CN112541733A - Engineering construction stage management control method based on BIM - Google Patents

Engineering construction stage management control method based on BIM Download PDF

Info

Publication number
CN112541733A
CN112541733A CN202011453801.5A CN202011453801A CN112541733A CN 112541733 A CN112541733 A CN 112541733A CN 202011453801 A CN202011453801 A CN 202011453801A CN 112541733 A CN112541733 A CN 112541733A
Authority
CN
China
Prior art keywords
bim
management
construction
management module
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011453801.5A
Other languages
Chinese (zh)
Inventor
解莎莎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN202011453801.5A priority Critical patent/CN112541733A/en
Publication of CN112541733A publication Critical patent/CN112541733A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • G06Q50/16Real estate
    • G06Q50/165Land development

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Primary Health Care (AREA)

Abstract

A BIM-based engineering construction stage management control method comprises the following steps: building a BIM model on BIM software; defining a management module on BIM software; associating the BIM model with the management module; and managing the construction progress on the BIM model. According to the BIM-based engineering construction stage management and control method, each function management module can be added in a user-defined mode according to the engineering quality and progress management requirements of construction units and the project management and control requirements, so that model member attribute information is searched, updated and called, construction progress management, engineering quality inspection and the like are carried out, and the construction efficiency and the engineering quality of construction engineering are improved.

Description

Engineering construction stage management control method based on BIM
Technical Field
The invention belongs to the technical field of engineering construction stage management control, and particularly relates to a BIM-based engineering construction stage management control method.
Background
With the rapid development of the national engineering informatization, the engineering construction informatization level is continuously improved, the progress of the construction technology and the increasing of the management level are promoted, the popularization and the application of the construction enterprise information system are basically realized, the application of a new construction information model technology in the engineering is accelerated, and the informatization construction is promoted.
Disclosure of Invention
In order to solve the above problems, the present invention provides a project construction stage management control method based on BIM, which comprises the steps of:
building a BIM model on BIM software;
defining a management module on BIM software;
associating the BIM model with the management module;
and managing the construction progress on the BIM model.
Preferably, the building of the BIM model on the BIM software includes the steps of:
building a BIM model by using BIM modeling software according to a design drawing;
introducing a BIM engineering management system plug-in into the BIM modeling software;
and carrying out lightweight treatment by using the BIM engineering management system plug-in.
Preferably, the BIM modeling software is a MicroStation series-based BIM modeling software.
Preferably, the defining a management module on the BIM software includes the steps of:
customizing the management module according to the engineering project management requirement;
and adding construction information in the corresponding management module according to project requirements.
Preferably, said associating said BIM model with said management module comprises the steps of:
hanging the BIM model and a construction quality form in the management module;
and hanging the BIM model and the quality acceptance record in the management module.
Preferably, the managing the construction progress on the BIM model includes the steps of:
integrating the BIM model with Project progress management;
tracking field progress management using the BIM model;
comparing and checking the actual progress and the planned progress;
and performing field resource configuration by using the BIM model.
According to the BIM-based engineering construction stage management and control method, each function management module can be added in a user-defined mode according to the engineering quality and progress management requirements of construction units and the project management and control requirements, so that model member attribute information is searched, updated and called, construction progress management, engineering quality inspection and the like are carried out, and the construction efficiency and the engineering quality of construction engineering are improved.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic flow chart of a project construction stage management control method based on BIM provided by the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention will be described in further detail with reference to the accompanying drawings in conjunction with the following detailed description. It should be understood that the description is intended to be exemplary only, and is not intended to limit the scope of the present invention. Moreover, in the following description, descriptions of well-known structures and techniques are omitted so as to not unnecessarily obscure the concepts of the present invention.
As shown in fig. 1, in the embodiment of the present application, the present invention provides a project construction phase management control method based on BIM, and the method includes the steps of:
s1: building a BIM model on BIM software;
s2: defining a management module on BIM software;
s3: associating the BIM model with the management module;
s4: and managing the construction progress on the BIM model.
In the embodiment of the application, when the management control is carried out in the engineering construction stage based on the BIM, the BIM model is firstly built on the BIM software, then the management module is defined on the BIM software, then the BIM model is associated with the management module, and finally the construction progress is managed on the BIM model.
In the embodiment of the present application, the building of the BIM model on the BIM software in step S1 includes the steps of:
building a BIM model by using BIM modeling software according to a design drawing;
introducing a BIM engineering management system plug-in into the BIM modeling software;
and carrying out lightweight treatment by using the BIM engineering management system plug-in.
In the embodiment of the application, when the BIM model is built on the BIM software, the BIM model is built by using the BIM modeling software according to a design drawing, then a BIM engineering management system plug-in is introduced into the BIM modeling software, and then the BIM engineering management system plug-in is used for carrying out lightweight processing.
In the embodiment of the application, the BIM modeling software is based on MicroStation series BIM modeling software.
In the embodiment of the present application, the defining the management module on the BIM software in step S2 includes the steps of:
customizing the management module according to the engineering project management requirement;
and adding construction information in the corresponding management module according to project requirements.
In the embodiment of the application, when the management module is defined on the BIM software, the management module is firstly customized according to the management requirement of the project, and then the construction information is added to the corresponding management module according to the project requirement.
In the embodiment of the present application, the associating the BIM model with the management module in step S3 includes the steps of:
hanging the BIM model and a construction quality form in the management module;
and hanging the BIM model and the quality acceptance record in the management module.
In the embodiment of the application, when the BIM model is associated with the management module, the BIM model is firstly hooked with the construction quality form in the management module, and then the BIM model is hooked with the quality acceptance record in the management module.
In the embodiment of the present application, the step of managing the construction progress on the BIM model in the step S4 includes the steps of:
integrating the BIM model with Project progress management;
tracking field progress management using the BIM model;
comparing and checking the actual progress and the planned progress;
and performing field resource configuration by using the BIM model.
In the embodiment of the application, when the construction progress is managed on the BIM, the BIM is combined with Project progress management, then the BIM is used for tracking field progress management, then the actual progress is compared with the planned progress for checking, and then the BIM is used for carrying out field resource allocation.
According to the BIM-based engineering construction stage management and control method, each function management module can be added in a user-defined mode according to the engineering quality and progress management requirements of construction units and the project management and control requirements, so that model member attribute information is searched, updated and called, construction progress management, engineering quality inspection and the like are carried out, and the construction efficiency and the engineering quality of construction engineering are improved.
It is to be understood that the above-described embodiments of the present invention are merely illustrative of or explaining the principles of the invention and are not to be construed as limiting the invention. Therefore, any modification, equivalent replacement, improvement and the like made without departing from the spirit and scope of the present invention should be included in the protection scope of the present invention. Further, it is intended that the appended claims cover all such variations and modifications as fall within the scope and boundaries of the appended claims or the equivalents of such scope and boundaries.

Claims (6)

1. A BIM-based engineering construction stage management control method is characterized by comprising the following steps:
building a BIM model on BIM software;
defining a management module on BIM software;
associating the BIM model with the management module;
and managing the construction progress on the BIM model.
2. The BIM-based engineering construction phase management control method according to claim 1, wherein the building of the BIM model on the BIM software comprises the steps of:
building a BIM model by using BIM modeling software according to a design drawing;
introducing a BIM engineering management system plug-in into the BIM modeling software;
and carrying out lightweight treatment by using the BIM engineering management system plug-in.
3. The BIM-based engineering construction phase management control method according to claim 2, wherein the BIM modeling software is a BIM modeling software based on MicroStation series.
4. The BIM-based engineering construction phase management control method according to claim 1, wherein the step of defining a management module on BIM software comprises the steps of:
customizing the management module according to the engineering project management requirement;
and adding construction information in the corresponding management module according to project requirements.
5. The BIM-based project construction phase management control method according to claim 1, wherein the associating the BIM model with the management module comprises the steps of:
hanging the BIM model and a construction quality form in the management module;
and hanging the BIM model and the quality acceptance record in the management module.
6. The BIM-based project construction phase management control method according to claim 1, wherein the managing construction progress on the BIM model comprises the steps of:
integrating the BIM model with Project progress management;
tracking field progress management using the BIM model;
comparing and checking the actual progress and the planned progress;
and performing field resource configuration by using the BIM model.
CN202011453801.5A 2020-12-12 2020-12-12 Engineering construction stage management control method based on BIM Pending CN112541733A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011453801.5A CN112541733A (en) 2020-12-12 2020-12-12 Engineering construction stage management control method based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011453801.5A CN112541733A (en) 2020-12-12 2020-12-12 Engineering construction stage management control method based on BIM

Publications (1)

Publication Number Publication Date
CN112541733A true CN112541733A (en) 2021-03-23

Family

ID=75018423

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011453801.5A Pending CN112541733A (en) 2020-12-12 2020-12-12 Engineering construction stage management control method based on BIM

Country Status (1)

Country Link
CN (1) CN112541733A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106803150A (en) * 2017-01-20 2017-06-06 上海市地下空间设计研究总院有限公司 Municipal Engineering Construction progress msg management method and system based on BIM
CN107818198A (en) * 2017-09-27 2018-03-20 中建三局基础设施工程有限公司 A kind of science of bridge building management platform based on BIM technology
CN108596423A (en) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 A kind of trackways engineering construction progress msg management method based on BIM
CN111369158A (en) * 2019-12-30 2020-07-03 中铁四局集团有限公司 BIM-based informatization quality management method and system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106803150A (en) * 2017-01-20 2017-06-06 上海市地下空间设计研究总院有限公司 Municipal Engineering Construction progress msg management method and system based on BIM
CN107818198A (en) * 2017-09-27 2018-03-20 中建三局基础设施工程有限公司 A kind of science of bridge building management platform based on BIM technology
CN108596423A (en) * 2018-03-02 2018-09-28 重庆机电装备技术研究院有限公司 A kind of trackways engineering construction progress msg management method based on BIM
CN111369158A (en) * 2019-12-30 2020-07-03 中铁四局集团有限公司 BIM-based informatization quality management method and system

Similar Documents

Publication Publication Date Title
CN101916299B (en) Three-dimensional spatial data storage and management method based on file system
CN102103497B (en) Finite state machine actuating device and method, and method for establishing and using finite state machine
CN111858615B (en) Database table generation method, system, computer system and readable storage medium
KR102042230B1 (en) Synchronizing local and remote data
CN108563697B (en) Data processing method, device and storage medium
CN105447051A (en) Database operation method and device
US9740994B2 (en) Simulation of supply chain plans using data model
CN111339561B (en) Data processing method, electronic device and storage medium
CN105631019A (en) Metadata extension method and device
CN107832440A (en) A kind of data digging method, device, server and computer-readable recording medium
US9595014B1 (en) System and method for executing workflow instance and modifying same during execution
CN105095515A (en) Bucket dividing method, device and equipment supporting fast query of Map-Reduce output result
CN116414316B (en) Illusion engine rendering method based on BIM model in digital city
CN111191050B (en) Knowledge graph ontology model construction method and device
CN112541733A (en) Engineering construction stage management control method based on BIM
CN104123135A (en) Method and device for unifying background interfaces
CN102456023A (en) Method and system for searching user information
CN112988278B (en) Meta file modification method and device of resource file, electronic equipment and storage medium
CN110955736B (en) Management model modeling method of basic data
CN112001022A (en) BIM model-based rapid splitting method and system
US20120072227A1 (en) Automatically generating high quality soa design from business process maps based on specified quality goals
US9785894B2 (en) Simulation of supply chain plans using web service
CN114820079B (en) Crowd determination method, device, equipment and medium
CN117992453A (en) Naming generation method, device, equipment and storage medium based on data center
US8473419B1 (en) Dependency resolution in publish/subscribe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210323

RJ01 Rejection of invention patent application after publication