CN107476337A - 明挖地铁装配式车站预制侧墙拼装施工方法 - Google Patents
明挖地铁装配式车站预制侧墙拼装施工方法 Download PDFInfo
- Publication number
- CN107476337A CN107476337A CN201710719147.XA CN201710719147A CN107476337A CN 107476337 A CN107476337 A CN 107476337A CN 201710719147 A CN201710719147 A CN 201710719147A CN 107476337 A CN107476337 A CN 107476337A
- Authority
- CN
- China
- Prior art keywords
- side wall
- prefabricated
- prefabricated side
- construction
- bottom plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/04—Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Environmental & Geological Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
一种明挖地铁装配式车站预制侧墙拼装施工方法,该发明能极大程度地降低传统地铁车站现浇侧墙建设对劳动力的需求及现场建筑周转料的使用,极大减少了施工现场的湿作业工作,减轻施工现场的扬尘、噪音等污染,降低对施工现场周边环境影响。施工现场采用预制侧墙拼装台车,保证侧墙精准对位拼装,提高施工机械化程度,降低工程对劳动力的需求。预制构件的大量使用显著提高相关工程的整体施工质量及施工效率,为产业化施工推广奠定基础。
Description
技术领域
本发明涉及明挖地铁装配式车站预制侧墙拼装施工方法,属于装配式地铁车站施工方法领域。
背景技术
常规地铁明挖车站主体结构侧墙均采用现浇混凝土的方式施工,该种施工方法在通长存在扬尘、噪音等污染,相关混凝土等物料运输对施工现场周边交通环境负担较重,施工现场对建筑周转料需求较高,单位工程机械化程度较低,对现场劳动力需求较高,且现浇混凝土的一些质量通病如蜂窝、麻面、裂缝、孔洞、烂边、烂根等普遍存在。
发明内容
明挖地铁装配式车站预制侧墙拼装施工方法,其特征在于,包括以下步骤:
预制侧墙构件采用模板预制,预制侧墙背面即迎土侧设置四个背面吊环(12),用于侧墙水平起吊、移动、运输;预制侧墙顶端对称设置两个顶端吊环(11),用于侧墙施工现场吊装及用于传递给拼装机起吊;
明挖地铁装配式车站预制侧墙拼装步骤具体如下:
①底板施工:明挖装配整体式结构地铁车站采用桩撑支护体系,基坑开挖支护完成后,由上到下设置三道水平钢支撑,钢支撑分为上、中、下三道,每道钢支撑有多根,均匀排列;首先进行底板(3)施工,底板(3)采用现浇混凝土结构,即底板(3)钢筋绑扎、模板安装完成后,浇筑底板(3)混凝土,钢筋定位模板严格与预制侧墙预留钢筋套筒(13)位置对应一致;在混凝土初凝前,在边导墙(4)与地下二层预制侧墙(1)连接的部位预埋钢板垫块,钢板垫块高程与地下二层预制侧墙(1)底高程相同,边导墙(4)混凝土顶面需进行凿毛处理;底板(3)结构强度达到设计要求,拆除下水平钢支撑(7);
②预制侧墙构件拼装:预制侧墙构件分为地下二层预制侧墙构件(1)和地下一层预制侧墙构件(2);底板(3)施工完成后,将拼装台车用吊车吊至底板(3)上;其中拼装台车和预制侧墙结合的位置正好在边导墙(4)正上方;首先进行地下二层预制侧墙构件(1)的吊装,先将两个钢丝绳套环(15)分别连接侧墙两个顶端吊环(11),然后将两个钢丝绳套环(15)分别穿入扁担梁(14)两端内侧固定套环,最后用龙门吊吊钩同时钩起扁担梁(14)的两端外侧固定套环;吊装准备工作就绪后,将地下二层预制侧墙构件(1)由上方和中间这两道水平钢支撑之间的竖向间隙吊至设计位置上方即导墙上方,拼装台车利用步履机构行走至侧墙吊装位置,悬臂伸出,顶升至扁担梁(14),龙门吊吊钩撤除,完成侧墙由龙门吊至台车的交接;拼装台车对地下二层预制侧墙构件(1)进行移动对位、下落、三维姿态调整工作,将地下二层预制侧墙构件(1)微调至设计位置后与边导墙(4)顶部预留钢筋(10)进行承插,把侧墙下部的灌浆套筒与边导墙(4)上部钢筋对位,顶升机构下落预制侧墙到设计位置,完成第一片侧墙的安装;
③预制侧墙构件的固定:侧墙安装完毕后进行临时固定,台车伸缩机构把悬臂缩回,顶升机构下降使台车处于行走状态,进入下一拼装循环;预制侧墙构件外侧预埋件与围护桩(9)作临时固定;预制侧墙构件与底板边导墙之间设置灌浆层(8),灌浆层(8)及预制侧墙构件底部预埋半灌浆套筒,预制侧墙构件底部预埋半灌浆套筒与现浇边导墙(4)预留钢筋连接,半灌浆套筒中的空隙采用灌浆料进行填充;
④侧墙后浇带施工:预制侧墙构件之间设置现浇混凝土后浇带;
侧墙后浇带采用现浇混凝土施工,施工模板与相邻两块预制侧墙构件上预埋件进行固结,模板采用穿墙止水对拉螺栓加固,不再架设模板背后支撑;
⑤待地下二层结构施工完成后,进行地下一层预制侧墙构件安装及侧墙后浇带施工,步骤与地下二层相同。
附图说明
图1:预制侧墙拼装的明挖地铁装配式车站横断面图
图2:预制侧墙吊装视图
图3:预制侧墙正视图(右)和侧视图(左)
图4:预制侧墙顶视图
图5:预制侧墙底视图
图6:预制侧墙剖面图(A-A)
图7:预制侧墙拼装台车正视图
图中数字表示的意义:
1、地下二层预制侧墙;
2、地下一层预制侧墙;
3、底板;
4、导墙;
5、上水平钢支撑;
6、中水平钢支撑;
7、下水平钢支撑;
8、灌浆层;
9、围护桩;
10、钢筋;
11、顶端吊环;
12、背面吊环;
13、钢筋套筒;
14、扁担梁;
15、钢丝绳套环;
16、钢丝绳;
具体实施方式
下面结合附图和实施例,对本发明型的具体实施方式作进一步详细描述。
明挖地铁装配式车站预制侧墙起吊技术,其特征在于,包括以下步骤:
①底板施工:明挖装配整体式结构地铁车站采用桩撑支护体系,基坑开挖支护完成后,由上到下设置三道水平钢支撑(5)、(6)、(7)(钢支撑分为上、中、下三道,每道钢支撑有多根,均匀排列)。首先进行底板(3)施工,底板(3)采用现浇混凝土结构,即底板(3)钢筋绑扎、模板安装完成后,浇筑底板(3)混凝土,钢筋定位模板严格与预制侧墙预留钢筋套筒(13)位置对应一致。在混凝土初凝前,在边导墙(4)与地下二层预制侧墙(1)连接的部位预埋钢板垫块,钢板垫块高程与地下二层预制侧墙(1)底高程相同,边导墙(4)混凝土顶面需进行凿毛处理。底板(3)结构强度达到设计要求,拆除下水平钢支撑(7)。
②预制侧墙构件拼装:预制侧墙构件分为地下二层预制侧墙构件(1)和地下一层预制侧墙构件(2)。底板(3)施工完成后,将拼装台车用吊车吊至底板(3)上(其中拼装台车和预制侧墙结合的位置正好在边导墙(4)正上方)。首先进行地下二层预制侧墙构件(1)的吊装,先将两个钢丝绳套环(15)分别连接侧墙两个顶端吊环(11),然后将两个钢丝绳套环(15)分别穿入扁担梁(14)两端内侧固定套环,最后用龙门吊吊钩同时钩起扁担梁(14)的两端外侧固定套环。吊装准备工作就绪后,将地下二层预制侧墙构件(1)由上方两道水平钢支撑(5)、(6)之间的竖向间隙吊至设计位置上方(即导墙上方),拼装台车利用步履机构行走至侧墙吊装位置,悬臂伸出,顶升至扁担梁(14),龙门吊吊钩撤除,完成侧墙由龙门吊至台车的交接。拼装台车对地下二层预制侧墙构件(1)进行移动对位、下落、三维姿态调整工作,将地下二层预制侧墙构件(1)微调至设计位置后与边导墙(4)顶部预留钢筋(10)进行承插,把侧墙下部的灌浆套筒与边导墙(4)上部钢筋精确对位,顶升机构下落预制侧墙到设计位置,完成第一片侧墙的安装。
③预制侧墙构件的固定:侧墙安装完毕后进行临时固定,台车伸缩机构把悬臂缩回,顶升机构下降使台车处于行走状态,进入下一拼装循环。预制侧墙构件外侧预埋件与围护桩(9)作临时固定。预制侧墙构件与底板边导墙之间设置灌浆层(8),灌浆层(8)及预制侧墙构件底部预埋半灌浆套筒,预制侧墙构件底部预埋半灌浆套筒与现浇边导墙(4)预留钢筋连接,套筒中的空隙采用高强度灌浆料进行填充。
④侧墙后浇带施工:预制侧墙构件之间设置现浇混凝土后浇带。
侧墙后浇带采用现浇混凝土施工,施工模板与相邻两块预制侧墙构件上预埋件进行固结,模板采用穿墙止水对拉螺栓加固,不再架设模板背后支撑。
⑤待地下二层结构施工完成后,进行地下一层预制侧墙构件安装及侧墙后浇带施工,步骤与地下二层相同。
Claims (3)
1.明挖地铁装配式车站预制侧墙拼装施工方法,其特征在于,包括以下步骤:
预制侧墙构件采用模板预制,预制侧墙背面即迎土侧设置四个背面吊环(12),用于侧墙水平起吊、移动、运输;预制侧墙顶端对称设置两个顶端吊环(11),用于侧墙施工现场吊装及用于传递给拼装机起吊;
明挖地铁装配式车站预制侧墙拼装步骤具体如下:
①底板施工:明挖装配整体式结构地铁车站采用桩撑支护体系,基坑开挖支护完成后,由上到下设置三道水平钢支撑,钢支撑分为上、中、下三道,每道钢支撑有多根,均匀排列;首先进行底板(3)施工,底板(3)采用现浇混凝土结构,即底板(3)钢筋绑扎、模板安装完成后,浇筑底板(3)混凝土,钢筋定位模板严格与预制侧墙预留钢筋套筒(13)位置对应一致;在混凝土初凝前,在边导墙(4)与地下二层预制侧墙(1)连接的部位预埋钢板垫块,钢板垫块高程与地下二层预制侧墙(1)底高程相同,边导墙(4)混凝土顶面需进行凿毛处理;底板(3)结构强度达到设计要求,拆除下水平钢支撑(7);
②预制侧墙构件拼装:预制侧墙构件分为地下二层预制侧墙构件(1)和地下一层预制侧墙构件(2);底板(3)施工完成后,将拼装台车用吊车吊至底板(3)上;其中拼装台车和预制侧墙结合的位置正好在边导墙(4)正上方;首先进行地下二层预制侧墙构件(1)的吊装,先将两个钢丝绳套环(15)分别连接侧墙两个顶端吊环(11),然后将两个钢丝绳套环(15)分别穿入扁担梁(14)两端内侧固定套环,最后用龙门吊吊钩同时钩起扁担梁(14)的两端外侧固定套环;吊装准备工作就绪后,将地下二层预制侧墙构件(1)由上方和中间这两道水平钢支撑之间的竖向间隙吊至设计位置上方即导墙上方,拼装台车利用步履机构行走至侧墙吊装位置,悬臂伸出,顶升至扁担梁(14),龙门吊吊钩撤除,完成侧墙由龙门吊至台车的交接;拼装台车对地下二层预制侧墙构件(1)进行移动对位、下落、三维姿态调整工作,将地下二层预制侧墙构件(1)微调至设计位置后与边导墙(4)顶部预留钢筋(10)进行承插,把侧墙下部的灌浆套筒与边导墙(4)上部钢筋对位,顶升机构下落预制侧墙到设计位置,完成第一片侧墙的安装;
③预制侧墙构件的固定:侧墙安装完毕后进行临时固定,台车伸缩机构把悬臂缩回,顶升机构下降使台车处于行走状态,进入下一拼装循环;预制侧墙构件外侧预埋件与围护桩(9)作临时固定;预制侧墙构件与底板边导墙之间设置灌浆层(8),灌浆层(8)及预制侧墙构件底部预埋半灌浆套筒,预制侧墙构件底部预埋半灌浆套筒与现浇边导墙(4)预留钢筋连接,半灌浆套筒中的空隙采用灌浆料进行填充;
④侧墙后浇带施工:预制侧墙构件之间设置现浇混凝土后浇带;侧墙后浇带采用现浇混凝土施工,施工模板与相邻两块预制侧墙构件上预埋件进行固结,模板采用穿墙止水对拉螺栓加固,不再架设模板背后支撑;
⑤待地下二层结构施工完成后,进行地下一层预制侧墙构件安装及侧墙后浇带施工,步骤与地下二层相同。
2.根据权利要求1所述的明挖地铁装配式车站预制侧墙拼装施工方法,其特征在于:拼装设备为预制侧墙拼装台车,起重设备为2台50t龙门吊,预制侧墙构件最大单重为34.5t。
3.根据权利要求1所述的明挖地铁装配式车站预制侧墙拼装施工方法,其特征在于:步骤③中预制侧墙构件与底部钢筋采用半灌浆套筒进行连接,属于一级接头;预制侧墙构件与底板边导墙之间设置15~20mm灌浆层。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710719147.XA CN107476337A (zh) | 2017-08-21 | 2017-08-21 | 明挖地铁装配式车站预制侧墙拼装施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710719147.XA CN107476337A (zh) | 2017-08-21 | 2017-08-21 | 明挖地铁装配式车站预制侧墙拼装施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107476337A true CN107476337A (zh) | 2017-12-15 |
Family
ID=60602008
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710719147.XA Pending CN107476337A (zh) | 2017-08-21 | 2017-08-21 | 明挖地铁装配式车站预制侧墙拼装施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107476337A (zh) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108590680A (zh) * | 2018-05-04 | 2018-09-28 | 北京市政建设集团有限责任公司 | 一种盾构始发井基坑竖向分段浇筑的施工方法 |
CN108867651A (zh) * | 2018-07-26 | 2018-11-23 | 江苏兴厦建设工程集团有限公司 | 一种用于基坑降水的透水混凝土井管安装装置 |
CN109183848A (zh) * | 2018-08-10 | 2019-01-11 | 广东省建工设计院有限公司 | 一种隧道设计和建设方法 |
CN109538245A (zh) * | 2018-12-04 | 2019-03-29 | 中铁十二局集团有限公司 | 一种无柱直墙拱顶地铁车站模板台车及其施工方法 |
CN110042867A (zh) * | 2019-04-29 | 2019-07-23 | 中铁第四勘察设计院集团有限公司 | 全复合装配式地铁车站预制构件机械化运输系统及方法 |
CN110318426A (zh) * | 2019-08-07 | 2019-10-11 | 哈尔滨工业大学 | 一种装配式钢-混凝土混合结构地铁车站及装配方法 |
CN111236309A (zh) * | 2020-02-28 | 2020-06-05 | 无锡地铁集团有限公司 | 一种装配式地下车站预制预应力板的施工方法 |
CN114687377A (zh) * | 2020-12-30 | 2022-07-01 | 上海建工二建集团有限公司 | 限时条件下大底板模块化结构及施工方法 |
CN114837224A (zh) * | 2022-06-08 | 2022-08-02 | 青岛中科坤泰装配建筑科技有限公司 | 一种地下车站多层预制墙体结构及其竖转安装工艺 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009209637A (ja) * | 2008-03-06 | 2009-09-17 | Aoshima Architects & Engineers Inc | 埋設構築物の構築方法 |
CN103912010A (zh) * | 2014-04-04 | 2014-07-09 | 北京城建设计发展集团股份有限公司 | 明挖预制装配式地下结构施工方法 |
CN104153389A (zh) * | 2014-08-11 | 2014-11-19 | 中铁建大桥工程局集团第六工程有限公司 | 预制装配式地铁车站施工方法 |
CN106223360A (zh) * | 2016-07-07 | 2016-12-14 | 中铁六局集团有限公司 | 采用桩撑支护体系的明挖装配整体式结构地铁站施工方法 |
-
2017
- 2017-08-21 CN CN201710719147.XA patent/CN107476337A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009209637A (ja) * | 2008-03-06 | 2009-09-17 | Aoshima Architects & Engineers Inc | 埋設構築物の構築方法 |
CN103912010A (zh) * | 2014-04-04 | 2014-07-09 | 北京城建设计发展集团股份有限公司 | 明挖预制装配式地下结构施工方法 |
CN104153389A (zh) * | 2014-08-11 | 2014-11-19 | 中铁建大桥工程局集团第六工程有限公司 | 预制装配式地铁车站施工方法 |
CN106223360A (zh) * | 2016-07-07 | 2016-12-14 | 中铁六局集团有限公司 | 采用桩撑支护体系的明挖装配整体式结构地铁站施工方法 |
Non-Patent Citations (1)
Title |
---|
铁道部华北铁路工程局: "《装吊工》", 31 December 1965, 人民铁道出版社 * |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108590680A (zh) * | 2018-05-04 | 2018-09-28 | 北京市政建设集团有限责任公司 | 一种盾构始发井基坑竖向分段浇筑的施工方法 |
CN108867651A (zh) * | 2018-07-26 | 2018-11-23 | 江苏兴厦建设工程集团有限公司 | 一种用于基坑降水的透水混凝土井管安装装置 |
CN109183848A (zh) * | 2018-08-10 | 2019-01-11 | 广东省建工设计院有限公司 | 一种隧道设计和建设方法 |
CN109183848B (zh) * | 2018-08-10 | 2019-06-21 | 广东省建工设计院有限公司 | 一种隧道设计和建设方法 |
CN109538245A (zh) * | 2018-12-04 | 2019-03-29 | 中铁十二局集团有限公司 | 一种无柱直墙拱顶地铁车站模板台车及其施工方法 |
CN109538245B (zh) * | 2018-12-04 | 2020-05-15 | 中铁十二局集团有限公司 | 一种无柱直墙拱顶地铁车站模板台车的施工方法 |
CN110042867B (zh) * | 2019-04-29 | 2023-11-10 | 中铁第四勘察设计院集团有限公司 | 全复合装配式地铁车站预制构件机械化运输系统及方法 |
CN110042867A (zh) * | 2019-04-29 | 2019-07-23 | 中铁第四勘察设计院集团有限公司 | 全复合装配式地铁车站预制构件机械化运输系统及方法 |
CN110318426A (zh) * | 2019-08-07 | 2019-10-11 | 哈尔滨工业大学 | 一种装配式钢-混凝土混合结构地铁车站及装配方法 |
CN110318426B (zh) * | 2019-08-07 | 2024-01-09 | 哈尔滨工业大学 | 一种装配式钢-混凝土混合结构地铁车站及装配方法 |
CN111236309A (zh) * | 2020-02-28 | 2020-06-05 | 无锡地铁集团有限公司 | 一种装配式地下车站预制预应力板的施工方法 |
CN114687377A (zh) * | 2020-12-30 | 2022-07-01 | 上海建工二建集团有限公司 | 限时条件下大底板模块化结构及施工方法 |
CN114687377B (zh) * | 2020-12-30 | 2023-08-08 | 上海建工二建集团有限公司 | 限时条件下大底板模块化结构及施工方法 |
CN114837224A (zh) * | 2022-06-08 | 2022-08-02 | 青岛中科坤泰装配建筑科技有限公司 | 一种地下车站多层预制墙体结构及其竖转安装工艺 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107476337A (zh) | 明挖地铁装配式车站预制侧墙拼装施工方法 | |
CN106223360B (zh) | 采用桩撑支护体系的明挖装配整体式结构地铁站施工方法 | |
CN104695337B (zh) | 自提升滑翻施工系统及施工方法 | |
CN108193608A (zh) | 移动式模架现浇道路排水沟及施工方法 | |
CN107476341A (zh) | 采用装配整体式结构地铁车站预制板拼装方法 | |
CN106869548B (zh) | 一种中心柱框架装配式地下停车场结构体系与施工方法 | |
CN107905114A (zh) | 一种特大跨径连续刚构拱桥的施工方法 | |
CN104532754B (zh) | 一种预应力混凝土箱梁封端模板施工方法 | |
CN110863498A (zh) | 一种紧邻地铁站的深基坑组合支护施工方法 | |
CN206512581U (zh) | 横向预应力全宽钢筋混凝土桥面板钢板组合梁 | |
CN105525753A (zh) | 一种构造柱与主体结构同时施工的方法及结构 | |
CN109487955A (zh) | 一种预制混凝土柱原位现浇施工方法 | |
CN107476338A (zh) | 预制纵梁拼装方法 | |
CN106930315B (zh) | 一种移动塔吊基础结构及施工方法 | |
CN107100083A (zh) | 一种t型高墩现浇盖梁支模结构及施工方法 | |
CN109505309A (zh) | 一种管廊节段的移位系统及应用移位系统的管廊安装方法 | |
CN111365033A (zh) | 一种用于城门洞形隧洞的快速衬砌方法及模板 | |
CN109457814B (zh) | 基于贝雷架结构的高耸及大直径建筑物顶盖施工方法 | |
JP6374353B2 (ja) | 橋梁の架設方法 | |
CN103993739B (zh) | 造粒塔喷淋层劲性梁的施工方法 | |
CN212054734U (zh) | 一种用于城门洞形隧洞快速衬砌的模板 | |
CN106948267A (zh) | 一种牌坊门楼式桥梁索塔塔柱同步施工方法 | |
CN205243529U (zh) | 隧道暗挖衬砌施工台车 | |
CN108792963A (zh) | 一种用于高层屋面构架的空间钢桁架式塔吊附墙支座方法 | |
CN104948206B (zh) | 一种用于城门洞型斜井混凝土浇筑的滑模台车 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20171215 |
|
WD01 | Invention patent application deemed withdrawn after publication |