CN107563089A - The method and computing device of PC components generation task list based on BIM - Google Patents
The method and computing device of PC components generation task list based on BIM Download PDFInfo
- Publication number
- CN107563089A CN107563089A CN201710830148.1A CN201710830148A CN107563089A CN 107563089 A CN107563089 A CN 107563089A CN 201710830148 A CN201710830148 A CN 201710830148A CN 107563089 A CN107563089 A CN 107563089A
- Authority
- CN
- China
- Prior art keywords
- components
- production
- information
- task list
- bim
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- General Factory Administration (AREA)
Abstract
The method and computing device of PC components generation task list of the present invention based on BIM, the overall BIM models of design are split, are decomposed into each PC components, and include details.The preliminary production schedule is established, the production schedule of the PC components is set based on time conditions, prevents production delay.The BIM models of each PC components decomposed will be split, classification set is carried out by PC Component Categories, be integrated to the resources of production demand classification template, improve scheduling production efficiency.Gather the production schedule of each PC components under the resources of production requirement templet, generate task list set.Output and parameter according to each PC components generate production planning and sequencing data, adjust the actual production planning and sequencing parameter of each PC components, improve production work efficiency.PC component task lists are uniformly issued by the format and content of setting, realize PC element factories standardization of information management, unitized, solve PC components and manufactured the data source standard in management source to differ problem.
Description
Technical field
The present invention relates to architectural design field, more particularly to the PC components based on BIM generate task list method and
Computing device.
Background technology
In modern architecture construction, PC is precast concrete(Precast concrete)English abbreviation, in house
Industrialization field is referred to as PC components.Corresponding traditional cast-in-place concrete needs building-site molding, cast-in-site and showed
Field maintenance.Precast concrete is widely used in the fields such as building, traffic, water conservancy, and important angle is played the part of in national economy
Color.Concrete prefabricated element factory establishes purchase order and manufacturing schedule with change release, is appointed with what is worked out according to design drawing
Business is single to carry out production technology and production line resource planning distribution.
PC element factories scheduling of production table and job order are the autonomous working text of different departments establishment in the prior art
Part, it can run into often in the case of manufacturing schedule establishment does not refer to job order and assign generation and plan, to production line, to cause because of technique
It is required that it is different and cause manufacturing schedule not perform according to plan, the uncontrollable of manufacturing schedule is caused, PC element factory pipes can not be realized
Information standardization, unitized is managed, solves PC components and manufactured the data source standard in management source to differ problem.
The content of the invention
Therefore, the technical problem to be solved in the present invention is how to realize PC element factories standardization of information management, unitize,
Solve PC and manufactured the data source standard in management source to differ problem.
To achieve the above object, the present invention uses following technical scheme:
The method of PC components generation task list based on BIM, suitable for being performed in computing device, is comprised the steps of:
Block mold is split, the overall BIM models of design are split, are decomposed into the BIM models of each PC components, each PC
The BIM models of component include 3-D view, node X-Y scheme, two-dimensional localization figure, scantling information, material information, technique will
Ask and quantities information;
The preliminary production schedule is established, the production schedule of the PC components is set based on time conditions;
Establish resources of production demand classification template, according to the characteristics of PC components, production technology establish using PC Component Categories as dimension
Resources of production demand classification template;
Resources integration, the BIM models of each PC components decomposed will be split, carry out classification set by PC Component Categories, be integrated to
The resources of production demand classification template;
Task list set is generated, gathers the production schedule of each PC components under the resources of production requirement templet, generates task
List collection;
Scheduling parameter regulation, output and parameter according to each PC components generate production planning and sequencing data, adjust the reality of each PC components
Border production planning and sequencing parameter;
Form is set, and sets output content and form;
Issue PC component task lists, task list include PC components essential information, project information, actual production plan information with
And owner information, the essential information include:PC component names, PC scantlings information, material information.
Wherein, also comprise the steps of:
Confirm link, check the availability for examining production planning and sequencing data, check not by then readjusting production planning and sequencing data.
Wherein, clicking on the PC component names in the PC components task list will deploy to generate PC component job orders, described
PC component job orders include:PC components three-dimensionals view, node X-Y scheme, two-dimensional localization figure, project information, Quick Response Code of tracing to the source letter
Breath, progress msg, scantling information, material information, technological requirement, quantities information.
The computing device of PC components generation task list based on BIM, comprising:
Processor, it is adapted for carrying out each instruction;And
Storage device, suitable for storing a plurality of instruction, the instruction is suitable to be loaded and performed by processor;
The fractionation instruction that the processor is sent is received, the overall BIM models of design are split, are decomposed into each PC components
BIM models, the BIM models of each PC components include 3-D view, node X-Y scheme, two-dimensional localization figure, scantling information,
Material information, technological requirement and quantities information;
The production schedule of the PC components is set based on time conditions;
Establish resources of production demand classification template, according to the characteristics of PC components, production technology establish using PC Component Categories as dimension
Resources of production demand classification template;
The BIM models of each PC components decomposed will be split, classification set is carried out by PC Component Categories, be integrated to the production money
Source demand classification template;
Gather the production schedule of each PC components under the resources of production requirement templet, generate task list set;
Output and parameter according to each PC components produce production planning and sequencing data, adjust the actual production plan of each PC components;
Output content and form are set;
Task list includes PC components essential information, project information, actual production plan information and owner information, the base
This packet contains:PC component names, PC scantlings information, material information.
Wherein, also include:
The availability for examining production planning and sequencing data is checked, is checked not by then readjusting production planning and sequencing data.
Wherein, clicking on the PC component names in the PC components task list will deploy to generate PC component job orders, described
PC component job orders include:PC components three-dimensionals view, node X-Y scheme, two-dimensional localization figure, project information, Quick Response Code of tracing to the source letter
Breath, progress msg, scantling information, material information, technological requirement, quantities information.
The present invention has the advantages that:
1st, the method and computing device of the PC components generation task list of the present invention based on BIM, by the overall BIM of design
Model is split, and is decomposed into each PC components, and include details.The preliminary production schedule is established, is set based on time conditions
The production schedule of the fixed PC components, prevents production delay.The BIM models of each PC components decomposed will be split, by PC components
Classification carries out classification set, is integrated to the resources of production demand classification template, improves scheduling production efficiency.Gather the production
The production schedule of each PC components under resource requirement template, generate task list set.Output and ginseng according to each PC components
Number generation production planning and sequencing data, adjust the actual production planning and sequencing parameter of each PC components, improve production work efficiency.By the lattice of setting
Formula and content uniformly issue PC component task lists, realize PC element factories standardization of information management, unitized, solution PC components
The data source standard for manufacturing management source differs problem.
2nd, the method and computing device of the PC components generation task list of the present invention based on BIM, also comprising confirmation
Link, the availability for examining production planning and sequencing data is checked, prevent occurring delivering sequence error, production effect during formal scheduling
Rate is low.
3rd, the method and computing device of the PC components generation task list of the present invention based on BIM, clicks on the PC
PC component names in component task list will deploy to generate PC component job orders, and the PC components job order includes:PC components
3-D view, node X-Y scheme, two-dimensional localization figure, project information, 2 D code information of tracing to the source, progress msg, scantling information,
The details such as material information, technological requirement, quantities information, convenient follow-up tracking.
Brief description of the drawings
In order that the content of invention is more likely to be clearly understood, the specific embodiment below according to the present invention simultaneously combines attached
Figure, the present invention is further detailed explanation, wherein
Fig. 1 is the flow chart of the method for PC component generation task list of the present invention based on BIM.
Embodiment
Embodiment one
Referring to Fig. 1, the method for the PC components generation task list based on BIM, suitable for being performed in computing device, inserted using BIM
Part is applied on the basis of Revit modelings, is completed the generation of job order by a series of clicking operations of plug-in unit, is included following step
Suddenly:
Block mold is split, the overall BIM models of design are split, using each PC components as classification, are decomposed into each PC structures
The BIM models of part.Such as by the overall BIM model decompositions of house desigh it is each PC components such as wall, beam, plate, post.Each PC structures
The BIM models of part include 3-D view, node X-Y scheme, two-dimensional localization figure, scantling information, material information, technological requirement
And quantities information.
The preliminary production schedule is established, the production schedule of the PC components is set based on time conditions, such as:Post, production are handed over
It is December 1 to pay the date.
Establish resources of production demand classification template, according to the characteristics of PC components, production technology establish using PC Component Categories as
The resources of production demand classification template of dimension, such as the PC components by all walls, are classified under " wall ".
Resources integration, the BIM models of each PC components decomposed will be split, classification set is carried out by PC Component Categories, collected
Into the extremely resources of production demand classification template, such as will own the PC component sets of " post " under the classification model of " post ".
Task list set is generated, gathers the production schedule of each PC components under the resources of production requirement templet, generation
Task list set.
Scheduling parameter regulation, output and parameter according to each PC components generate production planning and sequencing data, adjust each PC components
Actual production planning and sequencing parameter.Scheduling parameter is recorded simultaneously, and the purpose of record scheduling parameter is to understand actual production scheduling, example
If this moon " post " scheduling is that at full capacity, and " stake " scheduling rate is relatively low, then the Operational preparation for next month provides adjustment foundation.
Form is set, and sets output content and form, for example include what content and figure tableau format.
PC component task lists are issued, task list includes PC components essential information, project information, actual production plan letter
Breath and owner information, the essential information include:PC component names, PC scantlings information, material information.
It is of the present invention based on BIM PC components generation task list method by overall BIM models split after PC
Component figure element schedule, 4D models are formed, comprising manufacturing schedule information, a design phase can be according to plant requirements
Form generation production task book, and pass through mobile Internet application technology and realize and manufacture project management source information data
Agreement and process movement cooperation management.With hand woven job order in the prior art, schedule mode compared with, be based on
BIM automation job order generation can effectively improve operating efficiency, strengthen the accuracy and science of job order establishment, lifting
The uniformity and operability of task forms data.The actual production planning and sequencing parameter of each PC components is adjusted, improves production work efficiency.
PC component task lists are uniformly issued by the format and content of setting, PC element factories standardization of information management is realized, unitizes,
Solve PC components and manufactured the data source standard in management source to differ problem.
Preferably, also comprise the steps of:
Confirm link, check the availability for examining production planning and sequencing data, check not by then readjusting production planning and sequencing data, prevent
Only occur delivering sequence error during formal scheduling, production efficiency is low.Confirm link, the checking of account need to be carried out, tested
Whether the biological characteristic of card account matches, and prevents malice from distorting.
Preferably, clicking on the PC component names in the PC components task list will deploy to generate PC component job orders, institute
PC component job orders are stated to include:PC components three-dimensionals view, node X-Y scheme, two-dimensional localization figure, project information, Quick Response Code of tracing to the source letter
Breath, progress msg, scantling information, material information, technological requirement, quantities information.The Quick Response Code that will trace to the source is stamped described
On PC components, by handheld terminal scanning trace to the source Quick Response Code can go directly system database link, obtain the design of the PC components
Information, and information is manufactured, provide data basis for follow-up retrospect.
Embodiment two
The computing device of PC components generation task list based on BIM, comprising:
Processor, it is adapted for carrying out each instruction;And
Storage device, suitable for storing a plurality of instruction, the instruction is suitable to be loaded and performed by processor.
The fractionation instruction that the processor is sent is received, the overall BIM models of design are split, are decomposed into each PC
The BIM models of component, the BIM models of each PC components include 3-D view, node X-Y scheme, two-dimensional localization figure, scantling
Information, material information, technological requirement and quantities information.
The production schedule of the PC components is set based on time conditions.
Establish resources of production demand classification template, according to the characteristics of PC components, production technology establish using PC Component Categories as
The resources of production demand classification template of dimension.
The BIM models of each PC components decomposed will be split, carry out classification set by PC Component Categories, be integrated to the life
Produce resource requirement classification model.
Gather the production schedule of each PC components under the resources of production requirement templet, generate task list set.
Output and parameter according to each PC components produce production planning and sequencing data, adjust the actual production meter of each PC components
Draw.
Output content and form are set.
Task list includes PC components essential information, project information, actual production plan information and owner information, institute
Essential information is stated to include:PC component names, PC scantlings information, material information.
The computing device of PC components generation task list of the present invention based on BIM, by the overall BIM models of design
Split, be decomposed into each PC components, and include details.The preliminary production schedule is established, institute is set based on time conditions
The production schedule of PC components is stated, prevents production delay.The BIM models of each PC components decomposed will be split, by PC Component Categories
Classification set is carried out, is integrated to the resources of production demand classification template, improves scheduling production efficiency.Gather the resources of production
The production schedule of each PC components under requirement templet, generate task list set.Output and parameter according to each PC components are given birth to
Into scheduling planning data, the actual production planning and sequencing parameter of each PC components is adjusted, improves production work efficiency.By setting form and
Content uniformly issues PC component task lists, realizes PC element factories standardization of information management, unitized, solution PC component productions
The data source standard for manufacturing management source differs problem.
Preferably, also include:
The availability for examining production planning and sequencing data is checked, is checked not by then readjusting production planning and sequencing data.Prevent formal
Occur delivering sequence error during scheduling, production efficiency is low.
Preferably, clicking on the PC component names in the PC components task list will deploy to generate PC component job orders, institute
PC component job orders are stated to include:PC components three-dimensionals view, node X-Y scheme, two-dimensional localization figure, project information, Quick Response Code of tracing to the source letter
The details such as breath, progress msg, scantling information, material information, technological requirement, quantities information, convenient follow-up tracking.
Simply technical scheme is explained in detail for above-mentioned embodiment, the present invention not only only office
Be limited to above-described embodiment, it will be understood by those skilled in the art that it is every according to above-mentioned principle and spirit on the basis of the present invention
Improve, substitute, all should be within protection scope of the present invention.
Claims (6)
1. the method for the PC components generation task list based on BIM, suitable for being performed in computing device, it is characterised in that include
Following steps:
Block mold is split, the overall BIM models of design are split, are decomposed into the BIM models of each PC components, each PC
The BIM models of component include 3-D view, node X-Y scheme, two-dimensional localization figure, scantling information, material information, technique will
Ask and quantities information;
The preliminary production schedule is established, the production schedule of the PC components is set based on time conditions;
Establish resources of production demand classification template, according to the characteristics of PC components, production technology establish using PC Component Categories as dimension
Resources of production demand classification template;
Resources integration, the BIM models of each PC components decomposed will be split, carry out classification set by PC Component Categories, be integrated to
The resources of production demand classification template;
Task list set is generated, gathers the production schedule of each PC components under the resources of production requirement templet, generates task
List collection;
Scheduling parameter regulation, output and parameter according to each PC components generate production planning and sequencing data, adjust the reality of each PC components
Border production planning and sequencing parameter;
Form is set, and sets output content and form;
Issue PC component task lists, task list include PC components essential information, project information, actual production plan information with
And owner information, the essential information include:PC component names, PC scantlings information, material information.
2. as claimed in claim 1 based on BIM PC components generation task list method, it is characterised in that also include with
Lower step:
Confirm link, check the availability for examining production planning and sequencing data, check not by then readjusting production planning and sequencing data.
3. the method for the PC components generation task list based on BIM as claimed in claim 2, it is characterised in that described in click
PC component names in PC component task lists will deploy to generate PC component job orders, and the PC components job order includes:PC structures
Part 3-D view, node X-Y scheme, two-dimensional localization figure, project information, 2 D code information of tracing to the source, progress msg, scantling letter
Breath, material information, technological requirement, quantities information.
4. the computing device of the PC components generation task list based on BIM, it is characterised in that include:
Processor, it is adapted for carrying out each instruction;And
Storage device, suitable for storing a plurality of instruction, the instruction is suitable to be loaded and performed by processor;
The fractionation instruction that the processor is sent is received, the overall BIM models of design are split, are decomposed into each PC components
BIM models, the BIM models of each PC components include 3-D view, node X-Y scheme, two-dimensional localization figure, scantling information,
Material information, technological requirement and quantities information;
The production schedule of the PC components is set based on time conditions;
Establish resources of production demand classification template, according to the characteristics of PC components, production technology establish using PC Component Categories as dimension
Resources of production demand classification template;
The BIM models of each PC components decomposed will be split, classification set is carried out by PC Component Categories, be integrated to the production money
Source demand classification template;
Gather the production schedule of each PC components under the resources of production requirement templet, generate task list set;
Output and parameter according to each PC components produce production planning and sequencing data, adjust the actual production plan of each PC components;
Output content and form are set;
Task list includes PC components essential information, project information, actual production plan information and owner information, the base
This packet contains:PC component names, PC scantlings information, material information.
5. the computing device of the PC components generation task list based on BIM as claimed in claim 4, it is characterised in that also wrap
Contain:
The availability for examining production planning and sequencing data is checked, is checked not by then readjusting production planning and sequencing data.
6. the computing device of the PC components generation task list based on BIM as claimed in claim 5, it is characterised in that click on
PC component names in the PC components task list will deploy to generate PC component job orders, and the PC components job order includes:
PC components three-dimensionals view, node X-Y scheme, two-dimensional localization figure, project information, 2 D code information of tracing to the source, progress msg, component chi
Very little information, material information, technological requirement, quantities information.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710830148.1A CN107563089A (en) | 2017-09-15 | 2017-09-15 | The method and computing device of PC components generation task list based on BIM |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710830148.1A CN107563089A (en) | 2017-09-15 | 2017-09-15 | The method and computing device of PC components generation task list based on BIM |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107563089A true CN107563089A (en) | 2018-01-09 |
Family
ID=60981042
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710830148.1A Pending CN107563089A (en) | 2017-09-15 | 2017-09-15 | The method and computing device of PC components generation task list based on BIM |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107563089A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110110431A (en) * | 2019-04-30 | 2019-08-09 | 中国二十冶集团有限公司 | PC stair combine BIM modeling calculation amount method with site concrete |
CN111914325A (en) * | 2020-07-06 | 2020-11-10 | 上海宝冶冶金工程有限公司 | BIM technology-based blast furnace body frame structure model information interaction method |
CN113012000A (en) * | 2021-04-20 | 2021-06-22 | 重庆大学 | BIM-based intelligent management method and system for assembly type building construction |
CN113032872A (en) * | 2021-03-12 | 2021-06-25 | 北京六建集团有限责任公司 | BIM technology-based integrated resource management and control method for assembly type building progress plan |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20140121145A (en) * | 2013-04-05 | 2014-10-15 | 서울대학교산학협력단 | BIM based Integrated Management System for Constrcution Data |
CN104281729A (en) * | 2014-07-02 | 2015-01-14 | 哈尔滨工业大学 | BIM (building information model) method for digital processing and manufacturing of steel structure buildings |
CN106384200A (en) * | 2016-09-27 | 2017-02-08 | 朱海涛 | BIM (Building Information Modeling) technology-based management and application method of construction multidimensional model |
CN106600137A (en) * | 2016-12-08 | 2017-04-26 | 东莞华南设计创新院 | Application method of steel structure BIM (building information modeling) informatization platform |
-
2017
- 2017-09-15 CN CN201710830148.1A patent/CN107563089A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20140121145A (en) * | 2013-04-05 | 2014-10-15 | 서울대학교산학협력단 | BIM based Integrated Management System for Constrcution Data |
CN104281729A (en) * | 2014-07-02 | 2015-01-14 | 哈尔滨工业大学 | BIM (building information model) method for digital processing and manufacturing of steel structure buildings |
CN106384200A (en) * | 2016-09-27 | 2017-02-08 | 朱海涛 | BIM (Building Information Modeling) technology-based management and application method of construction multidimensional model |
CN106600137A (en) * | 2016-12-08 | 2017-04-26 | 东莞华南设计创新院 | Application method of steel structure BIM (building information modeling) informatization platform |
Non-Patent Citations (1)
Title |
---|
朱瑞添等: "基于BIM技术的装配式建筑设计与制造协同应用研究", 《中国建设信息化》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110110431A (en) * | 2019-04-30 | 2019-08-09 | 中国二十冶集团有限公司 | PC stair combine BIM modeling calculation amount method with site concrete |
CN111914325A (en) * | 2020-07-06 | 2020-11-10 | 上海宝冶冶金工程有限公司 | BIM technology-based blast furnace body frame structure model information interaction method |
CN111914325B (en) * | 2020-07-06 | 2022-04-22 | 上海宝冶冶金工程有限公司 | BIM technology-based blast furnace body frame structure model information interaction method |
CN113032872A (en) * | 2021-03-12 | 2021-06-25 | 北京六建集团有限责任公司 | BIM technology-based integrated resource management and control method for assembly type building progress plan |
CN113032872B (en) * | 2021-03-12 | 2023-12-15 | 北京六建集团有限责任公司 | BIM technology-based fabricated building progress plan comprehensive resource management and control method |
CN113012000A (en) * | 2021-04-20 | 2021-06-22 | 重庆大学 | BIM-based intelligent management method and system for assembly type building construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107563089A (en) | The method and computing device of PC components generation task list based on BIM | |
CN108971807A (en) | A kind of site welding construction technology intelligent management control method and management system | |
CN106845919A (en) | Construction information collection processing method | |
CN101256647A (en) | Item management system being suitable for garden engineering | |
CN109522527B (en) | Method for compiling field construction process by using software system | |
CN109522661A (en) | A kind of Building Information Model component and work breakdown structure (WBS) correlating method and system | |
CN105160458A (en) | Information processing system and method supporting seven-dimensional ledger equipment management | |
Lee et al. | Concurrent material flow analysis by P3R-driven modeling and simulation in PLM | |
CN112541749A (en) | Construction progress management system based on BIM technology | |
CN107368972A (en) | It is a kind of that work platform and its application method are sent based on BIM technology | |
CN110689214A (en) | Material supply intelligent collection management control platform | |
Melzner | BIM-based takt-time planning and takt control: Requirements for digital construction process management | |
CN109583534B (en) | Equipment purchase fee automatic statistical method based on material ID and Internet of things label | |
CN103136611A (en) | Digitization generation method for emergency plan | |
JP7111909B2 (en) | PROJECT MANAGEMENT DEVICE, PROJECT MANAGEMENT METHOD, AND RECORDING MEDIUM | |
McClymonds et al. | Information Exchange for Supporting BIM to Robotic Construction | |
CN112613849A (en) | BIM-based project supervision information management method | |
CN116663098A (en) | Construction scene graphical management method and device based on BIM | |
CN108256625A (en) | It is decomposed based on multilayer in modelling cloud and innovates creative method with the gunz summed up | |
Xiao et al. | Study on Construction Engineering Management Based on BIM from the perspective of big data | |
Khan et al. | A Systematic Review of Risks in Modular Integrated Construction Practice | |
CN112884455A (en) | Task plan processing system, method and device | |
Teufl et al. | Optimised–developing a state of the art system for production planning for industry 4.0 in the construction industry using simulation-based optimisation | |
Yang et al. | Manufacturing of modular buildings: A literature review | |
CN109344453A (en) | A kind of elevator the Automation Design production system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180109 |
|
RJ01 | Rejection of invention patent application after publication |