CN102644362A - 一种建筑装饰抹灰施工方法 - Google Patents

一种建筑装饰抹灰施工方法 Download PDF

Info

Publication number
CN102644362A
CN102644362A CN2012101188292A CN201210118829A CN102644362A CN 102644362 A CN102644362 A CN 102644362A CN 2012101188292 A CN2012101188292 A CN 2012101188292A CN 201210118829 A CN201210118829 A CN 201210118829A CN 102644362 A CN102644362 A CN 102644362A
Authority
CN
China
Prior art keywords
floating screed
metope
plastering
saw blade
mortar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012101188292A
Other languages
English (en)
Other versions
CN102644362B (zh
Inventor
李少强
曾晓镇
庞惠元
谭紫文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Guangtian group Limited by Share Ltd
Original Assignee
SHENZHEN GUANGTIAN DECORATION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHENZHEN GUANGTIAN DECORATION GROUP CO Ltd filed Critical SHENZHEN GUANGTIAN DECORATION GROUP CO Ltd
Priority to CN201210118829.2A priority Critical patent/CN102644362B/zh
Publication of CN102644362A publication Critical patent/CN102644362A/zh
Priority to PCT/CN2012/083952 priority patent/WO2013155833A1/zh
Priority to US14/395,792 priority patent/US9255413B2/en
Application granted granted Critical
Publication of CN102644362B publication Critical patent/CN102644362B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/02Coverings or linings, e.g. for walls or ceilings of plastic materials hardening after applying, e.g. plaster
    • E04F13/04Bases for plaster
    • E04F13/045Means for fastening plaster-bases to a supporting structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/02Implements for finishing work on buildings for applying plasticised masses to surfaces, e.g. plastering walls
    • E04F21/04Patterns or templates; Jointing rulers
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B41/00After-treatment of mortars, concrete, artificial stone or ceramics; Treatment of natural stone
    • C04B41/009After-treatment of mortars, concrete, artificial stone or ceramics; Treatment of natural stone characterised by the material treated
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/02Coverings or linings, e.g. for walls or ceilings of plastic materials hardening after applying, e.g. plaster
    • E04F13/04Bases for plaster
    • E04F13/047Plaster carrying meshes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/02Implements for finishing work on buildings for applying plasticised masses to surfaces, e.g. plastering walls
    • E04F21/06Implements for applying plaster, insulating material, or the like
    • E04F21/08Mechanical implements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/02Implements for finishing work on buildings for applying plasticised masses to surfaces, e.g. plastering walls
    • E04F21/16Implements for after-treatment of plaster or the like before it has hardened or dried, e.g. smoothing-tools, profile trowels

Abstract

本发明提供一种建筑装饰抹灰施工方法,包括以下步骤:(1)基层处理,(2)冲筋,(3)抹灰,(4)打磨墙面;所述步骤(2)冲筋是指:根据所需抹灰高度,进行施工定位放线,根据放线高度沿所述步骤(1)基层处理过的墙面纵向安装冲筋模板,相邻冲筋模板之间的横向间隔为1.3米至1.8米。所述步骤(4)打磨墙面是指:所述步骤(3)抹灰后的墙面静置12小时至24小时,直至所述墙面上的抹灰砂浆呈半干紧密的硬化状态,用锯片靠尺以其锯齿贴着所述砂浆顺着相邻的两个所述冲筋模板打磨至平整。本发明可提高抹灰施工效率、保证施工质量,进一步的可以配合机械化施工、提高大面积施工效率,克服以往人工施工效率低下、对施工人员技术要求高的缺陷。

Description

一种建筑装饰抹灰施工方法
技术领域
本发明涉及建筑装饰的内墙抹灰施工方法。 
背景技术
现有建筑装饰工程的抹灰施工流程一般是:基层处理;吊垂直,找规矩,放线,抹灰饼,墙面冲筋;人工抹灰,修补预留孔洞、电箱槽、盒等,收刮抹平;回收废料。采用原有的施工工艺存在以下弊端: 
(1)传统的墙面冲筋方法对抹灰工人技术要求较高,非熟练工作业时不仅会影响抹灰饼的速度,而且冲筋的精准度也难以保证,继而使墙面的平整度、水平度不易达到规范要求,墙体的观感度也不够理想,更重要的是,该冲筋过程无法与机械化施工进行匹配,难以达到大幅提高施工效率的要求; 
(2)人工抹灰或机械喷浆后,进行墙面磨平,抹平过程中,由于木抹子的旋转打磨,使砂浆内部触碰挤压,导致水份往外渗出,正因为跟内墙砖体接触的水份流失,所以会过早吸收砂浆中的水份,导致砂浆收缩出现“空鼓”,从而出现墙面开裂,砂浆脱落等现象;且需要大量的技术人员,施工耗时较长,影响工程进度,施工过程繁琐复杂,影响施工效率。 
发明内容
本发明要解决的技术问题是提供一种提高抹灰施工效率、保证施工质量、摆脱对施工人员技术水平的依赖的抹灰施工方法,进一步的可以配合机械化施工。 
为解决上述技术问题,本发明提供一种建筑装饰抹灰施工方法,包括以下步骤: 
(1)基层处理; 
(2)冲筋; 
(3)抹灰; 
(4)打磨墙面; 
所述步骤(2)冲筋是指:根据所需抹灰高度,进行施工定位放线,根据放线高度沿所述步骤(1)基层处理过的墙面纵向安装冲筋模板,相邻冲筋模板之间的横向间隔为1.3米至1.8米; 
所述步骤(4)打磨墙面是指:所述步骤(3)抹灰后的墙面静置12小时至24小时,直至所述墙面上的抹灰砂浆呈半干紧密的硬化状态,用锯片靠尺以其锯齿贴着所述砂浆顺着相邻的两个所述冲筋模板打磨至平整。 
所述步骤(1)基层处理是指:清洁墙面并待其干燥;在所述墙面上刷上抹面砂浆;在抹面砂浆初凝时将玻璃纤维网格布绷紧后贴于抹面砂浆上,将所述玻璃纤维网格布压入所述抹面砂浆表层直至微见其轮廓;在玻璃纤维网格布上刷抹面砂浆至将其完全覆盖;待抹面砂浆硬化。 
所述步骤(3)抹灰是指机械喷浆,过程如下:向冲筋完成的墙面洒水;用砂浆喷浆机将抹灰砂浆喷向所述墙面,直至覆盖冲筋模板、微见冲筋模板外沿轮廓;用普通靠尺贴着冲筋模板收刮;人工修补平整预留孔洞或预留位置。 
所述步骤(2)的冲筋模板由可与墙面连接的底座、冲筋板和连接所述底座与冲筋板的连接杆构成;所述底座有一个能让连接杆垂直于底座插入的安装通孔,所述冲筋板靠近墙面的那一侧面上沿长度方向设有能使连接杆的另一端垂直插入的卡槽,同一冲筋板至少连接两个所述连接杆和两个所述底座。 
所述冲筋模板安装过程如下:沿所述墙面纵向每隔50厘米用胶水粘贴所述底座;所述连接杆一端插入所述安装通孔,根据放线高度剪取相应长度的连接杆,将所述卡槽对准连接杆另一端按下。 
所述底座由一个小圆饼和一个可与墙面连接的大圆饼同轴一体成型,所述安装通孔与所述大圆饼和小圆饼同轴;所述安装通孔靠近冲筋板端有向内侧突起的卡脚; 
所述大圆饼沿周向均匀分布4个所述辅助通孔,所述冲筋板由沿长度方向对称折弯的折板和所述卡槽一体成型,所述卡槽设于所述折板的转角内凹面处并沿长度方向延伸;所述折板两侧分别设有沿长度方向分布的多个通孔。 
所述连接杆上沿长度方向均匀分布有垂直于连接杆长度方向、闭合的多个环状凹痕。 
所述步骤(4)的锯片靠尺包括沿长度方向设有锯齿的锯片及与所述锯片相连的夹持部。 
所述夹持部的横截面形状近似为等腰三角形,其顶角处张开为两片夹持锯片的夹板,所述夹板和锯片以螺栓紧固,所述夹持部与锯片长度相适配。 
所述锯片的长度为1.7米至2.3米,所述锯齿距离夹板邻近端端部的距 离为30毫米至70毫米;所述锯片被夹持部分的宽度为40毫米至60毫米;所述夹持部远离锯片的端面宽度为2厘米。 
本发明的建筑装饰抹灰施工方法的冲筋作业所用的冲筋装置安装、使用方便,对施工人员技术要求不高,同时保证墙面垂直度和平整度,摆脱对施工者的技术经验的依赖,冲筋完成后冲筋装置不需取出,留在墙面中即可,免除对原来位置的修补,节省工序,提高效率;该冲筋装置可配合机械喷浆作业,提高了抹灰效率;机械喷浆后不采用以往的人工抹平,而是让抹灰砂浆静置12小时至24小时,直至抹灰砂浆呈半干紧密的硬化状态,利用砂浆的自然凝固,解决空鼓问题,再用锯片靠尺进行打磨。与人工抹平相比,锯片靠尺打磨面积更大,适应大面积施工,操作简便,对施工人员技术要求不高,对施工人员数量要求更少。 
附图说明
下面结合附图和具体实施方式,对本发明作进一步地详细说明: 
图1为本发明冲筋步骤所用冲筋模板的主视图。 
图2为本发明冲筋步骤所用冲筋模板的左视图。 
图3为本发明冲筋步骤所用冲筋模板的俯视剖视示意图。 
图4为本发明打磨墙面步骤所用锯片靠尺的主视图。 
图5为本发明打磨墙面步骤所用锯片靠尺的左视图。 
图6为本发明打磨墙面步骤所用锯片靠尺的仰视图。 
图7为本发明建筑装饰抹灰施工方法流程示意图。 
具体实施方式
本发明用到新设计的工具——冲筋模板和锯片靠尺,使用冲筋模板能 提高冲筋效率,降低对施工人员的技术水平要求;用锯片靠尺打磨墙面,能有效解决空鼓问题,使用简便快捷,降低了对施工人员技术要求以及数量要求,对节省人力成本、时间成本有重大意义。图7所示为本发明建筑装饰抹灰施工方法流程示意图。 
本发明包括以下流程:基层处理;冲筋;机械喷浆;打磨墙面。 
以往基层处理时,防开裂的钢丝网固定是用钉子固定的,抹上砂浆后将钉子覆盖,留在墙面上的钉子以及钢丝网都易生锈,会造成墙面不同程度的损坏;为解决固定钢丝网的钉子生锈问题,本发明提供了一种更能保证抹灰施工墙面安全可靠、耐用、保温防水的砂浆贴压网格布的方法,摒弃了传统的钉子固定钢丝网。这既解决了钉子生锈的问题,又保证了墙面防开裂的功能。 
所述基层处理过程如下:(1)清洁墙面并待其干燥;(2)在所述墙面上刷上抹面砂浆;(3)在抹面砂浆初凝时将玻璃纤维网格布绷紧后贴于抹面砂浆上,将所述玻璃纤维网格布压入所述抹面砂浆表层直至微见其轮廓;(4)在玻璃纤维网格布上刷抹面砂浆至将其完全覆盖;(5)待抹面砂浆硬化。 
所述玻璃纤维网格布化学稳定性好,抗碱、耐酸、耐水、耐水泥浸蚀;物理性能好,高强度、高模量、重量轻;尺寸稳定性好、硬挺、平整、不易收缩变形、定位性佳;保温、绝缘、抗裂,其网眼尺寸为5mm×5mm,单张网格布长度不宜大于6米。铺贴遇有搭接时,搭接宽度至少为10厘米。步骤(3)中将所述玻璃纤维网格布压入抹面砂浆时,用抹子从中间向四周把玻璃纤维网格布压入砂浆的表层,要平整压实,严禁玻璃纤维网格布皱褶。抹面砂浆切忌不停揉搓,以免形成空鼓。 
抹面砂浆硬化后,即可进行冲筋作业。 
如图1至3所示为冲筋所用的冲筋模板,它由可固定在墙面上的底座10、冲筋板30和连接所述底座10与冲筋板30的连接杆20构成,同一冲筋板30至少连接两个所述连接杆20和两个所述底座10,所述底座10、冲筋板30和连接杆20均优选为回收塑料一体成型,节约成本,环保,也可以由其它材料制成。 
所述底座10有一个能让连接杆20垂直于底座10插入的安装通孔11,为使连接杆20更牢固地安装于底座10,所述底座10由一个小圆饼18和一个可与墙面连接的大圆饼17同轴一体成型,安装通孔11与所述大圆饼17和小圆饼18同轴,安装通孔11靠近冲筋板30端有向内侧突起的卡脚12,如图3所示,所述卡脚12用于固定连接杆20,使连接杆20垂直于底座10。所述大圆饼的直径为60毫米、高度为1毫米至2毫米,小圆饼的直径为9毫米、高度为3毫米。冲筋开始时,将底座10粘贴在墙面上,使大圆饼17与墙面相连,由于墙面情况不同,为使底座10更牢固地粘贴在墙面上,大圆饼17设有至少一个辅助通孔13,其形状为圆形,也可为其他形状,优选沿周向均布多个辅助通孔13,图2中所示为4个。 
所述冲筋板30用于定位抹灰高度,其靠近墙面的那一侧面设有能使连接杆20垂直插入的卡槽33。冲筋板30由沿长度方向对称折弯的折板31和卡槽33一体成型,折弯的角度为90°或60°不等,所述卡槽33设于折板31的转角内凹面处并沿长度方向延伸。为使避免卡槽33与折板31之间留有空隙造成空鼓,折板31的两侧分别设有沿长度方向均匀分布的多个通孔32,在图1和图2中其形状为六边形,砂浆可通过通孔32填充卡槽33与折板31之间。折板31两侧靠近底座10的端面与卡槽33开口的端部位于 同一平面。所述折板31厚度为1毫米至2毫米,每侧的宽度为1厘米至2厘米。 
所述连接杆20沿长度方向均匀分布有垂直于所述连接杆20长度方向、闭合的多个环状凹痕21,如图3所示,连接杆20一端垂直地插入底座10的安装通孔11中,卡脚12夹持连接杆20上的凹痕21以将其固定;另一端垂直地插入冲筋板30的卡槽33中,所述卡槽33夹持其上的凹痕21以固定。在冲筋作业时连接杆20的长度可根据抹灰厚度剪取。 
冲筋的过程如下:根据所需抹灰高度,进行施工定位放线,在抹面砂浆处理过的墙面纵向每隔50厘米用胶水粘贴所述底座10;所述连接杆20一端插入所述安装通孔11,根据放线高度剪取相应长度的连接杆20,将所述卡槽33对准连接杆20另一端按压,横向每隔1.3米至1.8米安装一个冲筋模板。 
本发明的冲筋作业对工人的技术要求较低,结构简单,安装方便,整个冲筋作业仅由冲筋模板独立完成,不需要再借助别的工具或砂浆材料,安装也非常方便快捷。由于冲筋模板相距较近,抹灰高度容易调适统一,施工效率提高。不需再担心工人的技术或碰撞使灰饼、冲筋变形走样影响抹灰高度。底座、连接杆以及冲筋板均由回收塑料一体成型,既环保又节约成本,无公害,无污染,有“绿色建筑”的公益效应。抹灰完成后埋在砂浆中即可,不需取出,简化流程,减少施工时间。以往冲筋完成后2小时才能开始抹灰,本发明冲筋完成后即可进行抹灰,提高施工速度。 
冲筋完成后,进行下一步骤——抹灰。抹灰可采用人工抹灰,也可采用机械喷浆,本实施例采用的是机械喷浆。 
机械喷浆的过程如下:向冲筋完成的墙面洒水;用砂浆喷浆机将抹灰 砂浆喷向所述墙面,直至覆盖冲筋模板、微见冲筋模板外沿轮廓;用普通靠尺贴着冲筋模板收刮;人工修补平整预留孔洞或预留位置,例如配电箱、槽、盒等。
本实施例中机械喷浆所用的砂浆喷浆机型号为TURBOSOL POLIT。砂浆通过砂浆喷浆机、输送管、喷头可直接喷涂在已进行基层处理的墙面上。喷浆厚度以覆盖冲筋模板、微见模板外沿轮廓为宜。用普通靠尺贴着冲筋模板收刮一遍,多余材料可回收,空缺的墙面可人工填补或机械重复喷涂,重复以上步骤以保证砂浆喷涂充分,砂浆稍有突出效果最佳,尽量避免空缺。 
人工抹灰需要大量的技术人员,施工耗时较长,影响工程进度,且施工过程繁琐复杂,影响施工效率。 
与人工抹灰相比,机械喷浆效率大大提高,且能适应大面积施工,降低对施工人员数量要求,节省人力成本。 
与现有技术不同,本发明取消了抹灰作业的人工抹平程序,增加了打磨墙面步骤。由于抹灰完成后,抹灰砂浆呈初凝状态,可塑性强,人工抹平过程中,由于木沫子的旋转打磨,使砂浆内部触碰挤压,导致水份往外渗出,正因为跟内墙砖体接触的水份流失,所以会过早吸收砂浆中的水份,导致砂浆收缩出现“空鼓”,从而出现墙面开裂,砂浆脱落等现象。为此,本发明让抹灰砂浆静置12小时至24小时,直至抹灰砂浆呈半干紧密的硬化状态,利用砂浆的自然凝固,解决空鼓问题,再用锯片靠尺进行打磨。与人工抹平相比,锯片靠尺打磨面积更大,适应大面积施工,操作简便,对施工人员技术要求不高,对施工人员数量要求更少,更能避免空鼓。不论是人工抹灰还是机械喷浆,均可进行打磨作业。 
如图4至6所示为墙面打磨用的锯片靠尺的结构图,它包括锯片300,夹持锯片300的夹持部200和紧固所述锯片300与夹持部200的螺栓100。沿锯片300的长度方向设有锯齿,该锯齿为通用锯齿。所述锯片300长度为1.7米至2.3米,在本实施例中长度优选为2米,以便配合间距为1.3米至1.8米的冲筋模板使用,锯片300宽度为0.1米至0.2米,厚度为1毫米。 
为方便施工,一个夹持部200连接在锯片300相对锯齿的另一侧,并且沿长度方向设置,夹持部200的长度优选与锯片300相适配。所述夹持部200是横截面形状近似等腰三角形的铝合金板材,其顶角处张开为两片夹持锯片300的夹板210。其底边,也就是夹持部200远离锯片300的端面的宽度为2厘米,以方便工人紧握。所述锯片300的锯齿距离夹板210端部的距离为30毫米至70毫米,锯片300被夹板210夹持部分的宽度为40毫米至60毫米。在本实施例中,锯片300的宽度为0.1米,锯片300的锯齿距离夹板210邻近端端部的距离为50毫米,锯片300被夹持部分的宽度为50毫米。 
为使锯片300固定在夹持部200的夹板210中,至少2个螺栓100(配相应的螺母)紧固所述夹板210和锯片300,将锯片300夹紧,如图4所示,所述螺栓100有两个,分别设置在夹持部200两端,一个靠近锯齿,一个远离锯齿,可实现固定作用。 
打磨墙面过程如下:机械喷浆完成后,抹灰砂浆静置12小时至24小时,待抹灰砂浆晾干至半干紧密的硬化状态,施工人员握着夹持部200,锯齿贴着抹灰砂浆,锯片300与墙面成30°~60°倾斜,顺着相邻的两根冲筋模板由下至上打磨至平整。 
经检查,墙面平整度和阴阳角垂直度均符合国家标准,墙面无空鼓、 裂纹和水印。 

Claims (10)

1.一种建筑装饰抹灰施工方法,其特征在于,包括以下步骤:
(1)基层处理;
(2)冲筋;
(3)抹灰;
(4)打磨墙面;
所述步骤(2)冲筋是指:根据所需抹灰高度,进行施工定位放线,根据放线高度沿所述步骤(1)基层处理过的墙面纵向安装冲筋模板,相邻冲筋模板之间的横向间隔为1.3米至1.8米;
所述步骤(4)打磨墙面是指:所述步骤(3)抹灰后的墙面静置12小时至24小时,直至所述墙面上的抹灰砂浆呈半干紧密的硬化状态,用锯片靠尺以其锯齿贴着所述砂浆顺着相邻的两个所述冲筋模板打磨至平整。
2.根据权利要求1所述的一种建筑装饰抹灰施工方法,其特征在于:所述步骤(1)基层处理是指:清洁墙面并待其干燥;在所述墙面上刷上抹面砂浆;在抹面砂浆初凝时将玻璃纤维网格布绷紧后贴于抹面砂浆上,将所述玻璃纤维网格布压入所述抹面砂浆表层直至微见其轮廓;在玻璃纤维网格布上刷抹面砂浆至将其完全覆盖;待抹面砂浆硬化。
3.根据权利要求1所述的一种建筑装饰抹灰施工方法,其特征在于:所述步骤(3)抹灰是指机械喷浆,过程如下:向冲筋完成的墙面洒水;用砂浆喷浆机将抹灰砂浆喷向所述墙面,直至覆盖冲筋模板、微见冲筋模板外沿轮廓;用普通靠尺贴着冲筋模板收刮;人工修补平整预留孔洞或预留位置。
4.根据权利要求1所述的一种建筑装饰抹灰施工方法,其特征在于:所述步骤(2)的冲筋模板由可与墙面连接的底座(10)、冲筋板(30)和连接所述底座(10)与冲筋板(30)的连接杆(20)构成;所述底座(10)有一个能让连接杆(20)垂直于底座(10)插入的安装通孔(11),所述冲筋板(30)靠近墙面的那一侧面上沿长度方向设有能使连接杆(20)的另一端垂直插入的卡槽(33),同一冲筋板(30)至少连接两个所述连接杆(20)和两个所述底座(10)。
5.根据权利要求4所述的一种建筑装饰抹灰施工方法,其特征在于:所述冲筋模板安装过程如下:沿所述墙面纵向每隔50厘米用胶水粘贴所述底座(10);所述连接杆(20)一端插入所述安装通孔(11),根据放线高度剪取相应长度的连接杆(20),将所述卡槽(33)对准连接杆(20)另一端按下。
6.根据权利要求4所述的一种建筑装饰抹灰施工方法,其特征在于:所述底座(10)由一个小圆饼(18)和一个可与墙面连接的大圆饼(17)同轴一体成型,所述安装通孔(11)与所述大圆饼(17)和小圆饼(18)同轴;所述安装通孔(11)靠近冲筋板(30)端有向内侧突起的卡脚(12);所述大圆饼(17)沿周向均匀分布4个所述辅助通孔(13),所述冲筋板(30)由沿长度方向对称折弯的折板(31)和所述卡槽(33)一体成型,所述卡槽(33)设于所述折板(31)的转角内凹面处并沿长度方向延伸;所述折板(31)两侧分别设有沿长度方向分布的多个通孔(32)。
7.根据权利要求4所述的一种建筑装饰抹灰施工方法,其特征在于,所述连接杆(20)上沿长度方向均匀分布有垂直于连接杆(20)长度方向、闭合的多个环状凹痕(21)。
8.根据权利要求1-7所述的一种建筑装饰抹灰施工方法,其特征在于:所述步骤(4)的锯片靠尺包括沿长度方向设有锯齿的锯片(300)及与所述锯片(300)相连的夹持部(200)。
9.根据权利要求7所述的一种建筑装饰抹灰施工方法,其特征在于:所述夹持部(200)的横截面形状近似为等腰三角形,其顶角处张开为两片夹持锯片(300)的夹板(210),所述夹板(210)和锯片(300)以螺栓(100)紧固,所述夹持部(200)与锯片(300)长度相适配。
10.根据权利要求7所述的一种建筑装饰抹灰施工方法,其特征在于:所述锯片(300)的长度为1.7米至2.3米,所述锯齿距离夹板(210)邻近端端部的距离为30毫米至70毫米;所述锯片(300)被夹持部分的宽度为40毫米至60毫米;所述夹持部(200)远离锯片(300)的端面宽度为2厘米。
CN201210118829.2A 2012-04-20 2012-04-20 一种建筑装饰抹灰施工方法 Active CN102644362B (zh)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN201210118829.2A CN102644362B (zh) 2012-04-20 2012-04-20 一种建筑装饰抹灰施工方法
PCT/CN2012/083952 WO2013155833A1 (zh) 2012-04-20 2012-11-02 一种建筑装饰抹灰施工方法
US14/395,792 US9255413B2 (en) 2012-04-20 2012-11-02 Method for plastering construction in architectural decoration

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210118829.2A CN102644362B (zh) 2012-04-20 2012-04-20 一种建筑装饰抹灰施工方法

Publications (2)

Publication Number Publication Date
CN102644362A true CN102644362A (zh) 2012-08-22
CN102644362B CN102644362B (zh) 2014-07-23

Family

ID=46657419

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210118829.2A Active CN102644362B (zh) 2012-04-20 2012-04-20 一种建筑装饰抹灰施工方法

Country Status (3)

Country Link
US (1) US9255413B2 (zh)
CN (1) CN102644362B (zh)
WO (1) WO2013155833A1 (zh)

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102888977A (zh) * 2012-10-26 2013-01-23 深圳广田装饰集团股份有限公司 一种内墙冲筋方法
CN102953505A (zh) * 2012-11-11 2013-03-06 苏州金螳螂建筑装饰股份有限公司 粉刷喷涂石膏墙面结构及其施工方法
CN103046709A (zh) * 2013-01-14 2013-04-17 山西省第二建筑工程公司 一种内墙面的建筑施工方法
CN103195218A (zh) * 2013-03-29 2013-07-10 浙江万华建设有限公司 一种墙体陶砂砂浆外抹灰施工工法
CN103291024A (zh) * 2013-05-28 2013-09-11 柴焕生 一种新型水泥基抹灰砂浆的施工方法
CN103866932A (zh) * 2014-04-04 2014-06-18 迪亚爱柯节能科技(上海)有限公司 粉化、低强度基层墙体表面增强处理结构的施工方法
CN104179308A (zh) * 2014-09-02 2014-12-03 陕西航天建筑工程有限公司 一种利用水泥砂浆造型特殊墙面施工工艺
US9255413B2 (en) 2012-04-20 2016-02-09 Shenzhen Grandland Decoration Group Co., Ltd. Method for plastering construction in architectural decoration
CN105822045A (zh) * 2016-04-06 2016-08-03 中亿丰建设集团股份有限公司 砂浆拉锚机自动抹灰施工方法
CN105926876A (zh) * 2016-06-21 2016-09-07 温州市华宁建筑机械有限公司 基于金属充筋条的墙面抹灰机械化施工方法
CN106088541A (zh) * 2016-07-14 2016-11-09 宁波工程学院 升降式砂浆条筋靠模及可用于高大墙体的条筋形成工艺
CN106193545A (zh) * 2016-09-20 2016-12-07 中铁建设集团有限公司 冲筋分隔缝成型套件及地面找平层施工方法
CN106205334A (zh) * 2016-07-25 2016-12-07 江苏建筑职业技术学院 抹灰施工危险源识别体验区及操作方法
CN106256970A (zh) * 2016-08-15 2016-12-28 邹学辉 一种喷涂抹灰工艺
CN107023130A (zh) * 2017-05-24 2017-08-08 君旺节能科技股份有限公司 多种涂料墙面粉刷方法
CN107345430A (zh) * 2017-08-01 2017-11-14 芜湖领航新材料科技有限公司 一种复合保温砖及其生产工艺
CN107476548A (zh) * 2017-07-19 2017-12-15 广东星艺装饰集团股份有限公司 墙镜工程工艺及装置
CN107620449A (zh) * 2017-08-28 2018-01-23 中建八局第三建设有限公司 一种圆柱面环形冲筋工具及圆柱面抹灰方法
CN109025296A (zh) * 2018-08-22 2018-12-18 上海中绿建材有限公司 一种轻质抹灰石膏与饰面腻子一体化施工工艺
CN109629803A (zh) * 2019-01-25 2019-04-16 中国五冶集团有限公司 可自动回收洒落砂浆的抹墙机
CN109853887A (zh) * 2019-01-29 2019-06-07 天津市武清区建筑工程总公司 一种砌体填充墙墙面抹灰的施工方法
CN112252679A (zh) * 2020-10-30 2021-01-22 黎家宏 基于抹墙机的内墙抹灰施工方法
CN112575978A (zh) * 2020-12-10 2021-03-30 中铁八局集团建筑工程有限公司 加气混凝土砌块喷浆抹灰施工方法
CN113356526A (zh) * 2021-05-28 2021-09-07 广东潮鑫建设工程有限公司 一种薄层抹灰辅助装置及施工工艺
CN113494167A (zh) * 2020-03-19 2021-10-12 广东博智林机器人有限公司 一种铺贴装置及铺贴机器人
CN113737821A (zh) * 2021-07-27 2021-12-03 泉州市华泰建设工程有限公司 一种路堑抗滑桩免抹灰附着式支模施工方法
CN114673313A (zh) * 2022-03-23 2022-06-28 中恒创兴建设有限公司 一种建筑内墙面装饰装修方法

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108590125B (zh) * 2015-05-26 2019-08-30 佛山市突破机械制造有限公司 一种具有可折叠直立轨道的抹墙机
CN106193542B (zh) * 2016-07-14 2018-11-06 宁波工程学院 一种机喷砂浆抹灰条筋靠模及一种条筋形成工艺
CN107023152A (zh) * 2017-06-07 2017-08-08 成都赋阳技术开发有限公司 建筑装修用自动铺沙灰设备
CN108824774A (zh) * 2018-07-12 2018-11-16 洛阳展腾科技有限公司 一种手提式粉墙机
CN109555241B (zh) * 2019-01-24 2024-04-12 王雄飞 确保砌体性能和墙面抹灰可靠性的结构网及其施工方法
CN111877697B (zh) * 2020-06-10 2022-02-15 广东博智林机器人有限公司 墙面抹平装置及墙面抹平设备
CN111779240B (zh) * 2020-08-20 2021-10-19 广西南君建设有限公司 一种建筑墙面粉刷设备及其粉刷方法
CN112012443B (zh) * 2020-08-26 2022-04-15 青岛基安豪智能装饰工程有限公司 一种装饰墙圆形槽侧壁腻子粉自动涂刷设备
CN114482478B (zh) * 2020-10-26 2023-12-01 洪伟祐 抹灰整平方法及套组
CN112459507B (zh) * 2020-12-01 2022-07-19 浙江至方建设有限公司 一种建筑墙体建造施工工艺
CN112609926A (zh) * 2020-12-11 2021-04-06 邢台职业技术学院 一种建筑墙体施工用自动化喷涂设备及其喷涂方法
CN115247483B (zh) * 2021-04-28 2024-01-16 广东博智林机器人有限公司 一种抹灰装置、抹灰设备及抹灰方法
CN113622635A (zh) * 2021-08-25 2021-11-09 湖州青米传媒科技有限公司 一种室内装饰施工的墙面抹灰装置及方法
CN113833236A (zh) * 2021-09-01 2021-12-24 乔龙云 一种建筑工程喷射混凝土施工设备
CN113863624A (zh) * 2021-10-13 2021-12-31 中国十七冶集团有限公司 一种墙体抹灰贴设灰饼的装置及施工方法
CN115405075B (zh) * 2022-10-10 2023-08-15 临清市安竣建设有限公司 一种可提高平整度的建筑外墙保温施工用高效抹灰装置

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1989006641A2 (en) * 1988-01-20 1989-07-27 Howard Wilkinson Compositions, system and method of controlling damp and/or mould
CN201095860Y (zh) * 2007-09-14 2008-08-06 贺孟强 建筑施工抹灰刮尺
CN201588390U (zh) * 2010-01-15 2010-09-22 深圳广田装饰集团股份有限公司 一种抹灰冲筋模板
CN101948289A (zh) * 2010-09-08 2011-01-19 深圳广田装饰集团股份有限公司 一种建筑抹灰施工时冲筋用的砂浆及其施工方法
CN202090569U (zh) * 2011-04-26 2011-12-28 深圳广田装饰集团股份有限公司 一种抹灰冲筋模板

Family Cites Families (29)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2867041A (en) * 1957-04-10 1959-01-06 Mcmillan Floor Products Compan Screed support and method of using
US3834107A (en) * 1973-07-19 1974-09-10 C Standing Device to repair damaged doors and walls
US4158937A (en) * 1978-01-12 1979-06-26 Henry Wendell L Concrete screed adjustable stirrup
US4371330A (en) * 1980-09-22 1983-02-01 W. R. Grace & Co. Adjustable screed bar apparatus
AU578852B2 (en) * 1985-12-03 1988-11-03 Keith HONEYMAN Screed rail
US4702641A (en) * 1986-05-01 1987-10-27 Atlanta Concrete Accessories Inc. Multi-purpose concrete working tool
US4892439A (en) * 1989-03-09 1990-01-09 Gerald M. Kiefer Screed rail system
US4945698A (en) * 1989-08-07 1990-08-07 Vanberg Enterprises Adjustable screed support
SE468097B (sv) * 1991-03-13 1992-11-02 Combiform Ab Stoedelement foer anvaendning vid gjutning av betonggolv
US5607256A (en) * 1995-02-10 1997-03-04 Mccleary Concepts & Creations, Inc. Adjustable floor tile mortar and grout spreader
US5609437A (en) * 1995-09-21 1997-03-11 Silva; Steve Concrete screed
US6016635A (en) * 1999-03-23 2000-01-25 Shaw; Lee A. Surface seeded aggregate and method of forming the same
US6314695B1 (en) * 1999-06-22 2001-11-13 Michael R. Belleau Stucco wall building arrangement
US6508043B1 (en) * 2000-02-11 2003-01-21 Art Bond Building construction system and method
US6397542B1 (en) * 2000-11-27 2002-06-04 Leo Flores Adjustable screed
US6393788B1 (en) * 2000-11-27 2002-05-28 Leo Flores Adjustable screed
US6669876B2 (en) * 2000-11-30 2003-12-30 Bruce Torrance Method of preparing smooth, watertight concrete surfaces on concrete pools
US6610224B2 (en) * 2001-02-22 2003-08-26 Sullivan Concrete Textures Processes for producing monolithic architectural cementitious structures having decorative aggregate-containing cementitious surfaces
US7591967B2 (en) * 2003-02-14 2009-09-22 Terr-Con Decorative Concrete Floors, Inc. Method for the aesthetic surface treatment of a monolithic concrete floor and product of the method
US7396187B1 (en) * 2005-01-26 2008-07-08 Beno J. Gundiach Company Upright trowel
US7493732B2 (en) * 2005-10-24 2009-02-24 Lithocrete, Inc. Litho-mosaic
US7878469B2 (en) * 2007-09-07 2011-02-01 Bryan Hasenoehrl Quick release screed bar holder
US20090277127A1 (en) * 2008-05-08 2009-11-12 Single Eagle, Inc. Decorative aggregate concrete surface preparation process
US20100139196A1 (en) * 2008-12-05 2010-06-10 Andrew Tyson Healy Vertical screed
US8381483B1 (en) * 2009-04-23 2013-02-26 Nancy Goldman Terrazzo process for existing concrete surfaces
US8567153B1 (en) * 2011-04-21 2013-10-29 Spray Rock Llc Composite concrete and framing system and method for building construction
CN102644362B (zh) 2012-04-20 2014-07-23 深圳广田装饰集团股份有限公司 一种建筑装饰抹灰施工方法
US8962088B2 (en) * 2013-03-15 2015-02-24 Lithocrete, Inc. Method and finish for concrete walls
US8936411B1 (en) * 2013-09-12 2015-01-20 Lithocrete, Inc. Architectural concrete

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1989006641A2 (en) * 1988-01-20 1989-07-27 Howard Wilkinson Compositions, system and method of controlling damp and/or mould
CN201095860Y (zh) * 2007-09-14 2008-08-06 贺孟强 建筑施工抹灰刮尺
CN201588390U (zh) * 2010-01-15 2010-09-22 深圳广田装饰集团股份有限公司 一种抹灰冲筋模板
CN101948289A (zh) * 2010-09-08 2011-01-19 深圳广田装饰集团股份有限公司 一种建筑抹灰施工时冲筋用的砂浆及其施工方法
CN202090569U (zh) * 2011-04-26 2011-12-28 深圳广田装饰集团股份有限公司 一种抹灰冲筋模板

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
邓泽贵等: "《抹灰工》", 30 April 2007, 重庆大学出版社 *

Cited By (37)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9255413B2 (en) 2012-04-20 2016-02-09 Shenzhen Grandland Decoration Group Co., Ltd. Method for plastering construction in architectural decoration
CN102888977A (zh) * 2012-10-26 2013-01-23 深圳广田装饰集团股份有限公司 一种内墙冲筋方法
WO2014063481A1 (zh) * 2012-10-26 2014-05-01 深圳广田装饰集团股份有限公司 一种内墙冲筋方法
CN102888977B (zh) * 2012-10-26 2014-11-26 深圳广田装饰集团股份有限公司 一种内墙冲筋方法
CN102953505A (zh) * 2012-11-11 2013-03-06 苏州金螳螂建筑装饰股份有限公司 粉刷喷涂石膏墙面结构及其施工方法
CN102953505B (zh) * 2012-11-11 2016-03-23 苏州金螳螂建筑装饰股份有限公司 粉刷喷涂石膏墙面结构及其施工方法
CN103046709A (zh) * 2013-01-14 2013-04-17 山西省第二建筑工程公司 一种内墙面的建筑施工方法
CN103195218B (zh) * 2013-03-29 2015-06-17 浙江万华建设有限公司 一种墙体陶砂砂浆外抹灰施工工法
CN103195218A (zh) * 2013-03-29 2013-07-10 浙江万华建设有限公司 一种墙体陶砂砂浆外抹灰施工工法
CN103291024A (zh) * 2013-05-28 2013-09-11 柴焕生 一种新型水泥基抹灰砂浆的施工方法
CN103291024B (zh) * 2013-05-28 2015-10-21 柴焕生 一种新型水泥基抹灰砂浆的施工方法
CN103866932A (zh) * 2014-04-04 2014-06-18 迪亚爱柯节能科技(上海)有限公司 粉化、低强度基层墙体表面增强处理结构的施工方法
CN104179308A (zh) * 2014-09-02 2014-12-03 陕西航天建筑工程有限公司 一种利用水泥砂浆造型特殊墙面施工工艺
CN104179308B (zh) * 2014-09-02 2016-06-15 中国航天建设集团有限公司 一种利用水泥砂浆造型特殊墙面施工工艺
CN105822045A (zh) * 2016-04-06 2016-08-03 中亿丰建设集团股份有限公司 砂浆拉锚机自动抹灰施工方法
CN105926876A (zh) * 2016-06-21 2016-09-07 温州市华宁建筑机械有限公司 基于金属充筋条的墙面抹灰机械化施工方法
CN106088541A (zh) * 2016-07-14 2016-11-09 宁波工程学院 升降式砂浆条筋靠模及可用于高大墙体的条筋形成工艺
CN106088541B (zh) * 2016-07-14 2019-03-01 宁波工程学院 升降式砂浆条筋靠模及可用于高大墙体的条筋形成工艺
CN106205334A (zh) * 2016-07-25 2016-12-07 江苏建筑职业技术学院 抹灰施工危险源识别体验区及操作方法
CN106256970A (zh) * 2016-08-15 2016-12-28 邹学辉 一种喷涂抹灰工艺
CN106256970B (zh) * 2016-08-15 2019-04-26 湖南瑞吉达科技有限公司 一种喷涂抹灰工艺
CN106193545A (zh) * 2016-09-20 2016-12-07 中铁建设集团有限公司 冲筋分隔缝成型套件及地面找平层施工方法
CN107023130A (zh) * 2017-05-24 2017-08-08 君旺节能科技股份有限公司 多种涂料墙面粉刷方法
CN107476548A (zh) * 2017-07-19 2017-12-15 广东星艺装饰集团股份有限公司 墙镜工程工艺及装置
CN107345430A (zh) * 2017-08-01 2017-11-14 芜湖领航新材料科技有限公司 一种复合保温砖及其生产工艺
CN107620449A (zh) * 2017-08-28 2018-01-23 中建八局第三建设有限公司 一种圆柱面环形冲筋工具及圆柱面抹灰方法
CN109025296A (zh) * 2018-08-22 2018-12-18 上海中绿建材有限公司 一种轻质抹灰石膏与饰面腻子一体化施工工艺
CN109025296B (zh) * 2018-08-22 2021-04-23 上海中绿建材有限公司 一种轻质抹灰石膏与饰面腻子一体化施工工艺
CN109629803A (zh) * 2019-01-25 2019-04-16 中国五冶集团有限公司 可自动回收洒落砂浆的抹墙机
CN109629803B (zh) * 2019-01-25 2024-03-19 中国五冶集团有限公司 可自动回收洒落砂浆的抹墙机
CN109853887A (zh) * 2019-01-29 2019-06-07 天津市武清区建筑工程总公司 一种砌体填充墙墙面抹灰的施工方法
CN113494167A (zh) * 2020-03-19 2021-10-12 广东博智林机器人有限公司 一种铺贴装置及铺贴机器人
CN112252679A (zh) * 2020-10-30 2021-01-22 黎家宏 基于抹墙机的内墙抹灰施工方法
CN112575978A (zh) * 2020-12-10 2021-03-30 中铁八局集团建筑工程有限公司 加气混凝土砌块喷浆抹灰施工方法
CN113356526A (zh) * 2021-05-28 2021-09-07 广东潮鑫建设工程有限公司 一种薄层抹灰辅助装置及施工工艺
CN113737821A (zh) * 2021-07-27 2021-12-03 泉州市华泰建设工程有限公司 一种路堑抗滑桩免抹灰附着式支模施工方法
CN114673313A (zh) * 2022-03-23 2022-06-28 中恒创兴建设有限公司 一种建筑内墙面装饰装修方法

Also Published As

Publication number Publication date
CN102644362B (zh) 2014-07-23
US20150059284A1 (en) 2015-03-05
WO2013155833A1 (zh) 2013-10-24
US9255413B2 (en) 2016-02-09

Similar Documents

Publication Publication Date Title
CN102644362B (zh) 一种建筑装饰抹灰施工方法
CN104863342B (zh) 一种圆柱的抹灰装置及方法
CN106193624A (zh) 一种改进的加气混凝土砌块墙体防裂缝施工技术
CN208122230U (zh) 一种房屋建设用多余水泥收集装置
CN104372952A (zh) 一种无应力渗透水洗凿毛工艺
CN106284998A (zh) 内墙抹灰满铺玻璃纤维网格布施工方法
CN202519978U (zh) 等同施工缝的后浇带支模结构
CN104120847A (zh) 一种混凝土多孔砖墙面免粉刷批腻子处理的施工方法
CN203834826U (zh) 一种新型楼梯间滴水槽
CN208981770U (zh) 一种吊模装置
CN107675834A (zh) 一种用于仿古建筑混凝土承重构件的施工方法
CN205476098U (zh) 仿古连体筒瓦和檐瓦
CN207420013U (zh) 清水模板的无痕拼接结构
CN202530723U (zh) 一种抹灰冲筋模板
CN102182323A (zh) 低纬度高原蒸压加气砼砌块干法砌筑施工工艺
CN101761183B (zh) 空心隔墙板及其安装方法
CN205935571U (zh) 建筑用拉毛刷
CN109162451A (zh) 一种用于外墙混凝土挑檐浇筑的模板定位工具及方法
CN201424811Y (zh) 混凝土现浇板管道预留洞口专用模具
CN107965136A (zh) 清水模板的无痕拼接结构与方法
CN210396034U (zh) 一种基于建筑工程的新型砂浆抹灰装置
CN209211890U (zh) 一种用于外墙混凝土挑檐浇筑的模板定位工具
CN202509637U (zh) 上人屋面悬臂式盖板变形缝结构
CN207892233U (zh) 结构与装饰一体化的现浇混凝土用弹性装饰造型模板系统
CN202530722U (zh) 一种建筑抹灰用的靠尺

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 518000 Guangdong, Shenzhen, Luohu District, Yanhe Road 1003, Beijing capital east 1~2 level.

Patentee after: Shenzhen Guangtian group Limited by Share Ltd

Address before: 518000 Guangdong, Shenzhen, Luohu District, Yanhe Road 1003, Beijing capital east 1~2 level.

Patentee before: Shenzhen Guangtian Decoration Group Co., Ltd.

CP01 Change in the name or title of a patent holder