CN106384200A - BIM (Building Information Modeling) technology-based management and application method of construction multidimensional model - Google Patents

BIM (Building Information Modeling) technology-based management and application method of construction multidimensional model Download PDF

Info

Publication number
CN106384200A
CN106384200A CN201610852631.5A CN201610852631A CN106384200A CN 106384200 A CN106384200 A CN 106384200A CN 201610852631 A CN201610852631 A CN 201610852631A CN 106384200 A CN106384200 A CN 106384200A
Authority
CN
China
Prior art keywords
data
engineering
multidimensional model
management
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610852631.5A
Other languages
Chinese (zh)
Inventor
朱海涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610852631.5A priority Critical patent/CN106384200A/en
Publication of CN106384200A publication Critical patent/CN106384200A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a BIM (Building Information Modeling) technology-based management and application method of a construction multidimensional model. The method includes the following steps that: a construction project multi-dimensional model is improved, and a variety of kinds of data are added into the model; modular parametric modeling is carried out according to units which are obtained through division according to a construction, and data arrangement is carried out according to the units which are obtained through division according to the construction; and data are queried according to the units which are obtained through division according to the construction; a component processing party or a material provider prepare data in the follow-up time periods of a plane through reading the multidimensional model; when the conditions of the project plan, such as the time, scheme or process of the project plan, change, the plan data and other related data of the multidimensional model are adjusted intelligently; the construction process data of specific components or portions are monitored and recorded, and are loaded into the multidimensional model; a GIS, the multi-dimensional model, a positioning system, the plan and an equipment intelligent system are integrated, so that intelligent driving or construction can be realized; if new information is added to the project or the information of the project changes, a model system can choose to separately add or update a certain part; the system intelligently chooses to only call model data which a user pays attention to or can be seen by the user; and intelligent analysis and replacement are carried out according to the service life decline curve of the components.

Description

The management and methods for using them of the engineering multidimensional model based on BIM technology
Technical field
Belong to civil engineering and information engineering crossing domain.The present invention relates to the management method of engineering, especially relate to base Management and application process in the engineering multidimensional model of BIM technology..
Background technology
BIM(BIM)Technology can be applied to each stages such as engineering project prospecting, design, construction, O&M, real Now build data sharing on the basis of same multidimensional BIM for each participant of full lifetime, be industrial chain insertion, work Industry construction and booming architectural creation provide technical guarantee;Support to the analysis of the aspects such as engineering-environment, economy, quality, safety, Check and simulate, the scheme optimization for project overall process and science decision provide foundation;Support the collaborative work of each specialty, project Virtual construction and fine-grained management, are that upgrading potentiation, the energy-conserving and environment-protective of building industry create conditions.
In engineering actual mechanical process, find that existing engineering construction information model lacks the support of some data, lack The weary effectively utilizes to data, lack of wisdom adjustment, lack of wisdom operation, surfing are relatively slow, model modification is relatively slow, operation is supported The problems such as pillar reason could be improved.
Content of the invention
The technical problem to be solved is the defect making up above-mentioned prior art, proposes one kind and is based on BIM technology The management of engineering multidimensional model and application process.
The technical problem of the present invention is solved by the following technical programs.
The management of this engineering multidimensional model based on BIM technology and application process, including 1)Prospecting, design, construction, Set up or improve the multidimensional model of engineering project in operation or maintenance processes, and by engineering multidimensional model be applied to prospecting, design, In each stages such as construction, operation or maintenance, wherein multidimensional model can be 3D, 4D, 5D, 6D, 7D etc..I.e. in engineering threedimensional model base Progress data, workload data, material are increased on plinth(Materials)Data, device data, cost data, work plan data, when Between arrange data, demographic data, service life, Quick Response Code or coding, survey data, test data, mix data, tensioning number According to, the data that paves, roll data, quality detecting data or monitoring data etc..
2)Set up the management system of engineering multidimensional model, according to the single component of engineering subdivision, single race, component groups or structure Part assembly construction procedure carries out the modularity of engineering project, parametric modeling;According to engineering subdivision single component, single race, Component groups or component assembly construction procedure carry out progress data, workload data, material(Materials)Data, device data, cost Data, work plan data, arrangement of time data, demographic data, service life, Quick Response Code or coding, survey data, test number According to, mix data, tension data, the data that paves, roll the data layout such as data, quality detecting data or monitoring data.
3)Single component by engineering subdivision(Title, ID, Quick Response Code), single race, component groups, engineering time section, construction Progress, construction procedure, Quick Response Code or coding are inquiring about progress data, workload data, material(Materials)Data, device data, Cost data, work plan data, arrangement of time data, demographic data, service life, Quick Response Code or coding, survey data, examination Test data, mix data, tension data, the data that paves, roll data, quality detecting data or monitoring data etc..
For example:The survey data on the road surface in a certain section can be inquired about, designer's data, workmen's data, construction set Standby data(Using relevant device), work progress data(Mix data, the data that paves, roll data etc.).
4)Component processing side or material(Materials)Provider passes through the subsequent period of time in plan for the reading project multidimensional model (For example:Second day or next month)Material requested(Materials)Inventory situation, wherein required component carries out customized, preparation or processes.
5)Change situations such as the one of planned time of the project implementation, scheme or progress, adjustment engineering is many Dimension module progress data, planning data and other related datas.
6)Monitor or record concrete component or position work progress data, and be loaded in multidimensional model, such as:Personnel's number According to, test data, mix data, tension data, the data that paves, roll data, quality detecting data.
7)By GIS, multidimensional model, alignment system, operation planning and engineering equipment intelligent operating system set, accomplish unmanned The function such as driving or intelligence construction.
For example:Intelligent control equipment reads the construction access road data of road roller plan(Roll data)Carry out grinding operation.
8)In the case that engineering increases newly or changes, multidimensional model system can select individually to increase certain part or structure newly Part, updates certain part or component, or a newly-increased record, and without updating whole models, thus lift scheme browses speed Degree or model management speed.
9)Model system can be according to the selection of user or visual angle, only the calling its concern or can watch of intelligent selection Department pattern data, never calls hiding data.Thus improving the speed of service of big figure model.
10)The asset management of operation stage, intellectual analysis;The service life decline of single component is pressed in operation, maintenance stage Curve is changed after being analyzed, and the time of component is changed in the depreciation curve optimization according to component, thus it is overall to lift engineering Life-span.
In sum, the beneficial effect that the present invention is compared with the prior art is:
The inventive method can solve the problems with finding in engineering actual mechanical process:Existing engineering BIM model lacks The support of some data weary, lacks effectively utilizes to data, lack of wisdom adjustment, lack of wisdom operation, surfing be relatively slow, The problems such as model modification is relatively slow, maintenance management could be improved.
The inventive method by newly-increased related data, newly-increased method using data, intelligent control plan, intelligent operation, Modification model modification pattern, modification model browse mode, improvement maintenance management method can effectively lift construction quality And the management level of engineering, it is that upgrading potentiation, the energy-conserving and environment-protective of building industry create conditions.The inventive method root in engineer applied According to specifically needing corresponding software is carried out configuring.
Specific embodiment
With reference to specific embodiment, the present invention is further illustrated.
The management of the engineering multidimensional model based on BIM technology and application process, including following some.
1)Set up or improve the multidimensional model of engineering project in prospecting, design, construction, operation or maintenance processes, and will Engineering multidimensional model is applied to prospecting, design, construction, operation or each stage such as maintenance, wherein multidimensional model can be 3D, 4D, 5D, 6D, 7D etc..On the basis of engineering threedimensional model, increase progress data, workload data, material(Materials)Data, equipment Data, cost data, work plan data, arrangement of time data, demographic data, service life, Quick Response Code or coding, prospecting number According to, test data, mix data, tension data, the data that paves, roll data, quality detecting data or monitoring data etc..
2)Set up the management system of engineering multidimensional model, according to the single component of engineering subdivision, single race, component groups or structure Part assembly construction procedure carries out the modularity of engineering project, parametric modeling;According to engineering subdivision single component, single race, Component groups or component assembly construction procedure carry out progress data, workload data, material(Materials)Data, device data, cost Data, work plan data, arrangement of time data, demographic data, service life, Quick Response Code or coding, survey data, test number According to, mix data, tension data, the data that paves, roll the data layout such as data, quality detecting data or monitoring data.
3)Single component by engineering subdivision(Title, ID, Quick Response Code), single race, component groups, engineering time section, construction Progress, construction procedure, Quick Response Code or coding are inquiring about progress data, workload data, material(Materials)Data, device data, Cost data, work plan data, arrangement of time data, demographic data, service life, Quick Response Code or coding, survey data, examination Test data, mix data, tension data, the data that paves, roll data, quality detecting data or monitoring data etc..
For example:The survey data on the road surface in a certain section can be inquired about, designer's data, workmen's data, construction set Standby data(Using relevant device), work progress data(Mix data, the data that paves, roll data etc.).
4)Component processing side or material(Materials)Provider passes through the subsequent period of time in plan for the reading project multidimensional model (For example:Second day or next month)Material requested(Materials)Inventory situation, wherein required component carries out customized, preparation or processes.
5)Change situations such as the one of planned time of the project implementation, scheme or progress, adjustment engineering is many Dimension module progress data, planning data and other related datas.
6)Monitor or record concrete component or position work progress data, and be loaded in multidimensional model, such as:Personnel's number According to, test data, mix data, tension data, the data that paves, roll data, quality detecting data.
7)By GIS, multidimensional model, alignment system, operation planning and engineering equipment intelligent operating system set, accomplish unmanned The function such as driving or intelligence construction.
For example:Intelligent control equipment reads the construction access road data of road roller plan(Roll data)Carry out grinding operation.
8)In the case that engineering increases newly or changes, multidimensional model system can select individually to increase certain part or structure newly Part, updates certain part or component, or a newly-increased record, and without updating whole models, thus lift scheme browses speed Degree or model management speed.
9)Model system can be according to the selection of user or visual angle, only the calling its concern or can watch of intelligent selection Department pattern data, never calls hiding data.Thus improving the speed of service of big figure model.
10)The asset management of operation stage, intellectual analysis;The service life decline of single component is pressed in operation, maintenance stage Curve is changed after being analyzed, and the time of component is changed in the depreciation curve optimization according to component, thus it is overall to lift engineering Life-span.
Above content is to further describe it is impossible to assert with reference to specific preferred implementation is made for the present invention Being embodied as of the present invention is confined to these explanations.For general technical staff of the technical field of the invention, Without departing from making some equivalent substitutes or obvious modification on the premise of present inventive concept, and performance or purposes are identical, then should It is considered as belonging to the protection domain that the present invention is determined by the claims submitted to.

Claims (10)

1. the management and methods for using them of the engineering multidimensional model based on BIM technology is it is characterised in that set up engineering multidimensional model Management system, sets up or improves engineering project multidimensional model, increases multiple data on the basis of engineering threedimensional model.
2. the engineering multidimensional model based on BIM technology management and methods for using them it is characterised in that according to engineering subdivision unit Carry out modularity, parametric modeling;Unit according to engineering subdivision carries out data layout.
3. the engineering multidimensional model based on BIM technology management and methods for using them it is characterised in that by engineering subdivision unit Lai Inquiry data.
4. the management and methods for using them of the engineering multidimensional model based on BIM technology is it is characterised in that component processing side or material (Materials)Provider is prepared work by reading project multidimensional model listings data in follow-up plan.
5. the management and methods for using them of the engineering multidimensional model based on BIM technology is it is characterised in that when the plan of the project implementation Between, scheme or when there is change situations such as progress, adjustment engineering multidimensional model progress data, planning data and other are related Data.
6. the management and methods for using them of the engineering multidimensional model based on BIM technology is it is characterised in that monitoring or recording concrete component Or position work progress data, and it is loaded in engineering multidimensional model.
7. the management and methods for using them of the engineering multidimensional model based on BIM technology is it is characterised in that by GIS, engineering multidimensional mould Type, alignment system, operation planning or construction plan and device intelligence operating system etc. are gathered, and realize unmanned or intelligence construction Etc. function.
8. the engineering multidimensional model based on BIM technology management and methods for using them it is characterised in that engineering increase newly or change In the case of, engineering multidimensional model can select a newly-increased record or individually increase newly or update certain part or component.
9. the engineering multidimensional model based on BIM technology management and methods for using them it is characterised in that can according to the needs of user, Intelligent selection only call its concern or the department pattern data that can watch, never call hiding data.
10. the management and methods for using them of the engineering multidimensional model based on BIM technology is it is characterised in that press the use of single component Life-span decline curve or depreciation curve are changed after carrying out intellectual analysis.
CN201610852631.5A 2016-09-27 2016-09-27 BIM (Building Information Modeling) technology-based management and application method of construction multidimensional model Pending CN106384200A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610852631.5A CN106384200A (en) 2016-09-27 2016-09-27 BIM (Building Information Modeling) technology-based management and application method of construction multidimensional model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610852631.5A CN106384200A (en) 2016-09-27 2016-09-27 BIM (Building Information Modeling) technology-based management and application method of construction multidimensional model

Publications (1)

Publication Number Publication Date
CN106384200A true CN106384200A (en) 2017-02-08

Family

ID=57935968

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610852631.5A Pending CN106384200A (en) 2016-09-27 2016-09-27 BIM (Building Information Modeling) technology-based management and application method of construction multidimensional model

Country Status (1)

Country Link
CN (1) CN106384200A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107133386A (en) * 2017-04-10 2017-09-05 东易日盛家居装饰集团股份有限公司 A kind of fitment material for family consumption inventory generation method and system based on BIM softwares
CN107563089A (en) * 2017-09-15 2018-01-09 中建海峡建设发展有限公司 The method and computing device of PC components generation task list based on BIM
CN107730142A (en) * 2017-11-02 2018-02-23 杭州埃欧哲建设工程咨询有限公司 Using Quick Response Code in BIM project management system
CN108428035A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of settlement method and device of the EMPC manufacture links based on BIM
CN108428094A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of design side's collaborative management method and device based on BIM
CN108427696A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of acquisition methods and device of the design document based on BIM
CN108428093A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of construction party collaborative management method and device based on BIM
CN108549963A (en) * 2018-02-22 2018-09-18 北京中建建筑设计院有限公司 A kind of novel execution management method therefor based on BIM information flow standards
CN109389358A (en) * 2018-08-23 2019-02-26 上海水顿智能科技有限公司 Project management system and method based on GIS
CN109460834A (en) * 2018-10-26 2019-03-12 上海达实联欣科技发展有限公司 Build operation management system and its management method
CN109918811A (en) * 2019-03-14 2019-06-21 吉林省双洮高速公路有限公司 Block-based concept establishes the method and system of highway BIM model

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103247004A (en) * 2013-04-28 2013-08-14 中建安装工程有限公司 Information management method and system based on electromechanical integrated BIM (building information model)
CN103970919A (en) * 2013-02-04 2014-08-06 上海市城市建设设计研究总院 Automatic building information modeling data processing method
CN105844380A (en) * 2016-01-26 2016-08-10 湖北文理学院 BIM-based BIM project element management method and system
CN105956310A (en) * 2016-05-16 2016-09-21 中建安装工程有限公司 Technology for electromechanical modularized design and combined installation
CN105976089A (en) * 2016-04-27 2016-09-28 中交第二航务工程局有限公司 Construction data classification system based on building information model and method thereof
CN106296473A (en) * 2015-05-28 2017-01-04 上海宝冶集团有限公司 A kind of construction project progress real-time control method based on BIM technology

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103970919A (en) * 2013-02-04 2014-08-06 上海市城市建设设计研究总院 Automatic building information modeling data processing method
CN103247004A (en) * 2013-04-28 2013-08-14 中建安装工程有限公司 Information management method and system based on electromechanical integrated BIM (building information model)
CN106296473A (en) * 2015-05-28 2017-01-04 上海宝冶集团有限公司 A kind of construction project progress real-time control method based on BIM technology
CN105844380A (en) * 2016-01-26 2016-08-10 湖北文理学院 BIM-based BIM project element management method and system
CN105976089A (en) * 2016-04-27 2016-09-28 中交第二航务工程局有限公司 Construction data classification system based on building information model and method thereof
CN105956310A (en) * 2016-05-16 2016-09-21 中建安装工程有限公司 Technology for electromechanical modularized design and combined installation

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107133386A (en) * 2017-04-10 2017-09-05 东易日盛家居装饰集团股份有限公司 A kind of fitment material for family consumption inventory generation method and system based on BIM softwares
CN108428035A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of settlement method and device of the EMPC manufacture links based on BIM
CN108428094A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of design side's collaborative management method and device based on BIM
CN108427696A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of acquisition methods and device of the design document based on BIM
CN108428093A (en) * 2017-08-12 2018-08-21 中民筑友科技投资有限公司 A kind of construction party collaborative management method and device based on BIM
CN108428035B (en) * 2017-08-12 2022-03-29 中民筑友科技投资有限公司 BIM-based EMPC manufacturing link settlement method and device
CN107563089A (en) * 2017-09-15 2018-01-09 中建海峡建设发展有限公司 The method and computing device of PC components generation task list based on BIM
CN107730142A (en) * 2017-11-02 2018-02-23 杭州埃欧哲建设工程咨询有限公司 Using Quick Response Code in BIM project management system
CN108549963A (en) * 2018-02-22 2018-09-18 北京中建建筑设计院有限公司 A kind of novel execution management method therefor based on BIM information flow standards
CN109389358A (en) * 2018-08-23 2019-02-26 上海水顿智能科技有限公司 Project management system and method based on GIS
CN109460834A (en) * 2018-10-26 2019-03-12 上海达实联欣科技发展有限公司 Build operation management system and its management method
CN109918811A (en) * 2019-03-14 2019-06-21 吉林省双洮高速公路有限公司 Block-based concept establishes the method and system of highway BIM model

Similar Documents

Publication Publication Date Title
CN106384200A (en) BIM (Building Information Modeling) technology-based management and application method of construction multidimensional model
CN111539583B (en) Production process simulation optimization method based on digital twin
Veile et al. Lessons learned from Industry 4.0 implementation in the German manufacturing industry
Luo et al. Supply chain management for prefabricated building projects in Hong Kong
Du et al. RFID and multi-agent based architecture for information sharing in prefabricated component supply chain
Bamana et al. Simulation of a construction project: assessing impact of just-in-time and lean principles
Hegazy et al. Efficient repetitive scheduling for high-rise construction
US20080097734A1 (en) System And Method For Simulating Global Product Development
CN101493864B (en) Method and system for analyzing performance of a wind farm
Chen et al. Multiperspective approach to exploring comprehensive cause factors for interface issues
Nick et al. Industry 4.0 readiness in manufacturing: Company Compass 2.0, a renewed framework and solution for Industry 4.0 maturity assessment
CN108198093B (en) CPS-based intelligent building system
CN103106559A (en) Virtual-actual fusion industrial engineering comprehensive experiment system
CN112052500A (en) BIM-based method and system for updating components in intelligent building platform
Abd Rashid et al. Critical success factors CSFs to automation and robotics in industrialized building system IBS
Potkány et al. Research into customer preferences of potential buyers of simple wood-based houses for the purpose of using the target costing
Majstorovic et al. Smart Manufacturing as a framework for Smart Mining
Liu et al. Optimization of flow shop scheduling in precast concrete component production via mixed-integer linear programming
CN102314527B (en) Metallurgical quality modeling method based on factory modeling
Saha et al. Identifying enablers of e-manufacturing
Šindelář et al. Simulation integration framework
Appleton et al. Special purpose simulation modeling of tower cranes
Teufl et al. Optimised–developing a state of the art system for production planning for industry 4.0 in the construction industry using simulation-based optimisation
Zheng et al. Cycle time reduction in assembly and test manufacturing factories: A KPI driven methodology
Yang et al. Quality Control in Modular Construction Manufacturing During COVID-19: Process and Management Standardization

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170208

RJ01 Rejection of invention patent application after publication