CN109814000A - A kind of control system and its application method for power grid rapid rush-repair - Google Patents
A kind of control system and its application method for power grid rapid rush-repair Download PDFInfo
- Publication number
- CN109814000A CN109814000A CN201910092547.1A CN201910092547A CN109814000A CN 109814000 A CN109814000 A CN 109814000A CN 201910092547 A CN201910092547 A CN 201910092547A CN 109814000 A CN109814000 A CN 109814000A
- Authority
- CN
- China
- Prior art keywords
- location information
- fault
- module
- repair
- repairing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
- Y04S10/52—Outage or fault management, e.g. fault detection or location
Landscapes
- Mobile Radio Communication Systems (AREA)
Abstract
The present invention provides a kind of control system for power grid rapid rush-repair, including field control case, repairing center, scheduling system and mobile terminal, the field control case is for obtaining fault message and fault location information, and fault message and fault location information are sent to repairing center, repairing center is used to the fault message of acquisition and fault location information being sent to scheduling system, and the processing result for the system of dispatching is exported to mobile terminal simultaneously, scheduling system is for carrying out analysis record to fault message and fault location information, it deals with result, processing result is fed back into repairing center simultaneously, mobile terminal is held or is carried by repair personnel, for obtaining processing result and fault location information.The present invention can greatly reduce emergency repair time, improve first-aid repair efficiency.
Description
Technical field
The present invention relates to electric power grid system technical fields, and in particular to a kind of control system for power grid rapid rush-repair
And its application method.
Background technique
Electric power is the basis of national economy, and the development national for one is most important, guarantees that power system security is effective
Operation it is particularly important, Modern power distribution net topology relationship is complicated, number of nodes is more and intensive, in actual moving process, due to
The reasons such as external force destruction, extreme weather or ageing equipment can inevitably make power distribution network break down.Distribution network failure repairing is distribution
An important process in net maintenance management, power supply department are attempting to shorten with various methods emergency repair time always also to subtract
National economy is lost caused by lacking due to fault outage.
Currently, the trouble shoot side that 10KV electric distribution network overhead wire failure ratio in city and rural area is more, traditional
Formula is time-consuming and laborious, influences the reliability of power supply.Once the line fails, it needs to search along artificial, still increases event
Barrier searches difficulty and time.
Summary of the invention
In view of this, the purpose of the present invention is to provide a kind of control system for power grid rapid rush-repair and its users
Method, to solve the problems mentioned in the above background technology.
In order to solve the above technical problems, the present invention provides a kind of control system for power grid rapid rush-repair, including scene
Control cabinet, repairing center, scheduling system and mobile terminal, the field control case is for obtaining fault message and fault bit confidence
Breath, and fault message and fault location information are sent to repairing center, the fault message and event that repairing center is used to obtain
Barrier location information is sent to scheduling system, and simultaneously exports the processing result for the system of dispatching to mobile terminal, and scheduling system is used for
Analysis record is carried out to fault message and fault location information, is dealt with as a result, simultaneously feeding back to processing result in repairing
The heart, mobile terminal is held or is carried by repair personnel, for obtaining processing result and fault location information.
As a further solution of the present invention: the field control case includes first be electrically connected with the first microcontroller
Locating module, power grid sensor, wireless transmitter module and the first power module, the first locating module is for obtaining field control case
Location information, and send it to the first microcontroller;Power grid sensor is for determining current Network with the presence or absence of failure, nothing
Line transmitting module is used for for realizing the wireless telecommunications between the first microcontroller and repairing center, the first microcontroller to failure
Signal and location information, which are associated, handles and sends it to repairing center, and the first power module is used to supply for above-mentioned component
Electricity.
As further scheme of the invention: the repairing center includes the second electricity being electrically connected with control circuit board
Source module, the first display device and wireless receiving module, the wireless receiving module are used to carry out data with field control case logical
News, receive fault-signal and location information that the first microcontroller is sent, and control circuit board is used to believe fault-signal and position
Breath handle and communicated simultaneously with scheduling system and mobile terminal, and the first display device is used for fault message and fault bit
Confidence breath is shown.
As further scheme of the invention: the scheduling system includes the first nothing being electrically connected with central controller
Line communication module, the second display device and third power module, the first wireless communication module for realizing central controller with rob
The data interchange at center is repaired, the second display device is for showing that fault message and fault location information, third power module are used for
For the power supply of above-mentioned component, central controller is used to carry out fault message processing analysis and generates processing result, via the first nothing
Processing result is sent to repairing center by line communication module.
As further scheme of the invention: the central controller is also connected with storage device, and storage device is hard
Disk.
As further scheme of the invention: the central controller is also connected with warning device.
As further scheme of the invention: the mobile terminal includes the second nothing being electrically connected with the second microcontroller
Line communication module, the 4th power module and third display device, second wireless communication module is for realizing the second microcontroller
The data communication of device and repairing center, third display device is for showing fault message and fault location information, the 4th power supply mould
Block is used to power for above-mentioned component.
As further scheme of the invention: further including the second locating module being electrically connected with the second microcontroller.
As further scheme of the invention: second microcontroller is also connected with loudspeaker and microphone, repairing
Control circuit board in center is also connected with voice talk module.
A kind of application method of the control system for power grid rapid rush-repair, comprising the following steps:
Step 1, after network is broken down, power grid sensor sends a signal to the first microcontroller, and the first microcontroller is got
After location information, fault-signal and location information are sent to by repairing center by wireless transmitter module;
Step 2, repairing center receive the fault-signal and location information of the first microcontroller transmission, and control circuit board will be former
Barrier signal and fault location information handle and are sent to scheduling system simultaneously;
Step 3, scheduling system carries out processing analysis to fault message and generates processing result, via the first wireless communication module
Processing result is sent to repairing center;
Step 4 after repairing center receives processing result, sends it to the mobile terminal of repair personnel's carrying, repair personnel's root
It is repaired according to fault message and fault location information to the scene shown on mobile terminal.
Compared with prior art, the beneficial effects of the present invention are: field control case obtains fault message and fault bit confidence
Breath, and fault message and fault location information are sent to repairing center, center is repaired by the fault message and fault bit of acquisition
Confidence breath is sent to scheduling system, and simultaneously exports the processing result for the system of dispatching to mobile terminal, dispatches system and is used for event
Barrier information and fault location information carry out analysis record, deal with as a result, processing result is fed back to repairing center simultaneously, move
Moved end is held or is carried by repair personnel, is got to go at abort situation after processing result and fault location information and be repaired
Processing, energy quick obtaining fault message and its position, wirelessly carry out data transmission, are determined with being scheduled for system
Plan, can greatly reduce emergency repair time, improve first-aid repair efficiency, later, repair personnel by the obtained processing result in mobile terminal and
It is gone directly at abort situation after fault location information.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the present invention for the control system of power grid rapid rush-repair.
In figure: 1- field control case, the first microcontroller of 101-, the first locating module of 102-, 103- power grid sensor,
104- wireless transmitter module, the first power module of 105-, 2- repairing center, 201- control circuit board, 202- second power supply module,
203- voice talk module, the first display device of 204-, 205- wireless receiving module, 3- scheduling system, 301- central controller,
302- storage device, the first wireless communication module of 303-, the second display device of 304-, 305- third power module, 306- alarm
Device, the mobile terminal 4-, the second microcontroller of 401-, the second wireless communication module of 402-, the 4th power module of 403-, 404- second
Locating module, 405- third display device, 406- loudspeaker, 407- microphone.
Specific embodiment
Example embodiments are described in detail here, and the example is illustrated in the accompanying drawings.Following description is related to
When attached drawing, unless otherwise indicated, the same numbers in different drawings indicate the same or similar elements.Following exemplary embodiment
Described in embodiment do not represent all implementations consistent with this disclosure.On the contrary, they be only with it is such as appended
The example of device and method being described in detail in claims, some aspects disclosed in the present embodiment are consistent.
Embodiment 1
Referring to Fig. 1, disclosing a kind of control system for power grid rapid rush-repair, including scene control in the embodiment of the present invention
Case 1, repairing center 2, scheduling system 3 and mobile terminal 4 processed, in the present embodiment, the field control case 1 is for obtaining failure letter
Breath and fault location information, and fault message and fault location information are sent to repairing center 2, repairing center 2 will be for that will obtain
The fault message and fault location information obtained is sent to scheduling system 3, and simultaneously exports the processing result of scheduling system 3 to shifting
Moved end 4, scheduling system 3 are dealt with for carrying out analysis record to fault message and fault location information as a result, simultaneously will place
Reason result feeds back to repairing center 2, and mobile terminal 4 is held or carried by repair personnel, gets processing result and fault bit confidence
It is gone to after breath and carries out repairing processing at abort situation, energy quick obtaining fault message and its position wirelessly carry out
Data transmission carries out decision to be scheduled for system 3, can greatly reduce emergency repair time, improve first-aid repair efficiency, later, repair personnel
By being gone directly at abort situation after the obtained processing result in mobile terminal 4 and fault location information.
Embodiment 2
Referring to Fig. 1, disclosing a kind of control system for power grid rapid rush-repair, including scene control in the embodiment of the present invention
Case 1, repairing center 2, scheduling system 3 and mobile terminal 4 processed, in the present embodiment, the field control case 1 is for obtaining failure letter
Breath and fault location information, and fault message and fault location information are sent to repairing center 2, repairing center 2 will be for that will obtain
The fault message and fault location information obtained is sent to scheduling system 3, and simultaneously exports the processing result of scheduling system 3 to shifting
Moved end 4, scheduling system 3 are dealt with for carrying out analysis record to fault message and fault location information as a result, simultaneously will place
Reason result feeds back to repairing center 2, and mobile terminal 4 is held or carried by repair personnel, gets processing result and fault bit confidence
It is gone to after breath and carries out repairing processing at abort situation.The field control case 1 includes being electrically connected with the first microcontroller 101
The first locating module 102, power grid sensor 103, wireless transmitter module 104 and the first power module 105, wherein first is fixed
Position module 102 is used to obtain the location information of field control case 1, and sends it to the first microcontroller 101;Power grid sensor
103 for determining that current Network whether there is failure, if it exists when failure, then sends fault-signal to the first microcontroller 101,
Wireless transmitter module 104 is for realizing the wireless telecommunications between the first microcontroller 101 and repairing center 2, the first microcontroller
101 for being associated processing to fault-signal and location information and sending it to repairing center 2, the first power module 105
For powering for above-mentioned component, in practical application, power grid sensor 103 detects that current Network there are when failure, issues letter
Number the first microcontroller 101 is given, after the first microcontroller 101 gets location information, by wireless transmitter module 104 by failure
Signal and location information are sent to repairing center 2.
Embodiment 3
Referring to Fig. 1, disclosing a kind of control system for power grid rapid rush-repair, including scene control in the embodiment of the present invention
Case 1, repairing center 2, scheduling system 3 and mobile terminal 4 processed, in the present embodiment, the field control case 1 is for obtaining failure letter
Breath and fault location information, and fault message and fault location information are sent to repairing center 2, repairing center 2 will be for that will obtain
The fault message and fault location information obtained is sent to scheduling system 3, and simultaneously exports the processing result of scheduling system 3 to shifting
Moved end 4, scheduling system 3 are dealt with for carrying out analysis record to fault message and fault location information as a result, simultaneously will place
Reason result feeds back to repairing center 2, and mobile terminal 4 is held or carried by repair personnel, gets processing result and fault bit confidence
It is gone to after breath and carries out repairing processing at abort situation.The repairing center 2 includes the be electrically connected with control circuit board 201
Two power modules 202, the first display device 204 and wireless receiving module 205, in the present embodiment, the wireless receiving module
205, for carrying out data communication with field control case 1, receive the fault-signal and position letter of the transmission of the first microcontroller 101
Breath, control circuit board 201 be used to that fault-signal and location information handle and simultaneously with scheduling system 3 and mobile terminal 4 into
Row communication, the first display device 204 is for showing fault message and fault location information.
Embodiment 4
Referring to Fig. 1, disclosing a kind of control system for power grid rapid rush-repair, including scene control in the embodiment of the present invention
Case 1, repairing center 2, scheduling system 3 and mobile terminal 4 processed, in the present embodiment, the field control case 1 is for obtaining failure letter
Breath and fault location information, and fault message and fault location information are sent to repairing center 2, repairing center 2 will be for that will obtain
The fault message and fault location information obtained is sent to repairing center 2, and simultaneously exports the processing result of scheduling system 3 to shifting
Moved end 4, scheduling system 3 are dealt with for carrying out analysis record to fault message and fault location information as a result, simultaneously will place
Reason result feeds back to scheduling system 3, and mobile terminal 4 is held or carried by repair personnel, gets processing result and fault bit confidence
It is gone to after breath and carries out repairing processing at abort situation.The scheduling system 3 includes the be electrically connected with central controller 301
One wireless communication module 303, the second display device 304 and third power module 305, in the present embodiment, the first wireless telecommunications
Module 303 is for realizing the data interchange of central controller 301 and repairing center 2, and the second display device 304 is for showing failure
Information and fault location information, third power module 305 are used to power for above-mentioned component, and central controller 301 is used for failure
Information carries out processing analysis and generates processing result, and processing result is sent in repairing via the first wireless communication module 303
The heart 2.
Meanwhile in order to store to fault message and fault location information, the central controller 301, which is also connected with, to be deposited
Storage device 302, fault message and fault location information are stored in storage device 302 in the form of log, and storage device 302 can
Think hard disk.
For fault message, in order to carry out indicating reminders, the central controller 301 to staff at scheduling system 3
It is also connected with warning device 306.
Embodiment 5
Referring to Fig. 1, disclosing a kind of control system for power grid rapid rush-repair, including scene control in the embodiment of the present invention
Case 1, repairing center 2, scheduling system 3 and mobile terminal 4 processed, in the present embodiment, the field control case 1 is for obtaining failure letter
Breath and fault location information, and fault message and fault location information are sent to repairing center 2, repairing center 2 will be for that will obtain
The fault message and fault location information obtained is sent to repairing center 2, and simultaneously exports the processing result of scheduling system 3 to shifting
Moved end 4, scheduling system 3 are dealt with for carrying out analysis record to fault message and fault location information as a result, simultaneously will place
Reason result feeds back to scheduling system 3, and mobile terminal 4 is held or carried by repair personnel, gets processing result and fault bit confidence
It is gone to after breath and carries out repairing processing at abort situation.The mobile terminal 4 includes the be electrically connected with the second microcontroller 401
Two wireless communication modules 402, the 4th power module 403 and third display device 405, in the present embodiment, described second is wireless
Communication module 402 is for realizing the data communication of the second microcontroller 401 and repairing center 2, and third display device 405 is for showing
Show that fault message and fault location information, the 4th power module 403 are used to power for above-mentioned component.
Although practical when field is repaired, abort situation is not easy to find moreover, faulty location information, because
This, the present embodiment further includes the second locating module 404 being electrically connected with the second microcontroller 401, it may be necessary to load electricity
Sub- map, the second locating module 404 can position the position of repair personnel, be convenient for repair personnel's trouble-shooting position.
Simultaneously as site environment is complicated, communication is interacted for the ease of repair personnel and repairing center 2, described the
Two microcontrollers 401 are also connected with loudspeaker 406 and microphone 407, necessary, and the control circuit board 201 repaired in center 2 is gone back
It is connected with voice talk module 203, speech talkback can be directly realized by when needing to link up, promotes first-aid repair efficiency.
Embodiment 6
Present embodiment discloses a kind of application methods of control system for power grid rapid rush-repair, comprising the following steps:
Step 1, after network is broken down, power grid sensor 103 sends a signal to the first microcontroller 101, the first microcontroller
After 101 get location information, fault-signal and location information are sent to by repairing center 2 by wireless transmitter module 104;
Step 2, repairing center 2 receive the fault-signal and location information of the transmission of the first microcontroller 101, control circuit board
Fault-signal and fault location information are carried out processing and are sent to scheduling system 3 simultaneously by 201;
Step 3, scheduling system 3 carries out processing analysis to fault message and generates processing result, via the first wireless communication module
Processing result is sent to repairing center 2 by 303;
Step 4 after repairing center 2 receives processing result, sends it to the mobile terminal 4 of repair personnel's carrying, repair personnel
It is repaired according to fault message and fault location information to the scene shown on mobile terminal 4.
In step 4, if repair personnel is with repairing center 2, there are communication requirements, and repair personnel is by there is 406 He of loudspeaker
Microphone 407 and repairing center 2 carry out speech talkback, promote first-aid repair efficiency.
Those skilled in the art will readily occur to other realities of the disclosure after considering the disclosure at specification and embodiment
Apply scheme.This application is intended to cover any variations, uses, or adaptations of the disclosure, these modifications, purposes or suitable
The variation of answering property follows the general principles of this disclosure and including the undocumented common knowledge in the art of the disclosure or used
Use technological means.The description and examples are only to be considered as illustrative, and the true scope and spirit of the disclosure are referred to by claim
Out.
It should be understood that the present disclosure is not limited to the precise structures that have been described above and shown in the drawings, and
And various modifications and changes may be made without departing from the scope thereof.The scope of the present disclosure is only limited by the accompanying claims.
Claims (10)
1. a kind of control system for power grid rapid rush-repair, comprising:
Field control case (1) is sent out for obtaining fault message and fault location information, and by fault message and fault location information
Give repairing center (2);
Repairing center (2) for the fault message of acquisition and fault location information to be sent to scheduling system (3), and simultaneously will
The processing result of scheduling system (3), which exports, gives mobile terminal (4);
Scheduling system (3) is dealt with for carrying out analysis record to fault message and fault location information as a result, simultaneously will
Processing result feeds back to repairing center (2);
Mobile terminal (4), is held by repair personnel or is carried, for obtaining processing result and fault location information,
It is characterized in that, the field control case (1), repairing center (2) scheduling system (3) and mobile terminal (4) are by wireless
Mode carries out data communication.
2. being used for the control system of power grid rapid rush-repair as described in claim 1, which is characterized in that the field control case
(1) include:
First locating module (102) for obtaining the location information of field control case (1), and sends it to the first microcontroller
Device (101);
Power grid sensor (103), for determining current Network with the presence or absence of failure;
Wireless transmitter module (104), for realizing the wireless telecommunications between the first microcontroller (101) and repairing center (2);
First microcontroller (101) is used to be associated fault-signal and location information and handles and send it to repairing center
(2);
First power module (105), for powering for above-mentioned component;
First microcontroller (101) is electrically connected the first locating module (102), power grid sensor (103), wireless transmitter module
(104) and the first power module (105).
3. a kind of control system for power grid rapid rush-repair as claimed in claim 2, which is characterized in that the repairing center
(2) include:
First display device (204), for being shown to fault message and fault location information;
Wireless receiving module (205) receives the first microcontroller (101) hair for carrying out data communication with field control case (1)
The fault-signal and location information sent;
Control circuit board (201), for fault-signal and location information handle and simultaneously with scheduling system (3) and mobile
End (4) is communicated;
Second power supply module (202), for powering for above-mentioned component;
Control circuit board (201) is electrically connected second power supply module (202), the first display device (204) and wireless receiving module
(205).
4. a kind of control system for power grid rapid rush-repair as claimed in claim 3, which is characterized in that the scheduling system
(3) include:
Central controller (301), for carrying out processing analysis to fault message and generating processing result, via the first wireless telecommunications
Processing result is sent to repairing center (2) by module (303);
First wireless communication module (303), for realizing the data interchange of central controller (301) and repairing center (2);
Second display device (304), for showing fault message and fault location information;
Third power module (305) is used to power for above-mentioned component;
The first wireless communication module (303), the second display device (304) and the third electricity that central controller (301) is electrically connected
Source module (305).
5. a kind of control system for power grid rapid rush-repair as claimed in claim 4, which is characterized in that the center control
Device (301) is also connected with storage device (302), and storage device (302) is hard disk.
6. a kind of control system for power grid rapid rush-repair as claimed in claim 5, which is characterized in that the center control
Device (301) is also connected with warning device (306).
7. a kind of control system for power grid rapid rush-repair as claimed in claim 6, which is characterized in that the mobile terminal
(4) include:
Second wireless communication module (402), for realizing the data communication of the second microcontroller (401) and repairing center (2);
Third display device (405), for showing fault message and fault location information;
4th power module (403), for powering for above-mentioned component;
Second wireless communication module (402), third display device (405) and the 4th power module (403) with the second microcontroller
Device (401) is electrically connected.
8. a kind of control system for power grid rapid rush-repair as claimed in claim 7, which is characterized in that further include and second
The second locating module (404) that microcontroller (401) is electrically connected.
9. a kind of control system for power grid rapid rush-repair as claimed in claim 7, which is characterized in that second micro-control
Device (401) processed is also connected with loudspeaker (406) and microphone (407), and the control circuit board (201) in repairing center (2) also connects
It is connected to voice talk module (203).
10. a kind of application method of the control system for power grid rapid rush-repair, which comprises the following steps:
Step 1, after network is broken down, power grid sensor (103) sends a signal to the first microcontroller (101), the first micro-control
After device (101) processed gets location information, fault-signal and location information are sent to by repairing by wireless transmitter module (104)
Center (2);
Step 2, repairing center (2) receive the fault-signal and location information of the first microcontroller (101) transmission, control electricity
Fault-signal and fault location information handle and be sent to scheduling system (3) simultaneously by road plate (201);
Step 3, scheduling system (3) carries out processing analysis to fault message and generates processing result, via the first wireless telecommunications mould
Processing result is sent to repairing center (2) by block (303);
Step 4 after repairing center (2) receives processing result, sends it to the mobile terminal (4) of repair personnel's carrying, repairing
Personnel repair according to the fault message and fault location information to scene that show on mobile terminal (4).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910092547.1A CN109814000A (en) | 2019-01-30 | 2019-01-30 | A kind of control system and its application method for power grid rapid rush-repair |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910092547.1A CN109814000A (en) | 2019-01-30 | 2019-01-30 | A kind of control system and its application method for power grid rapid rush-repair |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109814000A true CN109814000A (en) | 2019-05-28 |
Family
ID=66605811
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910092547.1A Pending CN109814000A (en) | 2019-01-30 | 2019-01-30 | A kind of control system and its application method for power grid rapid rush-repair |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109814000A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110994801A (en) * | 2019-12-19 | 2020-04-10 | 云南电网有限责任公司信息中心 | Distribution network automation-based distribution first-aid repair method and system |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102175951A (en) * | 2011-01-18 | 2011-09-07 | 广州思泰信息技术有限公司 | Distribution network fault detection system |
CN103065270A (en) * | 2013-01-05 | 2013-04-24 | 深圳供电局有限公司 | Visual monitored control system is salvageed to electric wire netting trouble |
CN103516054A (en) * | 2011-12-04 | 2014-01-15 | 江苏省电力公司南京供电公司 | Power distribution and utilization network fault automatic processing method |
CN103887794A (en) * | 2014-04-14 | 2014-06-25 | 杭州昊美科技有限公司 | Power distribution network production urgent repair system and method based on Internet of Things |
CN106291245A (en) * | 2016-08-25 | 2017-01-04 | 国网山东省电力公司青岛供电公司 | A kind of distribution network failure actively generates and sends repaiies method and apparatus |
CN106443345A (en) * | 2016-10-08 | 2017-02-22 | 国电南瑞科技股份有限公司 | Fault positioning system and method for overhead power distribution line |
CN108039775A (en) * | 2018-01-02 | 2018-05-15 | 马鞍山佳夫尼电气科技有限公司 | A kind of intelligent maintenance system of electric substation automation system |
CN108449381A (en) * | 2018-02-09 | 2018-08-24 | 鼎信信息科技有限责任公司 | Electric power network repairing dispatching method based on GIS and device |
-
2019
- 2019-01-30 CN CN201910092547.1A patent/CN109814000A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102175951A (en) * | 2011-01-18 | 2011-09-07 | 广州思泰信息技术有限公司 | Distribution network fault detection system |
CN103516054A (en) * | 2011-12-04 | 2014-01-15 | 江苏省电力公司南京供电公司 | Power distribution and utilization network fault automatic processing method |
CN103065270A (en) * | 2013-01-05 | 2013-04-24 | 深圳供电局有限公司 | Visual monitored control system is salvageed to electric wire netting trouble |
CN103065270B (en) * | 2013-01-05 | 2017-08-22 | 深圳供电局有限公司 | Visual monitored control system is salvageed to electric wire netting trouble |
CN103887794A (en) * | 2014-04-14 | 2014-06-25 | 杭州昊美科技有限公司 | Power distribution network production urgent repair system and method based on Internet of Things |
CN106291245A (en) * | 2016-08-25 | 2017-01-04 | 国网山东省电力公司青岛供电公司 | A kind of distribution network failure actively generates and sends repaiies method and apparatus |
CN106443345A (en) * | 2016-10-08 | 2017-02-22 | 国电南瑞科技股份有限公司 | Fault positioning system and method for overhead power distribution line |
CN108039775A (en) * | 2018-01-02 | 2018-05-15 | 马鞍山佳夫尼电气科技有限公司 | A kind of intelligent maintenance system of electric substation automation system |
CN108449381A (en) * | 2018-02-09 | 2018-08-24 | 鼎信信息科技有限责任公司 | Electric power network repairing dispatching method based on GIS and device |
Non-Patent Citations (1)
Title |
---|
张永健: "《电网监控与调度自动化》", 28 February 2007 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110994801A (en) * | 2019-12-19 | 2020-04-10 | 云南电网有限责任公司信息中心 | Distribution network automation-based distribution first-aid repair method and system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109217471A (en) | The identification device of low-voltage power distribution station area's network topology | |
CN204203354U (en) | Line loss monitoring device | |
CN103997533B (en) | A kind of dynamic terminal long-distance maintenance method based on wireless network | |
CN103606055A (en) | Intelligent interaction platform for power fault rush repair | |
CN109814000A (en) | A kind of control system and its application method for power grid rapid rush-repair | |
CN206820745U (en) | Transmission of electricity field operation communication system based on MANET | |
CN203968201U (en) | Automatically try telephone terminal and automatically try telephone system | |
CN113189445A (en) | Configurable multi-class fault positioning and identifying method and system in low-voltage transformer area | |
CN112491007A (en) | Leakage current protection, monitoring and early warning system and method | |
CN116633390A (en) | Power line carrier communication method and device and photovoltaic system | |
CN206557581U (en) | A kind of Allocation transformer safety monitoring system | |
CN105577967A (en) | Incoming call reminding device in shutdown state of mobile terminal and method thereof | |
CN109240162A (en) | A kind of insulator detecting robot control system | |
CN207733795U (en) | A kind of national standard examination hall examine business commander's retinue case | |
CN203522336U (en) | Power operation equipment on-line remote display and alarm device | |
CN112087054A (en) | Monitoring system for transformer substation and use method thereof | |
CN110221150A (en) | Topological structure automatic recognition system | |
CN111030297A (en) | Method and device for monitoring power failure of machine room commercial power | |
CN208241737U (en) | A kind of production telecord for substation | |
CN214410125U (en) | Intelligent access control lock control system for wind power generation tower | |
CN210533431U (en) | Temperature and humidity monitor with NB _ IOT as communication mode | |
CN216387251U (en) | 5G multipoint synchronous test equipment | |
CN211606194U (en) | Distributed photovoltaic data monitoring system based on GPRS wireless communication | |
CN214315353U (en) | Campus emergency communication system based on ZigBee network | |
CN106022661A (en) | Electronic sand table of distribution network |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190528 |