CN102182147B - 一种钢箱梁架设方法 - Google Patents
一种钢箱梁架设方法 Download PDFInfo
- Publication number
- CN102182147B CN102182147B CN2011100800200A CN201110080020A CN102182147B CN 102182147 B CN102182147 B CN 102182147B CN 2011100800200 A CN2011100800200 A CN 2011100800200A CN 201110080020 A CN201110080020 A CN 201110080020A CN 102182147 B CN102182147 B CN 102182147B
- Authority
- CN
- China
- Prior art keywords
- steel
- section
- segment
- concrete
- box girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 64
- 239000010959 steel Substances 0.000 title claims abstract description 64
- 238000000034 method Methods 0.000 title claims abstract description 33
- 238000010276 construction Methods 0.000 claims abstract description 29
- 239000000725 suspension Substances 0.000 claims abstract description 16
- 239000004567 concrete Substances 0.000 claims description 22
- 238000009434 installation Methods 0.000 claims description 3
- 239000011150 reinforced concrete Substances 0.000 description 32
- 230000001737 promoting effect Effects 0.000 description 6
- 238000004891 communication Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 238000006243 chemical reaction Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011100800200A CN102182147B (zh) | 2011-03-31 | 2011-03-31 | 一种钢箱梁架设方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011100800200A CN102182147B (zh) | 2011-03-31 | 2011-03-31 | 一种钢箱梁架设方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102182147A CN102182147A (zh) | 2011-09-14 |
CN102182147B true CN102182147B (zh) | 2012-12-05 |
Family
ID=44568425
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011100800200A Expired - Fee Related CN102182147B (zh) | 2011-03-31 | 2011-03-31 | 一种钢箱梁架设方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102182147B (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103334381A (zh) * | 2013-06-25 | 2013-10-02 | 宁波市政工程建设集团股份有限公司 | 安装钢箱梁的全支架轨道台车驼移装置及施工方法 |
CN111206513A (zh) * | 2020-01-13 | 2020-05-29 | 成都高源工程勘察设计有限公司 | 一种桥梁平移施工结构、装置和跨既有线桥梁的施工方法 |
Families Citing this family (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103031803B (zh) * | 2013-01-17 | 2014-11-26 | 铁道第三勘察设计院集团有限公司 | 小交角低高度钢筋混凝土跨线桥结构 |
CN103174093A (zh) * | 2013-03-14 | 2013-06-26 | 中交二航局第四工程有限公司 | 一种支架区钢箱梁的安装装置及其安装方法 |
CN103194978B (zh) * | 2013-04-16 | 2014-12-10 | 中铁十七局集团第三工程有限公司 | 用于铁路架桥中最后三孔箱梁架设方法 |
CN105200922B (zh) * | 2015-09-08 | 2018-06-29 | 贵州省公路工程集团有限公司 | 一种钢桁梁节段地面拼装运输装置和运输方法 |
CN105648913A (zh) * | 2015-12-17 | 2016-06-08 | 浙江大学 | 一种钢箱梁桥横向分块施工临时加固方法 |
CN106544956B (zh) * | 2016-10-09 | 2018-03-20 | 浙江大学 | 一种钢箱梁横向分块施工临时撑纵向布置方法 |
CN109972846A (zh) * | 2018-08-19 | 2019-07-05 | 中建六局安装工程有限公司 | 一种针对钢圆筒倒装顶升施工的胎架及其施工方法 |
CN108951433B (zh) * | 2018-09-26 | 2024-08-30 | 清华大学 | 钢箱梁悬拼施工的辅助设备 |
CN110242055A (zh) * | 2019-05-08 | 2019-09-17 | 江苏江都建设集团有限公司 | 一种钢桁架安装方法 |
CN110055902B (zh) | 2019-05-23 | 2020-12-22 | 中铁二局集团有限公司 | 一种大吨位箱梁正位提梁上桥施工方法及其架设方法 |
CN110578301A (zh) * | 2019-09-19 | 2019-12-17 | 常州市市政建设工程有限公司 | 一种钢箱梁纵横向滑移施工工艺 |
CN110629681A (zh) * | 2019-09-26 | 2019-12-31 | 常州市市政建设工程有限公司 | 一种多跨钢箱梁施工工艺 |
CN111962402A (zh) * | 2020-08-11 | 2020-11-20 | 中交路桥建设有限公司 | 一种钢箱梁侧向滑移安装方法 |
CN113863151A (zh) * | 2021-10-21 | 2021-12-31 | 中铁第四勘察设计院集团有限公司 | 一种钢箱系杆拱桥施工方法 |
CN114622488B (zh) * | 2022-03-01 | 2024-03-01 | 中铁广州工程局集团有限公司 | 一种节段梁水上提升站及节段梁提升方法 |
CN115125852B (zh) * | 2022-06-30 | 2025-01-10 | 中铁二十局集团第三工程有限公司 | 跨海斜拉桥的塔区无索梁段施工方法 |
CN115404778B (zh) * | 2022-07-25 | 2023-05-16 | 中铁十一局集团有限公司 | 一种跨越既有道路的大跨径钢箱梁顶推系统 |
CN115928583A (zh) * | 2022-12-02 | 2023-04-07 | 中铁广州工程局集团有限公司 | 跨多层公路斜拉桥钢箱梁多节段现场临时拼装架设工法 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005264533A (ja) * | 2004-03-18 | 2005-09-29 | Taisei Corp | Pc箱桁押出し架設工法 |
CN101914897A (zh) * | 2010-07-30 | 2010-12-15 | 中铁四局集团有限公司 | 单主缆斜吊杆地锚式悬索桥的施工方法 |
-
2011
- 2011-03-31 CN CN2011100800200A patent/CN102182147B/zh not_active Expired - Fee Related
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005264533A (ja) * | 2004-03-18 | 2005-09-29 | Taisei Corp | Pc箱桁押出し架設工法 |
CN101914897A (zh) * | 2010-07-30 | 2010-12-15 | 中铁四局集团有限公司 | 单主缆斜吊杆地锚式悬索桥的施工方法 |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103334381A (zh) * | 2013-06-25 | 2013-10-02 | 宁波市政工程建设集团股份有限公司 | 安装钢箱梁的全支架轨道台车驼移装置及施工方法 |
CN103334381B (zh) * | 2013-06-25 | 2015-01-07 | 宁波市政工程建设集团股份有限公司 | 安装钢箱梁的全支架轨道台车驮移装置及施工方法 |
CN111206513A (zh) * | 2020-01-13 | 2020-05-29 | 成都高源工程勘察设计有限公司 | 一种桥梁平移施工结构、装置和跨既有线桥梁的施工方法 |
CN111206513B (zh) * | 2020-01-13 | 2021-08-17 | 成都高源工程勘察设计有限公司 | 一种桥梁平移施工结构、装置和跨既有线桥梁的施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN102182147A (zh) | 2011-09-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102182147B (zh) | 一种钢箱梁架设方法 | |
CN102154988B (zh) | 大跨度钢箱叠拱桥先梁后拱的施工方法 | |
CN203529768U (zh) | 一种在楼面行走作业的门式起重机 | |
CN111172882A (zh) | 一种桥梁主梁悬臂拼装的梁段运输方法 | |
CN104018426B (zh) | 一种钢桁梁安装方法 | |
CN104790297A (zh) | 一种钢桁梁柔性拱拼装方法 | |
CN104762882A (zh) | 桥梁节段吊装装置及吊装方法 | |
CN104195946B (zh) | 多层桥面公轨两用悬索桥的分期实施方法 | |
CN102367650A (zh) | 一种钢管拱桥的施工方法 | |
CN101481903B (zh) | 跨缆吊机倒退拼装架设山区悬索桥主桁方法 | |
CN100497833C (zh) | 高空框架式简易架板机 | |
CN209652741U (zh) | 一种跨铁路站场大跨度高架桥 | |
CN106567337B (zh) | 钢桁架梁的转运平台及其施工方法 | |
CN105484168B (zh) | 一种悬索桥加劲梁旋转吊装设备及加劲梁架设方法 | |
CN113931068A (zh) | 钢与混凝土叠合梁安装的桥面吊机及其架梁方法 | |
CN104179123A (zh) | 一种两孔连做节段拼装造桥机 | |
CN108625270A (zh) | 导梁门吊安装桥梁预制箱梁施工方法 | |
CN205591116U (zh) | 用于立交桥钢箱梁底部施工的双梁移动小车操作平台 | |
CN115748513A (zh) | 基于悬臂空中作业平台的超小高跨比全焊钢桁梁桥施工方法 | |
CN207987749U (zh) | 骑索式桥面吊机 | |
WO2023216325A1 (zh) | 一种桥梁架设方法 | |
JP2001146716A (ja) | 橋桁の架設方法 | |
CN108004930A (zh) | 纵移系杆拱桥的施工方法 | |
CN210315235U (zh) | 可实现纵横向拼装的三工作面架桥机 | |
CN209338005U (zh) | 一种架梁施工用移动式高低腿龙门吊 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
ASS | Succession or assignment of patent right |
Owner name: CHINA RAILWAY PORT CHANNEL ENGINEERING CO., LTD. Effective date: 20120905 |
|
C41 | Transfer of patent application or patent right or utility model | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20120905 Address after: 510800, No. 34, Huadu District, Guangdong, Jianshe Road, Guangzhou Applicant after: THE SECOND CO., LTD. OF CHINA RAILWAY PORT CHANNEL ENGINEERING Group Applicant after: CHINA RAILWAY PORT AND CHANNEL ENGINEERING GROUP Co.,Ltd. Address before: 510800, No. 34, Huadu District, Guangdong, Jianshe Road, Guangzhou Applicant before: The Second Co., Ltd. of China Railway Port Channel Engineering Group |
|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 510800, No. 34, Huadu District, Guangdong, Jianshe Road, Guangzhou Co-patentee after: CHINA RAILWAY PORT AND CHANNEL ENGINEERING GROUP Co.,Ltd. Patentee after: CHINA RAILWAY GUANGZHOU ENGINEERING GROUP SECOND ENGINEERING Co.,Ltd. Address before: 510800, No. 34, Huadu District, Guangdong, Jianshe Road, Guangzhou Co-patentee before: CHINA RAILWAY PORT AND CHANNEL ENGINEERING GROUP Co.,Ltd. Patentee before: The Second Co., Ltd. of China Railway Port Channel Engineering Group |
|
CP01 | Change in the name or title of a patent holder | ||
TR01 | Transfer of patent right |
Effective date of registration: 20191211 Address after: 510800, No. 34, Huadu District, Guangdong, Jianshe Road, Guangzhou Co-patentee after: CHINA RAILWAY GUANGZHOU ENGINEERING GROUP Co.,Ltd. Patentee after: CHINA RAILWAY GUANGZHOU ENGINEERING GROUP SECOND ENGINEERING Co.,Ltd. Address before: 510800, No. 34, Huadu District, Guangdong, Jianshe Road, Guangzhou Co-patentee before: CHINA RAILWAY PORT AND CHANNEL ENGINEERING GROUP Co.,Ltd. Patentee before: CHINA RAILWAY GUANGZHOU ENGINEERING GROUP SECOND ENGINEERING Co.,Ltd. |
|
TR01 | Transfer of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20121205 |
|
CF01 | Termination of patent right due to non-payment of annual fee |