CN107944838A - A kind of intelligent barrier gate Field Monitoring System and method - Google Patents

A kind of intelligent barrier gate Field Monitoring System and method Download PDF

Info

Publication number
CN107944838A
CN107944838A CN201711366515.3A CN201711366515A CN107944838A CN 107944838 A CN107944838 A CN 107944838A CN 201711366515 A CN201711366515 A CN 201711366515A CN 107944838 A CN107944838 A CN 107944838A
Authority
CN
China
Prior art keywords
data
personnel
identification
presence server
server
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711366515.3A
Other languages
Chinese (zh)
Inventor
李平远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Da Yi Science And Technology Co Ltd
Original Assignee
Sichuan Da Yi Science And Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Da Yi Science And Technology Co Ltd filed Critical Sichuan Da Yi Science And Technology Co Ltd
Priority to CN201711366515.3A priority Critical patent/CN107944838A/en
Publication of CN107944838A publication Critical patent/CN107944838A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/109Time management, e.g. calendars, reminders, meetings or time accounting
    • G06Q10/1091Recording time for administrative or management purposes
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The present invention relates to a kind of intelligent barrier gate Field Monitoring System and method, its system includes testimony of a witness unification registration module, platform service management module, Platform Server, presence server, on-site identification component and controller;Platform service management module is used to create and management project agency information data, determines to have permission the listings data into the personnel of construction site;Platform Server is used to listings data being synchronized to presence server;On-site identification component is used to obtain the live identity information into the personnel of construction site;Presence server is used to analyze live identity information using listings data as target, and controls the switch of banister;Controller is used to position personnel;Platform service management module is used to be monitored banister scene according to the switch data of identification information, location data and banister.In the present invention, personnel enter scene with real name and true identity, it is ensured that civilian worker's attendance data is true and reliable, improves field management level and safety in production grade.

Description

A kind of intelligent barrier gate Field Monitoring System and method
Technical field
The present invention relates to construction site management field, and in particular to a kind of intelligent barrier gate Field Monitoring System and method.
Background technology
Building trade is an industry very high to security requirement.At present, with the construction of national basis facility, and Construction scale constantly expands, technological process numerous and complicated, how to carry out construction site management, controls accident rate, is always Construction enterprises, government administration section focus of attention.And to the management of building site staff, also just it is particularly important.At present Construction site supervision is primarily present following aspect problem:
(1) information-based supervision missing:Because construction site environment is complicated, building site disperses, without information-based remote supervisory hand Section, manual inspection difficulty is big, and the efficiency of management is low, and construction site situation can not be fed back in time in time, causes the hysteresis effect of management Should, effective control and support in real time are determined to accident;
(2) personal management difficulty is big:The phenomenon of engineering related personnel omission happens occasionally, to project manager, Project Technical Chief leading cadre's attendance difficulty is big, and violation operation is multiple, often leads to the accident of bitterness;
(3) unified platform support is lacked:Inconsistent, no unified platform and service are managed between each building site, go wrong branch Support is difficult, low-response, influences issue handling efficiency.
Between the above problem, establish the databases of dynamic reflection construction site staff's actual conditions, register and The management account books such as attendance volume, realize job site personnel turn out for work situation management system it is extremely urgent.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of intelligent barrier gate Field Monitoring System and method, it is possible to achieve Job site personnel is turned out for work the management of situation, and lifting field management is horizontal, improves safety in production grade.
The technical solution that the present invention solves above-mentioned technical problem is as follows:A kind of intelligent barrier gate Field Monitoring System,
Including testimony of a witness unification registration module, platform service management module, Platform Server, presence server, on-site identification Component and controller;
The testimony of a witness unifies registration module, it is used to gather the identity data needed into job site personnel, and carries out The testimony of a witness unifies authentication, and unifies the identity data generation testimony of a witness unification identity data after authentication success according to the testimony of a witness, And testimony of a witness unification identity data is uploaded to the Platform Server;
The platform service management module, it is used to from the Platform Server obtain the testimony of a witness unification identity data With create project organization information data, and closed according to the project organization information data of establishment from the testimony of a witness of acquisition Determine to have permission the listings data into the personnel of construction site in one identity data, and the listings data is uploaded to described Platform Server;
The Platform Server, it is used to the listings data being synchronized to the presence server;
The on-site identification component, it is used to obtain the live identity information into the personnel of construction site, and is uploaded to Presence server;
The presence server, it is used to the live identity information analyze using the listings data as target To identification data, and according to the switch of identification data control banister, and obtain the switch data of banister;
The controller, it is used to after presence server control banister is opened, obtain into the personnel's of construction site Location data, and location data is uploaded to presence server;
The Platform Server, is additionally operable to obtain the identification data, location data from the presence server With the switch data of banister;
The platform service management module, be additionally operable to according to the Platform Server obtain the identification data, Location data and the switch data of banister are monitored banister scene.
The beneficial effects of the invention are as follows:A kind of intelligent barrier gate Field Monitoring System of the present invention solves people by identification Member enters building-site with real name and true identity, it is ensured that civilian worker's attendance data is true, is follow-up civilian worker's wages class granting, project Progress control provides reliable basis;Marched into the arena personnel and each work post positional information by positioning real time monitoring, improve field management Level, improves safety in production grade.
Based on the above technical solutions, the present invention can also be improved as follows.
Further, the platform service management module, is additionally operable to be generated with needing to enter construction according to the identity data Identity uniquely corresponding the RFID codes and identification Quick Response Code of the personnel at scene;
Intelligent safety helmet is further included, RFID chip is provided with the intelligent safety helmet, the RFID chip memory contains The RFID codes, the positive and negative of the RFID chip are also printed with the identification Quick Response Code.
Further, the on-site identification component includes code reader, and the code reader is used for by reading the intelligent and safe RFID codes on cap obtain the live identity information into the personnel of construction site, and are uploaded to presence server;
The presence server, is additionally operable to analyze the RFID codes, generates the identification data of RFID codes.
Further, the on-site identification component further includes camera, and the camera is used to know by scanning the identity The picture of other Quick Response Code obtains the live identity information into the personnel of construction site, and is uploaded to presence server;
The presence server, is additionally operable to analyze the picture of the identification Quick Response Code, generates identification The identification data of Quick Response Code;
The camera, is additionally operable to existing into construction to obtain into the facial image of the personnel of construction site by collection The live identity information of the personnel of field, and it is uploaded to presence server;
The presence server, specifically for the facial image that gathers the camera and the listings data into Row contrast, if the matching rate of the facial image and the listings data reaches preset value, recognition of face is by and generating The identification data of face;
The presence server, also particularly useful for by the identification data of the RFID codes or identification Quick Response Code with The identification data of the face is contrasted, if the identification data and institute of the RFID codes or identification Quick Response Code The identification data for stating face matches, then controls the banister to open, otherwise control the banister to be not turned on.
Further, positioning chip is additionally provided with the intelligent safety helmet, the positioning chip is specially UWB chips, described Controller includes UWB register controls;
The UWB register controls, enter specifically for being obtained by the positioning chip on the intelligent safety helmet The UWB location datas of the personnel of construction site, and UWB location datas are uploaded to presence server.
Further, the personnel into construction site are equipped with the terminal with GPS positioning function, and the controller includes GPS positioning controller;
The GPS controllers, it is used to obtain into the personnel's of construction site by the terminal with GPS positioning function GPS positioning data, and GPS positioning data are uploaded to presence server;
The Platform Server, also particularly useful for obtaining the GPS positioning data from the presence server;
The platform service management module, described in being obtained by GIS map to the Platform Server GPS positioning data are parsed, and show access into specific location and work post letter of the personnel in delineation GIS map of construction site Breath.
Further, time threshold is preset with the platform service management module, when the institute that the Platform Server obtains State location data and show personnel when not moved more than the time threshold, the platform service management module is carried out at alarm Reason.
Further, monitoring module is further included, the monitoring module, it is used to unite to the working status of live software and hardware Meter, and show the working status tendency chart of the live software and hardware;
The corresponding threshold value of each live software and hardware and monitoring alarm strategy are additionally provided with the monitoring module, when scene is soft When hardware effort is abnormal, the monitoring module carries out Realtime Alerts prompting and sends work to handle.
It is using the above-mentioned further beneficial effect of scheme:Present invention additionally comprises being monitored to live software and hardware, pass through The working status of software and hardware is counted, and shows the working status tendency chart of software and hardware;System can set each software and hardware Parameter highest or minimum threshold values (door restrictor) and monitoring alarm strategy;If software and hardware operation irregularity, Realtime Alerts prompting, and can lead to The system of mistake is sent to be implemented personnel and is safeguarded nearby, ensures the stability of live software and hardware work.
Further, statistics display module is further included, the statistics display module is connected with the presence server, for uniting Meter shows the personnel state of construction site.
Based on a kind of above-mentioned intelligent barrier gate Field Monitoring System, present invention also offers a kind of intelligent barrier gate on-site supervision side Method.
A kind of intelligent barrier gate field monitoring method, comprises the following steps,
S1, testimony of a witness unification registration module collection need the identity data into job site personnel, and the pedestrian that goes forward side by side demonstrate,proves unification Authentication, and the identity data generation testimony of a witness unification identity data after authentication success is unified according to the testimony of a witness, and by the testimony of a witness Unification identity data is uploaded to Platform Server;
S2, platform service management module obtain the testimony of a witness unification identity data from Platform Server and create project team Loom structure information data, and unified according to the project organization information data of establishment from the testimony of a witness of acquisition in identity data Determine to have permission the listings data into the personnel of construction site, and the listings data is uploaded to Platform Server;
The listings data is synchronized to presence server by S3, Platform Server;
S4, on-site identification component obtains the live identity information into the personnel of construction site, and is uploaded to Site Service Device;
S5, presence server are analyzed to obtain identity knowledge using the listings data as target to the live identity information Other data, and according to the switch of identification data control banister, and obtain the switch data of banister;
S6, after presence server control banister is opened, controller obtains the location data into the personnel of construction site, And location data is uploaded to presence server;
S7, Platform Server obtain the switch of the identification data, location data and banister from presence server Data;
S8, the identification data, location data and the road that platform service management module is obtained according to Platform Server The switch data of lock is monitored banister scene.
The beneficial effects of the invention are as follows:A kind of intelligent barrier gate field monitoring method of the present invention solves people by identification Member enters building-site with real name and true identity, it is ensured that civilian worker's attendance data is true, is follow-up civilian worker's wages class granting, project Progress control provides reliable basis;Marched into the arena personnel and each work post positional information by positioning real time monitoring, improve field management Level, improves safety in production grade.
Brief description of the drawings
Fig. 1 is a kind of structure diagram of intelligent barrier gate Field Monitoring System of the present invention;
Fig. 2 is a kind of schematic diagram of intelligent barrier gate Field Monitoring System work of the present invention;
Fig. 3 is the flow chart that the demographic data that marches into the arena is initialized in a kind of intelligent barrier gate Field Monitoring System of the present invention;
Fig. 4 identifies banister data initialization workflow for Intelligent human-face in a kind of intelligent barrier gate Field Monitoring System of the present invention Cheng Tu;
Fig. 5 is the design flow diagram of intelligent safety helmet in a kind of intelligent barrier gate Field Monitoring System of the present invention;
Fig. 6 is the listings data Establishing process figure of personnel of marching into the arena in a kind of intelligent barrier gate Field Monitoring System of the present invention;
Fig. 7 is staff attendance flow chart of marching into the arena in a kind of intelligent barrier gate Field Monitoring System of the present invention;
Fig. 8 is the flow chart that software and hardware monitors in a kind of intelligent barrier gate Field Monitoring System of the present invention;
Fig. 9 is a kind of overall flow figure of intelligent barrier gate field monitoring method of the present invention.
Embodiment
The principle and features of the present invention will be described below with reference to the accompanying drawings, and the given examples are served only to explain the present invention, and It is non-to be used to limit the scope of the present invention.
As depicted in figs. 1 and 2, a kind of intelligent barrier gate Field Monitoring System, including testimony of a witness unification registration module, platform service (presence server is the service to communicate with the soft hardware equipment of construction site for management module, Platform Server, presence server Device), on-site identification component and controller;
The testimony of a witness unifies registration module, it is used to gather the identity data needed into job site personnel, and carries out The testimony of a witness unifies authentication, and unifies the identity data generation testimony of a witness unification identity data after authentication success according to the testimony of a witness, And testimony of a witness unification identity data is uploaded to the Platform Server;
The platform service management module, it is used to from the Platform Server obtain the testimony of a witness unification identity data With create project organization information data, and closed according to the project organization information data of establishment from the testimony of a witness of acquisition Determine to have permission the listings data into the personnel of construction site in one identity data, and the listings data is uploaded to described Platform Server;
The Platform Server, it is used to the listings data being synchronized to the presence server;
The on-site identification component, it is used to obtain the live identity information into the personnel of construction site, and is uploaded to Presence server;
The presence server, it is used to the live identity information analyze using the listings data as target To identification data, and according to the switch of identification data control banister, and obtain the switch data of banister;
The controller, it is used to after presence server control banister is opened, obtain into the personnel's of construction site Location data, and location data is uploaded to presence server;
The Platform Server, is additionally operable to obtain the identification data, location data from the presence server With the switch data of banister;
The platform service management module, be additionally operable to according to the Platform Server obtain the identification data, Location data and the switch data of banister are monitored banister scene.
In this embodiment:
The testimony of a witness unification registration module collection needs the identity data into job site personnel, and the pedestrian that goes forward side by side demonstrate,proves unification The flow of authentication as shown in figure 3, create needs the identity data into job site personnel to be also referred to as initialization to march into the arena people Member's data;Building needs the personnel into construction site to include manager and the worker of site operation, and manager voluntarily passes through platform Service management module (platform service management module can be cell phone application or business platform) is registered;Worker passes through teams and groups Squad leader's auxiliary direction is registered, it is ensured that the equal copying platform service management module of worker of each teams and groups, necessary information include:Name, Identity card picture, registrant's photo and job titles and operation class (of an amplifying stage);After data input, data need to be audited by platform, it is ensured that Information is correct, apparent, completes real-name authentication.
In addition, the platform service management module, is additionally operable to be generated with needing to enter construction according to the identity data of establishment The identity of Field Force uniquely corresponding RFID codes and identification Quick Response Code;Platform service management module is effective by identity card Information, automatically generates unique RFID codes and identification Quick Response Code, completes demographic data's initial work of marching into the arena.
Also need to carry out Intelligent human-face identification banister data initialization work, intelligence after the completion of demographic data's initialization of marching into the arena The data initialization work of energy recognition of face banister is as shown in Figure 4:Need to construction site in-site installation soft hardware equipment, comprising: Camera, banister, presence server, code reader and UWB register controls;Ensure the networking intercommunication of above soft hardware equipment, shooting The human face identification work-attendance checking data of head, the open and close data of banister, the reading code data of code reader, the positioning of UWB register controls Data are all stored in presence server, and platform service end is by real-time synchronization or delay asynchronous system, actively or passively from existing Obtaining field data in the server of field, (field data is exactly the switch number of identification information described above, location data and banister According to).
The system of the present invention further includes intelligent safety helmet, and the intelligent safety helmet is equipped with RFID chip and positioning chip, The RFID chip memory storage has the RFID codes, and the identification is also printed with the obverse and reverse sides of the RFID chip Quick Response Code.The design of intelligent safety helmet is as shown in Figure 5:Using the side of safety cap+intelligent chip (RFID chip and UWB chips) Formula;UWB chips are fixed on safety cap left or right side.
Fig. 6 is the listings data Establishing process figure of personnel of marching into the arena in a kind of intelligent barrier gate Field Monitoring System of the present invention; In the system of the present invention, administrative staff also need to establish the agency information of this project under construction by platform service management module Data, and determine to have permission from the testimony of a witness unification identity data of acquisition according to the project organization information data of establishment Into the listings data of the personnel of construction site.Listings data after the completion of foundation deposits in Platform Server;Platform Server By being communicated with presence server, listings data is synchronized to presence server, listings data emphasis includes personnel ID, work Make type (work post), name, identification card number, identity card pictorial information and photo site information.
The camera, code reader combination presence server are controlled banister the flow for realizing the attendance for the personnel that march into the arena As shown in fig. 7, the attendance mode for the personnel that march into the arena is specially (" to be namely target to the identification information using the listings data Analyzed, and according to the switch of the output control banister of analysis " detailed process):The on-site identification component, which further includes, to be taken the photograph As head, the camera is used to obtain into the personnel's of construction site by scanning the picture of the identification Quick Response Code Live identity information, and it is uploaded to presence server;The presence server carries out the picture of the identification Quick Response Code Analysis, generates the identification data of identification Quick Response Code;The camera is by gathering into the personnel's of construction site Facial image obtains the live identity information into the personnel of construction site, and is uploaded to presence server;The scene clothes Business device the facial image that the camera gathers and the listings data are contrasted, if the facial image with it is described When the matching rate of listings data reaches preset value, then recognition of face is by and generating the identification data of face (if the face When portion's information and the matching rate of the listings data are not reaching to preset value, then recognition of face is not by cannot then generate face Identification information);In recognition of face on the premise of, the presence server is by the RFID codes or identification Quick Response Code The identification data of identification data and the face is contrasted, if the body of the RFID codes or identification Quick Response Code Part identification data and the identification data of the face match, then control the banister to open, otherwise control the banister It is not turned on.
In this embodiment, the facial information and the preset value of the matching rate of the listings data can be set, Reach matching rate, then it represents that recognition of face is by the way that the preset value of acquiescence is 85% characteristic matching, its adjusting range can be 70%-100%.
Presence server opens banister condition:1. recognition of face information+identification 2 D code information, both compare, letter Breath matching;2.+RFID yards of information of recognition of face information, both compare, information matches;Both the above situation, meets a kind of, control Banister is opened.
In this embodiment, the controller includes UWB register controls, and the positioning chip is specially UWB cores Piece;The UWB register controls, are applied specifically for obtaining to enter by the UWB positioning chips on the intelligent safety helmet The UWB location datas of the personnel at work scene, and UWB location datas are uploaded to presence server.
In this embodiment, the acquisition of location data can also use following technical scheme:Into construction site Personnel are equipped with the terminal (can be smart mobile phone) with GPS positioning function, and the controller includes GPS positioning controller; The GPS controllers, it is used to obtain the GPS positioning into the personnel of construction site by the terminal with GPS positioning function Data, and GPS positioning data are uploaded to presence server;The Platform Server, also particularly useful for from the Site Service The GPS positioning data are obtained in device;The platform service management module, also particularly useful for by GIS map to the platform The GPS positioning data that server obtains are parsed, and show access into tool of the personnel in delineation GIS map of construction site Body position and work post information;Construction site scope can be drawn a circle to approve, in building site, map can be shown personnel by GIS map Specific location, leaves construction site scope, does not then show personnel location information.
Time threshold is preset with the platform service management module, when the positioning number that the Platform Server obtains According to display personnel when not moved more than the time threshold, the platform service management module carries out alert process.For example, After personnel march into the arena, by UWB localization methods (or GPS positioning method), can recognize that the detail location of personnel, judge personnel whether Scene and the work post for showing the personnel;When the personnel are small more than 4, (can customize the time) does not have shift position, then actively Alarm, prompts the personnel with the presence or absence of generation security risk.
The system of the present invention further includes monitoring module, and the monitoring module, it is used for the working status to live software and hardware Counted, and show the working status tendency chart of the live software and hardware;It is soft that each scene is additionally provided with the monitoring module The corresponding threshold value of hardware and monitoring alarm strategy, when live software and hardware operation irregularity, the monitoring module is reported in real time It is alert to prompt and send work to handle.Fig. 8 is the flow chart that software and hardware monitors in a kind of intelligent barrier gate Field Monitoring System of the present invention, if existing Software and hardware operation irregularity, Realtime Alerts prompting, and can be sent by system and implement personnel nearby and safeguarded.
In this embodiment, present invention additionally comprises statistics display module, the statistics display module and the scene Server is connected, and the personnel state of construction site is shown for counting;It can specifically count and show that each work post should arrive people Number and actual arrival number, can also show access into the identity information of job site personnel;In addition counting display module also has alarm Function, alarm can be realized when there is exception or special circumstances.
A kind of intelligent barrier gate Field Monitoring System of the present invention solves personnel with real name and true identity by identification Into building-site, it is ensured that civilian worker's attendance data is true, for follow-up civilian worker's wages class granting, project scheduling management provide reliably according to According to;Marched into the arena personnel and each work post positional information by positioning real time monitoring, improve field management level, improve safety in production Grade.
Based on a kind of above-mentioned intelligent barrier gate Field Monitoring System, present invention also offers a kind of intelligent barrier gate on-site supervision side Method.
As shown in figure 9, a kind of intelligent barrier gate field monitoring method, comprises the following steps,
S1, testimony of a witness unification registration module collection need the identity data into job site personnel, and the pedestrian that goes forward side by side demonstrate,proves unification Authentication, and the identity data generation testimony of a witness unification identity data after authentication success is unified according to the testimony of a witness, and by the testimony of a witness Unification identity data is uploaded to Platform Server;
S2, platform service management module obtain the testimony of a witness unification identity data from Platform Server and create project team Loom structure information data, and unified according to the project organization information data of establishment from the testimony of a witness of acquisition in identity data Determine to have permission the listings data into the personnel of construction site, and the listings data is uploaded to Platform Server;
The listings data is synchronized to presence server by S3, Platform Server;
S4, on-site identification component obtains the live identity information into the personnel of construction site, and is uploaded to Site Service Device;
S5, presence server are analyzed to obtain identity knowledge using the listings data as target to the live identity information Other data, and according to the switch of identification data control banister, and obtain the switch data of banister;
S6, after presence server control banister is opened, controller obtains the location data into the personnel of construction site, And location data is uploaded to presence server;
S7, Platform Server obtain the switch of the identification data, location data and banister from presence server Data;
S8, the identification data, location data and the road that platform service management module is obtained according to Platform Server The switch data of lock is monitored banister scene.
In a kind of intelligent barrier gate field monitoring method of the present invention, platform service management module, which is created and managed, to be needed to enter The specific method of the identity data of job site personnel can be:1. scene passes through testimony of a witness in-one device typing;2. remotely pass through APP typings, platform personnel examination & verification identity card and face head image information;Quick Response Code is generated, and is printed upon before and after RFID chip shell Two sides, 2 D code information keep unified information with chip information.
A kind of intelligent barrier gate field monitoring method of the present invention solves personnel with real name and true identity by identification Into building-site, it is ensured that civilian worker's attendance data is true, for follow-up civilian worker's wages class granting, project scheduling management provide reliably according to According to;Marched into the arena personnel and each work post positional information by positioning real time monitoring, improve field management level, improve safety in production Grade.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all the present invention spirit and Within principle, any modification, equivalent replacement, improvement and so on, should all be included in the protection scope of the present invention.

Claims (10)

  1. A kind of 1. intelligent barrier gate Field Monitoring System, it is characterised in that:Including testimony of a witness unification registration module, platform service management mould Block, Platform Server, presence server, on-site identification component and controller;
    The testimony of a witness unifies registration module, it is used to gather the identity data needed into job site personnel, the pedestrian that goes forward side by side card Unify authentication, and the identity data generation testimony of a witness unification identity data after authentication success is unified according to the testimony of a witness, and will Testimony of a witness unification identity data is uploaded to the Platform Server;
    The platform service management module, it is used to from the Platform Server obtain the testimony of a witness unification identity data and wound Project organization information data is built, and body is unified from the testimony of a witness of acquisition according to the project organization information data of establishment Determine to have permission the listings data into the personnel of construction site in part data, and the listings data is uploaded to the platform Server;
    The Platform Server, it is used to the listings data being synchronized to the presence server;
    The on-site identification component, it is used to obtain the live identity information into the personnel of construction site, and is uploaded to scene Server;
    The presence server, it is used to the live identity information is analyzed to obtain body using the listings data as target Part identification data, and according to the switch of identification data control banister, and obtain the switch data of banister;
    The controller, it is used to after presence server control banister is opened, obtain the positioning into the personnel of construction site Data, and location data is uploaded to presence server;
    The Platform Server, is additionally operable to obtain the identification data, location data and road from the presence server The switch data of lock;
    The platform service management module, is additionally operable to the identification data, the positioning obtained according to the Platform Server Data and the switch data of banister are monitored banister scene.
  2. A kind of 2. intelligent barrier gate Field Monitoring System according to claim 1, it is characterised in that:The platform service management Module, is additionally operable to generate the unique corresponding RFID codes of identity with needing the personnel for entering construction site according to the identity data With identification Quick Response Code;
    Intelligent safety helmet is further included, RFID chip is provided with the intelligent safety helmet, the RFID chip memory storage has described RFID codes, the positive and negative of the RFID chip are also printed with the identification Quick Response Code.
  3. A kind of 3. intelligent barrier gate Field Monitoring System according to claim 2, it is characterised in that:The on-site identification component Including code reader, the code reader is used to obtain into construction site by reading the RFID codes on the intelligent safety helmet The live identity information of personnel, and it is uploaded to presence server;
    The presence server, is additionally operable to analyze the RFID codes, generates the identification data of RFID codes.
  4. A kind of 4. intelligent barrier gate Field Monitoring System according to claim 3, it is characterised in that:The on-site identification component Camera is further included, the camera is used to obtain into construction site by scanning the picture of the identification Quick Response Code Personnel live identity information, and be uploaded to presence server;
    The presence server, is additionally operable to analyze the picture of the identification Quick Response Code, generation identification two dimension The identification data of code;
    The camera, is additionally operable to obtain into construction site by gathering into the facial image of the personnel of construction site The live identity information of personnel, and it is uploaded to presence server;
    The presence server, carries out pair specifically for the facial image that gathers the camera and the listings data Than if the matching rate of the facial image and the listings data reaches preset value, recognition of face is by and generating face Identification data;
    The presence server, also particularly useful for by the identification data of the RFID codes or identification Quick Response Code with it is described The identification data of face is contrasted, if the identification data of the RFID codes or identification Quick Response Code and the people The identification data of face matches, then controls the banister to open, otherwise control the banister to be not turned on.
  5. 5. according to a kind of intelligent barrier gate Field Monitoring System of claim 2 to 4 any one of them, it is characterised in that:The intelligence Positioning chip can be additionally provided with safety cap, the positioning chip is specially UWB chips, and the controller includes UWB location controls Device;
    The UWB register controls, enter construction specifically for being obtained by the positioning chip on the intelligent safety helmet The UWB location datas of the personnel at scene, and UWB location datas are uploaded to presence server.
  6. A kind of 6. intelligent barrier gate Field Monitoring System according to any one of claims 1 to 4, it is characterised in that:Into applying The personnel at work scene are equipped with the terminal with GPS positioning function, and the controller includes GPS positioning controller;
    The GPS controllers, it is used to obtain the GPS into the personnel of construction site by the terminal with GPS positioning function Location data, and GPS positioning data are uploaded to presence server;
    The Platform Server, also particularly useful for obtaining the GPS positioning data from the presence server;
    The platform service management module, determines the GPS that the Platform Server obtains also particularly useful for by GIS map Position data are parsed, and show access into specific location and work post information of the personnel in delineation GIS map of construction site.
  7. A kind of 7. intelligent barrier gate Field Monitoring System according to any one of claims 1 to 4, it is characterised in that:It is described flat Time threshold is preset with platform service management module, when the location data that the Platform Server obtains shows personnel super When crossing the time threshold and not moving, the platform service management module carries out alert process.
  8. A kind of 8. intelligent barrier gate Field Monitoring System according to any one of claims 1 to 4, it is characterised in that:Further include Monitoring module, the monitoring module, it is used to count the working status of live software and hardware, and it is soft or hard to show the scene The working status tendency chart of part;
    The corresponding threshold value of each live software and hardware and monitoring alarm strategy are additionally provided with the monitoring module, when live software and hardware During operation irregularity, the monitoring module carries out Realtime Alerts prompting and sends work to handle.
  9. A kind of 9. intelligent barrier gate Field Monitoring System according to any one of claims 1 to 4, it is characterised in that:Further include Display module is counted, the statistics display module is connected with the presence server, and the personnel of construction site are shown for counting State.
  10. A kind of 10. intelligent barrier gate field monitoring method, it is characterised in that:Comprise the following steps,
    S1, testimony of a witness unification registration module collection need the identity data into job site personnel, and the pedestrian that goes forward side by side demonstrate,proves unification identity Verification, and the identity data generation testimony of a witness unification identity data after authentication success is unified according to the testimony of a witness, and the testimony of a witness is unified Identity data is uploaded to Platform Server;
    S2, platform service management module obtain the testimony of a witness unification identity data from Platform Server and create project team's loom Structure information data, and determined according to the project organization information data of establishment from the testimony of a witness unification identity data of acquisition The listings data into the personnel of construction site is had permission, and the listings data is uploaded to Platform Server;
    The listings data is synchronized to presence server by S3, Platform Server;
    S4, on-site identification component obtains the live identity information into the personnel of construction site, and is uploaded to presence server;
    S5, presence server are analyzed to obtain identification number using the listings data as target to the live identity information According to, and according to the switch of identification data control banister, and obtain the switch data of banister;
    S6, after presence server control banister is opened, controller obtains the location data into the personnel of construction site, and will Location data is uploaded to presence server;
    S7, Platform Server obtain the switch data of the identification data, location data and banister from presence server;
    S8, the identification data, location data and the banister that platform service management module is obtained according to Platform Server Switch data is monitored banister scene.
CN201711366515.3A 2017-12-18 2017-12-18 A kind of intelligent barrier gate Field Monitoring System and method Pending CN107944838A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711366515.3A CN107944838A (en) 2017-12-18 2017-12-18 A kind of intelligent barrier gate Field Monitoring System and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711366515.3A CN107944838A (en) 2017-12-18 2017-12-18 A kind of intelligent barrier gate Field Monitoring System and method

Publications (1)

Publication Number Publication Date
CN107944838A true CN107944838A (en) 2018-04-20

Family

ID=61941842

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711366515.3A Pending CN107944838A (en) 2017-12-18 2017-12-18 A kind of intelligent barrier gate Field Monitoring System and method

Country Status (1)

Country Link
CN (1) CN107944838A (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108681884A (en) * 2018-06-26 2018-10-19 中海油惠州石化有限公司 Production operation management-control method and machine readable storage medium
CN109086897A (en) * 2018-07-20 2018-12-25 南通通亮网络科技有限公司 A kind of security protection articles entirely use cycle management system
CN109215153A (en) * 2018-09-05 2019-01-15 航天信息股份有限公司 Work attendance method and device
CN109344304A (en) * 2018-09-12 2019-02-15 广东电网有限责任公司 Position display method and device, electronic equipment, the readable storage medium storing program for executing of staff
CN109741475A (en) * 2018-12-26 2019-05-10 鲁班长(深圳)科技有限公司 System of real name Work attendance method, device, system and computer storage medium
CN109816837A (en) * 2019-03-13 2019-05-28 重庆芯力源科技有限公司 Mine operation personnel identity uniqueness detection system and method
CN109872055A (en) * 2019-01-30 2019-06-11 广州轨道交通建设监理有限公司 A kind of personnel management system based on construction site
CN110008676A (en) * 2019-04-02 2019-07-12 合肥智查数据科技有限公司 A kind of personnel's multidimensional challenge and true identity discrimination system and method
CN110084938A (en) * 2019-04-29 2019-08-02 中铁第一勘察设计院集团有限公司 The guard method for the anti-trailing behavior of operation of climbing to the top of a mountain is examined for subway column
CN110082705A (en) * 2019-04-29 2019-08-02 中铁第一勘察设计院集团有限公司 Subway column inspection operating personnel's localization method
CN110728495A (en) * 2019-10-11 2020-01-24 重庆厚盾安全技术有限公司 Practitioner information management system
WO2020019673A1 (en) * 2018-07-25 2020-01-30 深圳云天励飞技术有限公司 Construction site monitoring method and device based on image analysis, and readable storage medium
CN111260312A (en) * 2020-01-10 2020-06-09 北京朗道新科智能科技有限公司 Real-name system management system and method for industrial workers
CN112019611A (en) * 2020-08-24 2020-12-01 国网河北省电力有限公司 Construction site supervision system and method based on terminal acquisition and management fusion
CN112258001A (en) * 2020-10-15 2021-01-22 苏州市建设工程质量安全监督站(苏州市轨道交通工程质量安全监督站苏州市干将路工程指挥部办公室) Method for managing service personnel
CN113470308A (en) * 2021-08-23 2021-10-01 吉林建筑大学 Prevention eminence accident system that falls based on internet of things
CN113723578A (en) * 2021-09-16 2021-11-30 北京中安瑞力科技有限公司 Personnel information identification method and identification positioning system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103714431A (en) * 2013-12-26 2014-04-09 苏州清研微视电子科技有限公司 Airport people identity authentication management system based on face recognition
CN204270381U (en) * 2014-11-25 2015-04-15 北京爱必优得科技发展有限公司 The working-yard personnel of taking part in building are carried out to the system of system of real name management and control
CN204288309U (en) * 2014-12-17 2015-04-22 深圳市云骢建筑设备设计有限公司 A kind of portable RF ID attendance recorder for building ground and attendance checking system thereof
CN105913037A (en) * 2016-04-26 2016-08-31 广东技术师范学院 Face identification and radio frequency identification based monitoring and tracking system
CN205845121U (en) * 2016-05-31 2016-12-28 中国一冶集团有限公司 Construction site real-name management gate system
CN106296834A (en) * 2016-07-25 2017-01-04 苏州爱开客信息技术有限公司 Distinguish intelligent input-output control system and the method thereof of vehicle
CN106682647A (en) * 2017-01-20 2017-05-17 上海易销科技股份有限公司 Human and identity authentication integrated system and method based on face recognition

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103714431A (en) * 2013-12-26 2014-04-09 苏州清研微视电子科技有限公司 Airport people identity authentication management system based on face recognition
CN204270381U (en) * 2014-11-25 2015-04-15 北京爱必优得科技发展有限公司 The working-yard personnel of taking part in building are carried out to the system of system of real name management and control
CN204288309U (en) * 2014-12-17 2015-04-22 深圳市云骢建筑设备设计有限公司 A kind of portable RF ID attendance recorder for building ground and attendance checking system thereof
CN105913037A (en) * 2016-04-26 2016-08-31 广东技术师范学院 Face identification and radio frequency identification based monitoring and tracking system
CN205845121U (en) * 2016-05-31 2016-12-28 中国一冶集团有限公司 Construction site real-name management gate system
CN106296834A (en) * 2016-07-25 2017-01-04 苏州爱开客信息技术有限公司 Distinguish intelligent input-output control system and the method thereof of vehicle
CN106682647A (en) * 2017-01-20 2017-05-17 上海易销科技股份有限公司 Human and identity authentication integrated system and method based on face recognition

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108681884A (en) * 2018-06-26 2018-10-19 中海油惠州石化有限公司 Production operation management-control method and machine readable storage medium
CN109086897A (en) * 2018-07-20 2018-12-25 南通通亮网络科技有限公司 A kind of security protection articles entirely use cycle management system
WO2020019673A1 (en) * 2018-07-25 2020-01-30 深圳云天励飞技术有限公司 Construction site monitoring method and device based on image analysis, and readable storage medium
CN109215153A (en) * 2018-09-05 2019-01-15 航天信息股份有限公司 Work attendance method and device
CN109344304A (en) * 2018-09-12 2019-02-15 广东电网有限责任公司 Position display method and device, electronic equipment, the readable storage medium storing program for executing of staff
CN109741475A (en) * 2018-12-26 2019-05-10 鲁班长(深圳)科技有限公司 System of real name Work attendance method, device, system and computer storage medium
CN109872055A (en) * 2019-01-30 2019-06-11 广州轨道交通建设监理有限公司 A kind of personnel management system based on construction site
CN109816837A (en) * 2019-03-13 2019-05-28 重庆芯力源科技有限公司 Mine operation personnel identity uniqueness detection system and method
CN110008676A (en) * 2019-04-02 2019-07-12 合肥智查数据科技有限公司 A kind of personnel's multidimensional challenge and true identity discrimination system and method
CN110008676B (en) * 2019-04-02 2022-09-16 合肥智查数据科技有限公司 System and method for multi-dimensional identity checking and real identity discrimination of personnel
CN110084938A (en) * 2019-04-29 2019-08-02 中铁第一勘察设计院集团有限公司 The guard method for the anti-trailing behavior of operation of climbing to the top of a mountain is examined for subway column
CN110082705A (en) * 2019-04-29 2019-08-02 中铁第一勘察设计院集团有限公司 Subway column inspection operating personnel's localization method
CN110728495A (en) * 2019-10-11 2020-01-24 重庆厚盾安全技术有限公司 Practitioner information management system
CN111260312A (en) * 2020-01-10 2020-06-09 北京朗道新科智能科技有限公司 Real-name system management system and method for industrial workers
CN112019611A (en) * 2020-08-24 2020-12-01 国网河北省电力有限公司 Construction site supervision system and method based on terminal acquisition and management fusion
CN112258001A (en) * 2020-10-15 2021-01-22 苏州市建设工程质量安全监督站(苏州市轨道交通工程质量安全监督站苏州市干将路工程指挥部办公室) Method for managing service personnel
CN113470308A (en) * 2021-08-23 2021-10-01 吉林建筑大学 Prevention eminence accident system that falls based on internet of things
CN113723578A (en) * 2021-09-16 2021-11-30 北京中安瑞力科技有限公司 Personnel information identification method and identification positioning system

Similar Documents

Publication Publication Date Title
CN107944838A (en) A kind of intelligent barrier gate Field Monitoring System and method
CN108198281A (en) Intelligent barrier gate Field Monitoring System and its control method
CN107808502B (en) A kind of image detection alarm method and device
CN109903414A (en) One kind is based on Internet of Things monitoring office attendance control system and method
CN108846785A (en) A kind of safety educational applications method and system
CN109389360A (en) A kind of personnel safety management-control method based on multiple authentication manipulation permission
CN103150553A (en) Mobile terminal and method for realizing multi-mode identity characteristic recognition
CN201828978U (en) Double-door system for bank
CN104217483B (en) Campus Security monitoring system
CN207046617U (en) A kind of gate inhibition's Elevator Intelligent Control System
CN105184932A (en) Method and device for recognizing persons through intelligent access control machine
CN108171851A (en) A kind of intelligent door lock system and control method with scanning function
CN109359712A (en) Electric operating information dynamic collection monitoring device and its application method
CN103713616A (en) Transformer substation field safety monitoring system
CN106331630A (en) Construction site constructor registration and real-time monitoring information system
CN107944344A (en) Power supply enterprise's construction mobile security supervision platform
CN103258222A (en) Cell intelligent logistic management system
CN202205248U (en) Intelligent visitor safety management device
CN210428593U (en) Intelligent access control management system
Jaikumar et al. Fingerprint based student attendance system with SMS alert to parents
CN107730212A (en) A kind of project under construction personnel long-distance real-time management system
CN107301516A (en) A kind of method and system of work about electric power site safety management
CN107730697A (en) The guard method of identification can be carried out
CN106384415A (en) Entrance guard automation control system based on synchronous transmission
CN109712289A (en) A kind of garden security information processing method and processing device based on intelligent management platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180420