CN104573254A - Pre-construction technical disclosure method based on BIM - Google Patents
Pre-construction technical disclosure method based on BIM Download PDFInfo
- Publication number
- CN104573254A CN104573254A CN201510029192.3A CN201510029192A CN104573254A CN 104573254 A CN104573254 A CN 104573254A CN 201510029192 A CN201510029192 A CN 201510029192A CN 104573254 A CN104573254 A CN 104573254A
- Authority
- CN
- China
- Prior art keywords
- construction
- bim
- confiding
- dimensional model
- technological secret
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a pre-construction technical disclosure method based on BIM. The method includes the following steps: building a construction BIM three-dimensional model according to construction design and marking relevant technical parameters in the model; manufacturing a construction scheme disclosure written card; placing the construction BIM three-dimensional model on a communication screen through a visual device. The method further includes that a designer breaks down the BIM three-dimensional model through the communication screen and explain technical parameters to constructors to conduct technical disclosure, and the constructors feed back opinions through the technical disclosure. The method has the advantages of being visual, quick and capable of improving construction efficiency, enabling the constructors to learn construction steps and various construction requirements and ensuring construction quality.
Description
Technical field
The present invention relates to a kind of architecture information construction method, in particular, relate to a kind of based on method of confiding a technological secret before the construction of BIM.
Background technology
In engineering construction process, before each operation starts construction, all needing to confide a technological secret to construction crewmember. first the mode of confiding a technological secret adopted at present for working out technical annotation in construction form, then carry out at the bottom of an casual acquaintance to construction crewmember, finally Signature Confirmation on written record of telling somebody what one's real intentions are.Existing application number 201410362565.4; the patented technology of denomination of invention " a kind of joint examination of the drawing based on BIM technology system and method "; only to BIM three-dimensional model examination & verification construction drawing; workmen is not confided a technological secret; this can cause workmen can not understand completely construction content of telling somebody what one's real intentions are; in construction process, often there will be mistake and cause and do over again, harmful effect is produced to construction quality, progress, cost control.
Summary of the invention
The present invention is directed to the deficiencies in the prior art, and a kind of operating efficiency that improves is provided, reduce a kind of based on method of confiding a technological secret before the construction of BIM of construction cost.
Of the present invention a kind of based on method of confiding a technological secret before the construction of BIM, comprise the following steps:
Step 1: set up construction BIM three-dimensional model according to job design, and mark relevant technical parameter in a model;
Step 2: make arrangement and method for construction and to tell somebody what one's real intentions are written card;
Step 3: construction BIM three-dimensional model is placed on by visualization device and exchanges on screen;
Step 4: designer decomposes construction BIM three-dimensional model by exchanging screen, confides a technological secret to workmen by explaining every technical parameter;
Step 5: workmen is by feedback opinion of confiding a technological secret.
Job design in described step 1 is working drawing or arrangement and method for construction.
Described working drawing is reinforced bar engineering, masonry project and whitewashes engineering working drawing.
Described arrangement and method for construction is scaffolding work, template is set up and propping works arrangement and method for construction.
In described step 2 arrangement and method for construction tell somebody what one's real intentions are that written card is that construction BIM three-dimensional model is put down, stood, the decomposing schematic representation of section and construction process figure.
The invention has the beneficial effects as follows: (1) is directly perceived, quick, improves operating efficiency; (2) make workmen understand construction procedure and every construction requirement, guarantee construction quality.
Accompanying drawing explanation
Fig. 1 is process flow diagram of the present invention.
Embodiment
Below in conjunction with accompanying drawing, the invention will be further described.
In the drawings, of the present invention a kind of based on method of confiding a technological secret before the construction of BIM, comprise the following steps:
Step 1: set up construction BIM three-dimensional model according to working drawing or arrangement and method for construction, and mark relevant technical parameter in a model; Working drawing is reinforced bar engineering, masonry project and whitewashes engineering working drawing, and arrangement and method for construction is scaffolding work, template is set up and propping works arrangement and method for construction;
Step 2: make that construction BIM three-dimensional model is put down, stood, the decomposing schematic representation of section and construction process figure to tell somebody what one's real intentions are written card as arrangement and method for construction;
Step 3: construction BIM three-dimensional model is placed on by visualization device and exchanges on screen;
Step 4: designer decomposes construction BIM three-dimensional model by exchanging screen, confides a technological secret to workmen by explaining every technical parameter;
Step 5: workmen is by feedback opinion of confiding a technological secret.
Making workmen fully understand construction procedure and every construction requirement by above-mentioned steps, avoiding, because workmen causes because of not understanding work progress construction speed slow, guaranteeing construction quality.
Claims (5)
1., based on a method of confiding a technological secret before the construction of BIM, it is characterized in that, comprise the following steps:
Step 1: set up construction BIM three-dimensional model according to job design, and mark relevant technical parameter in a model;
Step 2: make arrangement and method for construction and to tell somebody what one's real intentions are written card;
Step 3: construction BIM three-dimensional model is placed on by visualization device and exchanges on screen;
Step 4: designer decomposes construction BIM three-dimensional model by exchanging screen, confides a technological secret to workmen by explaining every technical parameter;
Step 5: workmen is by feedback opinion of confiding a technological secret.
2. according to claim 1ly a kind ofly to it is characterized in that based on method of confiding a technological secret before the construction of BIM, the job design in described step 1 is working drawing or arrangement and method for construction.
3. according to claim 2ly a kind ofly to it is characterized in that based on method of confiding a technological secret before the construction of BIM, described working drawing is reinforced bar engineering, masonry project and whitewashes engineering working drawing.
4. according to claim 2ly a kind ofly to it is characterized in that based on method of confiding a technological secret before the construction of BIM, described arrangement and method for construction is scaffolding work, template is set up and propping works arrangement and method for construction.
5. according to claim 1ly a kind ofly to it is characterized in that based on method of confiding a technological secret before the construction of BIM, in described step 2 arrangement and method for construction tell somebody what one's real intentions are that written card is that construction BIM three-dimensional model is put down, stood, the decomposing schematic representation of section and construction process figure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510029192.3A CN104573254A (en) | 2015-01-21 | 2015-01-21 | Pre-construction technical disclosure method based on BIM |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510029192.3A CN104573254A (en) | 2015-01-21 | 2015-01-21 | Pre-construction technical disclosure method based on BIM |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104573254A true CN104573254A (en) | 2015-04-29 |
Family
ID=53089308
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510029192.3A Pending CN104573254A (en) | 2015-01-21 | 2015-01-21 | Pre-construction technical disclosure method based on BIM |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104573254A (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104850709A (en) * | 2015-05-25 | 2015-08-19 | 苏州金螳螂建筑装饰股份有限公司 | Three-dimensional simulation method for construction of architectural decoration project |
CN106250638A (en) * | 2016-08-04 | 2016-12-21 | 中建三局第建设工程有限责任公司 | A kind of backform comprehensive Design based on BIM and application process |
CN106295022A (en) * | 2016-08-15 | 2017-01-04 | 中国十七冶集团有限公司 | The simulation of a kind of arrangement and method for construction based on BIM and optimization method |
CN106412515A (en) * | 2016-10-14 | 2017-02-15 | 中建三局安装工程有限公司 | Visual disclosure device for technical disclosure on construction site |
CN106803163A (en) * | 2016-12-08 | 2017-06-06 | 中铁四局集团第二工程有限公司 | A kind of method of telling somebody what one's real intentions are based on AR technologies |
CN106803162A (en) * | 2016-12-02 | 2017-06-06 | 中铁四局集团第二工程有限公司 | A kind of three-dimensional construction operation guidance method based on BIM technology |
CN107563662A (en) * | 2017-09-15 | 2018-01-09 | 中建海峡建设发展有限公司 | A kind of method and computing device of PC components production curves |
CN107729609A (en) * | 2017-09-14 | 2018-02-23 | 北京致臻智造科技有限公司 | The display methods and system that a kind of building decoration technology is told somebody what one's real intentions are |
CN108507357A (en) * | 2018-03-28 | 2018-09-07 | 中国冶集团有限公司 | Industrial furnace branch pipe tee connection liner brick setting out method |
CN108589725A (en) * | 2018-05-15 | 2018-09-28 | 中国十七冶集团有限公司 | A kind of built-in fitting construction method based on BIM technology |
CN112434362A (en) * | 2020-11-23 | 2021-03-02 | 上海燃气工程设计研究有限公司 | BIM technology-based overground gas pipeline visual construction bottom crossing method |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103247004A (en) * | 2013-04-28 | 2013-08-14 | 中建安装工程有限公司 | Information management method and system based on electromechanical integrated BIM (building information model) |
CN104217065A (en) * | 2014-07-28 | 2014-12-17 | 成都市第四建筑工程公司 | BIM technology-based drawing reviewing system and method |
CN104281729A (en) * | 2014-07-02 | 2015-01-14 | 哈尔滨工业大学 | BIM (building information model) method for digital processing and manufacturing of steel structure buildings |
-
2015
- 2015-01-21 CN CN201510029192.3A patent/CN104573254A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103247004A (en) * | 2013-04-28 | 2013-08-14 | 中建安装工程有限公司 | Information management method and system based on electromechanical integrated BIM (building information model) |
CN104281729A (en) * | 2014-07-02 | 2015-01-14 | 哈尔滨工业大学 | BIM (building information model) method for digital processing and manufacturing of steel structure buildings |
CN104217065A (en) * | 2014-07-28 | 2014-12-17 | 成都市第四建筑工程公司 | BIM technology-based drawing reviewing system and method |
Non-Patent Citations (4)
Title |
---|
曹乐等: "BIM技术在云南科技馆新馆项目中钢结构吊装方案应用", 《第十六届中国科协年会论文集》 * |
王显斌等: "BIM技术在某医院工程中的应用", 《建筑》 * |
王永义: "BIM协同平台在铁路工程建造阶段的应用研究", 《铁路技术创新》 * |
赵军等: "BIM技术在贵阳金阳会展城某项目平面布置和可视化交底应用", 《城市建筑》 * |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104850709A (en) * | 2015-05-25 | 2015-08-19 | 苏州金螳螂建筑装饰股份有限公司 | Three-dimensional simulation method for construction of architectural decoration project |
CN106250638A (en) * | 2016-08-04 | 2016-12-21 | 中建三局第建设工程有限责任公司 | A kind of backform comprehensive Design based on BIM and application process |
CN106295022A (en) * | 2016-08-15 | 2017-01-04 | 中国十七冶集团有限公司 | The simulation of a kind of arrangement and method for construction based on BIM and optimization method |
CN106412515A (en) * | 2016-10-14 | 2017-02-15 | 中建三局安装工程有限公司 | Visual disclosure device for technical disclosure on construction site |
CN106803162A (en) * | 2016-12-02 | 2017-06-06 | 中铁四局集团第二工程有限公司 | A kind of three-dimensional construction operation guidance method based on BIM technology |
CN106803163A (en) * | 2016-12-08 | 2017-06-06 | 中铁四局集团第二工程有限公司 | A kind of method of telling somebody what one's real intentions are based on AR technologies |
CN107729609A (en) * | 2017-09-14 | 2018-02-23 | 北京致臻智造科技有限公司 | The display methods and system that a kind of building decoration technology is told somebody what one's real intentions are |
CN107563662A (en) * | 2017-09-15 | 2018-01-09 | 中建海峡建设发展有限公司 | A kind of method and computing device of PC components production curves |
CN108507357A (en) * | 2018-03-28 | 2018-09-07 | 中国冶集团有限公司 | Industrial furnace branch pipe tee connection liner brick setting out method |
CN108507357B (en) * | 2018-03-28 | 2020-01-31 | 中国一冶集团有限公司 | Laying-out method for bricks lined in three-way pipeline of industrial furnace |
CN108589725A (en) * | 2018-05-15 | 2018-09-28 | 中国十七冶集团有限公司 | A kind of built-in fitting construction method based on BIM technology |
CN112434362A (en) * | 2020-11-23 | 2021-03-02 | 上海燃气工程设计研究有限公司 | BIM technology-based overground gas pipeline visual construction bottom crossing method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104573254A (en) | Pre-construction technical disclosure method based on BIM | |
CN105204793A (en) | Method for applying BIM and 3D printing technology to construction | |
CN107256005A (en) | A kind of reinforcing steel bar numerical control processing method and equipment based on BIM technology | |
CN106652049A (en) | Full-professional design delivery method for building based on augmented reality technology of mobile terminal | |
CN106202831A (en) | A kind of pipeline layout optimization method based on BIM | |
CN106055829A (en) | Water supply and drainage pipeline assembly prefabrication system construction method based on BIM | |
CN105117514B (en) | Modularization automatic map delivery method and system | |
CN105913334A (en) | Visualized detection method for online abnormal movements of power distribution automation graph and model | |
CN107330970A (en) | A kind of threedimensional model processing method, server and computer read/write memory medium | |
CN106296473A (en) | A kind of construction project progress real-time control method based on BIM technology | |
CN103369836A (en) | Method and device for drilling band expansion/contraction | |
KR20140127038A (en) | Automatic creating method for 2D file from 3D file | |
CN107299762A (en) | A kind of concrete pouring procedure based on BIM | |
CN110795789A (en) | Application method in scaffold engineering based on BIM (building information modeling) cooperation technology | |
CN107451358A (en) | A kind of building method of the curved wall based on BIM | |
CN110929309B (en) | Automatic verification method for protection section list document in urban rail signal system | |
CN107895065A (en) | A kind of plant design method based on 3-D technology | |
CN106873437A (en) | Nuclear power station real-time information monitoring system picture is detected and automatic configuration system and method | |
CN104281727A (en) | Method for designing tire die on basis of Excel and CAD (computer aided design) platform | |
CN106777641B (en) | Rapid modeling method for reinforcing plate with inverted right angle | |
CN105260569A (en) | Method of automatically punching ground holes based on CadenceAllegro | |
CN112765711A (en) | BIM modeling method for green building simulation calculation | |
CN103745075A (en) | Method for automatically generating lamination information on PCB (Printed Circuit Board) drilling layer | |
JP4803447B2 (en) | CAD system and program implemented in this system | |
CN105446883A (en) | Model verification analysis method based on data configuration tool |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20150429 |
|
WD01 | Invention patent application deemed withdrawn after publication |