Summary of the invention
First technical problem that the present invention will solve is: propose a kind of current collection net fault information acquisition, study and judge, push incorporate full-automatic integrated treatment platform and processing method.
Second technical problem that the present invention will solve is: on the basis that solves above-mentioned first technical problem, propose a kind of full-automatic integrated treatment platform of adapted electrical network and the method that can carry out interaction with the user.
In order to solve above-mentioned first technical problem; One of technical scheme that the present invention proposes is: a kind of adapted electric network fault integrated treatment platform; Comprise that fault information acquisition system, fault message are studied and judged system and breakdown repair stops the information transmission system of supplying power, said fault information acquisition system comprises being arranged at and existing 95598 intrasystemly reports that fault message pushes module, the line fault information in the existing power distribution automation management system of being arranged at pushes module for repairment, is arranged at usefulness in the existing power information acquisition system and adopts fault message and push module, fault message receiver module, fault message processing module and fault message sending module; Said fault message is studied and judged system and is comprised the faulty equipment locating module, fault message screening module, line topological analysis module, equipment operation information analysis module, line switching analysis module, failure analysis module and fault display module; The said breakdown repair information transmission system that stops supplying power comprises that breakdown repair allocation schedule module, scene rush to repair administration module, repairing information push module and stop power supply information and pushes module;
The said fault message that reports for repairment pushes module and reports fault message for repairment in order to the user that will be reported to 95598 systems and be pushed to said fault message receiver module;
Said line fault information pushes module and is pushed to said fault message receiver module in order to the switch changed position fault message that will be reported to power distribution automation management system (DMS);
Said usefulness is adopted fault message propelling movement module and is pushed to said fault message receiver module in order to distribution transforming and user's fault message that will be reported to power information acquisition system (CSM);
Fault message pushes module to said fault message receiver module, line fault information pushes module and pushes the next fault message of module propelling movement with adopting fault message from reporting for repairment with verification in order to receive;
Said fault message processing module is stored in order to the fault message that said fault message receiver module is received, and from the low-voltage customer to the high-tension apparatus, carries out analytical integration with uniform data model according to the power network line topological structure;
The fault message of said fault message sending module in order to the fault message processing module is handled sent out passage outward through information and is sent to said faulty equipment locating module;
Said faulty equipment locating module is used to receive the fault message that said fault message sending module sends, and obtains the actual geographical position and the account information of the source device relevant with fault message through existing power distribution management system (PMS);
Said fault message screening module is used for the fault message behind the equipment location is screened, and gets rid of the scheduled outage fault message and the confirmed fault message that have generated;
Said line topological analysis module is used for the adapted electric line under the fault message that filters out is carried out topological analysis, obtains the topological structure of this adapted electric line and the circuit charging equipment tabulation of associated topologies structure;
Said equipment operation information analysis module is used for the circuit charging equipment of circuit charging equipment tabulation is carried out the cls analysis of calling together of equipment operation information step by step, and judges whether the circuit charging equipment exists fault;
Said line switching analysis module is used to the switch folding information that detects the On line switch on the adapted electric line and go out wiretap, and judges whether the adapted electric line exists line fault;
Said failure analysis module is used for confirming fault type, the position of fault and fault effects zone according to equipment operation information, switch folding information and topological structure; Fault type, the position of fault and fault effects zone are pushed to breakdown repair allocation schedule module, generate fault outage information and push to according to fault type, the position of fault and fault effects zone and stop power supply information propelling movement module;
Said breakdown repair allocation schedule module is used for confirming according to fault type, the position of fault and fault effects zone the repairing teams and groups and the scheduling recovery vehicle of fault;
Said scene rush to repair administration module is used to monitor and gather repairing personnel's the repairing procedural information and the information that restores electricity;
Said repairing information pushes module and is used for repairing procedural information is pushed to the fault display module, and will the information of restoring electricity be pushed to and stops power supply information propelling movement module;
Said fault display module is used for having circuit charging equipment and the account information thereof of fault, the influence area and the repairing procedural information of adapted electric line through existing adapted power grid GIS system demonstration;
The said power supply information propelling movement module of stopping is used for through existing 95598 customer service systems, short message service passage and fiber data passage the fault outage information and the information that restores electricity being influenced user's propelling movement to having a power failure.
In order to solve above-mentioned first technical problem, two of the technical scheme that the present invention proposes is: a kind of adapted electric network fault integrated conduct method, adopt above-mentioned adapted electric network fault integrated treatment platform, and carry out following steps:
1) setting is reported fault message for repairment and is pushed module in existing 95598 systems, sets up 95598 systems and reports the Web service data-transmission channel that fault message pushes module for repairment;
Line fault information is set in existing power distribution automation management system pushes module, set up GPRS message information transmission passage or IEB bus service data transmission passage that power distribution automation management system and line fault information push module;
In existing power information acquisition system, be provided with adopting fault message and push module, set up the power information acquisition system and use the Web service data-transmission channel of adopting fault message propelling movement module;
2) reporting fault message for repairment pushes module and will be reported to the user of existing 95598 systems to report fault message for repairment to be pushed to the fault message receiver module;
Line fault information pushes module and will be reported to the switch changed position fault message of existing power distribution automation management system to be pushed to the fault message receiver module;
To be reported to distribution transforming and user's fault message of existing power information acquisition system to be pushed to the fault message receiver module with adopting fault message propelling movement module;
3) fault message pushes module, line fault information pushes module and pushes the next fault message of module propelling movement with adopting fault message from reporting for repairment for reception of fault message receiver module and verification;
4) the fault message processing module will be stored through the fault message of reception of fault message receiver module and verification, from the low-voltage customer to the high-tension apparatus, carry out analytical integration with uniform data model according to the power network line topological structure;
5) the fault message sending module will be sent out passage outside through information through fault message that the fault message processing module is handled and be sent to the faulty equipment locating module;
6) the faulty equipment locating module receives the fault message that the fault message sending module sends, and obtains the actual geographical position and the account information of the source device relevant with fault message through existing power distribution management system;
7) the fault message screening module is screened the fault message behind the source device location, judges whether the fault message behind the source device location belongs to scheduled outage fault message and the confirmed fault message that has generated, and then eliminating in this way is not as being then to carry out next step;
8) the line topological analysis module is reviewed through power supply point the adapted electric line under the fault message that filters out is carried out topological analysis, obtains the topological structure of this adapted electric line and the circuit charging equipment tabulation of associated topologies structure;
9) the circuit charging equipment during equipment operation information analysis module is tabulated the circuit charging equipment carries out equipment operation information step by step and calls cls analysis together; Judge according to the equipment operation information that analyzes whether the circuit charging equipment exists fault; Then carry out next step in this way; As be not that then failure judgement information is user's internal fault information, finish to study and judge;
10) the line switching analysis module detects the On line switch on the adapted electric line and goes out the switch folding information of wiretap, judges whether the adapted electric line exists line fault;
11) failure analysis module is confirmed fault type according to said equipment operation information and switch folding information; Confirm the position of fault and fault effects zone according to said topological structure; Fault type, the position of fault and fault effects zone are pushed to breakdown repair allocation schedule module, generate fault outage information and push to according to fault type, the position of fault and fault effects zone and stop power supply information propelling movement module;
12) breakdown repair allocation schedule module is confirmed the repairing teams and groups and the scheduling recovery vehicle of fault according to fault type, the position of fault and fault effects zone;
13) monitoring of scene rush to repair administration module and collection repairing personnel's the repairing procedural information and the information that restores electricity;
14) repairing information pushes module and will rush to repair procedural information and push to the fault display module, and will the information of restoring electricity be pushed to and stops power supply information propelling movement module;
15) the fault display module exists circuit charging equipment and the account information thereof of fault, the influence area and the repairing procedural information of adapted electric line through existing adapted power grid GIS system demonstration;
16) stop power supply information propelling movement module and the fault outage information and the information that restores electricity are influenced user's propelling movement to having a power failure through existing 95598 customer service systems, short message service passage and fiber data passage.
In order to solve above-mentioned second technical problem; The present invention to the improvement of one of technique scheme is: also comprise being used for carrying out interactive interactive module through short message service passage and fiber data passage and user; Said interaction is that the user sends code and the user number inquiry stops sending electrical information, stops sending electrical information and transmission to inform the user by interactive module according to user number inquiring user region.
In order to solve above-mentioned second technical problem, the present invention to two improvement of technique scheme is: adopt improved technical scheme to increase in the lump and carry out the 17th) step: interactive module is carried out interaction through short message service passage and fiber data passage and user; Said interaction is that the user sends code and the user number inquiry stops sending electrical information, informs the user by interactive module according to user number inquiring user region power failure information and restore electricity information and transmission.
The perfect of one of technique scheme is: the said fault message propelling movement module of reporting for repairment links through the Web service data-transmission channel with existing 95598 systems; Said line fault information pushes module and links through GPRS message information transmission passage or IEB bus service data transmission passage with existing power distribution automation management system; Said usefulness is adopted fault message propelling movement module and is linked through the Web service data-transmission channel with existing power information acquisition system; It is to utilize the SIM of the remote signalling displacement device that is arranged on switch to constitute that said GPRS message information transmits passage, and it is LAN that said information is sent out passage outward.
The perfect of one of technique scheme is: said storage be with the fault message classification and storage of the separate sources that receives in the fault message table of type separately; Said analytical integration is top-down arrangement the in order of line topological structure according to mesolow; Comprise from user profile->ammeter information->distribution transforming information->On line switch information->transformer station's outlet switching information analyzes; And set up the relation that can inquire about each other, the result who analyzes is stored in the analysis result table.
The perfect of one of technique scheme is: said user reports fault message for repairment and comprises Customs Assigned Number, user's name, station address, contact method and fault content; Said switch changed position fault message comprises the message of switch number, on off state, circuit number, affiliated factory station, three-phase current and three-phase voltage; Said distribution transforming and user's fault message comprise distribution transforming numbering, distribution transforming title, critical point numbering, ammeter numbering, critical point numbering and acquisition time.
The perfect of one of technique scheme is: said fault message comprises 95598 user's repairing information, and existing power information acquisition system (CSM) reports fault message and existing power distribution automation management system (DMS) to report fault message; Said fault type comprises low district's fault, distribution transforming fault, middle pressure client's internal fault, part line fault and the circuit fault completely of presenting a theatrical performance as the last item on a programme.
The perfect of one of technique scheme is: when said fault message is that 95598 users are when reporting fault message for repairment; Said source device is low pressure ammeter box equipment or the negative control device that is associated through the existing acquisition user of power distribution management system according to the Customs Assigned Number that reports for repairment, and actual geographical coordinate information of said source device and account information are to obtain through existing power distribution management system queries according to low pressure ammeter box equipment or negative unique coding of controlling device; When said fault message is an existing power information acquisition system when reporting fault message or existing power distribution automation management system to report fault message, said source device is distribution transforming, switch and the negative control device that obtains through existing power distribution management system according to the asset of equipments numbering; Actual geographical coordinate information of said source device and account information are to obtain through existing power distribution management system queries according to source distribution transforming, switch and negative unique coding of controlling device.
The perfect of one of technique scheme is: said controller switching equipment comprises circuit, switch, distribution transformer and middle pressure user, and said power failure influences equipment and comprises low-pressure meter case and middle pressure user.
Technique scheme two perfectly be: the 3rd) in the step,, feed back to fault message propelling movement side to different fault message sources if the fault message of verification is an abnormal data; If the fault message of verification is normal data then pushes to the fault message processing module;
Technique scheme two perfectly be: the 4th) in the step, said storage be with the fault message classification and storage of the separate sources that receives in the fault message table of type separately; Said analytical integration is top-down arrangement the in order of line topological structure according to mesolow; Comprise from user profile->ammeter information->distribution transforming information->On line switch information->transformer station's outlet switching information analyzes; And set up the relation that can inquire about each other, the result who analyzes is stored in the analysis result table.
Technique scheme two perfectly be: it is to utilize the SIM of the remote signalling displacement device that is arranged on switch to constitute that said GPRS message information transmits passage; It is LAN that said information is sent out passage outward; Said user reports fault message for repairment and comprises Customs Assigned Number, user's name, station address, contact method and fault content; Said switch changed position fault message comprises the message of switch number, on off state, circuit number, affiliated factory station, three-phase current and three-phase voltage; Said distribution transforming and user's fault message comprise distribution transforming numbering, distribution transforming title, critical point numbering, ammeter numbering, critical point numbering and acquisition time.
Two improve and one be of technique scheme: the said the 6th) in the step; When said fault message is that 95598 users are when reporting fault message for repairment; According to the Customs Assigned Number that reports for repairment; Obtain low pressure ammeter box equipment that the user is associated or negative control device as source device through existing power distribution management system (PMS), and the unique coded query through low pressure ammeter box equipment or negative control device is to source device geographical coordinate information of reality and account information.
Two improve and two be of technique scheme: the said the 6th) in the step; When said fault message is that existing power information acquisition system is when reporting fault message or existing power distribution automation management system to report fault message; Obtain distribution transforming, switch and negative control device as source device according to asset of equipments numbering through existing power distribution management system, and the unique coded query through distribution transforming, switch and negative control device is to source device geographical coordinate information of reality and account information.
Technique scheme two perfectly be: the said the 7th) in the step; Whether fault message screening module at first failure judgement information is the scheduled outage fault message that has generated; Then get rid of this fault message in this way and do not study and judge, and inform through 95598 systems and to report the user for repairment; As be not scheduled outage then failure judgement information whether be confirmed fault message, then get rid of this fault message in this way and do not study and judge, and inform that through 95598 systems the user has confirmed the repairing situation of fault; As neither the scheduled outage fault message neither be confirmed fault message, then carry out next step.
Technique scheme two perfectly be: the said the 8th) in the step; It is to carry out power supply point according to the actual geographical position of source device to review and form and review the path that said power supply point is reviewed; Collect power supply point then and review the circuit charging equipment on the path; Circuit charging equipment equipment is classified, made up, form the tabulation of circuit charging equipment.
Technique scheme two perfectly be: the said the 9th) in the step, said circuit charging equipment is wiretap, On line switch, distribution transforming, negative control device and low pressure ammeter box.
Technique scheme two perfectly be: the said the 10th) in the step, saidly judge whether the adapted electric line exists line fault to comprise:
1. if the outlet switch closure then judges it is the part line failure;
2. if going out wiretap breaks off, then judge it is the whole piece line failure;
3. if go out wiretap and On line switch all is in closure state, then judgement is that circuit does not break down but device fails.
Technique scheme two perfectly be: the said the 11st) in the step, said definite fault type comprises:
A. report like the user transformers fault-free, confirm that then fault type is the low district's fault of presenting a theatrical performance as the last item on a programme;
B. have fault to report like user transformers, but the wireless switch of going up reports with the outlet switch fault, then definite fault type is the distribution transforming fault;
C. have fault to report like user transformers, and switch fault reports on wired, confirm that then fault type is a part line fault;
D. there is fault to report like user transformers, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely;
E. report like the negative control of user device fault-free, confirm that then fault type is middle pressure client internal fault;
F. have fault to report like the negative control of user device, and switch fault reports on wired, confirm that then fault type is a part line fault;
G. there is fault to report like the negative control of user device, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely.
Technique scheme two perfectly be: the said the 7th) in the step; Whether fault message screening module at first failure judgement information is the scheduled outage fault message that has generated; Then get rid of this fault message in this way and do not study and judge, and inform through 95598 systems and to report the user for repairment; As be not scheduled outage then failure judgement information whether be confirmed fault message, then get rid of this fault message in this way and do not study and judge, and inform that through 95598 systems the user has confirmed the repairing situation of fault; As neither the scheduled outage fault message neither be confirmed fault message, then carry out next step;
The said the 8th) in the step; It is to carry out power supply point according to the actual geographical position of source device to review and form and review the path that said power supply point is reviewed; Collect power supply point then and review the circuit charging equipment on the path; Circuit charging equipment equipment is classified, made up, form the tabulation of circuit charging equipment;
The said the 9th) in the step, said circuit charging equipment is wiretap, On line switch, distribution transforming, negative control device and low pressure ammeter box;
The said the 10th) in the step, if the outlet switch closure then judges it is the part line failure; Break off if go out wiretap, then judge it is the whole piece line failure; If go out wiretap and On line switch all is in closure state, then judgement is that circuit does not break down but device fails;
The said the 11st) in the step, said definite fault type comprises:
A. report like the user transformers fault-free, confirm that then fault type is the low district's fault of presenting a theatrical performance as the last item on a programme;
B. have fault to report like user transformers, but the wireless switch of going up reports with the outlet switch fault, then definite fault type is the distribution transforming fault;
C. have fault to report like user transformers, and switch fault reports on wired, confirm that then fault type is a part line fault;
D. there is fault to report like user transformers, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely;
E. report like the negative control of user device fault-free, confirm that then fault type is middle pressure client internal fault;
F. have fault to report like the negative control of user device, and switch fault reports on wired, confirm that then fault type is a part line fault;
G. there is fault to report like the negative control of user device, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely.
The invention has the beneficial effects as follows: 1), initiatively send the fault message that is reported to 95598 systems, power distribution automation management system and power information acquisition system to the fault message receiver module because fault message propelling movement module is reported in setting for repairment respectively in existing 95598 systems, power distribution automation management system and power information acquisition system, line fault information pushes module and pushes module with adopting fault message; Therefore realization gathers the electric network fault information that has the collection of various electrical network operation system channel now and initiatively transmits; 2) fault message is studied and judged system and can be shifted to an earlier date automatically the very first time after reception reports fault message and study and judge; And obtain accurately fault type, the position of fault and fault effects zone; Thereby, and then improve the efficient of breakdown repair and administration of power networks for breakdown repair and management provide strong foundation; 3) the breakdown repair information transmission system that stops supplying power can initiatively directly influence user's propelling movement with the power failure information and the information that restores electricity to having a power failure, and the user is known the very first time stop sending electrical information, is convenient to the user and carries out relative measures; 4) client can the short message service passage and fiber data passage inquiry power failure information with restore electricity information, be convenient to carry out alternately with the client.
Embodiment
Embodiment one
The adapted electric network fault integrated treatment platform of present embodiment comprises that the A of fault information acquisition system, fault message study and judge the B of system and the breakdown repair information transmission system C that stops supplying power.
The A of fault information acquisition system comprises being arranged at and existing 95598 intrasystemly reports that fault message pushes module 1, the line fault information in the existing power distribution automation management system of being arranged at pushes module 2 for repairment, is arranged at usefulness in the existing power information acquisition system and adopts fault message and push module 3, fault message receiver module 4, fault message processing module 5 and fault message sending module 6.
Fault message is studied and judged the B of system and is comprised faulty equipment locating module 7, fault message screening module 8, line topological analysis module 9, equipment operation information analysis module 10, line switching analysis module 11, failure analysis module 12 and fault display module 13.
The breakdown repair information transmission system C that stops supplying power comprises that breakdown repair allocation schedule module 14, scene rush to repair administration module 15, repairing information push module 16 and stop power supply information and pushes module 17.
Reporting fault message for repairment pushes module 1 and reports fault message for repairment in order to the user that will be reported to 95598 systems and be pushed to fault message receiver module 4;
Line fault information pushes module 2 and is pushed to fault message receiver module 4 in order to the switch changed position fault message that will be reported to power distribution automation management system (DMS);
Be pushed to fault message receiver module 4 with adopting fault message propelling movement module 3 in order to distribution transforming and user's fault message that will be reported to power information acquisition system (CSM);
Fault message pushes module 1 to fault message receiver module 4, line fault information pushes module 2 and pushes the next fault message of module 3 propelling movements with adopting fault message from reporting for repairment with verification in order to receive;
Fault message processing module 5 is stored in order to the fault message that fault message receiver module 4 is received; According to the power network line topological structure from the low-voltage customer to the high-tension apparatus; Carry out analytical integration with uniform data model, push to faulty equipment locating module 6 again;
The fault message of fault message sending module 6 in order to fault message processing module 5 is handled sent out passage outward through information and is sent to said faulty equipment locating module, and it generally is LAN that information is sent out passage outward;
Faulty equipment locating module 7 is used to receive the fault message that fault message sending module 6 sends, and obtains the actual geographical position and the account information of the source device relevant with fault message through existing power distribution management system (PMS);
Fault message screening module 8 is used for the fault message behind the equipment location is screened, and gets rid of the scheduled outage fault message and the confirmed fault message that have generated;
Line topological analysis module 9 is used for the adapted electric line under the fault message that filters out is carried out topological analysis, obtains the topological structure of this adapted electric line and the circuit charging equipment tabulation of associated topologies structure;
Equipment operation information analysis 10 modules are used for the circuit charging equipment of circuit charging equipment tabulation is carried out the cls analysis of calling together of equipment operation information step by step, and judge whether the circuit charging equipment exists fault;
Line switching analysis module 11 is used to the switch folding information that detects the On line switch on the adapted electric line and go out wiretap, and judges whether the adapted electric line exists line fault;
Failure analysis module 12 is used for confirming fault type, the position of fault and fault effects zone according to equipment operation information, switch folding information and topological structure; Fault type, the position of fault and fault effects zone are pushed to breakdown repair allocation schedule module 14, generate fault outage information and push to according to fault type, the position of fault and fault effects zone and stop power supply information propelling movement module 17;
Breakdown repair allocation schedule module 14 is used for confirming according to fault type, the position of fault and fault effects zone the repairing teams and groups and the scheduling recovery vehicle of fault;
Scene rush to repair administration module 15 is used to monitor and gather repairing personnel's the repairing procedural information and the information that restores electricity;
Repairing information pushes module 16 and is used for repairing procedural information is pushed to fault display module 13, and will the information of restoring electricity be pushed to and stops power supply information propelling movement module 17;
Fault display module 13 is used for having circuit charging equipment and the account information thereof of fault, the influence area and the repairing procedural information of adapted electric line through existing adapted power grid GIS system demonstration;
Stopping power supply information propelling movement module 17 is used for through existing 95598 customer service systems, short message service passage and fiber data passage the fault outage information and the information that restores electricity being influenced user's propelling movement to having a power failure.
The adapted electric network fault integrated conduct method of present embodiment adopts above-mentioned adapted electric network fault integrated treatment platform, and carries out following steps:
1) setting is reported fault message for repairment and is pushed module 1 in existing 95598 systems; Set up 95598 systems and report the Web service data-transmission channel that fault message pushes module 1 for repairment, the concrete user who pushes reports fault message for repairment and comprises: Customs Assigned Number, user's name, station address, contact method, fault content etc.
Line fault information is set in existing power distribution automation management system pushes module 2, set up the GPRS message information transmission passage (specifically being to utilize the SIM formation GPRS message information of the remote signalling displacement device that is arranged on switch to transmit passage) that power distribution automation management system and line fault information push module 2; The fault message that transmits is mainly out the displacement information that wiretap is operated a switch and On line switch is isolated, and the concrete switching information that transmits comprises: messages such as switch number, on off state, circuit number, affiliated factory station, three-phase current, three-phase voltage.
In existing power information acquisition system, be provided with adopting fault message and push module 3, set up the power information acquisition system and use the Web service data-transmission channel of adopting fault message propelling movement module 3; The distribution transforming that transmits and user's fault message comprise distribution transforming numbering, distribution transforming title, critical point numbering, ammeter numbering, critical point numbering and acquisition time etc.
2) reporting fault message for repairment pushes module 1 and will be reported to the user of existing 95598 systems to report fault message for repairment to be pushed to fault message receiver module 4;
Line fault information pushes module 2 and will be reported to the switch changed position fault message of existing power distribution automation management system (DMS) to be pushed to fault message receiver module 4;
To be reported to distribution transforming and user's fault message of existing power information acquisition system (CSM) to be pushed to fault message receiver module 4 with adopting fault message propelling movement module 3.
3) fault message pushes module 1, line fault information pushes module 2 and pushes the fault message that module 3 propelling movements come with adopting fault message from reporting for repairment for 4 receptions of fault message receiver module and verification; Fault message receiver module 4 is when receiving fault information data; Need the fault information data of separate sources is carried out verification; If the fault message of verification is an abnormal data, feed back to fault information data propelling movement side (operation system separately) to different fault information data sources; If the fault message of verification is a normal data, then push to fault message processing module 5.
4) fault message processing module 5 will be stored through the fault message of 4 receptions of fault message receiver module and verification; According to the power network line topological structure from the low-voltage customer to the high-tension apparatus; Carry out analytical integration with uniform data model, push to faulty equipment locating module 6 again;
Storage is: need classification and storage in the fault message table of type separately to the fault message of the separate sources that receives;
Analytical integration is: when data are carried out analytical integration; Top-down arrangement the in order of line topological structure according to mesolow; As: from user profile->ammeter information->distribution transforming information->On line switch information->transformer station's outlet switching information analyzes; And set up the relation (for example can inquire about the distribution transforming fault message) that can inquire about each other through user's fault message, the result who analyzes is stored in the analysis result table.
5) fault message sending module 6 will be sent out passage outside through information through fault message that fault message processing module 5 is handled and be sent to the faulty equipment locating module, and information is sent out passage outward and generally adopted LAN.
6) faulty equipment locating module 7 receives the fault message that fault message sending module 6 sends, and obtains the actual geographical position and the account information of the source device relevant with fault message through existing power distribution management system.
Concrete steps are: when said fault message is that 95598 users are when reporting fault message for repairment; According to the Customs Assigned Number that reports for repairment; Obtain low pressure ammeter box equipment that the user is associated or negative control device as source device through existing power distribution management system (PMS), and the unique coded query through low pressure ammeter box equipment or negative control device is to source device geographical coordinate information of reality and account information.When said fault message is that existing power information acquisition system is when reporting fault message or existing power distribution automation management system to report fault message; The distribution transforming, switch and the negative control device that obtain through existing power distribution management system according to asset of equipments numbering be as source device, and the unique coded query through distribution transforming, switch and negative control device is to source device geographical coordinate information of reality and account information.
7) fault message behind the 8 pairs of source devices of the fault message screening module location screens, and judges whether the fault message behind the source device location belongs to the scheduled outage fault message that has generated and confirmed fault message, and then eliminating in this way is not as being then to carry out next step.
Concrete screening step is: whether fault message screening module at first failure judgement information is the scheduled outage fault message that has generated, and the scheduled outage fault message is then got rid of this fault message and do not studied and judged in this way, and informs through 95598 systems and to report the user for repairment; As be not the scheduled outage fault message then failure judgement information whether be confirmed fault message, confirmed in this way fault message is then got rid of this fault message and is not is not studied and judged, and informs that through 95598 systems the user has confirmed the repairing situation of fault; As neither the scheduled outage fault message neither be confirmed fault message, then carry out next step.
8) line topological analysis module 9 is reviewed through power supply point the adapted electric line under the fault message that filters out is carried out topological analysis, obtains the topological structure of this adapted electric line and the circuit charging equipment tabulation of associated topologies structure.
The concrete analysis step is: at first carry out power supply point according to the actual geographical position of source device and review, form and review path (obtaining the topological structure of this adapted electric line); Collect power supply point then and review the circuit charging equipment on the path, circuit charging equipment equipment is classified, made up, form the tabulation of circuit charging equipment.
9) the circuit charging equipment during equipment operation information analysis module 10 is tabulated the circuit charging equipment carries out operation information step by step and calls cls analysis together; Judge according to the equipment operation information that analyzes whether the circuit charging equipment exists fault; Then carry out next step in this way; As be not that then failure judgement information is user's internal fault information, finish to study and judge.
The concrete analysis step is: go out wiretap, On line switch, distribution transforming, negative control device, low pressure ammeter box (circuit charging equipment) in the circuit charging equipment tabulation carry out operation information step by step and call survey together.If all move in the said equipment normally, the fault repairing information that causes inside to break down to report owing to client's self reason is described then.
10) line switching analysis module 11 detects the On line switch on the adapted electric line and goes out the switch folding information of wiretap, judges whether the adapted electric line exists line fault.
Specifically judge whether the adapted electric line exists the step of line fault to comprise:
1. if the outlet switch closure then judges it is the part line failure;
2. if going out wiretap breaks off, then judge it is the whole piece line failure;
3. if go out wiretap and On line switch all is in closure state, then judgement is that circuit does not break down but device fails.
11) failure analysis module 11 is confirmed fault type according to equipment operation information and switch folding information; Confirm the position of fault and fault effects zone according to topological structure; Fault type, the position of fault and fault effects zone are pushed to breakdown repair allocation schedule module 14, generate fault outage information and push to according to fault type, the position of fault and fault effects zone and stop power supply information propelling movement module 17.
Concrete steps are:
At first; According to the failure condition that the analysis result of the said equipment operating analysis and switch folding information is confirmed, further confirm the particular type (fault type comprises low district's fault, distribution transforming fault, middle pressure client's internal fault, part line fault and the circuit fault completely of presenting a theatrical performance as the last item on a programme) of fault; The detailed process of confirming fault type comprises:
A. report like the user transformers fault-free, confirm that then fault type is the low district's fault of presenting a theatrical performance as the last item on a programme;
B. have fault to report like user transformers, but the wireless switch of going up reports with the outlet switch fault, then definite fault type is the distribution transforming fault;
C. have fault to report like user transformers, and switch fault reports on wired, confirm that then fault type is a part line fault;
D. there is fault to report like user transformers, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely;
E. report like the negative control of user device fault-free, confirm that then fault type is middle pressure client internal fault;
F. have fault to report like the negative control of user device, and switch fault reports on wired, confirm that then fault type is a part line fault;
G. there is fault to report like the negative control of user device, and has the outlet switch fault to report, confirm that then fault type is a circuit fault completely.
12) breakdown repair allocation schedule module 12 is confirmed repairing teams and groups and scheduling recovery vehicle according to fault type, the position of fault and fault effects zone.
13) 13 monitoring of scene rush to repair administration module and collection repairing personnel's the repairing procedural information and the information that restores electricity.
14) repairing information pushes module 14, and the repairing procedural information pushes to fault display module 12, and will the information of restoring electricity be pushed to and stops power supply information and push module 17.
15) fault display module 12 exists circuit charging equipment and the account information thereof of fault, the influence area and the repairing procedural information of adapted electric line through existing adapted power grid GIS system demonstration;
16) stop power supply information propelling movement module 17 and the fault outage information and the information that restores electricity are influenced user's propelling movement to having a power failure through existing 95598 customer service systems, short message service passage and fiber data passage.
Embodiment two
The adapted electric network fault integrated treatment platform and the embodiment one of present embodiment are basic identical, and different is: also comprise being used for carrying out interactive interactive module 18 through short message service passage and fiber data passage and user; Interaction is meant that the user sends code and the user number inquiry stops sending electrical information. when code was power failure, interactive module 18 was according to user number inquiry client's region power failure information and Spoke-to-Client; When code when restoring electricity, interactive module 4 is according to restore electricity information and inform the user of user number inquiry client region.
The adapted electric network fault integrated conduct method and the embodiment one of present embodiment are basic identical, and different is:
1. increase execution in step 17): interactive module 18 is carried out interaction through short message channel and optical-fibre channel and user; Interaction is that the user sends code and the user number inquiry stops sending electrical information, and interactive module 4 is informed the user according to user number inquiring user region power failure information and restore electricity information and transmission.
2. the 1st) in the step, set up IEB bus service data between the module 2 and transmit passage and replace the GPRS message information to transmit passage through pushing in power distribution automation management system and line fault information.
3. the 7th) in the step, scheduled outage information and confirmed fault message do not need and inform through 95598 systems to report the user for repairment.
The present invention is not limited to the foregoing description, and the technical scheme that all employings and the invention described above technical scheme are equal to replacement all drops within protection scope of the present invention.