CN112507430B - Visual fusion method for BIM model and engineering project - Google Patents

Visual fusion method for BIM model and engineering project Download PDF

Info

Publication number
CN112507430B
CN112507430B CN202011390327.6A CN202011390327A CN112507430B CN 112507430 B CN112507430 B CN 112507430B CN 202011390327 A CN202011390327 A CN 202011390327A CN 112507430 B CN112507430 B CN 112507430B
Authority
CN
China
Prior art keywords
model
engineering
progress
project
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202011390327.6A
Other languages
Chinese (zh)
Other versions
CN112507430A (en
Inventor
郭政
黄桂林
吴武清
邱倬
杨贤辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Jiangxi Electric Power Co ltd Construction Branch
State Grid Corp of China SGCC
Original Assignee
State Grid Jiangxi Electric Power Co ltd Construction Branch
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Jiangxi Electric Power Co ltd Construction Branch, State Grid Corp of China SGCC filed Critical State Grid Jiangxi Electric Power Co ltd Construction Branch
Priority to CN202011390327.6A priority Critical patent/CN112507430B/en
Publication of CN112507430A publication Critical patent/CN112507430A/en
Application granted granted Critical
Publication of CN112507430B publication Critical patent/CN112507430B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Geometry (AREA)
  • Strategic Management (AREA)
  • Human Resources & Organizations (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Computer Hardware Design (AREA)
  • Marketing (AREA)
  • Economics (AREA)
  • Civil Engineering (AREA)
  • Primary Health Care (AREA)
  • General Engineering & Computer Science (AREA)
  • Pure & Applied Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Mathematical Optimization (AREA)
  • General Health & Medical Sciences (AREA)
  • Mathematical Analysis (AREA)
  • Computational Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Software Systems (AREA)
  • Data Mining & Analysis (AREA)
  • Computer Graphics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a visual fusion method of a BIM model and an engineering project, which comprises the steps of importing an engineering project progress plan model edited by an MSPROJ; importing a GIM model and carrying out analysis and format conversion; carrying out association binding on the imported planning model and the GIM model and setting time attributes; binding personnel data; updating data in real time; and (5) realizing visualization of the three-dimensional progress. The visual fusion method of the BIM model and the engineering project provided by the invention realizes the visual fusion of the BIM model and the engineering project through the conversion and data association of the model and the visual technology, and has the advantages of high reliability, good practicability and good effect.

Description

Visual fusion method for BIM model and engineering project
Technical Field
The invention belongs to the field of electrical automation, and particularly relates to a visual fusion method of a BIM model and engineering projects.
Background
Along with the development of economic technology and the improvement of living standard of people, electric energy becomes an indispensable secondary energy source in the production and living of people, and brings endless convenience to the production and living of people.
BIM (Building Information Modeling) technology is a datamation tool applied to engineering design, construction and management; the method is characterized in that the data of the project is shared and transferred in the whole life cycle process of project planning, operation and maintenance through integrating the data and informatization models of the building. At present, a power grid system widely applies BIM technology to monitor the whole life cycle of a project.
Meanwhile, microsoft Project (or MSPROJ) is a well-known general project tool software which can also help the project to monitor the whole life cycle; it also finds wide application in power grid systems.
However, in the current full life cycle monitoring of the power grid project, BIM data and MSPROJ data are not fused, so that the problems of low monitoring efficiency, poor monitoring quality and the like exist in the monitoring process.
Disclosure of Invention
The invention aims to provide a visual fusion method of a BIM model and engineering projects, which has high reliability, good practicability and good effect.
The visual fusion method of the BIM model and the engineering project provided by the invention comprises the following steps:
s1, importing an engineering project progress plan model edited by an MSPROJ;
s2, importing a GIM model, and analyzing and converting the format;
s3, carrying out association binding on the planning model imported in the step S1 and the GIM model imported in the step S2, and setting time attributes;
s4, binding personnel data;
s5, updating data in real time;
s6, realizing visualization of the three-dimensional progress.
The visual fusion method of the BIM model and the engineering project further comprises the following steps:
s7, according to the visual realization of the three-dimensional progress obtained in the step S6, comparing the difference between the actual progress and the planned progress of the engineering project, and analyzing.
The analysis is specifically carried out by adopting the following formulaCalculating plan general progress rate GPI and actual efficacy E i
Figure BDA0002812435310000021
Figure BDA0002812435310000022
/>
PA in i The engineering quantity of the partial project engineering completed in a specific time; TPA is the total engineering quantity of the project; n is the sum of all the procedures in a specific time; q (Q) i The engineering quantity of the i-th engineering; t (T) i The engineering time of the ith engineering.
The project progress plan model edited by the MSPROJ is imported in the step S1, specifically, an MSPROJ file is used as a storage file of project information, the original BIM-based data relation model is simplified, component ID information is stored in a remark column in a task worksheet view of the MSPROJ file, the associated component ID is directly recorded in a task, and the associated configuration resource is stored in the task configuration resource; and the "association configuration information" and the component ID recorded in the "task" correspond to each other in order.
The GIM model is imported in step S2, and parsing and format conversion are performed, specifically, a 7Z algorithm is adopted to decompress the GIM file, and UTF-8 is adopted to decode geometric model units (x.mod), combination models (x.phm), physical models (x.dev), logical models (x.sch), engineering models (x.cbm) and attribute information (x.fam) and convert the decoded GIM file into FBX format; the format of the geometric model unit is mod; the format of the combined model is phm; the format of the physical model is dev; the format of the logic model is; the format of the engineering model is; the format of the attribute information is fam.
Step S3, performing association binding on the planning model imported in step S1 and the GIM model imported in step S2, setting time attributes, namely, mutually connecting progress information and the three-dimensional model through WBS decomposition, so as to obtain an overall tree structure based on the project, and enabling the overall tree structure to reach the bottommost work package; then, on the basis of the WBS, carrying out specific progress planning and resource allocation on the project, and refining to the extreme end of the WBS; combining and matching the code with the component information; and finally, carrying out coding management on the engineering construction procedure of the machine transformer substation.
And step S4, binding personnel data, namely acquiring personnel data of field perception hardware through a data interface, and associating the personnel data with a progress plan.
The data in the step S5 is updated in real time, and particularly, project progress plans are continuously checked and displayed according to actual construction states; in the engineering progress management system, the construction progress is dynamically displayed and optimized according to the actual condition of the site; and when the progress information is modified, the progress information is updated and modified in the system according to the actual situation.
The three-dimensional progress visualization in the step S6 is realized by establishing a relation between a model component and progress information in an MSPROJ file by using a BIM-based engineering project management data relation model, then reading the progress information of a task from the MSPROJ file through an API, controlling the display state of the model component according to the relation among project time, system time and progress bar values, the progress information and the set related information, and displaying the engineering construction process and the construction state on a WEB interface in a 4D visualization mode to complete the engineering project construction progress simulation and visual display.
The visual fusion method of the BIM model and the engineering project provided by the invention realizes the visual fusion of the BIM model and the engineering project through the conversion and data association of the model and the visual technology, and has the advantages of high reliability, good practicability and good effect.
Drawings
FIG. 1 is a schematic flow chart of the method of the present invention.
Detailed Description
A schematic process flow diagram of the method of the present invention is shown in fig. 1: the visual fusion method of the BIM model and the engineering project provided by the invention comprises the following steps:
s1, importing an engineering project progress plan model edited by an MSPROJ; the method specifically comprises the steps of simplifying an original BIM-based data relation model by taking an MSPROJ file as a storage file of engineering project information, storing component ID information in a remark column in a task worksheet view of the MSPROJ file, directly recording an associated component ID in a task, and storing an associated configuration resource in the task configuration resource; and the "association configuration information" and the component ID recorded in the "task" correspond to each other in order;
s2, importing a GIM model, and analyzing and converting the format; the method comprises the steps of decompressing a GIM file by adopting a 7Z algorithm, decoding a geometric model unit (x.mod), a combined model (x.phm), a physical model (x.dev), a logic model (x.sch), an engineering model (x.cbm) and attribute information (x.fam) by adopting UTF-8, and converting the decoded file into an FBX format; the format of the geometric model unit is mod; the format of the combined model is phm; the format of the physical model is dev; the format of the logic model is; the format of the engineering model is; the format of the attribute information is fam;
s3, carrying out association binding on the planning model imported in the step S1 and the GIM model imported in the step S2, and setting time attributes; the method comprises the steps of connecting progress information and a three-dimensional model with each other through WBS decomposition, so that an overall tree structure based on projects is obtained until a work package at the bottom layer is obtained; then, on the basis of the WBS, carrying out specific progress planning and resource allocation on the project, and refining to the extreme end of the WBS; combining and matching the code with the component information; finally, carrying out coding management on the engineering construction procedure of the machine transformer substation;
s4, binding personnel data; the method comprises the steps of acquiring personnel data of field perception hardware through a data interface and correlating the personnel data with a progress plan;
s5, updating data in real time; the project schedule is continuously checked and displayed according to the actual construction state; in the engineering progress management system, the construction progress is dynamically displayed and optimized according to the actual condition of the site; when the progress information is modified, the progress information is updated and modified in the system according to the actual situation;
s6, realizing visualization of the three-dimensional progress; the method comprises the steps of establishing a relation between a model component and progress information in an MSPROJ file by using a BIM-based engineering project management data relation model, then reading the progress information of a task from the MSPROJ file through an API, controlling the display state of the model component according to the relation among project time, system time and progress bar values, the progress information and the set related information, and displaying the engineering construction process and the construction state on a WEB interface in a 4D visual mode to complete the simulation and visual display of the engineering project construction progress;
s7, according to the visual realization of the three-dimensional progress obtained in the step S6, comparing the difference between the actual progress and the planned progress of the engineering project, and analyzing; during analysis, the planned overall progress rate GPI and the actual efficacy E can be calculated by the following formula i
Figure BDA0002812435310000051
Figure BDA0002812435310000061
PA in i The engineering quantity of the partial project engineering completed in a specific time; TPA is the total engineering quantity of the project; n is the sum of all the procedures in a specific time; q (Q) i The engineering quantity of the i-th engineering; t (T) i The engineering time of the ith engineering.

Claims (4)

1. A visual fusion method of a BIM model and engineering projects comprises the following steps:
s1, importing an engineering project progress plan model edited by an MSPROJ; the method specifically comprises the steps of simplifying an original BIM-based data relation model by taking an MSPROJ file as a storage file of engineering project information, storing component ID information in a remark column in a task worksheet view of the MSPROJ file, directly recording an associated component ID in a task, and storing an associated configuration resource in the task configuration resource; and the "association configuration information" and the component ID recorded in the "task" correspond to each other in order;
s2, importing a GIM model, and analyzing and converting the format;
s3, carrying out association binding on the planning model imported in the step S1 and the GIM model imported in the step S2, and setting time attributes; the method comprises the steps of connecting progress information and a three-dimensional model with each other through WBS decomposition, so that an overall tree structure based on projects is obtained until a work package at the bottom layer is obtained; then, on the basis of the WBS, carrying out specific progress planning and resource allocation on the project, and refining to the extreme end of the WBS; combining and matching the code with the component information; finally, carrying out coding management on the engineering construction procedure of the machine transformer substation;
s4, binding personnel data;
s5, updating data in real time;
s6, realizing visualization of the three-dimensional progress; specifically, a BIM-based engineering project management data relation model is utilized to establish the relation between a model component and progress information in an MSPROJ file, then the progress information of a task is read from the MSPROJ file through an API, the display state of the model component is controlled according to the relation among project time, system time and progress bar values, the progress information and the set related information, the engineering construction process and the construction state are displayed on a WEB interface in a 4D visual mode, and the engineering project construction progress simulation and visual display are completed
S7, according to the visual realization of the three-dimensional progress obtained in the step S6, comparing the difference between the actual progress and the planned progress of the engineering project, and analyzing; in the concrete analysis, the planned comprehensive progress rate GPI and the actual efficacy E are calculated by adopting the following formulas i
Figure FDA0003985571530000021
Figure FDA0003985571530000022
PA in i The engineering quantity of the partial project engineering completed in a specific time; TPA is the total engineering quantity of the project; n is the sum of all the procedures in a specific time; q (Q) i The engineering quantity of the i-th engineering; t (T) i The engineering time of the ith engineering.
2. The visual fusion method of a BIM model and an engineering project according to claim 1, wherein the step S2 is characterized in that the GIM model is imported, parsed and format-converted, specifically, the GIM file is decompressed by using a 7Z algorithm, and then the geometric model unit, the combination model, the physical model, the logical model, the engineering model and the attribute information are decoded by using UTF-8 and converted into the FBX format; the format of the geometric model unit is mod; the format of the combined model is phm; the format of the physical model is dev; the format of the logic model is; the format of the engineering model is; the format of the attribute information is fam.
3. The visual fusion method of a BIM model and an engineering project according to claim 2, wherein the personnel data binding in step S4 is specifically that personnel data of field perception hardware is obtained through a data interface and is associated with a progress plan.
4. The visual fusion method of a BIM model and an engineering project according to claim 3, wherein the data in step S5 is updated in real time, specifically, the project schedule is continuously checked and displayed according to the actual construction state; in the engineering progress management system, the construction progress is dynamically displayed and optimized according to the actual condition of the site; and when the progress information is modified, the progress information is updated and modified in the system according to the actual situation.
CN202011390327.6A 2020-12-02 2020-12-02 Visual fusion method for BIM model and engineering project Active CN112507430B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011390327.6A CN112507430B (en) 2020-12-02 2020-12-02 Visual fusion method for BIM model and engineering project

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011390327.6A CN112507430B (en) 2020-12-02 2020-12-02 Visual fusion method for BIM model and engineering project

Publications (2)

Publication Number Publication Date
CN112507430A CN112507430A (en) 2021-03-16
CN112507430B true CN112507430B (en) 2023-04-28

Family

ID=74968531

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011390327.6A Active CN112507430B (en) 2020-12-02 2020-12-02 Visual fusion method for BIM model and engineering project

Country Status (1)

Country Link
CN (1) CN112507430B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113221297B (en) * 2021-03-29 2022-08-26 湘潭大学 Method for converting power grid information model into FBX three-dimensional model and storing attributes
CN113094861B (en) * 2021-05-08 2022-06-03 国网河北省电力有限公司经济技术研究院 Data storage method, device, equipment and storage medium
CN115098920A (en) * 2022-06-24 2022-09-23 国网安徽省电力有限公司安庆供电公司 Intelligent electric power management and control method, device and system based on mobile visualization
CN117371949B (en) * 2023-10-24 2024-05-31 国网山东省电力公司建设公司 Three-dimensional visual model-based power transmission line construction safety monitoring method and system
CN117196545A (en) * 2023-11-08 2023-12-08 北京达美盛软件股份有限公司 Design compliance examination method and system based on three-dimensional checking

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019198738A1 (en) * 2018-04-11 2019-10-17 国立大学法人千葉大学 Component management database, component management system, and component management method
CN110489888A (en) * 2019-08-23 2019-11-22 中铁第六勘察设计院集团有限公司 Based on the three-dimensional association general technology method of BIM platform two
CN209761315U (en) * 2018-11-29 2019-12-10 国网江西省电力有限公司建设分公司 Portable ladder stand for deep foundation pit of power transmission line engineering
CN111507002A (en) * 2020-04-17 2020-08-07 国网湖南省电力有限公司 Method and system for mounting power transformation project, readable storage medium and computer
CN111754138A (en) * 2020-07-07 2020-10-09 天津水泥工业设计研究院有限公司 Engineering construction progress plan management and control system and method based on BIM model

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9639516B2 (en) * 2012-11-08 2017-05-02 Solibri, Inc. System and method for express spreadsheet visualization for building information modeling
CN109377066A (en) * 2018-10-31 2019-02-22 广西路桥工程集团有限公司 A kind of live Schedule monitoring system and method based on threedimensional model
CN110084526B (en) * 2019-05-05 2022-05-31 广西路桥工程集团有限公司 BIM + WBS-based visual project management monitoring system
CN110991882A (en) * 2019-12-03 2020-04-10 中交第二航务工程勘察设计院有限公司 Project construction fine management method based on BIM5D
CN111143922A (en) * 2019-12-16 2020-05-12 中国建筑第八工程局有限公司 Multi-platform structure stratum digital twin modeling method and system
CN112001680A (en) * 2020-08-27 2020-11-27 四川公路桥梁建设集团有限公司 BIM-based highway engineering management system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019198738A1 (en) * 2018-04-11 2019-10-17 国立大学法人千葉大学 Component management database, component management system, and component management method
CN209761315U (en) * 2018-11-29 2019-12-10 国网江西省电力有限公司建设分公司 Portable ladder stand for deep foundation pit of power transmission line engineering
CN110489888A (en) * 2019-08-23 2019-11-22 中铁第六勘察设计院集团有限公司 Based on the three-dimensional association general technology method of BIM platform two
CN111507002A (en) * 2020-04-17 2020-08-07 国网湖南省电力有限公司 Method and system for mounting power transformation project, readable storage medium and computer
CN111754138A (en) * 2020-07-07 2020-10-09 天津水泥工业设计研究院有限公司 Engineering construction progress plan management and control system and method based on BIM model

Also Published As

Publication number Publication date
CN112507430A (en) 2021-03-16

Similar Documents

Publication Publication Date Title
CN112507430B (en) Visual fusion method for BIM model and engineering project
CN105844380A (en) BIM-based BIM project element management method and system
CN104123502A (en) Mechanical and electrical installation overall-planning system and method based on three-dimensional construction drawing model
CN109345195A (en) A kind of project supervision monitoring and managing method and system based on BIM
CN108053486A (en) Construction method and system based on virtual technology
CN111651818A (en) BIM model rapid change method
CN112907390A (en) Building full life cycle dynamic intelligent management system and method based on BIM
CN116127551A (en) Bridge construction progress refined control method based on digital twin multidimensional model
CN111861825A (en) Construction method and system of rail transit industry vocational training system model
CN115329448A (en) BIM-based fabricated building construction cost control method and system
CN116562802A (en) Intelligent construction application platform of track traffic based on BIM
CN107146165B (en) Distribution network planning data management method and system
CN104881739A (en) Marketing and distribution data consistency verification method based on IEC61970-61968 CIM standard
CN111597166B (en) Power database model construction method, device, computer equipment and storage medium
CN111815235A (en) Engineering material management and control method and device based on BIM, storage medium and computer equipment
CN115439598A (en) Presentation data processing method based on digital twins, computing device and storage medium
CN112734379A (en) Engineering cost management system based on BIM technology
CN113128846A (en) BIM-based large steel structure construction engineering full life cycle management method
KR100791475B1 (en) Architectural design management system for cooperating with active partners
CN112116322A (en) Three-dimensional design-based method and system for quickly and accurately compiling construction cost of power transformation project
CN101447065A (en) Method for uniformly collecting engineering progress data
CN216014298U (en) Building supervisory systems based on BIM
Yan et al. Developing a web-based BIM asset and facility management system of building digital twins
Liu Research on the Design of Digital Twin System for Construction Safety
CN115018458A (en) BIM technology-based substation-oriented engineering construction plan optimization method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant