CN116307537A - Construction scheduling method and system based on building engineering model - Google Patents

Construction scheduling method and system based on building engineering model Download PDF

Info

Publication number
CN116307537A
CN116307537A CN202310160613.0A CN202310160613A CN116307537A CN 116307537 A CN116307537 A CN 116307537A CN 202310160613 A CN202310160613 A CN 202310160613A CN 116307537 A CN116307537 A CN 116307537A
Authority
CN
China
Prior art keywords
construction
prefabricated
model
estimated
building structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310160613.0A
Other languages
Chinese (zh)
Inventor
闫磊超
白露
高姗
师松钢
张志霞
韩新欣
王高杰
王鹏
刘毅
张建刚
王岩
米少伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Chuangyou Science And Technology Research Institute Co ltd
Original Assignee
Henan Chuangyou Science And Technology Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Chuangyou Science And Technology Research Institute Co ltd filed Critical Henan Chuangyou Science And Technology Research Institute Co ltd
Priority to CN202310160613.0A priority Critical patent/CN116307537A/en
Publication of CN116307537A publication Critical patent/CN116307537A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a method and a system for carrying out construction scheduling based on a building engineering model, wherein the building engineering model is constructed, the building engineering model is divided into building structure sub-models according to the structural composition and the construction sequence of the building engineering, the building structure sub-models are divided into independent structural members, the material names, the material numbers, the material amount, the construction period and the labor cost of each structural member are calculated to obtain relatively accurate various materials, the material numbers, the material amount and the total labor cost of the whole building engineering, and when the construction scheduling is carried out, the period required by the scheduling is set through the estimated construction period or the prefabricated construction period of the complete structural member under each working procedure, so that the construction plan of the current period and the construction plan of the next construction period are called according to the period, and the purchasing of the various materials, the material amount and the distribution according to the construction period are determined by optimizing and adjusting in combination with the construction completion report corresponding to the construction schedule.

Description

Construction scheduling method and system based on building engineering model
Technical Field
The invention relates to the technical field of building construction scheduling, in particular to a method and a system for performing construction scheduling based on a building engineering model.
Background
At present, the building construction scheduling is manually managed, various materials required by engineering construction are purchased in advance according to the construction progress, but in practice, temporary change of a demand plan, temporary material allocation, urgent material standing and the like, and urgent time are often difficult to achieve reasonable and economic purchasing according to a program. The material is not strictly distributed according to the material consumption quota, and materials are only timely supplied according to engineering requirements in construction; the use process of the materials is difficult to monitor, and serious waste phenomenon exists in the actual use of the materials: the method is lack of effective and timely waste material recovery, only the last waste material recovery work is performed after the construction period is completed, and the loss of leftover materials is serious. Summarizing, mainly the following problems are included:
the material is collected by people, but the capability and quality of material management staff are not high. In the building industry of China, the phenomenon that recruitment of project management talents is not paid attention to is common, most building enterprises allocate common staff to monitor building materials at will from other departments in the unit in order to save cost, and special professional talents with management capability are not used for managing the building materials or management is carried out by using daily management means. These management staff, whether they have a gap from the requirements of modern engineering material management in terms of management ability or professional literacy, are mainly represented by: low professional knowledge level, insufficient practical experience, insufficient self-restraint and the like. Even if some personnel have high management capability and rich actual combat experience, the lack of professional management knowledge is not in line with the requirements of engineering building material management. The management mode is easy to cause the phenomenon of disordered enterprise management, is unfavorable for the cost control of building materials, is unfavorable for the scientific management of the building materials, and greatly influences the smooth development of building engineering.
The purchasing procedure of the building engineering materials is disordered: in practical engineering projects, effectively controlling building material funds has a direct impact on the overall cost of construction engineering. At present, most building enterprises lack cost consciousness in the process of purchasing building materials, blind purchasing is not provided with detailed purchasing schemes, and detailed budget is not provided for purchasing cost. Before purchasing, the market is not known, and the prices of building materials on the market are not mastered in detail, so that the prices of the materials are maliciously increased by partial suppliers, and the prices are important factors for increasing purchasing cost. Therefore, before purchasing building materials, the market price is thoroughly mastered, a detailed purchasing plan is formulated, so that purchasing cost funds can be effectively controlled, the investment of construction engineering cost and total cost is more effectively reduced, and scientific management of engineering construction enterprises is realized.
Disclosure of Invention
Accordingly, a primary object of the present invention is to provide a method and system for performing construction scheduling based on a construction model.
The technical scheme adopted by the invention is as follows:
the invention provides a construction scheduling method based on a building engineering model, which comprises the following steps:
1) Pre-constructing a plurality of prefabricated member models used for a building structure, manufacturing a standard drawing, a standard process and standard process parameters corresponding to each prefabricated member model, and acquiring a prefabricated material name, a prefabricated material number, a prefabricated material amount, a prefabricated construction period and a prefabricated construction cost corresponding to each prefabricated member model based on the standard drawing, the standard process and the standard process parameters; storing each prefabricated part model and the prefabricated material names, prefabricated material numbers, prefabricated material amounts, prefabricated construction periods and prefabricated construction costs corresponding to the prefabricated part models in a standby library;
2) Building a building engineering integral model, dividing the building engineering integral model into a plurality of building structure sub-models according to building structures, and recording the position and construction sequence of each building structure sub-model;
3) Loading the corresponding building structure sub-models into an analysis module according to the construction sequence and the position, loading the construction process, the construction process parameters and the construction drawing corresponding to each building structure sub-model, determining all structural members constituting the building structure sub-model contained in the building structure sub-model based on the construction process, the construction process parameters and the construction drawing, marking all structural members according to the building structure and the construction sequence, and obtaining the serial number of each structural member according to the construction procedure; and the serial numbers used by all structural members under the same building structure submodel have the same identification characteristic;
4) Loading structural members corresponding to the serial numbers into an accounting module, correspondingly matching structural member models corresponding to the structural members in a standby library according to the loading sequence, if the standby library is provided with a prefabricated member model corresponding to the matching, matching prefabricated material names, prefabricated material numbers, prefabricated material amounts, prefabricated construction periods and prefabricated cost corresponding to the prefabricated member models with the structural members, and if the standby library is not provided with the corresponding prefabricated member models, turning to the step 5);
5) Loading a structural member which is not matched with the prefabricated member model into an evaluation module, and correspondingly calling out a construction sub-drawing, a construction sub-process and construction sub-process parameters corresponding to the construction sub-process corresponding to the structural member in the evaluation module, so as to determine a corresponding estimated material name, an estimated material number, an estimated material amount, an estimated construction period and an estimated labor cost when the structural member is built;
6) Writing the name, number, amount, construction period and construction cost of the prefabricated material corresponding to the structural member into a control library according to the loading serial number and the identification characteristic; or, writing the estimated material name, the estimated material number, the estimated material amount, the estimated construction period and the estimated construction cost corresponding to the structural part into a control library;
7) When construction is carried out, the building structure submodel is loaded according to the sequence, and the corresponding structural component of the loaded building structure submodel and the corresponding prefabricated material name, prefabricated material number, prefabricated material amount, prefabricated construction period and prefabricated construction cost of the structural component are in the control library, or the corresponding estimated material name, estimated material number, estimated material amount, estimated construction period and estimated construction cost of the loaded structural component are adopted, so that the dispatching of the building construction is realized.
In step 4), for all the structural members under the same building structure sub-model, if at least more than one of the structural members has the same corresponding prefabricated member model, the corresponding prefabricated construction period is reduced according to the set proportion.
In the step 7), a construction scheduling manager is arranged, and is used for loading corresponding building structure sub-models according to construction sequences and positions, and loading the corresponding structural members of the building structure sub-models and the corresponding prefabricated material names, the prefabricated material numbers, the prefabricated material amounts, the prefabricated construction periods and the prefabricated construction costs of the structural members, or loading the corresponding estimated material names, the estimated material numbers, the estimated material amounts, the estimated construction periods and the estimated construction costs of the structural members;
meanwhile, the construction completion report corresponding to the construction progress is formed into a corresponding configuration file which can be read by a construction scheduling manager, and after the construction scheduling manager loads the configuration file to read the construction progress, the construction scheduling scheme corresponding to the next period is correspondingly scheduled.
Further, the construction scheduling scheme refers to a scheduling plan of material names, material numbers, material amounts, construction periods and labor costs corresponding to various structural members in a set construction period.
The invention also provides a system for performing construction scheduling based on the building engineering model, which comprises:
the prefabricated part model construction module is used for constructing a plurality of prefabricated part models used for the building structure in advance, manufacturing standard drawings, standard processes and standard process parameters corresponding to each prefabricated part model, and acquiring prefabricated material names, prefabricated material numbers, prefabricated material amounts, prefabricated construction periods and prefabricated construction costs corresponding to each prefabricated part model based on the standard drawings, the standard processes and the standard process parameters;
the standby library is connected with the prefabricated part model building module and used for storing each prefabricated part model and the prefabricated material name, the prefabricated material number, the prefabricated material amount, the prefabricated construction period and the prefabricated construction cost corresponding to the prefabricated part model in the standby library;
the construction engineering integral model construction module is used for constructing a construction engineering integral model according to an electronic drawing of construction engineering, a construction process configuration file and configuration parameters of each structural member in the drawing;
the segmentation module is used for determining the structure constitution corresponding to the building engineering integral model according to the electronic drawing of the building engineering construction, the construction process configuration file and the configuration parameters of each structural member in the drawing, so that the building engineering integral model is divided into a plurality of building structure sub-models, and the position and the construction sequence of each building structure sub-model are recorded;
the analysis module is used for loading the corresponding building structure sub-models according to the construction sequence and the position, correspondingly loading the construction process, the construction process parameters and the construction drawing corresponding to each building structure sub-model, and determining all structural members which form the building structure sub-models and are contained in the building structure sub-models based on the construction process, the construction process parameters and the construction drawing;
the accounting module is connected with the analysis module and comprises a matching unit and an accounting writing unit, wherein the matching unit is used for loading the structural member corresponding to the serial number, comparing the loaded loading construction with the prefabricated member models in the standby library to obtain whether the corresponding prefabricated member models exist in the standby library or not, and if yes, the accounting writing unit writes the prefabricated material names, the prefabricated material numbers, the prefabricated material quantity, the prefabricated construction period and the prefabricated construction cost corresponding to the prefabricated member models into the structural member configuration file;
the evaluation module is connected with the analysis module and the calculation module and is used for loading the structural member which is not matched with the prefabricated member model, and synchronously analyzing the construction sub-drawing, the construction sub-process and the construction sub-process parameters corresponding to the construction sub-process corresponding to the structural member in the module, so as to determine the corresponding estimated material name, the estimated material number, the estimated material amount, the estimated construction period and the estimated work cost of the structural member during construction;
the construction scheduling manager is used for loading the corresponding building structure sub-model according to the construction sequence and the position, and loading the corresponding structural member of the building structure sub-model and the corresponding prefabricated material name, prefabricated material number, prefabricated material amount, prefabricated construction period and prefabricated construction cost of the structural member, or loading the corresponding estimated material name, estimated material number, estimated material amount, estimated construction period and estimated construction cost of the structural member; meanwhile, the construction completion report corresponding to the construction progress is formed into a corresponding configuration file which can be read by a construction scheduling manager, and after the construction scheduling manager loads the configuration file to read the construction progress, the construction scheduling scheme corresponding to the next period is correspondingly scheduled.
Further, the analysis module further comprises:
the marking unit is used for marking all the structural members according to the building structure and the construction sequence, and acquiring the serial number of each structural member according to the construction procedure;
and the characteristic editing unit is used for writing the serial numbers used by all structural members under the same building structure submodel into the same identification characteristic.
Further, the construction scheduling manager is used for setting a period required by scheduling through the estimated construction period or the prefabricated construction period of the complete structural part in each working procedure.
The invention has the following beneficial effects:
according to the method, the whole building engineering model is built, then the whole building engineering model is divided into the sub building structure models according to the structural composition and the construction sequence of the building engineering, then the sub building structure models are divided into independent structural members, various materials, material numbers, total amount of materials and total labor cost of the whole building engineering can be obtained through accounting the material name, the material number, the construction period and the labor cost of each structural member, when construction scheduling is carried out, the period required by scheduling is set through the estimated construction period or the prefabricated construction period of the complete structural member under each working procedure, so that the construction plan of the current period and the construction plan of the next construction period are called out according to the period, and optimization adjustment is carried out by combining a construction completion report corresponding to the construction progress, so that purchasing of various materials, material numbers and material amounts is determined, and distribution is carried out according to the construction period scheduling.
Therefore, the method and the device can assist the manager to make an accurate material demand plan and a deployment plan, and can also be used by people according to the construction manual work of deployment corresponding to the structural member, so that the material deployment is reasonable.
The construction planning system and the construction planning method can simulate corresponding construction plans for arranging material purchase and temporary storage, and help management staff to make construction site planning and material management work.
Drawings
The following drawings are illustrative of the invention and are not intended to limit the scope of the invention, in which:
FIG. 1 is a schematic flow chart of the method of the present invention;
fig. 2 is a schematic diagram of the frame principle of the system in the present invention.
Detailed Description
The present invention will be further described in detail with reference to the following specific examples, which are given by way of illustration, in order to make the objects, technical solutions, design methods and advantages of the present invention more apparent. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the scope of the invention.
Example 1
According to the method, the whole building engineering model is built, then the whole building engineering model is divided into the sub building structure models according to the structural composition and the construction sequence of the building engineering, then the sub building structure models are divided into independent structural members, various materials, material numbers, total amount of materials and total labor cost of the whole building engineering can be obtained through accounting the material name, the material number, the construction period and the labor cost of each structural member, when construction scheduling is carried out, the period required by scheduling is set through the estimated construction period or the prefabricated construction period of the complete structural member under each working procedure, so that the construction plan of the current period and the construction plan of the next construction period are called out according to the period, and optimization adjustment is carried out by combining a construction completion report corresponding to the construction progress, so that purchasing of various materials, material numbers and material amounts is determined, and distribution is carried out according to the construction period scheduling. According to the foregoing, referring to fig. 1, the present application provides a method for performing construction scheduling based on a building engineering model, including:
1) Pre-constructing a plurality of prefabricated member models used for a building structure, manufacturing a standard drawing, a standard process and standard process parameters corresponding to each prefabricated member model, and acquiring a prefabricated material name, a prefabricated material number, a prefabricated material amount, a prefabricated construction period and a prefabricated construction cost corresponding to each prefabricated member model based on the standard drawing, the standard process and the standard process parameters; storing each prefabricated part model and the prefabricated material names, prefabricated material numbers, prefabricated material amounts, prefabricated construction periods and prefabricated construction costs corresponding to the prefabricated part models in a standby library;
2) Building a building engineering integral model, dividing the building engineering integral model into a plurality of building structure sub-models according to building structures, and recording the position and construction sequence of each building structure sub-model;
3) Loading the corresponding building structure sub-models into an analysis module according to the construction sequence and the position, loading the construction process, the construction process parameters and the construction drawing corresponding to each building structure sub-model, determining all structural members constituting the building structure sub-model contained in the building structure sub-model based on the construction process, the construction process parameters and the construction drawing, marking all structural members according to the building structure and the construction sequence, and obtaining the serial number of each structural member according to the construction procedure; and the serial numbers used by all structural members under the same building structure submodel have the same identification characteristic;
4) Loading structural members corresponding to the serial numbers into an accounting module, correspondingly matching structural member models corresponding to the structural members in a standby library according to the loading sequence, if the standby library is provided with a prefabricated member model corresponding to the matching, matching prefabricated material names, prefabricated material numbers, prefabricated material amounts, prefabricated construction periods and prefabricated cost corresponding to the prefabricated member models with the structural members, and if the standby library is not provided with the corresponding prefabricated member models, turning to the step 5);
5) Loading a structural member which is not matched with the prefabricated member model into an evaluation module, and correspondingly calling out a construction sub-drawing, a construction sub-process and construction sub-process parameters corresponding to the construction sub-process corresponding to the structural member in the evaluation module, so as to determine a corresponding estimated material name, an estimated material number, an estimated material amount, an estimated construction period and an estimated labor cost when the structural member is built;
6) Writing the name, number, amount, construction period and construction cost of the prefabricated material corresponding to the structural member into a control library according to the loading serial number and the identification characteristic; or, writing the estimated material name, the estimated material number, the estimated material amount, the estimated construction period and the estimated construction cost corresponding to the structural part into a control library;
7) When construction is carried out, the building structure submodel is loaded according to the sequence, and the corresponding structural component of the loaded building structure submodel and the corresponding prefabricated material name, prefabricated material number, prefabricated material amount, prefabricated construction period and prefabricated construction cost of the structural component are in the control library, or the corresponding estimated material name, estimated material number, estimated material amount, estimated construction period and estimated construction cost of the loaded structural component are adopted, so that the dispatching of the building construction is realized.
In some embodiments, the engineering construction includes a large number of prefabricated members, which may be purchased from outside or prepared manually, and in general, the prefabricated members used in the engineering construction have detailed standards, so that the prefabricated member name, the prefabricated member number, the prefabricated member amount, the prefabricated period and the prefabricated cost corresponding to each prefabricated member model can be obtained according to the standard drawing, the standard process and the standard process parameters corresponding to the prefabricated member; of course, in the building engineering, the same prefabricated member is used in a large amount, so that if at least more than one of the structural members has the same corresponding prefabricated member model for all structural members under the same building structure sub-model, the corresponding prefabricated construction period is reduced according to the set proportion. Wherein the more is used, the more is the construction period reduced.
In some embodiments, the construction of the structural member in situ is further included in the engineering building construction, for example, the bridge building, the pier column is required to be cast in situ, the bridge body can be prefabricated in advance, and for some structural members required to be cast in situ, the estimated material name, the estimated material number, the estimated material amount, the estimated construction period and the estimated labor cost corresponding to the structural member in construction can be determined according to the corresponding construction sub-drawing, the construction sub-process and the construction sub-process parameters corresponding to the construction sub-process.
In some embodiments, the Autodesk Revit is modeling software supporting the existing technology, and can provide needed designs, building drawings and component detail tables for building projects, for example, the Autodesk Revit supports fusion with BIM software, and a building engineering integral model can be built through the BIM software, meanwhile, engineering quantity information can be imported from the BIM software to the cost software through connection between the BIM software and the cost software through an API socket, and the cost software provides a bill of materials required for construction according to rating rules.
In some embodiments, the construction scheduling manager can correlate the construction item with the construction progress plan, so that construction work can be performed in each period in the future, engineering quantity and the required quantity of each material can be counted, material guidance limit materials required by each construction task can be accurately provided, and once the engineering construction process is changed, the material use plan can be automatically updated in real time, so that material management cost increase and material use waste caused by material purchase in advance and excessive quantity are avoided.
In the prior art, BIM-4D simulation technology can be effectively combined with BIM software, BIM-4D simulation technology can dynamically display the construction process of a building model in the whole construction period, so that a manager is helped to conduct site layout planning, and meanwhile, a storage module is configured for temporary storage of building materials and equipment on a construction site, which means that material management based on BIM technology can store purchased materials in a construction free area almost temporarily, and secondary transportation cost and the like generated in a traditional material warehouse storage mode are reduced. And assisting a construction site manager to perform coordinated management and dynamic cost analysis.
Therefore, the construction scheduling manager is accessed into BIM software, and is used for loading the corresponding building structure sub-model according to the construction sequence and the position, and loading the corresponding structural member of the building structure sub-model and the corresponding prefabricated material name, the prefabricated material number, the prefabricated material amount, the prefabricated construction period and the prefabricated construction cost of the structural member, or loading the corresponding estimated material name, the estimated material number, the estimated material amount, the estimated construction period and the estimated construction cost of the structural member;
meanwhile, the construction completion report corresponding to the construction progress is formed into a corresponding configuration file which can be read by a construction scheduling manager, and after the construction scheduling manager loads the configuration file to read the construction progress, the construction scheduling scheme corresponding to the next period is correspondingly scheduled.
Further, the construction scheduling scheme refers to a scheduling plan of material names, material numbers, material amounts, construction periods and labor costs corresponding to various structural members in a set construction period.
Example 2
The invention also provides a system for performing construction scheduling based on the building engineering model, which comprises:
the prefabricated part model construction module is used for constructing a plurality of prefabricated part models used for the building structure in advance, manufacturing standard drawings, standard processes and standard process parameters corresponding to each prefabricated part model, and acquiring prefabricated material names, prefabricated material numbers, prefabricated material amounts, prefabricated construction periods and prefabricated construction costs corresponding to each prefabricated part model based on the standard drawings, the standard processes and the standard process parameters;
the standby library is connected with the prefabricated part model building module and used for storing each prefabricated part model and the prefabricated material name, the prefabricated material number, the prefabricated material amount, the prefabricated construction period and the prefabricated construction cost corresponding to the prefabricated part model in the standby library;
the construction engineering integral model construction module is used for constructing a construction engineering integral model according to an electronic drawing of construction engineering, a construction process configuration file and configuration parameters of each structural member in the drawing;
the segmentation module is used for determining the structure constitution corresponding to the building engineering integral model according to the electronic drawing of the building engineering construction, the construction process configuration file and the configuration parameters of each structural member in the drawing, so that the building engineering integral model is divided into a plurality of building structure sub-models, and the position and the construction sequence of each building structure sub-model are recorded;
the analysis module is used for loading the corresponding building structure sub-models according to the construction sequence and the position, correspondingly loading the construction process, the construction process parameters and the construction drawing corresponding to each building structure sub-model, and determining all structural members which form the building structure sub-models and are contained in the building structure sub-models based on the construction process, the construction process parameters and the construction drawing;
the accounting module is connected with the analysis module and comprises a matching unit and an accounting writing unit, wherein the matching unit is used for loading the structural member corresponding to the serial number, comparing the loaded loading construction with the prefabricated member models in the standby library to obtain whether the corresponding prefabricated member models exist in the standby library or not, and if yes, the accounting writing unit writes the prefabricated material names, the prefabricated material numbers, the prefabricated material quantity, the prefabricated construction period and the prefabricated construction cost corresponding to the prefabricated member models into the structural member configuration file;
the evaluation module is connected with the analysis module and the calculation module and is used for loading the structural member which is not matched with the prefabricated member model, and synchronously analyzing the construction sub-drawing, the construction sub-process and the construction sub-process parameters corresponding to the construction sub-process corresponding to the structural member in the module, so as to determine the corresponding estimated material name, the estimated material number, the estimated material amount, the estimated construction period and the estimated work cost of the structural member during construction;
the construction scheduling manager is used for loading the corresponding building structure sub-model according to the construction sequence and the position, and loading the corresponding structural member of the building structure sub-model and the corresponding prefabricated material name, prefabricated material number, prefabricated material amount, prefabricated construction period and prefabricated construction cost of the structural member, or loading the corresponding estimated material name, estimated material number, estimated material amount, estimated construction period and estimated construction cost of the structural member; meanwhile, the construction completion report corresponding to the construction progress is formed into a corresponding configuration file which can be read by a construction scheduling manager, and after the construction scheduling manager loads the configuration file to read the construction progress, the construction scheduling scheme corresponding to the next period is correspondingly scheduled.
Further, the analysis module further comprises:
the marking unit is used for marking all the structural members according to the building structure and the construction sequence, and acquiring the serial number of each structural member according to the construction procedure;
and the characteristic editing unit is used for writing the serial numbers used by all structural members under the same building structure submodel into the same identification characteristic.
Further, the construction scheduling manager is used for setting a period required by scheduling through the estimated construction period or the prefabricated construction period of the complete structural part in each working procedure.
According to the method, the whole building engineering model is built, then the whole building engineering model is divided into the sub building structure models according to the structural composition and the construction sequence of the building engineering, then the sub building structure models are divided into independent structural members, various materials, material numbers, total amount of materials and total labor cost of the whole building engineering can be obtained through accounting the material name, the material number, the construction period and the labor cost of each structural member, when construction scheduling is carried out, the period required by scheduling is set through the estimated construction period or the prefabricated construction period of the complete structural member under each working procedure, so that the construction plan of the current period and the construction plan of the next construction period are called out according to the period, and optimization adjustment is carried out by combining a construction completion report corresponding to the construction progress, so that purchasing of various materials, material numbers and material amounts is determined, and distribution is carried out according to the construction period scheduling.
Therefore, the method and the device can assist the manager to make an accurate material demand plan and a deployment plan, and can also be used by people according to the construction manual work of deployment corresponding to the structural member, so that the material deployment is reasonable.
The construction planning system and the construction planning method can simulate corresponding construction plans for arranging material purchase and temporary storage, and help management staff to make construction site planning and material management work.
The foregoing description of embodiments of the invention has been presented for purposes of illustration and description, and is not intended to be exhaustive or limited to the embodiments disclosed. Many modifications and variations will be apparent to those of ordinary skill in the art without departing from the scope and spirit of the various embodiments described. The terminology used herein was chosen in order to best explain the principles of the embodiments, the practical application, or the technical improvements in the marketplace, or to enable others of ordinary skill in the art to understand the embodiments disclosed herein.

Claims (7)

1. The construction scheduling method based on the building engineering model is characterized by comprising the following steps of:
1) Pre-constructing a plurality of prefabricated member models used for a building structure, manufacturing a standard drawing, a standard process and standard process parameters corresponding to each prefabricated member model, and acquiring a prefabricated material name, a prefabricated material number, a prefabricated material amount, a prefabricated construction period and a prefabricated construction cost corresponding to each prefabricated member model based on the standard drawing, the standard process and the standard process parameters; storing each prefabricated part model and the prefabricated material names, prefabricated material numbers, prefabricated material amounts, prefabricated construction periods and prefabricated construction costs corresponding to the prefabricated part models in a standby library;
2) Building a building engineering integral model, dividing the building engineering integral model into a plurality of building structure sub-models according to building structures, and recording the position and construction sequence of each building structure sub-model;
3) Loading the corresponding building structure sub-models into an analysis module according to the construction sequence and the position, loading the construction process, the construction process parameters and the construction drawing corresponding to each building structure sub-model, determining all structural members constituting the building structure sub-model contained in the building structure sub-model based on the construction process, the construction process parameters and the construction drawing, marking all structural members according to the building structure and the construction sequence, and obtaining the serial number of each structural member according to the construction procedure; and the serial numbers used by all structural members under the same building structure submodel have the same identification characteristic;
4) Loading structural members corresponding to the serial numbers into an accounting module, correspondingly matching structural member models corresponding to the structural members in a standby library according to the loading sequence, if the standby library is provided with a prefabricated member model corresponding to the matching, matching prefabricated material names, prefabricated material numbers, prefabricated material amounts, prefabricated construction periods and prefabricated cost corresponding to the prefabricated member models with the structural members, and if the standby library is not provided with the corresponding prefabricated member models, turning to the step 5);
5) Loading a structural member which is not matched with the prefabricated member model into an evaluation module, and correspondingly calling out a construction sub-drawing, a construction sub-process and construction sub-process parameters corresponding to the construction sub-process corresponding to the structural member in the evaluation module, so as to determine a corresponding estimated material name, an estimated material number, an estimated material amount, an estimated construction period and an estimated labor cost when the structural member is built;
6) Writing the name, number, amount, construction period and construction cost of the prefabricated material corresponding to the structural member into a control library according to the loading serial number and the identification characteristic; or, writing the estimated material name, the estimated material number, the estimated material amount, the estimated construction period and the estimated construction cost corresponding to the structural part into a control library;
7) When construction is carried out, the building structure submodel is loaded according to the sequence, and the corresponding structural component of the loaded building structure submodel and the corresponding prefabricated material name, prefabricated material number, prefabricated material amount, prefabricated construction period and prefabricated construction cost of the structural component are in the control library, or the corresponding estimated material name, estimated material number, estimated material amount, estimated construction period and estimated construction cost of the loaded structural component are adopted, so that the dispatching of the building construction is realized.
2. The method according to claim 1, wherein in step 4), for all the structural members under the same building structure sub-model, if at least more than one of the structural members has the same corresponding prefabricated member model, the corresponding prefabricated construction period is reduced according to the set proportion.
3. The method for performing construction scheduling based on a building engineering model according to claim 1, wherein in step 7), a construction scheduling manager is provided, and the construction scheduling manager is configured to load a corresponding building structure sub-model according to a construction sequence and a position, and load a structural member corresponding to the building structure sub-model and a prefabricated material name, a prefabricated material number, a prefabricated material amount, a prefabricated construction period and a prefabricated construction cost corresponding to the structural member, or load a predicted material name, a predicted material number, a predicted material amount, a predicted construction period and a predicted construction cost corresponding to the structural member in a corresponding control library;
meanwhile, the construction completion report corresponding to the construction progress is formed into a corresponding configuration file which can be read by a construction scheduling manager, and after the construction scheduling manager loads the configuration file to read the construction progress, the construction scheduling scheme corresponding to the next period is correspondingly scheduled.
4. A method for performing construction scheduling based on a construction engineering model according to claim 3, wherein the construction scheduling scheme refers to a scheduling plan of material names, material numbers, material amounts, construction periods and construction costs corresponding to various structural members in a set construction period.
5. The system for performing construction scheduling based on the building engineering model is characterized by comprising the following components:
the prefabricated part model construction module is used for constructing a plurality of prefabricated part models used for the building structure in advance, manufacturing standard drawings, standard processes and standard process parameters corresponding to each prefabricated part model, and acquiring prefabricated material names, prefabricated material numbers, prefabricated material amounts, prefabricated construction periods and prefabricated construction costs corresponding to each prefabricated part model based on the standard drawings, the standard processes and the standard process parameters;
the standby library is connected with the prefabricated part model building module and used for storing each prefabricated part model and the prefabricated material name, the prefabricated material number, the prefabricated material amount, the prefabricated construction period and the prefabricated construction cost corresponding to the prefabricated part model in the standby library;
the construction engineering integral model construction module is used for constructing a construction engineering integral model according to an electronic drawing of construction engineering, a construction process configuration file and configuration parameters of each structural member in the drawing;
the segmentation module is used for determining the structure constitution corresponding to the building engineering integral model according to the electronic drawing of the building engineering construction, the construction process configuration file and the configuration parameters of each structural member in the drawing, so that the building engineering integral model is divided into a plurality of building structure sub-models, and the position and the construction sequence of each building structure sub-model are recorded;
the analysis module is used for loading the corresponding building structure sub-models according to the construction sequence and the position, correspondingly loading the construction process, the construction process parameters and the construction drawing corresponding to each building structure sub-model, and determining all structural members which form the building structure sub-models and are contained in the building structure sub-models based on the construction process, the construction process parameters and the construction drawing;
the accounting module is connected with the analysis module and comprises a matching unit and an accounting writing unit, wherein the matching unit is used for loading the structural member corresponding to the serial number, comparing the loaded loading construction with the prefabricated member models in the standby library to obtain whether the corresponding prefabricated member models exist in the standby library or not, and if yes, the accounting writing unit writes the prefabricated material names, the prefabricated material numbers, the prefabricated material quantity, the prefabricated construction period and the prefabricated construction cost corresponding to the prefabricated member models into the structural member configuration file;
the evaluation module is connected with the analysis module and the calculation module and is used for loading the structural member which is not matched with the prefabricated member model, and synchronously analyzing the construction sub-drawing, the construction sub-process and the construction sub-process parameters corresponding to the construction sub-process corresponding to the structural member in the module, so as to determine the corresponding estimated material name, the estimated material number, the estimated material amount, the estimated construction period and the estimated work cost of the structural member during construction;
the construction scheduling manager is used for loading the corresponding building structure sub-model according to the construction sequence and the position, and loading the corresponding structural member of the building structure sub-model and the corresponding prefabricated material name, prefabricated material number, prefabricated material amount, prefabricated construction period and prefabricated construction cost of the structural member, or loading the corresponding estimated material name, estimated material number, estimated material amount, estimated construction period and estimated construction cost of the structural member; meanwhile, the construction completion report corresponding to the construction progress is formed into a corresponding configuration file which can be read by a construction scheduling manager, and after the construction scheduling manager loads the configuration file to read the construction progress, the construction scheduling scheme corresponding to the next period is correspondingly scheduled.
6. The system for scheduling construction based on a construction model of claim 5, wherein the analysis module further comprises:
the marking unit is used for marking all the structural members according to the building structure and the construction sequence, and acquiring the serial number of each structural member according to the construction procedure;
and the characteristic editing unit is used for writing the serial numbers used by all structural members under the same building structure submodel into the same identification characteristic.
7. The system for scheduling construction based on the construction model according to claim 5, wherein the construction schedule manager is configured to set a period required for scheduling by estimating a construction period or a prefabrication construction period for the complete structural member in each process.
CN202310160613.0A 2023-02-24 2023-02-24 Construction scheduling method and system based on building engineering model Pending CN116307537A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310160613.0A CN116307537A (en) 2023-02-24 2023-02-24 Construction scheduling method and system based on building engineering model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310160613.0A CN116307537A (en) 2023-02-24 2023-02-24 Construction scheduling method and system based on building engineering model

Publications (1)

Publication Number Publication Date
CN116307537A true CN116307537A (en) 2023-06-23

Family

ID=86821503

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310160613.0A Pending CN116307537A (en) 2023-02-24 2023-02-24 Construction scheduling method and system based on building engineering model

Country Status (1)

Country Link
CN (1) CN116307537A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117236568A (en) * 2023-11-13 2023-12-15 山东九巨龙建设集团有限公司 Method and system for mounting and constructing management of prefabricated wall panel

Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108550020A (en) * 2018-03-30 2018-09-18 四川成化工程项目管理有限公司 Building cost control method based on BIM technology
CN109191577A (en) * 2018-10-22 2019-01-11 杭州睿兴栋宇建筑科技有限公司 A kind of distribution BIM collaborative platform
CN109492875A (en) * 2018-10-15 2019-03-19 筑梦高科建筑有限公司 Construction site role's management-control method based on BIM
CN110084527A (en) * 2019-05-05 2019-08-02 广西路桥工程集团有限公司 A kind of digitlization construction management system based on BIM model
CN111222786A (en) * 2020-01-04 2020-06-02 河南惠德工程咨询有限公司 Engineering cost control system based on BIM technology
CN111754138A (en) * 2020-07-07 2020-10-09 天津水泥工业设计研究院有限公司 Engineering construction progress plan management and control system and method based on BIM model
CN111881501A (en) * 2020-07-23 2020-11-03 广东腾美建设工程有限公司 Assembly type building management method and system based on BIM and cloud service
CN112016908A (en) * 2020-10-22 2020-12-01 广东恩胜科技有限公司 BIM-based construction progress monitoring method and system, electronic equipment and storage medium
CN112651126A (en) * 2020-12-24 2021-04-13 河南省第八建设集团有限公司 Building engineering construction optimization system, method, terminal and storage medium based on BIM
CN112990844A (en) * 2020-12-26 2021-06-18 上海建科工程咨询有限公司 Construction method and management system based on BIM
CN113003448A (en) * 2021-03-22 2021-06-22 中建四局第五建筑工程有限公司 Assembly type engineering tower crane arrangement method based on BIM technology
CN113343342A (en) * 2021-07-07 2021-09-03 贵州百胜工程建设咨询有限公司 BIM technology-based construction engineering quantity analysis management method and system and computer storage medium
CN113569382A (en) * 2021-06-25 2021-10-29 黄冀卓 BIM-based integrated decision optimization method and system for design and construction of fabricated building
CN115062939A (en) * 2022-06-06 2022-09-16 广州市第一装修有限公司 BIM-based decoration project management system and method
CN115168971A (en) * 2022-08-03 2022-10-11 南京工业大学 Component parameter library-based integrated collaborative method for design and construction of fabricated building
CN115329448A (en) * 2022-10-14 2022-11-11 中国电建集团山东电力建设第一工程有限公司 BIM-based fabricated building construction cost control method and system
CN115600426A (en) * 2022-11-07 2023-01-13 中国电建集团贵阳勘测设计研究院有限公司(Cn) Intelligent building construction simulation analysis system

Patent Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108550020A (en) * 2018-03-30 2018-09-18 四川成化工程项目管理有限公司 Building cost control method based on BIM technology
CN109492875A (en) * 2018-10-15 2019-03-19 筑梦高科建筑有限公司 Construction site role's management-control method based on BIM
CN109191577A (en) * 2018-10-22 2019-01-11 杭州睿兴栋宇建筑科技有限公司 A kind of distribution BIM collaborative platform
CN110084527A (en) * 2019-05-05 2019-08-02 广西路桥工程集团有限公司 A kind of digitlization construction management system based on BIM model
CN111222786A (en) * 2020-01-04 2020-06-02 河南惠德工程咨询有限公司 Engineering cost control system based on BIM technology
CN111754138A (en) * 2020-07-07 2020-10-09 天津水泥工业设计研究院有限公司 Engineering construction progress plan management and control system and method based on BIM model
CN111881501A (en) * 2020-07-23 2020-11-03 广东腾美建设工程有限公司 Assembly type building management method and system based on BIM and cloud service
CN112016908A (en) * 2020-10-22 2020-12-01 广东恩胜科技有限公司 BIM-based construction progress monitoring method and system, electronic equipment and storage medium
CN112651126A (en) * 2020-12-24 2021-04-13 河南省第八建设集团有限公司 Building engineering construction optimization system, method, terminal and storage medium based on BIM
CN112990844A (en) * 2020-12-26 2021-06-18 上海建科工程咨询有限公司 Construction method and management system based on BIM
CN113003448A (en) * 2021-03-22 2021-06-22 中建四局第五建筑工程有限公司 Assembly type engineering tower crane arrangement method based on BIM technology
CN113569382A (en) * 2021-06-25 2021-10-29 黄冀卓 BIM-based integrated decision optimization method and system for design and construction of fabricated building
CN113343342A (en) * 2021-07-07 2021-09-03 贵州百胜工程建设咨询有限公司 BIM technology-based construction engineering quantity analysis management method and system and computer storage medium
CN115062939A (en) * 2022-06-06 2022-09-16 广州市第一装修有限公司 BIM-based decoration project management system and method
CN115168971A (en) * 2022-08-03 2022-10-11 南京工业大学 Component parameter library-based integrated collaborative method for design and construction of fabricated building
CN115329448A (en) * 2022-10-14 2022-11-11 中国电建集团山东电力建设第一工程有限公司 BIM-based fabricated building construction cost control method and system
CN115600426A (en) * 2022-11-07 2023-01-13 中国电建集团贵阳勘测设计研究院有限公司(Cn) Intelligent building construction simulation analysis system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117236568A (en) * 2023-11-13 2023-12-15 山东九巨龙建设集团有限公司 Method and system for mounting and constructing management of prefabricated wall panel
CN117236568B (en) * 2023-11-13 2024-03-08 山东九巨龙建设集团有限公司 Method and system for mounting and constructing management of prefabricated wall panel

Similar Documents

Publication Publication Date Title
Tetiana et al. Innovative methods of performance evaluation of energy efficiency projects
CN116307537A (en) Construction scheduling method and system based on building engineering model
CN111652640B (en) Civil engineering auxiliary pricing method, system and storage medium thereof for electric power project
KR100712050B1 (en) Management method for risk in construction using analysis of cash flow and apparatus threrof, and management method for risk in construction using analysis of portfolio and apparatus threrof using that
KR102238926B1 (en) Cost managent system and cost managent method using the same
CN115456472A (en) Industrial product purchase supply chain carbon asset digital management method and system
JP4898086B2 (en) Rental real estate information management system
Wu et al. Modeling stockout risk and JIT purchasing in ready-mixed concrete batching plants
Kern et al. A model for integrating cost management and production planning and control in construction
Hatmoko et al. Managing risks of precast concrete supply chain: a case study
CN115689030A (en) Digital lean construction management method, system, electronic device and storage medium
Andhyal et al. Applications of 5D CAD for Billing in Construction using GIS
CN113657804A (en) Building engineering EPC cost and progress management system based on BIM technology
Sinenko et al. Economical aspects of the cost regulation for the construction of buildings
CN111680340B (en) Building material price information pushing method, system and device and storage medium thereof
Zhou Construction Cost Control Method Based on BIM information Integration Platform
Nguyen et al. Completing the construction management at Hoa Binh construction group
JP3235054U (en) Repair and maintenance management equipment and printed matter
Fan et al. Decision Making Optimization for Cost Control Based on Earned Value Method
Gurum Analysis of LCC and BIM during Operations and Maintenance phase from the Perspective of Cost
Ai Notice of Retraction: Analysis and countermeasures of project cost control in construction enterprises
Baker Time-cost relationships in construction.
Bind et al. Formation Of General Methodological Requirements for Modernization Approaches to Cost Engineering in The Activities of Construction Companies
CN114819463A (en) SMO labor cost measuring and calculating method based on working hours
JP6301430B2 (en) Profit / loss prediction apparatus and profit / loss prediction program

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination