CN105976089A - Construction data classification system based on building information model and method thereof - Google Patents
Construction data classification system based on building information model and method thereof Download PDFInfo
- Publication number
- CN105976089A CN105976089A CN201610270360.2A CN201610270360A CN105976089A CN 105976089 A CN105976089 A CN 105976089A CN 201610270360 A CN201610270360 A CN 201610270360A CN 105976089 A CN105976089 A CN 105976089A
- Authority
- CN
- China
- Prior art keywords
- information
- construction
- sort module
- pels
- bim
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 89
- 238000000034 method Methods 0.000 title claims abstract description 12
- 238000007726 management method Methods 0.000 claims description 62
- 239000000463 material Substances 0.000 claims description 9
- 238000013468 resource allocation Methods 0.000 claims description 7
- 239000004035 construction material Substances 0.000 claims description 6
- 238000005516 engineering process Methods 0.000 claims description 6
- 238000001514 detection method Methods 0.000 claims description 3
- 238000012407 engineering method Methods 0.000 claims description 3
- 238000007689 inspection Methods 0.000 claims description 3
- 238000012544 monitoring process Methods 0.000 claims description 3
- 238000011022 operating instruction Methods 0.000 claims description 3
- 230000029058 respiratory gaseous exchange Effects 0.000 claims description 3
- 238000012360 testing method Methods 0.000 claims description 3
- 238000013439 planning Methods 0.000 claims description 2
- 238000012800 visualization Methods 0.000 abstract description 5
- 230000000694 effects Effects 0.000 abstract description 2
- 230000001360 synchronised effect Effects 0.000 abstract 1
- 238000013523 data management Methods 0.000 description 4
- 238000012423 maintenance Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 150000001875 compounds Chemical class 0.000 description 1
- 238000009430 construction management Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 238000004088 simulation Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- General Business, Economics & Management (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Entrepreneurship & Innovation (AREA)
- General Physics & Mathematics (AREA)
- Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- General Health & Medical Sciences (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a construction data classification system based on a building information model and a method thereof. The construction data classification system comprises a progress classification module which stores construction progress plan information. The progress classification module configures a time shaft and associates the construction progress information with all the graphic elements on the time shaft. In the invention, visualization and integrated classification of a model and project management information are realized, which means that through defining the building information model, associating construction information of each element of project management, classifying the construction information and endowing a time dimension, a synchronous display effect of the model and the construction information is reached.
Description
Technical field
The present invention relates to construction engineering technical field.Based on BIM execute it is more particularly related to a kind of
Wage material categorizing system and method.
Background technology
Engineering construction data gradually forms in Process of Engineering Construction, is the protocol of Process of Engineering Construction.It is not only
The evidence of unit in charge of construction's quality responsibility, the reliable voucher that completion of works is checked and accepted, settled accounts especially.And whole engineering construction duration is more
Grow, part-to-item project is the most various, technology is the most complicated, construction information is the most.How standard construction data formation,
Work out, collect, arrange and filing-up work, it is ensured that the verity of data management, integrity, accuracy and systematicness, make to execute
The work of work data management runs through engineering construction overall process, will be one of key issue of facing of engineering project information construction.
At present, construction information manages mainly two kinds of forms: papery version data and the electronic edition data of two dimension.Its shortcoming is,
The easy distortion of papery version data, fragile loss, be difficult to preserve, not easy-to-search etc., the electronic edition data of two dimension is easily obscured, is managed
Reason maintenance difficulties is big, and above-mentioned data management relies on concrete documenter, and data management isolates, and is difficulty with data in time altogether
Enjoy.
BIM (BIM) is the numeral expression to construction project physics and functional characteristic, has shared knowledge money
Source, it is possible to share the information of construction project, it is possible to provide reliable basis for the decision-making in Whole Life Cycle of Projects.In project
Different phase, the different interests related side of project can give in BIM, extract and maintenance information, to support and to reflect each
Work compound in scope of offical duty.Therefore, Visualization Model based on BIM, multidimensional information integrated technology, utilize mould
Type pel structure tree, with model as carrier with index, the structured management and the automatization that carry out engineering construction data read, real
Existing engineering construction data effectively manages and shares, and has great engineering information management value.
Summary of the invention
It is an object of the invention to solve at least the above, and the advantage that at least will be described later is provided.
It is a still further object of the present invention to provide a kind of 3D realized engineering is in kind and visualize inquiry, the 4D of project progress
The visualization construction information classification of virtual emulation, engineering safety.
In order to realize according to object of the present invention and further advantage, it is provided that a kind of construction based on BIM provides
Material categorizing system, the building that the simulation of described BIM is to be onstructed, include the figure of at least one engineering structure object
Unit, described construction information categorizing system includes:
Progress sort module, it stores construction schedule information, described progress sort module axle setup time, and by described
Construction speed information is associated on the time axis with all described pels.
Being preferably based on the construction information categorizing system of BIM, also include: resource distribution sort module, it is deposited
Storage resource allocation information, described resource distribution sort module is relevant to all described pels by described storage resource configuration information
Connection, described resource allocation information includes that construction material itemized bill, construction material collect inventory, workmen's inventory and execute
Work machinery inventory;
Telling somebody what one's real intentions are sort module, its storage is told somebody what one's real intentions are information, described in tell somebody what one's real intentions are sort module by described information and all described pels of telling somebody what one's real intentions are
Be associated, described in the information of telling somebody what one's real intentions are include construction technology, engineering method video, technologic material, safe material, acceptance criteria, equipment
Operating instruction and the data of two dimension drawing;
Quality management sort module, it stores quality management information, and described quality management is believed by described quality management sort module
Breath be associated with all described pels, described quality management information include inspection lot, builder's diary, test in laboratory content and
The file of the amount of backbreaking detection content;And
Safety management sort module, it stores safety management information, and described safety management is believed by described safety management sort module
Breath is associated with all described pels, and described safety management information includes geologic prediction information, safe measures to rectify and reform, monitoring parameter
Survey and the safety management information of advance geologic prediction.
It is preferably based on the construction information categorizing system of BIM, also includes: construction top control module, it is with described
Progress sort module, described resource distribution sort module, described quality management sort module, described safety management sort module
Being associated, described construction top control module includes adding keyword message unit, and described keyword message unit is for according to submodule
Block title and the construction information of date inquiries submodule.
Preferably, described construction speed information includes that the engineering time planning under construction speed, workmen, construction machinery are joined
Number and the information of job site photo.
Preferably, described construction speed information also includes the engineering time under current construction speed, workmen, construction machinery
Parameter and the information of job site photo.
The present invention also provides for the sorting technique of a kind of construction information categorizing system based on BIM, it is characterised in that
Comprise the following steps:
S1, by modeling tool formulate modeling scheme, complete BIM, to BIM according to physics or merit
Characteristic can be divided into several pels;
S2, collection construction schedule information;And
The construction schedule information that all pels that step S1 is obtained by S3, progress sort module and step S2 obtain time
It is associated on countershaft, to constitute 4D model.
6, sorting technique as claimed in claim 5, it is characterised in that also include:
S4, collection resource allocation information;
All pels that step S1 is obtained by S5, resource distribution sort module and step S4 obtain described storage resource distribution letter
Manner of breathing associates;
S6, collect and tell somebody what one's real intentions are information;
All pels that step S1 is obtained by S7, sort module of telling somebody what one's real intentions are obtain with step S6 described in the information of telling somebody what one's real intentions are be associated;
S8, collection quality management information
All pels that step S1 is obtained by S9, quality management sort module and step S8 obtain described quality management information phase
Association;
S10, collection safety management information;
All pels that step S1 is obtained by S11, safety management sort module and step S10 obtain described quality management information
It is associated.
The present invention at least includes following beneficial effect:
Achieve model and the visualization of Project Management Information and Ensemble classifier, i.e. by definition building information model, association
The construction information of each key element of project management, classifies to construction information and gives time dimension, reaches model and construction information
Synchronize bandwagon effect.
Achieve to the in kind 3D visualization inquiry of engineering, the 4D virtual emulation of project progress, engineering safe can
Telling somebody what one's real intentions are depending on change, the construction management information such as the progress of integration engineering project, resource distribution, quality, safety also gives building letter
Breath model, reaches engineering information n D integrated management level, it is provided that the construction information classification stage of project coordination sharing in many ways.
Part is embodied by the further advantage of the present invention, target and feature by description below, and part also will be by the present invention
Research and practice and be understood by the person skilled in the art.
Detailed description of the invention
Below in conjunction with embodiment, the present invention is described in further detail, to make those skilled in the art with reference to description word
Can implement according to this.
The present invention provides the embodiment of a kind of construction information categorizing system based on BIM, described BIM
Simulating building to be onstructed, include the pel of at least one physics or functional characteristic, such as one bridge includes bridge pier, bridge
The pel such as platform, bridge floor, described construction information categorizing system includes:
Progress sort module, it stores construction schedule information, described progress sort module axle setup time, and by described
Construction speed information is associated on the time axis with all described pels.
This construction information categorizing system also includes: resource distribution sort module, its storage resource configuration information, and described resource is joined
Putting sort module to be associated with all described pels by described storage resource configuration information, described resource allocation information includes construction
Material specification inventory, construction material collect inventory, workmen's inventory and construction machinery inventory;
Telling somebody what one's real intentions are sort module, its storage is told somebody what one's real intentions are information, described in tell somebody what one's real intentions are sort module by described information and all described pels of telling somebody what one's real intentions are
Be associated, described in the information of telling somebody what one's real intentions are include construction technology, engineering method video, technologic material, safe material, acceptance criteria, equipment
Operating instruction and the data of two dimension drawing;
Quality management sort module, it stores quality management information, and described quality management is believed by described quality management sort module
Breath be associated with all described pels, described quality management information include inspection lot, builder's diary, test in laboratory content and
The file of the amount of backbreaking detection content;And
Safety management sort module, it stores safety management information, and described safety management is believed by described safety management sort module
Breath is associated with all described pels, and described safety management information includes geologic prediction information, safe measures to rectify and reform, monitoring parameter
Survey and the safety management information of advance geologic prediction.
This construction information categorizing system also includes: construction top control module, itself and described progress sort module, described resource distribution
Sort module, described quality management sort module, described safety management sort module are associated, described construction top control module bag
Including interpolation keyword message unit, described keyword message unit is for executing according to submodule title and date inquiries submodule
Wage material.
Described construction speed information includes engineering time, workmen, the construction machinery parameter planned under construction speed and executes
The information of work scene photograph.
Described construction speed information also include the engineering time under current construction speed, workmen, construction machinery parameter and
The information of job site photo.
The present invention also provides for the sorting technique of a kind of construction information categorizing system based on BIM, including following step
Rapid:
S1, by modeling tool formulate modeling scheme, complete BIM, to BIM according to physics or merit
Characteristic can be divided into several pels;
S2, collection construction schedule information;And
The construction schedule information that all pels that step S1 is obtained by S3, progress sort module and step S2 obtain time
It is associated on countershaft, to constitute 4D model.
S4, collection resource allocation information;
All pels that step S1 is obtained by S5, resource distribution sort module and step S4 obtain described storage resource distribution letter
Manner of breathing associates;
S6, collect and tell somebody what one's real intentions are information;
All pels that step S1 is obtained by S7, sort module of telling somebody what one's real intentions are obtain with step S6 described in the information of telling somebody what one's real intentions are be associated;
S8, collection quality management information
All pels that step S1 is obtained by S9, quality management sort module and step S8 obtain described quality management information phase
Association;
S10, collection safety management information;
All pels that step S1 is obtained by S11, safety management sort module and step S10 obtain described quality management information
It is associated.
Although embodiment of the present invention are disclosed as above, but it is not restricted in description and embodiment listed fortune
With, it can be applied to various applicable the field of the invention completely, for those skilled in the art, and can be easily
Realizing other amendment, therefore under the general concept limited without departing substantially from claim and equivalency range, the present invention does not limit
In specific details with shown here as the embodiment with description.
Claims (7)
1. a construction information categorizing system based on BIM, described BIM simulates to be onstructed building
Build thing, include the pel of at least one engineering structure object, it is characterised in that described construction information categorizing system includes:
Progress sort module, it stores construction schedule information, described progress sort module axle setup time, and by described
Construction speed information is associated on the time axis with all described pels.
2. construction information categorizing system based on BIM as claimed in claim 1, it is characterised in that also wrap
Including: resource distribution sort module, its storage resource configuration information, described storage resource is joined by described resource distribution sort module
Confidence breath is associated with all described pels, and described resource allocation information includes that construction material itemized bill, construction material collect
Inventory, workmen's inventory and construction machinery inventory;
Telling somebody what one's real intentions are sort module, its storage is told somebody what one's real intentions are information, described in tell somebody what one's real intentions are sort module by described information and all described pels of telling somebody what one's real intentions are
Be associated, described in the information of telling somebody what one's real intentions are include construction technology, engineering method video, technologic material, safe material, acceptance criteria, equipment
Operating instruction and the data of two dimension drawing;
Quality management sort module, it stores quality management information, and described quality management is believed by described quality management sort module
Breath be associated with all described pels, described quality management information include inspection lot, builder's diary, test in laboratory content and
The file of the amount of backbreaking detection content;And
Safety management sort module, it stores safety management information, and described safety management is believed by described safety management sort module
Breath is associated with all described pels, and described safety management information includes geologic prediction information, safe measures to rectify and reform, monitoring parameter
Survey and the safety management information of advance geologic prediction.
3. construction information categorizing system based on BIM as claimed in claim 2, it is characterised in that also wrap
Include: construction top control module, itself and described progress sort module, described resource distribution sort module, described quality management classification
Module, described safety management sort module are associated, and described construction top control module includes adding keyword message unit, described
Keyword message unit is for according to submodule title and the construction information of date inquiries submodule.
4. construction information categorizing system based on BIM as claimed in claim 1, it is characterised in that described
Construction speed information includes that engineering time, workmen, construction machinery parameter and the job site of planning under construction speed are shone
The information of sheet.
5. construction information categorizing system based on BIM as claimed in claim 4, it is characterised in that described
Construction speed information also includes the engineering time under current construction speed, workmen, construction machinery parameter and job site
The information of photo.
6. a sorting technique for construction information categorizing system based on BIM as claimed in claim 5, its
It is characterised by, comprises the following steps:
S1, by modeling tool formulate modeling scheme, complete BIM, to BIM according to physics or merit
Characteristic can be divided into several pels;
S2, collection construction schedule information;And
The construction schedule information that all pels that step S1 is obtained by S3, progress sort module and step S2 obtain time
It is associated on countershaft, to constitute 4D model.
7. sorting technique as claimed in claim 6, it is characterised in that also include:
S4, collection resource allocation information;
All pels that step S1 is obtained by S5, resource distribution sort module and step S4 obtain described storage resource distribution letter
Manner of breathing associates;
S6, collect and tell somebody what one's real intentions are information;
All pels that step S1 is obtained by S7, sort module of telling somebody what one's real intentions are obtain with step S6 described in the information of telling somebody what one's real intentions are be associated;
S8, collection quality management information
All pels that step S1 is obtained by S9, quality management sort module and step S8 obtain described quality management information phase
Association;
S10, collection safety management information;
All pels that step S1 is obtained by S11, safety management sort module and step S10 obtain described quality management information
It is associated.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610270360.2A CN105976089A (en) | 2016-04-27 | 2016-04-27 | Construction data classification system based on building information model and method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610270360.2A CN105976089A (en) | 2016-04-27 | 2016-04-27 | Construction data classification system based on building information model and method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105976089A true CN105976089A (en) | 2016-09-28 |
Family
ID=56993719
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610270360.2A Pending CN105976089A (en) | 2016-04-27 | 2016-04-27 | Construction data classification system based on building information model and method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105976089A (en) |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106384200A (en) * | 2016-09-27 | 2017-02-08 | 朱海涛 | BIM (Building Information Modeling) technology-based management and application method of construction multidimensional model |
CN106803150A (en) * | 2017-01-20 | 2017-06-06 | 上海市地下空间设计研究总院有限公司 | Municipal Engineering Construction progress msg management method and system based on BIM |
CN106845919A (en) * | 2016-12-16 | 2017-06-13 | 上海建工集团股份有限公司 | Construction information collection processing method |
CN106897534A (en) * | 2017-03-08 | 2017-06-27 | 蓝禹智慧建筑科技(北京)有限公司 | Construction speed methods of exhibiting and device |
CN106897453A (en) * | 2017-03-08 | 2017-06-27 | 朱海涛 | Engineering BIM progresses model and on-site supervision control methods |
CN107247757A (en) * | 2017-05-31 | 2017-10-13 | 上海建工四建集团有限公司 | Construction project document classification storage and retrieval method and system based on BIM |
CN107480370A (en) * | 2017-08-10 | 2017-12-15 | 嘉兴恒创电力设计研究院有限公司 | A kind of construction speed Forecasting Methodology and system based on BIM models |
CN107633382A (en) * | 2017-09-07 | 2018-01-26 | 苏州凯瑟兰特信息科技有限公司 | A kind of Construction Schedule management system and method |
CN107644124A (en) * | 2017-09-01 | 2018-01-30 | 中民筑友房屋科技有限公司 | A kind of method for making BIM |
CN108920559A (en) * | 2018-06-20 | 2018-11-30 | 深圳市关山月美术馆 | A kind of famous expert's chronology data management system |
CN109754181A (en) * | 2018-12-30 | 2019-05-14 | 国网北京市电力公司 | The treating method and apparatus of engineering project information |
CN110210771A (en) * | 2019-06-06 | 2019-09-06 | 重庆建工第九建设有限公司 | A kind of construction information management system and technique based on Building Information Model |
CN112053131A (en) * | 2020-09-07 | 2020-12-08 | 中国路桥工程有限责任公司 | Engineering project management system |
CN112541742A (en) * | 2020-12-21 | 2021-03-23 | 宁良武 | Building construction progress management method |
CN113157996A (en) * | 2020-01-23 | 2021-07-23 | 久瓴(上海)智能科技有限公司 | Document information processing method and device, computer equipment and readable storage medium |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104123502A (en) * | 2014-08-18 | 2014-10-29 | 中建安装工程有限公司 | Mechanical and electrical installation overall-planning system and method based on three-dimensional construction drawing model |
CN104166892A (en) * | 2014-06-19 | 2014-11-26 | 国家电网公司 | Engineering management and control method and system based on three-dimensional design system |
CN104680322A (en) * | 2015-02-13 | 2015-06-03 | 上海同筑信息科技有限公司 | Project acceptance system and method based on BIM |
CN104881751A (en) * | 2015-06-04 | 2015-09-02 | 北京建工土木工程有限公司 | System and method for construction material management based on building information model |
CN105335559A (en) * | 2015-10-28 | 2016-02-17 | 上海同筑信息科技有限公司 | Engineering standardized construction process control method and system on basis of BIM (building information modeling) |
-
2016
- 2016-04-27 CN CN201610270360.2A patent/CN105976089A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104166892A (en) * | 2014-06-19 | 2014-11-26 | 国家电网公司 | Engineering management and control method and system based on three-dimensional design system |
CN104123502A (en) * | 2014-08-18 | 2014-10-29 | 中建安装工程有限公司 | Mechanical and electrical installation overall-planning system and method based on three-dimensional construction drawing model |
CN104680322A (en) * | 2015-02-13 | 2015-06-03 | 上海同筑信息科技有限公司 | Project acceptance system and method based on BIM |
CN104881751A (en) * | 2015-06-04 | 2015-09-02 | 北京建工土木工程有限公司 | System and method for construction material management based on building information model |
CN105335559A (en) * | 2015-10-28 | 2016-02-17 | 上海同筑信息科技有限公司 | Engineering standardized construction process control method and system on basis of BIM (building information modeling) |
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106384200A (en) * | 2016-09-27 | 2017-02-08 | 朱海涛 | BIM (Building Information Modeling) technology-based management and application method of construction multidimensional model |
CN106845919A (en) * | 2016-12-16 | 2017-06-13 | 上海建工集团股份有限公司 | Construction information collection processing method |
CN106803150A (en) * | 2017-01-20 | 2017-06-06 | 上海市地下空间设计研究总院有限公司 | Municipal Engineering Construction progress msg management method and system based on BIM |
CN106897534B (en) * | 2017-03-08 | 2020-04-14 | 蓝禹智慧建筑科技(北京)有限公司 | Construction progress display method and device |
CN106897534A (en) * | 2017-03-08 | 2017-06-27 | 蓝禹智慧建筑科技(北京)有限公司 | Construction speed methods of exhibiting and device |
CN106897453A (en) * | 2017-03-08 | 2017-06-27 | 朱海涛 | Engineering BIM progresses model and on-site supervision control methods |
CN107247757A (en) * | 2017-05-31 | 2017-10-13 | 上海建工四建集团有限公司 | Construction project document classification storage and retrieval method and system based on BIM |
CN107480370A (en) * | 2017-08-10 | 2017-12-15 | 嘉兴恒创电力设计研究院有限公司 | A kind of construction speed Forecasting Methodology and system based on BIM models |
CN107644124A (en) * | 2017-09-01 | 2018-01-30 | 中民筑友房屋科技有限公司 | A kind of method for making BIM |
CN107633382A (en) * | 2017-09-07 | 2018-01-26 | 苏州凯瑟兰特信息科技有限公司 | A kind of Construction Schedule management system and method |
CN108920559A (en) * | 2018-06-20 | 2018-11-30 | 深圳市关山月美术馆 | A kind of famous expert's chronology data management system |
CN109754181A (en) * | 2018-12-30 | 2019-05-14 | 国网北京市电力公司 | The treating method and apparatus of engineering project information |
CN110210771A (en) * | 2019-06-06 | 2019-09-06 | 重庆建工第九建设有限公司 | A kind of construction information management system and technique based on Building Information Model |
CN110210771B (en) * | 2019-06-06 | 2023-02-03 | 重庆建工第九建设有限公司 | Construction data management system and method based on building information model |
CN113157996A (en) * | 2020-01-23 | 2021-07-23 | 久瓴(上海)智能科技有限公司 | Document information processing method and device, computer equipment and readable storage medium |
CN113157996B (en) * | 2020-01-23 | 2022-09-16 | 久瓴(上海)智能科技有限公司 | Document information processing method and device, computer equipment and readable storage medium |
CN112053131A (en) * | 2020-09-07 | 2020-12-08 | 中国路桥工程有限责任公司 | Engineering project management system |
CN112541742A (en) * | 2020-12-21 | 2021-03-23 | 宁良武 | Building construction progress management method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105976089A (en) | Construction data classification system based on building information model and method thereof | |
Lu et al. | Semi-automatic geometric digital twinning for existing buildings based on images and CAD drawings | |
CN104657563B (en) | The intelligentized design platform and its intellectualized design method of a kind of photovoltaic plant | |
CN107818198A (en) | A kind of science of bridge building management platform based on BIM technology | |
CN103984333B (en) | A kind of power plant monitoring and control management system | |
CN103646154A (en) | Three-dimensional digitization final assembly technology collaborative design system | |
Kamari et al. | AI-based risk assessment for construction site disaster preparedness through deep learning-based digital twinning | |
Shim et al. | Three-dimensional information model-based bridge engineering in Korea | |
CN106371456A (en) | Unmanned plane patrol method and system | |
Ahmad et al. | Building information modelling implementation plans a comparative analysis | |
CN109472483A (en) | A kind of building-site modeling method and system based on BIM model and technology of taking photo by plane | |
CN106774170B (en) | A kind of generation system of three-dimensional mechanical processing technique | |
CN109784758A (en) | Construction quality supervision early warning system and method based on BIM model | |
CN112988865B (en) | Industrial Internet service management system | |
CN104537131A (en) | Data collection method for satellite final assembly process | |
WO2024016877A1 (en) | Roadside sensing simulation system for vehicle-road collaboration | |
CN115858651A (en) | Support platform is used in integration of wisdom city | |
Piron et al. | Industry 4.0 and life cycle assessment: Evaluation of the technology applications as an asset for the life cycle inventory | |
CN106295006A (en) | A kind of product design system | |
Слесарев et al. | PROSPECTS FOR THE DEVELOPMENT OF THE REGULATORY FRAMEWORK OF INFORMATION SYSTEMS FOR" GREEN" STANDARDIZATION | |
Grishina et al. | Monitoring of the construction site using an information model | |
Li | Research on the Development of Digital Twins in Construction Industry | |
Lässig et al. | The ArchIBALD Data Integration Platform: Bridging Fragmented Processes in the Building Industry | |
Wan et al. | Application of “BIM+” Architecture Based on Cloud Technology in Intelligent Management of Rail Transit | |
Voronin et al. | Virtual Simulator for Making Castings Without Cracks Skills Development |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160928 |
|
RJ01 | Rejection of invention patent application after publication |