WO2022085061A1 - 工事用エレベーター及び工事用エレベーターの主ロープの延長方法 - Google Patents

工事用エレベーター及び工事用エレベーターの主ロープの延長方法 Download PDF

Info

Publication number
WO2022085061A1
WO2022085061A1 PCT/JP2020/039315 JP2020039315W WO2022085061A1 WO 2022085061 A1 WO2022085061 A1 WO 2022085061A1 JP 2020039315 W JP2020039315 W JP 2020039315W WO 2022085061 A1 WO2022085061 A1 WO 2022085061A1
Authority
WO
WIPO (PCT)
Prior art keywords
rope
machine room
main rope
gripping device
pulley
Prior art date
Application number
PCT/JP2020/039315
Other languages
English (en)
French (fr)
Inventor
悠人 樋野
遼 小松
章智 五十嵐
尚文 尾方
Original Assignee
株式会社日立製作所
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社日立製作所 filed Critical 株式会社日立製作所
Priority to PCT/JP2020/039315 priority Critical patent/WO2022085061A1/ja
Priority to EP20958614.8A priority patent/EP4234471A1/en
Priority to JP2022556845A priority patent/JP7455221B2/ja
Priority to CN202080105805.6A priority patent/CN116323461A/zh
Publication of WO2022085061A1 publication Critical patent/WO2022085061A1/ja

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation

Definitions

  • the present invention relates to a construction elevator and a method of extending the main rope of the construction elevator.
  • construction elevators have been proposed as elevators for transporting materials and people installed in building structures under construction.
  • This construction elevator expands the range in which the car can be raised and lowered, that is, the range in which it can be operated, by raising the machine room unit having a hoisting machine, control panel, etc., according to the progress of construction of the building structure. I'm letting you.
  • the main rope connected to the car is extended.
  • Patent Document 1 As a conventional elevator for construction work, for example, there is one described in Patent Document 1.
  • the main rope is pulled out by a gripping device in order to prevent the main rope from being pulled out from the main rope reel unintentionally by its own weight. It is gripped with a predetermined force. Then, by raising the machine room unit, the main rope slides on the gripping device, and the main rope is extended.
  • the purpose of this purpose is to provide a construction elevator and a method of extending the main rope of a construction elevator, which can extend the main rope without damaging the main rope in consideration of the above problems.
  • the construction elevator is provided with a rope reel, an elevating body, a pulley, a first rope gripping device, and a second rope gripping device.
  • the main rope is wound around the rope reel.
  • the main rope drawn from the rope reel is wound around the elevating body, and the elevating body moves up and down the hoistway of the building structure.
  • the pulley is arranged between the rope reel and the elevating body on the main rope, and the main rope drawn from the rope reel is wound around the pulley.
  • the first rope gripping device grips the main rope on the rope reel side with respect to the pulley so as to be openable.
  • the second rope gripping device grips the main rope on the elevating body side so as to be openable with respect to the pulley. Then, the pulley is movably supported along the elevating direction of the elevating body.
  • the method of extending the main rope of the construction elevator having the above-mentioned configuration includes the steps shown in the following (1) to (4).
  • the installation work of the machine room unit can be easily performed without damaging the main rope.
  • FIG. 1 is a schematic configuration diagram showing a construction elevator of this example.
  • the elevator shown in Fig. 1 is a construction elevator installed in a building structure under construction and used to transport materials and people.
  • the construction elevator 1 includes a support member 2 arranged at the upper part of a hoistway 100 of a building structure, a machine room unit 3, and a lifting machine 6 for lifting the machine room unit 3. I have.
  • the construction elevator 1 includes a hoisting machine 9, a main rope 10, a car 11 for carrying people and materials, and a balance weight 12.
  • the car 11 and the counterweight 12 show an example of an elevating body.
  • the positional relationship between the car 11 and the balance weight 12 may be reversed. That is, in FIG. 1, the balance weight may correspond to the reference numeral 11 and the car may correspond to the reference numeral 12.
  • the direction in which the car 11 and the balance weight 12, which are elevating bodies, move up and down is referred to as the vertical direction.
  • a car-side pulley 11a is provided on the upper part of the car 11. Further, a weight side pulley 12a is provided on the upper portion of the balance weight 12.
  • the main rope 10 is wound around the car-side pulley 11a and the weight-side pulley 12a. Further, the main rope 10 is wound around a sheave of the hoisting machine 9 installed in the machine room unit 3 described later.
  • the main rope 10 is wound around a rope reel 15 provided in the machine room unit 3 described later, and is pulled out from the rope reel 15.
  • the end of the main rope 10 on the opposite side of the rope reel 15 is fixed to the rope fixing portion 14 in the machine room unit 3.
  • the main rope 10 is wound from the rope reel 15 in the order of the weight side pulley 12a, the hoisting machine 9, and the car side pulley 11a via the pulley 19 described later, and the end portions thereof are fixed to the rope fixing portion 14.
  • the hoisting machine 9 is driven, the car 11 and the counterweight 12 move up and down in the hoistway 100.
  • the support member 2 is installed in the beam 101a provided at the uppermost portion of the hoistway 100 or in the recess provided on the wall surface of the hoistway 100.
  • the support member 2 is provided with a lifting machine 6.
  • the machine room unit 3 is arranged below the support member 2 in the vertical direction.
  • the machine room unit 3 is suspended from the support member 2 via the lifting machine 6.
  • the machine room unit 3 is supported by the lifting machine 6 so as to be liftable (movable).
  • the lifting machine 6 may be provided in the first machine room 4 and the second machine room 5 of the machine room unit 3, which will be described later, and the lifting rope of the lifting machine 6 may be provided in the support member 2.
  • the machine room unit 3 has a first machine room 4 and a second machine room 5.
  • the first machine room 4 is arranged below the second machine room 5 in the vertical direction.
  • the first machine room 4 and the second machine room 5 are connected to each other in a divisible manner, and are independently lifted by the lifting machine 6.
  • a movable support mechanism 7 is provided at the lower part of the first machine room 4 in the vertical direction.
  • the movable support mechanism 7 is configured to be expandable and contractible from the first machine room 4 toward the wall surface of the hoistway 100.
  • the movable support mechanism 7 is placed in the beams 101b, 101c, 101d provided in the hoistway 100 or in the recesses provided in the wall surface of the hoistway 100.
  • the movable support mechanism 7 supports the machine room unit 3 or the first machine room 4 at a predetermined position in the hoistway 100.
  • the movable support mechanism 7 is not limited to the above-mentioned one, but is a guide rail that supports the car 11 so as to be able to move up and down, an engaging member that engages with the wall surface of the hoistway 100, and is fastened and fixed to the wall surface.
  • Various other fixing mechanisms such as fastening members may be applied.
  • the first machine room 4 has an upper machine room 4a and a lower machine room 4b.
  • the upper machine room 4a is installed in the upper part of the lower machine room 4b in the vertical direction.
  • a second machine room 5 is installed in the upper part of the upper machine room 4a in the vertical direction.
  • a hoisting machine 9 is installed in the lower machine room 4b.
  • a rope fixing portion 14 for fixing the end portion of the main rope 10 is installed in the lower machine room 4b.
  • the first machine room 4 is divided into an upper machine room 4a and a lower machine room 4b, but the first machine room 4 may be one machine room. It may be divided into three or more machine rooms. Further, in the second machine room 5, although described as one machine room in this example, the machine room may be divided into two or more as in the first machine room 4.
  • a rope reel 15 around which the main rope 10 is wound, a first rope gripping device 16, a second rope gripping device 17, and a warp wheel 22 are installed.
  • An extension of the main rope 10 is wound around the rope reel 15. Then, when the machine room unit 3 is raised, the main rope 10 for the extension is pulled out from the rope reel 15.
  • the rope reel 15 includes a pit 100b which is a lower part of the hoistway 100 and a hoistway. It may be installed outside the 100.
  • a warp wheel 22 is arranged in the vicinity of the rope reel 15.
  • the warp wheel 22 changes the direction of the main rope 10 pulled out from the rope reel 15 in the direction toward the second machine room 5.
  • a first rope gripping device 16 is provided in the vicinity of the warp wheel 22 and the rope reel 15.
  • the first rope gripping device 16 grips the main rope 10 whose direction has been changed by the warp wheel 22 so as to be openable. Further, the first rope gripping device 16 grips the main rope 10 on the rope reel side (hereinafter, simply referred to as “first side”) A with respect to the pulley 19 described later in the main rope 10. Then, the first rope gripping device 16 regulates the movement of the main rope 10 by gripping the main rope 10.
  • the first rope gripping device 16 may be provided on the rope reel 15 or the warp wheel 22.
  • the second rope gripping device 17 is arranged on the elevating body side, that is, on the equilibrium weight 12 and the car 11 side (hereinafter, simply referred to as "second side") B with respect to the pulley 19 described later in the main rope 10.
  • the second rope gripping device 17 has a gripping portion 17a and a rope drum 17b.
  • the gripping portion 17a grips the main rope 10 so as to be openable, similarly to the first rope gripping device 16. Then, the grip portion 17a regulates the movement of the main rope 10 by gripping the main rope 10.
  • a rope drum 17b is arranged at the upper part of the grip portion 17a in the vertical direction.
  • the rope drum 17b is arranged on the pulley 19 side of the grip portion 17a. Therefore, the grip portion 17a is arranged on the elevating body side, that is, on the equilibrium weight 12 and the car 11 side with respect to the rope drum 17b.
  • the rope drum 17b is supported so that its rotation can be fixed and released.
  • the main rope 10 is wound around the rope drum 17b N times or more (N is 1 or more). When the rotation of the rope drum 17b is fixed, a frictional force is generated between the rope drum 17b and the main rope 10.
  • the first machine room 4 is not limited to the second-floor structure of the upper machine room 4a and the lower machine room 4b, but has a first-floor structure such as a hoisting machine 9, a rope fixing portion 14, and a rope reel 15.
  • the first rope gripping device 16 and the second rope gripping device 17 may be installed in one machine room.
  • the second machine room 5 is divisiblely connected to the upper part of the upper machine room 4a in the first machine room 4.
  • a control panel 8 for controlling a hoisting machine 9, a car 11, and the like, a pulley 19, and a third rope gripping device 18 are installed.
  • the control panel 8 and the car 11 are electrically connected via the tail cord 13. Further, a tail code reel 20 is installed in the vicinity of the control panel 8. An extension of the tail cord 13 is wound around the tail cord reel 20. Then, when ascending the second machine room 5, the tail code 13 is pulled out from the tail code reel 20.
  • the pulley 19 is rotatably supported by the second machine room 5.
  • the pulley 19 is arranged between the rope reel 15, the car 11 indicating the elevating body, and the balance weight 12.
  • the main rope 10 drawn from the rope reel 15 is wound around the pulley 19. Then, the pulley 19 changes the direction in which the main rope 10 extends from the upper side to the lower side.
  • a third rope gripping device 18 is arranged in the vicinity of the pulley 19.
  • the third rope gripping device 18 is arranged on the second side B with respect to the pulley 19 in the main rope 10. Further, the third rope gripping device 18 is arranged on the pulley 19 side of the rope drum 17b of the second rope gripping device 17.
  • the third rope gripping device 18 grips the main rope 10 so as to be openable, similarly to the first rope gripping device 16.
  • the third rope gripping device 18 operates to grip the main rope 10, and the first rope gripping device 16 and the second rope gripping device 17 are gripped.
  • the portion 17a is open. Therefore, one end of the main rope 10 is fixed to the rope fixing portion 14, and the other end of the main rope 10 is fixed to the third rope gripping device 18.
  • the rope drum 17b of the second rope gripping device 17 is fixed so as not to rotate.
  • a frictional force is generated between the rope drum 17b and the main rope 10.
  • the frictional force generated between the rope drum 17b and the main rope 10 can reduce the load applied to the third rope gripping device 18.
  • the force (grip force) for the third rope gripping device 18 to grip the main rope 10 can be reduced, and the gripping by the third rope gripping device 18 suppresses the main rope 10 from being scratched. be able to.
  • the third rope gripping device 18 grips the main rope 10 to fix the other end of the main rope 10
  • the present invention is not limited to this.
  • the third rope gripping device 18 may be opened, the main rope 10 may be gripped by the first rope gripping device 16, and the other end of the main rope 10 may be fixed by the first rope gripping device 16.
  • the main rope 10 may be gripped between the rope drum 17b of the second rope gripping device 17 and the rope reel 15, and the other end of the main rope 10 may be fixed. Therefore, in the rope reel 15, the other end of the main rope 10 may be fixed.
  • FIGS. 2 to 4 are explanatory views showing a method of extending the main rope 10.
  • the car 11 and the first machine room 4 are first connected by the chain 201, and the car 11 is fixed. Further, the balance weight 12 is lowered to the pit 100b, and the balance weight 12 is placed on a buffer (not shown) installed in the pit 100b. As a result, the main rope 10 is not tensioned from the car 11 and the counterweight 12.
  • the main rope 10 is gripped by the grip portion 17a of the second rope gripping device 17, and the grip of the main rope 10 by the third rope gripping device 18 is released.
  • the first rope gripping device 16 grips the main rope 10
  • the gripping of the main rope 10 by the first rope gripping device 16 is released.
  • the first machine room 4 and the second machine room 5 are divided.
  • the lifting machine 6 connected to the second machine room 5 is operated to raise only the second machine room 5 to a predetermined height (beam 101b in the example shown in FIG. 2). Since the main rope 10 is folded back by the pulley 19, the length (height) for raising the second machine room 5 may be about half the length of the extension of the main rope 10. As the second machine room 5 rises, the pulley 19 provided in the second machine room 5 also rises. When the second machine room 5 rises to a predetermined height, the lifting machine 6 is stopped, and the second machine room 5 and the pulley 19 are temporarily fixed by using the lifting machine 6 or a second machine room support mechanism (not shown). ..
  • one end of the main rope 10 is fixed by the grip portion 17a of the second rope gripping device 17, but the other end side of the main rope 10, that is, the rope reel 15 side is not fixed. Therefore, as the second machine room 5 and the pulley 19 rise, the main rope 10 on the rope reel 15 side is pulled, and the extended main rope 10 is pulled out from the rope reel 15. As a result, the ascending operation of the second machine room 5 and the pulley 19 and the operation of pulling out the main rope 10 from the rope reel 15 can be performed at the same time.
  • the other end of the main rope 10 is fixed by the grip portion 17a of the second rope gripping device 17 provided in the first machine room 4. Therefore, the main rope 10 is not pulled out downward from the first machine room 4 in the vertical direction. As a result, the hoisting machine 9 can be driven and the car 11 can be used even while the second machine room 5 is moving.
  • the main rope 10 is gripped by the first rope gripping device 16, and the gripping portion 17a of the second rope gripping device 17 is released from gripping the main rope 10. Further, the rope drum 17b of the second rope gripping device 17 is released from being fixed, and the rope drum 17b is made rotatable. Therefore, one end of the main rope 10 is fixed to the rope fixing portion 14, and the other end of the main rope 10 is fixed to the first rope gripping device 16.
  • the movable support mechanism 7 is reduced to release the support of the first machine room 4 by the movable support mechanism 7. Then, the lifting machine 6 connected to the first machine room 4 is operated to raise the first machine room 4 to a predetermined height (beam 101c in the examples shown in FIGS. 3 and 4). As a result, the extended main rope 10 pulled out from the rope reel 15 by the operation shown in FIG. 2 is sent out to the counterweight 12 and the car 11 side via the pulley 19 and the second rope gripping device 17.
  • the lifting machine 6 is stopped. Then, as shown in FIG. 4, the movable support mechanism 7 is extended and the movable support mechanism 7 is placed on the beam 101c. Further, the first machine room 4 and the second machine room 5 are connected. As a result, the machine room unit 3 including the first machine room 4 and the second machine room 5 can be raised to a predetermined height.
  • the rotation of the rope drum 17b of the second rope gripping device 17 is fixed, and the main rope 10 is gripped by the third rope gripping device 18.
  • the main rope 10 is first gripped by the grip portion 17a of the second rope gripping device 17.
  • the rope drum 17b of the second rope gripping device 17 is not subject to the weight of the main rope 10, so that the rope drum 17b can be easily rotated and the phase adjustment work of the rope drum 17b can be easily performed. It can be carried out.
  • the phase adjustment work of the rope drum 17b is completed, the rotation of the rope drum 17b is fixed.
  • the main rope 10 is gripped by the third rope gripping device 18. After that, the grip of the main rope 10 by the grip portion 17a of the second rope gripping device 17 is released. In this way, by gripping the main rope 10 once with the grip portion 17a of the second rope gripping device 17, it is possible to prevent the balance weight 12 from falling and the main rope 10 from being lowered by its own weight.
  • the grip of the main rope 10 by the first rope gripping device 16 is released. Then, the connection between the car 11 and the first machine room 4 is released, and the balance weight 12 is pulled up from the buffer (not shown). By performing such a process, the extension work of the main rope 10 and the expansion work of the operation floor of the construction elevator 1 are completed.
  • the main rope 10 can be extended without sliding the main rope 10 on the rope gripping devices 16 and 18 and the gripping portion 17a.
  • wear of the main rope 10 can be prevented, and the gripping force of the rope gripping devices 16 and 18 and the gripping portion 17a can be easily adjusted.
  • the machine room unit 3 is divided into a first machine room 4 and a second machine room 5, and each is independently lifted. As a result, the weight applied to the lifting machine 6 can be reduced, and the lifting machine 6 can be prevented from becoming large in size.
  • FIG. 5 is a schematic configuration diagram showing a construction elevator according to the second embodiment
  • FIGS. 6 and 7 are diagrams showing a method of extending the main rope in the construction elevator according to the second embodiment. Is.
  • the difference between the construction elevator according to the second embodiment and the construction elevator 1 according to the first embodiment is the configuration of the machine room unit. Therefore, here, the same reference numerals are given to the parts common to the construction elevator 1 according to the first embodiment, and duplicate description will be omitted.
  • the construction elevator 1B has a machine room unit 3B including a first machine room 4B and a second machine room 5B.
  • a hoisting machine 9 a rope fixing portion 14 for fixing the end portion of the main rope 10
  • a rope reel 15 a first rope gripping device 16 and a second rope gripping device 27 are installed.
  • a control panel 8, a tail code reel 20, and a pulley 19 are installed in the second machine room 5B.
  • the configuration of the control panel 8, the hoist 9, the rope fixing portion 14, the rope reel 15, the first rope gripping device 16, the pulley 19, and the tail cord reel 20 includes the construction elevator 1 according to the first embodiment. Since they are the same, the description thereof will be omitted. The detailed configuration of the second rope gripping device 27 will be described later.
  • the second machine room 5B is arranged above the first machine room 4B in the vertical direction.
  • the second machine room 5B is provided with the movable support mechanism 21 as in the first machine room 4B.
  • the movable support mechanism 21 is configured to be expandable and contractible from the second machine room 5B toward the wall surface of the hoistway 100.
  • the movable support mechanism 21 is placed in the beams 101b, 101c, 101d provided in the hoistway 100 or in the recesses provided in the wall surface of the hoistway 100.
  • the movable support mechanism 21 supports the machine room unit 3 or the second machine room 5B at a predetermined position in the hoistway 100.
  • the third rope gripping device 18 is not provided in the second machine room 5B according to the second embodiment.
  • the second rope gripping device 27 has a lower gripping portion 27a, a rope drum 27b, and an upper gripping portion 27c. Since the configurations of the lower grip portion 27a and the rope drum 27b are the same as those of the grip portion 17a and the rope drum 17b of the second rope gripping device 17 according to the first embodiment, the description thereof will be omitted.
  • the upper grip portion 27c is arranged above the rope drum 27b in the vertical direction. That is, the upper grip portion 27c is arranged on the pulley 19 side with respect to the rope drum 27b.
  • the upper grip portion 27c grips the main rope 10 so as to be openable, similarly to the first rope grip device 16 and the lower grip portion 27a.
  • the upper grip portion 27c has the same operation and operation as the third rope grip device 18 according to the first embodiment.
  • the upper grip portion 27c of the second rope gripping device 27 operates to grip the main rope 10, and the first rope gripping device 16 and the second rope are gripped.
  • the lower grip portion 27a of the grip device 27 is open. Therefore, one end of the main rope 10 is fixed to the rope fixing portion 14, and the other end of the main rope 10 is fixed to the upper gripping portion 27c of the second rope gripping device 27.
  • the upper grip portion 27c of the second rope gripping device 27 is opened, the main rope 10 is gripped by the first rope gripping device 16, and the first rope is gripped.
  • the other end of the main rope 10 may be fixed by the gripping device 16.
  • FIGS. 6 and 7 a method of extending the main rope 10 in the construction elevator 1B according to the second embodiment will be described with reference to FIGS. 6 and 7.
  • the car 11 and the first machine room 4 are connected by a chain 201, and the car 11 is fixed. Further, the balance weight 12 is lowered to the pit 100b, and the balance weight 12 is placed on a buffer (not shown) installed in the pit 100b.
  • the movable support mechanism 21 is reduced to release the support of the second machine room 5B by the movable support mechanism 21.
  • the lifting machine 6 connected to the second machine room 5B is operated to raise only the second machine room 5B to a predetermined height (beam 101b in the example shown in FIG. 2). As the second machine room 5B rises, the pulley 19 provided in the second machine room 5B also rises.
  • the other end of the main lobe 10 may be fixed by the lower grip portion 27a of the second rope gripping device 27 provided in the first machine room 4B. Even in this case, the main rope 10 is not pulled out downward from the first machine room 4B in the vertical direction.
  • the main rope 10 is gripped by the first rope gripping device 16, and the gripping of the main rope 10 by the upper gripping portion 27c of the second rope gripping device 27 is released. Further, the rope drum 27b of the second rope gripping device 27 is released from being fixed, and the rope drum 27b is made rotatable. Therefore, one end of the main rope 10 is fixed to the rope fixing portion 14, and the other end of the main rope 10 is fixed to the first rope gripping device 16.
  • the movable support mechanism 7 is reduced to release the support of the first machine room 4B by the movable support mechanism 7. Then, the lifting machine 6 connected to the first machine room 4B is operated to raise the first machine room 4B to a predetermined height (beam 101c in the example shown in FIG. 7). Then, when the first machine room 4B rises to a predetermined height, the lifting machine 6 is stopped, the movable support mechanism 7 is extended, and the movable support mechanism 7 is placed on the beam 101c. As a result, the first machine room 4B and the second machine room 5B can be raised to a predetermined height.
  • a predetermined height beam 101c in the example shown in FIG. 7
  • the rotation of the rope drum 27b of the second rope gripping device 27 is fixed, and the main rope 10 is gripped by the upper gripping portion 27c.
  • the main rope 10 is first gripped by the lower grip portion 27a of the second rope gripping device 27. Then, the phase of the rope drum 27b is adjusted to fix the rotation of the rope drum 27b.
  • the main rope 10 is gripped by the upper grip portion 27c. After that, the grip of the main rope 10 by the lower grip portion 27a is released.
  • the grip of the main rope 10 by the first rope gripping device 16 is released. Then, the connection between the car 11 and the first machine room 4B is released, and the balance weight 12 is pulled up from the buffer (not shown). As a result, the extension work of the main rope 10 and the expansion work of the operation floor of the construction elevator 1B are completed.
  • construction elevator 1B according to the second embodiment can also obtain the same effect as the construction elevator 1 according to the first embodiment described above.
  • FIG. 8 is a schematic configuration diagram showing a construction elevator according to the third embodiment
  • FIGS. 9 and 10 are views showing a method of extending the main rope in the construction elevator according to the third embodiment. Is.
  • the difference between the construction elevator according to the third embodiment and the construction elevator 1 according to the first embodiment is the configuration of the machine room unit. Therefore, here, the same reference numerals are given to the parts common to the construction elevator 1 according to the first embodiment, and duplicate description will be omitted.
  • the construction elevator 1C has a machine room unit 3C including a first machine room 4C and a second machine room 5C, and a pulley 19C.
  • the first machine room 4C and the second machine room 5C are integrally formed.
  • a hoisting machine 9 a rope fixing portion 14 for fixing the end portion of the main rope 10, a rope reel 15, a first rope gripping device 16 and a second rope gripping device 17 are installed.
  • a control panel 8, a tail cord reel 20, and a third rope gripping device 18 are installed in the second machine room 5B.
  • control panel 8 The configuration of the control panel 8, the hoist 9, the rope fixing portion 14, the rope reel 15, the first rope gripping device 16, the second rope gripping device 17, the third rope gripping device 18, and the tail cord reel 20 is the first. Since it is the same as the construction elevator 1 according to the embodiment, the description thereof will be omitted.
  • the pulley 19C is supported by the pulley lifting machine 6C so that it can be lifted (moved) along the vertical direction. That is, the pulley 19C moves independently of the machine room unit 3C by the pulley lifting machine 6C. Further, the pulley 19C is rotatably supported, and the main rope 10 is wound around it.
  • the first rope gripping device 16 is arranged on the rope reel 15 side, that is, on the first side A with respect to the pulley 19C in the main rope 10.
  • a second rope gripping device 17 and a third rope gripping device 18 are arranged on the counterweight weight 12 and the car 11 side with respect to the pulley 19C on the main rope, and on the second side B.
  • the third rope gripping device 18 operates to grip the main rope 10, and the first rope gripping device 16 and the second rope gripping device 17 are gripped.
  • the portion 17a is open. Therefore, one end of the main rope 10 is fixed to the rope fixing portion 14, and the other end of the main rope 10 is fixed to the third rope gripping device 18. Further, since the rope drum 17b of the second rope gripping device 17 is fixed so as not to rotate, the load applied to the third rope gripping device 18 can be reduced.
  • the third rope gripping device 18 is opened, the main rope 10 is gripped by the first rope gripping device 16, and the first rope gripping device 16 mainly grips the main rope 10.
  • the other end of the rope 10 may be fixed.
  • FIGS. 9 and 10 a method of extending the main rope 10 in the construction elevator 1C according to the third embodiment will be described with reference to FIGS. 9 and 10.
  • the car 11 and the machine room unit 3C are connected by a chain 201, and the car 11 is fixed. Further, the balance weight 12 is lowered to the pit 100b, and the balance weight 12 is placed on a buffer (not shown) installed in the pit 100b.
  • the pulley lifting machine 6C connected to the pulley 19C is driven, and only the pulley 19C is raised to a predetermined height.
  • the second side B is fixed to the pulley 19C in the main rope 10 by the third rope gripping device 18. Therefore, the main rope 10 can be pulled out from the rope reel 15 by raising the pulley 19C.
  • the length (height) for raising the pulley 19C may be about half the length of the extension of the main rope 10.
  • the present invention is not limited to this, and the third rope gripping device 18 is opened and the gripping portion 17a of the second rope gripping device 17 is opened.
  • the main rope 10 may be fixed with.
  • the lifting machine 6 is stopped to temporarily fix the pulley 19C in the hoistway 100.
  • the main rope 10 is gripped by the first rope gripping device 16 and the gripping of the main rope 10 by the third rope gripping device 18 is released. Further, the rope drum 17b of the second rope gripping device 17 is released from being fixed, and the rope drum 17b is made rotatable. Therefore, one end of the main rope 10 is fixed to the rope fixing portion 14, and the other end of the main rope 10 is fixed to the first rope gripping device 16.
  • the car 11 and the machine room unit 3C are used before the above-mentioned work (process) is performed. And put the balance weight 12 on the buffer.
  • the movable support mechanism 7 is reduced to release the support of the machine room unit 3C by the movable support mechanism 7. Then, the lifting machine 6 connected to the machine room unit 3C is operated to raise the machine room unit 3C to a predetermined height. Then, when the machine room unit 3C rises to a predetermined height, the lifting machine 6 is stopped, the movable support mechanism 7 is extended, and the movable support mechanism 7 is placed on the beam 101c. As a result, the machine room unit 3C can be raised to a predetermined height.
  • the rotation of the rope drum 17b of the second rope gripping device 17 is fixed, and the main rope 10 is gripped by the third rope gripping device 18.
  • the main rope 10 is first gripped by the grip portion 17a of the second rope gripping device 17. Then, the phase of the rope drum 17b is adjusted to fix the rotation of the rope drum 17b.
  • the main rope 10 is gripped by the third rope gripping device 18. After that, the grip of the main rope 10 by the grip portion 17a of the second rope gripping device 17 is released.
  • construction elevator 1C according to the third embodiment can also have the same effect as the construction elevator 1 according to the first embodiment described above.
  • the pulley 19 rises together with the second machine rooms 5 and 5B, so that the main rope 10 is used. Is pulled out from the rope reel 15. That is, in the construction elevator 1 according to the first embodiment and the construction elevator 1B according to the second embodiment, the lifting machine 6 for lifting the machine room units 3 and 3B serves as a pulley lifting machine. Has the role of. On the other hand, in the construction elevator 1C according to the third embodiment, only the pulley 19C rises independently of the machine room unit 3C, so that the main rope 10 is pulled out from the rope reel 15.
  • FIG. 11 is a schematic configuration diagram showing a construction elevator according to a fourth embodiment.
  • the difference between the construction elevator according to the fourth embodiment and the construction elevator according to the first and third embodiments is the order in which the main rope is hung on the car and the balance weight. Therefore, here, the same reference numerals are given to the parts common to the construction elevators 1 and 1C according to the first and third embodiments, and duplicate description will be omitted.
  • the construction elevator 1D has a machine room unit 3D, a car 11, and a balance weight 12.
  • a rope reel 15 around which the main rope 10 is wound, a hoisting machine 9, and the like are arranged.
  • the main rope 10 is provided from the rope reel 15 via the pulley 19 to the car side pulley 11a, the hoisting machine 9, and the balance weight.
  • the weight side pulleys 12a provided on the 12 are wound in this order.
  • One end of the main rope 10 extending from the weight side pulley 12a is fixed to the rope fixing portion 14 of the machine room unit 3D.
  • construction elevator 1D according to the fourth embodiment can also obtain the same effect as the construction elevators 1 and 1C according to the first and third embodiments described above.
  • FIG. 12 is a schematic configuration diagram showing a construction elevator according to a fifth embodiment.
  • the difference between the construction elevator according to the fifth embodiment and the construction elevator according to the second embodiment is the order in which the main rope is hung on the car and the balance weight. Therefore, here, the same reference numerals are given to the parts common to the construction elevator 1B according to the second embodiment, and duplicate description will be omitted.
  • the construction elevator 1E has a machine room unit 3E, a car 11, and a balance weight 12.
  • a rope reel 15 around which the main rope 10 is wound, a hoisting machine 9, and the like are arranged.
  • the main rope 10 is provided from the rope reel 15 via the pulley 19 to the car side pulley 11a, the hoisting machine 9, and the balance weight.
  • the weight side pulleys 12a provided on the 12 are wound in this order.
  • One end of the main rope 10 extending from the weight side pulley 12a is fixed to the rope fixing portion 14 of the machine room unit 3E.
  • construction elevator 1E according to the fifth embodiment can also obtain the same effect as the construction elevator 1B according to the second embodiment described above.

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

工事用エレベーターは、工事用エレベーターは、ロープリールと、昇降体と、滑車と、第1ロープ把持装置と、第2ロープ把持装置と、を備えている。滑車は、主ロープにおけるロープリールと昇降体との間に配置され、ロープリールから引き出された主ロープが巻き掛けられる。第1ロープ把持装置は、滑車に対してロープリール側の主ロープを開放可能に把持する。第2ロープ把持装置は、滑車に対して昇降体側の主ロープを開放可能に把持する。そして、滑車は、昇降体の昇降方向に沿って移動可能に支持される。

Description

工事用エレベーター及び工事用エレベーターの主ロープの延長方法
 本発明は、工事用エレベーター及び工事用エレベーターの主ロープの延長方法に関するものである。
 近年、建設中の建築構造物に設けられて、資材や人を運搬するためのエレベーターとして工事用エレベーターが提案されている。この工事用エレベーターは、建築構造物の建設の進捗状況に応じて、巻上機や制御盤等を有する機械室ユニットを上昇させることで、乗りかごが昇降する範囲、すなわち運行可能な範囲を拡大させている。また、乗りかごの昇降範囲の拡大に伴って乗りかごに接続される主ロープの延長作業も行われる。
 従来の工事用エレベーターとしては、例えば、特許文献1に記載されているようなものがある。特許文献1に記載された技術では、機械室ユニットを上昇させる際に、主ロープが自重により主ロープリールから作業者の意図に反して引き出されることを防止するために、把持装置により主ロープを所定の力で把持している。そして、機械室ユニットを上昇させることで、主ロープが把持装置上を滑り、主ロープの延長が行われる。
特開2001-287881号公報
 しかしながら、特許文献1に開示された技術では、主ロープを延長する際に、主ロープが把持装置上を滑るため、主ロープと把持装置との摩擦により主ロープに傷や摩耗が生じるおそれがあった。また、把持装置で主ロープを把持しているため、機械室ユニットを揚重させる力が増大する、という問題も有していた。その結果、特許文献1に開示された技術では、主ロープを延長する際に把持装置で主ロープを把持する力を調整することが煩雑になるという問題を有していた。
 本目的は、上記の問題点を考慮し、主ロープを傷つけることなく、主ロープの延長作業を行うことができる工事用エレベーター及び工事用エレベーターの主ロープの延長方法を提供することにある。
 上記課題を解決し、目的を達成するため、工事用エレベーターは、ロープリールと、昇降体と、滑車と、第1ロープ把持装置と、第2ロープ把持装置と、を備えている。ロープリールには、主ロープが巻回されている。昇降体は、ロープリールから引き出された主ロープが巻き掛けられ、建築構造物の昇降路を昇降する。滑車は、主ロープにおけるロープリールと昇降体との間に配置され、ロープリールから引き出された主ロープが巻き掛けられる。第1ロープ把持装置は、滑車に対してロープリール側の主ロープを開放可能に把持する。第2ロープ把持装置は、滑車に対して昇降体側の主ロープを開放可能に把持する。そして、滑車は、昇降体の昇降方向に沿って移動可能に支持される。
 また、上述した構成を有する工事用エレベーターの主ロープの延長方法は、以下(1)から(4)に示す工程を含む。
(1)第2ロープ把持装置で主ロープを把持する工程。
(2)第1ロープ把持装置による主ロープの把持を開放し、滑車を昇降体の昇降方向に沿って所定の高さまで上昇させ、ロープリールから主ロープを引き出す工程。
(3)滑車を所定の高さまで上昇させた後、第1ロープ把持装置で主ロープを把持し、第2ロープ把持装置による主ロープの把持を開放する工程。
(4)第2ロープ把持装置が設置された機械室ユニットを所定の高さまで上昇させる工程。
 上記構成の工事用エレベーターによれば、主ロープを傷つけることなく、機械室ユニットの設置作業を容易に行うことができる。
第1の実施の形態例にかかる工事用エレベーターを示す概略構成図である。 第1の実施の形態例にかかる工事用エレベーターにおける主ロープの延長方法を示すもので、第2機械室の移動中の状態を示す図である。 第1の実施の形態例にかかる工事用エレベーターにおける主ロープの延長方法を示すもので、第1機械室の移動中の状態を示す図である。 第1の実施の形態例にかかる工事用エレベーターにおける主ロープの延長方法を示すもので、機械室ユニットの移動後の状態を示す図である。 第2の実施の形態例にかかる工事用エレベーターを示す概略構成図である。 第2の実施の形態例にかかる工事用エレベーターにおける主ロープの延長方法を示すもので、第2機械室の移動中の状態を示す図である。 第2の実施の形態例にかかる工事用エレベーターにおける主ロープの延長方法を示すもので、第1機械室の移動中の状態を示す図である。 第3の実施の形態例にかかる工事用エレベーターを示す概略構成図である。 第3の実施の形態例にかかる工事用エレベーターにおける主ロープの延長方法を示すもので、滑車の移動中の状態を示す図である。 第3の実施の形態例にかかる工事用エレベーターにおける主ロープの延長方法を示すもので、機械室ユニットの移動中の状態を示す図である。 第4の実施の形態例にかかる工事用エレベーターを示す概略構成図である。 第5の実施の形態例にかかる工事用エレベーターを示す概略構成図である。
 以下、実施の形態例にかかる工事用エレベーター及び主ロープの延長方法について、図1~図12を参照して説明する。なお、各図において共通の部材には、同一の符号を付している。
1.第1の実施の形態例
1-1.工事用エレベーターの構成例
 まず、第1の実施の形態例(以下、「本例」という。)にかかる工事用エレベーターの構成について、図1を参照して説明する。
 図1は、本例の工事用エレベーターを示す概略構成図である。
 図1に示すエレベーターは、建設中の建築構造物に設けられて、資材や人を運搬するために用いられる工事用エレベーターである。図1に示すように、工事用エレベーター1は、建築構造物の昇降路100の上部に配置された支持部材2と、機械室ユニット3と、機械室ユニット3を揚重する揚重機6とを備えている。また、工事用エレベーター1は、巻上機9と、主ロープ10と、人や資材を乗せる乗りかご11と、釣合おもり12とを備えている。乗りかご11及び釣合おもり12は、昇降体の一例を示している。なお、乗りかご11と釣合おもり12の位置関係は逆でもよい。すなわち、図1において釣合おもりが符号11に相当し、乗りかごが符号12に相当してもよい。以下、昇降体である乗りかご11及び釣合おもり12が昇降する方向を上下方向とする。
 乗りかご11の上部には、かご側プーリ11aが設けられている。また、釣合おもり12の上部には、おもり側プーリ12aが設けられている。かご側プーリ11a及びおもり側プーリ12aには、主ロープ10が巻き掛けられる。また、主ロープ10は、後述する機械室ユニット3に設置された巻上機9の綱車に巻き掛けられている。
 主ロープ10は、後述する機械室ユニット3に設けたロープリール15に巻回されており、このロープリール15から引き出されている。そして、主ロープ10におけるロープリール15とは反対側の端部は、機械室ユニット3においてロープ固定部14に固定されている。そして、主ロープ10は、ロープリール15から、後述する滑車19を介して、おもり側プーリ12a、巻上機9、かご側プーリ11aの順に巻き掛けられ、その端部がロープ固定部14に固定されている。そして、巻上機9が駆動することで、乗りかご11及び釣合おもり12は、昇降路100内を昇降移動する。
 支持部材2は、昇降路100の最上部に設けられた梁101a又は、昇降路100の壁面に設けた凹部に設置される。支持部材2には、揚重機6が設けられている。支持部材2の上下方向の下方には、機械室ユニット3が配置される。そして、機械室ユニット3は、揚重機6を介して支持部材2から吊り下げられている。機械室ユニット3は、揚重機6に揚重(移動)可能に支持される。なお、揚重機6を後述する機械室ユニット3の第1機械室4及び第2機械室5に設け、揚重機6の揚重ロープを支持部材2に設けてもよい。
 機械室ユニット3は、第1機械室4と、第2機械室5とを有している。第1機械室4は、第2機械室5よりも上下方向の下方に配置される。第1機械室4と第2機械室5は、分割可能に連結されており、それぞれ揚重機6によって独立して揚重される。
 第1機械室4の上下方向の下部には、可動支持機構7が設けられている。可動支持機構7は、第1機械室4から昇降路100の壁面に向けて伸縮可能に構成されている。そして、可動支持機構7は、昇降路100に設けた梁101b、101c、101dや昇降路100の壁面に設けた凹部に載置される。可動支持機構7は、機械室ユニット3又は第1機械室4を昇降路100における所定の位置で支持する。なお、可動支持機構7としては、上述したものに限定されるものではなく、乗りかご11を昇降可能に支持するガイドレールや昇降路100の壁面に係合する係合部材や、壁面に締結固定する締結部材等その他各種の固定機構を適用してもよい。
 第1機械室4は、上部機械室4aと、下部機械室4bとを有している。上部機械室4aは、下部機械室4bの上下方向の上部に設置されている。そして、上部機械室4aの上下方向の上部には、第2機械室5が設置されている。下部機械室4bには、巻上機9が設置されている。そして、下部機械室4bには、主ロープ10の端部を固定するロープ固定部14が設置されている。
 なお、本例では、第1機械室4を上部機械室4aと、下部機械室4bの2つに分ける構成で説明したが、第1機械室4は、1つの機械室であってもよく、3つ以上の機械室に分ける構成でもよい。また、第2機械室5においても、本例では、1つの機械室として説明したが、第1機械室4と同様に2つ以上に機械室が分かれる構成であってもよい。
 上部機械室4aには、主ロープ10が巻回されたロープリール15と、第1ロープ把持装置16と、第2ロープ把持装置17と、反らせ車22が設置されている。ロープリール15には、延長分の主ロープ10が巻回されている。そして、機械室ユニット3を上昇する際に、ロープリール15から延長分の主ロープ10が引き出される。なお、本例では、ロープリール15を機械室ユニット3に設置した例を説明したが、これに限定されるものではなく、ロープリール15は、昇降路100の下部であるピット100bや、昇降路100の外側に設置してもよい。
 ロープリール15の近傍には、反らせ車22が配置されている。反らせ車22は、ロープリール15から引き出された主ロープ10の向きを第2機械室5に向く方向に変化させせる。
 反らせ車22及びロープリール15の近傍には、第1ロープ把持装置16が設けられている。第1ロープ把持装置16は、反らせ車22によって方向が変化した主ロープ10を開放可能に把持する。また、第1ロープ把持装置16は、主ロープ10における後述する滑車19に対してロープリール側(以下、単に「第1側」という)Aの主ロープ10を把持する。そして、第1ロープ把持装置16は、主ロープ10を把持することで、主ロープ10の移動を規制する。なお、第1ロープ把持装置16は、ロープリール15や反らせ車22に設けてもよい。
 第2ロープ把持装置17は、主ロープ10における後述する滑車19に対して昇降体側、すなわち釣合おもり12及び乗りかご11側(以下、単に「第2側」という)Bに配置されている。第2ロープ把持装置17は、把持部17aと、ロープドラム17bとを有している。把持部17aは、第1ロープ把持装置16と同様に、主ロープ10を開放可能に把持する。そして、把持部17aは、主ロープ10を把持することで、主ロープ10の移動を規制する。
 把持部17aにおける上下方向の上部には、ロープドラム17bが配置されている。そして、ロープドラム17bは、把持部17aよりも滑車19側に配置される。そのため、把持部17aは、ロープドラム17bよりも昇降体側、すなわち釣合おもり12及び乗りかご11側に配置される。ロープドラム17bは、その回転を固定及び解除可能に支持されている。ロープドラム17bには、主ロープ10がN回以上(Nは1以上)巻き掛けられている。ロープドラム17bの回転を固定した際、ロープドラム17bと主ロープ10との間には、摩擦力が発生する。
 このように、第1機械室4を上部機械室4aと下部機械室4bの2階構造にすることで、昇降路100における水平方向のスペースを削減することができる。なお、第1機械室4は、上部機械室4aと下部機械室4bの2階構造に限定されるものではなく、1階構造にして、巻上機9、ロープ固定部14、ロープリール15、第1ロープ把持装置16及び第2ロープ把持装置17を一つの機械室に設置してもよい。
 次に、第2機械室5について説明する。
 第2機械室5は、第1機械室4における上部機械室4aの上部に分割可能に連結されている。第2機械室5には、巻上機9や乗りかご11等を制御する制御盤8と、滑車19と、第3ロープ把持装置18が設置されている。
 制御盤8と乗りかご11は、テールコード13を介して電気的に接続されている。また、制御盤8の近傍には、テールコードリール20が設置されている。テールコードリール20には、延長分のテールコード13が巻回されている。そして、第2機械室5を上昇する際に、テールコードリール20からテールコード13が引き出される。
 滑車19は、第2機械室5に回転可能に支持されている。滑車19は、ロープリール15と昇降体を示す乗りかご11及び釣合おもり12の間に配置される。滑車19には、ロープリール15から引き出された主ロープ10が巻き掛けられる。そして、滑車19は、主ロープ10が延在する向きを上方から下方に変化させる。
 滑車19の近傍には、第3ロープ把持装置18が配置されている。第3ロープ把持装置18は、主ロープ10における滑車19に対して第2側Bに配置されている。また、第3ロープ把持装置18は、第2ロープ把持装置17のロープドラム17bよりも滑車19側に配置される。第3ロープ把持装置18は、第1ロープ把持装置16と同様に、主ロープ10を開放可能に把持する。
 図面では、第1ロープ把持装置16、第2ロープ把持装置17の把持部17a及び第3ロープ把持装置18において、主ロープ10を把持している状態を黒塗りで示し、主ロープ10を開放している状態を白抜きで示している。
 図1に示すように、工事用エレベーター1の運転中では、第3ロープ把持装置18が作動して主ロープ10を把持しており、第1ロープ把持装置16及び第2ロープ把持装置17の把持部17aは、開放されている。そのため、主ロープ10の一端部は、ロープ固定部14に固定され、主ロープ10の他端部は、第3ロープ把持装置18に固定されている。
 また、第2ロープ把持装置17のロープドラム17bは、回転不能に固定されている。上述したように、ロープドラム17bには、主ロープ10が巻き掛けられているため、ロープドラム17bと主ロープ10の間には、摩擦力が発生する。このロープドラム17bと主ロープ10の間に発生した摩擦力により、第3ロープ把持装置18にかかる荷重を低減させることができる。その結果、第3ロープ把持装置18が主ロープ10を把持する力(把持力)を小さくすることができ、第3ロープ把持装置18が把持することで主ロープ10に傷がつくことを抑制することができる。ロープドラム17bへの主ロープ10の巻き掛け数が多いほど、第3ロープ把持装置18の把持力を小さくすることができる。
 なお、本例では、第3ロープ把持装置18が主ロープ10を把持することで主ロープ10の他端部を固定する例を説明したが、これに限定されるものではない。例えば、第3ロープ把持装置18を開放し、第1ロープ把持装置16によって主ロープ10を把持し、第1ロープ把持装置16で主ロープ10の他端部を固定してもよい。少なくとも、第2ロープ把持装置17のロープドラム17bと、ロープリール15の間で主ロープ10を把持し、主ロープ10の他端部を固定すればよい。そのため、ロープリール15において、主ロープ10の他端部を固定してもよい。
1-2.主ロープの延長方法
 次に、上述した構成を有する工事用エレベーター1における主ロープ10の延長方法、すなわち機械室ユニット3を上昇させて、運行階の拡張方法について図2から図4を参照して説明する。
 図2から図4は、主ロープ10の延長方法を示す説明図である。
 図2に示すように、主ロープ10の延長作業を行う際、まず乗りかご11と第1機械室4をチェーン201で連結し、乗りかご11を固定する。また、釣合おもり12をピット100bまで下げて、ピット100bに設置した不図示のバッファの上に釣合おもり12を載置させる。これにより、主ロープ10には、乗りかご11と釣合おもり12からの張力がかからなくなる。
 次に、第2ロープ把持装置17の把持部17aで主ロープ10を把持すると共に、第3ロープ把持装置18による主ロープ10の把持を開放する。なお、第1ロープ把持装置16が主ロープ10を把持している場合は、第1ロープ把持装置16による主ロープ10の把持を開放する。そして、第1機械室4と第2機械室5を分割させる。
 次に、第2機械室5に連結された揚重機6を作動させて、第2機械室5のみを所定の高さ(図2に示す例では、梁101b)まで上昇させる。なお、主ロープ10は、滑車19により折り返されているため、第2機械室5を上昇させる長さ(高さ)は、主ロープ10の延長分の長さの約半分でよい。第2機械室5が上昇することで、第2機械室5に設けた滑車19も上昇する。第2機械室5が所定の高さまで上昇すると、揚重機6を停止させて、揚重機6又は不図示の第2機械室支持機構等を用いて第2機械室5及び滑車19を仮固定する。
 ここで、主ロープ10の一端部は、第2ロープ把持装置17の把持部17aで固定されているが、主ロープ10の他端部側、すなわちロープリール15側は、固定されていない。そのため、第2機械室5及び滑車19の上昇に伴って、ロープリール15側の主ロープ10が引っ張られ、ロープリール15から延長分の主ロープ10が引き出される。これにより、第2機械室5及び滑車19の上昇動作と主ロープ10をロープリール15から引き出す動作を同時に行うことができる。
 第2機械室5を移動させる際、主ロープ10の他端部は、第1機械室4に設けた第2ロープ把持装置17の把持部17aによって固定されている。そのため、主ロープ10は、第1機械室4から上下方向の下方に引き出されることがない。これにより、第2機械室5の移動中においても、巻上機9を駆動させて、乗りかご11を使用することができる。
 次に、図3に示すように、第1ロープ把持装置16で主ロープ10を把持すると共に、第2ロープ把持装置17の把持部17aによる主ロープ10の把持を開放する。また、第2ロープ把持装置17のロープドラム17bの固定を解除し、ロープドラム17bを回転可能にする。そのため、主ロープ10の一端部は、ロープ固定部14に固定され、主ロープ10の他端部は、第1ロープ把持装置16に固定される。
 次に、可動支持機構7を縮小させて、可動支持機構7による第1機械室4の支持を解除する。そして、第1機械室4に連結された揚重機6を作動させて、第1機械室4を所定の高さ(図3及び図4に示す例では、梁101c)まで上昇させる。これにより、図2に示す動作でロープリール15から引き出された延長分の主ロープ10は、滑車19及び第2ロープ把持装置17を介して釣合おもり12及び乗りかご11側に送り出される。
 第1機械室4が所定の高さまで上昇すると、揚重機6を停止させる。そして、図4に示すように、可動支持機構7を伸長させて、可動支持機構7を梁101cに載置させる。また、第1機械室4と第2機械室5を連結させる。これにより、第1機械室4及び第2機械室5からなる機械室ユニット3を所定の高さまで上昇させることができる。
 次に、第2ロープ把持装置17のロープドラム17bの回転を固定し、第3ロープ把持装置18で主ロープ10を把持する。ロープドラム17bの回転を固定する際、ロープドラム17bの位相を調整することが好ましい。そのため、ロープドラム17bの回転を固定する前に、まず第2ロープ把持装置17の把持部17aで主ロープ10を把持する。これにより、第2ロープ把持装置17のロープドラム17bには、主ロープ10の自重がかからなくなるため、ロープドラム17bを容易に回転させることができ、ロープドラム17bの位相の調整作業を容易に行うことができる。そして、ロープドラム17bの位相の調整作業が完了すると、ロープドラム17bの回転を固定させる。
 また、ロープドラム17bの回転の固定作業が完了すると、第3ロープ把持装置18で主ロープ10を把持させる。その後、第2ロープ把持装置17の把持部17aによる主ロープ10の把持を開放させる。このように、第2ロープ把持装置17の把持部17aで主ロープ10を一度把持させることで、釣合おもり12の落下や主ロープ10が自重により下がることを防止することができる。
 次に、第1ロープ把持装置16による主ロープ10の把持を開放する。そして、乗りかご11と第1機械室4の連結を解除し、釣合おもり12を不図示のバッファから引き上げる。このような工程を行うことで、主ロープ10の延長作業及び工事用エレベーター1の運行階の拡張作業が完了する。
 本例の工事用エレベーター1及び主ロープ10の延長方法によれば、主ロープ10をロープ把持装置16、18や把持部17a上で滑らせることなく、主ロープ10を延長させることができる。これにより、主ロープ10の摩耗を防ぐことができると共に、ロープ把持装置16、18や把持部17aの把持力の調整を容易に行うことができる。
 また、機械室ユニット3を第1機械室4と第2機械室5に分割し、それぞれ独立させて揚重している。これにより、揚重機6にかかる重量を軽減することができ、揚重機6が大型化することを防止することができる。
2.第2の実施の形態例
 次に、図5から図7を参照して第2の実施の形態例にかかる工事用エレベーターについて説明する。
 図5は、第2の実施の形態例にかかる工事用エレベーターを示す概略構成図、図6及び図7は、第2の実施の形態例にかかる工事用エレベーターにおける主ロープの延長方法を示す図である。
 この第2の実施の形態例にかかる工事用エレベーターが、第1の実施の形態例にかかる工事用エレベーター1と異なる点は、機械室ユニットの構成である。そのため、ここでは、第1の実施の形態例にかかる工事用エレベーター1と共通する部分には、同一の符号を付して重複した説明を省略する。
 図5に示すように、工事用エレベーター1Bは、第1機械室4Bと第2機械室5Bからなる機械室ユニット3Bを有している。第1機械室4Bには、巻上機9、主ロープ10の端部を固定するロープ固定部14、ロープリール15、第1ロープ把持装置16及び第2ロープ把持装置27が設置されている。第2機械室5Bには、制御盤8、テールコードリール20及び滑車19が設置されている。
 制御盤8、巻上機9、ロープ固定部14、ロープリール15、第1ロープ把持装置16、滑車19及びテールコードリール20の構成は、第1の実施の形態例にかかる工事用エレベーター1と同様であるため、その説明は省略する。第2ロープ把持装置27の詳細な構成については、後述する。
 第2機械室5Bは、第1機械室4Bよりも上下方向の上方に配置されている。そして、第2機械室5Bには、第1機械室4Bと同様に、可動支持機構21が設けられている。可動支持機構21は、第2機械室5Bから昇降路100の壁面に向けて伸縮可能に構成されている。そして、可動支持機構21は、昇降路100に設けた梁101b、101c、101dや昇降路100の壁面に設けた凹部に載置される。可動支持機構21は、機械室ユニット3又は第2機械室5Bを昇降路100における所定の位置で支持する。
 この第2の実施の形態例にかかる第2機械室5Bには、第3ロープ把持装置18が設けられていない。
 第2ロープ把持装置27は、下部把持部27aと、ロープドラム27bと、上部把持部27cとを有している。下部把持部27a及びロープドラム27bの構成は、第1の実施の形態例にかかる第2ロープ把持装置17の把持部17a及びロープドラム17bと同様であるため、その説明は省略する。
 上部把持部27cは、ロープドラム27bよりも上下方向の上方に配置されている。すなわち、上部把持部27cは、ロープドラム27bよりも滑車19側に配置される。上部把持部27cは、第1ロープ把持装置16及び下部把持部27aと同様に、主ロープ10を開放可能に把持する。この上部把持部27cは、第1の実施の形態例にかかる第3ロープ把持装置18と同様の動作及び作用を有している。
 図5に示すように、工事用エレベーター1Bの運転中では、第2ロープ把持装置27の上部把持部27cが作動して主ロープ10を把持しており、第1ロープ把持装置16及び第2ロープ把持装置27の下部把持部27aは、開放されている。そのため、主ロープ10の一端部は、ロープ固定部14に固定され、主ロープ10の他端部は、第2ロープ把持装置27の上部把持部27cに固定される。
 また、第2ロープ把持装置27のロープドラム27bは、回転不能に固定されているため、上部把持部27cにかかる荷重を低減させることができる。
 なお、第2の実施の形態例にかかる工事用エレベーター1Bにおいても、第2ロープ把持装置27の上部把持部27cを開放し、第1ロープ把持装置16によって主ロープ10を把持し、第1ロープ把持装置16で主ロープ10の他端部を固定してもよい。
 次に、図6及び図7を参照して第2の実施の形態例にかかる工事用エレベーター1Bにおける主ロープ10の延長方法について説明する。
 まず、図6に示すように、乗りかご11と第1機械室4をチェーン201で連結し、乗りかご11を固定する。また、釣合おもり12をピット100bまで下げて、ピット100bに設置した不図示のバッファの上に釣合おもり12を載置させる。
 次に、第2ロープ把持装置27の上部把持部27cで主ロープ10を把持した状態で、可動支持機構21を縮小させて、可動支持機構21による第2機械室5Bの支持を解除する。第2機械室5Bに連結された揚重機6を作動させて、第2機械室5Bのみを所定の高さ(図2に示す例では、梁101b)まで上昇させる。第2機械室5Bが上昇することで、第2機械室5Bに設けた滑車19も上昇する。
 図7に示すように、第2機械室5Bが所定の高さまで上昇すると、揚重機6を停止させて、可動支持機構21を伸長させて、可動支持機構21を梁101bに載置させる。また、第2機械室5B及び滑車19の上昇に伴って、ロープリール15側の主ロープ10が引っ張られ、ロープリール15から延長分の主ロープ10が引き出される。これにより、第2機械室5B及び滑車19の上昇動作と主ロープ10をロープリール15から引き出す動作を同時に行うことができる。
 図6に示すように、第2機械室5Bを移動させる際、主ロープ10の他端部は、第1機械室4Bに設けた第2ロープ把持装置27の上部把持部27cによって固定されている。そのため、主ロープ10は、第1機械室4Bから上下方向の下方に引き出されることがない。これにより、第2機械室5Bの移動中においても、巻上機9を駆動させて、乗りかご11を使用することができる。すなわち、主ロープ10の延長作業中も工事用エレベーター1Bを運動させることができ、工事用エレベーター1Bの設置工事や建築構造物の建設作業の向上を図ることができる。
 なお、第2機械室5Bを移動させる際、主ローブ10の他端部を第1機械室4Bに設けた第2ロープ把持装置27の下部把持部27aによって固定してもよい。この場合においても、主ロープ10は、第1機械室4Bから上下方向の下方に引き出されることがない。
 次に、図7に示すように、第1ロープ把持装置16で主ロープ10を把持すると共に、第2ロープ把持装置27の上部把持部27cによる主ロープ10の把持を開放する。また、第2ロープ把持装置27のロープドラム27bの固定を解除し、ロープドラム27bを回転可能にする。そのため、主ロープ10の一端部は、ロープ固定部14に固定され、主ロープ10の他端部は、第1ロープ把持装置16に固定される。
 次に、可動支持機構7を縮小させて、可動支持機構7による第1機械室4Bの支持を解除する。そして、第1機械室4Bに連結された揚重機6を作動させて、第1機械室4Bを所定の高さ(図7に示す例では、梁101c)まで上昇させる。そして、第1機械室4Bが所定の高さまで上昇すると、揚重機6を停止させ、可動支持機構7を伸長させて、可動支持機構7を梁101cに載置させる。これにより、第1機械室4B及び第2機械室5Bを所定の高さまで上昇させることができる。
 次に、第2ロープ把持装置27のロープドラム27bの回転を固定し、上部把持部27cで主ロープ10を把持する。ここで、ロープドラム27bの回転を固定する前に、まず第2ロープ把持装置27の下部把持部27aで主ロープ10を把持する。そして、ロープドラム27bの位相を調整し、ロープドラム27bの回転を固定する。ロープドラム27bの回転の固定作業が完了すると、上部把持部27cで主ロープ10を把持させる。その後、下部把持部27aによる主ロープ10の把持を開放させる。
 次に、第1ロープ把持装置16による主ロープ10の把持を開放する。そして、乗りかご11と第1機械室4Bの連結を解除し、釣合おもり12を不図示のバッファから引き上げる。これにより、主ロープ10の延長作業及び工事用エレベーター1Bの運行階の拡張作業が完了する。
 その他の構成は、第1の実施の形態例にかかる工事用エレベーター1と同様であるため、それらの説明は省略する。この第2の実施の形態例にかかる工事用エレベーター1Bによっても、上述した第1の実施の形態例にかかる工事用エレベーター1と同様の作用効果を得ることができる。
3.第3の実施の形態例
 次に、図8から図10を参照して第3の実施の形態例にかかる工事用エレベーターについて説明する。
 図8は、第3の実施の形態例にかかる工事用エレベーターを示す概略構成図、図9及び図10は、第3の実施の形態例にかかる工事用エレベーターにおける主ロープの延長方法を示す図である。
 この第3の実施の形態例にかかる工事用エレベーターが、第1の実施の形態例にかかる工事用エレベーター1と異なる点は、機械室ユニットの構成である。そのため、ここでは、第1の実施の形態例にかかる工事用エレベーター1と共通する部分には、同一の符号を付して重複した説明を省略する。
 図8に示すように、工事用エレベーター1Cは、第1機械室4Cと第2機械室5Cからなる機械室ユニット3Cと、滑車19Cと、を有している。第1機械室4Cと第2機械室5Cは、一体に形成されている。第1機械室4Cには、巻上機9、主ロープ10の端部を固定するロープ固定部14、ロープリール15、第1ロープ把持装置16及び第2ロープ把持装置17が設置されている。第2機械室5Bには、制御盤8、テールコードリール20及び第3ロープ把持装置18が設置されている。
 制御盤8、巻上機9、ロープ固定部14、ロープリール15、第1ロープ把持装置16、第2ロープ把持装置17、第3ロープ把持装置18及びテールコードリール20の構成は、第1の実施の形態例にかかる工事用エレベーター1と同様であるため、その説明は省略する。
 滑車19Cは、滑車用揚重機6Cにより上下方向に沿って揚重(移動)可能に支持されている。すなわち、滑車19Cは、滑車用揚重機6Cにより機械室ユニット3Cから独立して移動する。また、滑車19Cは、回転可能に支持されており、主ロープ10が巻き掛けられている。主ロープ10における滑車19Cに対してロープリール15側、すなわち第1側Aには、第1ロープ把持装置16が配置される。そして、主ロープにおける滑車19Cに対して釣合おもり12及び乗りかご11側、第2側Bには、第2ロープ把持装置17及び第3ロープ把持装置18が配置される。
 図9に示すように、工事用エレベーター1Cの運転中では、第3ロープ把持装置18が作動して主ロープ10を把持しており、第1ロープ把持装置16及び第2ロープ把持装置17の把持部17aは、開放されている。そのため、主ロープ10の一端部は、ロープ固定部14に固定され、主ロープ10の他端部は、第3ロープ把持装置18に固定される。また、第2ロープ把持装置17のロープドラム17bは、回転不能に固定されているため、第3ロープ把持装置18にかかる荷重を低減させることができる。
 なお、第3の実施の形態例にかかる工事用エレベーター1Cにおいても、第3ロープ把持装置18を開放し、第1ロープ把持装置16によって主ロープ10を把持し、第1ロープ把持装置16で主ロープ10の他端部を固定してもよい。
 次に、図9及び図10を参照して第3の実施の形態例にかかる工事用エレベーター1Cにおける主ロープ10の延長方法について説明する。
 まず、図9に示すように、乗りかご11と機械室ユニット3Cをチェーン201で連結し、乗りかご11を固定する。また、釣合おもり12をピット100bまで下げて、ピット100bに設置した不図示のバッファの上に釣合おもり12を載置させる。
 次に、滑車19Cに連結された滑車用揚重機6Cを駆動し、滑車19Cのみを所定の高さまで上昇させる。このとき、主ロープ10における滑車19Cに対して第2側Bは、第3ロープ把持装置18によって固定されている。そのため、滑車19Cを上昇させることで、主ロープ10をロープリール15から引き出すことができる。また、主ロープ10は、滑車19Cによって折り返されているため、滑車19Cを上昇させる長さ(高さ)は、主ロープ10の延長分の約半分の長さでよい。
 なお、第3ロープ把持装置18で主ロープ10を把持する例を説明したが、これに限定されるものではなく、第3ロープ把持装置18を開放し、第2ロープ把持装置17の把持部17aで主ロープ10を固定してもよい。滑車19Cが所定の高さまで上昇すると、揚重機6を停止させて、滑車19Cを昇降路100内に仮固定する。
 図9に示す例では、乗りかご11と機械室ユニット3Cを連結し、釣合おもり12をバッファ上に載置させた例を説明したが、これに限定されるものではない。ここで、滑車19Cを上昇動作中における主ロープ10の第2側Bの一端部は、ロープ固定部14に固定され、第2側Bの他端部は、第3ロープ把持装置18に固定されている。そのため、滑車19Cの移動中においても、乗りかご11を機械室ユニット3Cに連結させずに、釣合おもり12をバッファに載置させなくてもよい。そして、滑車19Cの移動中においても、巻上機9を駆動させて、乗りかご11を使用してもよい。
 次に、機械室ユニット3Cを上昇させる場合、図10に示すように、第1ロープ把持装置16で主ロープ10を把持すると共に、第3ロープ把持装置18による主ロープ10の把持を開放する。また、第2ロープ把持装置17のロープドラム17bの固定を解除し、ロープドラム17bを回転可能にする。そのため、主ロープ10の一端部は、ロープ固定部14に固定され、主ロープ10の他端部は、第1ロープ把持装置16に固定される。
 ここで、乗りかご11を機械室ユニット3Cに連結させずに、釣合おもり12をバッファに載置させていない場合、上述した作業(工程)を行う前に、乗りかご11と機械室ユニット3Cを連結させると共に、釣合おもり12をバッファ上に載置させる。
 次に、可動支持機構7を縮小させて、可動支持機構7による機械室ユニット3Cの支持を解除する。そして、機械室ユニット3Cに連結された揚重機6を作動させて、機械室ユニット3Cを所定の高さまで上昇させる。そして、機械室ユニット3Cが所定の高さまで上昇すると、揚重機6を停止させ、可動支持機構7を伸長させて、可動支持機構7を梁101cに載置させる。これにより、機械室ユニット3Cを所定の高さまで上昇させることができる。
 次に、第2ロープ把持装置17のロープドラム17bの回転を固定し、第3ロープ把持装置18で主ロープ10を把持する。ここで、ロープドラム17bの回転を固定する前に、まず第2ロープ把持装置17の把持部17aで主ロープ10を把持する。そして、ロープドラム17bの位相を調整し、ロープドラム17bの回転を固定する。ロープドラム17bの回転の固定作業が完了すると、第3ロープ把持装置18で主ロープ10を把持させる。その後、第2ロープ把持装置17の把持部17aによる主ロープ10の把持を開放させる。
 次に、第1ロープ把持装置16による主ロープ10の把持を開放する。そして、乗りかご11と機械室ユニット3Cの連結を解除し、釣合おもり12を不図示のバッファから引き上げる。これにより、主ロープ10の延長作業及び工事用エレベーター1Cの運行階の拡張作業が完了する。
 その他の構成は、第1の実施の形態例にかかる工事用エレベーター1と同様であるため、それらの説明は省略する。この第3の実施の形態例にかかる工事用エレベーター1Cによっても、上述した第1の実施の形態例にかかる工事用エレベーター1と同様の作用効果を得ることができる。
 また、第1の実施の形態例にかかる工事用エレベーター1及び第2の実施の形態例にかかる工事用エレベーター1Bでは、滑車19が第2機械室5、5Bと共に上昇することで、主ロープ10がロープリール15から引き出される。すなわち、第1の実施の形態例にかかる工事用エレベーター1及び第2の実施の形態例にかかる工事用エレベーター1Bでは、機械室ユニット3、3Bを揚重する揚重機6が滑車用揚重機としての役割を有している。これに対して、第3の実施の形態例にかかる工事用エレベーター1Cでは、滑車19Cのみが機械室ユニット3Cとは独立して上昇することで、主ロープ10がロープリール15から引き出される。
4.第4の実施の形態例
 次に、図11を参照して第4の実施の形態例にかかる工事用エレベーターについて説明する。
 図11は、第4の実施の形態例にかかる工事用エレベーターを示す概略構成図である。
 第4の実施の形態例にかかる工事用エレベーターが、第1及び第3の実施の形態例にかかる工事用エレベーターと異なる点は、主ロープを乗りかご及び釣合おもりに架け渡す順番である。そのため、ここでは、第1及び第3の実施の形態例にかかる工事用エレベーター1、1Cと共通する部分には、同一の符号を付して重複した説明を省略する。
 図11に示すように、工事用エレベーター1Dは、機械室ユニット3Dと、乗りかご11と、釣合おもり12とを有している。機械室ユニット3Dには、主ロープ10が巻回されたロープリール15及び巻上機9等が配置されている。
 第4の実施の形態例にかかる工事用エレベーター1Dでは、主ロープ10が、ロープリール15から、滑車19を介して、乗りかご11に設けたかご側プーリ11a、巻上機9、釣合おもり12に設けたおもり側プーリ12aの順に巻き掛けられている。そして、おもり側プーリ12aから延在する主ロープ10の一端部は、機械室ユニット3Dのロープ固定部14に固定されている。
 その他の構成は、第1及び第3の実施の形態例にかかる工事用エレベーター1、1Cと同様であるため、それらの説明は省略する。この第4の実施の形態例にかかる工事用エレベーター1Dによっても、上述した第1及び第3の実施の形態例にかかる工事用エレベーター1、1Cと同様の作用効果を得ることができる。
5.第5の実施の形態例
 次に、図12を参照して第5の実施の形態例にかかる工事用エレベーターについて説明する。
 図12は、第5の実施の形態例にかかる工事用エレベーターを示す概略構成図である。
 第5の実施の形態例にかかる工事用エレベーターが、第2の実施の形態例にかかる工事用エレベーターと異なる点は、主ロープを乗りかご及び釣合おもりに架け渡す順番である。そのため、ここでは、第2の実施の形態例にかかる工事用エレベーター1Bと共通する部分には、同一の符号を付して重複した説明を省略する。
 図12に示すように、工事用エレベーター1Eは、機械室ユニット3Eと、乗りかご11と、釣合おもり12とを有している。機械室ユニット3Eには、主ロープ10が巻回されたロープリール15及び巻上機9等が配置されている。
 第5の実施の形態例にかかる工事用エレベーター1Eでは、主ロープ10が、ロープリール15から、滑車19を介して、乗りかご11に設けたかご側プーリ11a、巻上機9、釣合おもり12に設けたおもり側プーリ12aの順に巻き掛けられている。そして、おもり側プーリ12aから延在する主ロープ10の一端部は、機械室ユニット3Eのロープ固定部14に固定されている。
 その他の構成は、第2の実施の形態例にかかる工事用エレベーター1Bと同様であるため、それらの説明は省略する。この第5の実施の形態例にかかる工事用エレベーター1Eによっても、上述した第2の実施の形態例にかかる工事用エレベーター1Bと同様の作用効果を得ることができる。
 なお、本発明は上述しかつ図面に示した実施の形態に限定されるものではなく、請求の範囲に記載した発明の要旨を逸脱しない範囲内で種々の変形実施が可能である。
 なお、本明細書において、「平行」及び「直交」等の単語を使用したが、これらは厳密な「平行」及び「直交」のみを意味するものではなく、「平行」及び「直交」を含み、さらにその機能を発揮し得る範囲にある、「略平行」や「略直交」の状態であってもよい。
  1、1B、1C、1D、1E…工事用エレベーター、 2…支持部材、 3、3B、3C、3D、3E…機械室ユニット、 4、4B、4C…第1機械室、 4a…上部機械室、 4b…下部機械室、 5、5B、5C…第2機械室、 6…揚重機、 6C…滑車用揚重機、 7、21…可動支持機構、 8…制御盤、 9…巻上機、 10…主ロープ、 11…乗りかご(昇降体)、 11a…かご側プーリ、 12…釣合おもり(昇降体)、 12a…おもり側プーリ、 13…テールコード、 14…ロープ固定部、 15…ロープリール、 16…第1ロープ把持装置、 17、27…第2ロープ把持装置、 17a…把持部、 17b…ロープドラム、 18…第3ロープ把持装置、 19、19C…滑車、 20…テールコードリール、 27a…下部把持部、 27b…ロープドラム、 27c…上部把持部、 100…昇降路 100b…ピット、 101a、101b、101c、101d…梁

Claims (10)

  1.  主ロープが巻回されたロープリールと、
     前記ロープリールから引き出された前記主ロープが巻き掛けられ、建築構造物の昇降路を昇降する昇降体と、
     前記主ロープにおける前記ロープリールと前記昇降体との間に配置され、前記ロープリールから引き出された前記主ロープが巻き掛けられる滑車と、
     前記滑車に対して前記ロープリール側の前記主ロープを開放可能に把持する第1ロープ把持装置と、
     前記滑車に対して前記昇降体側の前記主ロープを開放可能に把持する第2ロープ把持装置と、を備え、
     前記滑車は、前記昇降体の昇降方向に沿って移動可能に支持される
     工事用エレベーター。
  2.  前記第2ロープ把持装置は、
     前記主ロープを開放可能に把持する把持部と、
     前記主ロープが少なくとも1回以上巻き掛けられるロープドラムと、を有し、
     前記ロープドラムは、回転を固定及び解除可能に支持される
     請求項1に記載の工事用エレベーター。
  3.  前記滑車に対して前記昇降体側の前記主ロープを開放可能に把持する第3ロープ把持装置をさらに備え、
     前記第3ロープ把持装置は、前記第2ロープ把持装置の前記ロープドラムよりも前記滑車側に配置される
     請求項2に記載の工事用エレベーター。
  4.  前記把持部は、前記ロープドラムよりも前記滑車側に配置された上部把持部と、
     前記ロープドラムよりも前記昇降体側に配置された下部把持部と、を有する
     請求項2に記載の工事用エレベーター。
  5.  前記主ロープの端部を固定するロープ固定部が設けられた機械室ユニットと、
     前記機械室ユニットを揚重可能に支持する揚重機と、をさらに備えた
     請求項1に記載の工事用エレベーター。
  6.  前記機械室ユニットは、
     前記ロープ固定部が設けられた第1機械室と、
     前記第1機械室よりも上下方向の上部に配置され、前記滑車が配置される第2機械室と、を有する
     請求項5に記載の工事用エレベーター。
  7.  前記第1機械室と前記第2機械室は、分割可能に連結される
     請求項6に記載の工事用エレベーター。
  8.  前記滑車は、前記第2機械室に回転可能に支持され、前記第2機械室と共に前記揚重機により揚重可能に支持される
     請求項7に記載の工事用エレベーター。
  9.  前記第2ロープ把持装置は、前記第1機械室に配置される
     請求項6から8のいずれか1項に記載の工事用エレベーター。
  10.  主ロープが巻回されたロープリールと、前記ロープリールから引き出された前記主ロープが巻き掛けられ、建築構造物の昇降路を昇降する昇降体と、前記主ロープにおける前記ロープリールと前記昇降体との間に配置され、前記ロープリールから引き出された前記主ロープが巻き掛けられる滑車と、前記滑車に対して前記ロープリール側の前記主ロープを開放可能に把持する第1ロープ把持装置と、前記滑車に対して前記昇降体側の前記主ロープを開放可能に把持する第2ロープ把持装置と、を備えた工事用エレベーターの主ロープの延長方法において、
     前記第2ロープ把持装置で前記主ロープを把持する工程と、
     前記第1ロープ把持装置による前記主ロープの把持を開放し、前記滑車を前記昇降体の昇降方向に沿って所定の高さまで上昇させ、前記ロープリールから前記主ロープを引き出す工程と、
     前記滑車を所定の高さまで上昇させた後、前記第1ロープ把持装置で前記主ロープを把持し、前記第2ロープ把持装置による前記主ロープの把持を開放する工程と、
     前記第2ロープ把持装置が設置された機械室ユニットを所定の高さまで上昇させる工程と、
     含む工事用エレベーターの主ロープの延長方法。
PCT/JP2020/039315 2020-10-20 2020-10-20 工事用エレベーター及び工事用エレベーターの主ロープの延長方法 WO2022085061A1 (ja)

Priority Applications (4)

Application Number Priority Date Filing Date Title
PCT/JP2020/039315 WO2022085061A1 (ja) 2020-10-20 2020-10-20 工事用エレベーター及び工事用エレベーターの主ロープの延長方法
EP20958614.8A EP4234471A1 (en) 2020-10-20 2020-10-20 Construction elevator and method for extending main rope of construction elevator
JP2022556845A JP7455221B2 (ja) 2020-10-20 2020-10-20 工事用エレベーター及び工事用エレベーターの主ロープの延長方法
CN202080105805.6A CN116323461A (zh) 2020-10-20 2020-10-20 施工用电梯及施工用电梯的主绳索的延长方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2020/039315 WO2022085061A1 (ja) 2020-10-20 2020-10-20 工事用エレベーター及び工事用エレベーターの主ロープの延長方法

Publications (1)

Publication Number Publication Date
WO2022085061A1 true WO2022085061A1 (ja) 2022-04-28

Family

ID=81290307

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2020/039315 WO2022085061A1 (ja) 2020-10-20 2020-10-20 工事用エレベーター及び工事用エレベーターの主ロープの延長方法

Country Status (4)

Country Link
EP (1) EP4234471A1 (ja)
JP (1) JP7455221B2 (ja)
CN (1) CN116323461A (ja)
WO (1) WO2022085061A1 (ja)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2024053036A1 (ja) * 2022-09-08 2024-03-14 株式会社日立製作所 工事用エレベーター

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5651995B2 (ja) * 1974-05-31 1981-12-09
JPH08133634A (ja) * 1994-11-04 1996-05-28 Otis Elevator Co ジャンプアップエレベーターのジャンプ方法
JP2001287881A (ja) * 2000-04-04 2001-10-16 Hitachi Building Systems Co Ltd 工事用エレベータおよびその据付方法
US20140367205A1 (en) * 2012-01-16 2014-12-18 Kone Corporation Method and elevator arrangement
WO2020044444A1 (ja) * 2018-08-28 2020-03-05 三菱電機株式会社 揚程延長式工事用エレベーター

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5651995B2 (ja) * 1974-05-31 1981-12-09
JPH08133634A (ja) * 1994-11-04 1996-05-28 Otis Elevator Co ジャンプアップエレベーターのジャンプ方法
JP2001287881A (ja) * 2000-04-04 2001-10-16 Hitachi Building Systems Co Ltd 工事用エレベータおよびその据付方法
US20140367205A1 (en) * 2012-01-16 2014-12-18 Kone Corporation Method and elevator arrangement
WO2020044444A1 (ja) * 2018-08-28 2020-03-05 三菱電機株式会社 揚程延長式工事用エレベーター

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2024053036A1 (ja) * 2022-09-08 2024-03-14 株式会社日立製作所 工事用エレベーター

Also Published As

Publication number Publication date
JPWO2022085061A1 (ja) 2022-04-28
JP7455221B2 (ja) 2024-03-25
CN116323461A (zh) 2023-06-23
EP4234471A1 (en) 2023-08-30

Similar Documents

Publication Publication Date Title
US8291568B2 (en) Method of installing an elevator
EP2804828B1 (en) Method and elevator arrangement
JP5577275B2 (ja) 床高さ調節機構付きエレベーター
KR20070045207A (ko) 엘리베이터를 설치하는 방법 및 엘리베이터
KR102308534B1 (ko) 기계실이 필요없는 로프식 자체구동 엘리베이터
JP6813123B2 (ja) エレベーターの揚程延長技術の適用方法
JPH07237861A (ja) 昇降装置
JPH09263372A (ja) エレベータかご天井昇降装置
WO2022085061A1 (ja) 工事用エレベーター及び工事用エレベーターの主ロープの延長方法
KR102308532B1 (ko) 기계실이 필요없는 로프식 자체구동 경사형 엘리베이터
WO2020142001A1 (en) A moveable platform
WO2020044444A1 (ja) 揚程延長式工事用エレベーター
JP2000344430A (ja) ダブルデッキエレベータ
CN110191855B (zh) 电梯的安装方法
JP6798644B2 (ja) エレベーターの釣合いおもりの揚重装置および揚重方法
KR20040007690A (ko) 엘리베이터 장치의 승강기구 및 승강방법
JP2002173281A (ja) エレベータ
WO2023084721A1 (ja) 工事用エレベーター及び工事用エレベーターのコンペンロープの延長方法
JP6336225B2 (ja) エレベータ装置
JP2008162769A (ja) エレベータの乗客救出装置
WO2022230140A1 (ja) エレベーターおよび昇降行程延伸方法
WO2015125288A1 (ja) エレベーター装置
JP6694598B2 (ja) ダブルデッキエレベータ及びその駆動方法
JPH0480188A (ja) ダブルデッキエレベータ
JP2000318954A (ja) 可変式ダブルデッキエレベータ

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20958614

Country of ref document: EP

Kind code of ref document: A1

ENP Entry into the national phase

Ref document number: 2022556845

Country of ref document: JP

Kind code of ref document: A

NENP Non-entry into the national phase

Ref country code: DE

ENP Entry into the national phase

Ref document number: 2020958614

Country of ref document: EP

Effective date: 20230522