Construction speed methods of exhibiting and device Download PDFInfo
- Publication number
- CN106897534A CN106897534A CN201710135077.3A CN201710135077A CN106897534A CN 106897534 A CN106897534 A CN 106897534A CN 201710135077 A CN201710135077 A CN 201710135077A CN 106897534 A CN106897534 A CN 106897534A
- Authority
- CN
- China
- Prior art keywords
- construction
- module
- information
- models
- identity information
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 253
- 238000000034 method Methods 0.000 title claims abstract description 55
- 230000001747 exhibiting effect Effects 0.000 title claims abstract description 22
- 238000004891 communication Methods 0.000 claims abstract description 11
- 239000004035 construction material Substances 0.000 claims description 43
- 230000002159 abnormal effect Effects 0.000 claims description 15
- 239000000463 material Substances 0.000 claims description 8
- 230000005540 biological transmission Effects 0.000 claims description 4
- 230000000007 visual effect Effects 0.000 claims description 3
- 238000009435 building construction Methods 0.000 claims 1
- 230000015654 memory Effects 0.000 description 16
- 238000010586 diagram Methods 0.000 description 9
- 230000006870 function Effects 0.000 description 9
- 238000013461 design Methods 0.000 description 5
- 238000003860 storage Methods 0.000 description 5
- 230000008569 process Effects 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 230000008901 benefit Effects 0.000 description 2
- 230000008859 change Effects 0.000 description 2
- 238000004590 computer program Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000009471 action Effects 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 239000003086 colorant Substances 0.000 description 1
- 238000009430 construction management Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 230000002452 interceptive effect Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Physics & Mathematics (AREA)
- Strategic Management (AREA)
- Theoretical Computer Science (AREA)
- Human Resources & Organizations (AREA)
- General Physics & Mathematics (AREA)
- Geometry (AREA)
- Tourism & Hospitality (AREA)
- Computer Hardware Design (AREA)
- General Business, Economics & Management (AREA)
- Marketing (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Architecture (AREA)
- Mathematical Optimization (AREA)
- Primary Health Care (AREA)
- General Health & Medical Sciences (AREA)
- Structural Engineering (AREA)
- Computational Mathematics (AREA)
- Mathematical Analysis (AREA)
- Civil Engineering (AREA)
- Pure & Applied Mathematics (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Data Mining & Analysis (AREA)
- Health & Medical Sciences (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention provides a kind of construction speed methods of exhibiting and device, is applied to the displaying terminal being connected with least one communication of mobile terminal, and the displaying terminal includes that a job site shows interface, and methods described includes:Building 3D models are obtained, multiple construction modules are split as by 3D models are built according to construction structure;Receive the construction speed information that mobile terminal sends;The identity information of the construction director in the construction speed information is verified with the identity information of construction module according to the module relationship table;When being verified, the construction module for matching is shown on the displaying interface of the job site.Shown by receiving the construction speed information that Field Force's mobile terminal sends, and construction speed being simulated on building 3D models according to the construction speed information.In this way, can intuitively and accurately to the progress and live details of administrative staff's reflection construction.
Description
Technical field
The present invention relates to 3D modelling techniques field, in particular to a kind of construction speed methods of exhibiting and device.
Background technology
The progress management and control of construction is important step in construction management, to the accuracy of construction speed acquisition of information and i.e.
Management and control of the direct Image Management personnel of when property to engineering.Site operation is only reflected by data or writing record in the prior art
Situation, not directly perceived to practice of construction progress or the reflection of job site situation, it is existing that administrative staff can not timely and accurately obtain construction
The actual conditions of field.
The content of the invention
In order to overcome above-mentioned deficiency of the prior art, it is an object of the invention to a kind of construction speed methods of exhibiting, should
For the displaying terminal that the communication of mobile terminal with least one Field Force is connected, the displaying terminal includes a job site
Displaying interface, methods described includes:
Building 3D models are obtained, multiple construction modules are split as by 3D models are built according to construction structure, its
In, each described construction module has unique identity information;
A module relationship table is set up, the module relationship table includes corresponding with each construction module identity information
The identity information of construction director;
The construction speed information that mobile terminal sends is received, the construction speed information includes the identity letter of construction director
The identity information of breath and construction module to be shown;
The identity information of the construction director in the construction speed information is applied with building according to the module relationship table
The identity information of work module is verified;
When being verified, the construction module is shown on the displaying interface of the job site.
Further, in the above-mentioned methods, the construction module also includes the corresponding progress of different progress percentages
Dispaly state, the progress dispaly state includes the visual display effect of the current construction speed of construction module;It is described to apply
Also include progress percentage in work progress msg;It is described the construction module is entered on the displaying interface of the job site
The step of row display, including:
Corresponding progress dispaly state is shown in the construction module being verified according to the progress percentage.
Further, in the above-mentioned methods, the workmen of the construction module is also included in construction speed information
Information, workmen's information includes constructor's number;It is described to show on interface to the construction in the job site
The step of module is shown, also includes:
Applying for the construction module is shown in the corresponding construction module according to workmen's information
Workman's number is identified.
Further, in the above-mentioned methods, workmen's information include, the work post information of each workmen;It is described
The construction number mark of the construction module is shown in the corresponding construction module according to workmen's information
Know step, including:
The construction number mark of the construction module is shown in the construction module, and to the people of different work posts
Number is differently shown.
Further, in the above-mentioned methods, methods described also includes:
The construction abnormal information that mobile terminal sends is received, the construction abnormal information includes the construction mould of exception
The identity information of block;
Abnormal construction module is identified in the building 3D models.
Further, in the above-mentioned methods, the job site displaying interface is additionally operable to display according to construction equipment foundation
Construction equipment 3D models;Methods described, also includes:
The configuration information of the construction equipment that mobile terminal sends is received, the configuration information of the construction equipment includes construction
The identity information of equipment 3D models and equipment display location;
According to construction equipment configuration information, what construction equipment configuration information described in displaying interface was specified at the construction field (site) sets
The construction equipment 3D models are shown on standby display location.
Further, in the above-mentioned methods, the job site displaying interface is additionally operable to display according to construction equipment foundation
Construction material stack 3D models;Methods described also includes:
The construction material stacking information that mobile terminal sends is received, the construction material stacking information includes construction material
Stack identity information and the placing of material position of 3D models;
Information is stacked according to the construction material, shows that construction material described in interface is stacked information and specified at the construction field (site)
Placing of material position on show that the construction material stacks 3D models.
Further, in the above-mentioned methods, the displaying terminal also includes that a map shows interface, and methods described is also wrapped
Include:
The construction material transit information that mobile terminal sends is received, the construction material transit information includes construction material
Transporting position;
According to the construction material transit information, the traffic condition of construction material is shown on map displaying interface.
Further, in the above-mentioned methods, the displaying terminal also includes a construction speed preview interface;Methods described is also
Including:
For the construction module specifies Estimated Time Of Completion;
Estimated Time Of Completion and selected preview time point according to construction module, in the construction speed preview interface
Show that corresponding construction module forms preview model.
Another object of the present invention is to provide a kind of construction speed exhibiting device, it is applied to and at least one mobile terminal
The displaying terminal of communication connection, the displaying terminal includes that a job site shows interface, and described device includes:
Model acquisition module, for obtain building 3D models, according to construction structure will build 3D models be split as it is many
Individual construction module, wherein, each described construction module has unique identity information;
Relation table sets up module, and for setting up a module relationship table, the module relationship table includes being applied with each building
The corresponding mobile terminal identity information of work module identity information;
Receiver module, the construction speed information for receiving mobile terminal transmission, the construction speed information includes construction
The identity information of the identity information of director and construction module to be shown;
Authentication module, for according to the module relationship table to the mobile terminal identity information in the construction speed information
Identity information with construction module is verified;
Display module, for when being verified, to the construction mould of matching on the displaying interface of the job site
Block is shown.
In terms of existing technologies, the invention has the advantages that:
Construction speed methods of exhibiting and device that the present invention is provided, receive Field Force's mobile terminal and send out by displaying terminal
The construction speed information sent, and displaying is simulated to construction speed on building 3D models according to the construction speed information.
In this way, can intuitively and accurately to the progress and live details of administrative staff's reflection construction.
Brief description of the drawings
Technical scheme in order to illustrate more clearly the embodiments of the present invention, below will be attached to what is used needed for embodiment
Figure is briefly described, it will be appreciated that the following drawings illustrate only certain embodiments of the present invention, thus be not construed as it is right
The restriction of scope, for those of ordinary skill in the art, on the premise of not paying creative work, can also be according to this
A little accompanying drawings obtain other related accompanying drawings.
Fig. 1 is displaying terminal provided in an embodiment of the present invention interacts schematic diagram with mobile terminal;
Fig. 2 is displaying terminal schematic diagram provided in an embodiment of the present invention;
Fig. 3 is construction speed methods of exhibiting schematic flow sheet provided in an embodiment of the present invention;
Fig. 4 is construction speed exhibiting device schematic diagram provided in an embodiment of the present invention.
Icon:100- displaying terminals;110- construction speed exhibiting devices;111- model acquisition modules;112- relation tables are built
Formwork erection block;113- receiver modules;114- authentication modules;115- display modules;120- memories;130- processors;140- communicates
Unit;200- mobile terminals;300- networks.
Specific embodiment
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with the embodiment of the present invention
In accompanying drawing, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is
A part of embodiment of the present invention, rather than whole embodiments.Present invention implementation generally described and illustrated in accompanying drawing herein
The component of example can be arranged and designed with a variety of configurations.
Therefore, the detailed description of embodiments of the invention below to providing in the accompanying drawings is not intended to limit claimed
The scope of the present invention, but be merely representative of selected embodiment of the invention.Based on the embodiment in the present invention, this area is common
The every other embodiment that technical staff is obtained under the premise of creative work is not made, belongs to the model of present invention protection
Enclose.
It should be noted that:Similar label and letter represents similar terms in following accompanying drawing, therefore, once a certain Xiang Yi
It is defined in individual accompanying drawing, then it need not be further defined and explained in subsequent accompanying drawing.
In the description of the invention, in addition it is also necessary to explanation, unless otherwise clearly defined and limited, term " setting ",
" installation ", " connected ", " connection " should be interpreted broadly, for example, it may be fixedly connected, or be detachably connected, or one
The connection of body ground;Can mechanically connect, or electrically connect;Can be joined directly together, it is also possible to indirect by intermediary
It is connected, can is two connections of element internal.For the ordinary skill in the art, can be with concrete condition understanding
State term concrete meaning in the present invention.
As shown in figure 1, being that the displaying terminal 100 that present pre-ferred embodiments are provided communicates with an at least mobile terminal 200
Interactive schematic diagram.The displaying terminal 100 can be communicated by network 300 with the mobile terminal 200, to realize displaying
Data communication between terminal 100 and mobile terminal 200 is interacted.
In the present embodiment, the displaying terminal 100 may be, but not limited to, PC (personal computer,
PC), web (website) server, ftp (file transfer protocol, FTP) server etc..The movement
Terminal 200 may be, but not limited to, smart mobile phone, panel computer, personal digital assistant (personal digital
Assistant, PDA), mobile internet surfing equipment (mobile Internet device, MID) etc..
As shown in Fig. 2 being the block diagram of the displaying terminal 100 shown in Fig. 1.The displaying terminal 100 includes construction
Progress display device 110, memory 120, processor 130, communication unit 140.
The memory 120, processor 130 and each element of communication unit 140 are directly or indirectly electrical each other
Connection, to realize the transmission or interaction of data.For example, these elements each other can be by one or more communication bus or letter
Number line is realized being electrically connected with.The construction speed exhibiting device 110 can be with software or firmware (firmware) including at least one
Form be stored in the memory 120 or be solidificated in the operating system (operating of the displaying terminal 100
System, OS) in software function module.The processor 130 is used to perform the executable mould stored in the memory 120
Block, such as software function module and computer program included by described construction speed exhibiting device 110 etc..
Wherein, the memory 120 may be, but not limited to, random access memory (RandomAccess Memory,
RAM), read-only storage (Read Only Memory, ROM), programmable read only memory (Programmable Read-Only
Memory, PROM), erasable read-only memory (Erasable Programmable Read-Only Memory, EPROM),
Electricallyerasable ROM (EEROM) (Electric Erasable Programmable Read-Only Memory, EEPROM) etc..
Wherein, memory 120 is used for storage program, and the processor 130 performs described program after execute instruction is received.
The communication unit 140 be used for by the network 300 set up the displaying terminal 100 and mobile terminal 200 it
Between communication connection, and for by the transceiving data of the network 300.
Fig. 3 is refer to, Fig. 3 is that the flow of the construction speed methods of exhibiting for being applied to displaying terminal 100 shown in Fig. 1 is illustrated
Figure, the specific steps to methods described are described in detail below.
Step S110, obtains building 3D models, will build 3D models according to construction structure and be split as multiple buildings and apply
Work module, wherein, each described construction module has unique identity information.
Specifically, in the present embodiment, it is described 3D models will be built according to construction structure be split as multiple buildings apply
Work module can be including ground, raft plate, post, beam, wall, metope etc..
Step S120, sets up a module relationship table, and the module relationship table includes and each construction module identity
The identity information of the corresponding construction director of information.
Specifically, in the present embodiment, it is necessary to receive Field Force mobile terminal 200 send construction speed information with
The displaying of 3D models is carried out, in order to ensure that Field Force is corresponding with the construction module, therefore a module relationship table is set up
Record is responsible for the corresponding relation of each construction module and site operation director.Wherein, the identity letter of the construction director
Breath is etc. the number, ID registered in advance of user of service's mobile terminal 200.
Step S130, receives the construction speed information that mobile terminal 200 sends, and the construction speed information includes that construction is negative
Blame the identity information of people and the identity information of construction module to be shown.
Specifically, in the present embodiment, when needing to update site operation progress situation, site operation director is led to
Cross mobile terminal 200 and send construction speed information to the displaying terminal 100, the condition of construction at scene is reported to the displaying
Terminal 100.
Step S140, according to the module relationship table in the construction speed information construction director identity information
Identity information with construction module is verified.
Specifically, for the director that prevents from constructing carries out wrong modification to non-oneself responsible construction module, in this implementation
In example, the displaying terminal 100 verifies the identity information and construction module of construction director in the construction speed information
Corresponding relation.
Step S150, when being verified, enters on the displaying interface of the job site to the construction module for matching
Row display.
The construction module specified in the construction speed information of the displaying terminal 100 pairs shows, to represent
The construction module completes construction.
Further, in the present embodiment, the construction module also includes the corresponding progress of different progress percentages
Dispaly state, the progress dispaly state includes the visual display effect of the current construction speed of construction module, described to apply
Also include progress percentage in work progress msg.
The displaying terminal 100 shows corresponding according to the progress percentage in the construction module being verified
Progress dispaly state.Such as, the construction speed information includes completing 50% to certain wall construction, then the displaying terminal 100
The display of progress dispaly state 50% is carried out to the specified premise.
In the construction speed methods of exhibiting provided based on above-mentioned design, embodiment, the displaying terminal 100 receives scene and applies
The construction speed information that work director is sent by mobile terminal 200, then carries out building 3D according to the construction Credo information
The displaying of model.So so that administrative staff can accurately obtain entering for site operation by the way that the displaying terminal 100 is directly perceived
Degree situation, greatly facilitates administrative staff to the overall control of engineering.
Further, in the present embodiment, the personal information of construction module is also included in construction speed information, it is described
Workmen's information includes constructor's number.
The displaying terminal 100 shows that this is built according to workmen's information in the corresponding construction module
Build the construction number mark of construction module.Such as, the construction speed information includes that the construction number of certain wall is 3 people, described
Displaying terminal 100 shows 3 workmen's marks on the building 3D models, to represent that the wall is constructed by 3 people.
Further, in the present embodiment, workmen's information includes applying the work post information of each workman person.
The displaying terminal 100 shows the construction number mark of the construction module in the construction module,
And the number to different work posts is differently shown.Such as, in the case of above-mentioned, the workmen of certain wall includes the people of bricklayer's 2 and fortune
The people of defeated work 1, then the displaying terminal 100 pairs 3 workmens are differently shown by different colors.
In the construction speed methods of exhibiting provided based on above-mentioned design, embodiment, the displaying terminal 100 receives scene and applies
The corresponding informance that work director passes through mobile terminal 200 workmen for sending and module of constructing, and in the building 3D models
On corresponding mark display is carried out to workmen.In this way, administrative staff can intuitively be recognized by the displaying terminal 100
The distribution of site operation manpower, facilitates the scheduling and arrangement of manpower.
Further, in the present embodiment, the mobile terminal 200 can also send to the displaying terminal 100 and construct
Abnormal information, the construction abnormal information includes the identity information of the construction module of exception.Mobile terminal 200 is received to send out
The construction abnormal information sent, is identified in the building 3D models to abnormal construction module.Such as, certain wall construction
When going wrong, construction director sends the construction abnormal information of the wall, the displaying terminal 100 by mobile terminal 200
After receiving the construction abnormal information, to being identified to the abnormal wall in the building 3D models.
In the construction speed methods of exhibiting provided based on above-mentioned design, embodiment, the displaying terminal 100 receives scene and applies
Work director sends construction abnormal information by mobile terminal 200, and to abnormal construction module on the building 3D models
Carry out alarm identifier.In this way, administrative staff intuitively can in time have found the situation at scene by the displaying terminal 100, can
And when processed for problem.
Further, in the present embodiment, the job site displaying interface is additionally operable to display according to construction equipment foundation
Construction equipment 3D models.
The displaying terminal 100 receives the configuration information of the construction equipment that mobile terminal 200 sends, the construction equipment
Configuration information includes identity information and the equipment display location of construction equipment 3D models.
The construction equipment information that the displaying terminal 100 pairs is received first is verified.Then, set according to construction equipment
Information, the construction is shown on the equipment display location that construction equipment configuration information is specified described in displaying interface at the construction field (site)
Equipment 3D models.Such as, construction director sends the configuration information of certain tower crane, the displaying terminal 100 by mobile terminal 200
Show the construction equipment 3D models of the corresponding position display tower crane in interface in the job site according to the configuration information.
Equally, the construction equipment that also the acceptable mobile terminal 200 sends of the displaying terminal 100 removes information, and
Remove the construction equipment 3D models shown on the job site displaying interface.
Further, in the present embodiment, the job site displaying interface is additionally operable to display according to construction equipment foundation
Construction material stack 3D models.
The displaying terminal 100 receives the construction material stacking information that mobile terminal 200 sends, and the construction material is stacked
Information includes that construction material stacks identity information and the placing of material position of 3D models.
Then, information is stacked according to the construction material, shows that construction material stacks letter described in interface at the construction field (site)
Show that the construction material stacks 3D models on the placing of material position that breath is specified.Such as, construction director passes through mobile terminal 200
The construction material for sending certain batch scaffolding steel pipe stacks information, and the displaying terminal 100 is stacked according to the construction material and believed
The construction material ceased in the corresponding position display batch scaffolding steel pipe in job site displaying interface stacks 3D models.
Further, in the present embodiment, the displaying terminal 100 also includes that a map shows interface.The displaying is eventually
End 100 receives the construction material transit information that mobile terminal 200 sends, and the construction material transit information includes using material
Transporting position.
Then according to the construction material transit information, the traffic condition of construction material on map displaying interface.
Such as, construction director sends the construction material transit information of certain car sandstone, the displaying terminal 100 by mobile terminal 200
According to the construction material transit information in the position of the map displaying interface display car sandstone.
In the construction speed methods of exhibiting provided based on above-mentioned design, embodiment, the displaying terminal 100 receives scene and applies
Work director sends stacking or the transit information of construction material by mobile terminal 200, and is shown accordingly.In this way, pipe
Reason personnel can be visually known stacking or the situation of construction material by the displaying terminal 100, convenient to construction material
Arrange or dispatch.
Further, in the present embodiment, the displaying terminal 100 also includes a construction speed preview interface.The exhibition
Show terminal 100 for the construction module specify Estimated Time Of Completion, then according to it is described construction module estimated completion when
Between and selected preview time point, show that corresponding construction module forms preview model in the construction speed preview interface.
In the construction speed methods of exhibiting provided based on above-mentioned design, embodiment, the displaying terminal 100 can simulate pre-
Look at the progress situation of following site operation, be the arrangement provided auxiliary of construction working.
Fig. 4 is refer to, the present embodiment also provides a kind of Construction Schedule exhibiting device 110, is applied to the exhibition shown in Fig. 1
Show terminal 100, the displaying terminal 100 includes that a job site shows interface, described device include model acquisition module 111,
Relation table sets up module 112, receiver module 113, authentication module 114 and display module 115.
The model acquisition module 111, for obtaining building 3D models, tears open according to construction structure by 3D models are built
It is divided into multiple construction modules, wherein, each described construction module has unique identity information.
The relation table sets up module 112, and for setting up a module relationship table, the module relationship table includes and each
The corresponding identity information of mobile terminal 200 of construction module identity information.
The receiver module 113, the construction speed information for receiving the transmission of mobile terminal 200, the construction speed letter
Breath includes the construct identity information of director and the identity information of construction module to be shown.
The authentication module 114, for according to the module relationship table to the mobile terminal in the construction speed information
200 identity informations are verified with the identity information of construction module.
The display module 115, for when being verified, to the building of matching on the displaying interface of the job site
Construction module is shown.
In sum, the present invention is provided construction speed methods of exhibiting and device 110, are connect by the displaying terminal 100
The construction speed information that Field Force's mobile terminal 200 sends is received, and according to the construction speed information on building 3D models
Construction speed is simulated and is shown.In this way, can intuitively and accurately to the progress and live details of administrative staff's reflection construction.
In embodiment provided herein, it should be understood that disclosed apparatus and method, it is also possible to by other
Mode realize.Device embodiment described above is only schematical, for example, the flow chart and block diagram in accompanying drawing show
Device, the architectural framework in the cards of method and computer program product, the function of multiple embodiments of the invention
And operation.At this point, each square frame in flow chart or block diagram can represent one the one of module, program segment or code
Point, a part for the module, program segment or code is used for the executable of the logic function that realization specifies comprising one or more
Instruction.It should also be noted that in some are as the implementation replaced, the function of being marked in square frame can also be with different from attached
The order marked in figure occurs.For example, two continuous square frames can essentially be performed substantially in parallel, they also may be used sometimes
To perform in the opposite order, this is depending on involved function.It is also noted that each in block diagram and/or flow chart
The combination of the square frame in square frame and block diagram and/or flow chart, can with perform the function of regulation or the special of action based on
The system of hardware is realized, or can be realized with the combination of computer instruction with specialized hardware.
In addition, each functional module in each embodiment of the invention can integrate to form an independent portion
Divide, or modules individualism, it is also possible to which two or more modules are integrated to form an independent part.
If the function is to realize in the form of software function module and as independent production marketing or when using, can be with
Storage is in a computer read/write memory medium.Based on such understanding, technical scheme is substantially in other words
The part contributed to prior art or the part of the technical scheme can be embodied in the form of software product, the meter
Calculation machine software product is stored in a storage medium, including some instructions are used to so that a computer equipment (can be individual
People's computer, server, or network equipment etc.) perform all or part of step of each embodiment methods described of the invention.
And foregoing storage medium includes:USB flash disk, mobile hard disk, read-only storage (ROM, Read-Only Memory), arbitrary access are deposited
Reservoir (RAM, Random Access Memory), magnetic disc or CD etc. are various can be with the medium of store program codes.
It should be noted that herein, such as first and second or the like relational terms are used merely to a reality
Body or operation make a distinction with another entity or operation, and not necessarily require or imply these entities or deposited between operating
In any this actual relation or order.And, term " including ", "comprising" or its any other variant be intended to
Nonexcludability is included, so that process, method, article or equipment including a series of key elements not only will including those
Element, but also other key elements including being not expressly set out, or also include being this process, method, article or equipment
Intrinsic key element.In the absence of more restrictions, the key element limited by sentence "including a ...", it is not excluded that
Also there is other identical element in process, method, article or equipment including the key element.
The preferred embodiments of the present invention are the foregoing is only, is not intended to limit the invention, for the skill of this area
For art personnel, the present invention can have various modifications and variations.It is all within the spirit and principles in the present invention, made any repair
Change, equivalent, improvement etc., should be included within the scope of the present invention.It should be noted that:Similar label and letter exists
Similar terms is represented in following accompanying drawing, therefore, once being defined in a certain Xiang Yi accompanying drawing, then it is not required in subsequent accompanying drawing
It is further defined and is explained.
The above, specific embodiment only of the invention, but protection scope of the present invention is not limited thereto, and it is any
Those familiar with the art the invention discloses technical scope in, change or replacement can be readily occurred in, should all contain
Cover within protection scope of the present invention.Therefore, protection scope of the present invention described should be defined by scope of the claims.
Claims (10)
1. a kind of construction speed methods of exhibiting, is applied to the displaying end being connected with the communication of mobile terminal of at least one Field Force
End, it is characterised in that the displaying terminal includes that a job site shows interface, and methods described includes:
Building 3D models are obtained, multiple construction modules are split as by 3D models are built according to construction structure, wherein, often
The individual construction module has unique identity information;
A module relationship table is set up, the module relationship table includes construction corresponding with each construction module identity information
The identity information of director;
Receive mobile terminal send construction speed information, the construction speed information include construction director identity information and
The identity information of construction module to be shown;
According to the module relationship table to identity information and the construction mould of the construction director in the construction speed information
The identity information of block is verified;
When being verified, the construction module is shown on the displaying interface of the job site.
2. method according to claim 1, it is characterised in that the construction module also includes different progress percentages
Corresponding progress dispaly state, the progress dispaly state includes that the visual presence of the current construction speed of construction module is imitated
Really;Also include progress percentage in the construction speed information;It is described to show on interface to the building in the job site
The step of construction module is shown, including:
Corresponding progress dispaly state is shown in the construction module being verified according to the progress percentage.
3. method according to claim 2, it is characterised in that also include the construction module in construction speed information
Workmen's information, workmen's information include constructor's number;It is described to show on interface to institute in the job site
The step of stating construction module and shown, also include:
The constructor of the construction module is shown in the corresponding construction module according to workmen's information
Number mark.
4. method according to claim 3, it is characterised in that workmen's information includes, the work of each workmen
The information of kind;It is described that the construction module is shown in the corresponding construction module according to workmen's information
Construction number identification of steps, including:
The construction number mark of the construction module is shown in the construction module, and number to different work posts is entered
Row is distinctly displayed.
5. method according to claim 2, it is characterised in that methods described also includes:
The construction abnormal information that mobile terminal sends is received, the construction abnormal information includes the construction module of exception
Identity information;
Abnormal construction module is identified in the building 3D models.
6. method according to claim 1, it is characterised in that the job site displaying interface is additionally operable to display according to applying
The construction equipment 3D models that construction equipment is set up;Methods described, also includes:
The configuration information of the construction equipment that mobile terminal sends is received, the configuration information of the construction equipment includes construction equipment
The identity information of 3D models and equipment display location;
According to construction equipment configuration information, show that the equipment that construction equipment configuration information is specified described in interface shows at the construction field (site)
Show and shown on position the construction equipment 3D models.
7. method according to claim 1, it is characterised in that the job site displaying interface is additionally operable to display according to applying
The construction material that construction equipment is set up stacks 3D models;Methods described also includes:
The construction material stacking information that mobile terminal sends is received, the construction material stacking information includes that construction material is stacked
The identity information of 3D models and placing of material position;
Information is stacked according to the construction material, shows that construction material described in interface stacks the material that information is specified at the construction field (site)
Show that the construction material stacks 3D models on material stowed location.
8. method according to claim 1, it is characterised in that the displaying terminal also includes that a map shows interface, institute
Stating method also includes:
The construction material transit information that mobile terminal sends is received, the construction material transit information includes that construction material is transported
Position;
According to the construction material transit information, the traffic condition of construction material is shown on map displaying interface.
9. method according to claim 1, it is characterised in that the displaying terminal also includes construction speed preview circle
Face;Methods described also includes:
For the construction module specifies Estimated Time Of Completion;
Estimated Time Of Completion and selected preview time point according to construction module, show in the construction speed preview interface
Corresponding construction module forms preview model.
10. a kind of construction speed exhibiting device, is applied to the displaying terminal being connected with least one communication of mobile terminal, the exhibition
Show that terminal includes that a job site shows interface, it is characterised in that described device includes:
Model acquisition module, for obtaining building 3D models, will build 3D models and be split as multiple and build according to construction structure
Construction module is built, wherein, each described construction module has unique identity information;
Relation table sets up module, and for setting up a module relationship table, the module relationship table includes and each construction mould
The corresponding mobile terminal identity information of block identity information;
Receiver module, the construction speed information for receiving mobile terminal transmission, the construction speed information includes that construction is responsible for
The identity information of the identity information of people and construction module to be shown;
Authentication module, for according to the module relationship table to the mobile terminal identity information in the construction speed information with build
The identity information for building construction module is verified;
Display module, for when being verified, entering to the construction module for matching on the displaying interface of the job site
Row display.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710135077.3A CN106897534B (en) | 2017-03-08 | 2017-03-08 | Construction progress display method and device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710135077.3A CN106897534B (en) | 2017-03-08 | 2017-03-08 | Construction progress display method and device |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106897534A true CN106897534A (en) | 2017-06-27 |
CN106897534B CN106897534B (en) | 2020-04-14 |
Family
ID=59185314
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710135077.3A Expired - Fee Related CN106897534B (en) | 2017-03-08 | 2017-03-08 | Construction progress display method and device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106897534B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107527143A (en) * | 2017-08-10 | 2017-12-29 | 嘉兴恒创电力设计研究院有限公司 | Job site data-pushing, management method and management system based on BIM models |
CN114117596A (en) * | 2021-11-15 | 2022-03-01 | 国能大渡河猴子岩发电有限公司 | Real-time monitoring and management method for water conservancy and hydropower engineering |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104766182A (en) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | Intelligent monitoring system for building design construction based on BIM |
US20150310135A1 (en) * | 2014-04-24 | 2015-10-29 | The Board Of Trustees Of The University Of Illinois | 4d vizualization of building design and construction modeling with photographs |
CN105335559A (en) * | 2015-10-28 | 2016-02-17 | 上海同筑信息科技有限公司 | Engineering standardized construction process control method and system on basis of BIM (building information modeling) |
CN105976089A (en) * | 2016-04-27 | 2016-09-28 | 中交第二航务工程局有限公司 | Construction data classification system based on building information model and method thereof |
CN106127412A (en) * | 2016-07-05 | 2016-11-16 | 重庆交通大学 | A kind of engineering quality supervision and management method and device |
-
2017
- 2017-03-08 CN CN201710135077.3A patent/CN106897534B/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20150310135A1 (en) * | 2014-04-24 | 2015-10-29 | The Board Of Trustees Of The University Of Illinois | 4d vizualization of building design and construction modeling with photographs |
CN104766182A (en) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | Intelligent monitoring system for building design construction based on BIM |
CN105335559A (en) * | 2015-10-28 | 2016-02-17 | 上海同筑信息科技有限公司 | Engineering standardized construction process control method and system on basis of BIM (building information modeling) |
CN105976089A (en) * | 2016-04-27 | 2016-09-28 | 中交第二航务工程局有限公司 | Construction data classification system based on building information model and method thereof |
CN106127412A (en) * | 2016-07-05 | 2016-11-16 | 重庆交通大学 | A kind of engineering quality supervision and management method and device |
Non-Patent Citations (1)
Title |
---|
王婷 等: "BIM 技术在4D施工进度模拟的应用探讨", 《图学学报》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107527143A (en) * | 2017-08-10 | 2017-12-29 | 嘉兴恒创电力设计研究院有限公司 | Job site data-pushing, management method and management system based on BIM models |
CN114117596A (en) * | 2021-11-15 | 2022-03-01 | 国能大渡河猴子岩发电有限公司 | Real-time monitoring and management method for water conservancy and hydropower engineering |
Also Published As
Publication number | Publication date |
---|---|
CN106897534B (en) | 2020-04-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111814240B (en) | Highway engineering farmer management system based on BIM technology | |
CN100468246C (en) | Real time monitoring system for production processes and monitoring method | |
CN117391640B (en) | Engineering construction project construction period management method and system based on BIM and GIS | |
CN107944838A (en) | A kind of intelligent barrier gate Field Monitoring System and method | |
CN104700192A (en) | Aided intelligent management and control system for power transmission and transformation project and management and control method thereof | |
CN103793857A (en) | Electric power field operating system combined with smartphone | |
CN202167063U (en) | Onsite operation safety control system | |
CN109461142A (en) | Route Analysis of Potential method, apparatus and electric terminal | |
CN104732345A (en) | Supervision and management information system used for field management in power transmission and transformation engineering | |
CN111881501B (en) | BIM and cloud service-based fabricated building management method and system | |
CN111860889A (en) | Electromechanical device intelligent maintenance management system based on BIM | |
CN104809507A (en) | Electronic ticket ordering ticket checking method applicable to intelligent mobile terminal | |
CN111127974A (en) | Virtual reality and augmented reality three-dimensional application service platform for transformer substation operation | |
CN114186011A (en) | Management method and device based on electronic fence, computer equipment and storage medium | |
CN106897534A (en) | Construction speed methods of exhibiting and device | |
CN107481162A (en) | A kind of information feedback method and equipment for ensureing special messenger and carrying out assigned work at the construction field (site) | |
WO2024114543A1 (en) | Unmanned aerial vehicle permission management method and system, and storage medium | |
CN107977718A (en) | Substation equipment maintaining method and system based on BIM models | |
CN108696475A (en) | A kind of distribution power automation terminal automatic registration method and device with safety certification | |
CN112365201B (en) | Neural network-based infrastructure construction monitoring and early warning system and method | |
CN201796373U (en) | Mobile anti-counterfeiting verification terminal based on double-frequency RFID | |
KR20090121981A (en) | Method and apparatus for managing and building process of electric power facility | |
CN103984739A (en) | Data processing method and device for achieving continuous real-time security trading business processing | |
CN113746888B (en) | Intelligent assistant decision-making method for work ticket monitoring link | |
CN105321225A (en) | Management instrument for installation and maintenance of engineering machinery and application of management instrument |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200414 |
|
CF01 | Termination of patent right due to non-payment of annual fee |