CN109558606A - BIM Tender System - Google Patents
BIM Tender System Download PDFInfo
- Publication number
- CN109558606A CN109558606A CN201710871729.XA CN201710871729A CN109558606A CN 109558606 A CN109558606 A CN 109558606A CN 201710871729 A CN201710871729 A CN 201710871729A CN 109558606 A CN109558606 A CN 109558606A
- Authority
- CN
- China
- Prior art keywords
- model
- bim
- component
- classification
- conversion
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000004364 calculation method Methods 0.000 claims abstract description 17
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 15
- 238000010276 construction Methods 0.000 claims abstract description 13
- 238000005034 decoration Methods 0.000 claims abstract description 9
- 238000004458 analytical method Methods 0.000 claims abstract description 7
- 238000009428 plumbing Methods 0.000 claims abstract description 6
- 238000006243 chemical reaction Methods 0.000 claims description 19
- 238000010586 diagram Methods 0.000 claims description 11
- 239000003086 colorant Substances 0.000 claims description 3
- 230000011218 segmentation Effects 0.000 claims description 3
- 238000009423 ventilation Methods 0.000 claims description 3
- 229910000831 Steel Inorganic materials 0.000 claims description 2
- 239000010959 steel Substances 0.000 claims description 2
- 238000009825 accumulation Methods 0.000 abstract description 3
- 238000007726 management method Methods 0.000 description 7
- 238000013461 design Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 230000005662 electromechanics Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000004088 simulation Methods 0.000 description 1
- 238000012800 visualization Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/18—Network design, e.g. design based on topological or interconnect aspects of utility systems, piping, heating ventilation air conditioning [HVAC] or cabling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Business, Economics & Management (AREA)
- Geometry (AREA)
- Strategic Management (AREA)
- Human Resources & Organizations (AREA)
- Computer Hardware Design (AREA)
- General Engineering & Computer Science (AREA)
- Evolutionary Computation (AREA)
- Computational Mathematics (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Economics (AREA)
- Marketing (AREA)
- Data Mining & Analysis (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Computer Networks & Wireless Communication (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Instructional Devices (AREA)
Abstract
The invention discloses a kind of BIM Tender Systems, comprising the following steps: the following steps are included: (1) creates Revit model;(2) BIM buildings model is established;(3) adjustment of model is checked;(4) classification and calculation amount of component;(5) data generation table will be calculated and summarized and exported again, and establish 5D relational database in BIM buildings model, pass through contract, the analysis of plan and practice of construction data, realize more calculation comparisons.Operation of the present invention is simple and convenient, more intelligence and efficiently will the specialized engineerings such as building, structure, decoration, reinforcing bar, plumbing, electromechanical equipment integrate a BIM model, be enterprise realization construction project Life cycle project cost coordinated management, data accumulation and depth analysis integrated management.
Description
Technical field
The present invention relates to a kind of BIM Tender Systems.
Background technique
BIM Building Information Model (Building Information Modeling) is the items with construction-engineering project
Basis of the relevant information data as model, carries out the foundation of buildings model.It has visualization, harmony, simulation, optimization
Property and the big feature of figure five can be gone out.It allows design, construction, management to be unified under a platform and work, and is the integrated of architectural engineering
Management environment can make architectural engineering significantly improve efficiency throughout its entire process, largely reduce risk.Because in Earlier designs
Stage can find the various problems that will appear the real construction stage in later period, carry out advanced processing, lay for later period activity firm
Basis.It can also be instructed as feasibility, as the practical guidance of construction to provide reasonable construction party in construction in later period
Case and personnel, the reasonable disposition of materials'use, to realize resource reasonable utilization in maximum magnitude.
Summary of the invention
The object of the present invention is to provide a kind of simple to operate, more intelligence and efficiently by building, structure, decoration,
The specialized engineerings such as reinforcing bar, plumbing, electromechanical equipment integrate a BIM model, realize construction project Life cycle for enterprise
The BIM Tender System of project cost coordinated management, data accumulation and depth analysis integrated management.
A kind of technical solution: BIM Tender System of the present invention, comprising the following steps:
(1) create Revit model: link CAD diagram paper converts CAD diagram paper directly on Revit platform, can be in CAD
Revit model is created on the original position of drawing;
(2) establish BIM buildings model: each professional CAD drawing converted on Revit platform, by two secondary members into
Row intelligent layout establishes BIM buildings model;
(3) adjustment of model is checked: by auxiliary tool, the BIM buildings model of foundation is adjusted and is checked, backman
Tool includes that attribute is checked and component editor;
(4) classification and calculation amount of component: the calculation amount software based on BIM obtains each directly from the BIM buildings model of foundation
Various components are divided into rebar model component classification, the classification of civil engineering model component and electromechanical model component classification by kind component information,
Rebar model component classification, the classification of civil engineering model component and electromechanical model component classification according to respective computation rule and
Classification carries out calculation amount;
(5) data generation table will be calculated and summarized and exported again, and establish 5D relation data in BIM buildings model
Realize that calculate compares more by contract, the analysis of plan and practice of construction data in library.
Further, in step (1) on Revit platform convert CAD diagram paper include axis net conversion, column conversion, beam conversion,
Isolated footing conversion, foundation beam conversion and wall conversion.
Further, two secondary members are carried out intelligent layout in step (2) includes intelligent layout, decoration, thermal-insulating waterproof, zero
Star component and basis.
Further, it includes to set to building, structure, plumbing and ventilation, electromechanics that BIM buildings model is established in step (2)
The modeling of standby, reinforcing bar and decoration.
Further, component editor includes intersection in Liang Zhu, height adjustment, floor segmentation, region three in step (3)
Dimension, floor are three-dimensional, view cuts off, component screens, component is matched colors, component shows hidden, cancel connection, mark option and single-beam setting.
Further, the calculation amount of rebar model component classification includes system parameter, reinforcing bar attribute, reinforcing bar cloth in step (4)
It sets, accounting report, reinforcing bar define and work arrangement.
Compared with the prior art, the present invention has the following advantages: it is simple to operate, more will intelligently and efficiently build,
The specialized engineerings such as structure, decoration, reinforcing bar, plumbing, electromechanical equipment integrate a BIM model, realize that construction project is complete for enterprise
Project cost coordinated management, data accumulation and the depth analysis integrated management of life cycle;Civil engineering, reinforcing bar and each profession of installation
A model is shared, the repetition typing of data is avoided, it is ensured that data are unified, realize resource-sharing, coordinated management;Based on BIM
Calculation amount software, directly obtain various component informations from the BIM buildings model of foundation, various components be divided into rebar model structure
Part classification, the classification of civil engineering model component and electromechanical model component classification are automatically performed quantities calculation in conjunction with various regions computation rule
And inventory, quota project are applied;Can be according to construction flowing water section, plan, time, floor, component isotype, number needed for extracting
According to realization Dynamic Cost Control.
Specific embodiment
In order to deepen understanding of the invention, below we the invention will be further described, which is only used for solving
The present invention is released, is not intended to limit the scope of the present invention..
The present invention is a kind of BIM Tender System, comprising the following steps:
(1) create Revit model: link CAD diagram paper converts CAD diagram paper, in Revit platform directly on Revit platform
Upper conversion CAD diagram paper includes the conversion of axis net, column conversion, beam conversion, isolated footing conversion, foundation beam conversion and wall conversion
Revit model is created on the original position of CAD diagram paper;
(2) establish BIM buildings model: each professional CAD drawing converted on Revit platform, by two secondary members into
Row intelligent layout, it includes intelligent layout, decoration, thermal-insulating waterproof, fragmentary component and basis that two secondary members, which are carried out intelligent layout, is built
Vertical BIM buildings model, establishing BIM buildings model includes to building, structure, plumbing and ventilation, electromechanical equipment, reinforcing bar and decoration
Modeling;
(3) adjustment of model is checked: by auxiliary tool, the BIM buildings model of foundation is adjusted and is checked, backman
Tool include attribute check with component editor, component editor include Liang Zhu in intersection, height adjustment, floor segmentation, area three-dimensional,
Floor is three-dimensional, view cuts off, component screens, component is matched colors, component shows hidden, cancel connection, label option and single-beam are arranged;
(4) classification and calculation amount of component: the calculation amount software based on BIM obtains each directly from the BIM buildings model of foundation
Various components are divided into rebar model component classification, the classification of civil engineering model component and electromechanical model component classification by kind component information,
Rebar model component classification, the classification of civil engineering model component and electromechanical model component classification according to respective computation rule and
Classification carries out calculation amount, wherein the calculation amount of rebar model component classification includes system parameter, reinforcing bar attribute, steel bar arrangement, calculates report
Table, reinforcing bar definition and work arrangement, inventory quota is applied according to embedded software automatically, and calculation amount data and design data is made to implement to join
It is dynamic, it completes engineering metering and works and be applied to the Life cycle data sharing of architectural engineering;
(5) data generation table will be calculated and summarized and exported again, and establish 5D relation data in BIM buildings model
Realize that calculate compares more by contract, the analysis of plan and practice of construction data in library.
Above-mentioned specific embodiment, only technical concept and structure feature to illustrate the invention, it is therefore intended that allow and be familiar with this
The stakeholder of item technology can implement accordingly, but the above content is not intended to limit protection scope of the present invention, all according to this hair
Any equivalent change or modification made by bright Spirit Essence, should all fall under the scope of the present invention.
Claims (6)
1. a kind of BIM Tender System, it is characterised in that: the following steps are included:
(1) create Revit model: link CAD diagram paper converts CAD diagram paper directly on Revit platform, can be former in CAD diagram paper
There is creation Revit model on position;
(2) it establishes BIM buildings model: each professional CAD drawing is converted on Revit platform, two secondary members are subjected to intelligence
It can arrange, establish BIM buildings model;
(3) adjustment of model is checked: by auxiliary tool, the BIM buildings model of foundation is adjusted and is checked, auxiliary tool packet
Attribute is included to check and component editor;
(4) classification and calculation amount of component: the calculation amount software based on BIM directly obtains various structures from the BIM buildings model of foundation
Various components are divided into rebar model component classification, the classification of civil engineering model component and electromechanical model component classification, reinforcing bar by part information
Model component classification, the classification of civil engineering model component and electromechanical model component classification are according to respective computation rule and classification
Carry out calculation amount;
(5) data generation table will be calculated and summarized and exported again, and establish 5D relational database in BIM buildings model,
By contract, the analysis of plan and practice of construction data, realize that calculate compares more.
2. BIM Tender System according to claim 1, it is characterised in that: step is converted on Revit platform in (1)
CAD diagram paper includes the conversion of axis net, column conversion, beam conversion, isolated footing conversion, foundation beam conversion and wall conversion.
3. BIM Tender System according to claim 1, it is characterised in that: two secondary members are carried out intelligence in step (2)
Arrangement includes intelligent layout, decoration, thermal-insulating waterproof, fragmentary component and basis.
4. BIM Tender System according to claim 1 or 3, it is characterised in that: step establishes BIM buildings model in (2)
Include the modeling to building, structure, plumbing and ventilation, electromechanical equipment, reinforcing bar and decoration.
5. BIM Tender System according to claim 1, it is characterised in that: component editor includes Liang Zhu in step (3)
Interior intersection, height adjustment, floor segmentation, area three-dimensional, floor is three-dimensional, view cuts off, component screens, component is matched colors, component is shown
Hidden, cancellation connection, label option and single-beam setting.
6. BIM Tender System according to claim 1, it is characterised in that: rebar model component classification in step (4)
Calculation amount includes system parameter, reinforcing bar attribute, steel bar arrangement, accounting report, reinforcing bar definition and work arrangement.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710871729.XA CN109558606A (en) | 2017-09-25 | 2017-09-25 | BIM Tender System |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710871729.XA CN109558606A (en) | 2017-09-25 | 2017-09-25 | BIM Tender System |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109558606A true CN109558606A (en) | 2019-04-02 |
Family
ID=65862411
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710871729.XA Pending CN109558606A (en) | 2017-09-25 | 2017-09-25 | BIM Tender System |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109558606A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110096800A (en) * | 2019-04-30 | 2019-08-06 | 中国二十冶集团有限公司 | PC rectangular beam and Cast-in-situ Beam realize the method that materials are estimated by BIM |
CN110968907A (en) * | 2019-12-04 | 2020-04-07 | 北京建都设计研究院有限责任公司 | BIM-based implementation method of group real estate construction project |
CN112001012A (en) * | 2020-08-17 | 2020-11-27 | 宇构科技(上海)有限公司 | Building system based on BIM technology preset model |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20110054652A1 (en) * | 2009-08-27 | 2011-03-03 | Heil Duane A | Building Construction Software and System |
CN103246951A (en) * | 2012-12-11 | 2013-08-14 | 中建三局第一建设工程有限责任公司 | Intelligent electromechanical equipment management system and method based on BIM (building information modeling) |
CN106202723A (en) * | 2016-07-10 | 2016-12-07 | 北京工业大学 | A kind of BIM subway work method |
CN106682257A (en) * | 2016-11-16 | 2017-05-17 | 上海建工集团股份有限公司 | Construction facility BIM component library construction method |
-
2017
- 2017-09-25 CN CN201710871729.XA patent/CN109558606A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20110054652A1 (en) * | 2009-08-27 | 2011-03-03 | Heil Duane A | Building Construction Software and System |
CN103246951A (en) * | 2012-12-11 | 2013-08-14 | 中建三局第一建设工程有限责任公司 | Intelligent electromechanical equipment management system and method based on BIM (building information modeling) |
CN106202723A (en) * | 2016-07-10 | 2016-12-07 | 北京工业大学 | A kind of BIM subway work method |
CN106682257A (en) * | 2016-11-16 | 2017-05-17 | 上海建工集团股份有限公司 | Construction facility BIM component library construction method |
Non-Patent Citations (1)
Title |
---|
王淑嫱;周启慧;: "基于BIM软件的工程量计算方法研究" * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110096800A (en) * | 2019-04-30 | 2019-08-06 | 中国二十冶集团有限公司 | PC rectangular beam and Cast-in-situ Beam realize the method that materials are estimated by BIM |
CN110968907A (en) * | 2019-12-04 | 2020-04-07 | 北京建都设计研究院有限责任公司 | BIM-based implementation method of group real estate construction project |
CN112001012A (en) * | 2020-08-17 | 2020-11-27 | 宇构科技(上海)有限公司 | Building system based on BIM technology preset model |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106709660B (en) | BIM-based building design method | |
Zhang et al. | Optimal machine operation planning for construction by Contour Crafting | |
CN106156408A (en) | The building of the classification of a kind of Component-Based Development and combination works in coordination with constructing system and method | |
Astour et al. | BIM-and simulation-based site layout planning | |
CN104102765A (en) | BIM (Building Information Modeling)-based curtain wall parametrization design method | |
KR20130016620A (en) | 3d process management method for bim(building information modeling) | |
CN109544051A (en) | A kind of construction management application platform based on BIM technology application | |
CN109583149A (en) | Super large lid rolling stock section in-depth modernization system and its construction method based on BIM management | |
CN109558606A (en) | BIM Tender System | |
Kim et al. | Construction-specific spatial information reasoning in building information models | |
CN107256310B (en) | Three-dimensional design method for water collecting device of high-level water collecting cooling tower | |
Ji et al. | Integration of parametric geometry into IFC-Bridge | |
CN110978204A (en) | BIM-based intelligent concrete pouring method and related product | |
CN109086490A (en) | A kind of tower crane type selecting method for arranging of the assembled engineering based on BIM technology | |
CN116070311A (en) | BIM forward design method for long and large bridge | |
CN209486723U (en) | A kind of construction management application platform based on BIM technology application | |
Marx et al. | Modeling and simulating spatial requirements of construction activities | |
Han et al. | Simulation of mobile crane operations in 3D space | |
CN101736925A (en) | Modular construction method for nuclear island of nuclear power station | |
Lee et al. | Conceptual design algorithm configuration using generative design techniques | |
CN101748915B (en) | Modularization construction method for nuclear power station nuclear island | |
KR100486670B1 (en) | 3-dimensional graphic data producing system and the method using 2-dimensional graphic drawings | |
CN109816263A (en) | A method of based on Beidou GNSS, BIM construction time labor service, equipment dynamic supervision | |
Baran et al. | Structural Engineering by way of BIM | |
CN105844016B (en) | A method of the proposed building quantity of acquisition based on buildings model cutting |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20190402 |
|
WD01 | Invention patent application deemed withdrawn after publication |