CN106803150A - Municipal Engineering Construction progress msg management method and system based on BIM - Google Patents

Municipal Engineering Construction progress msg management method and system based on BIM Download PDF

Info

Publication number
CN106803150A
CN106803150A CN201710041846.3A CN201710041846A CN106803150A CN 106803150 A CN106803150 A CN 106803150A CN 201710041846 A CN201710041846 A CN 201710041846A CN 106803150 A CN106803150 A CN 106803150A
Authority
CN
China
Prior art keywords
bim
construction
progress
module
bim models
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710041846.3A
Other languages
Chinese (zh)
Inventor
巴雅吉呼
刘艳滨
张湄
严佳梁
孔祥平
段创峰
滕丽
顾沉颖
胡珉
喻钢
杨子松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai City Road Investment (group) Co Ltd
Shanghai Underground Space Architectural Design & Research Institute
University of Shanghai for Science and Technology
Original Assignee
Shanghai City Road Investment (group) Co Ltd
Shanghai Underground Space Architectural Design & Research Institute
University of Shanghai for Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai City Road Investment (group) Co Ltd, Shanghai Underground Space Architectural Design & Research Institute, University of Shanghai for Science and Technology filed Critical Shanghai City Road Investment (group) Co Ltd
Priority to CN201710041846.3A priority Critical patent/CN106803150A/en
Publication of CN106803150A publication Critical patent/CN106803150A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063116Schedule adjustment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/90Details of database functions independent of the retrieved data types
    • G06F16/904Browsing; Visualisation therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • Economics (AREA)
  • Databases & Information Systems (AREA)
  • Strategic Management (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Data Mining & Analysis (AREA)
  • General Engineering & Computer Science (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a kind of Municipal Engineering Construction progress msg management method based on BIM,When BIM models are set up,Urban geography position coordinates is converted to the position coordinates being mutually equal to project basic point in modeling software first,Then BIM models are set up under unified basic point,Therefore,BIM models are combined with the geographical position in city,More can intuitively reflect construction work overview,Coding numbering is carried out to BIM models,Establishment construction schedule,Construction schedule is divided into multiple operations and is numbered,And associated with the coding numbering of BIM models,So that it is determined that plan engineering time of each component in BIM models,By typing practice of construction progress,Practice of construction progress is contrasted with the construction speed of plan,And enter shape with various exhibition methods to show and analysis,The progress msg for comprehensively understanding construction work more directly perceived.

Description

Municipal Engineering Construction progress msg management method and system based on BIM
Technical field
The invention belongs to Municipal Engineering Construction technical field, and in particular to a kind of Municipal Engineering Construction progress based on BIM Approaches to IM and system.
Background technology
The construction project time management of engineering project is the important step of project management, and traditional progress control method information is stagnant Afterwards, the features such as level of informatization is relatively low, the development of engineering constraint progress control level.BIM, abbreviation BIM (building information modeling), BIM technology has the features such as informationization, visualization, the construction based on BIM Application of the progress msg management mode in municipal works improves the whole of engineering to lifting the managerial skills of such engineering Body value is significant.
In the prior art, although there is also some construction project time management methods, but these methods are for a certain spy Determine the solution of engineering customization, engineering project can only be reflected in itself in scheme, actual city coordinate can not be combined.Due to Municipal works are closely related with daily life, and the influence journey to daily life is should be taken into account in work progress Degree, when construction plan is formulated, should formulate rational scheme, and energy according to the daily life of construction surrounding resident and pedestrian It is enough intuitively to show, therefore, there is presently no the related public technology suitable for municipal works.Also, prior art is being based on In the Municipal Engineering Construction progress msgization management of BIM, the establishment to BIM models, BIM models are associated with WBS can not be met The requirement of municipal works progress control, and it is too single with analysis to information displaying, it is impossible to staff is met to construction work The requirement of the information management of journey.
The content of the invention
The present invention is carried out to solve the above problems, it is therefore intended that is provided one kind and is entered suitable for Municipal Engineering Construction Degree information management, and can intuitively, it is many analysis with displaying Municipal Engineering Construction progress the municipal works based on BIM Construction speed approaches to IM and system.
The invention provides a kind of Municipal Engineering Construction progress msg management method based on BIM, it is characterised in that including Following steps:Step 1, builds BIM models, comprises the following steps:
Step 1-1, project basic point unification, the geographical position coordinates in city is converted, with the item in BIM MBMs Mesh basic point coordinate unification,
Step 1-2, BIM model creation, each Professional Model is created under unified basic point coordinate,
Step 1-3, model based coding is carried out to BIM models,
Step 2, works out construction schedule, and the BIM models that step 1 is set up are associated with construction schedule, described to apply Work schedule is divided into multiple operations according to the task of engineering, and each operation is numbered, operation numbering with it is corresponding BIM models model based coding be associated,
Step 3, the incidence relation between BIM models, construction schedule, BIM models and construction plan is stored,
Step 4, the actual progress of typing construction process, system is compared actual progress with construction schedule Compared with,
Step 5, is respectively adopted vivid progress display, progress backtracking, Gantt chart and Report Server Management and construction speed information is entered Row displaying and analysis.
Further, in the Municipal Engineering Construction progress msg management method based on BIM that the present invention is provided, can also have There is such feature:Wherein, vivid progress display:Respectively with engineering project beginning and ending time and actual beginning and ending time as foundation, On BIM models task and unfinished task have been completed with two kinds of color marks.
Further, in the Municipal Engineering Construction progress msg management method based on BIM that the present invention is provided, can also have There is such feature:Wherein, the progress recalls the construction figure progress for checking any date, and the time is set comprising module Axle, the module on time shaft can arbitrarily be dragged in construction period, by dragging the module on time shaft, can check any The construction figure progress on date.
Further, in the Municipal Engineering Construction progress msg management method based on BIM that the present invention is provided, can also have There is such feature:Wherein, Gantt chart is used to show the contrast situation of target advance and actual progress.
Further, in the Municipal Engineering Construction progress msg pipe physico-chemical method based on BIM that the present invention is provided, can be with Have the feature that:Wherein, the list of engineering that progress report is completed comprising completed works inventory and next cycle planning.
Built according to above-mentioned Municipal Engineering Construction progress msg management method based on BIM present invention also offers a kind of System, it is characterised in that:Including:Construction data initialization module, comprising:BIM MBMs, modular converter and coding module, The BIM MBMs are used to build the BIM models of engineering, and the modular converter is used to convert the geographical position coordinates in city It is to be used to enter on the BIM models that the BIM MBMs build with identical unit in BIM MBMs, the coding module Row model based coding, the operation of construction schedule is numbered;Relating module, for by construction schedule and BIM models It is associated;Input module, the actual progress for being input into construction schedule, input work progress;Memory module, for depositing Store up the incidence relation between the BIM models, the construction schedule, the BIM models and construction schedule, constructed The actual progress of journey;Display module, comprising:For having been completed task and not completed with two kinds of color marks on BIM models to appoint The vivid progress display module of business, for check the progress backtracking module of the construction figure progress on any date in construction period, For with the gunter module of gunter diagram form displaying target advance and the contrast situation of actual progress and for form Pattern displaying has completed list of engineering and lower cycle planning completes the statement management module of inventory.
Advantages of the present invention is as follows:
According to the Municipal Engineering Construction progress msg management method based on BIM involved in the present invention, BIM models are being set up When, urban geography position coordinates is converted to the position coordinates being mutually equal to project basic point in modeling software first, then in system BIM models are set up under one basic point, therefore, BIM models are combined with the geographical position in city, more can intuitively reflect construction work Journey overview, coding numbering is carried out to BIM models, works out construction schedule, and construction schedule is divided into multiple operations simultaneously Numbering, and associate with the coding of BIM models numbering, so that it is determined that the plan engineering time of each component in BIM models, logical Typing practice of construction progress is crossed, practice of construction progress is contrasted with the construction speed of plan, and use various exhibition methods Enter shape displaying and analysis, the progress msg for comprehensively understanding construction work more directly perceived.Municipal works based on BIM of the invention Construction speed approaches to IM suitable for Municipal Engineering Construction progress msg manage, and can intuitively, many analyses With displaying Municipal Engineering Construction progress.
The present invention provide message tube physics and chemistry system, by essential information input system after, can intuitively, comprehensively will construction The information of engineering shows staff, improves the managerial skills of engineering.
Brief description of the drawings
Fig. 1 is the flow chart of the Municipal Engineering Construction progress msg management method based on BIM in the present invention;
The flow chart of BIM models is built during Fig. 2 in the present invention;
Fig. 3 is the structural representation of information management system in the present invention.
Specific embodiment
In order that technological means, creation characteristic, reached purpose and effect that the present invention is realized are easy to understand, it is real below Example combination accompanying drawing is applied to be specifically addressed Municipal Engineering Construction progress msg managementization method and system of the present invention based on BIM.
As shown in figure 1, in the present embodiment, the Municipal Engineering Construction progress msg management method based on BIM is comprising following Step:
Step S1, builds BIM models, as shown in Fig. 2 comprising the following steps:
Step S1-1, the unification of project basic point, in BIM modeling softwares, each model, structure, position coordinates are measured with millimeter, The geographical position coordinates in city are measured with km, therefore need to be converted the geographical position coordinates in city, it is modeled with BIM Project basic point coordinate unification in module.
Step S1-2, BIM model creation, each Professional Model is created under unified basic point coordinate.The fineness that model splits Meet the fineness requirement of Engineering Construction Management, the material of model meets difference requirement clearly demarcated, elegant in appearance.
Step S1-3, model based coding numbering is carried out to BIM models.By BIM models according to Engineering Speciality, section partition, work Journey scale etc. carries out differentiation establishment, and uniqueness is respectively provided with comprising each numbering in numbering, and each numbering represents BIM models In certain component, numbering is comprising position coordinates, element type etc..Numbering can as engineering foundation information, construction speed information, The label of retrieval.
Step S2, establishment construction schedule (Work Break Structure, abbreviation WBS), step 1 is set up BIM models are associated with WBS.Wherein, WBS is divided into multiple operations according to the task of engineering, and each operation is numbered, and gives The working time of fixed each operation.The model based coding numbering numbered on unique, BIM models of each operation of WBS is unique, by work Sequence is numbered to be associated with the model based coding numbering of corresponding BIM models, sets up logical relation.
Step S3, the incidence relation between BIM models, construction schedule, BIM models and construction plan is deposited Storage.
Step S4, the actual progress of typing construction process, system is compared actual progress with construction schedule Compared with.The actual progress of construction process is by Data Collection, data screening, data according to the progress msg to engineering site Record obtains actual progress information.
Step S5, is respectively adopted vivid progress display, progress backtracking, Gantt chart and Report Server Management and construction speed information is entered Row displaying and analysis.Using various displayings and analysis method, so that staff can more fully understand construction work Information.
Vivid progress display:Respectively with engineering project beginning and ending time and actual beginning and ending time as foundation, on BIM models Task and unfinished task have been completed with two kinds of color marks.Can intuitively show engineering in construction speed on threedimensional model Progress under plan, and the progress in the case of practice of construction progress.
Progress recalls the construction figure progress for checking any date in construction period, with BIM models as object, comprising Module sets time shaft, and the module on time shaft can arbitrarily be dragged in construction period, by dragging the module on time shaft, The construction figure progress on any date can be checked.
Gantt chart is used to show the contrast situation of target advance and actual progress, can intuitively find out engineering actual development with The difference of target advance.
The list of engineering that progress report is completed comprising completed works inventory and next cycle planning.According to progress report Style, the list of engineering that generation is completed with the list of engineering for completing and next cycle planning.In the present embodiment, data in form Classification statistics is carried out according to work area, element type.
A kind of message tube physics and chemistry system 100, including:Construction data initialization module 10, relating module 20, input module 30th, memory module 40 and display module 50.
Construction data initialization module 10 is included:BIM MBMs 11, modular converter 12 and coding module 13.BIM is modeled Module 11 is used to build the BIM models of engineering.Modular converter 12 is used to be converted into the geographical position coordinates in city and BIM modelings Identical unit in module.Coding module 13 is used to for the BIM models that BIM MBMs build to carry out model based coding, will construct The operation of schedule is numbered.
Relating module 20 is used to be associated construction schedule with BIM models.
Input module 30 is used to be input into construction schedule, the actual progress of input work progress.
Memory module 40 is used to store the pass between BIM models, construction schedule, BIM models and construction schedule The actual progress of connection relation, work progress.
Display module 50 is included:Vivid progress display module 51, progress backtracking module 52, gunter module 53, Yi Jibao Table management module 54.
Vivid progress display module 51 is used on BIM models completed task and not completed with two kinds of color marks to appoint Business.
Progress backtracking module 52 is used to check the construction figure progress on any date in construction period.
Gunter module 53 is used for the contrast situation with actual progress with gunter diagram form displaying target advance.
Statement management module 54 is used to complete list of engineering with the pattern displaying of form and lower cycle planning completes inventory.
Above-mentioned implementation method is preferred case of the invention, is not intended to limit protection scope of the present invention.

Claims (6)

1. a kind of Municipal Engineering Construction progress msg management method based on BIM, it is characterised in that comprise the following steps:
Step 1, builds BIM models, comprises the following steps:
Step 1-1, project basic point unification, the geographical position coordinates in city is converted, with the project base in BIM MBMs Point coordinates is unified,
Step 1-2, BIM model creation, each Professional Model is created under unified basic point coordinate,
Step 1-3, model based coding is carried out to BIM models,
Step 2, works out construction schedule, and the BIM models that step 1 is set up associate with construction schedule, it is described construct into Degree plan is divided into multiple operations according to the task of engineering, and each operation is numbered, and operation is numbered and corresponding BIM The model based coding of model is associated,
Step 3, the incidence relation between BIM models, construction schedule, BIM models and construction plan is stored,
With construction schedule be compared actual progress by step 4, the actual progress of typing construction process, system,
Step 5, is respectively adopted vivid progress display, progress backtracking, Gantt chart and Report Server Management and construction speed information is opened up Show and analysis.
2. the Municipal Engineering Construction progress msg management method based on BIM according to claim 1, it is characterised in that:
Wherein, the vivid progress display:Respectively with engineering project beginning and ending time and actual beginning and ending time as foundation, in BIM On model task and unfinished task have been completed with two kinds of color marks.
3. the Municipal Engineering Construction progress msg management method based on BIM according to claim 1, it is characterised in that:
Wherein, the progress recalls the construction figure progress for checking any date, and time shaft, time shaft are set comprising module On module can arbitrarily be dragged in construction period, by dragging the module on time shaft, applying for any date can be checked Work image progress.
4. the Municipal Engineering Construction progress msg management method based on BIM according to claim 1, it is characterised in that:
Wherein, the Gantt chart is used to show the contrast situation of target advance and actual progress.
5. the Municipal Engineering Construction progress msg management method based on BIM according to claim 1, it is characterised in that:
Wherein, the list of engineering that the progress report is completed comprising completed works inventory and next cycle planning.
6. a kind of structure of the Municipal Engineering Construction progress msg management method based on BIM according to claim 1 to 5 is System, it is characterised in that including:
Construction data initialization module, comprising:BIM MBMs, modular converter and coding module, the BIM MBMs are used In build engineering BIM models, the modular converter be used for by the geographical position coordinates in city be converted into in BIM MBMs Identical unit, the coding module is used to for the BIM models that the BIM MBMs build to carry out model based coding, will construct The operation of schedule is numbered;
Relating module, for construction schedule to be associated with BIM models;
Input module, the actual progress for being input into construction schedule, input work progress;
Memory module, for store the BIM models, the construction schedule, the BIM models and construction schedule it Between incidence relation, the actual progress of work progress;
Display module, comprising:For having completed task with two kinds of color marks on BIM models and abortive image is entered Degree display module, for checking the progress backtracking module of the construction figure progress on any date in construction period, for gunter Diagram form shows target advance with the gunter module of the contrast situation of actual progress and for the pattern displaying with form Complete list of engineering and lower cycle planning completes the statement management module of inventory.
CN201710041846.3A 2017-01-20 2017-01-20 Municipal Engineering Construction progress msg management method and system based on BIM Pending CN106803150A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710041846.3A CN106803150A (en) 2017-01-20 2017-01-20 Municipal Engineering Construction progress msg management method and system based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710041846.3A CN106803150A (en) 2017-01-20 2017-01-20 Municipal Engineering Construction progress msg management method and system based on BIM

Publications (1)

Publication Number Publication Date
CN106803150A true CN106803150A (en) 2017-06-06

Family

ID=58986942

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710041846.3A Pending CN106803150A (en) 2017-01-20 2017-01-20 Municipal Engineering Construction progress msg management method and system based on BIM

Country Status (1)

Country Link
CN (1) CN106803150A (en)

Cited By (50)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107368972A (en) * 2017-07-25 2017-11-21 中建安装工程有限公司 It is a kind of that work platform and its application method are sent based on BIM technology
CN107516161A (en) * 2017-08-03 2017-12-26 中国建筑第五工程局有限公司 A kind of project progress management-control method based on BIM
CN107563703A (en) * 2017-09-22 2018-01-09 熊志军 A kind of method and system of material information management
CN107679310A (en) * 2017-09-26 2018-02-09 华北电力大学 The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology
CN107688908A (en) * 2017-09-06 2018-02-13 北京城乡建设集团有限责任公司 Study and judge the method and device of construction safety risk
CN107798194A (en) * 2017-10-30 2018-03-13 毕埃慕(上海)建筑数据技术股份有限公司 The analogy method and device of engineering construction
CN107818430A (en) * 2017-12-15 2018-03-20 武汉理工大学 A kind of building engineering construction progress msg management method and system based on BIM
CN108009758A (en) * 2018-01-09 2018-05-08 中建七局安装工程有限公司 A kind of site operation material intelligent management based on BIM
CN108229923A (en) * 2018-01-29 2018-06-29 联合建管(北京)国际工程科技有限责任公司 The methods of exhibiting and device of continuous type project schedule plan
CN108256213A (en) * 2018-01-16 2018-07-06 中铁局集团有限公司 Depot of urban railway transit vehicles modular construction analogy method based on VR and BIM
CN108537462A (en) * 2018-04-17 2018-09-14 万翼科技有限公司 Confirmation method, device, computer readable storage medium and the system of project process
CN108681879A (en) * 2018-05-24 2018-10-19 广州市建筑科学研究院有限公司 A kind of filling pile construction management method and system based on BIM technology
CN109190962A (en) * 2018-08-24 2019-01-11 北京中联环建设工程管理有限公司 Project process supervision control system
CN109360123A (en) * 2018-10-22 2019-02-19 上海建工四建集团有限公司 A kind of multi-specialized execution management method therefor and system based on room
CN109446668A (en) * 2018-10-31 2019-03-08 广西路桥工程集团有限公司 A kind of component Schedule monitoring system and method based on threedimensional model
CN109522661A (en) * 2018-11-23 2019-03-26 上海蓝色星球科技股份有限公司 A kind of Building Information Model component and work breakdown structure (WBS) correlating method and system
CN109685479A (en) * 2018-12-29 2019-04-26 中铁十九局集团第六工程有限公司 A kind of methods of exhibiting, computer installation and the computer readable storage medium of construction tunnel progress
CN109872127A (en) * 2019-02-01 2019-06-11 重庆工商职业学院 Building intelligence builds progress control method
CN109886838A (en) * 2019-01-29 2019-06-14 杭州凌望建筑科技有限公司 Smart city operation management platform based on CIM
CN110084526A (en) * 2019-05-05 2019-08-02 广西路桥工程集团有限公司 A kind of visualization project management monitoring system based on BIM+WBS
CN110119565A (en) * 2019-05-08 2019-08-13 中铁八局集团建筑工程有限公司 A method of quick association and displaying based on BIM model and project programme
CN110428176A (en) * 2019-08-05 2019-11-08 中国电力企业联合会电力建设技术经济咨询中心 Project progress checking method and system
CN110505452A (en) * 2019-08-26 2019-11-26 广东电网有限责任公司 A kind of capital construction power transmission engineering Schedule monitoring method and monitoring system
CN110555661A (en) * 2018-05-31 2019-12-10 西安海平方网络科技有限公司 information display method, device and equipment of building element and readable storage medium
CN110580267A (en) * 2019-09-23 2019-12-17 重庆渝高科技产业(集团)股份有限公司 engineering information display control method for urban engineering management
CN110598260A (en) * 2019-08-16 2019-12-20 南京紫城工程设计有限公司 Municipal engineering design system based on BIM technology
CN110599027A (en) * 2019-09-09 2019-12-20 中铁建设集团有限公司 Method for automatically acquiring progress data of BIM platform by using weighbridge weighing system
CN110852696A (en) * 2019-10-08 2020-02-28 上海建工五建集团有限公司 Project progress monitoring method and system
CN110942239A (en) * 2019-11-21 2020-03-31 中国电力企业联合会电力建设技术经济咨询中心 Automatic inspection method and device for actual engineering progress
CN110968751A (en) * 2019-11-29 2020-04-07 中国电力企业联合会电力建设技术经济咨询中心 Dynamic display method and device for engineering project capital curve
CN111080239A (en) * 2019-11-29 2020-04-28 中国电力企业联合会电力建设技术经济咨询中心 Real-time dynamic tracking method and device for construction cost
CN111429097A (en) * 2020-03-24 2020-07-17 上海捷规建筑工程咨询有限公司 BIM-based automatic matching method and system for field progress and model
CN111506949A (en) * 2020-04-10 2020-08-07 中国电建集团昆明勘测设计研究院有限公司 BIM-based visualization method for road soft foundation treatment construction progress
CN111754138A (en) * 2020-07-07 2020-10-09 天津水泥工业设计研究院有限公司 Engineering construction progress plan management and control system and method based on BIM model
CN111815235A (en) * 2020-07-01 2020-10-23 中国电建集团华东勘测设计研究院有限公司 Engineering material management and control method and device based on BIM, storage medium and computer equipment
CN111899343A (en) * 2020-07-02 2020-11-06 广州市第一市政工程有限公司 Traffic dispersion method in municipal engineering based on BIM technology
CN111967837A (en) * 2020-07-16 2020-11-20 译筑信息科技(上海)有限公司 BIM-based assembly type component construction process control method and system
CN112100725A (en) * 2020-09-18 2020-12-18 中国电建集团华东勘测设计研究院有限公司 Engineering whole-element process information display method based on BIM (building information modeling) model and crosswalk diagram
CN112486613A (en) * 2020-11-27 2021-03-12 东南大学 Engineering project Web end construction progress management method and device and readable storage medium
CN112488663A (en) * 2020-12-14 2021-03-12 广西路桥工程集团有限公司 Progress management system based on WBS
CN112541733A (en) * 2020-12-12 2021-03-23 中冶天工集团有限公司 Engineering construction stage management control method based on BIM
CN112581030A (en) * 2020-12-29 2021-03-30 基建通(三亚)国际科技有限公司 Bridge BIM model component level progress display method and device and storage medium
CN112613109A (en) * 2021-01-04 2021-04-06 中国铁道科学研究院集团有限公司电子计算技术研究所 Construction progress and cost management method and device of railway BIM system based on web real-time modeling
CN113538661A (en) * 2021-07-06 2021-10-22 万翼科技有限公司 Information display method based on building model and related device
CN113609550A (en) * 2021-07-05 2021-11-05 江苏徐工工程机械研究院有限公司 BIM-based construction process planning management method and system
CN113673899A (en) * 2021-08-28 2021-11-19 江苏苏科建设项目管理有限公司 Road engineering progress management method based on supervision cloud system
CN114282909A (en) * 2022-01-04 2022-04-05 中广核工程有限公司 Nuclear power facility installation progress monitoring method and system, electronic equipment and nuclear power project progress monitoring method
CN114418279A (en) * 2021-12-07 2022-04-29 中国电建集团华东勘测设计研究院有限公司 BIM model-based visual management method for progress and cost of whole construction process
CN115878872A (en) * 2023-02-08 2023-03-31 一智科技(成都)有限公司 Construction progress visualization method and system
CN118194399A (en) * 2024-03-15 2024-06-14 中交三航局第九工程有限公司 Overpass bridge construction progress management method based on illusion engine BIM technology

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104766182A (en) * 2015-04-30 2015-07-08 北京宁晖兴业科技有限公司 Intelligent monitoring system for building design construction based on BIM
CN105335559A (en) * 2015-10-28 2016-02-17 上海同筑信息科技有限公司 Engineering standardized construction process control method and system on basis of BIM (building information modeling)
KR101648027B1 (en) * 2016-01-04 2016-08-17 (주) 한길아이티 Building information modeling design collaboration device
CN105976089A (en) * 2016-04-27 2016-09-28 中交第二航务工程局有限公司 Construction data classification system based on building information model and method thereof
CN106339820A (en) * 2016-08-31 2017-01-18 中国电建集团昆明勘测设计研究院有限公司 Virtual reality-based hydraulic structure actual measurement performance multi-dimensional analysis method and system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104766182A (en) * 2015-04-30 2015-07-08 北京宁晖兴业科技有限公司 Intelligent monitoring system for building design construction based on BIM
CN105335559A (en) * 2015-10-28 2016-02-17 上海同筑信息科技有限公司 Engineering standardized construction process control method and system on basis of BIM (building information modeling)
KR101648027B1 (en) * 2016-01-04 2016-08-17 (주) 한길아이티 Building information modeling design collaboration device
CN105976089A (en) * 2016-04-27 2016-09-28 中交第二航务工程局有限公司 Construction data classification system based on building information model and method thereof
CN106339820A (en) * 2016-08-31 2017-01-18 中国电建集团昆明勘测设计研究院有限公司 Virtual reality-based hydraulic structure actual measurement performance multi-dimensional analysis method and system

Cited By (57)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107368972A (en) * 2017-07-25 2017-11-21 中建安装工程有限公司 It is a kind of that work platform and its application method are sent based on BIM technology
CN107516161A (en) * 2017-08-03 2017-12-26 中国建筑第五工程局有限公司 A kind of project progress management-control method based on BIM
CN107688908A (en) * 2017-09-06 2018-02-13 北京城乡建设集团有限责任公司 Study and judge the method and device of construction safety risk
CN107563703A (en) * 2017-09-22 2018-01-09 熊志军 A kind of method and system of material information management
CN107679310A (en) * 2017-09-26 2018-02-09 华北电力大学 The real-time progress 3 D stereo methods of exhibiting of engineering based on BIM and image congruencing technology
CN107798194A (en) * 2017-10-30 2018-03-13 毕埃慕(上海)建筑数据技术股份有限公司 The analogy method and device of engineering construction
CN107818430A (en) * 2017-12-15 2018-03-20 武汉理工大学 A kind of building engineering construction progress msg management method and system based on BIM
CN108009758B (en) * 2018-01-09 2022-04-15 中建七局安装工程有限公司 BIM-based intelligent management method for field construction materials
CN108009758A (en) * 2018-01-09 2018-05-08 中建七局安装工程有限公司 A kind of site operation material intelligent management based on BIM
CN108256213A (en) * 2018-01-16 2018-07-06 中铁局集团有限公司 Depot of urban railway transit vehicles modular construction analogy method based on VR and BIM
CN108229923A (en) * 2018-01-29 2018-06-29 联合建管(北京)国际工程科技有限责任公司 The methods of exhibiting and device of continuous type project schedule plan
CN108537462A (en) * 2018-04-17 2018-09-14 万翼科技有限公司 Confirmation method, device, computer readable storage medium and the system of project process
CN108681879A (en) * 2018-05-24 2018-10-19 广州市建筑科学研究院有限公司 A kind of filling pile construction management method and system based on BIM technology
CN110555661A (en) * 2018-05-31 2019-12-10 西安海平方网络科技有限公司 information display method, device and equipment of building element and readable storage medium
CN109190962A (en) * 2018-08-24 2019-01-11 北京中联环建设工程管理有限公司 Project process supervision control system
CN109360123A (en) * 2018-10-22 2019-02-19 上海建工四建集团有限公司 A kind of multi-specialized execution management method therefor and system based on room
CN109446668A (en) * 2018-10-31 2019-03-08 广西路桥工程集团有限公司 A kind of component Schedule monitoring system and method based on threedimensional model
CN109522661A (en) * 2018-11-23 2019-03-26 上海蓝色星球科技股份有限公司 A kind of Building Information Model component and work breakdown structure (WBS) correlating method and system
CN109685479A (en) * 2018-12-29 2019-04-26 中铁十九局集团第六工程有限公司 A kind of methods of exhibiting, computer installation and the computer readable storage medium of construction tunnel progress
CN109886838A (en) * 2019-01-29 2019-06-14 杭州凌望建筑科技有限公司 Smart city operation management platform based on CIM
CN109872127A (en) * 2019-02-01 2019-06-11 重庆工商职业学院 Building intelligence builds progress control method
CN110084526A (en) * 2019-05-05 2019-08-02 广西路桥工程集团有限公司 A kind of visualization project management monitoring system based on BIM+WBS
CN110084526B (en) * 2019-05-05 2022-05-31 广西路桥工程集团有限公司 BIM + WBS-based visual project management monitoring system
CN110119565A (en) * 2019-05-08 2019-08-13 中铁八局集团建筑工程有限公司 A method of quick association and displaying based on BIM model and project programme
CN110428176A (en) * 2019-08-05 2019-11-08 中国电力企业联合会电力建设技术经济咨询中心 Project progress checking method and system
CN110428176B (en) * 2019-08-05 2020-10-30 中国电力企业联合会电力建设技术经济咨询中心 Project progress auditing method and system
CN110598260A (en) * 2019-08-16 2019-12-20 南京紫城工程设计有限公司 Municipal engineering design system based on BIM technology
CN110505452A (en) * 2019-08-26 2019-11-26 广东电网有限责任公司 A kind of capital construction power transmission engineering Schedule monitoring method and monitoring system
CN110599027A (en) * 2019-09-09 2019-12-20 中铁建设集团有限公司 Method for automatically acquiring progress data of BIM platform by using weighbridge weighing system
CN110580267A (en) * 2019-09-23 2019-12-17 重庆渝高科技产业(集团)股份有限公司 engineering information display control method for urban engineering management
CN110852696A (en) * 2019-10-08 2020-02-28 上海建工五建集团有限公司 Project progress monitoring method and system
CN110942239A (en) * 2019-11-21 2020-03-31 中国电力企业联合会电力建设技术经济咨询中心 Automatic inspection method and device for actual engineering progress
CN110968751A (en) * 2019-11-29 2020-04-07 中国电力企业联合会电力建设技术经济咨询中心 Dynamic display method and device for engineering project capital curve
CN111080239A (en) * 2019-11-29 2020-04-28 中国电力企业联合会电力建设技术经济咨询中心 Real-time dynamic tracking method and device for construction cost
CN111080239B (en) * 2019-11-29 2021-03-26 中国电力企业联合会电力建设技术经济咨询中心 Real-time dynamic tracking method and device for construction cost
CN111429097A (en) * 2020-03-24 2020-07-17 上海捷规建筑工程咨询有限公司 BIM-based automatic matching method and system for field progress and model
CN111429097B (en) * 2020-03-24 2024-03-05 上海捷规建筑工程咨询有限公司 BIM-based automatic field progress and model matching method and system
CN111506949A (en) * 2020-04-10 2020-08-07 中国电建集团昆明勘测设计研究院有限公司 BIM-based visualization method for road soft foundation treatment construction progress
CN111815235A (en) * 2020-07-01 2020-10-23 中国电建集团华东勘测设计研究院有限公司 Engineering material management and control method and device based on BIM, storage medium and computer equipment
CN111899343A (en) * 2020-07-02 2020-11-06 广州市第一市政工程有限公司 Traffic dispersion method in municipal engineering based on BIM technology
CN111754138B (en) * 2020-07-07 2021-07-23 天津水泥工业设计研究院有限公司 Engineering construction progress plan management and control system and method based on BIM model
CN111754138A (en) * 2020-07-07 2020-10-09 天津水泥工业设计研究院有限公司 Engineering construction progress plan management and control system and method based on BIM model
CN111967837A (en) * 2020-07-16 2020-11-20 译筑信息科技(上海)有限公司 BIM-based assembly type component construction process control method and system
CN112100725A (en) * 2020-09-18 2020-12-18 中国电建集团华东勘测设计研究院有限公司 Engineering whole-element process information display method based on BIM (building information modeling) model and crosswalk diagram
CN112486613A (en) * 2020-11-27 2021-03-12 东南大学 Engineering project Web end construction progress management method and device and readable storage medium
CN112541733A (en) * 2020-12-12 2021-03-23 中冶天工集团有限公司 Engineering construction stage management control method based on BIM
CN112488663B (en) * 2020-12-14 2022-06-21 广西路桥工程集团有限公司 Progress management system based on WBS
CN112488663A (en) * 2020-12-14 2021-03-12 广西路桥工程集团有限公司 Progress management system based on WBS
CN112581030A (en) * 2020-12-29 2021-03-30 基建通(三亚)国际科技有限公司 Bridge BIM model component level progress display method and device and storage medium
CN112613109A (en) * 2021-01-04 2021-04-06 中国铁道科学研究院集团有限公司电子计算技术研究所 Construction progress and cost management method and device of railway BIM system based on web real-time modeling
CN113609550A (en) * 2021-07-05 2021-11-05 江苏徐工工程机械研究院有限公司 BIM-based construction process planning management method and system
CN113538661A (en) * 2021-07-06 2021-10-22 万翼科技有限公司 Information display method based on building model and related device
CN113673899A (en) * 2021-08-28 2021-11-19 江苏苏科建设项目管理有限公司 Road engineering progress management method based on supervision cloud system
CN114418279A (en) * 2021-12-07 2022-04-29 中国电建集团华东勘测设计研究院有限公司 BIM model-based visual management method for progress and cost of whole construction process
CN114282909A (en) * 2022-01-04 2022-04-05 中广核工程有限公司 Nuclear power facility installation progress monitoring method and system, electronic equipment and nuclear power project progress monitoring method
CN115878872A (en) * 2023-02-08 2023-03-31 一智科技(成都)有限公司 Construction progress visualization method and system
CN118194399A (en) * 2024-03-15 2024-06-14 中交三航局第九工程有限公司 Overpass bridge construction progress management method based on illusion engine BIM technology

Similar Documents

Publication Publication Date Title
CN106803150A (en) Municipal Engineering Construction progress msg management method and system based on BIM
CN102930374B (en) A kind of system using three-dimensional model simulating reality to carry out project management
Kelly et al. BIM for facility management: a review and a case study investigating the value and challenges
CN108038915A (en) A kind of substation project progress msg visualization system based on WEB terminal three-dimensional simulation
US20060044307A1 (en) System and method for visually representing project metrics on 3-dimensional building models
CN109190252A (en) A kind of construction method based on R-N5DL-BIM technology
CN104008218A (en) Electric power engineering three-dimensional integrated design platform
Port The management of CAD for construction
CN117173367B (en) Method and equipment for establishing dynamic landscape plant component library based on Rhino
CN108053486A (en) Construction method and system based on virtual technology
CN104268346B (en) A kind of implementation method of the Simulation Application visualization the integration environment based on object class interaction figure
CN110990914A (en) BIM technology-based large boiler installation method
CN108694260A (en) Application process of the BIM technology in Steel Bridge processing and manufacturing
CN105426601A (en) Diversity design scheme reporting method and system based on BIM (Building Information Modeling)
Žurić et al. Integrating HBIM and sustainability certification: A pilot study using GBC historic building certification
CN108153572A (en) GIS display methods, device and system
Alam et al. EvoSpaces: 3D Visualization of Software Architecture.
Fassi et al. Complex architecture in 3D: from survey to web
Abdelhai Integration BIM and emerging technologies in architectural academic programs
CN110490980A (en) A kind of Virtual Construction template information processing system and method based on fixation and recognition
Shariatpour et al. Urban 3D Modeling as a Precursor of City Information Modeling and Digital Twin for Smart City Era: A Case Study of the Narmak Neighborhood of Tehran City, Iran
CN113496548A (en) Transparent factory oriented production field data mapping method
KR20110109710A (en) Three dimensional system and method for monitoring process
Ma et al. Combine BIM-based and mobile technologies to design on-site support system for the communication and management of architectural heritage conservation works
CN107133787A (en) Highway project management method and system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170606

WD01 Invention patent application deemed withdrawn after publication