CN111754138A - Engineering construction progress plan management and control system and method based on BIM model - Google Patents

Engineering construction progress plan management and control system and method based on BIM model Download PDF

Info

Publication number
CN111754138A
CN111754138A CN202010646445.2A CN202010646445A CN111754138A CN 111754138 A CN111754138 A CN 111754138A CN 202010646445 A CN202010646445 A CN 202010646445A CN 111754138 A CN111754138 A CN 111754138A
Authority
CN
China
Prior art keywords
task
bim
plan
bim model
progress
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010646445.2A
Other languages
Chinese (zh)
Other versions
CN111754138B (en
Inventor
何小龙
何卫红
刘涛
胡亚东
孙利波
王威
王汝贤
杨超
张明生
孔庆森
段然
王倩
伊丁
彭妙培
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Cement Industry Design and Research Institute Co Ltd
Original Assignee
Tianjin Cement Industry Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Cement Industry Design and Research Institute Co Ltd filed Critical Tianjin Cement Industry Design and Research Institute Co Ltd
Priority to CN202010646445.2A priority Critical patent/CN111754138B/en
Publication of CN111754138A publication Critical patent/CN111754138A/en
Application granted granted Critical
Publication of CN111754138B publication Critical patent/CN111754138B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F3/00Input arrangements for transferring data to be processed into a form capable of being handled by the computer; Output arrangements for transferring data from processing unit to output unit, e.g. interface arrangements
    • G06F3/01Input arrangements or combined input and output arrangements for interaction between user and computer
    • G06F3/048Interaction techniques based on graphical user interfaces [GUI]
    • G06F3/0484Interaction techniques based on graphical user interfaces [GUI] for the control of specific functions or operations, e.g. selecting or manipulating an object, an image or a displayed text element, setting a parameter value or selecting a range
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F3/00Input arrangements for transferring data to be processed into a form capable of being handled by the computer; Output arrangements for transferring data from processing unit to output unit, e.g. interface arrangements
    • G06F3/01Input arrangements or combined input and output arrangements for interaction between user and computer
    • G06F3/048Interaction techniques based on graphical user interfaces [GUI]
    • G06F3/0484Interaction techniques based on graphical user interfaces [GUI] for the control of specific functions or operations, e.g. selecting or manipulating an object, an image or a displayed text element, setting a parameter value or selecting a range
    • G06F3/0486Drag-and-drop
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063114Status monitoring or status determination for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063116Schedule adjustment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Game Theory and Decision Science (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • General Engineering & Computer Science (AREA)
  • Human Computer Interaction (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses an engineering construction progress plan management and control system and method based on a BIM (building information modeling) model, which are used for effectively managing and controlling plan progress data. Belong to engineering construction technical field, its characterized in that includes at least: the BIM coding standard establishing module is used for establishing a unified BIM coding standard; the BIM model building module is used for building a BIM model; the engineering construction plan generation module is used for generating an engineering construction plan based on the BIM model; the plan display and compilation module is used for displaying and compiling a plan based on the BIM model; a BIM model change module; a progress feedback module; after plan editing is completed, acquiring actual progress in real time; a plan progress simulation module; and the analysis module is used for analyzing the influence factors of the progress plan.

Description

Engineering construction progress plan management and control system and method based on BIM model
The technical field is as follows:
the invention belongs to the technical field of engineering construction, and particularly relates to an engineering construction progress plan management and control system and method based on a BIM (building information modeling).
Background art:
at present, BIM at home and abroad enters a rapid development stage. Although China starts late, the BIM development trend is clear. Enterprises begin to accelerate data mining related to BIM, focus on application of BIM in the aspects of engineering quantity calculation, bid decision making and the like, and practice integrated project management and control, post-maintenance and the like of BIM.
The whole engineering construction period relates to the influence of factors such as project planning, design, purchase, logistics, construction and debugging, the complexity is higher and higher, and the requirement on the professional level of project progress plan management and control personnel is higher and higher. The traditional method for planning project and discussing periodic meetings to correct the project cannot provide comprehensive guidance for engineering construction. The rapid development of the BIM technology provides a plan progress control means, engineering construction data is associated through a BIM model, an information island is opened, and a visual display platform is provided to guide planning and progress control.
At present, a great deal of research is conducted on progress control based on the BIM technology by many scholars at home and abroad, and the progress control is mainly reflected in the generation of a construction plan, a lightweight display model, the comparative analysis of the construction progress plan and the actual progress based on the BIM technology and the like. However, in the engineering construction field, relevant research results are still lacking at home and abroad for BIM coding, BIM characteristic extraction, engineering full-period influence factors, planning data problem tracing and the like. In summary, how to effectively solve the problems that the project construction complete cycle planning is unreasonable, the progress cannot be effectively controlled, the project construction period is affected, and the like, is a problem which needs to be solved by technical personnel in the field at present.
The invention content is as follows:
aiming at the defects in the prior art, the invention provides a BIM (building information modeling) -model-based engineering construction progress plan management and control system and method, which solve the practical problems of unreasonable plan generation, incomplete elements, influence factors, one-sided reworking and the like in the conventional progress management and control at present and can effectively correct the plan.
The first purpose of the invention is to provide an engineering construction progress plan management and control system based on a BIM model, which comprises:
the BIM coding standard establishing module is used for establishing a unified BIM coding standard; the method specifically comprises the following steps:
according to an engineering construction control method, a unified BIM coding standard is formulated, and relevant attribute information of each component is represented by numbers and letters; meanwhile, the attribute value corresponding to the component is retrieved from the database according to the coding information;
the BIM model building module is used for building a BIM model; the method specifically comprises the following steps:
building a three-dimensional model in a BIM modeling system according to professional requirements and BIM standard specifications, and integrating the built three-dimensional model into a complete BIM model according to factory and workshop requirements;
the engineering construction plan generation module is used for generating an engineering construction plan based on the BIM model; the method specifically comprises the following steps:
based on the BIM coding parameters, the attribute of the BIM model defines the attribution relation expression of the component in the planning task; generating an engineering construction plan task according to the plan task attribution relationship;
1) defining a set T of tasks T ═ { T1, T2, … }; t is ═ v, w, s, d >, v refers to the version, w refers to whether the change is made, s refers to the task state, and d refers to the programming time;
2) defining a task t level representation method;
representing a planned task hierarchical relation based on the attribute association set, and generating a planned task table;
the method for representing the association set is as follows:
{x=value|(S01,1),(S02,2),(S03,3),(Si,k))}(i,k>0);
wherein, X represents a specific category attribute, value represents a given attribute value, Si represents a task code, and k represents a task hierarchy;
the expression means: when x is value, Si∈S03∈S02∈S01(k>3);
Extracting coded data according to a BIM, and determining the hierarchical relation of the planned tasks by combining with a defined association set;
the plan display and compilation module is used for displaying and compiling a plan based on the BIM model; the method specifically comprises the following steps:
a light-weight method is adopted to display the BIM model and the planning task; the BIM model is browsed on a browser after being converted through lightweight, and the planned task level relation and the content are displayed on the browser end through a Web front-end development method; the BIM model and the planning task both contain the same task code (S)i) The BIM model is positioned to a specific component ID according to the task number, and the database is positioned to a specific planned task ID according to the task code, so that mapping between the BIM model and the planned task is realized;
adding corresponding logic association and making plan starting time and plan finishing time to the task at the browser end; the logic relation is dragged and labeled on the BIM, meanwhile, planning task connection lines are made on the Web plan, and based on the mapping relation between the BIM and the planning tasks, after data are stored, the logic relation between the BIM data and the planning tasks is mutually unified;
a BIM model change module;
the planning task needs to acquire the latest data according to the version number of the BIM model component;
a progress feedback module;
after plan editing is completed, acquiring actual progress in real time;
a plan progress simulation module;
performing progress simulation by combining the BIM model and the planned progress data, simulating engineering construction, civil engineering, installation and the like in a time period, finding out planned tasks which are delayed and possibly overdue by comparing planned time with actual progress, and marking different early warning colors on the BIM model from a component level;
the analysis module is used for analyzing the influence factors of the progress plan;
according to the deferred planning task and the region, the member and the associated logic correlation on the BIM model, a big data analysis method is adopted to carry out system analysis on the design factor, the procurement factor, the logistics factor and the scheduling factor related to the planning task, the true reason causing the deferred planning task is found out, and then the plan is corrected.
The second purpose of the invention is to provide a BIM model-based engineering construction progress plan control method, which comprises the following steps:
s1, establishing a unified BIM coding standard; the method specifically comprises the following steps:
according to an engineering construction control method, a unified BIM coding standard is formulated, and relevant attribute information of each component is represented by numbers and letters; meanwhile, the attribute value corresponding to the component is retrieved from the database according to the coding information;
s2, building a BIM model; the method specifically comprises the following steps:
building a three-dimensional model in a BIM modeling system according to professional requirements and BIM standard specifications, and integrating the built three-dimensional model into a complete BIM model according to factory and workshop requirements;
s3, generating an engineering construction plan based on the BIM model; the method specifically comprises the following steps:
based on the BIM coding parameters, the attribute of the BIM model defines the attribution relation expression of the component in the planning task; generating an engineering construction plan task according to the plan task attribution relationship;
1) defining a set T of tasks T ═ { T1, T2, … }; t is ═ v, w, s, d >, v refers to the version, w refers to whether the change is made, s refers to the task state, and d refers to the programming time;
2) defining a task t level representation method;
representing a planned task hierarchical relation based on the attribute association set, and generating a planned task table;
the method for representing the association set is as follows:
{x=value|(S01,1),(S02,2),(S03,3),(Si,k))}(i,k>0);
wherein, X represents a specific category attribute, value represents a given attribute value, Si represents a task code, and k represents a task hierarchy;
the expression means: when x is value, Si∈S03∈S02∈S01(k>3);
Extracting coded data according to a BIM, and determining the hierarchical relation of the planned tasks by combining with a defined association set;
s4, plan display and compilation based on the BIM model;
a light-weight method is adopted to display the BIM model and the planning task; the BIM model is browsed on a browser after being converted through lightweight, and the planned task level relation and the content are displayed on the browser end through a Web front-end development method; the BIM model and the planning task both contain the same task code (S)i) The BIM model is positioned to a specific component ID according to the task number, and the database is positioned to a specific planned task ID according to the task code, so that mapping between the BIM model and the planned task is realized;
adding corresponding logic association and making plan starting time and plan finishing time to the task at the browser end; the logic relation is dragged and labeled on the BIM, meanwhile, planning task connection lines are made on the Web plan, and based on the mapping relation between the BIM and the planning tasks, after data are stored, the logic relation between the BIM data and the planning tasks is mutually unified;
s5, changing a BIM model;
the planning task needs to acquire the latest data according to the version number of the BIM model component;
s6, progress feedback;
after plan editing is completed, acquiring actual progress in real time;
s7, simulating a planned schedule;
performing progress simulation by combining the BIM model and the planned progress data, simulating engineering construction, civil engineering, installation and the like in a time period, finding out planned tasks which are delayed and possibly overdue by comparing planned time with actual progress, and marking different early warning colors on the BIM model from a component level;
s8, analyzing the influence factors of the schedule plan;
according to the deferred planning task and the region, the member and the associated logic correlation on the BIM model, a big data analysis method is adopted to carry out system analysis on the design factor, the procurement factor, the logistics factor and the scheduling factor related to the planning task, the true reason causing the deferred planning task is found out, and then the plan is corrected.
Further, the BIM model modification specifically includes:
the BIM model change does not affect the existing planning task level;
if the BIM model component is added, directly adding the BIM model component into a planned task table according to the component coding attribute, and marking a change state;
if the BIM model component attribute is modified, storing the latest version number data in the database, and acquiring the component attribute value of the latest version by the scheduling task table;
the BIM model changes the task level of the influence plan;
if the BIM model component is deleted, the original hierarchy and task logic are changed, the planned task is adjusted according to the corresponding approval process, and the change state is marked in the planned task;
further, the progress feedback includes:
acquiring an actual progress model of an engineering site by adopting a BIM technical means, comparing the actual progress model with a planned BIM model, calculating the actual completion percentage, and feeding the actual completion percentage back to a planned task table through an interface;
adopting computer deep learning, according to the feedback picture of each intelligent camera on site, calculating the actual completion progress according to a preset progress threshold value, and feeding back the actual completion progress to the scheduled task table through an interface;
and feeding back by adopting a mobile APP terminal, generating a two-dimensional code or a record for each planned task, confirming that the task is completed by constructors or inspection personnel on the APP terminal, and feeding the completion time back to the planned task database.
The third purpose of the invention is to provide an information data processing terminal for implementing the engineering construction progress plan management and control method based on the BIM model.
A fourth object of the present invention is to provide a computer-readable storage medium, which includes instructions that, when executed on a computer, cause the computer to execute the above-mentioned project construction progress plan management and control method based on the BIM model.
The invention has the following beneficial effects:
the project construction plan progress control based on the BIM model is based on a digital platform, and is not used for controlling specific products, so that the storage, query and mutual calling of the BIM model and the plan task data are very convenient, the repetitive work is reduced, and the execution efficiency of the plan task is improved; the problem tracing, collection, comparative analysis and the like can be carried out on the planned progress, and the completion of the quality guarantee period of the engineering construction is ensured.
Description of the drawings:
FIG. 1 is a process plan administration analysis step in accordance with a preferred embodiment of the present invention;
FIG. 2 is a task association set in accordance with a preferred embodiment of the present invention;
FIG. 3 is a task hierarchy in a preferred embodiment of the present invention;
FIG. 4 is a diagram illustrating changes in the BIM model that result in changes to the planned task in accordance with a preferred embodiment of the present invention;
FIG. 5 illustrates BIM model forewarning in a preferred embodiment of the present invention;
FIG. 6 is a diagram of the hardware architecture of the preferred embodiment of the present invention;
fig. 7 is a functional block diagram of a preferred embodiment of the present invention.
The specific implementation mode is as follows:
the invention is further explained by the embodiments in the following figures.
In the embodiment, the engineering construction progress plan management and control method based on the BIM model; the BIM model management and control system is used for carrying out BIM coding, BIM model management and control, BIM plan generation, BIM progress feedback, BIM progress simulation and plan correction; referring to fig. 1, the method comprises the following steps:
s1, establishing a unified BIM coding standard;
referring to table 1, the unified BIM coding standard includes project information, workshop information, service information, professional information, spatial region information, floor information, category information, device coding information, and the like.
TABLE 1 base Material Properties and product Properties
Figure BDA0002573208520000051
For within a BIM model, a model building block code may be represented as: XXX.002.ER.BA.DB1.1F.PR.PR01
S2, building a BIM model
And building the three-dimensional model in BIM modeling software according to professional requirements and BIM standard specifications, and integrating the built three-dimensional model into a complete BIM model according to factories and workshops. The code standard information is automatically contained in each component, and when the component is clicked, the specific code classification data and the relevant attributes of the component can be looked up from the database.
S3 plan generation based on BIM model
The invention provides an attribution relation expression of a BIM (building information modeling) model attribute definition component in a planning task based on BIM coding parameters by combining the engineering construction characteristics so as to flexibly express the complex logic relation of the engineering construction task. The project construction plan tasks can be automatically generated according to the plan task affiliation relationship, and meanwhile, the model performs light mapping in the system, so that the one-to-one correspondence between construction and tasks is realized.
1) Defining a set T of tasks T ═ { T1, T2, … }; t is ═ v, w, s, d >, v refers to the version, w refers to whether the change is made, s refers to the task state, and d refers to the programming time; in the storage model, there are multiple records for a task, but there is only one valid tree structure for a plan instance in the case of versioning.
Referring to table 2, a task in the database includes two records, and the task attributes include a task code, a task name, a pre-task, a construction period, a weight, a project amount, a scheduled start time, a scheduled finish time, an actual start time, an actual finish time, and the like. The latest version and state (state 1, version number V2) are read at the time of task loading.
TABLE 2 planning of collaborative tasks
Figure BDA0002573208520000061
2) Definition task t-level representation method
And (3) determining a task attribute hierarchy association set according to the step 2 of the specification, wherein the task attribute hierarchy association set is used for quickly generating a plan table, a plan tree can be obtained through one-time query, and the problem of long time consumption of recursive operation is solved.
The method for representing the association set is as follows:
{x=value|(S01,1),(S02,2),(S03,3),(Si,k))}(i,k>0);
where X represents a specific class attribute, value is a value representing a given attribute value, SiIndicating the task code and k the hierarchy of tasks.
Referring to fig. 2, a task association set is sorted out according to an engineering construction management and control method and a task attribute hierarchy association method. For each BIM model, all sets are traversed and automatically collected under specific parent and child planning tasks.
S4 plan display and compilation based on BIM model
And (3) displaying the BIM model and the planning task by adopting a lightweight method. The BIM model can be browsed on a browser after being converted through light weight, and the planned task level relation and the content are displayed on the browser end (hereinafter referred to as a Web schedule) through a Web front-end development method. Because the BIM and the plan both contain the same task code (Si), the BIM can position the specific member ID according to the task number, and the database can position the specific plan task ID according to the task code, thereby realizing the mapping between the BIM and the plan task.
And the planning engineer adds corresponding logic association to the task at the browser end and formulates a planning start time and a planning completion time. The logic relation can be dragged and labeled on the BIM, and can also be a planned task connecting line on a Web plan table, and based on the mapping relation between the BIM and the planned tasks, the logic relation between the BIM data and the planned tasks is unified after the data is stored.
Referring to fig. 3, the BIM model and the planning task show effects on the browser, and the BIM model and the planning task can be linked. The plan editor edits the logical association on the interface, as well as the planning time.
S5, BIM model modification
The BIM model is changed to some extent due to various reasons, model components and attributes thereof are changed by adding, deleting and modifying, and the planning task needs to be readjusted. The planning task needs to obtain the latest data according to the BIM model component version number.
To facilitate the management and control of the planned task change, step S5 includes the following sub-steps:
s51, changing BIM model does not affect the existing planning task hierarchy
If the BIM model component is added, the change state is marked in the planning task table directly added according to the component coding attribute.
For example, a concrete column is added to a certain floor, and if the original scheduled task table does not have the task, the concrete column needs to be added to the scheduled task table when the task table is loaded.
If the BIM model component attribute is modified, the latest version number data is stored in the database, the project task table acquires the component attribute value of the latest version, such as engineering quantity and the like, and the change state is marked.
For example, the work load of a concrete column is modified on a certain floor, the task is in the original scheduling task table, the task logic relation and scheduling time are not influenced, the overall scheduling progress is only influenced, and the work load of the concrete column needs to be modified when the task table is loaded.
S52, changing and influencing planning task level of BIM model
If the BIM model component is deleted, the original hierarchy and task logic are changed, corresponding examination and approval processes need to be installed to carry out relevant adjustment on the planned task, and a change state is marked in the planned task.
Referring to fig. 4, when a task in the original planned task list is deleted, the related logic condition associated with the deleted task needs to be redefined to ensure the accurate planning, and the marking is performed on the interface (the deleted task is added, and a horizontal line is added).
S6, progress feedback and simulation
After plan editing is completed, the actual progress needs to be fed back in real time, and the project construction progress can be conveniently and comprehensively mastered by a plan management and control worker.
Preferably, the BIM progress feedback includes the following sub-steps:
and S61, acquiring an actual progress model of the engineering site by adopting BIM technical means, such as a 3D scanner, an unmanned aerial vehicle aerial photography and other technical means, comparing the actual progress model with the plan BIM model, calculating the actual completion percentage, and feeding the actual completion percentage back to the plan task list through an interface.
For example, after scanning a key workshop by a comes RTC360 scanner, a video is processed to generate a Revit model, and then the percentage of completion of each part is analyzed according to an algorithm.
And S62, calculating the actual completion progress according to the intelligent camera feedback picture of each site and a preset progress threshold value by adopting a computer deep learning (video algorithm), and feeding back the actual completion progress to the scheduled task list through an interface.
For example, the progress of the position of a floor in the marked picture is 30%, the progress of the specific equipment above the floor is 50%, the picture captured by the camera returns to the intelligent algorithm server, and the actual progress is calculated through deep learning.
And S63, feeding back by adopting the mobile APP terminal, generating a two-dimensional code or a record for each planned task, clicking on the APP terminal to confirm after the constructor finishes, and feeding back the data to the planned task database.
For example, an APP code scanning function is developed, a constructor or a patrol inspector performs code scanning feedback on the completion content, and the completion time automatically enters the database.
S7 plan progress simulation
And performing progress simulation by combining the BIM model and the planned progress data, simulating engineering construction, civil engineering, installation and the like in an exact time period, finding out planned tasks which are delayed and possibly over-timed by comparing planned time and actual progress, and marking different early warning colors on the BIM model from a component level. The reason is analyzed for the overdue tasks in the system, the plan is revised, and the final plan is ensured to be completed according to the reason.
Referring to fig. 5, the column represented by 2 will be indicated in red for severe overrun and the roof represented by 1 will be indicated in yellow for early warning. According to the progress simulation feedback result, the engineering construction management and control personnel analyze the associated task logic from the system, find out the subjective and objective reasons influencing the task lag, adjust the task plan and ensure that the task is finished finally.
S8, analyzing influence factors of progress plan
According to the found out planning task with the delay and the areas, components, associated logic association and the like on the BIM model, a big data analysis method is adopted to carry out systematic analysis on design factors, purchasing factors, logistics factors, scheduling factors, other subjective and objective factors and the like related to the planning task, and the true reason causing the delay of the planning task is found out. The plan is then revised to ensure that the final plan is completed as it is.
For example, an overdue for a planned task may be due to design errors, quality issues with procurement equipment, delays in logistics delivery, or other associated task delays, such as a delay in compliance with a piece of equipment, or may be due to a lack of compliance with the equipment infrastructure. Thereby starting to solve the problem from the source of the delay of the planning task.
A project construction progress plan management and control system based on a BIM model comprises:
the BIM coding standard establishing module is used for establishing a unified BIM coding standard; the method specifically comprises the following steps:
according to an engineering construction control method, a unified BIM coding standard is formulated, and relevant attribute information of each component is represented by numbers and letters; meanwhile, the attribute value corresponding to the component is retrieved from the database according to the coding information;
the BIM model building module is used for building a BIM model; the method specifically comprises the following steps:
building a three-dimensional model in a BIM modeling system according to professional requirements and BIM standard specifications, and integrating the built three-dimensional model into a complete BIM model according to factory and workshop requirements;
the engineering construction plan generation module is used for generating an engineering construction plan based on the BIM model; the method specifically comprises the following steps:
based on the BIM coding parameters, the attribute of the BIM model defines the attribution relation expression of the component in the planning task; generating an engineering construction plan task according to the plan task attribution relationship;
1) defining a set T of tasks T ═ { T1, T2, … }; t is ═ v, w, s, d >, v refers to the version, w refers to whether the change is made, s refers to the task state, and d refers to the programming time;
2) defining a task t level representation method;
representing a planned task hierarchical relation based on the attribute association set, and generating a planned task table;
the method for representing the association set is as follows:
{x=value|(S01,1),(S02,2),(S03,3),(Si,k))}(i,k>0);
wherein, X represents a specific category attribute, value represents a given attribute value, Si represents a task code, and k represents a task hierarchy;
the expression means: when x is value, Si∈S03∈S02∈S01(k>3);
Extracting coded data according to a BIM, and determining the hierarchical relation of the planned tasks by combining with a defined association set;
the plan display and compilation module is used for displaying and compiling a plan based on the BIM model; the method specifically comprises the following steps:
a light-weight method is adopted to display the BIM model and the planning task; the BIM model is browsed on a browser after being converted through lightweight, and the planned task level relation and the content are displayed on the browser end through a Web front-end development method; the BIM model and the planning task both contain the same task code (S)i) The BIM model is positioned to a specific component ID according to the task number, and the database is positioned to a specific planned task ID according to the task code, so that mapping between the BIM model and the planned task is realized;
adding corresponding logic association and making plan starting time and plan finishing time to the task at the browser end; the logic relation is dragged and labeled on the BIM, meanwhile, planning task connection lines are made on the Web plan, and based on the mapping relation between the BIM and the planning tasks, after data are stored, the logic relation between the BIM data and the planning tasks is mutually unified;
a BIM model change module;
the planning task needs to acquire the latest data according to the version number of the BIM model component;
a progress feedback module;
after plan editing is completed, acquiring actual progress in real time;
a plan progress simulation module;
performing progress simulation by combining the BIM model and the planned progress data, simulating engineering construction, civil engineering, installation and the like in a time period, finding out planned tasks which are delayed and possibly overdue by comparing planned time with actual progress, and marking different early warning colors on the BIM model from a component level;
the analysis module is used for analyzing the influence factors of the progress plan;
according to the deferred planning task and the region, the member and the associated logic correlation on the BIM model, a big data analysis method is adopted to carry out system analysis on the design factor, the procurement factor, the logistics factor and the scheduling factor related to the planning task, the true reason causing the deferred planning task is found out, and then the plan is corrected.
Please refer to fig. 6 and 7: a BIM model-based engineering construction plan progress control system is used for BIM coding, BIM model control, BIM plan generation, BIM plan feedback, BIM plan progress simulation and plan correction. The plan progress control system comprises a plurality of client terminals, an application server and a database. Each client computer is provided with a user operation interface for technicians to execute related operations of schedule management and control, and BIM model information, schedule feedback operation and the like are displayed. The application server comprises a plurality of function modules for managing and controlling the plan progress, and is used for processing BIM model data, performing algorithm analysis, issuing functions and the like. The database is used for storing BIM model data, progress plan data, logic business relation data and the like. The management and control system comprises:
the BIM code management 810 is used for managing and controlling the established BIM code and the attribute list of the BIM components.
And the BIM model management and control 820 is used for uploading the BIM model designed by the BIM modeling software to the application server, extracting the model attribute to the relational database and performing lightweight processing on the BIM model.
And the planning task generating module 830 is configured to automatically generate a planning task for the BIM model data, and can display a gantt chart effect at a browser end, and can map the planning task with the BIM model through task coding.
A planning task changing module 840 for updating the latest planning task.
And the progress feedback module 850 is used for collecting and calculating the actual progress information of the task and finally feeding back the data to the scheduled task table.
And the progress simulation module 860 simulates the contents of construction, civil engineering, installation and the like for the BIM according to a set time period according to the planned time and the actual progress feedback time, and finds out the overdue tasks. Areas, components, and planning tasks that are out of date are marked on the BIM model and Web plans.
And analyzing and correcting the overdue reasons 870, analyzing the influence plan factors according to the progress simulation data, and adjusting the associated task plan time.
An information data processing terminal for realizing the engineering construction progress plan management and control method based on the BIM model.
A computer-readable storage medium comprising instructions which, when executed on a computer, cause the computer to perform the above-described BIM model-based engineering construction progress plan management and control method.
In the above embodiments, the implementation may be wholly or partially realized by software, hardware, firmware, or any combination thereof. When used in whole or in part, can be implemented in a computer program product that includes one or more computer instructions. When loaded or executed on a computer, cause the flow or functions according to embodiments of the invention to occur, in whole or in part. The computer may be a general purpose computer, a special purpose computer, a network of computers, or other programmable device. The computer instructions may be stored in a computer readable storage medium or transmitted from one computer readable storage medium to another, for example, the computer instructions may be transmitted from one website site, computer, server, or data center to another website site, computer, server, or data center via wire (e.g., coaxial cable, fiber optic, Digital Subscriber Line (DSL), or wireless (e.g., infrared, wireless, microwave, etc.)). The computer-readable storage medium can be any available medium that can be accessed by a computer or a data storage device, such as a server, a data center, etc., that includes one or more of the available media. The usable medium may be a magnetic medium (e.g., floppy Disk, hard Disk, magnetic tape), an optical medium (e.g., DVD), or a semiconductor medium (e.g., Solid State Disk (SSD)), among others.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, improvement and the like made within the spirit and principle of the present invention are within the scope of the claims of the present invention.

Claims (6)

1. The utility model provides an engineering construction progress plan management and control system based on BIM model which characterized in that includes at least:
the BIM coding standard establishing module is used for establishing a unified BIM coding standard; the method specifically comprises the following steps:
according to an engineering construction control method, a unified BIM coding standard is formulated, and relevant attribute information of each component is represented by numbers and letters; meanwhile, the attribute value corresponding to the component is retrieved from the database according to the coding information;
the BIM model building module is used for building a BIM model; the method specifically comprises the following steps:
building a three-dimensional model in a BIM modeling system according to professional requirements and BIM standard specifications, and integrating the built three-dimensional model into a complete BIM model according to factory and workshop requirements;
the engineering construction plan generation module is used for generating an engineering construction plan based on the BIM model; the method specifically comprises the following steps:
based on the BIM coding parameters, the attribute of the BIM model defines the attribution relation expression of the component in the planning task; generating an engineering construction plan task according to the plan task attribution relationship;
1) defining a set T of tasks T ═ { T1, T2, … }; t ═ v, w, s, d >, v denotes version, w denotes whether or not change, s denotes task state, d denotes compilation time;
2) defining a task t level representation method;
representing a planned task hierarchical relation based on the attribute association set, and generating a planned task table;
the method for representing the association set is as follows:
{x=value|(S01,1),(S02,2),(S03,3),(Si,k))}(i,k>0);
wherein, X represents a specific category attribute, value represents a given attribute value, Si represents a task code, and k represents a task hierarchy;
the expression means: when x is value, Si∈S03∈S02∈S01(k>3);
Extracting coded data according to a BIM, and determining the hierarchical relation of the planned tasks by combining with a defined association set;
the plan display and compilation module is used for displaying and compiling a plan based on the BIM model; the method specifically comprises the following steps:
a light-weight method is adopted to display the BIM model and the planning task; the BIM model is browsed on a browser after being converted through lightweight, and the planned task level relation and the content are displayed on the browser end through a Web front-end development method; the BIM model and the planning task both contain the same task code (S)i) The BIM model is positioned to a specific component ID according to the task number, and the database is positioned to a specific planned task ID according to the task code, so that mapping between the BIM model and the planned task is realized;
adding corresponding logic association and making plan starting time and plan finishing time to the task at the browser end; the logic relation is dragged and labeled on the BIM, meanwhile, planning task connection lines are made on the Web plan, and based on the mapping relation between the BIM and the planning tasks, after data are stored, the logic relation between the BIM data and the planning tasks is mutually unified;
a BIM model change module;
the planning task needs to acquire the latest data according to the version number of the BIM model component;
a progress feedback module;
after plan editing is completed, acquiring actual progress in real time;
a plan progress simulation module;
performing progress simulation by combining the BIM model and the planned progress data, simulating engineering construction, civil engineering, installation and the like in a time period, finding out planned tasks which are delayed and possibly overdue by comparing planned time with actual progress, and marking different early warning colors on the BIM model from a component level;
the analysis module is used for analyzing the influence factors of the progress plan;
according to the deferred planning task and the region, the member and the associated logic correlation on the BIM model, a big data analysis method is adopted to carry out system analysis on the design factor, the procurement factor, the logistics factor and the scheduling factor related to the planning task, the true reason causing the deferred planning task is found out, and then the plan is corrected.
2. A BIM model-based engineering construction progress plan management and control method is characterized by comprising the following steps:
s1, establishing a unified BIM coding standard; the method specifically comprises the following steps:
according to an engineering construction control method, a unified BIM coding standard is formulated, and relevant attribute information of each component is represented by numbers and letters; meanwhile, the attribute value corresponding to the component is retrieved from the database according to the coding information;
s2, building a BIM model; the method specifically comprises the following steps:
building a three-dimensional model in a BIM modeling system according to professional requirements and BIM standard specifications, and integrating the built three-dimensional model into a complete BIM model according to factory and workshop requirements;
s3, generating an engineering construction plan based on the BIM model; the method specifically comprises the following steps:
based on the BIM coding parameters, the attribute of the BIM model defines the attribution relation expression of the component in the planning task; generating an engineering construction plan task according to the plan task attribution relationship;
1) defining a set T of tasks T ═ { T1, T2, … }; t is ═ v, w, s, d >, v refers to the version, w refers to whether the change is made, s refers to the task state, and d refers to the programming time;
2) defining a task t level representation method;
representing a planned task hierarchical relation based on the attribute association set, and generating a planned task table;
the method for representing the association set is as follows:
{x=value|(S01,1),(S02,2),(S03,3),(Si,k))}(i,k>0);
wherein, X represents a specific category attribute, value represents a given attribute value, Si represents a task code, and k represents a task hierarchy;
the expression means: when x is value, Si∈S03∈S02∈S01(k>3);
Extracting coded data according to a BIM, and determining the hierarchical relation of the planned tasks by combining with a defined association set;
s4, plan display and compilation based on the BIM model;
a light-weight method is adopted to display the BIM model and the planning task; the BIM model is browsed on a browser after being converted through lightweight, and the planned task level relation and the content are displayed on the browser end through a Web front-end development method; the BIM model and the planning task both contain the same task code (S)i) The BIM model is positioned to a specific component ID according to the task number, and the database is positioned to a specific planned task ID according to the task code, so that mapping between the BIM model and the planned task is realized;
adding corresponding logic association and making plan starting time and plan finishing time to the task at the browser end; the logic relation is dragged and labeled on the BIM, meanwhile, planning task connection lines are made on the Web plan, and based on the mapping relation between the BIM and the planning tasks, after data are stored, the logic relation between the BIM data and the planning tasks is mutually unified;
s5, changing a BIM model;
the planning task needs to acquire the latest data according to the version number of the BIM model component;
s6, progress feedback;
after plan editing is completed, acquiring actual progress in real time;
s7, simulating a planned schedule;
performing progress simulation by combining the BIM model and the planned progress data, simulating engineering construction, civil engineering, installation and the like in a time period, finding out planned tasks which are delayed and possibly overdue by comparing planned time with actual progress, and marking different early warning colors on the BIM model from a component level;
s8, analyzing the influence factors of the schedule plan;
according to the deferred planning task and the region, the member and the associated logic correlation on the BIM model, a big data analysis method is adopted to carry out system analysis on the design factor, the procurement factor, the logistics factor and the scheduling factor related to the planning task, the true reason causing the deferred planning task is found out, and then the plan is corrected.
3. The BIM-model-based engineering construction progress plan management and control method according to claim 2, wherein the BIM model modification specifically comprises:
the BIM model change does not affect the existing planning task level;
if the BIM model component is added, directly adding the BIM model component into a planned task table according to the component coding attribute, and marking a change state;
if the BIM model component attribute is modified, storing the latest version number data in the database, and acquiring the component attribute value of the latest version by the scheduling task table;
the BIM model changes the task level of the influence plan;
if the BIM model component is deleted, the original hierarchy and task logic are changed, the planned task is adjusted according to the corresponding approval process, and the change state is marked in the planned task;
4. the BIM model-based engineering construction progress plan management and control method according to claim 2, wherein the progress feedback comprises:
acquiring an actual progress model of an engineering site by adopting a BIM technical means, comparing the actual progress model with a planned BIM model, calculating the actual completion percentage, and feeding the actual completion percentage back to a planned task table through an interface;
adopting computer deep learning, according to the feedback picture of each intelligent camera on site, calculating the actual completion progress according to a preset progress threshold value, and feeding back the actual completion progress to the scheduled task table through an interface;
and feeding back by adopting a mobile APP terminal, generating a two-dimensional code or a record for each planned task, confirming that the task is completed by constructors or inspection personnel on the APP terminal, and feeding the completion time back to the planned task database.
5. An information data processing terminal for implementing the BIM model-based project construction progress plan management and control method of any one of claims 2 to 4.
6. A computer-readable storage medium comprising instructions that, when executed on a computer, cause the computer to perform the BIM model-based engineering construction progress plan management and control method according to any one of claims 2 to 4.
CN202010646445.2A 2020-07-07 2020-07-07 Engineering construction progress plan management and control system and method based on BIM model Active CN111754138B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010646445.2A CN111754138B (en) 2020-07-07 2020-07-07 Engineering construction progress plan management and control system and method based on BIM model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010646445.2A CN111754138B (en) 2020-07-07 2020-07-07 Engineering construction progress plan management and control system and method based on BIM model

Publications (2)

Publication Number Publication Date
CN111754138A true CN111754138A (en) 2020-10-09
CN111754138B CN111754138B (en) 2021-07-23

Family

ID=72679874

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010646445.2A Active CN111754138B (en) 2020-07-07 2020-07-07 Engineering construction progress plan management and control system and method based on BIM model

Country Status (1)

Country Link
CN (1) CN111754138B (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112184874A (en) * 2020-10-20 2021-01-05 国网湖南省电力有限公司 High-performance graphic marking, progress simulating and navigating method for lightweight three-dimensional model
CN112446937A (en) * 2020-11-10 2021-03-05 上海宝冶集团有限公司 Project progress three-dimensional visualization method based on BIM technology
CN112486613A (en) * 2020-11-27 2021-03-12 东南大学 Engineering project Web end construction progress management method and device and readable storage medium
CN112507430A (en) * 2020-12-02 2021-03-16 国网江西省电力有限公司建设分公司 Visual fusion method of BIM (building information modeling) model and engineering project
CN112818459A (en) * 2021-03-12 2021-05-18 黄河勘测规划设计研究院有限公司 BIM and Gantt chart-based visual progress management method for engineering construction period
CN112819427A (en) * 2021-01-28 2021-05-18 比姆泰客信息科技(上海)有限公司 Full life cycle intelligent interactive plan management system based on BIM technology
CN113360583A (en) * 2021-06-15 2021-09-07 东南大学 Construction progress visualization method based on BIM model and monitoring image comparison
CN114066424A (en) * 2021-11-24 2022-02-18 华东交通大学 Municipal bridge engineering cooperative management platform based on BIM and method thereof
CN115293749A (en) * 2022-10-08 2022-11-04 深圳市地铁集团有限公司 Method, system and equipment for deriving engineering quantity list based on BIM
CN115545681A (en) * 2022-11-30 2022-12-30 北京鸿游科技有限公司 Intelligent process analysis and supervision method and system for engineering project management
CN116307537A (en) * 2023-02-24 2023-06-23 河南创优科学技术研究院有限公司 Construction scheduling method and system based on building engineering model

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106803150A (en) * 2017-01-20 2017-06-06 上海市地下空间设计研究总院有限公司 Municipal Engineering Construction progress msg management method and system based on BIM
CN108920770A (en) * 2018-06-08 2018-11-30 上海大学 Based on the BIM component autocoding of Revit software and the method that is associated with BIM model
CN109409840A (en) * 2018-10-31 2019-03-01 广西路桥工程集团有限公司 A kind of Highway Project management system and method combined based on BIM with WBS
US20190228115A1 (en) * 2018-01-19 2019-07-25 Autodesk, Inc. Building information design synthesis (bids)
CN110880097A (en) * 2019-11-21 2020-03-13 中国电力企业联合会电力建设技术经济咨询中心 Project progress simulation display method and device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106803150A (en) * 2017-01-20 2017-06-06 上海市地下空间设计研究总院有限公司 Municipal Engineering Construction progress msg management method and system based on BIM
US20190228115A1 (en) * 2018-01-19 2019-07-25 Autodesk, Inc. Building information design synthesis (bids)
CN108920770A (en) * 2018-06-08 2018-11-30 上海大学 Based on the BIM component autocoding of Revit software and the method that is associated with BIM model
CN109409840A (en) * 2018-10-31 2019-03-01 广西路桥工程集团有限公司 A kind of Highway Project management system and method combined based on BIM with WBS
CN110880097A (en) * 2019-11-21 2020-03-13 中国电力企业联合会电力建设技术经济咨询中心 Project progress simulation display method and device

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112184874A (en) * 2020-10-20 2021-01-05 国网湖南省电力有限公司 High-performance graphic marking, progress simulating and navigating method for lightweight three-dimensional model
CN112446937A (en) * 2020-11-10 2021-03-05 上海宝冶集团有限公司 Project progress three-dimensional visualization method based on BIM technology
CN112446937B (en) * 2020-11-10 2023-07-14 上海宝冶集团有限公司 Project progress three-dimensional visualization method based on BIM technology
CN112486613A (en) * 2020-11-27 2021-03-12 东南大学 Engineering project Web end construction progress management method and device and readable storage medium
CN112507430B (en) * 2020-12-02 2023-04-28 国网江西省电力有限公司建设分公司 Visual fusion method for BIM model and engineering project
CN112507430A (en) * 2020-12-02 2021-03-16 国网江西省电力有限公司建设分公司 Visual fusion method of BIM (building information modeling) model and engineering project
CN112819427A (en) * 2021-01-28 2021-05-18 比姆泰客信息科技(上海)有限公司 Full life cycle intelligent interactive plan management system based on BIM technology
CN112818459A (en) * 2021-03-12 2021-05-18 黄河勘测规划设计研究院有限公司 BIM and Gantt chart-based visual progress management method for engineering construction period
CN113360583A (en) * 2021-06-15 2021-09-07 东南大学 Construction progress visualization method based on BIM model and monitoring image comparison
CN113360583B (en) * 2021-06-15 2024-05-14 东南大学 Construction progress visualization method based on BIM model and monitoring image comparison
CN114066424B (en) * 2021-11-24 2022-07-26 华东交通大学 Municipal bridge engineering cooperative management platform system based on BIM and method thereof
CN114066424A (en) * 2021-11-24 2022-02-18 华东交通大学 Municipal bridge engineering cooperative management platform based on BIM and method thereof
CN115293749A (en) * 2022-10-08 2022-11-04 深圳市地铁集团有限公司 Method, system and equipment for deriving engineering quantity list based on BIM
CN115293749B (en) * 2022-10-08 2022-12-27 深圳市地铁集团有限公司 Method, system and equipment for deriving engineering quantity list based on BIM
CN115545681A (en) * 2022-11-30 2022-12-30 北京鸿游科技有限公司 Intelligent process analysis and supervision method and system for engineering project management
CN115545681B (en) * 2022-11-30 2024-03-15 北京鸿游科技有限公司 Intelligent process analysis and supervision method and system for engineering project management
CN116307537A (en) * 2023-02-24 2023-06-23 河南创优科学技术研究院有限公司 Construction scheduling method and system based on building engineering model

Also Published As

Publication number Publication date
CN111754138B (en) 2021-07-23

Similar Documents

Publication Publication Date Title
CN111754138B (en) Engineering construction progress plan management and control system and method based on BIM model
Stoyanova Good practices and recommendations for success in construction digitalization
CN109583762B (en) System for production process modeling and product data tracking
US7899756B2 (en) Critical parameter/requirements management process and environment
CN109559069B (en) Production management method and device based on assembly type building platform and terminal equipment
US20150019178A1 (en) System And Method For Managing Changes In Building Information Models
US20080208661A1 (en) Method and system of using anrtifacts to identify elements of a component business model
Parchami Jalal et al. A BIM-based construction claim management model for early identification and visualization of claims
US10642838B2 (en) Real-time or event-based analysis of process data
US20220083941A1 (en) Systems and methods for generating construction models for construction projects
Fernandes Advantages and disadvantages of BIM platforms on construction site
CN115427990A (en) System for mapping models, costs and schedules of large-scale infrastructure projects
CN111651818A (en) BIM model rapid change method
Brinda et al. Developments of facility management using building information modelling
Roberti et al. Increasing Autodesk Revit Productivity for BIM Projects: A practical guide to using Revit workflows to improve productivity and efficiency in BIM projects
KR20220046380A (en) System for classifying and managing contents asset
CN112288150A (en) Boats and ships industry pipe fitting processing management and control integrated system
NOVIKOV et al. Improving the enterprise resource planning system based on digital modules of the industry 4.0 concept
WO2020056671A1 (en) Data growth method and device for fabricated building construction platform
US20140149186A1 (en) Method and system of using artifacts to identify elements of a component business model
Melzer et al. Simulation of database interactions for early validation of digitized enterprise processes
KR20220046378A (en) System, server and method for providing cooperation solution among multiple workers
Barlas et al. Towards automated simulation input data
Shi et al. Implementation method of construction schedule management for metro engineering based on BIM modeling
CN114897493A (en) Large-screen visual intelligent management system for digital engineering

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant