28 | 中交第二航务工程局有限公司 | Construction data classification system based on building information model and method thereof |
CN106339820A (en) * | 2016-08-31 | 2017-01-18 | 中国电建集团昆明勘测设计研究院有限公司 | Virtual reality-based hydraulic structure actual measurement performance multi-dimensional analysis method and system |
-
2017
- 2017-01-20 CN CN201710041846.3A patent/CN106803150A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104766182A (en) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | Intelligent monitoring system for building design construction based on BIM |
CN105335559A (en) * | 2015-10-28 | 2016-02-17 | 上海同筑信息科技有限公司 | Engineering standardized construction process control method and system on basis of BIM (building information modeling) |
KR101648027B1 (en) * | 2016-01-04 | 2016-08-17 | (주) 한길아이티 | Building information modeling design collaboration device |
CN105976089A (en) * | 2016-04-27 | 2016-09-28 | 中交第二航务工程局有限公司 | Construction data classification system based on building information model and method thereof |
CN106339820A (en) * | 2016-08-31 | 2017-01-18 | 中国电建集团昆明勘测设计研究院有限公司 | Virtual reality-based hydraulic structure actual measurement performance multi-dimensional analysis method and system |
Cited By (57)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107368972A (en) * | 2017-07-25 | 2017-11-21 | 中建安装工程有限公司 | It is a kind of that work platform and its application method are sent based on BIM technology |
CN107516161A (en) * | 2017-08-03 | 2017-12-26 | 中国建筑第五工程局有限公司 | A kind of project progress management-control method based on BIM |
CN107688908A (en) * | 2017-09-06 | 2018-02-13 | 北京城乡建设集团有限责任公司 | Study and judge the method and device of construction safety risk |
CN107563703A (en) * | 2017-09-22 | 2018-01-09 | 熊志军 | A kind of method and system of material information management |
CN107679310A (en) * | 2017-09-26 | 2018-02-09 | 华北电力大学 | The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology |
CN107798194A (en) * | 2017-10-30 | 2018-03-13 | 毕埃慕(上海)建筑数据技术股份有限公司 | The analogy method and device of engineering construction |
CN107818430A (en) * | 2017-12-15 | 2018-03-20 | 武汉理工大学 | A kind of building engineering construction progress msg management method and system based on BIM |
CN108009758B (en) * | 2018-01-09 | 2022-04-15 | 中建七局安装工程有限公司 | BIM-based intelligent management method for field construction materials |
CN108009758A (en) * | 2018-01-09 | 2018-05-08 | 中建七局安装工程有限公司 | A kind of site operation material intelligent management based on BIM |
CN108256213A (en) * | 2018-01-16 | 2018-07-06 | 中铁局集团有限公司 | Depot of urban railway transit vehicles modular construction analogy method based on VR and BIM |
CN108229923A (en) * | 2018-01-29 | 2018-06-29 | 联合建管(北京)国际工程科技有限责任公司 | The methods of exhibiting and device of continuous type project schedule plan |
CN108537462A (en) * | 2018-04-17 | 2018-09-14 | 万翼科技有限公司 | Confirmation method, device, computer readable storage medium and the system of project process |
CN108681879A (en) * | 2018-05-24 | 2018-10-19 | 广州市建筑科学研究院有限公司 | A kind of filling pile construction management method and system based on BIM technology |
CN110555661A (en) * | 2018-05-31 | 2019-12-10 | 西安海平方网络科技有限公司 | information display method, device and equipment of building element and readable storage medium |
CN109190962A (en) * | 2018-08-24 | 2019-01-11 | 北京中联环建设工程管理有限公司 | Project process supervision control system |
CN109360123A (en) * | 2018-10-22 | 2019-02-19 | 上海建工四建集团有限公司 | A kind of multi-specialized execution management method therefor and system based on room |
CN109446668A (en) * | 2018-10-31 | 2019-03-08 | 广西路桥工程集团有限公司 | A kind of component Schedule monitoring system and method based on threedimensional model |
CN109522661A (en) * | 2018-11-23 | 2019-03-26 | 上海蓝色星球科技股份有限公司 | A kind of Building Information Model component and work breakdown structure (WBS) correlating method and system |
CN109685479A (en) * | 2018-12-29 | 2019-04-26 | 中铁十九局集团第六工程有限公司 | A kind of methods of exhibiting, computer installation and the computer readable storage medium of construction tunnel progress |
CN109886838A (en) * | 2019-01-29 | 2019-06-14 | 杭州凌望建筑科技有限公司 | Smart city operation management platform based on CIM |
CN109872127A (en) * | 2019-02-01 | 2019-06-11 | 重庆工商职业学院 | Building intelligence builds progress control method |
CN110084526A (en) * | 2019-05-05 | 2019-08-02 | 广西路桥工程集团有限公司 | A kind of visualization project management monitoring system based on BIM+WBS |
CN110084526B (en) * | 2019-05-05 | 2022-05-31 | 广西路桥工程集团有限公司 | BIM + WBS-based visual project management monitoring system |
CN110119565A (en) * | 2019-05-08 | 2019-08-13 | 中铁八局集团建筑工程有限公司 | A method of quick association and displaying based on BIM model and project programme |
CN110428176A (en) * | 2019-08-05 | 2019-11-08 | 中国电力企业联合会电力建设技术经济咨询中心 | Project progress checking method and system |
CN110428176B (en) * | 2019-08-05 | 2020-10-30 | 中国电力企业联合会电力建设技术经济咨询中心 | Project progress auditing method and system |
CN110598260A (en) * | 2019-08-16 | 2019-12-20 | 南京紫城工程设计有限公司 | Municipal engineering design system based on BIM technology |
CN110505452A (en) * | 2019-08-26 | 2019-11-26 | 广东电网有限责任公司 | A kind of capital construction power transmission engineering Schedule monitoring method and monitoring system |
CN110599027A (en) * | 2019-09-09 | 2019-12-20 | 中铁建设集团有限公司 | Method for automatically acquiring progress data of BIM platform by using weighbridge weighing system |
CN110580267A (en) * | 2019-09-23 | 2019-12-17 | 重庆渝高科技产业(集团)股份有限公司 | engineering information display control method for urban engineering management |
CN110852696A (en) * | 2019-10-08 | 2020-02-28 | 上海建工五建集团有限公司 | Project progress monitoring method and system |
CN110942239A (en) * | 2019-11-21 | 2020-03-31 | 中国电力企业联合会电力建设技术经济咨询中心 | Automatic inspection method and device for actual engineering progress |
CN110968751A (en) * | 2019-11-29 | 2020-04-07 | 中国电力企业联合会电力建设技术经济咨询中心 | Dynamic display method and device for engineering project capital curve |
CN111080239A (en) * | 2019-11-29 | 2020-04-28 | 中国电力企业联合会电力建设技术经济咨询中心 | Real-time dynamic tracking method and device for construction cost |
CN111080239B (en) * | 2019-11-29 | 2021-03-26 | 中国电力企业联合会电力建设技术经济咨询中心 | Real-time dynamic tracking method and device for construction cost |
CN111429097A (en) * | 2020-03-24 | 2020-07-17 | 上海捷规建筑工程咨询有限公司 | BIM-based automatic matching method and system for field progress and model |
CN111429097B (en) * | 2020-03-24 | 2024-03-05 | 上海捷规建筑工程咨询有限公司 | BIM-based automatic field progress and model matching method and system |
CN111506949A (en) * | 2020-04-10 | 2020-08-07 | 中国电建集团昆明勘测设计研究院有限公司 | BIM-based visualization method for road soft foundation treatment construction progress |
CN111815235A (en) * | 2020-07-01 | 2020-10-23 | 中国电建集团华东勘测设计研究院有限公司 | Engineering material management and control method and device based on BIM, storage medium and computer equipment |
CN111899343A (en) * | 2020-07-02 | 2020-11-06 | 广州市第一市政工程有限公司 | Traffic dispersion method in municipal engineering based on BIM technology |
CN111754138B (en) * | 2020-07-07 | 2021-07-23 | 天津水泥工业设计研究院有限公司 | Engineering construction progress plan management and control system and method based on BIM model |
CN111754138A (en) * | 2020-07-07 | 2020-10-09 | 天津水泥工业设计研究院有限公司 | Engineering construction progress plan management and control system and method based on BIM model |
CN111967837A (en) * | 2020-07-16 | 2020-11-20 | 译筑信息科技(上海)有限公司 | BIM-based assembly type component construction process control method and system |
CN112100725A (en) * | 2020-09-18 | 2020-12-18 | 中国电建集团华东勘测设计研究院有限公司 | Engineering whole-element process information display method based on BIM (building information modeling) model and crosswalk diagram |
CN112486613A (en) * | 2020-11-27 | 2021-03-12 | 东南大学 | Engineering project Web end construction progress management method and device and readable storage medium |
CN112541733A (en) * | 2020-12-12 | 2021-03-23 | 中冶天工集团有限公司 | Engineering construction stage management control method based on BIM |
CN112488663B (en) * | 2020-12-14 | 2022-06-21 | 广西路桥工程集团有限公司 | Progress management system based on WBS |
CN112488663A (en) * | 2020-12-14 | 2021-03-12 | 广西路桥工程集团有限公司 | Progress management system based on WBS |
CN112581030A (en) * | 2020-12-29 | 2021-03-30 | 基建通(三亚)国际科技有限公司 | Bridge BIM model component level progress display method and device and storage medium |
CN112613109A (en) * | 2021-01-04 | 2021-04-06 | 中国铁道科学研究院集团有限公司电子计算技术研究所 | Construction progress and cost management method and device of railway BIM system based on web real-time modeling |
CN113609550A (en) * | 2021-07-05 | 2021-11-05 | 江苏徐工工程机械研究院有限公司 | BIM-based construction process planning management method and system |
CN113538661A (en) * | 2021-07-06 | 2021-10-22 | 万翼科技有限公司 | Information display method based on building model and related device |
CN113673899A (en) * | 2021-08-28 | 2021-11-19 | 江苏苏科建设项目管理有限公司 | Road engineering progress management method based on supervision cloud system |
CN114418279A (en) * | 2021-12-07 | 2022-04-29 | 中国电建集团华东勘测设计研究院有限公司 | BIM model-based visual management method for progress and cost of whole construction process |
CN114282909A (en) * | 2022-01-04 | 2022-04-05 | 中广核工程有限公司 | Nuclear power facility installation progress monitoring method and system, electronic equipment and nuclear power project progress monitoring method |
CN115878872A (en) * | 2023-02-08 | 2023-03-31 | 一智科技(成都)有限公司 | Construction progress visualization method and system |
CN118194399A (en) * | 2024-03-15 | 2024-06-14 | 中交三航局第九工程有限公司 | Overpass bridge construction progress management method based on illusion engine BIM technology |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106803150A (en) | Municipal Engineering Construction progress msg management method and system based on BIM | |
CN102930374B (en) | A kind of system using three-dimensional model simulating reality to carry out project management | |
Kelly et al. | BIM for facility management: a review and a case study investigating the value and challenges | |
CN108038915A (en) | A kind of substation project progress msg visualization system based on WEB terminal three-dimensional simulation | |
Ivson et al. | A systematic review of visualization in building information modeling | |
US20060044307A1 (en) | System and method for visually representing project metrics on 3-dimensional building models | |
CN109190252A (en) | A kind of construction method based on R-N5DL-BIM technology | |
KR100844467B1 (en) | A simulation system and method for construction progression state with 3d | |
CN104008218A (en) | Electric power engineering three-dimensional integrated design platform | |
CN117173367B (en) | Method and equipment for establishing dynamic landscape plant component library based on Rhino | |
CN108053486A (en) | Construction method and system based on virtual technology | |
CN110990914A (en) | BIM technology-based large boiler installation method | |
CN108694260A (en) | Application process of the BIM technology in Steel Bridge processing and manufacturing | |
Žurić et al. | Integrating HBIM and sustainability certification: A pilot study using GBC historic building certification | |
CN108153572A (en) | GIS display methods, device and system | |
Alam et al. | EvoSpaces: 3D Visualization of Software Architecture. | |
CN102646286B (en) | Digital graph medium simulation method with three-dimensional space structure | |
Fassi et al. | Complex architecture in 3D: from survey to web | |
Abdelhai | Integration BIM and emerging technologies in architectural academic programs | |
CN110490980A (en) | A kind of Virtual Construction template information processing system and method based on fixation and recognition | |
Shariatpour et al. | Urban 3D Modeling as a Precursor of City Information Modeling and Digital Twin for Smart City Era: A Case Study of the Narmak Neighborhood of Tehran City, Iran | |
CN113496548A (en) | Transparent factory oriented production field data mapping method | |
Francis | A chronographic protocol for modelling construction projects | |
CN107133787A (en) | Highway project management method and system | |
Bansal et al. | Extended GIS for construction engineering by adding direct sunlight visualisations on buildings |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170606 |
|
WD01 | Invention patent application deemed withdrawn after publication |