CN102570602A - Fault comprehensive processing platform and method of distribution network - Google Patents

Fault comprehensive processing platform and method of distribution network Download PDF

Info

Publication number
CN102570602A
CN102570602A CN2011103967094A CN201110396709A CN102570602A CN 102570602 A CN102570602 A CN 102570602A CN 2011103967094 A CN2011103967094 A CN 2011103967094A CN 201110396709 A CN201110396709 A CN 201110396709A CN 102570602 A CN102570602 A CN 102570602A
Authority
CN
China
Prior art keywords
fault
information
module
fault message
message
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011103967094A
Other languages
Chinese (zh)
Other versions
CN102570602B (en
Inventor
王海林
许海清
陈楷
徐爱华
张文俊
朱红
吴文书
韦磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU SUYUAN HIGH-TECH Co Ltd
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Nanjing Power Supply Co of Jiangsu Electric Power Co
Original Assignee
JIANGSU SUYUAN HIGH-TECH Co Ltd
Nanjing Power Supply Co of Jiangsu Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU SUYUAN HIGH-TECH Co Ltd, Nanjing Power Supply Co of Jiangsu Electric Power Co filed Critical JIANGSU SUYUAN HIGH-TECH Co Ltd
Priority to CN2011103967094A priority Critical patent/CN102570602B/en
Priority to CN201310489872.4A priority patent/CN103516054B/en
Priority to CN201310489657.4A priority patent/CN103490521B/en
Priority to CN201310489820.7A priority patent/CN103501051B/en
Priority to CN201310489744.XA priority patent/CN103501050B/en
Publication of CN102570602A publication Critical patent/CN102570602A/en
Application granted granted Critical
Publication of CN102570602B publication Critical patent/CN102570602B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/12Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment
    • Y04S40/126Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment using wireless data transmission
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/12Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment
    • Y04S40/128Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment involving the use of Internet protocol

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention relates to a fault comprehensive processing platform and method of a distribution network, belonging to the technical field of power grid management. The fault comprehensive processing platform comprises a fault information acquisition system, a fault information judgment system and a fault repair power failure information pushing system. The fault comprehensive processing method comprises the steps of: acquiring information of repair faults, line faults and consumption faults in a distribution automatic management system and a power utilization information acquisition system, receiving and checking the information; carrying out equipment location, fault information screening, line topology analysis, equipment operation information analysis and line switch analysis; determining fault types, places and affected regions and showing in the traditional GIS (Geographic Information System); and guiding fault repair according to a determined fault result, and pushing fault power failure information and power supply recovering information to a user. The platform and the method realize concentrated acquisition and automatic pre-judgment on the traditional fault information, can also be used for actively pushing power failure and power supply recovering information to the user, and interact with the user.

Description

Adapted electric network fault integrated treatment platform and processing method
Technical field
The present invention relates to a kind of electric network fault information of gathering by all kinds of means, fault message carried out automatic anticipation, and the anticipation result is pushed to repairing and user, and with the processing platform and the processing method of user interaction, belong to the administration of power networks technical field.
Background technology
Existing electrical network automated management system does not form integrated treatment to electric network fault; To the collection of fault message, judge, notify the processing of each link such as user and commander's breakdown repair all to isolate; Lack contact each other, and result can not form interaction with the user.Concrete manifestation is following:
1, the collection of fault message is single isolated
Existing electric network fault information gathering has 95598 to report the mode that channel such as reports, user's intelligent electric meter fault reports, distribution transforming acquisition terminal fault reports, circuit On line switch fault reports, transformer station's outlet switch fault reports to obtain for repairment; But the fault message that these channels obtain all is to be stored in separately separately in the operation system; Be stored in 95598 customer service systems like 95598 fault messages that report for repairment; The failed storage that reports of user's intelligent electric meter is in power information acquisition system (CSM) for another example, and and for example circuit On line switch and transformer station go out the fault message that wiretap reports and be stored in the power distribution automation management system (DMS).This shows; The channel that existing various electrical network operation systems are gathered fault message is (battalion of respectively doing for oneself) that isolates; The information of various channel collections lacks unified access road; Not contact between the fault message that various channels are gathered, therefore the various automation operation systems of existing electrical network can not be shared the fault message that various channels are gathered simultaneously, thereby can not satisfy the requirement of electric network fault information being carried out analysis-by-synthesis and utilization.
2, lack early stage anticipation automatically for fault message
For a long time; When power matching network breaks down; Before fault reports back entering scene rush to repair; Can not analyze and accurately fault location source and relevant device information for fault message, the affirmation of description and the repairing personnel that can only depend on the user behind the scene promptly can not in time accurately be judged the type of fault, the scope of influence etc.What bring thus is, accurate fault location source and relevant device information during the power failure repairing, accurately obtains fault type and coverage and exists and lag behind, and depends on the affirmation of repairing personnel behind the scene, thus the scheduling of the progress of influence repairing and repairing resource.
3, fault message and repairing recovery situation can't push to user side
For a long time; The user can only obtain power failure information through TV, newpapers and periodicals and network; But the limitation of traditional media makes the client often can't grasp power failure information in time because of ignoring, and more can not grasp electric network fault power failure information and the expectation temporal information that restores electricity in real time.Though existing electrical network 95598 customer service systems itself possess the inquiry and the issuing function of fault outage information; But 95598 contact staff normally initiatively do not issue fault outage information to the user; Just when the user condescends to inquire, just inform the user, 95598 can not inform user's fault outage repairing progress and the expectation temporal information that restores electricity.In addition during scene rush to repair, the repairing personnel at the scene can not with breakdown repair system real-time, interactive, repairing work can not effectively be supervised.
Summary of the invention
First technical problem that the present invention will solve is: propose a kind of current collection net fault information acquisition, study and judge, push incorporate full-automatic integrated treatment platform and processing method.
Second technical problem that the present invention will solve is: on the basis that solves above-mentioned first technical problem, propose a kind of full-automatic integrated treatment platform of adapted electrical network and the method that can carry out interaction with the user.
In order to solve above-mentioned first technical problem; One of technical scheme that the present invention proposes is: a kind of adapted electric network fault integrated treatment platform; Comprise that fault information acquisition system, fault message are studied and judged system and breakdown repair stops the information transmission system of supplying power, said fault information acquisition system comprises being arranged at and existing 95598 intrasystemly reports that fault message pushes module, the line fault information in the existing power distribution automation management system of being arranged at pushes module for repairment, is arranged at usefulness in the existing power information acquisition system and adopts fault message and push module, fault message receiver module, fault message processing module and fault message sending module; Said fault message is studied and judged system and is comprised the faulty equipment locating module, fault message screening module, line topological analysis module, equipment operation information analysis module, line switching analysis module, failure analysis module and fault display module; The said breakdown repair information transmission system that stops supplying power comprises that breakdown repair allocation schedule module, scene rush to repair administration module, repairing information push module and stop power supply information and pushes module;
The said fault message that reports for repairment pushes module and reports fault message for repairment in order to the user that will be reported to 95598 systems and be pushed to said fault message receiver module;
Said line fault information pushes module and is pushed to said fault message receiver module in order to the switch changed position fault message that will be reported to power distribution automation management system (DMS);
Said usefulness is adopted fault message propelling movement module and is pushed to said fault message receiver module in order to distribution transforming and user's fault message that will be reported to power information acquisition system (CSM);
Fault message pushes module to said fault message receiver module, line fault information pushes module and pushes the next fault message of module propelling movement with adopting fault message from reporting for repairment with verification in order to receive;
Said fault message processing module is stored in order to the fault message that said fault message receiver module is received, and from the low-voltage customer to the high-tension apparatus, carries out analytical integration with uniform data model according to the power network line topological structure;
The fault message of said fault message sending module in order to the fault message processing module is handled sent out passage outward through information and is sent to said faulty equipment locating module;
Said faulty equipment locating module is used to receive the fault message that said fault message sending module sends, and obtains the actual geographical position and the account information of the source device relevant with fault message through existing power distribution management system (PMS);
Said fault message screening module is used for the fault message behind the equipment location is screened, and gets rid of the scheduled outage fault message and the confirmed fault message that have generated;
Said line topological analysis module is used for the adapted electric line under the fault message that filters out is carried out topological analysis, obtains the topological structure of this adapted electric line and the circuit charging equipment tabulation of associated topologies structure;
Said equipment operation information analysis module is used for the circuit charging equipment of circuit charging equipment tabulation is carried out the cls analysis of calling together of equipment operation information step by step, and judges whether the circuit charging equipment exists fault;
Said line switching analysis module is used to the switch folding information that detects the On line switch on the adapted electric line and go out wiretap, and judges whether the adapted electric line exists line fault;
Said failure analysis module is used for confirming fault type, the position of fault and fault effects zone according to equipment operation information, switch folding information and topological structure; Fault type, the position of fault and fault effects zone are pushed to breakdown repair allocation schedule module, generate fault outage information and push to according to fault type, the position of fault and fault effects zone and stop power supply information propelling movement module;
Said breakdown repair allocation schedule module is used for confirming according to fault type, the position of fault and fault effects zone the repairing teams and groups and the scheduling recovery vehicle of fault;
Said scene rush to repair administration module is used to monitor and gather repairing personnel's the repairing procedural information and the information that restores electricity;
Said repairing information pushes module and is used for repairing procedural information is pushed to the fault display module, and will the information of restoring electricity be pushed to and stops power supply information propelling movement module;
Said fault display module is used for having circuit charging equipment and the account information thereof of fault, the influence area and the repairing procedural information of adapted electric line through existing adapted power grid GIS system demonstration;
The said power supply information propelling movement module of stopping is used for through existing 95598 customer service systems, short message service passage and fiber data passage the fault outage information and the information that restores electricity being influenced user's propelling movement to having a power failure.
In order to solve above-mentioned first technical problem, two of the technical scheme that the present invention proposes is: a kind of adapted electric network fault integrated conduct method, adopt above-mentioned adapted electric network fault integrated treatment platform, and carry out following steps:
1) setting is reported fault message for repairment and is pushed module in existing 95598 systems, sets up 95598 systems and reports the Web service data-transmission channel that fault message pushes module for repairment;
Line fault information is set in existing power distribution automation management system pushes module, set up GPRS message information transmission passage or IEB bus service data transmission passage that power distribution automation management system and line fault information push module;
In existing power information acquisition system, be provided with adopting fault message and push module, set up the power information acquisition system and use the Web service data-transmission channel of adopting fault message propelling movement module;
2) reporting fault message for repairment pushes module and will be reported to the user of existing 95598 systems to report fault message for repairment to be pushed to the fault message receiver module;
Line fault information pushes module and will be reported to the switch changed position fault message of existing power distribution automation management system to be pushed to the fault message receiver module;
To be reported to distribution transforming and user's fault message of existing power information acquisition system to be pushed to the fault message receiver module with adopting fault message propelling movement module;
3) fault message pushes module, line fault information pushes module and pushes the next fault message of module propelling movement with adopting fault message from reporting for repairment for reception of fault message receiver module and verification;
4) the fault message processing module will be stored through the fault message of reception of fault message receiver module and verification, from the low-voltage customer to the high-tension apparatus, carry out analytical integration with uniform data model according to the power network line topological structure;
5) the fault message sending module will be sent out passage outside through information through fault message that the fault message processing module is handled and be sent to the faulty equipment locating module;
6) the faulty equipment locating module receives the fault message that the fault message sending module sends, and obtains the actual geographical position and the account information of the source device relevant with fault message through existing power distribution management system;
7) the fault message screening module is screened the fault message behind the source device location, judges whether the fault message behind the source device location belongs to scheduled outage fault message and the confirmed fault message that has generated, and then eliminating in this way is not as being then to carry out next step;
8) the line topological analysis module is reviewed through power supply point the adapted electric line under the fault message that filters out is carried out topological analysis, obtains the topological structure of this adapted electric line and the circuit charging equipment tabulation of associated topologies structure;
9) the circuit charging equipment during equipment operation information analysis module is tabulated the circuit charging equipment carries out equipment operation information step by step and calls cls analysis together; Judge according to the equipment operation information that analyzes whether the circuit charging equipment exists fault; Then carry out next step in this way; As be not that then failure judgement information is user's internal fault information, finish to study and judge;
10) the line switching analysis module detects the On line switch on the adapted electric line and goes out the switch folding information of wiretap, judges whether the adapted electric line exists line fault;
11) failure analysis module is confirmed fault type according to said equipment operation information and switch folding information; Confirm the position of fault and fault effects zone according to said topological structure; Fault type, the position of fault and fault effects zone are pushed to breakdown repair allocation schedule module, generate fault outage information and push to according to fault type, the position of fault and fault effects zone and stop power supply information propelling movement module;
12) breakdown repair allocation schedule module is confirmed the repairing teams and groups and the scheduling recovery vehicle of fault according to fault type, the position of fault and fault effects zone;
13) monitoring of scene rush to repair administration module and collection repairing personnel's the repairing procedural information and the information that restores electricity;
14) repairing information pushes module and will rush to repair procedural information and push to the fault display module, and will the information of restoring electricity be pushed to and stops power supply information propelling movement module;
15) the fault display module exists circuit charging equipment and the account information thereof of fault, the influence area and the repairing procedural information of adapted electric line through existing adapted power grid GIS system demonstration;
16) stop power supply information propelling movement module and the fault outage information and the information that restores electricity are influenced user's propelling movement to having a power failure through existing 95598 customer service systems, short message service passage and fiber data passage.
In order to solve above-mentioned second technical problem; The present invention to the improvement of one of technique scheme is: also comprise being used for carrying out interactive interactive module through short message service passage and fiber data passage and user; Said interaction is that the user sends code and the user number inquiry stops sending electrical information, stops sending electrical information and transmission to inform the user by interactive module according to user number inquiring user region.
In order to solve above-mentioned second technical problem, the present invention to two improvement of technique scheme is: adopt improved technical scheme to increase in the lump and carry out the 17th) step: interactive module is carried out interaction through short message service passage and fiber data passage and user; Said interaction is that the user sends code and the user number inquiry stops sending electrical information, informs the user by interactive module according to user number inquiring user region power failure information and restore electricity information and transmission.
The perfect of one of technique scheme is: the said fault message propelling movement module of reporting for repairment links through the Web service data-transmission channel with existing 95598 systems; Said line fault information pushes module and links through GPRS message information transmission passage or IEB bus service data transmission passage with existing power distribution automation management system; Said usefulness is adopted fault message propelling movement module and is linked through the Web service data-transmission channel with existing power information acquisition system; It is to utilize the SIM of the remote signalling displacement device that is arranged on switch to constitute that said GPRS message information transmits passage, and it is LAN that said information is sent out passage outward.
The perfect of one of technique scheme is: said storage be with the fault message classification and storage of the separate sources that receives in the fault message table of type separately; Said analytical integration is top-down arrangement the in order of line topological structure according to mesolow; Comprise from user profile->ammeter information->distribution transforming information->On line switch information->transformer station's outlet switching information analyzes; And set up the relation that can inquire about each other, the result who analyzes is stored in the analysis result table.
The perfect of one of technique scheme is: said user reports fault message for repairment and comprises Customs Assigned Number, user's name, station address, contact method and fault content; Said switch changed position fault message comprises the message of switch number, on off state, circuit number, affiliated factory station, three-phase current and three-phase voltage; Said distribution transforming and user's fault message comprise distribution transforming numbering, distribution transforming title, critical point numbering, ammeter numbering, critical point numbering and acquisition time.
The perfect of one of technique scheme is: said fault message comprises 95598 user's repairing information, and existing power information acquisition system (CSM) reports fault message and existing power distribution automation management system (DMS) to report fault message; Said fault type comprises low district's fault, distribution transforming fault, middle pressure client's internal fault, part line fault and the circuit fault completely of presenting a theatrical performance as the last item on a programme.
The perfect of one of technique scheme is: when said fault message is that 95598 users are when reporting fault message for repairment; Said source device is low pressure ammeter box equipment or the negative control device that is associated through the existing acquisition user of power distribution management system according to the Customs Assigned Number that reports for repairment, and actual geographical coordinate information of said source device and account information are to obtain through existing power distribution management system queries according to low pressure ammeter box equipment or negative unique coding of controlling device; When said fault message is an existing power information acquisition system when reporting fault message or existing power distribution automation management system to report fault message, said source device is distribution transforming, switch and the negative control device that obtains through existing power distribution management system according to the asset of equipments numbering; Actual geographical coordinate information of said source device and account information are to obtain through existing power distribution management system queries according to source distribution transforming, switch and negative unique coding of controlling device.
The perfect of one of technique scheme is: said controller switching equipment comprises circuit, switch, distribution transformer and middle pressure user, and said power failure influences equipment and comprises low-pressure meter case and middle pressure user.
Technique scheme two perfectly be: the 3rd) in the step,, feed back to fault message propelling movement side to different fault message sources if the fault message of verification is an abnormal data; If the fault message of verification is normal data then pushes to the fault message processing module;
Technique scheme two perfectly be: the 4th) in the step, said storage be with the fault message classification and storage of the separate sources that receives in the fault message table of type separately; Said analytical integration is top-down arrangement the in order of line topological structure according to mesolow; Comprise from user profile->ammeter information->distribution transforming information->On line switch information->transformer station's outlet switching information analyzes; And set up the relation that can inquire about each other, the result who analyzes is stored in the analysis result table.
Technique scheme two perfectly be: it is to utilize the SIM of the remote signalling displacement device that is arranged on switch to constitute that said GPRS message information transmits passage; It is LAN that said information is sent out passage outward; Said user reports fault message for repairment and comprises Customs Assigned Number, user's name, station address, contact method and fault content; Said switch changed position fault message comprises the message of switch number, on off state, circuit number, affiliated factory station, three-phase current and three-phase voltage; Said distribution transforming and user's fault message comprise distribution transforming numbering, distribution transforming title, critical point numbering, ammeter numbering, critical point numbering and acquisition time.
Two improve and one be of technique scheme: the said the 6th) in the step; When said fault message is that 95598 users are when reporting fault message for repairment; According to the Customs Assigned Number that reports for repairment; Obtain low pressure ammeter box equipment that the user is associated or negative control device as source device through existing power distribution management system (PMS), and the unique coded query through low pressure ammeter box equipment or negative control device is to source device geographical coordinate information of reality and account information.
Two improve and two be of technique scheme: the said the 6th) in the step; When said fault message is that existing power information acquisition system is when reporting fault message or existing power distribution automation management system to report fault message; Obtain distribution transforming, switch and negative control device as source device according to asset of equipments numbering through existing power distribution management system, and the unique coded query through distribution transforming, switch and negative control device is to source device geographical coordinate information of reality and account information.
Technique scheme two perfectly be: the said the 7th) in the step; Whether fault message screening module at first failure judgement information is the scheduled outage fault message that has generated; Then get rid of this fault message in this way and do not study and judge, and inform through 95598 systems and to report the user for repairment; As be not scheduled outage then failure judgement information whether be confirmed fault message, then get rid of this fault message in this way and do not study and judge, and inform that through 95598 systems the user has confirmed the repairing situation of fault; As neither the scheduled outage fault message neither be confirmed fault message, then carry out next step.
Technique scheme two perfectly be: the said the 8th) in the step; It is to carry out power supply point according to the actual geographical position of source device to review and form and review the path that said power supply point is reviewed; Collect power supply point then and review the circuit charging equipment on the path; Circuit charging equipment equipment is classified, made up, form the tabulation of circuit charging equipment.
Technique scheme two perfectly be: the said the 9th) in the step, said circuit charging equipment is wiretap, On line switch, distribution transforming, negative control device and low pressure ammeter box.
Technique scheme two perfectly be: the said the 10th) in the step, saidly judge whether the adapted electric line exists line fault to comprise:
1. if the outlet switch closure then judges it is the part line failure;
2. if going out wiretap breaks off, then judge it is the whole piece line failure;
3. if go out wiretap and On line switch all is in closure state, then judgement is that circuit does not break down but device fails.
Technique scheme two perfectly be: the said the 11st) in the step, said definite fault type comprises:
A. report like the user transformers fault-free, confirm that then fault type is the low district's fault of presenting a theatrical performance as the last item on a programme;
B. have fault to report like user transformers, but the wireless switch of going up reports with the outlet switch fault, then definite fault type is the distribution transforming fault;
C. have fault to report like user transformers, and switch fault reports on wired, confirm that then fault type is a part line fault;
D. there is fault to report like user transformers, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely;
E. report like the negative control of user device fault-free, confirm that then fault type is middle pressure client internal fault;
F. have fault to report like the negative control of user device, and switch fault reports on wired, confirm that then fault type is a part line fault;
G. there is fault to report like the negative control of user device, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely.
Technique scheme two perfectly be: the said the 7th) in the step; Whether fault message screening module at first failure judgement information is the scheduled outage fault message that has generated; Then get rid of this fault message in this way and do not study and judge, and inform through 95598 systems and to report the user for repairment; As be not scheduled outage then failure judgement information whether be confirmed fault message, then get rid of this fault message in this way and do not study and judge, and inform that through 95598 systems the user has confirmed the repairing situation of fault; As neither the scheduled outage fault message neither be confirmed fault message, then carry out next step;
The said the 8th) in the step; It is to carry out power supply point according to the actual geographical position of source device to review and form and review the path that said power supply point is reviewed; Collect power supply point then and review the circuit charging equipment on the path; Circuit charging equipment equipment is classified, made up, form the tabulation of circuit charging equipment;
The said the 9th) in the step, said circuit charging equipment is wiretap, On line switch, distribution transforming, negative control device and low pressure ammeter box;
The said the 10th) in the step, if the outlet switch closure then judges it is the part line failure; Break off if go out wiretap, then judge it is the whole piece line failure; If go out wiretap and On line switch all is in closure state, then judgement is that circuit does not break down but device fails;
The said the 11st) in the step, said definite fault type comprises:
A. report like the user transformers fault-free, confirm that then fault type is the low district's fault of presenting a theatrical performance as the last item on a programme;
B. have fault to report like user transformers, but the wireless switch of going up reports with the outlet switch fault, then definite fault type is the distribution transforming fault;
C. have fault to report like user transformers, and switch fault reports on wired, confirm that then fault type is a part line fault;
D. there is fault to report like user transformers, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely;
E. report like the negative control of user device fault-free, confirm that then fault type is middle pressure client internal fault;
F. have fault to report like the negative control of user device, and switch fault reports on wired, confirm that then fault type is a part line fault;
G. there is fault to report like the negative control of user device, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely.
The invention has the beneficial effects as follows: 1), initiatively send the fault message that is reported to 95598 systems, power distribution automation management system and power information acquisition system to the fault message receiver module because fault message propelling movement module is reported in setting for repairment respectively in existing 95598 systems, power distribution automation management system and power information acquisition system, line fault information pushes module and pushes module with adopting fault message; Therefore realization gathers the electric network fault information that has the collection of various electrical network operation system channel now and initiatively transmits; 2) fault message is studied and judged system and can be shifted to an earlier date automatically the very first time after reception reports fault message and study and judge; And obtain accurately fault type, the position of fault and fault effects zone; Thereby, and then improve the efficient of breakdown repair and administration of power networks for breakdown repair and management provide strong foundation; 3) the breakdown repair information transmission system that stops supplying power can initiatively directly influence user's propelling movement with the power failure information and the information that restores electricity to having a power failure, and the user is known the very first time stop sending electrical information, is convenient to the user and carries out relative measures; 4) client can the short message service passage and fiber data passage inquiry power failure information with restore electricity information, be convenient to carry out alternately with the client.
Description of drawings
Below in conjunction with accompanying drawing adapted electric network fault integrated treatment platform of the present invention and method are described further.
Fig. 1 is the module rack composition of embodiment one adapted electric network fault integrated treatment platform.
Fig. 2 is the flow chart of embodiment one adapted electric network fault integrated conduct method.
Fig. 3 is the module rack composition of embodiment two adapted electric network fault integrated treatment platforms.
Fig. 4 is the flow chart of embodiment two adapted electric network fault integrated conduct methods.
Embodiment
Embodiment one
The adapted electric network fault integrated treatment platform of present embodiment comprises that the A of fault information acquisition system, fault message study and judge the B of system and the breakdown repair information transmission system C that stops supplying power.
The A of fault information acquisition system comprises being arranged at and existing 95598 intrasystemly reports that fault message pushes module 1, the line fault information in the existing power distribution automation management system of being arranged at pushes module 2 for repairment, is arranged at usefulness in the existing power information acquisition system and adopts fault message and push module 3, fault message receiver module 4, fault message processing module 5 and fault message sending module 6.
Fault message is studied and judged the B of system and is comprised faulty equipment locating module 7, fault message screening module 8, line topological analysis module 9, equipment operation information analysis module 10, line switching analysis module 11, failure analysis module 12 and fault display module 13.
The breakdown repair information transmission system C that stops supplying power comprises that breakdown repair allocation schedule module 14, scene rush to repair administration module 15, repairing information push module 16 and stop power supply information and pushes module 17.
Reporting fault message for repairment pushes module 1 and reports fault message for repairment in order to the user that will be reported to 95598 systems and be pushed to fault message receiver module 4;
Line fault information pushes module 2 and is pushed to fault message receiver module 4 in order to the switch changed position fault message that will be reported to power distribution automation management system (DMS);
Be pushed to fault message receiver module 4 with adopting fault message propelling movement module 3 in order to distribution transforming and user's fault message that will be reported to power information acquisition system (CSM);
Fault message pushes module 1 to fault message receiver module 4, line fault information pushes module 2 and pushes the next fault message of module 3 propelling movements with adopting fault message from reporting for repairment with verification in order to receive;
Fault message processing module 5 is stored in order to the fault message that fault message receiver module 4 is received; According to the power network line topological structure from the low-voltage customer to the high-tension apparatus; Carry out analytical integration with uniform data model, push to faulty equipment locating module 6 again;
The fault message of fault message sending module 6 in order to fault message processing module 5 is handled sent out passage outward through information and is sent to said faulty equipment locating module, and it generally is LAN that information is sent out passage outward;
Faulty equipment locating module 7 is used to receive the fault message that fault message sending module 6 sends, and obtains the actual geographical position and the account information of the source device relevant with fault message through existing power distribution management system (PMS);
Fault message screening module 8 is used for the fault message behind the equipment location is screened, and gets rid of the scheduled outage fault message and the confirmed fault message that have generated;
Line topological analysis module 9 is used for the adapted electric line under the fault message that filters out is carried out topological analysis, obtains the topological structure of this adapted electric line and the circuit charging equipment tabulation of associated topologies structure;
Equipment operation information analysis 10 modules are used for the circuit charging equipment of circuit charging equipment tabulation is carried out the cls analysis of calling together of equipment operation information step by step, and judge whether the circuit charging equipment exists fault;
Line switching analysis module 11 is used to the switch folding information that detects the On line switch on the adapted electric line and go out wiretap, and judges whether the adapted electric line exists line fault;
Failure analysis module 12 is used for confirming fault type, the position of fault and fault effects zone according to equipment operation information, switch folding information and topological structure; Fault type, the position of fault and fault effects zone are pushed to breakdown repair allocation schedule module 14, generate fault outage information and push to according to fault type, the position of fault and fault effects zone and stop power supply information propelling movement module 17;
Breakdown repair allocation schedule module 14 is used for confirming according to fault type, the position of fault and fault effects zone the repairing teams and groups and the scheduling recovery vehicle of fault;
Scene rush to repair administration module 15 is used to monitor and gather repairing personnel's the repairing procedural information and the information that restores electricity;
Repairing information pushes module 16 and is used for repairing procedural information is pushed to fault display module 13, and will the information of restoring electricity be pushed to and stops power supply information propelling movement module 17;
Fault display module 13 is used for having circuit charging equipment and the account information thereof of fault, the influence area and the repairing procedural information of adapted electric line through existing adapted power grid GIS system demonstration;
Stopping power supply information propelling movement module 17 is used for through existing 95598 customer service systems, short message service passage and fiber data passage the fault outage information and the information that restores electricity being influenced user's propelling movement to having a power failure.
The adapted electric network fault integrated conduct method of present embodiment adopts above-mentioned adapted electric network fault integrated treatment platform, and carries out following steps:
1) setting is reported fault message for repairment and is pushed module 1 in existing 95598 systems; Set up 95598 systems and report the Web service data-transmission channel that fault message pushes module 1 for repairment, the concrete user who pushes reports fault message for repairment and comprises: Customs Assigned Number, user's name, station address, contact method, fault content etc.
Line fault information is set in existing power distribution automation management system pushes module 2, set up the GPRS message information transmission passage (specifically being to utilize the SIM formation GPRS message information of the remote signalling displacement device that is arranged on switch to transmit passage) that power distribution automation management system and line fault information push module 2; The fault message that transmits is mainly out the displacement information that wiretap is operated a switch and On line switch is isolated, and the concrete switching information that transmits comprises: messages such as switch number, on off state, circuit number, affiliated factory station, three-phase current, three-phase voltage.
In existing power information acquisition system, be provided with adopting fault message and push module 3, set up the power information acquisition system and use the Web service data-transmission channel of adopting fault message propelling movement module 3; The distribution transforming that transmits and user's fault message comprise distribution transforming numbering, distribution transforming title, critical point numbering, ammeter numbering, critical point numbering and acquisition time etc.
2) reporting fault message for repairment pushes module 1 and will be reported to the user of existing 95598 systems to report fault message for repairment to be pushed to fault message receiver module 4;
Line fault information pushes module 2 and will be reported to the switch changed position fault message of existing power distribution automation management system (DMS) to be pushed to fault message receiver module 4;
To be reported to distribution transforming and user's fault message of existing power information acquisition system (CSM) to be pushed to fault message receiver module 4 with adopting fault message propelling movement module 3.
3) fault message pushes module 1, line fault information pushes module 2 and pushes the fault message that module 3 propelling movements come with adopting fault message from reporting for repairment for 4 receptions of fault message receiver module and verification; Fault message receiver module 4 is when receiving fault information data; Need the fault information data of separate sources is carried out verification; If the fault message of verification is an abnormal data, feed back to fault information data propelling movement side (operation system separately) to different fault information data sources; If the fault message of verification is a normal data, then push to fault message processing module 5.
4) fault message processing module 5 will be stored through the fault message of 4 receptions of fault message receiver module and verification; According to the power network line topological structure from the low-voltage customer to the high-tension apparatus; Carry out analytical integration with uniform data model, push to faulty equipment locating module 6 again;
Storage is: need classification and storage in the fault message table of type separately to the fault message of the separate sources that receives;
Analytical integration is: when data are carried out analytical integration; Top-down arrangement the in order of line topological structure according to mesolow; As: from user profile->ammeter information->distribution transforming information->On line switch information->transformer station's outlet switching information analyzes; And set up the relation (for example can inquire about the distribution transforming fault message) that can inquire about each other through user's fault message, the result who analyzes is stored in the analysis result table.
5) fault message sending module 6 will be sent out passage outside through information through fault message that fault message processing module 5 is handled and be sent to the faulty equipment locating module, and information is sent out passage outward and generally adopted LAN.
6) faulty equipment locating module 7 receives the fault message that fault message sending module 6 sends, and obtains the actual geographical position and the account information of the source device relevant with fault message through existing power distribution management system.
Concrete steps are: when said fault message is that 95598 users are when reporting fault message for repairment; According to the Customs Assigned Number that reports for repairment; Obtain low pressure ammeter box equipment that the user is associated or negative control device as source device through existing power distribution management system (PMS), and the unique coded query through low pressure ammeter box equipment or negative control device is to source device geographical coordinate information of reality and account information.When said fault message is that existing power information acquisition system is when reporting fault message or existing power distribution automation management system to report fault message; The distribution transforming, switch and the negative control device that obtain through existing power distribution management system according to asset of equipments numbering be as source device, and the unique coded query through distribution transforming, switch and negative control device is to source device geographical coordinate information of reality and account information.
7) fault message behind the 8 pairs of source devices of the fault message screening module location screens, and judges whether the fault message behind the source device location belongs to the scheduled outage fault message that has generated and confirmed fault message, and then eliminating in this way is not as being then to carry out next step.
Concrete screening step is: whether fault message screening module at first failure judgement information is the scheduled outage fault message that has generated, and the scheduled outage fault message is then got rid of this fault message and do not studied and judged in this way, and informs through 95598 systems and to report the user for repairment; As be not the scheduled outage fault message then failure judgement information whether be confirmed fault message, confirmed in this way fault message is then got rid of this fault message and is not is not studied and judged, and informs that through 95598 systems the user has confirmed the repairing situation of fault; As neither the scheduled outage fault message neither be confirmed fault message, then carry out next step.
8) line topological analysis module 9 is reviewed through power supply point the adapted electric line under the fault message that filters out is carried out topological analysis, obtains the topological structure of this adapted electric line and the circuit charging equipment tabulation of associated topologies structure.
The concrete analysis step is: at first carry out power supply point according to the actual geographical position of source device and review, form and review path (obtaining the topological structure of this adapted electric line); Collect power supply point then and review the circuit charging equipment on the path, circuit charging equipment equipment is classified, made up, form the tabulation of circuit charging equipment.
9) the circuit charging equipment during equipment operation information analysis module 10 is tabulated the circuit charging equipment carries out operation information step by step and calls cls analysis together; Judge according to the equipment operation information that analyzes whether the circuit charging equipment exists fault; Then carry out next step in this way; As be not that then failure judgement information is user's internal fault information, finish to study and judge.
The concrete analysis step is: go out wiretap, On line switch, distribution transforming, negative control device, low pressure ammeter box (circuit charging equipment) in the circuit charging equipment tabulation carry out operation information step by step and call survey together.If all move in the said equipment normally, the fault repairing information that causes inside to break down to report owing to client's self reason is described then.
10) line switching analysis module 11 detects the On line switch on the adapted electric line and goes out the switch folding information of wiretap, judges whether the adapted electric line exists line fault.
Specifically judge whether the adapted electric line exists the step of line fault to comprise:
1. if the outlet switch closure then judges it is the part line failure;
2. if going out wiretap breaks off, then judge it is the whole piece line failure;
3. if go out wiretap and On line switch all is in closure state, then judgement is that circuit does not break down but device fails.
11) failure analysis module 11 is confirmed fault type according to equipment operation information and switch folding information; Confirm the position of fault and fault effects zone according to topological structure; Fault type, the position of fault and fault effects zone are pushed to breakdown repair allocation schedule module 14, generate fault outage information and push to according to fault type, the position of fault and fault effects zone and stop power supply information propelling movement module 17.
Concrete steps are:
At first; According to the failure condition that the analysis result of the said equipment operating analysis and switch folding information is confirmed, further confirm the particular type (fault type comprises low district's fault, distribution transforming fault, middle pressure client's internal fault, part line fault and the circuit fault completely of presenting a theatrical performance as the last item on a programme) of fault; The detailed process of confirming fault type comprises:
A. report like the user transformers fault-free, confirm that then fault type is the low district's fault of presenting a theatrical performance as the last item on a programme;
B. have fault to report like user transformers, but the wireless switch of going up reports with the outlet switch fault, then definite fault type is the distribution transforming fault;
C. have fault to report like user transformers, and switch fault reports on wired, confirm that then fault type is a part line fault;
D. there is fault to report like user transformers, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely;
E. report like the negative control of user device fault-free, confirm that then fault type is middle pressure client internal fault;
F. have fault to report like the negative control of user device, and switch fault reports on wired, confirm that then fault type is a part line fault;
G. there is fault to report like the negative control of user device, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely.
12) breakdown repair allocation schedule module 12 is confirmed repairing teams and groups and scheduling recovery vehicle according to fault type, the position of fault and fault effects zone.
13) 13 monitoring of scene rush to repair administration module and collection repairing personnel's the repairing procedural information and the information that restores electricity.
14) repairing information pushes module 14, and the repairing procedural information pushes to fault display module 12, and will the information of restoring electricity be pushed to and stops power supply information and push module 17.
15) fault display module 12 exists circuit charging equipment and the account information thereof of fault, the influence area and the repairing procedural information of adapted electric line through existing adapted power grid GIS system demonstration;
16) stop power supply information propelling movement module 17 and the fault outage information and the information that restores electricity are influenced user's propelling movement to having a power failure through existing 95598 customer service systems, short message service passage and fiber data passage.
Embodiment two
The adapted electric network fault integrated treatment platform and the embodiment one of present embodiment are basic identical, and different is: also comprise being used for carrying out interactive interactive module 18 through short message service passage and fiber data passage and user; Interaction is meant that the user sends code and the user number inquiry stops sending electrical information. when code was power failure, interactive module 18 was according to user number inquiry client's region power failure information and Spoke-to-Client; When code when restoring electricity, interactive module 4 is according to restore electricity information and inform the user of user number inquiry client region.
The adapted electric network fault integrated conduct method and the embodiment one of present embodiment are basic identical, and different is:
1. increase execution in step 17): interactive module 18 is carried out interaction through short message channel and optical-fibre channel and user; Interaction is that the user sends code and the user number inquiry stops sending electrical information, and interactive module 4 is informed the user according to user number inquiring user region power failure information and restore electricity information and transmission.
2. the 1st) in the step, set up IEB bus service data between the module 2 and transmit passage and replace the GPRS message information to transmit passage through pushing in power distribution automation management system and line fault information.
3. the 7th) in the step, scheduled outage information and confirmed fault message do not need and inform through 95598 systems to report the user for repairment.
The present invention is not limited to the foregoing description, and the technical scheme that all employings and the invention described above technical scheme are equal to replacement all drops within protection scope of the present invention.

Claims (21)

1. adapted electric network fault integrated treatment platform; It is characterized in that: comprise that fault information acquisition system, fault message are studied and judged system and breakdown repair stops the information transmission system of supplying power, said fault information acquisition system comprises being arranged at and existing 95598 intrasystemly reports that fault message pushes module, the line fault information in the existing power distribution automation management system of being arranged at pushes module for repairment, is arranged at usefulness in the existing power information acquisition system and adopts fault message and push module, fault message receiver module, fault message processing module and fault message sending module; Said fault message is studied and judged system and is comprised faulty equipment locating module, fault message screening module, line topological analysis module, equipment operation information analysis module, line switching analysis module, failure analysis module and fault display module; The said breakdown repair information transmission system that stops supplying power comprises that breakdown repair allocation schedule module, scene rush to repair administration module, repairing information push module and stop power supply information and pushes module;
The said fault message that reports for repairment pushes module and reports fault message for repairment in order to the user that will be reported to 95598 systems and be pushed to said fault message receiver module;
Said line fault information pushes module and is pushed to said fault message receiver module in order to the switch changed position fault message that will be reported to the power distribution automation management system;
Said usefulness is adopted fault message propelling movement module and is pushed to said fault message receiver module in order to distribution transforming and user's fault message that will be reported to the power information acquisition system;
Fault message pushes module to said fault message receiver module, line fault information pushes module and pushes the next fault message of module propelling movement with adopting fault message from reporting for repairment with verification in order to receive;
Said fault message processing module is stored in order to the fault message that said fault message receiver module is received, and from the low-voltage customer to the high-tension apparatus, carries out analytical integration with uniform data model according to the power network line topological structure;
The fault message of said fault message sending module in order to the fault message processing module is handled sent out passage outward through information and is sent to said faulty equipment locating module;
Said faulty equipment locating module is used to receive the fault message that said fault message sending module sends, and obtains the actual geographical position and the account information of the source device relevant with fault message through existing power distribution management system;
Said fault message screening module is used for the fault message behind the equipment location is screened, and gets rid of the scheduled outage fault message and the confirmed fault message that have generated;
Said line topological analysis module is used for the adapted electric line under the fault message that filters out is carried out topological analysis, obtains the topological structure of this adapted electric line and the circuit charging equipment tabulation of associated topologies structure;
Said equipment operation information analysis module is used for the circuit charging equipment of circuit charging equipment tabulation is carried out the cls analysis of calling together of equipment operation information step by step, and judges whether the circuit charging equipment exists fault;
Said line switching analysis module is used to the switch folding information that detects the On line switch on the adapted electric line and go out wiretap, and judges whether the adapted electric line exists line fault;
Said failure analysis module is used for confirming fault type, the position of fault and fault effects zone according to equipment operation information, switch folding information and topological structure; Fault type, the position of fault and fault effects zone are pushed to breakdown repair allocation schedule module, generate fault outage information and push to according to fault type, the position of fault and fault effects zone and stop power supply information propelling movement module;
Said breakdown repair allocation schedule module is used for confirming according to fault type, the position of fault and fault effects zone the repairing teams and groups and the scheduling recovery vehicle of fault;
Said scene rush to repair administration module is used to monitor and gather repairing personnel's the repairing procedural information and the information that restores electricity;
Said repairing information pushes module and is used for repairing procedural information is pushed to said fault display module, and will the information of restoring electricity be pushed to and stops power supply information propelling movement module;
Said fault display module is used for having circuit charging equipment and the account information thereof of fault, the influence area and the repairing procedural information of adapted electric line through existing adapted power grid GIS system demonstration;
The said power supply information propelling movement module of stopping is used for through existing 95598 customer service systems, short message service passage and fiber data passage the fault outage information and the information that restores electricity being influenced user's propelling movement to having a power failure.
2. according to the said adapted electric network fault of claim 1 integrated treatment platform, it is characterized in that: also comprise being used for carrying out interactive interactive module through short message service passage and fiber data passage and user; Said interaction is that the user sends code and the user number inquiry stops sending electrical information, stops sending electrical information and transmission to inform the user by interactive module according to user number inquiring user region.
3. according to the said adapted electric network fault of claim 2 integrated treatment platform; It is characterized in that: the said fault message propelling movement module of reporting for repairment links through the Web service data-transmission channel with existing 95598 systems; Said line fault information pushes module and links through GPRS message information transmission passage or IEB bus service data transmission passage with existing power distribution automation management system; Said usefulness is adopted fault message propelling movement module and is linked through the Web service data-transmission channel with existing power information acquisition system; It is to utilize the SIM of the remote signalling displacement device that is arranged on switch to constitute that said GPRS message information transmits passage, and it is LAN that said information is sent out passage outward.
4. according to claim 1,2 or 3 said adapted electric network fault integrated treatment platforms, it is characterized in that: said storage be with the fault message classification and storage of the separate sources that receives in the fault message table of type separately; Said analytical integration is top-down arrangement the in order of line topological structure according to mesolow; Comprise from user profile->ammeter information->distribution transforming information->On line switch information->transformer station's outlet switching information analyzes; And set up the relation that can inquire about each other, the result who analyzes is stored in the analysis result table.
5. according to claim 1,2 or 3 said adapted electric network fault integrated treatment platforms, it is characterized in that: said user reports fault message for repairment and comprises Customs Assigned Number, user's name, station address, contact method and fault content; Said switch changed position fault message comprises the message of switch number, on off state, circuit number, affiliated factory station, three-phase current and three-phase voltage; Said distribution transforming and user's fault message comprise distribution transforming numbering, distribution transforming title, critical point numbering, ammeter numbering, critical point numbering and acquisition time.
6. according to claim 1,2 or 3 said adapted electric network fault integrated treatment platforms; It is characterized in that: said fault message comprises 95598 user's repairing information, and existing power information acquisition system reports fault message and existing power distribution automation management system to report fault message; Said fault type comprises low district's fault, distribution transforming fault, middle pressure client's internal fault, part line fault and the circuit fault completely of presenting a theatrical performance as the last item on a programme.
7. according to claim 1,2 or 3 said adapted electric network fault integrated treatment platforms; It is characterized in that: when said fault message is that 95598 users are when reporting fault message for repairment; Said source device is low pressure ammeter box equipment or the negative control device that is associated through the existing acquisition user of power distribution management system according to the Customs Assigned Number that reports for repairment, and actual geographical coordinate information of said source device and account information are to obtain through existing power distribution management system queries according to low pressure ammeter box equipment or negative unique coding of controlling device; When said fault message is an existing power information acquisition system when reporting fault message or existing power distribution automation management system to report fault message, said source device is distribution transforming, switch and the negative control device that obtains through existing power distribution management system according to the asset of equipments numbering; Actual geographical coordinate information of said source device and account information are to obtain through existing power distribution management system queries according to source distribution transforming, switch and negative unique coding of controlling device.
8. according to claim 1,2 or 3 said adapted electric network fault integrated treatment platforms, it is characterized in that: said controller switching equipment comprises circuit, switch, distribution transformer and middle pressure user, and said power failure influences equipment and comprises low-pressure meter case and middle pressure user.
9. an adapted electric network fault integrated conduct method adopts adapted electric network fault integrated treatment platform according to claim 1, and carries out following steps:
1) setting is reported fault message for repairment and is pushed module in existing 95598 systems, sets up 95598 systems and reports the Web service data-transmission channel that fault message pushes module for repairment;
Line fault information is set in existing power distribution automation management system pushes module, set up GPRS message information transmission passage or IEB bus service data transmission passage that power distribution automation management system and line fault information push module;
In existing power information acquisition system, be provided with adopting fault message and push module, set up the power information acquisition system and use the Web service data-transmission channel of adopting fault message propelling movement module;
2) reporting fault message for repairment pushes module and will be reported to the user of existing 95598 systems to report fault message for repairment to be pushed to the fault message receiver module;
Line fault information pushes module and will be reported to the switch changed position fault message of existing power distribution automation management system to be pushed to the fault message receiver module;
To be reported to distribution transforming and user's fault message of existing power information acquisition system to be pushed to the fault message receiver module with adopting fault message propelling movement module;
3) fault message pushes module, line fault information pushes module and pushes the next fault message of module propelling movement with adopting fault message from reporting for repairment for reception of fault message receiver module and verification;
4) the fault message processing module will be stored through the fault message of reception of fault message receiver module and verification, from the low-voltage customer to the high-tension apparatus, carry out analytical integration with uniform data model according to the power network line topological structure;
5) the fault message sending module will be sent out passage outside through information through fault message that the fault message processing module is handled and be sent to the faulty equipment locating module;
6) the faulty equipment locating module receives the fault message that the fault message sending module sends, and obtains the actual geographical position and the account information of the source device relevant with fault message through existing power distribution management system;
7) the fault message screening module is screened the fault message behind the source device location, judges whether the fault message behind the source device location belongs to scheduled outage fault message and the confirmed fault message that has generated, and then eliminating in this way is not as being then to carry out next step;
8) the line topological analysis module is reviewed through power supply point the adapted electric line under the fault message that filters out is carried out topological analysis, obtains the topological structure of this adapted electric line and the circuit charging equipment tabulation of associated topologies structure;
9) the circuit charging equipment during equipment operation information analysis module is tabulated the circuit charging equipment carries out equipment operation information step by step and calls cls analysis together; Judge according to the equipment operation information that analyzes whether the circuit charging equipment exists fault; Then carry out next step in this way; As be not that then failure judgement information is user's internal fault information, finish to study and judge;
10) the line switching analysis module detects the On line switch on the adapted electric line and goes out the switch folding information of wiretap, judges whether the adapted electric line exists line fault;
11) failure analysis module is confirmed fault type according to said equipment operation information and switch folding information; Confirm the position of fault and fault effects zone according to said topological structure; Fault type, the position of fault and fault effects zone are pushed to breakdown repair allocation schedule module, generate fault outage information and push to according to fault type, the position of fault and fault effects zone and stop power supply information propelling movement module;
12) breakdown repair allocation schedule module is confirmed the repairing teams and groups and the scheduling recovery vehicle of fault according to fault type, the position of fault and fault effects zone;
13) monitoring of scene rush to repair administration module and collection repairing personnel's the repairing procedural information and the information that restores electricity;
14) repairing information pushes module and will rush to repair procedural information and push to the fault display module, and will the information of restoring electricity be pushed to and stops power supply information propelling movement module;
15) fault display module 3 exists circuit charging equipment and the account information thereof of fault, the influence area and the repairing procedural information of adapted electric line through existing adapted power grid GIS system demonstration;
16) stop power supply information propelling movement module and the fault outage information and the information that restores electricity are influenced user's propelling movement to having a power failure through existing 95598 customer service systems, short message service passage and fiber data passage.
10. according to the said adapted electric network fault of claim 9 integrated conduct method; It is characterized in that adopting like the said adapted electric network fault of claim 2 integrated treatment platform and increase and carry out the 17th) step: interactive module is carried out interaction through short message service passage and fiber data passage and user; Said interaction is that the user sends code and the user number inquiry stops sending electrical information, stops sending electrical information and transmission to inform the user by interactive module according to user number inquiring user region.
11., it is characterized in that: the 3rd according to claim 9 or 10 said adapted electric network fault integrated conduct methods) in the step,, feed back to fault message propelling movement side to different fault message sources if the fault message of verification is an abnormal data; If the fault message of verification is a normal data, then push to the fault message processing module.
12., it is characterized in that: the 4th according to claim 9 or 10 said adapted electric network fault integrated conduct methods) in the step, said storage be with the fault message classification and storage of the separate sources that receives in the fault message table of type separately; Said analytical integration is top-down arrangement the in order of line topological structure according to mesolow; Comprise from user profile->ammeter information->distribution transforming information->On line switch information->transformer station's outlet switching information analyzes; And set up the relation that can inquire about each other, the result who analyzes is stored in the analysis result table.
13. according to claim 9 or 10 said adapted electric network fault integrated conduct methods, it is characterized in that: it is to utilize the SIM of the remote signalling displacement device that is arranged on switch to constitute that said GPRS message information transmits passage; It is LAN that said information is sent out passage outward; Said user reports fault message for repairment and comprises Customs Assigned Number, user's name, station address, contact method and fault content; Said switch changed position fault message comprises the message of switch number, on off state, circuit number, affiliated factory station, three-phase current and three-phase voltage; Said distribution transforming and user's fault message comprise distribution transforming numbering, distribution transforming title, critical point numbering, ammeter numbering, critical point numbering and acquisition time.
14. according to claim 9 or 10 said adapted electric network fault integrated conduct methods; It is characterized in that: the said the 6th) in the step; When said fault message is that 95598 users are when reporting fault message for repairment; Obtain low pressure ammeter box equipment that the user is associated or negative control device as source device according to the Customs Assigned Number that reports for repairment through existing power distribution management system, and the unique coded query through low pressure ammeter box equipment or negative control device is to source device geographical coordinate information of reality and account information.
15. according to claim 9 or 10 said adapted electric network fault integrated conduct methods; It is characterized in that: the said the 6th) in the step; When said fault message is that existing power information acquisition system is when reporting fault message or existing power distribution automation management system to report fault message; Obtain distribution transforming, switch and negative control device as source device according to asset of equipments numbering through existing power distribution management system, and the unique coded query through distribution transforming, switch and negative control device is to source device geographical coordinate information of reality and account information.
16. according to claim 9 or 10 said adapted electric network fault integrated conduct methods; It is characterized in that: the said the 7th) in the step; Whether fault message screening module at first failure judgement information is the scheduled outage fault message that has generated; Then get rid of this fault message in this way and do not study and judge, and inform through 95598 systems and to report the user for repairment, as not being that then whether failure judgement information is confirmed fault message; Then get rid of this fault message in this way and do not study and judge, and inform that through 95598 systems the user has confirmed the repairing situation of fault; As neither the scheduled outage fault message neither confirmed fault message, then carry out next step.
17. according to claim 9 or 10 said adapted electric network fault integrated conduct methods; It is characterized in that: the said the 8th) in the step; It is to carry out power supply point according to the actual geographical position of source device to review and form and review the path that said power supply point is reviewed; Collect power supply point then and review the circuit charging equipment on the path, circuit charging equipment equipment is classified, made up, form the tabulation of circuit charging equipment.
18., it is characterized in that: the said the 9th according to claim 9 or 10 said adapted electric network fault integrated conduct methods) in the step, said circuit charging equipment is wiretap, On line switch, distribution transforming, negative control device and low pressure ammeter box.
19., it is characterized in that: the said the 10th according to claim 9 or 10 said adapted electric network fault integrated conduct methods) in the step, saidly judge whether the adapted electric line exists line fault to comprise:
1. if the outlet switch closure then judges it is the part line failure;
2. if going out wiretap breaks off, then judge it is the whole piece line failure;
3. if go out wiretap and On line switch all is in closure state, then judgement is that circuit does not break down but device fails.
20., it is characterized in that: the said the 11st according to claim 9 or 10 said adapted electric network fault integrated conduct methods) in the step, said definite fault type comprises:
A. report like the user transformers fault-free, confirm that then fault type is the low district's fault of presenting a theatrical performance as the last item on a programme;
B. have fault to report like user transformers, but the wireless switch of going up reports with the outlet switch fault, then definite fault type is the distribution transforming fault;
C. have fault to report like user transformers, and switch fault reports on wired, confirm that then fault type is a part line fault;
D. there is fault to report like user transformers, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely;
E. report like the negative control of user device fault-free, confirm that then fault type is middle pressure client internal fault;
F. have fault to report like the negative control of user device, and switch fault reports on wired, confirm that then fault type is a part line fault;
G. there is fault to report like the negative control of user device, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely.
21. according to claim 9 or 10 said adapted electric network fault integrated conduct methods; It is characterized in that: the said the 7th) in the step; Whether fault message screening module at first failure judgement information is the scheduled outage fault message that has generated; Then get rid of this fault message in this way and do not study and judge, and inform through 95598 systems and to report the user for repairment; As be not scheduled outage then failure judgement information whether be confirmed fault message, then get rid of this fault message in this way and do not study and judge, and inform that through 95598 systems the user has confirmed the repairing situation of fault; As neither the scheduled outage fault message neither be confirmed fault message, then carry out next step;
The said the 8th) in the step; It is to carry out power supply point according to the actual geographical position of source device to review and form and review the path that said power supply point is reviewed; Collect power supply point then and review the circuit charging equipment on the path; Circuit charging equipment equipment is classified, made up, form the tabulation of circuit charging equipment;
The said the 9th) in the step, said circuit charging equipment is wiretap, On line switch, distribution transforming, negative control device and low pressure ammeter box;
The said the 10th) in the step, if the outlet switch closure then judges it is the part line failure; Break off if go out wiretap, then judge it is the whole piece line failure; If go out wiretap and On line switch all is in closure state, then judgement is that circuit does not break down but device fails;
The said the 11st) in the step, said definite fault type comprises:
A. report like the user transformers fault-free, confirm that then fault type is the low district's fault of presenting a theatrical performance as the last item on a programme;
B. have fault to report like user transformers, but the wireless switch of going up reports with the outlet switch fault, then definite fault type is the distribution transforming fault;
C. have fault to report like user transformers, and switch fault reports on wired, confirm that then fault type is a part line fault;
D. there is fault to report like user transformers, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely;
E. report like the negative control of user device fault-free, confirm that then fault type is middle pressure client internal fault;
F. have fault to report like the negative control of user device, and switch fault reports on wired, confirm that then fault type is a part line fault;
G. there is fault to report like the negative control of user device, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely.
CN2011103967094A 2011-12-04 2011-12-04 Fault comprehensive processing platform and method of distribution network Active CN102570602B (en)

Priority Applications (5)

Application Number Priority Date Filing Date Title
CN2011103967094A CN102570602B (en) 2011-12-04 2011-12-04 Fault comprehensive processing platform and method of distribution network
CN201310489872.4A CN103516054B (en) 2011-12-04 2011-12-04 Power distribution network fault automatic processing method
CN201310489657.4A CN103490521B (en) 2011-12-04 2011-12-04 Intelligent power distribution network fault treatment platform
CN201310489820.7A CN103501051B (en) 2011-12-04 2011-12-04 Power distribution network fault processing platform
CN201310489744.XA CN103501050B (en) 2011-12-04 2011-12-04 Power distribution network fault integrated treatment platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011103967094A CN102570602B (en) 2011-12-04 2011-12-04 Fault comprehensive processing platform and method of distribution network

Related Child Applications (10)

Application Number Title Priority Date Filing Date
CN201310489872.4A Division CN103516054B (en) 2011-12-04 2011-12-04 Power distribution network fault automatic processing method
CN201310489711.5A Division CN103490522A (en) 2011-12-04 2011-12-04 Intelligent power distribution network fault treatment method
CN201310490103.6A Division CN103501053B (en) 2011-12-04 2011-12-04 Comprehensive fault handling system for power distribution and consumption network
CN201310490158.7A Division CN103501054A (en) 2011-12-04 2011-12-04 Fault handling method for power distribution network
CN201310490038.7A Division CN103501052A (en) 2011-12-04 2011-12-04 Comprehensive fault handling method for power distribution and consumption network
CN201310489560.3A Division CN103490520B (en) 2011-12-04 2011-12-04 Power distribution network fault treatment method
CN201310489657.4A Division CN103490521B (en) 2011-12-04 2011-12-04 Intelligent power distribution network fault treatment platform
CN201310489820.7A Division CN103501051B (en) 2011-12-04 2011-12-04 Power distribution network fault processing platform
CN201310489744.XA Division CN103501050B (en) 2011-12-04 2011-12-04 Power distribution network fault integrated treatment platform
CN201310490067.3A Division CN103490523B (en) 2011-12-04 2011-12-04 Intelligent power distribution network fault treatment system

Publications (2)

Publication Number Publication Date
CN102570602A true CN102570602A (en) 2012-07-11
CN102570602B CN102570602B (en) 2013-10-30

Family

ID=46415309

Family Applications (5)

Application Number Title Priority Date Filing Date
CN2011103967094A Active CN102570602B (en) 2011-12-04 2011-12-04 Fault comprehensive processing platform and method of distribution network
CN201310489744.XA Active CN103501050B (en) 2011-12-04 2011-12-04 Power distribution network fault integrated treatment platform
CN201310489657.4A Active CN103490521B (en) 2011-12-04 2011-12-04 Intelligent power distribution network fault treatment platform
CN201310489820.7A Active CN103501051B (en) 2011-12-04 2011-12-04 Power distribution network fault processing platform
CN201310489872.4A Active CN103516054B (en) 2011-12-04 2011-12-04 Power distribution network fault automatic processing method

Family Applications After (4)

Application Number Title Priority Date Filing Date
CN201310489744.XA Active CN103501050B (en) 2011-12-04 2011-12-04 Power distribution network fault integrated treatment platform
CN201310489657.4A Active CN103490521B (en) 2011-12-04 2011-12-04 Intelligent power distribution network fault treatment platform
CN201310489820.7A Active CN103501051B (en) 2011-12-04 2011-12-04 Power distribution network fault processing platform
CN201310489872.4A Active CN103516054B (en) 2011-12-04 2011-12-04 Power distribution network fault automatic processing method

Country Status (1)

Country Link
CN (5) CN102570602B (en)

Cited By (59)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103149548A (en) * 2013-01-31 2013-06-12 重庆市电力公司电力科学研究院 Method and device of information display based on electric energy metering device
CN103268571A (en) * 2013-04-28 2013-08-28 北京臻迪科技有限公司 Method and system for displaying power equipment status
CN103279841A (en) * 2013-06-09 2013-09-04 广东电网公司佛山供电局 Pushing method and system of power utilization information
CN103427417A (en) * 2013-07-31 2013-12-04 国电南瑞科技股份有限公司 Power distribution network fault processing method based on multi-source information fusion
CN103490521A (en) * 2011-12-04 2014-01-01 江苏省电力公司南京供电公司 Intelligent power distribution network fault treatment platform
CN103837796A (en) * 2014-03-12 2014-06-04 国家电网公司 Transmission line malfunction visualized report method and system based on Web and GIS
CN103869217A (en) * 2012-12-07 2014-06-18 国家电网公司 Method and device for power grid fault matching and analysis
CN103903184A (en) * 2012-12-24 2014-07-02 天津市电力公司 Method for processing information between power distribution network first-aid repair command platform and mobile terminal
CN103915827A (en) * 2014-03-14 2014-07-09 国网山东省电力公司青岛供电公司 Power distribution network fault studying and judging method and system
CN104182815A (en) * 2012-10-22 2014-12-03 国网山东省电力公司青岛供电公司 Power supply reliability acquisition method and system
CN104218485A (en) * 2014-09-23 2014-12-17 国网河南省电力公司周口供电公司 Power grid quick rush-repair control system and using method thereof
CN104219070A (en) * 2013-05-31 2014-12-17 华为技术有限公司 Network fault monitoring method and network fault monitoring system
CN104269926A (en) * 2014-09-30 2015-01-07 国家电网公司 Power utilization information comprehensive acquisition system for power supply guaranteeing platform
CN104281979A (en) * 2014-09-26 2015-01-14 广东电网有限责任公司电力科学研究院 Method and system for detecting distribution room low-voltage fault type of distribution transformer
CN104362738A (en) * 2014-10-14 2015-02-18 深圳市三江电气有限公司 Intelligent power transmission and distribution equipment
CN104504513A (en) * 2014-12-17 2015-04-08 昆明能讯科技有限责任公司 Quick collection method for power grid line equipment based on configuration library
CN104678258A (en) * 2015-02-27 2015-06-03 国家电网公司 Method for actively studying and judging power distribution network fault based on public/specific transformer information
CN104933502A (en) * 2014-11-27 2015-09-23 国网山东省电力公司应急管理中心 Emergency intelligent unified communication scheduling system based on power grid GIS and scheduling method thereof
CN105025107A (en) * 2015-07-28 2015-11-04 国网北京市电力公司 Power failure information processing method, client and server
CN105048630A (en) * 2015-09-24 2015-11-11 国网天津武清供电有限公司 Intelligent scheduling control system and method based on data automatic analysis system
CN105207121A (en) * 2015-09-23 2015-12-30 国家电网公司 Power distribution network fault emergency maintenance method based on topology analysis
CN105277851A (en) * 2015-10-16 2016-01-27 国网甘肃省电力公司天水供电公司 Distribution network fault judgment searching and positioning system
CN105303316A (en) * 2015-11-01 2016-02-03 国网山东省电力公司聊城供电公司 National power grid distribution network fault processing system
CN105334839A (en) * 2015-12-16 2016-02-17 国家电网公司 10kV distribution network equipment management system
CN105429144A (en) * 2015-12-31 2016-03-23 国网浙江奉化市供电公司 Information processing method and information processing device for emergency repairing of distribution network
CN105699760A (en) * 2016-01-22 2016-06-22 国网冀北电力有限公司电力科学研究院 Electric energy metering equipment and method for analyzing operating condition of power utilization information collection equipment
CN105700506A (en) * 2016-04-29 2016-06-22 南京信息职业技术学院 Remote transformer substation temperature and humidity control system
CN105809373A (en) * 2016-04-27 2016-07-27 国网山东省电力公司济南市长清区供电公司 Distribution network fault information comprehensive collection and management platform
CN105967063A (en) * 2016-05-16 2016-09-28 上海振华重工电气有限公司 Failure analyzing and handling system and method of maintenance platform
CN106230120A (en) * 2016-09-09 2016-12-14 国家电网公司 A kind of method of supplying power to
CN106291245A (en) * 2016-08-25 2017-01-04 国网山东省电力公司青岛供电公司 A kind of distribution network failure actively generates and sends repaiies method and apparatus
CN106815373A (en) * 2017-02-10 2017-06-09 国网山东省电力公司 Big data methods of exhibiting and system are rushed to repair in distribution based on BI analyses
CN106814286A (en) * 2017-02-10 2017-06-09 国网山东省电力公司 Distribution Fault Location System, method and server based on polynary fault collection
CN106841908A (en) * 2016-12-19 2017-06-13 国电南瑞科技股份有限公司 The visual presentation method of the distribution network failure positioning based on power grid GIS
CN106872856A (en) * 2017-03-01 2017-06-20 国网山东省电力公司 Distribution network failure based on polynary fault collection actively rushes to repair system, method
CN106960283A (en) * 2017-03-27 2017-07-18 国网山东省电力公司夏津县供电公司 Special transformer acquisition terminal fault handling method, device and system
CN106980071A (en) * 2017-05-16 2017-07-25 国网山东省电力公司 Repairing system and its method of work are visualized based on power grid GIS
CN106990328A (en) * 2017-05-16 2017-07-28 国网山东省电力公司 The analysis of distribution repairing abnormal data, fault location system and method
CN107147215A (en) * 2017-05-16 2017-09-08 国网山东省电力公司 The Distribution Fault Location System and method of combined circuit overload data analysis
CN107171436A (en) * 2017-05-08 2017-09-15 国网山东省电力公司烟台供电公司 It is a kind of automatic screening information and the supervising device and its monitoring method of crash analysis to be carried out
CN107167704A (en) * 2017-05-16 2017-09-15 国网山东省电力公司 Fault Diagnosis of Distribution Network system and method based on CIM
CN107516891A (en) * 2016-06-17 2017-12-26 中兴通讯股份有限公司 The power consumption control method, apparatus and equipment of a kind of communication power supply
CN107765123A (en) * 2017-10-19 2018-03-06 中领世能(天津)科技有限公司 Detected rule update method and Electrical Safety monitoring system
CN108107318A (en) * 2017-11-03 2018-06-01 国网北京市电力公司 The localization method and device of user malfunction
CN108460468A (en) * 2018-01-23 2018-08-28 国网江西省电力有限公司电力科学研究院 It is a kind of public to become failure event management method and device
CN108539736A (en) * 2018-04-26 2018-09-14 广州供电局有限公司 Power-off event analysis method, system and computer equipment based on multi-source data
CN108539856A (en) * 2018-04-28 2018-09-14 国网河南省电力公司周口供电公司 Power distribution network complete perception operation monitoring power distribution rush-repair system
CN108734381A (en) * 2018-04-11 2018-11-02 国网山东省电力公司 A kind of outage information collaborative management method, apparatus and system
CN108875975A (en) * 2018-06-27 2018-11-23 国网甘肃省电力公司金昌供电公司 A kind of excellent dress system of wisdom precisely informed based on client's outage information
CN109193946A (en) * 2018-10-22 2019-01-11 国家电网有限公司 Repairing information issuing system towards power consumer
CN109447284A (en) * 2018-10-22 2019-03-08 国家电网有限公司 Distribution Network Failure method for sending information and system for electric service maneuvering platform
CN109460833A (en) * 2018-10-22 2019-03-12 国家电网有限公司 The device data of Distribution Network Failure and report work order data processing method and system for repairment
CN110738329A (en) * 2019-09-06 2020-01-31 国网浙江桐乡市供电有限公司 first-aid repair informing method based on cloud platform
CN111262344A (en) * 2020-03-30 2020-06-09 佛山科学技术学院 Power grid monitoring emergency system
CN111931511A (en) * 2019-04-26 2020-11-13 中国电力科学研究院有限公司 Semantic analysis method and system based on wide-area distributed architecture
CN112162174A (en) * 2020-09-03 2021-01-01 国电南瑞科技股份有限公司 Distribution room fault positioning method and system based on marketing and distribution integration
CN112769231A (en) * 2020-12-24 2021-05-07 深圳供电局有限公司 Main distribution integrated alarm pushing method and device of intelligent power grid dispatching control system
WO2022021549A1 (en) * 2020-07-31 2022-02-03 广东卓维网络有限公司 Power consumption emergency management system
CN115575765A (en) * 2022-10-31 2023-01-06 国网浙江省电力有限公司金华供电公司 Ground fault section selection analysis system based on four-area data of distribution automation

Families Citing this family (32)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103501054A (en) * 2011-12-04 2014-01-08 江苏省电力公司南京供电公司 Fault handling method for power distribution network
CN103501053B (en) * 2011-12-04 2015-05-13 江苏省电力公司南京供电公司 Comprehensive fault handling system for power distribution and consumption network
CN103501052A (en) * 2011-12-04 2014-01-08 江苏省电力公司南京供电公司 Comprehensive fault handling method for power distribution and consumption network
CN103490523B (en) * 2011-12-04 2015-05-13 江苏省电力公司南京供电公司 Intelligent power distribution network fault treatment system
CN104091202A (en) * 2014-07-11 2014-10-08 国家电网公司 Power distribution network power supply capacity risk assessment method
CN104079075B (en) * 2014-07-24 2016-06-01 国网黑龙江省电力有限公司双鸭山供电公司 Dispatching automation novel maintenance terminal and its implementation
CN104317821A (en) * 2014-09-29 2015-01-28 国家电网公司 Method for checking power failure information by using image technology
CN104394020A (en) * 2014-12-04 2015-03-04 国家电网公司 Automatic fault processing and safety control system and method for power information collection device
CN104753178A (en) * 2015-04-16 2015-07-01 河南行知专利服务有限公司 Power grid fault handling system
CN104751305A (en) * 2015-04-28 2015-07-01 国网上海市电力公司 Trouble analysis and repair-based intelligent interaction system and control method thereof
CN105049223B (en) * 2015-05-29 2018-06-15 国家电网公司 A kind of power telecom network defect troubleshooting decision assistant analysis method
CN105320113B (en) * 2015-10-19 2018-04-10 国家电网公司 The information interacting method of power network spatial Information Service platform and electrical power distribution automatization system
CN105509728A (en) * 2015-11-02 2016-04-20 湖南红太阳新能源科技有限公司 Photovoltaic power station failure equipment navigation method and system
CN105259896B (en) * 2015-11-11 2018-03-20 国网山西省电力公司大同供电公司 A kind of method for diagnosing faults based on power dispatch data network
CN106302113A (en) * 2016-08-05 2017-01-04 海南电保姆科技有限公司 Feedback information treating method and apparatus
CN106355357B (en) * 2016-10-12 2021-04-30 深圳供电局有限公司 Power distribution network fault processing method and information processing system
CN107766949A (en) * 2017-09-19 2018-03-06 河海大学 Failure rapid rush-repair commander's business information exchange method based on meta-model
CN107730397A (en) * 2017-09-20 2018-02-23 国网天津市电力公司 A kind of energy coordination approach for ensureing the low-voltage region quality of power supply
CN108512223B (en) * 2018-04-11 2020-07-03 江苏电力信息技术有限公司 Intelligent auxiliary studying and judging method for switching tripping of substation in power transmission and transformation operation and detection control platform
CN109523038A (en) * 2018-10-30 2019-03-26 深圳供电局有限公司 A kind of gridding outage analysis method and system
CN109871965A (en) * 2019-01-21 2019-06-11 长沙理工大学 A kind of breakdown repair App platform of combination GIS and power customer fault location information
CN109814000A (en) * 2019-01-30 2019-05-28 国家电网有限公司 A kind of control system and its application method for power grid rapid rush-repair
CN109934273A (en) * 2019-03-01 2019-06-25 长沙理工大学 It is a kind of based on the fault characteristic of DML-KNN algorithm and active damage repair technology draw a portrait new method
CN110441655B (en) * 2019-08-08 2022-08-12 中广核玉溪元江风力发电有限公司 Lightning grounding fault monitoring system for wind power plant current collecting line
CN110648482B (en) * 2019-09-30 2021-07-06 武汉理工光科股份有限公司 Distributed vibration optical cable positioning method and system based on long-distance oil and gas pipeline GIS
CN111181245A (en) * 2020-01-07 2020-05-19 广东卓维网络有限公司 Intelligent power consumption management system
CN111579917A (en) * 2020-04-08 2020-08-25 广西电网有限责任公司北海供电局 Low-voltage distribution network fault positioning system and method
CN112070243A (en) * 2020-07-08 2020-12-11 国网浙江杭州市富阳区供电有限公司 Multi-channel automatic pushing method for power grid fault information
CN113447882B (en) * 2021-06-01 2022-09-09 国网河北省电力有限公司营销服务中心 Fault processing method based on electric energy meter, server and terminal
CN114021999A (en) * 2021-11-09 2022-02-08 国网山东省电力公司信息通信公司 Full scene power grid dispatching exchange network management and control system and method
CN114336551A (en) * 2022-01-14 2022-04-12 贵州大学 Flexible direct current transmission system fault protection system based on MMC
CN116111591B (en) * 2023-04-12 2023-07-04 广东电网有限责任公司佛山供电局 Distribution network line rapid power restoration capability analysis method and system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101951027A (en) * 2010-09-01 2011-01-19 中国电力科学研究院 Uniform data acquisition and monitoring system of low-medium voltage power distribution network
CN102208048A (en) * 2011-03-15 2011-10-05 福建省电力有限公司 Technology support system of marketing and distribution integration power supply service and method thereof
EP2388883A1 (en) * 2009-01-13 2011-11-23 Hitachi, Ltd. Power demand-supply management server and power demand-supply management system
CN202475009U (en) * 2011-12-04 2012-10-03 江苏省电力公司南京供电公司 Comprehensive processing system of failure of power distribution and supply grid

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103501054A (en) * 2011-12-04 2014-01-08 江苏省电力公司南京供电公司 Fault handling method for power distribution network
CN103490520B (en) * 2011-12-04 2015-05-13 江苏省电力公司南京供电公司 Power distribution network fault treatment method
CN103501053B (en) * 2011-12-04 2015-05-13 江苏省电力公司南京供电公司 Comprehensive fault handling system for power distribution and consumption network
CN103490522A (en) * 2011-12-04 2014-01-01 江苏省电力公司南京供电公司 Intelligent power distribution network fault treatment method
CN103501052A (en) * 2011-12-04 2014-01-08 江苏省电力公司南京供电公司 Comprehensive fault handling method for power distribution and consumption network
CN102570602B (en) * 2011-12-04 2013-10-30 江苏省电力公司南京供电公司 Fault comprehensive processing platform and method of distribution network
CN103490523B (en) * 2011-12-04 2015-05-13 江苏省电力公司南京供电公司 Intelligent power distribution network fault treatment system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2388883A1 (en) * 2009-01-13 2011-11-23 Hitachi, Ltd. Power demand-supply management server and power demand-supply management system
CN101951027A (en) * 2010-09-01 2011-01-19 中国电力科学研究院 Uniform data acquisition and monitoring system of low-medium voltage power distribution network
CN102208048A (en) * 2011-03-15 2011-10-05 福建省电力有限公司 Technology support system of marketing and distribution integration power supply service and method thereof
CN202475009U (en) * 2011-12-04 2012-10-03 江苏省电力公司南京供电公司 Comprehensive processing system of failure of power distribution and supply grid

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
凌永玉: "省级电力公司客户服务中心系统分析与设计", 《中国优秀硕士学位论文全文数据库》 *

Cited By (88)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103490521A (en) * 2011-12-04 2014-01-01 江苏省电力公司南京供电公司 Intelligent power distribution network fault treatment platform
CN103490521B (en) * 2011-12-04 2015-09-30 江苏省电力公司南京供电公司 Intelligent power distribution network fault treatment platform
CN103501050B (en) * 2011-12-04 2016-01-27 江苏省电力公司南京供电公司 Power distribution network fault integrated treatment platform
CN103501050A (en) * 2011-12-04 2014-01-08 江苏省电力公司南京供电公司 Comprehensive fault handling platform for power distribution and consumption network
CN104182815A (en) * 2012-10-22 2014-12-03 国网山东省电力公司青岛供电公司 Power supply reliability acquisition method and system
CN104182815B (en) * 2012-10-22 2017-04-05 国网山东省电力公司青岛供电公司 A kind of power supply reliability acquisition methods and system
CN103869217A (en) * 2012-12-07 2014-06-18 国家电网公司 Method and device for power grid fault matching and analysis
CN103903184A (en) * 2012-12-24 2014-07-02 天津市电力公司 Method for processing information between power distribution network first-aid repair command platform and mobile terminal
CN103149548B (en) * 2013-01-31 2015-11-18 重庆市电力公司电力科学研究院 A kind of method for information display based on electric power meter and device
CN103149548A (en) * 2013-01-31 2013-06-12 重庆市电力公司电力科学研究院 Method and device of information display based on electric energy metering device
CN103268571A (en) * 2013-04-28 2013-08-28 北京臻迪科技有限公司 Method and system for displaying power equipment status
CN103268571B (en) * 2013-04-28 2016-08-24 北京臻迪科技股份有限公司 Status of electric power display packing and system
CN104219070A (en) * 2013-05-31 2014-12-17 华为技术有限公司 Network fault monitoring method and network fault monitoring system
CN103279841A (en) * 2013-06-09 2013-09-04 广东电网公司佛山供电局 Pushing method and system of power utilization information
CN103279841B (en) * 2013-06-09 2016-12-28 广东电网公司佛山供电局 The method for pushing of a kind of power information and system
CN103427417A (en) * 2013-07-31 2013-12-04 国电南瑞科技股份有限公司 Power distribution network fault processing method based on multi-source information fusion
CN103837796A (en) * 2014-03-12 2014-06-04 国家电网公司 Transmission line malfunction visualized report method and system based on Web and GIS
CN103837796B (en) * 2014-03-12 2016-09-07 国家电网公司 The transmission line malfunction visualization report method of a kind of sing on web and GIS and system
CN103915827A (en) * 2014-03-14 2014-07-09 国网山东省电力公司青岛供电公司 Power distribution network fault studying and judging method and system
CN103915827B (en) * 2014-03-14 2016-08-24 国网山东省电力公司青岛供电公司 Power distribution network fault analysis method and study and judge system
CN105785201B (en) * 2014-03-14 2018-08-17 国网山东省电力公司青岛供电公司 A kind of power distribution network fault analysis method and study and judge system
CN105785201A (en) * 2014-03-14 2016-07-20 国网山东省电力公司青岛供电公司 Adapted power grid fault research and judging method and research and judging system thereof
CN104218485A (en) * 2014-09-23 2014-12-17 国网河南省电力公司周口供电公司 Power grid quick rush-repair control system and using method thereof
CN104281979A (en) * 2014-09-26 2015-01-14 广东电网有限责任公司电力科学研究院 Method and system for detecting distribution room low-voltage fault type of distribution transformer
CN104281979B (en) * 2014-09-26 2018-05-04 广东电网有限责任公司电力科学研究院 Distribution transformer platform area low voltage failure type detection method and system
CN104269926A (en) * 2014-09-30 2015-01-07 国家电网公司 Power utilization information comprehensive acquisition system for power supply guaranteeing platform
CN104362738A (en) * 2014-10-14 2015-02-18 深圳市三江电气有限公司 Intelligent power transmission and distribution equipment
CN104933502A (en) * 2014-11-27 2015-09-23 国网山东省电力公司应急管理中心 Emergency intelligent unified communication scheduling system based on power grid GIS and scheduling method thereof
CN104504513A (en) * 2014-12-17 2015-04-08 昆明能讯科技有限责任公司 Quick collection method for power grid line equipment based on configuration library
CN104678258B (en) * 2015-02-27 2017-08-01 国家电网公司 It is a kind of specially to become the method that information to distribution network failure actively study and judge based on public
CN104678258A (en) * 2015-02-27 2015-06-03 国家电网公司 Method for actively studying and judging power distribution network fault based on public/specific transformer information
CN105025107A (en) * 2015-07-28 2015-11-04 国网北京市电力公司 Power failure information processing method, client and server
CN105207121A (en) * 2015-09-23 2015-12-30 国家电网公司 Power distribution network fault emergency maintenance method based on topology analysis
CN105048630A (en) * 2015-09-24 2015-11-11 国网天津武清供电有限公司 Intelligent scheduling control system and method based on data automatic analysis system
CN105277851A (en) * 2015-10-16 2016-01-27 国网甘肃省电力公司天水供电公司 Distribution network fault judgment searching and positioning system
CN105303316A (en) * 2015-11-01 2016-02-03 国网山东省电力公司聊城供电公司 National power grid distribution network fault processing system
CN105334839B (en) * 2015-12-16 2018-01-09 国家电网公司 10kV distribution net equipment management systems
CN105334839A (en) * 2015-12-16 2016-02-17 国家电网公司 10kV distribution network equipment management system
CN105429144A (en) * 2015-12-31 2016-03-23 国网浙江奉化市供电公司 Information processing method and information processing device for emergency repairing of distribution network
CN105699760B (en) * 2016-01-22 2018-09-18 国网冀北电力有限公司电力科学研究院 The operating condition analysis method of electric energy measuring equipment and power information collecting device
CN105699760A (en) * 2016-01-22 2016-06-22 国网冀北电力有限公司电力科学研究院 Electric energy metering equipment and method for analyzing operating condition of power utilization information collection equipment
CN105809373A (en) * 2016-04-27 2016-07-27 国网山东省电力公司济南市长清区供电公司 Distribution network fault information comprehensive collection and management platform
CN105700506A (en) * 2016-04-29 2016-06-22 南京信息职业技术学院 Remote transformer substation temperature and humidity control system
CN105967063A (en) * 2016-05-16 2016-09-28 上海振华重工电气有限公司 Failure analyzing and handling system and method of maintenance platform
CN105967063B (en) * 2016-05-16 2018-08-14 上海振华重工电气有限公司 Maintenance platform fault analysis process system and method
CN107516891A (en) * 2016-06-17 2017-12-26 中兴通讯股份有限公司 The power consumption control method, apparatus and equipment of a kind of communication power supply
CN107516891B (en) * 2016-06-17 2022-06-03 中兴通讯股份有限公司 Power utilization control method, device and equipment for communication power supply
CN106291245A (en) * 2016-08-25 2017-01-04 国网山东省电力公司青岛供电公司 A kind of distribution network failure actively generates and sends repaiies method and apparatus
CN106230120A (en) * 2016-09-09 2016-12-14 国家电网公司 A kind of method of supplying power to
CN106841908A (en) * 2016-12-19 2017-06-13 国电南瑞科技股份有限公司 The visual presentation method of the distribution network failure positioning based on power grid GIS
CN106814286B (en) * 2017-02-10 2019-12-31 国网山东省电力公司 Power distribution network fault positioning system, method and server based on multi-element fault acquisition
CN106815373B (en) * 2017-02-10 2020-04-03 国网山东省电力公司 Distribution network first-aid repair big data display method and system based on BI analysis
CN106814286A (en) * 2017-02-10 2017-06-09 国网山东省电力公司 Distribution Fault Location System, method and server based on polynary fault collection
CN106815373A (en) * 2017-02-10 2017-06-09 国网山东省电力公司 Big data methods of exhibiting and system are rushed to repair in distribution based on BI analyses
CN106872856A (en) * 2017-03-01 2017-06-20 国网山东省电力公司 Distribution network failure based on polynary fault collection actively rushes to repair system, method
CN106872856B (en) * 2017-03-01 2019-12-24 国网山东省电力公司 Power distribution network fault active first-aid repair system and method based on multi-element fault collection
CN106960283A (en) * 2017-03-27 2017-07-18 国网山东省电力公司夏津县供电公司 Special transformer acquisition terminal fault handling method, device and system
CN107171436B (en) * 2017-05-08 2020-02-28 国网山东省电力公司烟台供电公司 Monitoring device capable of automatically screening information and analyzing accidents and monitoring method thereof
CN107171436A (en) * 2017-05-08 2017-09-15 国网山东省电力公司烟台供电公司 It is a kind of automatic screening information and the supervising device and its monitoring method of crash analysis to be carried out
CN106980071A (en) * 2017-05-16 2017-07-25 国网山东省电力公司 Repairing system and its method of work are visualized based on power grid GIS
CN107147215A (en) * 2017-05-16 2017-09-08 国网山东省电力公司 The Distribution Fault Location System and method of combined circuit overload data analysis
CN106990328A (en) * 2017-05-16 2017-07-28 国网山东省电力公司 The analysis of distribution repairing abnormal data, fault location system and method
CN107167704A (en) * 2017-05-16 2017-09-15 国网山东省电力公司 Fault Diagnosis of Distribution Network system and method based on CIM
CN106990328B (en) * 2017-05-16 2019-12-31 国网山东省电力公司 Distribution network emergency repair abnormal data analysis and fault positioning system and method
CN107167704B (en) * 2017-05-16 2019-12-31 国网山东省电力公司 Power distribution network fault diagnosis system and method based on CIM model
CN106980071B (en) * 2017-05-16 2019-12-06 国网山东省电力公司 Visual first-aid repair system based on power grid GIS and working method thereof
CN107765123A (en) * 2017-10-19 2018-03-06 中领世能(天津)科技有限公司 Detected rule update method and Electrical Safety monitoring system
CN108107318B (en) * 2017-11-03 2020-08-11 国网北京市电力公司 User fault positioning method and device
CN108107318A (en) * 2017-11-03 2018-06-01 国网北京市电力公司 The localization method and device of user malfunction
CN108460468A (en) * 2018-01-23 2018-08-28 国网江西省电力有限公司电力科学研究院 It is a kind of public to become failure event management method and device
CN108734381A (en) * 2018-04-11 2018-11-02 国网山东省电力公司 A kind of outage information collaborative management method, apparatus and system
CN108539736A (en) * 2018-04-26 2018-09-14 广州供电局有限公司 Power-off event analysis method, system and computer equipment based on multi-source data
CN108539856A (en) * 2018-04-28 2018-09-14 国网河南省电力公司周口供电公司 Power distribution network complete perception operation monitoring power distribution rush-repair system
CN108875975A (en) * 2018-06-27 2018-11-23 国网甘肃省电力公司金昌供电公司 A kind of excellent dress system of wisdom precisely informed based on client's outage information
CN109460833A (en) * 2018-10-22 2019-03-12 国家电网有限公司 The device data of Distribution Network Failure and report work order data processing method and system for repairment
CN109447284A (en) * 2018-10-22 2019-03-08 国家电网有限公司 Distribution Network Failure method for sending information and system for electric service maneuvering platform
CN109193946A (en) * 2018-10-22 2019-01-11 国家电网有限公司 Repairing information issuing system towards power consumer
CN109193946B (en) * 2018-10-22 2022-04-22 国家电网有限公司 Urgent repair information release system for power consumer
CN109460833B (en) * 2018-10-22 2021-11-09 国家电网有限公司 Method and system for processing equipment data and repair work order data of distribution network fault
CN109447284B (en) * 2018-10-22 2021-11-12 国家电网有限公司 Distribution network fault information sending method and system for power supply service command platform
CN111931511A (en) * 2019-04-26 2020-11-13 中国电力科学研究院有限公司 Semantic analysis method and system based on wide-area distributed architecture
CN110738329A (en) * 2019-09-06 2020-01-31 国网浙江桐乡市供电有限公司 first-aid repair informing method based on cloud platform
CN111262344A (en) * 2020-03-30 2020-06-09 佛山科学技术学院 Power grid monitoring emergency system
WO2022021549A1 (en) * 2020-07-31 2022-02-03 广东卓维网络有限公司 Power consumption emergency management system
CN112162174A (en) * 2020-09-03 2021-01-01 国电南瑞科技股份有限公司 Distribution room fault positioning method and system based on marketing and distribution integration
CN112162174B (en) * 2020-09-03 2024-04-26 国电南瑞科技股份有限公司 Station area fault positioning method and system based on marketing and distribution integration
CN112769231A (en) * 2020-12-24 2021-05-07 深圳供电局有限公司 Main distribution integrated alarm pushing method and device of intelligent power grid dispatching control system
CN115575765A (en) * 2022-10-31 2023-01-06 国网浙江省电力有限公司金华供电公司 Ground fault section selection analysis system based on four-area data of distribution automation

Also Published As

Publication number Publication date
CN103501050A (en) 2014-01-08
CN103501050B (en) 2016-01-27
CN103501051A (en) 2014-01-08
CN103490521A (en) 2014-01-01
CN103501051B (en) 2015-09-16
CN103490521B (en) 2015-09-30
CN103516054B (en) 2015-09-16
CN103516054A (en) 2014-01-15
CN102570602B (en) 2013-10-30

Similar Documents

Publication Publication Date Title
CN102570602B (en) Fault comprehensive processing platform and method of distribution network
CN202475009U (en) Comprehensive processing system of failure of power distribution and supply grid
CN103490520B (en) Power distribution network fault treatment method
CN103490523B (en) Intelligent power distribution network fault treatment system
CN103490522A (en) Intelligent power distribution network fault treatment method
CN103501054A (en) Fault handling method for power distribution network
CN103501052A (en) Comprehensive fault handling method for power distribution and consumption network
CN103501053B (en) Comprehensive fault handling system for power distribution and consumption network
CN109995145B (en) Low-voltage distribution network fault active study and judgment method based on intelligent distribution transformer terminal
CN102565572B (en) Platform and method for judging fault of match power grid
CN105305393A (en) Distribution network emergency repair commanding system and method based on marketing and distribution communication
CN102403798A (en) Intelligent automatic transformer district monitoring method and system based on GIS (geographical information system)
CN106875114A (en) The SMS platform optimization system and method for distribution repairing maneuvering platform
CN104091231A (en) Distribution network fault repairing commanding and processing system and method
CN103887794A (en) Power distribution network production urgent repair system and method based on Internet of Things
CN104601383B (en) A kind of power telecom network fault piecewise analysis method
CN102497017B (en) Power grid failure information comprehensive collection platform and collection method
CN109447284B (en) Distribution network fault information sending method and system for power supply service command platform
CN109871965A (en) A kind of breakdown repair App platform of combination GIS and power customer fault location information
CN109472476A (en) A kind of power failure identifying and analyzing method and system
CN105429301B (en) A kind of Intelligent power distribution network self-healing control method based on modal analysis
CN105790990A (en) Method and system for monitoring and managing power distribution and utilization communication business
CN109064140A (en) Internet of things equipment operation management system
CN104332993B (en) A kind of intelligent distribution type feeder automation load transfer method
CN112731062B (en) Method for diagnosing low-voltage user power failure by utilizing telecommunication terminal equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: JIANGSU SUYUAN HIGH-TECH CO., LTD. STATE GRID CORP

Free format text: FORMER OWNER: JIANGSU SUYUAN HIGH-TECH CO., LTD.

Effective date: 20121221

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20121221

Address after: 210008 Zhongshan Road, Jiangsu, No. 251,

Applicant after: Nanjing Power Supply Co., Jiangsu Prov. Power Co.

Applicant after: Jiangsu Suyuan High-Tech Co., Ltd.

Applicant after: State Grid Corporation of China

Applicant after: Jiangsu Electric Power Company

Address before: 210008 Zhongshan Road, Jiangsu, No. 251,

Applicant before: Nanjing Power Supply Co., Jiangsu Prov. Power Co.

Applicant before: Jiangsu Suyuan High-Tech Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant