Prior art keywords
work
progress management
progress
worker
terminal
Prior art date
Application number
PCT/JP2021/019905
Other languages
English (en)
French (fr)
Inventor
淳紀 関根
真人 牛村
Original Assignee
株式会社日立ビルシステム
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社日立ビルシステム filed Critical 株式会社日立ビルシステム
Priority to PCT/JP2021/019905 priority Critical patent/WO2022249309A1/ja
Priority to JP2023523784A priority patent/JPWO2022249309A1/ja
Publication of WO2022249309A1 publication Critical patent/WO2022249309A1/ja

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Definitions

  • the present invention relates to a progress management server and a progress management system.
  • the progress of the construction site is managed by the construction manager at the construction site. Since the construction manager manages multiple construction sites, it is often the case that he cannot be permanently stationed at the site. Therefore, the construction manager had to make a phone call to the field worker who actually performed the work at the site to inquire about the progress of the construction, and directly confirm the progress, which made the progress management complicated. In addition, the worker who receives an inquiry from the construction manager must temporarily stop the construction work and check the progress of the construction work. During this confirmation work, the work at the site stopped, so the work was sometimes delayed.
  • Patent Document 1 A technique disclosed in Patent Document 1 is known as a technique for reducing the labor of such on-site management.
  • a maintenance and inspection support system includes a work management unit and a report generation unit.
  • the work management unit stores inspection results of maintenance and inspection work.
  • the inspection results include a plurality of inspection items.
  • a maintenance worker who is performing maintenance and inspection work selects from among a plurality of determination results for each of , and the plurality of inspection items are input by the report generation unit included in the maintenance and inspection work of the maintenance and inspection target device.
  • a report of maintenance and inspection work is generated based on the inspection results stored in the work management unit. This allows the maintenance and inspection support system to reduce the work load of maintenance personnel.”
  • the present invention has been made in view of this situation, and aims to enable a manager to grasp the progress of work at a construction site at the timing requested by the manager.
  • a progress management server stores, for each construction site, a planned process in which work to be performed at a construction site is planned and an actual work process in which results of work performed at the construction site according to the planned process are registered. If there is a difference between the progress management database to be managed and the planned process read from the progress management database and the actual work process, the progress information created based on the difference will be sent from the administrator terminal that manages the progress of the construction site. and a progress management unit that outputs to an administrator terminal in response to a request.
  • the progress information created based on the difference between the planned process and the actual work process is output to the manager terminal at the timing requested by the construction manager.
  • the progress of work at the construction site can be grasped without inquiring of the site worker.
  • FIG. 1 is a block diagram showing an example of the overall configuration of a progress management support system according to one embodiment of the present invention
  • FIG. FIG. 5 is a sequence diagram showing an example of processing for confirming and registering work instruction content for the day performed by the progress management support system according to the embodiment of the present invention
  • It is a figure which shows the example of a display of the screen information at the time of registration of the work of the day displayed on a worker terminal which concerns on one Embodiment of this invention.
  • FIG. 3A is a diagram showing a display example of a site selection screen.
  • FIG. 3B is a diagram showing a display example of the work content selection screen.
  • FIG. 3C is a diagram showing a display example of a work content selection screen on which a calendar for date selection is displayed.
  • FIG. 3D is a diagram showing a display example of a work content selection screen on which work instruction content is displayed.
  • FIG. 7 is a diagram showing a display example of screen information displayed on the worker terminal when starting work and when registering work execution results according to the embodiment of the present invention;
  • FIG. 5 is a sequence diagram showing an example of processing for registering the execution results of work performed by the progress management support system according to the embodiment of the present invention; It is a figure which shows the display example of the screen information displayed on a worker terminal at the time of registration of the work execution result which concerns on one Embodiment of this invention.
  • FIG. 7 is a diagram showing a display example of screen information displayed on the worker terminal when starting work and when registering work execution results according to the embodiment of the present invention
  • FIG. 5 is a sequence diagram showing an example of processing for registering the execution results of work performed by the progress management support system according to the embodiment of the present invention. It is a figure which shows the display example of the screen information displayed on a worker terminal at the time of registration
  • FIG. 10 is a diagram showing a display example of a confirmation screen for a work execution result according to one embodiment of the present invention. It is a figure which shows a mode that the delay of work is notified to the worker terminal which concerns on one Embodiment of this invention.
  • 1 is a block diagram showing a hardware configuration example of a computer according to an embodiment of the present invention; FIG.
  • FIG. 1 is a block diagram showing an overall configuration example of a progress management support system 1 according to one embodiment of the present invention.
  • the progress management support system 1 includes a progress management server 10, an operator terminal 20, and an administrator terminal 30, which are connected to each other via a network N. As shown in FIG.
  • the progress management server 10 is an example of an information processing device managed by a construction management department of a company that manages the progress of an elevator installation site.
  • the progress management server 10 manages, for example, the progress of elevator installation work.
  • the progress management server 10 includes a progress management database 40 (hereinafter abbreviated as progress management DB 40 ), a progress management section 50 and a communication section 56 .
  • the progress management DB 40 is a database that manages, for each construction site, a planned process in which work to be performed at a construction site is planned and an actual work process in which the results of work performed at the construction site according to the planned process are registered.
  • the progress management DB 40 has site A information 41 that stores site information on site A, site B information 41 that stores site information on site B, and site C information 41 that stores site information on site C. . In this way, the progress management DB 40 accumulates and manages site information for each site.
  • the progress management unit 50 accesses the site A information 41 in which the site information of the site A is stored.
  • the worker terminal 20 is used by the site worker at the site A
  • the manager terminal 30 is used by the construction manager at the site A. Description of the site B information 41 and the site C information 41 is omitted.
  • the site A information 41 includes construction specification information 42, installation site related person information 43, process chart 44, customer information 45, and work execution form 46.
  • the construction specification information 42 is information indicating the construction specification of the elevator at the installation site (referred to as site A).
  • the installation site related person information 43 includes construction managers, site workers, material transporters, product designers, sales representatives, construction specification determiners, etc. (hereinafter collectively referred to as "site related parties"). This is information that manages the name, affiliation, etc. of a person (to be called) in association with the work ID. Each work performed at the installation site is identified by the work ID.
  • the process chart 44 is information including a planned process chart in which the schedule of each work process at the installation site is planned and an actual work process chart in which the results of implementation of the work instructions of the site workers are recorded.
  • the customer information 45 is information for managing the person in charge, contact information, address, etc. of the customer.
  • the work execution form 46 is a form containing information such as work procedure manuals, danger prediction activity entry forms, danger prediction activity case studies, related accident cases, work check sheets, etc.
  • the forms according to the present embodiment are various types of information displayed on the worker terminal 20 and the manager terminal 30 .
  • the risk prediction activity is not described as an item in the planned process, but the company that manages the worker imposes on the worker to implement the risk prediction activity before starting work.
  • Danger prediction activity is an activity to check whether obstacles leading to danger have been eliminated by listing dangerous events that may occur in the work performed on the day before starting work. The degree of danger is defined for each assumed dangerous event, and the higher the degree of danger, the more serious the accident.
  • site workers are urged to perform safety inspections before starting work so that dangerous events with a high degree of risk can be eliminated. It is expected that even if an accident occurs during work, it will be kept to a minor accident by conducting risk prediction activities by site workers.
  • the progress management unit 50 When there is a difference between the planned process read from the progress management DB 40 and the actual work process, the progress management unit 50 provides progress information created based on the difference in response to a request from the manager terminal 30 that manages the work progress. output to the administrator terminal 30 according to the As this progress information, for example, highlighting of the work content that has not been completed according to the planned process and a message indicating that the work is behind schedule are assumed.
  • the progress management unit 50 generates progress information for managing the progress of the elevator installation site, receives requests from the worker terminal 20 and the manager terminal 30, and outputs the progress information to these terminals.
  • the progress management unit 50 includes a work extraction unit 51, a planned process registration unit 52, an actual work process registration unit 53, a form creation unit 54, a process difference extraction unit 55, and a communication unit 56.
  • the communication unit 56 When the communication unit 56 receives a request (for example, an information acquisition request) from the worker terminal 20 or the administrator terminal 30 via the network N, it passes the request to the progress management unit 50 . Further, when receiving response information (for example, screen information) from the progress management unit 50, the communication unit 56 responds to the worker terminal 20 or the administrator terminal 30, which is the source of the request, via the network N. return information.
  • a request for example, an information acquisition request
  • response information for example, screen information
  • the work extraction unit 51 extracts the work at the construction site and work date requested from the worker terminal 20 from the planned process. For example, when receiving a work extraction request from the worker terminal 20 or the manager terminal 30, the work extraction unit 51 extracts work scheduled to be performed at the corresponding site in the progress management DB 40.
  • FIG. For example, when receiving a work extraction request for site A, the work extraction unit 51 selects the site A information 41, refers to the construction specification information 42, the installation site related person information 43, and the process chart 44, and The work scheduled to be performed on the date specified by the terminal 20 or the administrator terminal 30 is extracted.
  • the progress management DB 40 stores a large amount of site information, and a work day is planned for each site information. Therefore, by inputting the construction site and work date to the worker terminal 20, the site worker can confirm the work planned for the specific construction site and work date.
  • the work extraction unit 51 outputs the actual work process registered in the process chart 44 by construction site and work date to the worker terminal 20 or manager terminal 30 requesting acquisition of the actual work process.
  • the form including the actual work process displayed on the administrator terminal 30 can also be printed on paper from a printing machine with which the administrator terminal 30 can communicate. Therefore, the construction manager or the site worker can display the progress of the construction site on the screen or print it on paper and submit it according to the request of the customer of the construction site.
  • the work extraction unit 51 outputs the danger prediction activity extracted from the form to the worker terminal 20 according to the work. For this reason, the worker terminal 20 also displays a form including a risk prediction activity that is performed in accordance with the work.
  • the planned process registration unit 52 registers the planned process input from the administrator terminal 30 in the progress management DB 40.
  • the planned process registration unit 52 registers the planned process for the site A input to the manager terminal 30 in the process chart 44 of the site A information 41 .
  • the planned process registration unit 52 refers to the construction specification information 42 and the installation site related person information 43 of the progress management DB 40, confirms the number of workers who can be secured at the site A, their skills, etc.
  • the created planned process can be registered in the process chart 44 .
  • the actual work process registration unit 53 registers the implementation result data received from the worker terminal 20 in the progress management DB 40 as the actual work process.
  • the result of the work performed by the site worker according to the planned process is input from the worker terminal 20 .
  • the actual work process registration unit 53 registers the result of implementation at the site received from the worker terminal 20 in the process chart 44 of the site A information 41 as the actual work process.
  • the actual work process registration unit 53 can also register in the process chart 44 the implementation results of the risk prediction activities performed at the construction site, which are input from the worker terminal 20 .
  • the form creation unit 54 creates a form (for example, the work execution form 46) including the work contents of the work instructed to the worker at the construction site according to the planned process registered in the process chart 44, and manages progress. Register the form in the DB 40.
  • the form creating unit 54 also creates a form including risk prediction activities to be performed in accordance with the work of the planned process, and registers the form in the progress management DB 40 .
  • the contents of work instructions for instructing the site workers to perform the work of the planned process, the results of hazard prediction activities and the implementation results of the hazard prediction activities, the contents of the work instructions and the results of the work, the work procedures and the work At least one of the inspection result of the procedure manual and the description result on the check sheet in which the installation accuracy and the installation result in the installation work of the elevator are confirmed is included.
  • the worker terminal 20 receives the data of the planned process and the actual work process read from the process chart 44 by the work extraction section 51 from the progress management section 50, and displays the planned process and the actual work process. In addition, the worker terminal 20 outputs a form acquired from the work execution form 46 of the progress management DB 40 according to the work extracted from the planned process by the work extractor 51 . Also, progress information indicating the difference between the planned process and the actual work process is output to the manager terminal 30 . The progress information indicating the difference between the planned process and the actual work process is indicated by highlighting in FIG. 7, which will be described later. Information indicating the difference between the planned process and the actual work process is displayed on the worker terminal 20 as notification information shown in FIG. 8, which will be described later.
  • the process difference extraction unit 55 reads the planned process and the actual work process from the progress management DB 40, extracts the difference between the planned process and the actual work process, and creates progress information. For example, the process difference extraction unit 55 reads the process chart 44 from the site A information 41 and extracts the difference between the planned process and the actual work process. If there is a difference, the process difference extraction unit 55 outputs progress information created based on this difference to the manager terminal 30 .
  • the process difference extraction unit 55 outputs progress information indicating the work delay to the manager terminal 30 or the worker terminal 20 at the timing requested by the manager terminal 30 . Therefore, the construction manager can operate the manager terminal 30 to check the progress information indicating the work delay at the intended timing. In addition, when a work delay occurs, progress information indicating the work delay is automatically displayed on the worker terminal 20 or the manager terminal 30 to alert the site worker or construction manager. good too.
  • the administrator terminal 30 can execute all functional units of the progress management unit 50. On the other hand, the worker terminal 20 cannot execute the function of the planned process registration section 52 .
  • the worker terminal 20 is an example of an information processing terminal operated by a field worker at an installation site where elevator installation work is performed.
  • a mobile terminal such as a mobile phone, a smart phone, a tablet-type mobile terminal, or a laptop-type personal computer is used as the worker terminal 20 .
  • a site worker can easily operate the worker terminal 20 at the site. Through the Web browser installed in the worker terminal 20, the field worker confirms the work to be done on the day and inputs the execution result of the work.
  • the worker terminal 20 includes a display section 21 that displays various types of information, and an input section 22 that receives information input by the field worker.
  • the worker terminal 20 has the same functions as those of general mobile terminals.
  • the operator terminal 20 has a call function and a function of displaying information acquired from the progress management server 10 via the network N on the display unit 21 .
  • the worker terminal 20 has a function of receiving input of work execution results from the input unit 22 and transmitting and receiving various data to and from the progress management server 10 .
  • the worker terminal 20 receives the data of the work of the day and the contents of work instructions from the progress management server 10 .
  • a site worker activates a web browser on the worker terminal 20 to browse the construction specification information 42 at the construction site, browse the work instruction content specified in the planned process, and view the work instruction content of the day. It is possible to register the result of the work performed in response to the request as a progress result in the process chart 44 .
  • the progress result may be the result of inputting the work instruction content, or the input of the risk prediction activity linked to the work instruction content on the day and the implementation result thereof.
  • the entry result of the check sheet which confirmed the installation accuracy of the installation work of the elevator in a work site, and the work implementation result may be input.
  • the manager terminal 30 is a terminal operated by a construction manager at the installation site.
  • a mobile terminal such as a mobile phone, a smart phone, a tablet-type mobile terminal, or a laptop-type personal computer is used.
  • the construction manager checks the work to be done on the day for each site and checks the progress of the work.
  • the administrator terminal 30 has the same functions as general desktop personal computers, mobile terminals, etc., that is, functions that can perform various processes such as displaying, inputting, and transmitting/receiving information via calls and networks.
  • the data of the progress management server 10 including the planned processes and actual work processes registered in the progress management server 10 is transmitted from the progress management server 10 in response to access from the manager terminal 30 .
  • the construction manager operates the manager terminal 30 to create a planned process chart for the installation site that the construction manager is in charge of, and registers it in the progress management server 10. Then, the construction manager can use the manager terminal 30 to manage the progress and the like at the installation site.
  • the manager terminal 30 includes a display section 31 that displays various types of information, and an input section 32 that receives information input by the construction manager.
  • the manager registers the created planned process in the progress management server 10 through the input unit 32 of the manager terminal 30 . Also, the manager can manage the progress of the actual work by confirming the difference between the planned process and the actual work process displayed on the display unit 31 of the manager terminal 30 .
  • FIG. 2 is a sequence diagram showing an example of processing for confirming and registering the work instruction content of the day performed by the progress management support system 1. As shown in FIG. Here, a flow will be described in which the worker operates the worker terminal 20, confirms the content of the work instruction for the day from the planned process chart registered in the progress management server 10, and registers the confirmation result in the progress management server 10. .
  • the worker selects the site name and work date of the site through the worker terminal 20 before starting work on the day.
  • the worker terminal 20 transmits data of the site name and work date selected by the site worker to the progress management server 10 (S1).
  • the work extraction unit 51 of the progress management server 10 receives the data of the work site name and the work date of the work site from the worker terminal 20, the work extraction unit 51 extracts the data of the day from the planned process included in the process chart 44 of the work site according to the date information. Work is extracted (S2).
  • the progress management unit 50 transmits the work of the day extracted by the work extraction unit 51 to the worker terminal 20 as work instruction content data. (S3)
  • the display unit 21 of the worker terminal 20 Upon receiving the work instruction content data from the progress management server 10, the display unit 21 of the worker terminal 20 displays the work instruction content on the screen (S4). For example, if the work planned for the morning and the afternoon of the day are different, the work planned for the morning and the afternoon are displayed on the worker terminal 20 as the work content of the day. After confirming the contents of the work instruction displayed on the screen, the worker inputs confirmation of the contents of the work instruction to the progress management server 10 through the input unit 22 . Then, the worker terminal 20 transmits the data of the result of confirming the content of the work instruction by the worker to the progress management server 10 (S5), and ends this process.
  • the planned process registration unit 52 of the progress management server 10 registers the confirmation result of the work contents of the day in the process chart 44 based on the data of the confirmation result of the work instruction contents received from the worker terminal 20 (S6). End the process.
  • the site stakeholders (including workers and construction managers) request the progress management server 10 to acquire the process chart 44 via the worker terminal 20 or the manager terminal 30, can check the work contents of the planned process registered in the process chart 44 at any time.
  • the worker terminal 20 displays the work instruction content, for example, it is possible to display the work execution form 46 that matches the work instruction content of the day. Since the work execution form 46 contains various types of information corresponding to the content of the work instruction, the field worker can check the information necessary for the work on the day without excess or deficiency.
  • FIG. 3 is a diagram showing a display example of screen information displayed on the worker terminal 20 at the time of registering work for the day.
  • FIG. 3A is a diagram showing a display example of the site selection screen W1.
  • a list of site names of a plurality of sites is displayed on the site selection screen W1.
  • the site worker selects a site name corresponding to the site where work is to be performed on the day through the site selection screen W1 displayed on the display unit 21 of the worker terminal 20.
  • FIG. After the site name is selected on the site selection screen W1, the display unit 21 displays a work content selection screen W2 shown in FIG. 3B.
  • FIG. 3B is a diagram showing a display example of the work content selection screen W2.
  • the field worker inputs the work date and time from the work content selection screen W2.
  • a today button is displayed at the top of the date selection screen.
  • today's date when the field worker is operating the worker terminal 20 is displayed in the date input field.
  • FIG. 3C is a diagram showing a display example of the work content selection screen W2 on which a calendar for date selection is displayed.
  • a calendar for date selection is displayed over the date selection screen.
  • the field worker can select any date from the date selection calendar if he/she wants to check the planned process on a day other than today.
  • the selected date is displayed in the date input field.
  • FIG. 3D is a diagram showing a display example of the work content selection screen W2 on which work instruction content is displayed.
  • Fig. 3D shows an example in which "Scaffolding assembly” and “Centering in tower” are displayed in the "Select work schedule in the morning” column as work instruction contents. Note that the fact that the "select work schedule for the afternoon” field is blank means that the same work as the work shown in the "select work schedule for the morning” field will be performed in the afternoon. If there is no work in the afternoon, a blank or “no work” is displayed in the "Select work schedule for the afternoon” field.
  • the field worker After confirming the work instruction content displayed on the work content selection screen W2, the field worker selects the "Next" button at the bottom of the work content selection screen W2.
  • the operator terminal 20 transmits the confirmation result data to the progress management server 10 .
  • the progress management unit 50 of the progress management server 10 receives the confirmation result data from the worker terminal 20, the work extracted by the work extraction unit 51 is registered in the process chart 44 as the work of the day.
  • FIG. 4 is a diagram showing a display example of screen information displayed on the worker terminal 20 when starting work and when registering work execution results.
  • a risk prediction activity confirmation screen W3 is displayed on the display unit 21 of the worker terminal 20 when the work is started and when the work execution result is registered.
  • the site worker can utilize the risk prediction activity displayed on the risk prediction activity confirmation screen W3 at the start of the work for the work of the day.
  • the danger prediction activity is displayed as "KY" in the figure.
  • a pull-down list is displayed in the input field for the number of workers, and the site worker can register the number of workers selected from the pull-down list as the number of workers.
  • links to related accident cases and related work procedures are displayed for each work instruction content of "start of construction/safety measures" and "delivery of products". By clicking the link, the site worker can confirm one or more related accident cases and related work procedures for each work instruction content.
  • Risk prediction activities are carried out as part of safety measures at work sites. As mentioned above, risk prediction activities are an initiative to prevent injuries during work by identifying points of danger that can lead to accidents and injuries from the work and site environment of the day and recognizing them by all workers. is. For this reason, a form dedicated to risk prediction activities is not provided. As information used for risk prediction activities, a wide variety of materials and forms are assumed, such as procedures describing elevator assembly work and case studies of occupational accidents that occurred in similar work in the past. A field worker can check these materials and forms at any time.
  • a check box is displayed for each work for the field worker to enter whether or not to execute "work review".
  • "Work review” is an item for the field worker to input whether or not the risk prediction activity is implemented. Details of the work review will be described later with reference to FIG.
  • KY sheets work implementation forms are also used in paper media called "KY sheets".
  • the on-site worker fills in the necessary items on the KY sheet and the results of the implementation of the risk prediction activities in the check items, photographs the KY sheet with the camera attached to the worker terminal 20, and then manages the progress of the photograph of the KY sheet. It can also be uploaded to the server 10 . The uploaded photograph is registered in the process chart 44 as part of the actual work process.
  • FIG. 5 is a sequence diagram showing an example of processing for registering the execution results of work performed by the progress management support system 1.
  • the field worker operates the worker terminal 20 and registers the implementation result for the work of the day registered in the progress management server 10 .
  • the worker terminal 20 transmits to the progress management server 10 data indicating that the site worker will input the work execution result of the day (S11). This process is performed by the site worker to display the work instruction contents registered in the progress management server 10 before the work on the worker terminal 20 after the work on the day.
  • step S6 in FIG. Extracts the contents of the work instruction for the day registered in (S12). Then, the progress management unit 50 transmits the data of the work instruction content for the day extracted from the site A information 41 to the worker terminal 20 (S13).
  • the display unit 21 of the worker terminal 20 displays on the screen the work instruction content registered before the work on the day based on the work instruction content data received from the progress management server 10 (S14).
  • the field worker confirms that the content of the work instruction displayed on the screen is the content of the work instruction registered before starting the work. Then, the field worker transmits the execution result of the work instruction to the worker terminal 20 through the input unit 22 .
  • the worker terminal 20 transmits the data of the execution result of the work instruction to the progress management server 10 (S15).
  • the actual work process registration unit 53 registers the implementation result as the actual work process in the process chart 44 (S16). Then, the process difference extraction unit 55 extracts process differences based on the planned process and the actual work process from the process chart 44 (S17).
  • the process difference extraction unit 55 determines whether or not there is a difference between the planned process and the actual work process (S18). If there is no difference between the planned process and the actual work process (NO in S18), the progress management unit 50 notifies the worker terminal 20 that there is no difference (S21), and terminates this process.
  • the progress management unit 50 transmits to the worker terminal 20 that the work is delayed based on this difference (S19). .
  • the display unit 21 of the worker terminal 20 displays the fact that the work is delayed, which is received from the progress management server 10 (S20), and ends this process.
  • the field worker confirms that the work is delayed, he/she can grasp the cause of the work delay and take countermeasures such as accelerating the progress of the work.
  • the work instruction implementation result and the actual work process chart can be checked at any time by requesting the progress management server 10 from the site personnel via the worker terminal 20 or the manager terminal 30. It is possible.
  • FIG. 6 is a diagram showing a display example of screen information displayed on the worker terminal 20 when registering work execution results.
  • a display example of the risk prediction activity confirmation screen W3 similar to that of FIG. 4 is shown.
  • the site worker registers the risk prediction activity as the work execution result of the day when registering the execution result of the work of the day displayed on the worker terminal 20 .
  • On-site workers carry out risk prediction activities, and when the work for the day is completed, just before leaving the site on that day, check whether the "risk prediction activities" decided by the site workers themselves are reviewed. Checking the review performed by the on-site worker also serves to register the implementation results of the work performed on-site. Therefore, inputting a check in the check box of "work review" by the field worker is also called “work registration”.
  • the field worker displays the risk prediction activity confirmation screen W3 on the screen of the worker terminal 20 after performing the work on the day, and performs "work review" to confirm whether the risk prediction activity has been performed. If the field worker has completed the risk prediction activity, the field worker checks the check box on the registration screen shown in FIG. On the other hand, if the risk prediction activity is insufficient, the site worker inputs the reason for not being able to perform the risk prediction activity on the registration screen.
  • the registration of the work execution results on the worker terminal 20 ends.
  • the worker terminal 20 transmits data of the implementation result of the risk prediction activity to the progress management server 10 .
  • the actual work process registration unit 53 of the progress management server 10 shown in FIG. By registering the work execution result in the work schedule 44, the registration of the actual work process on the work execution date is completed.
  • FIG. 7 is a diagram showing a display example of a work execution result confirmation screen.
  • the work execution result including the work content and the completion date of the work registered in the progress management DB 40 can be confirmed by the person concerned in the field.
  • the worker terminal 20 or the manager terminal 30 requests the progress management server 10 to acquire the work execution result. do.
  • the work execution result data acquired by the progress management server 10 from the progress management DB 40 is transmitted to the worker terminal 20 or manager terminal 30 that made the request. Based on the data received from the progress management DB 40, the worker terminal 20 or the manager terminal 30 displays the work execution result on the work execution result confirmation screen.
  • the work execution result confirmation screen displays the work details registered in the planned process, a check box indicating whether the work is completed, and the completion date of the work.
  • a work content in which a check is entered in the check box indicating whether or not the work is completed and a date is entered in the work completion date indicates that the work has been completed.
  • the work content displayed as "work delayed" on the work completion date indicates that the work was not completed on the work day according to the planned process.
  • the delayed work content is highlighted in a different color (e.g., red) or font (e.g., bold) from other work content, or the delayed work content column is highlighted in a different color. (eg, red).
  • the construction manager can consult with the contractor of the work and take measures such as changing the delivery date or the planned process at an early stage.
  • FIG. 8 is a diagram showing how the worker terminal 20 is notified of the work delay. If the work is not completed according to the planned process, the work delay is notified on the danger prediction activity confirmation screen W3 of the worker terminal 20 . The worker can recognize that the work was not completed according to the planned process by seeing a message such as "work is delayed" superimposed on the danger prediction activity confirmation screen W3.
  • FIG. 9 is a block diagram showing a hardware configuration example of the computer 60.
  • the computer 60 is an example of hardware used as a computer operable as the progress management server 10, the worker terminal 20, or the manager terminal 30 according to this embodiment.
  • the respective functional blocks shown in FIG. implement a progress management method.
  • the computer 60 includes a CPU (Central Processing Unit) 61, a ROM (Read Only Memory) 62, and a RAM (Random Access Memory) 63 connected to a bus 64 respectively.
  • Computer 60 further comprises display device 65 , input device 66 , non-volatile storage 67 and network interface 68 .
  • the CPU 61 reads the program code of the software that implements each function according to the present embodiment from the ROM 62, loads it into the RAM 63, and executes it. Variables, parameters, etc. generated during the arithmetic processing of the CPU 61 are temporarily written in the RAM 63 , and these variables, parameters, etc. are read by the CPU 61 as appropriate.
  • an MPU Micro Processing Unit
  • the function of the progress management unit 50 of the progress management server 10 is implemented by the CPU 61 .
  • the worker terminal 20 and the manager terminal 30 also have a CPU 61, a ROM 62 and a RAM 63, and the operation of each terminal is controlled by the CPU 61 and the like.
  • the display device 65 is, for example, a liquid crystal display monitor, and displays the results of the processing performed by the computer 60 to the workers involved in the work.
  • a keyboard, a mouse, or the like is used as the input device 66, and the operator can perform predetermined operation inputs and instructions.
  • the progress management server 10 may not be provided with the display device 65 and the input device 66 .
  • nonvolatile storage 67 for example, HDD (Hard Disk Drive), SSD (Solid State Drive), flexible disk, optical disk, magneto-optical disk, CD-ROM, CD-R, magnetic tape, nonvolatile memory, or the like is used. be done.
  • the nonvolatile storage 67 stores an OS (Operating System), various parameters, and programs for making the computer 60 function.
  • the ROM 62 and the non-volatile storage 67 record programs and data necessary for the operation of the CPU 61, and are examples of computer-readable non-transitory storage media storing programs executed by the computer 60. Used.
  • the progress management DB 40 shown in FIG. 1 is configured in the non-volatile storage 67 provided in the progress management server 10 .
  • a NIC Network Interface Card
  • various data can be transmitted and received between devices via a LAN (Local Area Network), a dedicated line, or the like connected to the terminal of the NIC.
  • LAN Local Area Network
  • the function of the communication unit 56 of the progress management server 10 is implemented by the network interface 68 .
  • the network interface 68 of the operator terminal 20 and the administrator terminal 30 realizes the function of a communication unit that can be connected to the network N.
  • the site worker operates the worker terminal 20 to check the daily work on the designated day at the construction site and input the work execution result. .
  • the implementation result input to the worker terminal 20 is registered in the process chart 44 as an actual work process. If there is a difference between the planned process and the actual work process for each site, the progress information indicating the work delay is displayed on the manager terminal 30 at the timing requested by the construction manager. Therefore, the construction manager can timely grasp the delay of the actual work process with respect to the planned process. Then, the construction manager can promptly respond to the delayed work by prompting the field workers to implement the work, reexamining the schedule, and the like.
  • the construction manager can check the planned and actual work processes at the site at any time requested by the construction manager without directly inquiring the construction progress status to the site workers at the construction site. Therefore, it is possible to eliminate the temporary interruption of the site work due to the construction manager's inquiry to the site worker, and eliminate the influence of the work delay caused by the construction manager.
  • the construction manager can grasp the progress of the work at the installation site he is in charge of at the timing desired by the construction manager. Therefore, even if the construction manager is in charge of a plurality of installation sites, he or she can check the current progress status of the plurality of installation sites without taking much time.
  • the field worker can check the work planned for the day through the worker terminal 20 before starting work on the day. In addition, after finishing the work for the day, the field worker can input completion of the work through the worker terminal 20 at the work site. Therefore, the on-site worker does not need to return to the office or the like to input completion of the work, thereby reducing the travel time from the work site to the office or the like. Moreover, when the work is delayed, the site worker can recognize the work delay based on the progress information displayed on the worker terminal 20 in the same way as the construction manager.
  • the site worker can confirm the risk prediction activity through the worker terminal 20 before starting work on the day. Therefore, the site worker can remove obstacles that may cause an accident based on the risk prediction activity before starting the work, so that a safe work site can be ensured.
  • the site worker can display the details of the risk prediction activity on the worker terminal 20 and grasp it.
  • the on-site worker can input whether or not the risk prediction activity is to be performed through the worker terminal 20 with a simple operation. Then, if the risk prediction activity has not been implemented, the site worker inputs the reason for the non-implementation from the worker terminal 20, so that the workers involved in the work can carefully examine the details of the risk prediction activity. .
  • the on-site worker inputs the contents of the work instruction for the work to be performed on the day, the work execution result, and the danger prediction activity and the work result into the progress management DB 40.
  • the on-site worker may register the contents of the work procedure manual and the result of viewing the work procedure manual in the progress management DB 40, or the on-site worker may check the installation accuracy and results of the on-site installation work. You may register the entry result of a sheet
  • the progress management unit 50 outputs progress information indicating the delay of the actual work to the manager terminal 30 when a difference occurs between the planned process and the actual work process. You may The construction manager who operates the manager terminal 30 can immediately grasp the site where the actual work is delayed based on the notified progress information.
  • the present invention is not limited to the above-described embodiments, and of course, various other application examples and modifications can be made without departing from the gist of the present invention described in the scope of claims.
  • the above-described embodiments describe the configuration of the system in detail and specifically in order to explain the present invention in an easy-to-understand manner, and are not necessarily limited to those having all the configurations described.
  • the control lines and information lines indicate those considered necessary for explanation, and not all control lines and information lines are necessarily indicated on the product. In practice, it may be considered that almost all configurations are interconnected.

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Theoretical Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • Primary Health Care (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)

Abstract

進捗管理サーバは、進捗管理データベースと、進捗管理部と、を備える。進捗管理データベースは、工事現場で行われる作業が計画された計画工程と、計画工程に従って工事現場で実施された作業の実施結果が登録された実作業工程とを、工事現場ごとに管理する。進捗管理部は、進捗管理データベースから読み出した計画工程と実作業工程との差異が生じた場合に、差異に基づいて作成した進捗情報を、工事現場の進捗を管理する管理者端末からの要求に応じて管理者端末に出力する。

Description

進捗管理サーバ及び進捗管理システム
 本発明は、進捗管理サーバ及び進捗管理システムに関する。
 例えば、昇降機の据付工事が行われる際、工事現場の進捗状況は、工事現場の施工管理者によって管理されている。施工管理者は、複数個所の工事現場を管理するので、現場に常駐できないことが多い。そこで、施工管理者は、現場で実際に作業を行う現場作業者に電話を掛けて工事の進捗状況を問合せ、進捗状況を直接確認していたので、進捗管理が煩雑であった。また、施工管理者から問い合わせを受けた作業者は、一時的に工事を中断し、工事の実施状況を確認しなければならない。この確認作業の間は、現場の作業が止まるので、作業が遅れることがあった。
 特に、建屋に昇降機を据え付ける工事の場合、一人の施工管理者が複数の据付工事の現場を管理している。このため、施工管理者は、各現場の進捗状況を把握することに苦慮していた。このような現場管理の手間を軽減する技術として、特許文献1に開示された技術が知られている。
 特許文献1には、「保守点検支援システムは、作業管理部と、報告書生成部と、を備える。作業管理部は、保守点検作業の点検結果を記憶する。点検結果は、複数の点検項目の各々について複数の判定結果の中から保守点検作業を行っている保守員が選択することで入力される。複数の点検項目は、保守点検対象装置の保守点検作業に含まれる報告書生成部は、作業管理部が記憶している点検結果に基づいて、保守点検作業の報告書を生成する。これにより、保守点検支援システムは、保守員の作業負担を軽減できる。」と記載されている。
国際公開第2020/202574号
 しかしながら、特許文献1に記載されている報告書作成システムでは、単に保守点検作業内容やその点検結果に基づいて、報告書が作成されるに過ぎない。このため、施工管理者が作業の進捗を把握するためには、工事現場にいる現場作業者に直接問い合わせる必要があった。また、従来、事前に計画された作業工程と、作業の実施結果との差異は管理されておらず、施工管理者が作業の遅れを把握するのに時間がかかっていた。
 本発明はこのような状況に鑑みて成されたものであり、管理者が要求するタイミングで工事現場における作業の進捗状況を把握できるようにすることを目的とする。
 本発明は、進捗管理サーバは、工事現場で行われる作業が計画された計画工程と、計画工程に従って工事現場で実施された作業の実施結果が登録された実作業工程とを、工事現場ごとに管理する進捗管理データベースと、進捗管理データベースから読み出した計画工程と実作業工程との差異が生じた場合に、差異に基づいて作成した進捗情報を、工事現場の進捗を管理する管理者端末からの要求に応じて管理者端末に出力する進捗管理部と、を備える。
 本発明によれば、例えば、施工管理者が要求するタイミングで計画工程と実作業工程との差異に基づいて作成された進捗情報が管理者端末に出力されるので、施工管理者が工事現場の現場作業者に問い合わせなくても、工事現場における作業の進捗状況を把握できる。
本発明の一実施形態に係る進捗管理支援システムの全体構成例を示すブロック図である。 本発明の一実施形態に係る進捗管理支援システムで行われる当日の作業指示内容の確認及び登録の処理の例を示すシーケンス図である。 本発明の一実施形態に係る作業者端末に表示される当日の作業の登録時の画面情報の表示例を示す図である。図3Aは、現場選択画面の表示例を示す図である。図3Bは、作業内容選択画面の表示例を示す図である。図3Cは、日付選択用のカレンダーが表示された作業内容選択画面の表示例を示す図である。図3Dは、作業指示内容が表示された作業内容選択画面の表示例を示す図である。 本発明の一実施形態に係る作業開始時及び作業実施結果の登録時に作業者端末に表示される画面情報の表示例を示す図である。 本発明の一実施形態に係る進捗管理支援システムで行われる作業の実施結果を登録する処理の例を示すシーケンス図である。 本発明の一実施形態に係る作業実施結果の登録時に作業者端末に表示される画面情報の表示例を示す図である。 本発明の一実施形態に係る作業実施結果の確認画面の表示例を示す図である。 本発明の一実施形態に係る作業者端末に作業の遅れが通知される様子を示す図である。 本発明の一実施の形態に係る計算機のハードウェア構成例を示すブロック図である。
 以下、本発明を実施するための形態について、添付図面を参照して説明する。本明細書及び図面において、実質的に同一の機能又は構成を有する構成要素については、同一の符号を付することにより重複する説明を省略する。
[一実施形態]
 始めに、進捗管理支援システムの構成例について説明する。
 図1は、本発明の一実施形態に係る進捗管理支援システム1の全体構成例を示すブロック図である。
 進捗管理支援システム1は、ネットワークNを介して互いに接続された進捗管理サーバ10、作業者端末20及び管理者端末30を備える。
<進捗管理サーバの構成例>
 進捗管理サーバ10は、昇降機の据付現場の進捗管理を行う会社の施工管理部門により管理される情報処理装置の一例である。進捗管理サーバ10は、例えば、昇降機の据付工事の進捗状況を管理する。進捗管理サーバ10は、進捗管理データベース40(以下、進捗管理DB40と略記する)、進捗管理部50及び通信部56を備える。
(進捗管理DB)
 始めに、進捗管理DB40の構成例について説明する。
 進捗管理DB40は、工事現場で行われる作業が計画された計画工程と、計画工程に従って工事現場で実施された作業の実施結果が登録された実作業工程とを、工事現場ごとに管理するデータベースである。例えば、進捗管理DB40は、現場Aの現場情報が格納される現場A情報41、現場Bの現場情報が格納される現場B情報41、現場Cの現場情報が格納される現場C情報41を持つ。このように、進捗管理DB40には、現場ごとに現場情報が蓄積され、管理されている。以下の説明では、現場A情報41に注目し、進捗管理部50は、現場Aの現場情報が格納される現場A情報41にアクセスするものとする。同じく、作業者端末20は現場Aの現場作業者により使用され、管理者端末30は、現場Aの施工管理者により使用されるものとする。現場B情報41、現場C情報41については説明を省略する。
 現場A情報41は、工事仕様情報42、据付現場関係者情報43、工程表44、顧客情報45、及び作業実施用帳票46を有する。
 工事仕様情報42は、据付現場(現場Aと呼ぶ)の昇降機の工事仕様を示す情報である。
 据付現場関係者情報43は、据付現場の施工管理者、現場作業者、資材運搬業者、製品設計者、営業担当者、工事仕様決定者など(以下、これらを総称して「現場関係者」とも呼ぶ)の氏名や所属等を作業IDに紐づけて管理する情報である。なお、作業IDにより、据付現場で実施される各作業が識別される。
 工程表44は、据付現場の各作業工程のスケジュールが計画された計画工程表と、現場作業者の作業指示内容に対する実施結果が記録された実作業工程表とを含む情報である。
 顧客情報45は、顧客の担当者や連絡先、住所などを管理する情報である。
 作業実施用帳票46は、作業実施時に活用する作業手順書、危険予知活動記入表、危険予知活動事例集、関連する事故事例、作業上のチェックシートなどの情報を含む帳票である。本実施の形態に係る帳票は、作業者端末20及び管理者端末30に表示される各種の情報である。ここで、危険予知活動は、計画工程に項目として表記されるものではないが、作業者を管理する会社から作業者には、作業開始前に危険予知活動を実施することが課される。危険予知活動は、作業開始前に、作業日当日に行われる作業で発生する可能性のある危険事象を予めリストアップしておき、危険に繋がる障害を排除できたかを確認する活動である。想定される危険事象ごとに危険度が規定されており、危険度が高いほど重大な事故につながる。そこで、危険予知活動では、危険度が高い危険事象を排除できるように、現場作業者に作業開始前の安全点検が促される。現場作業者が危険予知活動を行うことで、仮に作業時に事故が起こったとしても、軽微な事故に留めることが期待される。
(進捗管理部)
 次に、進捗管理部50の構成例について説明する。
 進捗管理部50は、進捗管理DB40から読み出した計画工程と実作業工程との差異が生じた場合に、差異に基づいて作成した進捗情報を、作業の進捗を管理する管理者端末30からの要求に応じて管理者端末30に出力する。この進捗情報として、例えば、計画工程通りに完了していない作業内容の強調表示や、作業が遅れていることを示すメッセージが想定される。進捗管理部50は、昇降機の据付現場の進捗を管理するための進捗情報を生成し、作業者端末20及び管理者端末30からの要求を受けて、これらの端末に進捗情報を出力する。
 進捗管理部50は、作業抽出部51、計画工程登録部52、実作業工程登録部53、帳票作成部54、工程差異抽出部55、及び通信部56を備える。
 通信部56は、ネットワークNを介して作業者端末20又は管理者端末30からの要求(例えば、情報の取得要求)を受信すると、進捗管理部50に要求を渡す。また、通信部56は、進捗管理部50からの応答情報(例えば、画面情報)を受け取ると、要求の送信元である作業者端末20又は管理者端末30に対して、ネットワークNを介して応答情報を返す。ただし、以下の進捗管理部50が有する各機能部の処理の説明では、通信部56の処理を省略し、各機能部が直接、作業者端末20又は管理者端末30と各種の情報及びデータを送受信するものとして説明する。
 作業抽出部51は、作業者端末20から要求される工事現場及び作業日付の作業を計画工程から抽出する。例えば、作業抽出部51は、作業者端末20又は管理者端末30から作業抽出要求を受付けると、進捗管理DB40の該当する現場で実施予定の作業を抽出する。例えば、作業抽出部51は、現場Aの作業抽出要求を受付けた場合、現場A情報41を選択して、工事仕様情報42、据付現場関係者情報43、及び工程表44を参照し、作業者端末20又は管理者端末30が指定した日で実施予定の作業を抽出する。進捗管理DB40には、多数の現場情報が格納され、各現場情報には作業日が計画されている。このため、現場作業者は、作業者端末20に工事現場及び作業日付を入力することで、特定の工事現場及び作業日付で計画された作業を確認することができる。
 また、作業抽出部51は、工事現場及び作業日付で工程表44に登録された実作業工程を、実作業工程の取得を要求する作業者端末20又は管理者端末30に出力する。管理者端末30に表示された実作業工程を含む帳票は、管理者端末30が通信可能な印刷機から用紙に印刷することもできる。このため、施工管理者又は現場作業者は、工事現場の顧客の要望に応じて、工事現場の進捗状況を画面に示したり、用紙に印刷して提出したりすることができる。また、作業抽出部51は、作業に合わせて帳票から抽出した危険予知活動を作業者端末20に出力する。このため、作業者端末20には、作業に合わせて実施される危険予知活動を含む帳票も表示される。
 計画工程登録部52は、管理者端末30から入力された計画工程を進捗管理DB40に登録する。例えば、計画工程登録部52は、管理者端末30に入力された現場Aの計画工程を現場A情報41の工程表44に登録する。この際、計画工程登録部52は、進捗管理DB40の工事仕様情報42及び据付現場関係者情報43を参照し、現場Aで確保できる作業者の人数、スキル等を確認して、施工管理者が作成した計画工程を工程表44に登録することができる。
 実作業工程登録部53は、作業者端末20から受信した実施結果のデータを実作業工程として進捗管理DB40に登録する。計画工程に従って現場作業者が実施した作業の実施結果は、作業者端末20から入力される。例えば、実作業工程登録部53は、作業者端末20から受信した現場での実施結果を実作業工程として現場A情報41の工程表44に登録する。また、実作業工程登録部53は、作業者端末20から入力される、工事現場で実施された危険予知活動の実施結果を工程表44に登録することもできる。
 帳票作成部54は、工程表44に登録された計画工程に合わせて、工事現場の作業者に指示される作業の作業内容を含む帳票(例えば、作業実施用帳票46)を作成し、進捗管理DB40に帳票を登録する。また、帳票作成部54は、計画工程の作業に合わせて実施される危険予知活動を含む帳票を作成し、進捗管理DB40に帳票を登録する。この帳票には、計画工程の作業を現場作業者に指示するための作業指示内容、危険予知活動及び危険予知活動の実施結果、作業の指示内容及び作業の実施結果、作業の作業手順書及び作業手順書の閲覧結果、並びに、昇降機の据付作業における据付精度及び据付結果が確認されたチェックシートへの記載結果のうち、少なくとも一つが含まれる。
 作業者端末20は、作業抽出部51が工程表44から読み出した計画工程と実作業工程のデータを進捗管理部50から受信し、計画工程と実作業工程を表示する。また、作業者端末20は、作業抽出部51が計画工程から抽出した作業に合わせて進捗管理DB40の作業実施用帳票46から取得する帳票が出力される。また、管理者端末30には、計画工程と実作業工程との差異を示す進捗情報が出力される。計画工程と実作業工程との差異を示す進捗情報は、後述する図7に示す強調表示として示される。また、計画工程と実作業工程との差異を示す情報は、後述する図8に示す通知情報として作業者端末20に表示される。
 工程差異抽出部55は、進捗管理DB40から計画工程、及び実作業工程を読み出し、計画工程と実作業工程との差異を抽出して進捗情報を作成する。例えば、工程差異抽出部55は、現場A情報41から工程表44を読み出し、計画工程と実作業工程との差異を抽出する。工程差異抽出部55は、差異が存在する場合、この差異に基づいて作成した進捗情報を管理者端末30に出力する。
 そして、工程差異抽出部55は、作業の遅延を示す進捗情報を、管理者端末30が要求したタイミングで管理者端末30又は作業者端末20に出力する。このため、施工管理者は、管理者端末30を操作して、意図したタイミングで作業の遅延を示す進捗情報を確認できる。なお、作業の遅延が発生した時点で作業者端末20又は管理者端末30に対して、作業の遅延を示す進捗情報が自動的に表示され、現場作業者又は施工管理者に注意喚起がなされてもよい。
 管理者端末30は、進捗管理部50が有する全ての機能部を実行することができる。一方、作業者端末20は、計画工程登録部52の機能を実行できない。
<作業者端末の構成例>
 次に、作業者端末20の構成例について説明する。
 作業者端末20は、昇降機据付工事を行う据付現場の現場作業者により操作される情報処理端末の一例である。作業者端末20として、携帯電話、スマートフォン、タブレット型携帯端末、又はラップトップ型パーソナルコンピューター等の携帯端末が用いられる。現場作業者は、現場で作業者端末20を容易に操作が可能である。そして、現場作業者は、作業者端末20にインストールされたWebブラウザを通じて、当日行う作業を確認したり、作業の実施結果を入力したりする。
 作業者端末20は、各種の情報を表示する表示部21、及び現場作業者が入力する情報を受付ける入力部22を備える。そして、作業者端末20は、一般的な携帯端末等と同様の機能を有する。例えば、作業者端末20は、通話機能や、ネットワークNを介して、進捗管理サーバ10から取得した情報を表示部21に表示する機能を有する。
 また、作業者端末20は、入力部22から作業の実施結果の入力を受付けて、進捗管理サーバ10と各種のデータを送受信する機能を有する。作業者端末20は、進捗管理サーバ10から当日の作業及び作業指示内容のデータを受信する。例えば、現場作業者は、作業者端末20でWebブラウザを起動して、工事現場における工事仕様情報42を閲覧したり、計画工程に規定される作業指示内容を閲覧したり、当日の作業指示内容に応じて実施した作業の実施結果を進捗結果として工程表44に登録したりすることができる。進捗結果とは、作業指示内容に対する結果が入力されたものでもよいし、当該日における作業指示内容に紐づいた危険予知活動及びその実施結果が入力されたものでもよい。また、作業現場における昇降機の据付作業の据付精度や作業実施結果を確認したチェックシートの記載結果が入力されたものでもよい。
<管理者端末の構成例>
 次に、管理者端末30の構成例について説明する。
 管理者端末30は、その据付現場の施工管理者により操作される端末である。管理者端末30として、携帯電話、スマートフォン、タブレット型携帯端末、又はラップトップ型パーソナルコンピューター等の携帯端末が用いられる。施工管理者は、管理者端末30にインストールされたWebブラウザを通じて、現場ごとに当日行われる作業を確認したり、作業の進捗状況を確認したりする。
 管理者端末30は、一般的なデスクトップ型パーソナルコンピューターや携帯端末等と同様の機能、すなわち通話やネットワークを介しての情報の表示や入力、送受信等の各処理が実施できる機能を備える。進捗管理サーバ10に登録された計画工程及び実作業工程を含む工程表44のデータは、管理者端末30からのアクセスに応じて、進捗管理サーバ10から送信される。
 施工管理者は、管理者端末30を操作して、施工管理者が担当する据付現場の計画工程表を作成し、進捗管理サーバ10へ登録する。そして、施工管理者は、管理者端末30は、その据付現場における進捗状況等の管理を行うことができる。
 管理者端末30は、各種の情報を表示する表示部31、及び施工管理者が入力する情報を受付ける入力部32を備える。
 管理者は、管理者端末30の入力部32を通じて作成した計画工程を進捗管理サーバ10に登録する。また、管理者は、管理者端末30の表示部31に表示された計画工程及び実作業工程の差異を確認することで実作業の進捗を管理することができる。
<現場作業者が当日の作業指示内容を確認し、登録する処理>
 次に、進捗管理支援システム1の動作の例について説明する。
 図2は、進捗管理支援システム1で行われる当日の作業指示内容の確認及び登録の処理の例を示すシーケンス図である。ここでは、作業者が作業者端末20を操作し、進捗管理サーバ10に登録されている計画工程表から当日の作業指示内容を確認し、進捗管理サーバ10に確認結果を登録する流れについて説明する。
 始めに、作業者は、当日の作業開始前に作業者端末20を通じて、当該現場の現場名及び作業日付を選択する。作業者端末20は、現場作業者が選択した現場名及び作業日付のデータを進捗管理サーバ10へ送信する(S1)。
 進捗管理サーバ10の作業抽出部51は、作業者端末20から当該現場の現場名及び作業日付のデータを受信すると、当該現場の工程表44に含まれる計画工程から日付情報に合わせて、当日の作業を抽出する(S2)。
 次に、進捗管理部50は、作業抽出部51が抽出した当日の作業を、作業指示内容のデータとして作業者端末20へ送信する。(S3)
 作業者端末20の表示部21は、進捗管理サーバ10から作業指示内容のデータを受信すると、画面に作業指示内容を表示する(S4)。例えば、当日の午前と午後で計画された作業が異なる場合、午前と午後のそれぞれに計画された作業が当日の作業内容として作業者端末20に表示される。作業者は、画面上に表示された作業指示内容を確認すると、入力部22を通じて進捗管理サーバ10へ作業指示内容を確認した旨を入力する。そして、作業者端末20は、作業者による作業指示内容の確認結果のデータを進捗管理サーバ10に送信し(S5)、本処理を終了する。
 進捗管理サーバ10の計画工程登録部52は、作業者端末20から受信した作業指示内容の確認結果のデータに基づいて、工程表44に当日の作業内容の確認結果を登録し(S6)、本処理を終了する。
 このように現場関係者(作業者及び施工管理者を含む)が作業者端末20又は管理者端末30を介して、工程表44の取得要求を進捗管理サーバ10へ要求することで、現場関係者が工程表44に登録された計画工程の作業内容を随時確認することが可能である。
 また、作業者端末20が作業指示内容を表示する際に、例えば、当日の作業指示内容に合わせた作業実施用帳票46を表示することもできる。作業実施用帳票46には、作業指示内容に合わせた各種の情報が含まれるので、現場作業者は、当日の作業に必要な情報を過不足なく確認できる。
<作業登録時の画面の表示例>
 次に、作業者端末20に表示される当日の作業の登録時の画面情報について説明する。
 図3は、作業者端末20に表示される当日の作業の登録時の画面情報の表示例を示す図である。
 図3Aは、現場選択画面W1の表示例を示す図である。
 現場選択画面W1には、複数の現場の現場名が一覧表示される。現場作業者は、作業者端末20の表示部21に表示された現場選択画面W1を通じて、当日の作業が行われる現場に該当する現場名を選択する。現場選択画面W1で現場名が選択された後、表示部21には、図3Bに示す作業内容選択画面W2が表示される。
 図3Bは、作業内容選択画面W2の表示例を示す図である。
 現場作業者は、作業内容選択画面W2から作業日時を入力する。日付選択画面の上部には、本日ボタンが表示される。現場作業者が本日ボタンを押すと、現場作業者が作業者端末20を操作している本日の日付が日付入力欄に表示される。
 図3Cは、日付選択用のカレンダーが表示された作業内容選択画面W2の表示例を示す図である。
 現場作業者が日付入力欄の右側にあるカレンダーアイコンを押すと、日付選択画面に重ねて日付選択用のカレンダーが表示される。現場作業者は、本日以外の日で計画工程を確認したい場合、日付選択用のカレンダーから任意の日付を選択できる。選択された日付は、日付入力欄に表示される。
 図3Dは、作業指示内容が表示された作業内容選択画面W2の表示例を示す図である。
 図3B又は図3Cに示したように作業内容選択画面W2から日付が入力された後、現場名と日付の情報が進捗管理サーバ10に送信される。そして、作業者端末20は、進捗管理サーバ10から作業指示内容のデータを受信すると、作業内容選択画面W2の「午前中の作業予定を選択」欄及び「午後の作業予定を選択」欄のうち、少なくとも一つの欄に該当する作業指示内容が表示される。
 図3Dでは、「午前中の作業予定を選択」欄に、作業指示内容として「足場組立」及び「塔内芯出し」が表示された例が示される。なお、「午後の作業予定を選択」欄が空欄であることは、「午前中の作業予定を選択」欄に示される作業と同じ作業が午後に行われることを表す。午後の作業が無い場合、「午後の作業予定を選択」欄には、空欄又は「作業無し」のように表示される。
 現場作業者は、作業内容選択画面W2に表示された作業指示内容を確認すると、作業内容選択画面W2の下部にある「次へ」ボタンを選択する。作業者端末20は、進捗管理サーバ10に確認結果のデータを送信する。進捗管理サーバ10の進捗管理部50は、作業者端末20から確認結果のデータを受信すると、作業抽出部51が抽出した作業を、当日の作業として工程表44に登録する。
 図4は、作業開始時及び作業実施結果の登録時に作業者端末20に表示される画面情報の表示例を示す図である。
 作業開始時及び作業実施結果の登録時には、作業者端末20の表示部21に危険予知活動確認画面W3が表示される。現場作業者は、作業開始時に危険予知活動確認画面W3に表示される危険予知活動を当日の作業に活用できる。危険予知活動は、図中で「KY」と表示される。
 危険予知活動確認画面W3には、当日の作業で必要な作業人数、作業内容の項目が表示される。
 作業人数入力欄には、プルダウンリストが表示され、現場作業者は、プルダウンリストから選択した人数を作業人数として登録可能である。
 作業内容表示欄には、「着工・安全対策」と「製品搬入」の作業指示内容ごとに関連事故事例と関連作業手順へのリンクが表示される。現場作業者は、リンクをクリックすることで、作業指示内容ごとに一又は複数の関連事故事例と関連作業手順を確認することができる。
 現場作業者が、例えば、「作業内容」欄の関連事故事例項目から丸数字で表されるリンクボタンを押すと、関連事故事例の情報が作業者端末20に表示される。また、現場作業者が、例えば、「作業内容」欄の関連作業手順項目から丸数字で表されるリンクボタンを押すと、関連作業手順の情報が作業者端末20に表示される。このように現場作業者がリンクボタンを押して表示される情報を「作業実施用帳票」と呼ぶ。作業実施用帳票は、作業者が現場で危険予知活動を実施するために用いられる。現場作業者は、作業者端末20を操作して進捗管理サーバ10へ当日の作業を登録する際に、表示部21に表示された作業実施用帳票を通じて、作業内容に合わせた作業手順書や関連する事故事例などを確認することができる。
 危険予知活動は作業現場における安全対策の一環として行われる。上述したように危険予知活動は、事故やケガにつながる危険のポイントを、当日の作業及び現場環境から洗い出して、作業行う人間の全員で認識することで、作業途中のけがを未然に防止する取り組みである。このため、危険予知活動専用の帳票が設けられるわけではない。危険予知活動に使用される情報として、例えば、昇降機の組立作業を記した手順、類似の作業で過去に発生した労働災害の事例紹介など、多岐に渡る資料及び帳票が想定される。そして、現場作業者は、随時、これらの資料及び帳票を確認することができる。
 作業内容表示欄には、各作業に対して、現場作業者が「作業振り返り」の実行有無を入力するためのチェックボックスが表示される。「作業振り返り」は、現場作業者が危険予知活動の実施有無を入力するための項目である。作業振り返りの詳細については、図6を参照して後述する。
 また、作業実施用帳票は、「KYシート」と呼ばれる紙媒体でも用いられる。この場合、現場作業者がKYシートに必要事項、チェック項目に危険予知活動の実施結果を記入して、作業者端末20に付属するカメラでKYシートを撮影した後、KYシートの写真を進捗管理サーバ10にアップロードすることもできる。アップロードされた写真は、実作業工程の一部として工程表44に登録される。
<現場作業者が作業の実施結果を登録する処理>
 次に、進捗管理支援システム1の動作の例について説明する。
 図5は、進捗管理支援システム1で行われる作業の実施結果を登録する処理の例を示すシーケンス図である。ここでは、現場作業者が作業者端末20を操作し、進捗管理サーバ10に登録した当日の作業に対して、実施結果の登録を行う。
 始めに、作業者端末20は、現場作業者が当日の作業実施結果を入力する旨のデータを進捗管理サーバ10へ送信する(S11)。この処理は、現場作業者が、作業前に進捗管理サーバ10に登録した作業指示内容を、当日の作業後に作業者端末20へ表示させるために行われる。
 進捗管理サーバ10の作業抽出部51は、作業者端末20から当日の作業実施結果を入力する旨のデータを受信すると、現場A情報41の工程表44から、作業開始前に図2のステップS6で登録された当日の作業指示内容を抽出する(S12)。そして、進捗管理部50は、現場A情報41から抽出した当日の作業指示内容のデータを作業者端末20へ送信する(S13)。
 作業者端末20の表示部21は、進捗管理サーバ10から受信した作業指示内容のデータに基づいて、当日の作業前に登録された作業指示内容を画面上に表示する(S14)。現場作業者は、画面に表示された作業指示内容が、作業開始前に登録した作業指示内容であることを確認する。そして、現場作業者は、作業指示の実施結果を、入力部22を通じて作業者端末20に送信する。作業者端末20は、作業指示の実施結果のデータを進捗管理サーバ10へ送信する(S15)。
 進捗管理サーバ10の進捗管理部50が実施結果を受信すると、実作業工程登録部53が実施結果を実作業工程として工程表44に登録する(S16)。そして、工程差異抽出部55は、工程表44から計画工程と実作業工程とに基づいて、工程の差異を抽出する(S17)。
 次に、工程差異抽出部55は、計画工程と実作業工程とに差異があるか否かを判定する(S18)。計画工程と実作業工程とに差異がない場合(S18のNO)、進捗管理部50は、作業者端末20に差異がない旨を送信し(S21)、本処理を終了する。
 一方、計画工程と実作業工程とに差異がある場合(S18のYES)、進捗管理部50は、この差異に基づいて、作業者端末20に作業が遅延している旨を送信する(S19)。作業者端末20の表示部21は、進捗管理サーバ10から受信した、作業が遅延している旨を表示し(S20)、本処理を終了する。現場作業者は、作業が遅延している旨を確認すると、作業遅延の原因を把握し、作業の進捗を早める等の対処を行うことができる。
 このように、作業指示の実施結果と実作業工程表についても、作業者端末20又は管理者端末30を介して現場関係者が、進捗管理サーバ10へ要求することで、随時確認をすることが可能である。
 図6は、作業実施結果の登録時に作業者端末20に表示される画面情報の表示例を示す図である。ここでは、図4と同様の危険予知活動確認画面W3の表示例が示される。現場作業者は、作業者端末20に表示される当日の作業に対する実施結果の登録時に、危険予知活動を当日の作業実施結果として登録する。
 現場作業者が危険予知活動を実施し、当日の作業が完了して、その日に現場から退館する直前に、現場作業者自身が決めた「危険予知活動」に対する振り返りの実施有無をチェックする。現場作業者が行う振り返りをチェックすることは、現場で実施した作業の実施結果を登録することを兼ねる。そこで、現場作業者が「作業振り返り」のチェックボックスにチェックを入力することを「作業登録」とも呼ぶ。
 そこで、現場作業者は、当日の作業実施後、危険予知活動確認画面W3を作業者端末20の画面上へ表示させ、危険予知活動を実施したかを確認するための「作業振り返り」を行う。現場作業者が危険予知活動を完了したのであれば、現場作業者は、図6に示された登録画面のチェックボックスにチェックを入力する。一方、危険予知活動が不十分であれば、現場作業者は、危険予知活動をできなかった理由等を登録画面に入力する。
 現場作業者が「作業振り返り」にチェックを入力した後、「次へ」ボタンを選択することにより、作業者端末20での作業実施結果の登録が終了する。作業者端末20は、危険予知活動の実施結果のデータを進捗管理サーバ10に送信する。図1に示した進捗管理サーバ10の実作業工程登録部53は、作業者端末20から受信したデータに基づいて、作業日毎に危険予知活動の作業実施結果を工程表44に登録する。工程表44に作業実施結果が登録されることで、作業実施日における実作業工程の登録が終了する。
 図7は、作業実施結果の確認画面の表示例を示す図である。
 進捗管理DB40に登録された作業内容と作業の完了日とを含む作業実施結果は、現場関係者が確認することができる。現場関係者は、作業者端末20又は管理者端末30を操作して、作業内容と完了日を入力すると、作業者端末20又は管理者端末30が進捗管理サーバ10に作業実施結果の取得を要求する。進捗管理サーバ10が進捗管理DB40から取得した作業実施結果のデータが、要求元の作業者端末20又は管理者端末30に送信される。そして、作業者端末20又は管理者端末30は、進捗管理DB40から受信したデータに基づいて、作業実施結果の確認画面に作業実施結果を表示する。
 作業実施結果の確認画面には、計画工程で登録された作業内容と、作業の完了有無を示すチェックボックスと、作業の完了日とが表示される。作業の完了有無を示すチェックボックスにチェックが入力され、作業の完了日に日付が入力された作業内容は、作業が実施されたことを表す。一方、作業の完了日に「作業遅れ」と表示された作業内容は、作業が計画工程通りの作業日に完了しなかったことを表す。作業が遅れたことは、例えば、遅れた作業内容が、他の作業内容とは異なる色(例えば、赤字)又は字体(例えば、太字)で強調表示されたり、遅れた作業内容の欄が異なる色(例えば、赤色)で表示されたりして表される。このように遅れた作業内容が強調表示されると、現場関係者が作業の遅れを気づきやすくなる。作業が遅れた場合、施工管理者は、作業の発注業者と相談して、納期や計画工程を変更する対処等を早い段階で行うことができる。
 図8は、作業者端末20に作業の遅れが通知される様子を示す図である。
 計画工程通りに作業が完了しなかった場合、作業者端末20の危険予知活動確認画面W3には、作業の遅れが通知される。作業者は、危険予知活動確認画面W3に重ねて表示される「作業が遅れています」等のメッセージを見て、計画工程通りに作業が完了しなかったことを認識できる。
<計算機のハードウェア構成例>
 ここで、進捗管理支援システム1の各装置を構成する計算機60のハードウェア構成例について説明する。
 図9は、計算機60のハードウェア構成例を示すブロック図である。計算機60は、本実施の形態に係る進捗管理サーバ10、作業者端末20又は管理者端末30として動作可能なコンピューターとして用いられるハードウェアの一例である。本実施の形態に係る進捗管理支援システム1は、サーバ及び端末を構成する各計算機60(コンピューター)がプログラムを実行することにより、図1に示した各機能ブロックが連携して行う、施工現場の進捗管理方法を実現する。
 計算機60は、バス64にそれぞれ接続されたCPU(Central Processing Unit)61、ROM(Read Only Memory)62、及びRAM(Random Access Memory)63を備える。さらに、計算機60は、表示装置65、入力装置66、不揮発性ストレージ67及びネットワークインターフェイス68を備える。
 CPU61は、本実施の形態に係る各機能を実現するソフトウェアのプログラムコードをROM62から読み出してRAM63にロードし、実行する。RAM63には、CPU61の演算処理の途中で発生した変数やパラメーター等が一時的に書き込まれ、これらの変数やパラメーター等がCPU61によって適宜読み出される。ただし、CPU61に代えてMPU(Micro Processing Unit)を用いてもよい。進捗管理サーバ10の進捗管理部50の機能は、CPU61により実現される。なお、図1では不図示としたが、作業者端末20及び管理者端末30もCPU61、ROM62及びRAM63を有しており、各端末の動作は、CPU61等により制御される。
 表示装置65は、例えば、液晶ディスプレイモニターであり、計算機60で行われる処理の結果等を作業関係者に表示する。入力装置66には、例えば、キーボード、マウス等が用いられ、作業関係者が所定の操作入力、指示を行うことが可能である。なお、進捗管理サーバ10には、表示装置65、入力装置66が設けられなくてもよい。
 不揮発性ストレージ67としては、例えば、HDD(Hard Disk Drive)、SSD(Solid State Drive)、フレキシブルディスク、光ディスク、光磁気ディスク、CD-ROM、CD-R、磁気テープ又は不揮発性のメモリ等が用いられる。この不揮発性ストレージ67には、OS(Operating System)、各種のパラメーターの他に、計算機60を機能させるためのプログラムが記録されている。ROM62及び不揮発性ストレージ67は、CPU61が動作するために必要なプログラムやデータ等を記録しており、計算機60によって実行されるプログラムを格納したコンピューター読取可能な非一過性の記憶媒体の一例として用いられる。図1に示した進捗管理DB40は、進捗管理サーバ10に設けられた不揮発性ストレージ67に構成される。
 ネットワークインターフェイス68には、例えば、NIC(Network Interface Card)等が用いられ、NICの端子に接続されたLAN(Local Area Network)、専用線等を介して各種のデータを装置間で送受信することが可能である。例えば、進捗管理サーバ10の通信部56の機能は、ネットワークインターフェイス68により実現される。また、作業者端末20及び管理者端末30が有するネットワークインターフェイス68によりネットワークNに接続可能な通信部の機能が実現される。
 以上説明した一実施の形態に係る進捗管理支援システム1では、現場作業者が作業者端末20を操作して、日々の工事現場において指定した日の作業を確認し、作業の実施結果を入力する。進捗管理サーバ10では、作業者端末20に入力された実施結果を実作業工程として工程表44に登録する。現場ごとの計画工程及び実作業工程の差異が生じた場合、管理者端末30には、施工管理者が要求するタイミングで、作業の遅れを示す進捗情報が表示される。このため、施工管理者は、計画工程に対する実作業工程の遅れをタイムリーに把握できる。そして、施工管理者は、遅れが生じた作業に対する、現場作業者への実施の促進、スケジュールの再検討等を早めに対応することができる。
 また、施工管理者は、工事現場にいる現場作業者に直接、工事の進捗状況を問い合わせなくても、施工管理者が要求する任意のタイミングで現場の計画工程及び実作業工程を確認できる。このため、施工管理者が現場作業者に問い合わせることによる、現場作業の一時中断を無くし、施工管理者に由来する作業遅延の影響を無くすことができる。
 また、施工管理者は、自身が担当する据付現場における作業の進捗状況を、施工管理者が所望するタイミングで把握できる。このため、施工管理者は、複数の据付現場を担当していても、複数の据付現場の現在の進捗状況を、時間をかけずに確認することができる。
 また、現場作業者は、当日の作業開始前に、作業者端末20を通じて当日計画されている作業を確認できる。また、当日の作業終了後には、作業現場で現場作業者が作業者端末20を通じて作業の完了を入力することができる。このため、現場作業者は、事務所等に戻って作業の完了を入力する必要がなく、作業現場から事務所等への移動時間を削減できる。また、作業の遅れが生じた場合には、施工管理者と同様に現場作業者も作業者端末20に表示される進捗情報に基づいて、作業の遅れを認識することができる。
 また、現場作業者は、当日の作業開始前に、作業者端末20を通じて危険予知活動を確認できる。このため、現場作業者は、作業に取り掛かる前に、危険予知活動に基づいて、事故の発生するおそれのある障害を取り除けるので、安全な作業現場を確保できる。
 また、現場作業者は、危険予知活動の詳細を作業者端末20に表示して把握することができ。また、危険予知活動の実施有無は、現場作業者が作業者端末20を通じて簡単な操作で入力することができる。そして、現場作業者は、危険予知活動が未実施であった場合、未実施とした理由等を作業者端末20から入力することで、作業関係者が危険予知活動の内容を精査することができる。
[変形例]
 なお、現場作業者が未完の作業を完了したと誤って登録した場合であっても、当日中であれば修正できるようにしてよい。また、現場作業者とは異なる検査員が現場で検査することにより、作業完了の誤登録を認識することも可能である。このため、施工管理者は、工程表44に基づいて作業の進捗状況を正しく管理することができる。
 上述した実施の形態では、現場作業者が、当日実施する作業の作業指示内容及びその作業の実施結果と、危険予知活動及びその実施結果を、進捗管理DB40に入力することについて説明した。この際、現場作業者は、作業手順書の内容及びその作業手順書の閲覧結果を、進捗管理DB40に登録してもよいし、現場作業者が現場据付作業における据付精度や結果を確認したチェックシートの記載結果を、進捗管理DB40に登録してもよい。
 また、進捗管理部50は、管理者端末30からの要求が無くても、計画工程と実作業工程との差異が生じた時点で、実作業の遅れを示す進捗情報を管理者端末30に出力してもよい。管理者端末30を操作する施工管理者は、通知された進捗情報に基づいて、実作業の遅れが生じた現場を直ちに把握することができる。
 なお、本発明は上述した実施形態に限られるものではなく、請求の範囲に記載した本発明の要旨を逸脱しない限りその他種々の応用例、変形例を取り得ることは勿論である。
 例えば、上述した実施形態は本発明を分かりやすく説明するためにシステムの構成を詳細かつ具体的に説明したものであり、必ずしも説明した全ての構成を備えるものに限定されない。また、本実施形態の構成の一部について、他の構成の追加、削除、置換をすることも可能である。
 また、制御線や情報線は説明上必要と考えられるものを示しており、製品上必ずしも全ての制御線や情報線を示しているとは限らない。実際には殆ど全ての構成が相互に接続されていると考えてもよい。
 1…進捗管理支援システム、10…進捗管理サーバ、20…作業者端末、30…管理者端末、40…進捗管理DB、41…現場A情報、50…進捗管理部、51…作業抽出部、52…計画工程登録部、53…実作業工程登録部、54…帳票作成部、55…工程差異抽出部、56…通信部

Claims (10)

  1.  工事現場で行われる作業が計画された計画工程と、前記計画工程に従って前記工事現場で実施された作業の実施結果が登録された実作業工程とを、前記工事現場ごとに管理する進捗管理データベースと、
     前記進捗管理データベースから読み出した前記計画工程と前記実作業工程との差異が生じた場合に、前記差異に基づいて作成した進捗情報を、前記作業の進捗を管理する管理者端末からの要求に応じて前記管理者端末に出力する進捗管理部と、を備える
     進捗管理サーバ。
  2.  前記進捗管理部は、
     前記管理者端末から入力された前記計画工程を前記進捗管理データベースに登録する計画工程登録部と、
     前記計画工程に従って実施された前記作業の前記実施結果が作業者端末から入力されると、前記実施結果を前記実作業工程として前記進捗管理データベースに登録する実作業工程登録部と、
     前記進捗管理データベースから前記計画工程、及び前記実作業工程を読み出し、前記計画工程と前記実作業工程との差異を抽出して前記進捗情報を作成する工程差異抽出部と、を有する
     請求項1に記載の進捗管理サーバ。
  3.  前記工程差異抽出部は、前記作業の遅延を示す前記進捗情報を、前記管理者端末が要求したタイミングで前記管理者端末又は前記作業者端末に出力する
     請求項2に記載の進捗管理サーバ。
  4.  前記進捗管理部は、
     前記作業者端末から要求される前記工事現場及び作業日付の作業を前記計画工程から抽出する作業抽出部を備える
     請求項3に記載の進捗管理サーバ。
  5.  前記進捗管理部は、
     前記計画工程に合わせて、前記工事現場の作業者に指示される作業の作業内容を含む帳票を作成し、前記進捗管理データベースに前記帳票を登録する帳票作成部を有し、
     前記作業抽出部は、前記計画工程から抽出した前記作業に合わせて前記進捗管理データベースから取得する前記帳票を前記作業者端末に出力する
     請求項4に記載の進捗管理サーバ。
  6.  前記帳票作成部は、前記作業に合わせて実施される危険予知活動を含む前記帳票を作成し、前記進捗管理データベースに前記帳票を登録する
     請求項5に記載の進捗管理サーバ。
  7.  前記作業抽出部は、前記作業に合わせて前記帳票から抽出した前記危険予知活動を前記作業者端末に出力し、
     前記実作業工程登録部は、前記作業者端末から入力される、前記工事現場で実施された前記危険予知活動の実施結果を前記進捗管理データベースに登録する
     請求項6に記載の進捗管理サーバ。
  8.  前記作業抽出部は、前記工事現場及び作業日付で前記進捗管理データベースに登録された前記実作業工程を前記作業者端末又は前記管理者端末に出力する
     請求項5に記載の進捗管理サーバ。
  9.  前記帳票には、前記計画工程の作業を指示するための作業指示内容、前記危険予知活動及び前記危険予知活動の実施結果、前記作業の指示内容及び前記作業の実施結果、前記作業の作業手順書及び前記作業手順書の閲覧結果、並びに、昇降機の据付作業における据付精度及び据付結果が確認されたチェックシートへの記載結果のうち、少なくとも一つが含まれ、
     前記実作業工程登録部は、前記作業者が前記帳票に基づいて作業した前記実施結果を前記実作業工程として登録する
     請求項6に記載の進捗管理サーバ。
  10.  工事現場で行われる作業が計画された計画工程に従って前記工事現場で実施された作業の実施結果が入力される作業者端末と、
     前記作業の進捗を管理する管理者端末と、
     前記計画工程、及び前記計画工程に従って前記工事現場で実施された前記作業の実施結果が管理される進捗管理サーバと、を備え、
     前記進捗管理サーバは、
     前記計画工程と、前記実施結果が登録された実作業工程とを、前記工事現場ごとに管理する進捗管理データベースと、
     前記進捗管理データベースから読み出した前記計画工程と前記実作業工程との差異が生じた場合に、前記差異に基づいて作成した進捗情報を、前記工事現場の進捗を管理する管理者端末からの要求に応じて前記管理者端末に出力する進捗管理部と、を備える
     進捗管理システム。
PCT/JP2021/019905 2021-05-26 2021-05-26 進捗管理サーバ及び進捗管理システム WO2022249309A1 (ja)

Priority Applications (2)

Application Number Priority Date Filing Date Title
PCT/JP2021/019905 WO2022249309A1 (ja) 2021-05-26 2021-05-26 進捗管理サーバ及び進捗管理システム
JP2023523784A JPWO2022249309A1 (ja) 2021-05-26 2021-05-26

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2021/019905 WO2022249309A1 (ja) 2021-05-26 2021-05-26 進捗管理サーバ及び進捗管理システム

Publications (1)

Publication Number Publication Date
WO2022249309A1 true WO2022249309A1 (ja) 2022-12-01

Family

ID=84228597

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2021/019905 WO2022249309A1 (ja) 2021-05-26 2021-05-26 進捗管理サーバ及び進捗管理システム

Country Status (2)

Country Link
JP (1) JPWO2022249309A1 (ja)
WO (1) WO2022249309A1 (ja)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002007657A (ja) * 2000-06-26 2002-01-11 Fujitsu Systems Construction Ltd プロジェクト管理装置及び記録媒体
JP2003050839A (ja) * 2001-06-01 2003-02-21 Ishin Co Ltd 建築用工程管理システム
JP2005272067A (ja) * 2004-03-24 2005-10-06 Hitachi Building Systems Co Ltd 昇降機の保全作業実績管理装置
JP2009193406A (ja) * 2008-02-15 2009-08-27 Tobishima Corp 工事管理システム
JP2017182546A (ja) * 2016-03-31 2017-10-05 積水ハウス株式会社 帳票作成システム、帳票作成方法及び帳票作成プログラム
JP2018181085A (ja) * 2017-04-18 2018-11-15 株式会社日立プラントコンストラクション 建設現場の管理情報共有システム

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002007657A (ja) * 2000-06-26 2002-01-11 Fujitsu Systems Construction Ltd プロジェクト管理装置及び記録媒体
JP2003050839A (ja) * 2001-06-01 2003-02-21 Ishin Co Ltd 建築用工程管理システム
JP2005272067A (ja) * 2004-03-24 2005-10-06 Hitachi Building Systems Co Ltd 昇降機の保全作業実績管理装置
JP2009193406A (ja) * 2008-02-15 2009-08-27 Tobishima Corp 工事管理システム
JP2017182546A (ja) * 2016-03-31 2017-10-05 積水ハウス株式会社 帳票作成システム、帳票作成方法及び帳票作成プログラム
JP2018181085A (ja) * 2017-04-18 2018-11-15 株式会社日立プラントコンストラクション 建設現場の管理情報共有システム

Also Published As

Publication number Publication date
JPWO2022249309A1 (ja) 2022-12-01

Similar Documents

Publication Publication Date Title
US20200193049A1 (en) Lockout-tagout and safety compliance systems and methods
JP2004164614A (ja) 作業担当者支援方法及び作業担当者支援プログラム
JP2021101376A (ja) 土木・建設現場における工事作業に対する危険予知活動の分析支援システム及び連絡配布支援システム
KR102391197B1 (ko) 디지털 안전 작업관리 시스템 및 방법
JPH09259181A (ja) ワークフロー管理システム
KR101620605B1 (ko) 스마트 안전 진단 보고 장치 및 그 방법
JP2006227669A (ja) 業務指示管理システムおよびプログラム
JP2007094494A (ja) 生産計画支援システム、生産計画支援方法及びプログラム
WO2022249309A1 (ja) 進捗管理サーバ及び進捗管理システム
JP2008146107A (ja) 施工検査による品質管理システム、品質管理プログラム及びその記録媒体。
WO2002007026A1 (fr) Systeme de gestion de flux de travaux
JP5334013B2 (ja) 現地エレベータの物件データ確認システム
JP4262655B2 (ja) ワークフローシステム及びワークフローシステムの管理方法
JP2019074993A (ja) 安全施工サイクル支援システム
JP6559214B2 (ja) スケジュール管理システムおよびスケジュール管理プログラム
JP6940362B2 (ja) 組立手順表示システム
JP6570604B2 (ja) スケジュール管理システムおよびスケジュール管理プログラム
JP2004240772A (ja) 刷版進行装置
JP2002366718A (ja) 作業情報管理方法および作業情報管理システム
JP2010218324A (ja) 業務割振り装置、業務割振り方法及び業務割振りプログラム
JP2003288375A (ja) 施設データベースシステム
JP2020173541A (ja) 労働契約管理装置、労働条件通知書作成方法及び労働条件通知書作成プログラム
JP2023183217A (ja) 現場作業支援方法および現場作業支援システム
JP7082435B2 (ja) 情報入力システム
JP2004070516A (ja) ワークフロー管理システム

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21942963

Country of ref document: EP

Kind code of ref document: A1

ENP Entry into the national phase

Ref document number: 2023523784

Country of ref document: JP

Kind code of ref document: A

NENP Non-entry into the national phase

Ref country code: DE