WO2014030483A1 PCT/JP2013/070109 JP2013070109W WO2014030483A1 WO 2014030483 A1 WO2014030483 A1 WO 2014030483A1 JP 2013070109 W JP2013070109 W JP 2013070109W WO 2014030483 A1 WO2014030483 A1 WO 2014030483A1
Authority
WO
WIPO (PCT)
Prior art keywords
reinforcement
existing
reinforcing
column
shaped
Prior art date
Application number
PCT/JP2013/070109
Other languages
English (en)
French (fr)
Inventor
豊範 野田
俊比古 飯島
Original Assignee
名工建設株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 名工建設株式会社 filed Critical 名工建設株式会社
Priority to CN201380042929.4A priority Critical patent/CN104541006B/zh
Priority to KR20157006858A priority patent/KR20150033749A/ko
Priority to KR1020157003554A priority patent/KR101587387B1/ko
Publication of WO2014030483A1 publication Critical patent/WO2014030483A1/ja

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/92Protection against other undesired influences or dangers
    • E04B1/98Protection against other undesired influences or dangers against vibrations or shocks; against mechanical destruction, e.g. by air-raids
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/025Structures with concrete columns
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/027Preventive constructional measures against earthquake damage in existing buildings

Definitions

  • This invention relates to the seismic reinforcement method in the seismic reinforcement work for existing buildings.
  • a general method includes a method of adding a reinforced concrete wall and a method of adding a steel brace.
  • the method of adding reinforced concrete walls has problems such as affecting indoor lighting because the openings of existing buildings are covered with walls. Therefore, when it is desired to open the interior of a building, it is common to perform seismic reinforcement with a method of adding steel braces, but part of the opening is blocked and the view from the window is damaged. There is a problem such as a step in the floor.
  • Patent Documents 1 to 3 describe that the divided pillars are transported inside the inner peripheral surface of the opening of the existing column beam frame composed of the columns and beams of the existing building. A method of inserting and inserting a reinforcing unit that facilitates installation is disclosed.
  • the reinforcement unit is inserted and fitted inside the inner peripheral surface of the opening of the existing column beam frame of the existing building. A part of the opening of the beam frame is blocked, and the opening area of the opening of the existing column beam frame is reduced. Therefore, when the opening of the existing column beam frame is like an entrance to a building, there is a risk that it may hinder people from entering and exiting.
  • windows and doors are generally installed in the opening of the existing column beam frame. However, if a part of the opening of the existing column beam frame is blocked by the reinforcement unit, sunlight is blocked by the reinforcement unit. End up. Therefore, the influence on the habitability and lighting of the building after reinforcement may not be sufficiently reduced.
  • the installation specifications of windows and doors installed in the openings of the existing column beam frame are diverse, and depending on the installation specifications of the windows and doors, reinforcement is made inside the inner peripheral surface of the opening of the existing column beam frame.
  • reinforcement is made inside the inner peripheral surface of the opening of the existing column beam frame.
  • the present invention has been made to solve the above-mentioned problems, and it is an object to provide an earthquake-resistant reinforcement method that can sufficiently reduce the habitability, functionality, and lighting of buildings after reinforcement.
  • the seismic reinforcement method in one aspect of the present invention made to solve the above problems is a method of seismic reinforcement with a unit that reinforces an existing column beam frame composed of existing columns and existing beams of an existing building,
  • the seismic reinforcement method of assembling a gate-type reinforcement unit by connecting a pair of L-shaped reinforcing pieces and a pair of I-shaped reinforcing pieces with bolts, column reinforcement main bars arranged in parallel to the columns outside the existing columns;
  • a column reinforcement striking step in which a column reinforcement striking portion having a reinforcing band wound in a direction perpendicular to the column reinforcing main reinforcement is provided by an anchor, and arranged outside the existing beam in parallel with the beam.
  • a beam reinforcement striking step in which a beam reinforcement striking portion in which a beam reinforcement main reinforcing bar and a reinforcing reinforcing bar wound in a direction orthogonal to the beam reinforcing main reinforcement are installed is increased by an anchor, the column reinforcement striking portion and the beam reinforcement For extra hits
  • the pair of L-shaped reinforcing pieces and the pair of I-shaped reinforcing pieces are anchored, and the column reinforcing striking portion, the beam reinforcing striking portion, the pair of L-shaped reinforcing pieces and the pair of I-shaped A reinforcing piece fixing step of injecting an adhesive resin between the reinforcing pieces.
  • the reinforcement piece is fixed to the column reinforcement striking portion that is struck outside the existing column and the beam reinforcement striking portion that is struck outside the existing beam, the reinforcement composed of the reinforcement piece It can suppress that the opening area of the opening part of the existing column beam frame becomes small with a unit. Therefore, when the opening of the existing column beam frame is like an entrance to a building, it is difficult for people to enter and exit. Moreover, it can suppress that the sunlight taken in into the room
  • the beam reinforcing striking portion includes a space portion at a position corresponding to a portion where the exhaust sleeve is disposed.
  • the exhaust sleeve since the exhaust sleeve is not blocked by the beam reinforcement striking portion, the exhaust from the interior of the building can be discharged to the outside of the building through the exhaust sleeve without any problem. Therefore, the functionality of the existing building can be maintained. And even if there is a part that is not overstrung in part of the beam reinforcement striking part in this way, as described above, the column reinforcement striking with the column reinforcement main reinforcement and the reinforcement strips installed inside the existing pillar Reinforcement unit maintains seismic strength under the structure in which the beam reinforcement striking part with the beam reinforcement main bar and reinforcement bar on the outside of the beam and the existing beam is added, and the exhaust sleeve is arranged Since the size of the part that is made is very limited, it is possible to ensure sufficient strength of seismic reinforcement.
  • the height of the beam reinforcing increased portion is smaller than the height of the existing beam.
  • the seismic reinforcement method in another aspect of the present invention made to solve the above problems is a method of seismically reinforcing an existing column beam frame constructed from an existing column and an existing beam with respect to an existing building by a reinforcement unit.
  • the seismic reinforcement method of assembling a gate-type reinforcement unit by combining a pair of L-type reinforcement pieces and a pair of I-type reinforcement pieces the pair of L-type reinforcement pieces and the pair of I-type reinforcement pieces Are provided with studs, and the pair of I-shaped reinforcement pieces are arranged along the existing pillar outside the existing column, and the pair of L-shaped reinforcement is arranged outside the existing beam.
  • a piece is arranged along the existing pillar and the existing beam, a reinforcing piece assembling step for assembling the pair of I-shaped reinforcing pieces and the pair of L-shaped reinforcing pieces, and after the reinforcing piece assembling step,
  • the column reinforcing main bars are arranged outside the existing columns so that the studs of the pair of I-shaped reinforcing pieces and the studs on one side of the pair of L-shaped reinforcing pieces along the existing columns are provided internally.
  • the reinforcement unit includes the column reinforcement increased portion that is placed in the column reinforcement reinforcement portion outside the existing column, and the beam reinforcement increase portion that is placed in the beam reinforcement reinforcement portion outside the existing beam.
  • the beam reinforcement increased portion provided in the beam reinforcing reinforcement portion is provided close to the upper end side of the existing beam, and the height of the beam reinforcement increased portion is equal to the height of the existing beam. It is preferable that the height is smaller.
  • the reinforcement unit can surely suppress the opening area of the opening of the existing column beam frame from becoming smaller, and can sufficiently suppress the influence on habitability, functionality, and lighting. That is, in the case where the opening of the existing column beam frame is an entrance / exit of an existing building, it is difficult for people to enter and exit even after the existing building is reinforced. Moreover, it can suppress that the sunlight taken in into the room
  • the height of the beam-reinforced striking portion is not more than 1/2 the height of the beam of the existing beam.
  • the reinforcing piece that is one side along the existing beam (one side of the reinforcing unit) is directed from the lower surface of the existing beam on the upper beam side toward the opening of the existing column beam frame. It can be suppressed from protruding. Therefore, for example, existing buildings are apartment buildings, etc., and seismic reinforcement is applied to existing buildings with structures with large spans in the direction of the existing beams in the column beam frame at the border between the veranda and the room. When applied, the influence on the habitability, functionality, and daylighting by the reinforcing unit is suppressed to a small extent, and the existing building can be effectively seismically reinforced. In particular, in recent years, there has been a demand for development of seismic reinforcement technology that can sufficiently ensure such comfort, functionality, and daylighting as customer needs from residents of apartment houses, etc. Can fully meet such customer needs.
  • the beam reinforcing striking portion includes a space portion at a position corresponding to a portion where the exhaust sleeve is disposed.
  • the exhaust sleeve is not blocked by the beam reinforcement striking portion, and can maintain the function of exhausting the exhaust from the room of the existing building to the outside through the exhaust sleeve. Sex is maintained.
  • the portion where the exhaust sleeve is disposed is extremely limited in size, even if there is a portion that is not added to the beam reinforcement hitting portion due to the space portion, Existing buildings that have been seismically reinforced can ensure sufficient seismic strength.
  • each of the pair of L-shaped reinforcing pieces and the pair of I-shaped reinforcing pieces is a precast concrete member formed by integrally forming a steel material as a core material and concrete, and the stud is fixed to the steel material. It is preferable that
  • the stud when the stud is fixed to the steel material at the seismic reinforcement site of the existing building, there are many restrictions on the space and the stud cannot be fixed efficiently. If the stud is fixed, the productivity of the stud fixing is improved, so that the cost of the reinforcing unit can be reduced. Moreover, when fixing a stud to steel materials by welding, it is not necessary to bring a welding machine and a curing sheet to an earthquake-proof reinforcement site only for welding a stud to steel materials. In addition, it is not necessary to place a qualified person of welding technology on the seismic reinforcement site just to weld the stud to the steel material.
  • the seismic strengthening method of the present invention does not require the above-mentioned fixed required time at all, unlike the adhesive bonding method that requires a fixed required time until the strength of the adhesive is developed. Therefore, if the stud is fixed to the steel material at the factory in advance, it is possible to immediately start preparation for the next reinforcement piece assembly process for the reinforcement piece with the stud carried into the seismic reinforcement site. It can contribute to shortening the construction period of seismic reinforcement work.
  • the influence on the habitability, functionality, and lighting of the building after reinforcement is sufficiently reduced.
  • Example 1 of Embodiment 1 it is the figure which showed the schematic front of the reinforcement unit.
  • Example 1 of Embodiment 1 it is a schematic front view of the reinforcement piece which comprises a reinforcement unit. It is a figure which shows performing the existing finish removal in Example 1 of Embodiment 1.
  • FIG. 1 of Embodiment 1 it is a figure which shows performing anchor drilling etc. with respect to the existing pillar and the existing beam.
  • Example 1 of Embodiment 1 it is a figure which shows performing a roughening and bar arrangement
  • Example 1 of Embodiment 1 it is a figure which shows performing concrete placement in the part which is to be struck out.
  • Example 1 of Embodiment 1 it is a figure which shows performing anchor drilling to a column reinforcement
  • Example 1 of Embodiment 1 it is a figure which shows attaching the left type I reinforcement piece.
  • Example 1 of Embodiment 1 it is a figure which shows attaching the left side L-shaped reinforcement piece.
  • FIG. 10 is a view of the flange portion of the joint portion as seen through the column reinforcement striking portion from the left side of FIG. 9.
  • Example 1 of Embodiment 1 it is a figure which shows attaching the right type I reinforcement piece.
  • Example 1 of Embodiment 1 it is a figure which shows attaching the L type reinforcement piece of the right side.
  • Example 1 of Embodiment 1 it is a figure which shows inject
  • Example 1 of Embodiment 1 it is a figure which shows pouring grout into the joint part etc. of an I-type reinforcement piece and an L-type reinforcement piece.
  • FIG. 16 is a cross-sectional view taken along line AA of FIG.
  • FIG. 16 is a sectional view taken along line BB in FIG. It is sectional drawing corresponding to FIG.
  • FIG. 16 in the example which changed the arrangement position of an I-type reinforcement piece and an L-type reinforcement piece.
  • FIG. 17 in the example which changed the arrangement position of an I-type reinforcement piece and an L-type reinforcement piece.
  • FIG. 17 It is a schematic front view of the column reinforcement striking part, the beam reinforcement striking part, the reinforcement unit, and their periphery after the completion of the seismic reinforcement work by the seismic strengthening method of Example 2 of the first embodiment. It is the figure which showed the schematic front of the reinforcement unit of the modification 1 of Embodiment 1.
  • FIG. It is a figure explaining the earthquake-proof reinforcement construction method concerning the modification 2 of Embodiment 1, and is a schematic front view equivalent to FIG.
  • FIG. 23 is a cross-sectional view taken along line FF in FIG. 22.
  • FIG. 23 is a cross-sectional view taken along line FF in FIG. 22.
  • FIG. 23 is a cross-sectional view taken along the line GG in FIG. 22. It is a front view which shows schematically the reinforcement unit which concerns on Example 1 among Embodiment 2, and is a figure shown in the state by which the reinforcement piece was assembled.
  • FIG. 26 is a front view of the reinforcing unit shown in FIG. 25, showing the reinforcing piece in an exploded state.
  • FIG. 27 is a cross-sectional view of a reinforcing piece that constitutes a reinforcing unit according to Example 1 in Embodiment 2, and is a cross-sectional view corresponding to a cross section taken along arrows HH and II shown in FIG. 26.
  • FIG. 31 is a process diagram subsequent to FIG. 30, and is a fourth process diagram illustrating a state in which the left I-type reinforcement piece and the left L-type reinforcement piece are to be joined.
  • FIG. 32 is a process diagram subsequent to FIG. 31, and is a fifth process diagram illustrating a state in which the right I-shaped reinforcement piece is disposed after the left I-shaped reinforcement piece and the left L-shaped reinforcement piece are joined.
  • FIG. 34 is a process diagram following FIG. 33, showing that the right L-shaped reinforcing piece is to be joined to the right I-shaped reinforcing piece and the left L-shaped reinforcing piece joined to the left I-shaped reinforcing piece.
  • FIG. 35 is a process drawing subsequent to FIG. 34, and is a seventh process chart showing a state in which the left and right I-shaped reinforcement pieces and the left and right L-shaped reinforcement pieces are joined to form a gate shape.
  • FIG. 36 is a process diagram subsequent to FIG. 35, and is an eighth process diagram illustrating a column reinforcing bar arranging step and a beam reinforcing bar arranging step of the seismic strengthening method according to Example 1 in Embodiment 2.
  • 36 is a process diagram subsequent to FIG. 36, and is a ninth process diagram illustrating a reinforcement unit fixing process of the earthquake-proof reinforcement method according to Example 1 in Embodiment 2.
  • FIG. FIG. 38 is a process diagram following FIG.
  • FIG. 40 is a cross-sectional view taken along the line KK in FIG.
  • FIG. 40 is a cross-sectional view taken along line LL in FIG.
  • FIG. 40 is an explanatory view showing a first case in which the position where the reinforcing unit according to Example 1 is arranged in the existing column beam frame is changed in the second embodiment, and is a cross-section corresponding to the position of the arrow KK in FIG.
  • FIG. 40 is an explanatory view showing a second case in which the position where the reinforcing unit according to Example 1 is arranged on the existing column beam frame is changed in the second embodiment, and is a cross-section corresponding to the position of the arrow KK in FIG.
  • FIG. 40 is a front view schematically showing an existing building that is seismically reinforced by the seismic reinforcement method according to Example 2 in Embodiment 2, and is an explanatory view corresponding to FIG. 39. It is a front view which shows schematically the reinforcement unit which concerns on the modification of Example 1, 2 among Embodiment 2, and is explanatory drawing equivalent to FIG.
  • Embodiments 1 and 2 embodying the seismic reinforcement method according to the present invention will be described with reference to the drawings.
  • Examples 1 and 2 and Modifications 1 and 2 are given in Embodiment 1
  • Examples 1 and 2 and Modifications are given in Embodiment 2.
  • Example 1 ⁇ Example 1> First, Example 1 will be described. First, the reinforcing unit 10 will be described.
  • FIG. 1 is a diagram showing a schematic front view of the reinforcing unit 10.
  • FIG. 2 is a schematic front view of the reinforcing piece constituting the reinforcing unit 10.
  • the reinforcing unit 10 is connected so as to extend two L-shaped reinforcing pieces 12 composed of two orthogonal sides and extend one side of each of the two L-shaped reinforcing pieces 12.
  • Two I-shaped reinforcing pieces 14 are provided.
  • the reinforcement unit 10 is comprised by the portal shape by joining symmetrically so that the front-end
  • the reinforcing unit 10 is a reinforcing member in which concrete is wound around a steel frame.
  • the L-shaped reinforcing piece 12 is formed in an L shape.
  • the L-shaped reinforcement piece 12 includes an upper side portion 16 disposed in a beam reinforcement increased portion 64 (see FIG. 6 and the like) described later, and a column reinforcement increased portion 62 (described in FIG. 6 and the like) orthogonal to the upper side portion 16 and described later. And a vertical column portion 18 arranged in the reference).
  • the I-type reinforcement piece 14 is formed in a prismatic shape.
  • the I-shaped reinforcing piece 14 is disposed in the column reinforcement striking portion 62 at the time of the seismic reinforcement, and the upper end is connected to the lower end of the vertical column portion 18 of the L-shaped reinforcing piece 12.
  • the I-type reinforcement piece 14 is provided with the base plate 20 mounted in the balcony slab 36 (refer FIG. 3 etc.) mentioned later in a lower end.
  • the L-shaped reinforcing piece 12 and the I-shaped reinforcing piece 14 are so-called steel concrete in which concrete is wound around a steel material as a bone.
  • H-type steel is used for the steel material, and the concrete wound around the steel material may be used for general SRC (Steel Reinforced Concrete) construction or may be a fiber reinforced concrete.
  • the H-shaped steel 22 that becomes the bone of the L-shaped reinforcing piece 12 is composed of two sides welded so as to be orthogonal to each other. Further, the H-shaped steel 24 that becomes the bone of the I-type reinforcing piece 14 is linear.
  • the base plate 20 is placed on the lower end of the H-shaped steel 24 of the I-type reinforcing piece 14 so that the lower end of the H-shaped steel 24 abuts on the base plate 20, and is fixed by welding.
  • a bolt hole 26 is provided in each of the end of the H-shaped steel 22 of the L-shaped reinforcing piece 12 and the end of the H-shaped steel 24 of the I-shaped reinforcing piece 14.
  • the position and number of the bolt holes 26 are not particularly limited.
  • the seismic reinforcement method according to the first embodiment is roughly divided into a step-up process and a reinforcement piece fixing process.
  • the additional punching process will be described.
  • the existing finish is removed.
  • a finishing member for example, an outer wall material such as a tile or a painting
  • an existing column beam frame 34 composed of the existing column 30 and the existing beam 32 of the existing building 1
  • remove More specifically, with respect to the existing pillar 30, the finishing member in the portion to be struck out in the portion excluding the balcony slab 36 on the outer surface (the front side in FIG. 3) is removed. Further, with respect to the existing beam 32, the finishing member in the additional hitting portion 40 is removed on the outer side (the front side in FIG.
  • the additional hitting portion 40 is a portion on the side of the balcony slab 36 in the existing beam 32 and a portion excluding the periphery of the exhaust sleeve 46.
  • rebar exploration and anchor drilling are performed. Specifically, the reinforcing bars inside the existing columns 30 and the existing beams 32 are searched, and the anchor holes 48 are formed as shown in FIG. 4 while avoiding the reinforcing bars inside the existing columns 30 and the existing beams 32. To do. More specifically, a plurality of anchor holes 48 are formed in the additional hitting portion 38 of the existing column 30 and the additional hitting portion 40 of the existing beam 32. At this time, a through-hole 50 is formed in the balcony slab 36 so as to penetrate in the thickness direction of the balcony slab 36 (vertical direction in FIG. 4).
  • various reinforcing bars are arranged in the anchor hole 48 (see FIG. 4) in the additional striking portion 38 of the existing column 30 and the planned striking portion 40 of the existing beam 32.
  • a reinforcement reinforcing bar 52 of a reinforcing bar arranged in parallel to the existing column 30 and a reinforcement of a reinforcing bar wound in a direction orthogonal to the reinforcing pillar 52 of the column are provided in the additional hitting portion 38.
  • a band 54 is arranged.
  • a beam reinforcing main bar 56 arranged in parallel with the existing beam 32 and a reinforcing bar 58 wound in the direction orthogonal to the beam reinforcing main bar 56 are arranged in the additional hitting portion 40.
  • the roughening is performed on the additional hitting planned portion 38 of the existing pillar 30 and the additional hitting planned portion 40 of the existing beam 32.
  • the “meshing” is an operation of forming a rough surface on the surface of the old concrete to improve the integrity with the new concrete to be succeeded later.
  • a sheath tube 60 is installed below the through hole 50 of the balcony slab 36.
  • concrete placement is performed. Specifically, as shown in FIG. 6, concrete is driven into the additional striking portion 38 (see FIG. 5) of the existing pillar 30 and the striking portion 40 (see FIG. 5) of the existing beam 32 to reinforce the column.
  • the increased hitting part 62 and the beam reinforcing increased hitting part 64 are formed.
  • a space 66 is formed in the existing beam 32 at a location corresponding to the site where the exhaust sleeve 46 is disposed so as not to form the beam reinforcement hitting portion 64.
  • the column reinforcement striking portion 62 in which the column reinforcing main bars 52 and the reinforcing strips 54 are provided outside the existing columns 30 (the front side of the drawing in FIG. 6) is increased by the anchors.
  • a column-strike process is performed.
  • a beam augmentation unit in which a beam reinforcement striking portion 64 in which a beam reinforcing main bar 56 and a reinforcing bar 58 are provided on the outside of the existing beam 32 (the front side in FIG. 6) is increased by an anchor.
  • a punching process is also performed.
  • beam reinforcement is provided at a location corresponding to the portion where the exhaust sleeve 46 is disposed in the existing beam 32.
  • the additional hitting portion 64 is not increased.
  • the additional striking step concrete is driven into a portion of the existing beam 32 to be reinforced to form a beam reinforcing increased portion 64.
  • the height (vertical width) of the beam reinforcement hitting portion 64 is made smaller than the height (vertical width) of the existing beam 32. More specifically, as shown in FIG. 6 and FIG. 16 to be described later, the height h of the beam reinforcement hitting portion 64 is made smaller than the height H of the portion below the balcony slab 36 in the existing beam 32. As described above, the additional punching process is performed.
  • anchor drilling is performed on the column reinforcement striking portion 62 and the beam reinforcement striking portion 64.
  • anchor holes 68 are formed in the column reinforcing hitting portion 62 and the beam reinforcing hitting portion 64 with a concrete drill.
  • four anchor holes 68 are formed in each of the left and right column reinforcing increased portions 62 and the beam reinforcing increased portion 64, but the number of anchor holes 68 is as follows.
  • the through bolt 70 is disposed inside the through hole 50 and the sheath tube 60. At this time, it is preferable that the construction of the reinforcing unit 10 has already been completed on the lower floor.
  • the left I-shaped reinforcement piece 14 is attached. Specifically, as shown in FIG. 8, the I-type reinforcement piece 14 is attached by moving the I-type reinforcement piece 14 toward the left column reinforcement striking portion 62 and temporarily fastening the through bolts 70 with the base plate 20. .
  • the left L-shaped reinforcing piece 12 is attached. Specifically, as shown in FIG. 9, the L-shaped reinforcing piece 12 is arranged on the upper side of the I-shaped reinforcing piece 14 and close to the left column reinforcing hitting portion 62 and the beam reinforcing hitting portion 64. Then, the bolt is temporarily tightened via the plate 74 at the joint portion 71 (H-shaped steel 22) of the L-shaped reinforcing piece 12 and the joint portion 72 (H-shaped steel 24) of the I-shaped reinforcing piece 14.
  • the bolts are temporarily tightened via the plate 77 also in the flange portion 73 ⁇ / b> A of the joint portion 71 and the flange portion 75 ⁇ / b> A of the joint portion 72.
  • the bolts are also temporarily tightened via the plate 79 at the flange portion 73B of the joint portion 71 and the flange portion 75B of the joint portion 72.
  • the L-shaped reinforcing piece 12 is attached.
  • the L-shaped reinforcing piece 12 is supported by the support member 76.
  • FIG. 10 shows a view of the flange portion 73 ⁇ / b> B of the joint portion 71 and the flange portion 75 ⁇ / b> B of the joint portion 72 as seen through the column reinforcement striking portion 62 from the left side of FIG. 9.
  • a hole 81 for anchoring is formed on the left side (inner side) of the flange portion 73B of the joint portion 71 and the flange portion 75B of the joint portion 72.
  • the right I-shaped reinforcement piece 14 is attached. Specifically, as shown in FIG. 11, the new I-type reinforcing piece 14 is brought to the right column reinforcement striking portion 62, and the through bolt 70 is temporarily tightened with the base plate 20, whereby the I-type reinforcing piece 14. Install.
  • the L-shaped reinforcing piece 12 on the right side is attached, and the bolts are finally tightened and anchors are fixed.
  • the new L-shaped reinforcing piece 12 is brought close to the right column reinforcing striking portion 62 and the beam reinforcing striking portion 64 above the right I-shaped reinforcing piece 14. Arrange. At this time, the L-shaped reinforcing piece 12 is supported by the support member 76.
  • the bolt is finally tightened through the plate 74 at the joint portion 71 of the left L-shaped reinforcing piece 12 and the joint portion 72 of the left I-shaped reinforcing piece 14.
  • the bolts are finally tightened via the plate 77 also in the flange portion 73 ⁇ / b> A of the joint portion 71 and the flange portion 75 ⁇ / b> A of the joint portion 72.
  • the bolts are finally tightened via the plate 79 at the flange portion 73 ⁇ / b> B of the joint portion 71 and the flange portion 75 ⁇ / b> B of the joint portion 72.
  • the bolt is finally tightened via the plate 74 at the joint portion 71 of the right L-shaped reinforcing piece 12 and the joint portion 72 of the right I-shaped reinforcing piece 14.
  • the bolts are finally tightened via the plate 77 also in the flange portion 73 ⁇ / b> A of the joint portion 71 and the flange portion 75 ⁇ / b> A of the joint portion 72.
  • the bolts are finally tightened via the plate 79 at the flange portion 73 ⁇ / b> B of the joint portion 71 and the flange portion 75 ⁇ / b> B of the joint portion 72.
  • the bolts are finally tightened via the plate 80 at the joint portion 78 (H-shaped steel 22) of the L-shaped reinforcement piece 12 on the right side and the joint portion 78 of the L-type reinforcement piece 12 on the left side.
  • the reinforcing unit 10 is preferably constructed integrally because it is possible to increase the strength when it is configured integrally.
  • a welding machine and a power source are required at the site, and there is a problem such as extra costs. Therefore, it is more advantageous to be able to fasten with bolts or the like.
  • the reinforcing unit 10 composed of the pair of L-shaped reinforcing pieces 12 and the pair of I-shaped reinforcing pieces 14 is attached to the column reinforcing hitting portion 62 and the beam reinforcing hitting portion 64 by an adhesive anchor.
  • a cutting bolt 82 is attached together with the chemical to the flange portion 73B of the joint portion 71 and the flange portion 73 of the joint portion 72.
  • the chemical is cured.
  • the type of anchor is not particularly limited as long as it can integrally construct a protruding object on a column or beam, such as a hole-in anchor or a chemical anchor.
  • an epoxy resin putty material is used to inject an epoxy resin into the gap between the column reinforcement striking portion 62 and the reinforcement unit 10 or the gap between the beam reinforcement striking portion 64 and the reinforcement unit 10 as will be described later. Seal with.
  • an epoxy resin that is an adhesive resin is injected.
  • the gap between the column reinforcement increased portion 62 and the reinforcement unit 10 or the gap between the beam reinforcement increased portion 64 and the reinforcement unit 10 is sealed with an epoxy resin putty material. And inject epoxy resin.
  • the resin part 84 is formed in the three directions of the column reinforcement hitting part 62 and the beam reinforcement hitting part 64.
  • epoxy resin is also injected under the base plate 20 of the I-type reinforcing piece 14.
  • grout is injected into the joint. Specifically, the joint part 71 (see FIG. 13) of the L-shaped reinforcement piece 12 and the joint part 72 (see FIG. 13) of the I-type reinforcement piece 14 and the joint part 78 ( As shown in FIG. 14, a grout 88 is injected into the joint portion 86 (see FIG. 13) at the lower ends of the left and right I-shaped reinforcement pieces 14.
  • the grout 88 may be composed of non-shrink mortar, but in this embodiment, fiber reinforced concrete is used in order to increase the strength of the reinforcing unit 10.
  • the outer wall is finished by attaching finishing members or painting the surfaces of the column reinforcement striking portion 62, the beam reinforcement striking portion 64, and the reinforcement unit 10. .
  • the pillar reinforcement striking portion 62, the beam reinforcement striking portion 64, and the reinforcement unit 10 are made inconspicuous, so that it does not matter that the building is seismically reinforced in appearance.
  • the AA cross-sectional view of FIG. 15 is shown in FIG. 16, and the BB cross-sectional view of FIG. 15 is shown in FIG.
  • the L-shaped reinforcing piece 12 is anchored to the inside of the beam reinforcement hitting portion 64 using a dimension bolt 82 and a reinforcing plate 90 via a resin portion 84.
  • the I-type reinforcing piece 14 is anchored to the inner side of the column reinforcing hitting portion 62 using a dimension bolt 82 and a reinforcing plate 92 via a resin portion 84.
  • FIG. 16 the L-shaped reinforcing piece 12 is anchored to the inside of the beam reinforcement hitting portion 64 using a dimension bolt 82 and a reinforcing plate 90 via a resin portion 84.
  • the I-type reinforcing piece 14 is anchored to the inner side of the column reinforcing hitting portion 62 using a dimension bolt 82 and a reinforcing plate 92 via a resin portion 84.
  • the position 31 of the existing beam 32 is indicated by a virtual line, and the surface 31 on the outer side of the existing column 30 (outside, lower side in FIG. 17) is outside the existing beam 32 (outside, in FIG. 17). It is flush with the lower surface 33.
  • the pair of L-shaped reinforcing pieces 12 and the pair of I-shaped reinforcing pieces 14 are anchored to the column reinforcing increased portion 62 and the beam reinforcing increased portion 64, and the column An epoxy resin is injected between the reinforcing hitting portion 62, the beam reinforcing hitting portion 64, the pair of L-shaped reinforcing pieces 12, and the pair of I-shaped reinforcing pieces 14.
  • the seismic reinforcement method of this embodiment is completed.
  • the first embodiment is a method of seismic reinforcement with a unit that reinforces an existing column beam frame 34 composed of an existing column 30 and an existing beam 32 of an existing building 1, and includes a pair of L-shaped reinforcing pieces 12 and a pair of
  • the seismic reinforcement method of assembling the portal reinforcement unit 10 by joining the I-type reinforcement piece 14 with bolts, a column reinforcement main bar 52 arranged in parallel to the existing column 30 outside the existing column 30, and a column reinforcement main bar 52
  • a column reinforcement striking step in which a column reinforcement striking portion 62 having a reinforcing band 54 wound in an orthogonal direction is added by an anchor, and a beam disposed outside the existing beam 32 in parallel with the existing beam 32
  • a beam reinforcement striking step in which a beam reinforcement striking portion 64 having a reinforcement main reinforcement 56 and a reinforcement reinforcement 58 wound in a direction orthogonal to the beam reinforcement principal reinforcement 56 is added by an anchor, a column reinforcement striking portion 62 and a beam Reinforcement hitting part 6
  • the strength of the existing building 1 can be increased. Toughness can be improved.
  • a pair of L-shaped reinforcing pieces 12 and a pair of I-shaped reinforcing pieces are provided for the column reinforcing striking portion 62 that strikes outside the existing column 30 and the beam reinforcing striking portion 64 that strikes outside the existing beam 32. 14 is fixed, it is possible to prevent the opening area of the opening 42 of the existing column beam frame 34 from being reduced by the reinforcing unit 10. Therefore, when the opening 42 of the existing column beam frame 34 is like an entrance to the existing building 1, it is difficult for people to enter and exit. Moreover, it can suppress that the sunlight taken in into the room
  • the beam reinforcement striking portion 64 includes a space portion 66 at a location corresponding to a location where the exhaust sleeve 46 is disposed. That is, in the existing beam 32, the beam reinforcement hitting portion 64 is not added to the space 66 corresponding to the portion where the exhaust sleeve 46 is disposed. Thereby, since the exhaust sleeve 46 is not blocked by the beam reinforcing striking portion 64, the exhaust can be discharged from the room of the existing building 1 through the exhaust sleeve 46 to the outside of the existing building 1 without any problem. Therefore, the functionality of the existing building 1 can be maintained.
  • the column reinforcing main bar 52 and the reinforcing band 54 are provided outside the existing column 30 as described above.
  • the reinforcement unit 10 can reliably suppress the opening area of the opening 42 of the existing column beam frame 34 from being reduced. it can. Therefore, the influence on the habitability, functionality, and lighting of the existing building 1 after reinforcement is more sufficiently reduced.
  • the reinforcing unit 10 can be divided into the L-shaped reinforcing piece 12 and the I-shaped reinforcing piece 14, it becomes easy to carry in, and it is not necessary to particularly secure a loading path for the L-shaped reinforcing piece 12 and the I-shaped reinforcing piece 14. There is a high possibility that it will be completed.
  • positions the L-shaped reinforcement piece 12 and the I-type reinforcement piece 14 can be changed suitably.
  • the L-shaped reinforcing piece 12 is brought into contact with the existing beam 32, and as shown in FIG. 19, the I-shaped reinforcing piece 14 is placed against the existing column 30 and the column reinforcing striking portion 62.
  • the L-shaped reinforcing piece 12 and the I-shaped reinforcing piece 14 may be arranged so as to be anchored.
  • the outer surface 31 of the existing column 30 is located outside the outer surface 33 of the existing beam 32 (outdoor, lower side of FIG. 19). Protruding to the side).
  • Example 2 As shown in FIG. 20, an example in which the exhaust beam 46 is not formed in the existing beam 32 and the space portion 66 is not formed in the beam reinforcing striking portion 64 is also considered. It is done. According to the second embodiment, in addition to the effects of the first embodiment, the effect of further improving the earthquake resistance can be obtained.
  • the reinforcing unit 10 may be shaped as shown in FIG. In the modification shown in FIG. 21, the L-shaped reinforcing piece 12 is thickened on the inner side of the L-shape, and the width of the L-shaped reinforcing piece 12 in the direction parallel to the existing pillar 30 (vertical direction in FIG. 21) is increased. ing.
  • FIG. 22 is a diagram for explaining the seismic reinforcement method according to Modification 2 of Embodiment 1, and is a schematic front view corresponding to FIG. 15.
  • 23 is a cross-sectional view taken along the line FF in FIG. 22, and
  • FIG. 24 is a cross-sectional view taken along the line GG corresponding to the vicinity of the connection portion between the L-type reinforcement piece and the I-type reinforcement piece in FIG. is there.
  • the beam reinforcing striking portion 64 is provided in contact with the outer surface 33 of the existing beam 32 and the lower surface of the balcony slab 36, and L
  • the die reinforcement piece 12 (reinforcement unit 10) is fixed to the lower surface of the beam reinforcement hitting portion 64 via the resin portion 84 by a dimension bolt 82 inserted through the flange portion of the H-shaped steel 22.
  • a column reinforcement striking portion 62 is provided in contact with the outer surface 31 of the existing column 30, and the flange portion 75A of the H-shaped steel 22 of the I-type reinforcement piece 14 (reinforcement unit 10) and the L-type reinforcement piece 12 A plate 77 connecting the flanges inside the opening 42 is bolted. Further, the flange portion 75B of the I-shaped reinforcing piece 14 and the plate 79 that connects the flange portion outside the opening 42 of the L-shaped reinforcing piece 12 are bolted. And the I type reinforcement piece 14 is being fixed to the column reinforcement striking part 62 side surface via the resin part 84 with the dimension bolt 82 which penetrated the indoor side (upper side in FIG. 24) of the flange part 75A. .
  • the maximum layer shear force that can be withstood was 235.5 kN for the existing structural test body, whereas it was 420.0 kN for the first structural test body, and 524.k for the second structural test body. It became 5kN. That is, the value of the maximum layer shear force that can be endured was increased by about 80% for the first structural specimen and about 123% for the second structural specimen relative to the existing structural specimen.
  • strength of earthquake resistance reinforcement is acquired. It should be noted that sufficient strength of the seismic reinforcement was obtained even in the first structural test body having the structure in which the space portion 66 is present in the beam reinforcement striking portion 64.
  • the iron frame (the H-shaped steel 22 and the steel frame 22) This is probably because the H-shaped steel 24) maintains the seismic strength.
  • Embodiment 2 that embodies the seismic strengthening method according to the present invention will be described with reference to the drawings, taking Examples 1 and 2 and modifications thereof.
  • FIG. 25 is a front view schematically showing a reinforcement unit according to Example 1 in Embodiment 2, and is a view showing a state where the reinforcement pieces are assembled.
  • FIG. 26 is a front view of the reinforcing unit shown in FIG. 25, and shows the reinforcing piece in an exploded state.
  • the reinforcing unit 110 is connected so as to extend two L-shaped reinforcing pieces 112 composed of two orthogonal sides and one side of each of the two L-shaped reinforcing pieces 112. Two I-shaped reinforcing pieces 114 are provided. And the reinforcement unit 110 is comprised by the portal shape by joining symmetrically so that the front-end
  • the reinforcement unit 110 is composed of a so-called steel-concrete reinforcement member in which both the L-type reinforcement piece 112 and the I-type reinforcement piece 114 are made of steel and covered with concrete around the bone.
  • FIG. 27 is a cross-sectional view of a reinforcing piece constituting the reinforcing unit according to Example 1 in Embodiment 2, and is a cross-sectional view corresponding to a cross section taken along the line HH and a cross section taken along the line II in FIG. It is.
  • the L-shaped reinforcing piece 112 is formed in an L-shape.
  • the L-shaped reinforcing piece 112 is a precast concrete member in which an H-shaped steel 122 as a core material and a concrete 123 are integrally formed.
  • the H-shaped steel 122 is composed of two sides obtained by welding two steel materials orthogonal to the L-shaped shape, and a plurality of bolt holes 126 are drilled at the ends of the H-shaped steel 122. ing.
  • a plurality of headed studs 113 are fixed to the flange portion 173B of the H-shaped steel 122 by welding in two rows at regular intervals.
  • the L-shaped reinforcing piece 112 includes an upper side portion 116 fixed by a beam reinforcing increased portion 164, a vertical column portion 118 fixed by a column reinforcing increased portion 162, and orthogonal to the upper side portion 116, (See FIG. 36 and the like).
  • a stud missing portion 117 is provided as shown in FIG. 26 in order to avoid interference between the headed stud 113H and the exhaust sleeve 146 of the existing building 101. Yes.
  • the I-shaped reinforcing piece 114 is formed in a prismatic shape.
  • the I-type reinforcing piece 114 is a precast concrete member in which an H-shaped steel 124 that is a core material and a concrete 125 are integrally formed.
  • the H-shaped steel 124 is a straight steel material having one side, and a plurality of bolt holes 126 are drilled in the upper end portion of the H-shaped steel 124.
  • a plurality of headed studs 115 are fixed to the flange portion 175B of the H-shaped steel 124 by welding in two rows at regular intervals.
  • the I-type reinforcing piece 114 is joined at the upper end to the lower end of the vertical column portion 18 of the L-type reinforcing piece 112 and fixed by the column reinforcing additional portion 162 when performing seismic reinforcement. Further, the I-type reinforcing piece 114 includes a base plate 120 fixed to a balcony slab 136 of the existing building 101, which will be described later, at the lower end, and the base plate 120 abuts on the lower end portion of the H-shaped steel 124 and is fixed by welding. (See FIG. 30 and the like).
  • the concrete 123 and 125 covered around the H-shaped steel 122 and 124 is fiber reinforced concrete or the like.
  • the height direction dimension (the vertical size in FIG. 26) of the upper side portion 116 is the width direction of the vertical column portion 118. Although it is smaller than the dimension (the size in the left-right direction in FIG. 26), the magnitude relationship between the height-direction dimension and the width-direction dimension is determined according to the seismic reinforcement required for the existing building 101. Is.
  • the magnitude relationship between the height direction dimension and the width direction dimension is not particularly limited, for example, the width direction dimension and the height direction dimension may be the same.
  • the position and number of the bolt holes 126 provided at the end portions of the H-shaped steels 122 and 124 are not particularly limited.
  • the seismic reinforcement method is broadly divided into a reinforcement preparation process, a reinforcement piece assembly process, a column reinforcement arrangement process, a beam reinforcement arrangement process, a reinforcement unit fixing process, and a reinforcement unit finishing process.
  • FIG. 28 is a first process diagram in which the existing finish is removed from the existing column and the existing beam at the portion to be hit.
  • FIG. 29 is a second process diagram in which drilling and roughening of the anchor hole are performed at the portion to be increased in the existing column and the existing beam.
  • an existing column beam frame 134 composed of an existing column 130 and an existing beam 132, and the outside of the existing column 130 excluding the balcony slab 136
  • a finishing member for example, an outer wall material such as a tile or a paint
  • the outer surface 131 of the existing pillar 130 from which the finishing member has been removed is an increased hitting portion 138.
  • a portion of the outer surface 133 that is the outside of the existing beam 132 (the front side in FIG. 28) excluding the lower end side outer surface portion 144 and the peripheral portion of the exhaust sleeve 46 is a balcony slab.
  • the finishing member applied to the side close to 136 (the upper end side of the existing beam 132) is removed.
  • a portion of the outer surface 133 of the existing beam 132 from which the finishing member has been removed is the additional hitting scheduled portion 140.
  • rebar exploration and anchor drilling are performed. Specifically, the reinforcing bars installed in the existing pillar 130 and the existing beam 132 are searched for, and while avoiding these reinforcing bars, as shown in FIG. A plurality of anchor holes 148 are drilled in the additional hitting portions 140 of the beam 132. Further, a through-hole 150 that penetrates the balcony slab 136 in the plate thickness direction (vertical direction in FIG. 29) of the balcony slab 136 is drilled. The through-hole 150 is drilled for inserting an anchor or bolt used to fix the base plate 120 of the I-shaped reinforcing piece 114 to the balcony slab 136.
  • a sheath tube 160 is provided at the lower part of the balcony slab 136 so as to communicate with the through hole 150. Then, a fixing bolt 170 described later is inserted through a through hole 150 from a bolt insertion hole (not shown) of the base plate 120 of the I-type reinforcing piece 114 and screwed with a female screw (not shown) provided in the sheath tube 160. . At this time, when the through bolt 70 is disposed inside the through hole 150 and the sheath tube 160, it is preferable that the construction of the reinforcing unit 10 has already been completed on the lower floor.
  • the fixing bolt 170 may be a dimensioned bolt used together with an adhesive, or may be fixed by curing the adhesive.
  • An anchor may be used instead of the fixing bolt 170 and the female screw.
  • the type of the anchor is not particularly limited as long as the base plate 120 of the I-type reinforcing piece 114 can be constructed integrally with the balcony slab 136, such as a hole-in anchor or a chemical anchor.
  • the base plate 120 of the I-shaped reinforcing piece 114 may be fixed to the balcony slab 136 with an adhesive, and in this case, the through hole 150 is not necessary.
  • roughening is performed on the additional hitting planned portion 138 of the existing pillar 130 and the additional hitting planned portion 140 of the existing beam 132.
  • “Roughing” is an operation performed to roughen this surface by forming irregularities on the surface of the old concrete, and to improve the integrity of the surface of the old concrete and the new concrete to be succeeded later.
  • FIG. 30 is a process diagram of the reinforcement piece assembling process of the seismic reinforcement method according to Example 1 in the second embodiment, and is a third process chart showing a state in which the left I-shaped reinforcement piece is arranged.
  • FIG. 31 is a process diagram subsequent to FIG. 30, and is a fourth process diagram illustrating a state in which the left I-shaped reinforcement piece and the left L-shaped reinforcement piece are to be joined.
  • FIG. 32 is a view when the flange portion on the existing column side of the H-shaped steel is viewed from the position indicated by the arrow J in FIG. 31.
  • FIG. 33 is a process diagram subsequent to FIG.
  • FIG. 31 is a fifth process diagram showing a state in which the right I-shaped reinforcement piece is arranged after joining the left I-shaped reinforcement piece and the left L-shaped reinforcement piece.
  • FIG. 34 is a process diagram following FIG. 33, in which the right L-shaped reinforcing piece is joined to the right I-shaped reinforcing piece and the left L-shaped reinforcing piece joined to the left I-shaped reinforcing piece, respectively. It is a 6th process figure which shows a mode to do.
  • the reinforcement piece assembling process is a process of arranging a pair of I-type reinforcement pieces 114 at positions along the existing pillars 130 on the outside of the existing pillars 130 (on the front side in FIG. 30 and on the outdoor side of the existing building 101).
  • a pair of L-shaped reinforcing pieces 112 are arranged at positions along the existing pillars 130 and the existing beams 132 on the outside of the beam 132 (on the front side of the paper in FIG. 30 and on the outdoor side of the existing building 101).
  • the piece 114 and the pair of L-shaped reinforcing pieces 112 are assembled.
  • the left-side I-shaped reinforcing piece 114 is arranged and installed at a position along the left-side existing column 130 of the existing column beam frame 134. Specifically, as shown in FIG. 30, among the existing pillar 130 on the left side, the side surface facing the opening 142 (the right side surface in FIG. 30) and the flange of the H-shaped steel 124 of the I-type reinforcing piece 114 The I-type reinforcing piece 114 is moved to the existing pillar 130 on the left side and the base plate 120 of the I-type reinforcing piece 114 is placed on the balcony slab 136 until the portion 175B is flush with the portion 175B. The fixing bolt 170 is inserted into the base plate 120 and the through hole 150 and temporarily tightened, whereby the I-type reinforcing piece 114 is installed.
  • the left L-shaped reinforcing piece 112 is disposed above the left I-shaped reinforcing piece 114 at a position along the existing pillar 130 on the left side of the existing column beam frame 134 and the existing piece.
  • the beam 132 is placed on the left side of the beam 132 and installed.
  • the side surface facing the opening 142 (the right side surface in FIG. 30) and the H-shaped steel 122 of the left L-shaped reinforcing piece 112.
  • the L-shaped reinforcing piece 112 is arranged close to the existing pillar 130 on the left side until the flange portion 173B is flush with the flange portion 173B.
  • the support member 176 supports the space between the upper side portion 116 of the L-shaped reinforcing piece 112 and the balcony slab 136 on the floor side.
  • the joint portion 171 and the joint portion 172 are joined together by the plate 174, and the plate 174 and the joint portion 171 are joined together. And the plate 174 and the joint portion 172 are each temporarily tightened with bolts. Further, the flange portion 173A of the joint portion 171 and the flange portion 175A of the joint portion 172 are connected by a plate 177, and the plate 177 and the flange portion 173A, and the plate 177 and the flange portion 175A are respectively bolted. Tighten temporarily.
  • the flange portion 173B of the joint portion 171 and the flange portion 175B of the joint portion 172 are joined together by a plate 179, and the plate 179 and the flange portion 173B and the plate 179 and the flange portion 175B are temporarily attached with bolts. Tighten.
  • the plate 179 is arrange
  • the right I-shaped reinforcing piece 114 is disposed and installed at a position along the existing pillar 130 on the right side of the existing column beam frame 134. Specifically, as shown in FIG. 33, of the existing pillar 130 on the right side, the side surface facing the opening 142 (the left side surface in FIG. 33) and the flange of the H-shaped steel 124 of the I-type reinforcing piece 114 The I-type reinforcement piece 114 is brought to the existing pillar 130 on the right side until the portion 175B is flush with the base plate 120, and the base plate 120 of the I-type reinforcement piece 114 is placed on the balcony slab 136. The fixing bolt 170 is inserted into the base plate 120 and the through hole 150 and temporarily tightened, whereby the I-type reinforcing piece 114 is installed.
  • the right L-shaped reinforcing piece 112 is arranged above the right I-shaped reinforcing piece 114 at a position along the existing pillar 130 on the right side of the existing column beam frame 134 and the existing beam. It is arranged near the right side of 132. Specifically, as shown in FIG. 34, of the existing pillar 130 on the right side, the side surface facing the opening 142 (the right side surface in FIG. 34) and the H-shaped steel 122 of the L-shaped reinforcing piece 112 on the right side. The L-shaped reinforcing piece 112 is arranged close to the existing pillar 130 on the right side until the flange portion 173B is flush with the flange portion 173B. At this time, the support member 176 supports the upper side portion 116 of the right L-shaped reinforcing piece 112 and the balcony slab 136 on the floor side.
  • the plate 174, the joint portion 171 and the plate 174 is joined by tightening a bolt.
  • the plate 177 and the flange portion 173A, and the plate 177 and the flange portion 175A are joined by fastening the bolts.
  • the plate 179 and the flange portion 173B, and the plate 179 and the flange portion 175B are joined by tightening the bolts.
  • the joint portion 171 and the joint portion 172 are joined by the plate 174, and the plate 174 and the joint are joined.
  • the part 171 and the plate 174 and the joint part 172 are joined by tightening the bolts.
  • the flange portion 173A of the joint portion 171 and the flange portion 175A of the joint portion 172 are connected by a plate 177, and the plate 177 and the flange portion 173A, and the plate 177 and the flange portion 175A are respectively bolted. Tighten and join.
  • the flange portion 173B of the joint portion 171 and the flange portion 175B of the joint portion 172 are connected by the plate 179, and the plate 179 is connected. And the flange portion 173B, and the plate 179 and the flange portion 175B are joined by tightening the bolts.
  • the joint portion 178 of the H-shaped steel 122 of the left L-shaped reinforcing piece 112 and the joint portion 178 of the H-shaped steel 122 of the right L-shaped reinforcing piece 112 are connected by a plate 180. The two joint portions 178 are finally tightened with bolts and joined via the plate 180. Further, in the I-type reinforcement pieces 114 on the left and right sides, the fixing bolts 170 are finally tightened to fix the I-type reinforcement pieces 114.
  • the L-shaped reinforcement pieces 112 on the left and right sides and the I-type reinforcement pieces 114 on the left and right sides are assembled in a gate shape and formed as the reinforcement unit 110.
  • the headed stud 113V of the L-shaped reinforcing piece 112 and the headed stud 115 of the I-shaped reinforcing piece 114 are opposed to the planned hitting portion 138 of the existing column 130.
  • the headed stud 113 ⁇ / b> H of the L-shaped reinforcing piece 112 is arranged at a position facing the additional hitting planned portion 140 of the existing beam 132.
  • the column reinforcing main reinforcement 152 and the reinforcement strip 154 are arranged in the column reinforcing arrangement step.
  • anchoring and anchoring for arranging the beam reinforcing main bar 156 and the reinforcing bar 158 in the beam reinforcing bar arrangement process cannot be performed. In order to avoid this, care must be taken in determining the drilling position of the anchor hole 148.
  • a welding structure can be considered in addition to the bolt fastening.
  • the reinforcement unit 110 itself can be strengthened if the reinforcement unit 110 itself is integrally formed. Rather than having a structure, it is preferable to mechanically join.
  • a welding machine and a power source are required at the site of seismic reinforcement work, so there are problems such as extra costs, and it is difficult to ensure safety because welding uses fire. Since there is a possibility that it may occur, the advantage is that it can be easily fastened with a bolt or the like.
  • FIG. 36 is a process diagram subsequent to FIG. 35, and is an eighth process diagram for explaining the column reinforcement placement process and the beam reinforcement placement process of the seismic strengthening method according to Example 1 in the second embodiment.
  • the column reinforcement main reinforcement 152 is arranged on the outer surface 131 side of the existing column 130 so that the stud 113V is provided inside, and the column reinforcement reinforcement 155 is formed by winding the reinforcement reinforcement bars 154 perpendicular to the column reinforcement main reinforcement 152.
  • the beam reinforcing main reinforcement 156 is arranged on the outer surface 133 side of the existing beam 132 so that the headed stud 113H of the upper side portion 116 along the existing beam 132 of the pair of L-shaped reinforcing pieces 112 is internally provided.
  • the beam reinforcing bar 159 is formed by winding the reinforcing bar 158 so as to be orthogonal to the beam reinforcing main bar 156.
  • various reinforcing bars are arranged in a plurality of anchor holes 148 drilled in the additional hitting planned portion 138 of the existing column 130 and the additional hitting planned portion 140 of the existing beam 132.
  • a column reinforcement main reinforcing bar 152 (reinforcing bar) arranged in parallel to the existing column 130 and a reinforcing bar wound in a direction perpendicular to the column reinforcing main reinforcing bar 152 are provided in the additional hitting portion 138.
  • a reinforcing band 154 is arranged.
  • a beam reinforcement main bar 156 (reinforcing bar) arranged in parallel with the existing beam 132 and a reinforcing bar 158 wound in a direction perpendicular to the beam reinforcement main bar 156 are arranged in the additional hitting planned portion 140.
  • FIG. 37 is a process diagram subsequent to FIG. 36, and is a ninth process diagram illustrating a reinforcement unit fixing process of the earthquake-proof reinforcement method according to Example 1 in Embodiment 2.
  • the headed stud 113V of the L-shaped reinforcing piece 112 and the headed stud 115 of the I-shaped reinforcing piece 114 are added to the column reinforcing hitting portion 162, and the headed stud 113H of the L-shaped reinforcing piece 112 is changed to the beam reinforcing hitting portion.
  • 164 is fixed in a state of being installed inside. Therefore, the reinforcing unit 110 can be fixed to the column reinforcing hitting portion 162 and the beam reinforcing hitting portion 164 without using anchoring or an adhesive.
  • the exhaust sleeve 146 is disposed on the existing beam 132.
  • the beam reinforcement striking portion 164 includes a space portion 166 at a location corresponding to the portion where the exhaust sleeve 146 is disposed. That is, by providing the space portion 166 at a position corresponding to the position where the exhaust sleeve 146 is disposed, the beam reinforcing increased portion 164 is formed avoiding the exhaust sleeve 146.
  • FIG. 39 is a process diagram subsequent to FIG. 38, and is an eleventh process diagram showing a state where the seismic reinforcement work has been completed by surface finishing the reinforcing unit and the additional hitting portion.
  • a cross-sectional view is shown in FIG. However, in FIG. 41, in order to make the drawing easier to see, the beam reinforcement main reinforcing bar and the reinforcing reinforcing bar in the beam reinforcing bar arrangement portion are omitted.
  • the beam reinforcing increased portion 164 placed on the beam reinforcing bar 159 is brought close to the upper end side (the upper side in FIG. 41) of the existing beam 132 and is in contact with the lower surface of the balcony slab 136 and the outer surface 133 of the existing beam 132.
  • the height H3 of the beam reinforcing striking portion 164 is smaller than the height (beam length) H1 of the existing beam 132.
  • the height H3 of the beam reinforcing increased portion 164 is smaller than the height H2 of the lower portion of the existing beam 132 from the balcony slab 136, and the height H3 of the beam reinforcing increased portion 164 is the existing height.
  • the height of the beam 132 is equal to or less than 1 ⁇ 2 of the beam height H1.
  • the protruding amount h1 is a size that hardly influences the habitability, the functionality, and the daylighting property for a person inside the existing building 101.
  • FIG. 38 is a process diagram subsequent to FIG. 37, and is a tenth process diagram illustrating a state in which a joint portion connecting reinforcement pieces is filled with grout.
  • the grout 188 is injected and the surface of the reinforcing unit 110 is finished.
  • the vertical column joining portion 128 of the L-type reinforcement piece 112 and the I-type reinforcement piece 114 (see FIG. 37).
  • a grout 188 is injected into the upper side joint portion 127 (see FIG. 37) between the L-shaped reinforcing pieces 112 and the support portions 186 at the lower ends of the left and right I-shaped reinforcing pieces 114.
  • the grout 188 is made of fiber reinforced grout in order to increase the strength of the reinforcing unit 110.
  • the grout 188 may be made of non-shrink mortar.
  • surface finishing is performed. Specifically, as shown in FIG. 39, finishing of the outer wall is performed by attaching or painting a finishing member on the surfaces of the column reinforcing hitting portion 162, the beam reinforcing hitting portion 164, and the reinforcing unit 110. .
  • the seismic reinforcement work by the seismic reinforcement method of this embodiment is completed.
  • the column reinforcement striking portion 162, the beam reinforcement striking portion 164, and the reinforcement unit 110 are finished inconspicuously. I don't mind being a building.
  • FIG. 40 is a cross-sectional view taken along arrow KK in FIG.
  • FIG. 42 is an explanatory view showing a first case in the second embodiment in which the position where the reinforcing unit according to the first embodiment is arranged on the existing column beam frame is changed.
  • FIG. 43 is an explanatory diagram of the same case as FIG. 42, and is a cross-sectional view corresponding to the LL arrow position in FIG. FIG.
  • FIG. 44 is an explanatory diagram showing a second case in which the position where the reinforcing unit according to Example 1 is arranged on the existing column beam frame is changed in the second embodiment, and is a position taken along the arrow KK in FIG. FIG. 40 to 44, in order to make the drawings easier to see, the column reinforcing main bar and the reinforcing bar of the column reinforcing bar arrangement and the beam reinforcing main bar and the reinforcing bar of the beam reinforcing bar are omitted. It is illustrated as follows.
  • the column reinforcement increased portion 162 is a surface of the outer surface 131 of the existing column 130.
  • the I-shaped reinforcing piece 114 is formed only on the upper side, and is disposed with a gap from the outer surface 131 in the depth direction of the existing pillar 130 (the vertical direction in FIG. 40). As shown in FIG.
  • the beam reinforcing striking portion 164 is formed in contact with the lower surface of the balcony slab 136 and the outer surface 133 of the existing beam 132, and the L-shaped reinforcing piece 112 is formed in the depth direction of the existing beam 132 (in FIG. 41). In the left-right direction) with a gap from the outer surface 133. And the I type reinforcement piece 114 and the L type reinforcement piece 112 which were arrange
  • the existing outer surface 133 of the existing beam 132 is located on the indoor side (upper side in FIG. 42) in the depth direction of the existing column 130 (vertical direction in FIG. 42) from the outer surface 131 of the existing column 130.
  • the column reinforcement striking portion 162 is formed only on the outer surface 131 of the existing column 130.
  • a plurality of headed studs 115 are arranged in a single row at a predetermined pitch interval, and the flange portion 175B (H-shaped steel 122) of the H-shaped steel 124 is used.
  • the pitch interval between the adjacent head studs 115 is, for example, 1/1 compared to the case where the head studs 115 (head studs 113V) are arranged in two rows as described above.
  • the pitch is smaller, such as a pitch of 2 or less.
  • the beam reinforcement increasing portion 164 is formed in contact with the lower surface of the balcony slab 136 and the outer surface 133 of the existing beam 132, and the L-shaped reinforcing piece 112 is formed on the outer surface 133 of the existing beam 132. It is arrange
  • the outer surface 133 of the existing beam 132 is located on the indoor side (upper side in FIG. 44) of the existing column 130 in the depth direction of the existing column 130 (vertical direction in FIG. 44), and the outer surface of the existing beam 132
  • there is a restriction such as a small protrusion of the balcony slab 136 from 133 to the outdoor side (left side in FIG. 43).
  • the column reinforcement striking portion 162 is not provided as shown in FIG.
  • the I-type reinforcement piece 114 (the vertical column portion 118 of the L-type reinforcement piece 112) is a portion of the column reinforcement increased hitting portion 162 that is not opposed to the outer surface 131 of the existing column 130, and is a headed stud 115. (Headed stud 113V) is fixed inside.
  • the seismic reinforcement method of the first embodiment is a method of seismically reinforcing an existing column beam frame 134 constructed from an existing column 130 and an existing beam 132 with respect to the existing building 101 by the reinforcing unit 110, and a pair of L
  • the seismic reinforcement method of assembling the gate-type reinforcement unit 110 by combining the mold reinforcement piece 112 and the pair of I-type reinforcement pieces 114 the pair of L-type reinforcement pieces 112 and the pair of I-type reinforcement pieces 114 include The studs 113 and 115 are provided, and a pair of I-shaped reinforcement pieces 114 are arranged along the existing pillar 132 outside the existing pillar 130, and a pair of L-shaped reinforcement is provided outside the existing beam 132.
  • the beam reinforcing main bar 156 is arranged outside the existing beam 132 so that the stud 113H (113) of the upper side portion 116 along the existing beam 132 of the pair of L-shaped reinforcing pieces 112 is provided inside.
  • the beam reinforcing barbing step 159 is formed by winding the reinforcing bar 158 perpendicularly to the beam reinforcing main bar 156, and the beam reinforcing barbing part 155 is placed to hit the existing column 130.
  • a reinforcing piece fixing step for fixing the reinforcing unit 110 by placing the existing beam 132 on the reinforcing bar 159 and hitting the existing beam 132.
  • the seismic reinforcement method of the first embodiment the impact on the habitability, functionality, and lighting of the existing building 101 after the reinforcement can be sufficiently reduced, and the cost of the seismic reinforcement work can be suppressed. , Has an excellent effect.
  • the beam reinforcing increased portion 164 provided in the beam reinforcing bar arrangement portion 159 is provided close to the upper end side of the existing beam 132 (side adjacent to the balcony slab 136). Since the height H3 of the beam reinforcing increased portion 164 is smaller than the height H1 of the existing beam 132, the opening area of the opening 142 of the existing column beam frame 134 is made smaller by the reinforcing unit 110. Can be reliably suppressed, and the influence on habitability, functionality, and lighting can be sufficiently suppressed.
  • the opening 142 of the existing column beam frame 134 serves as an indoor / outdoor entrance / exit of the existing building 101, it is difficult for people to enter and exit even after the existing building 101 is reinforced. Moreover, it can suppress that the sunlight taken in into the room
  • the seismic reinforcement method of the first embodiment is characterized in that the height H3 of the beam reinforcement striking portion 164 is 1 ⁇ 2 or less of the beam length H1 of the existing beam 132.
  • the upper side portion 116 that is one side (one side of the reinforcing unit) along the existing beam 132 of the pair of L-shaped reinforcing pieces 112 is an opening of the existing column beam frame 134 from the lower surface of the existing beam 132 on the upper beam side. The amount h1 of protrusion toward the portion 142 can be suppressed.
  • the existing building 101 is an apartment house, and the existing beam structure (existing column beam frame 134) at the boundary between the veranda and the room has a large span in the direction of the existing beam 132.
  • earthquake-proof reinforcement is applied to a building, the influence on the habitability, functionality, and daylighting by the reinforcing unit 110 is suppressed to a small extent, and the existing building 101 can be effectively earthquake-proofed.
  • seismic reinforcement technology that can sufficiently ensure such amenity, functionality, and daylighting as customer needs from residents of apartment houses, etc. Can fully meet such customer needs.
  • the beam reinforcing increased portion 164 includes the space portion 166 at a position corresponding to the portion where the exhaust sleeve 146 is disposed.
  • the sleeve 146 is not blocked by the beam reinforcement striking portion 164, and can maintain the function of exhausting the exhaust from the room of the existing building 101 to the outside through the exhaust sleeve 164, and the functionality of the existing building 101 is maintained. Is done.
  • the portion where the exhaust sleeve 146 is disposed is very limited in size, even if there is a portion that is not increased by the space portion 166, a part of the beam reinforcement increased portion 164 exists.
  • the existing building 101 that has been seismically reinforced by the reinforcing unit 110 can ensure sufficient seismic strength.
  • the pair of L-shaped reinforcing pieces 112 and the pair of I-shaped reinforcing pieces 114 are precasts in which H-shaped steels 122 and 124, which are core materials, and concrete 123 and 125 are integrally molded. It is a concrete member, and the headed studs 113 and 115 are fixed to the H-shaped steels 122 and 124. Therefore, if the stud is fixed to the steel material at the seismic reinforcement site of the existing building 101, the space is increased. , There are many restrictions and the stud fixing work cannot be performed efficiently.
  • the productivity of the stud fixing is improved, so the cost of the reinforcing unit 110 can be reduced.
  • the productivity of the stud fixing is improved, so the cost of the reinforcing unit 110 can be reduced.
  • the productivity of the stud fixing is improved, so the cost of the reinforcing unit 110 can be reduced.
  • the headed studs 113 and 115 are welded to the H-shaped steels 122 and 124, so that it is not necessary to place a qualified person of welding technology on the seismic reinforcement site of the existing building 101.
  • the seismic reinforcement method of Example 1 does not require any of the above-mentioned certain required times, unlike the adhesive bonding method that requires a certain amount of time to reach the strength of the adhesive. Therefore, if the headed studs 113 and 115 are fixed to the H-shaped steels 122 and 124 in advance at the factory, the stud-attached reinforcing pieces carried into the seismic reinforcement site, that is, the L-shaped reinforcing piece 112 and the I-shaped reinforcing piece 114 are used. On the other hand, since preparations for the next reinforcement piece assembly process can be started immediately, it is possible to contribute to shortening the construction period of the seismic reinforcement work.
  • the reinforcement unit 110 is configured by assembling the reinforcement pieces divided into the L-type reinforcement piece 112 and the I-type reinforcement piece 114, the L-type reinforcement piece 112 and the I-type reinforcement piece 114 are the existing buildings. 101, it is easy to carry in to the seismic reinforcement site, and the necessity to secure the carrying path for the special L-shaped reinforcing piece 112 and the I-shaped reinforcing piece 114 is kept low.
  • Example 2 As Example 2 of Embodiment 2, as shown in FIG. 45, the existing beam 132 is not formed with the exhaust sleeve 146 (see FIG. 39), and the beam reinforcing increased portion 164 has a space 166. Embodiments that do not form can also be considered. According to this Example 2, in addition to the effect of Example 1 mentioned above, the effect which further improves seismic strength can be acquired. In the seismic reinforcement method of the second embodiment, since the reinforcing unit 110 has a rigid and strong structure, particularly the horizontal strength of the existing structure is improved, and the seismic strength of the existing building 101 is further improved.
  • the reinforcing unit 110 may be shaped as shown in FIG. In the modification shown in FIG. 46, the L-shaped reinforcing piece 112 is thickened on the inner side of the L-shape, and the width of the L-shaped reinforcing piece 112 in the direction parallel to the existing pillar 130 (vertical direction in FIG. 46) is increased. is doing.
  • first embodiment has been described with reference to the first and second embodiments and the first and second modifications
  • second embodiment has been described with the first and second embodiments and the modification.
  • the first and second embodiments are merely examples, and the present invention is not limited to the first and second embodiments, and can be appropriately modified and applied without departing from the gist thereof.
  • the reinforcement units 10 and 110 are configured in a gate shape, but the shape of the reinforcement unit may be a square frame shape.
  • the number of studs, the arrangement position, and the interval (pitch) between adjacent studs are limited to the arrangement positions exemplified in the second embodiment. It is not a thing and can be changed suitably.
  • the earthquake resistance is improved and the opening area in the opening in the existing column beam frame is improved.
  • existing buildings after seismic reinforcement can be provided in which the habitability, functionality, and daylighting performance are further improved compared to conventional seismic reinforcement methods.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Emergency Management (AREA)
  • Business, Economics & Management (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Mechanical Engineering (AREA)
  • Electrochemistry (AREA)
  • Chemical & Material Sciences (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

 本発明は、既存建築物の既存柱と既存梁から構成される既存柱梁フレームを補強するユニットにより耐震補強する工法であって、一対のL型補強ピースと、一対のI型補強ピースとボルトで結合させて門型の補強ユニットを組み立てる耐震補強工法において、既存柱の外側に、柱に平行に配置される柱補強主筋と、柱補強主筋の直交方向に巻かれる補強帯筋とを内設した柱補強増打部をアンカーにより増し打ちする柱増し打ち工程と、既存梁の外側に、梁と平行に配置される梁補強主筋と、梁補強主筋の直交方向に巻かれる補強肋筋とを内設した梁補強増打部をアンカーにより増し打ちする梁増し打ち工程と、柱補強増打部と梁補強増打部に対して、一対のL型補強ピースと一対のI型補強ピースとをアンカー止めし、柱補強増打部と梁補強増打部と、一対のL型補強ピースと一対のI型補強ピースとの間に接着用樹脂を注入する補強ピース固定工程と、を有する。

Description

耐震補強工法
 この発明は、既存建築物に対する耐震補強工事における耐震補強工法に関する。
 既存建物等の中には、現行の建築基準を満足していないものもあり、耐震強度を高める必要のあるものも多い。このような既存建築物の耐震強度を高める技術としては、一般的なものとして、鉄筋コンクリート壁を増設する工法と、鉄骨ブレースを増設する工法とがある。
 しかし、鉄筋コンクリート壁を増設する工法では既存建物等の開口部が壁面で覆われてしまうために、室内の採光に影響が出るなどの問題もある。そこで、建物の室内を開放したい場合には鉄骨ブレースを増設する工法で耐震補強を行うことが一般的であるが、開口部の一部が塞がれて窓からの景観を損なう、開口部の床部分に段差が生じる等の問題がある。
 そこで、以上のような問題を解消するため、特許文献1~3には、既存建築物の柱と梁から構成される既存柱梁フレームの開口部の内周面の内側に、分割して運搬設置を容易にした補強ユニットを挿入して嵌め込む工法が開示されている。
特許第4445007号公報 特許第4400833号公報 特許第4446401号公報
 しかしながら、特許文献1~3に開示された工法によれば、既存建築物の既存柱梁フレームの開口部の内周面のさらに内側に補強ユニットを挿入して嵌め込むので、補強ユニットによって既存柱梁フレームの開口部の一部が塞がれて既存柱梁フレームの開口部の開口面積が小さくなってしまう。そのため、既存柱梁フレームの開口部が建築物への出入口のような場合には、人の出入りに支障が生じてしまうおそれがある。また、既存柱梁フレームの開口部には一般に窓や戸が設置されているが、補強ユニットによって既存柱梁フレームの開口部の一部が塞がれると、補強ユニットによって太陽光が遮断されてしまう。したがって、補強後の建築物の居住性や採光に対する影響が十分に小さくならないおそれがある。
 また、既存柱梁フレームの開口部に設置されている窓や戸の設置仕様は多種多様であり、窓や戸の設置仕様によっては、既存柱梁フレームの開口部の内周面の内側に補強ユニットを挿入して嵌め込んだときに窓や戸の開閉に支障を来たすおそれがある。そのため、補強後の建築物の機能性に対する影響が十分に小さくならないおそれがある。
 そこで、本発明は上記した問題点を解決するためになされたものであり、補強後の建築物の居住性、機能性、採光に対する影響が十分に小さくなる耐震補強工法を提供すること、を課題とする。
 上記課題を解決するためになされた本発明の一態様における耐震補強工法は、既存建築物の既存柱と既存梁から構成される既存柱梁フレームを補強するユニットにより耐震補強する工法であって、一対のL型補強ピースと、一対のI型補強ピースとボルトで結合させて門型の補強ユニットを組み立てる耐震補強工法において、前記既存柱の外側に、柱に平行に配置される柱補強主筋と、前記柱補強主筋の直交方向に巻かれる補強帯筋とを内設した柱補強増打部をアンカーにより増し打ちする柱増し打ち工程と、前記既存梁の外側に、梁と平行に配置される梁補強主筋と、前記梁補強主筋の直交方向に巻かれる補強肋筋とを内設した梁補強増打部をアンカーにより増し打ちする梁増し打ち工程と、前記柱補強増打部と前記梁補強増打部に対して、前記一対のL型補強ピースと前記一対のI型補強ピースとをアンカー止めし、前記柱補強増打部と前記梁補強増打部と、前記一対のL型補強ピースと前記一対のI型補強ピースとの間に接着用樹脂を注入する補強ピース固定工程と、を有すること、を特徴とする。
 この態様によれば、既存柱の外側に増し打ちする柱補強増打部と既存梁の外側に増し打ちする梁補強増打部とに対して補強ピースを固定するので、当該補強ピースからなる補強ユニットによって既存柱梁フレームの開口部の開口面積が小さくなることを抑制できる。そのため、既存柱梁フレームの開口部が建築物への出入口のような場合に、人の出入りに支障が生じ難い。また、既存柱梁フレームの開口部に設置される窓や戸から建築物の室内に採り込まれる太陽光が、補強ユニットによって遮断されることを抑制できる。さらに、補強ユニットによって既存柱梁フレームの開口部に設置される窓や戸の開閉に支障を来たすおそれがなくなる。したがって、補強後の建築物の居住性、機能性、採光に対する影響が十分に小さくなる。
 上記の態様においては、前記梁補強増打部は、排気用スリーブが配設されている部位に対応する箇所に空間部を備えること、が好ましい。
 この態様によれば、排気用スリーブが梁補強増打部により閉塞されないので、排気用スリーブを通して建築物の室内からの排気を問題なく建築物の外部に排出することができる。そのため、既存建築物の機能性を維持することができる。そして、このように梁補強増打部の一部に増し打ちされない部分が存在していても、前記のように既存柱の外側に柱補強主筋と補強帯筋とを内設した柱補強増打部と既存梁の外側に梁補強主筋と補強肋筋とを内設した梁補強増打部を増し打ちした構造下にて補強ユニットが耐震強度を保っており、また、排気用スリーブが配設されている部位はごく限られた大きさなので、十分な耐震補強の強度を確保することができる。
 上記の態様においては、前記梁補強増打部の高さを前記既存梁の高さよりも小さくすること、が好ましい。
 この態様によれば、補強ユニットによって既存柱梁フレームの開口部の開口面積が小さくなることを確実に抑制できる。そのため、より確実に、補強後の建築物の居住性、機能性、採光に対する影響が十分に小さくなる。
 上記課題を解決するためになされた本発明の他の態様における耐震補強工法は、既存建築物に対し、既存柱と既存梁とから構築される既存柱梁フレームを、補強ユニットにより耐震補強する工法であって、一対のL型補強ピースと、一対のI型補強ピースとを結合させて門型の補強ユニットを組み立てる耐震補強工法において、前記一対のL型補強ピースと前記一対のI型補強ピースには、スタッドがそれぞれ設けられていること、前記既存柱の外側で、前記一対のI型補強ピースを前記既存柱に沿って配置すると共に、前記既存梁の外側で、前記一対のL型補強ピースを前記既存柱と前記既存梁に沿って配置し、前記一対のI型補強ピースと前記一対のL型補強ピースとを組み立てる補強ピース組立工程と、前記補強ピース組立工程後、前記一対のI型補強ピースの前記スタッドと、前記一対のL型補強ピースのうち、前記既存柱に沿う一辺の前記スタッドとが内設するよう、柱補強主筋を前記既存柱の外側に配筋し、前記柱補強主筋に補強帯筋を直交させて巻いた柱補強配筋部を形成する柱補強配筋工程と、前記一対のL型補強ピースのうち、前記既存梁に沿う一辺の前記スタッドが内設するよう、梁補強主筋を前記既存梁の外側に配筋し、前記梁補強主筋に補強肋筋を直交させて巻いた梁補強配筋部を形成する梁補強配筋工程と、前記柱補強配筋部に打設して前記既存柱を増し打ちすると共に、前記梁補強配筋部に打設して前記既存梁を増し打ちすることにより、前記補強ユニットを固定する補強ユニット固定工程と、を有すること、を特徴とする。
 この態様によれば、補強ユニットが、既存柱の外側で柱補強配筋部に打設された柱補強増打部と、既存梁の外側で梁補強配筋部に打設された梁補強増打部とにより固定されることで、既存柱梁フレームにおける曲げ耐力、及び剪断耐力が増大し、既存建築物の耐力と靭性が増大するため、既存建築物の耐震性が向上する。また、このような耐震性の向上と共に、既存柱梁フレームの開口部において、開口面積の減少を抑制することができる。そのため、耐震補強後の既存建築物では、居住性、機能性、及び採光への影響を十分に小さく抑えることができる。また、補強ユニットを既存柱と既存梁とに固定させるのに、既存柱の増し打ち部分や既存梁の増し打ち部分に、補強ユニットをアンカー止めすることや、接着剤等で固定させる工程が不要となり、耐震補強工事全体の工程数が削減できるため、工期が短縮でき、工事コストが低減できる。従って、補強後の既存建築物の居住性、機能性、採光への影響を十分に小さくすることができると共に、耐震補強工事のコストが抑制できる、という優れた効果を奏する。
 上記の態様においては、前記梁補強配筋部に打設された梁補強増打部は、前記既存梁の上端側に寄せて設けられ、前記梁補強増打部の高さが、前記既存梁の高さより小さいこと、が好ましい。
 この態様によれば、補強ユニットにより、既存柱梁フレームの開口部の開口面積がより小さくなるのを確実に抑制でき、居住性、機能性、及び採光への影響を十分に抑えることができる。すなわち、既存柱梁フレームの開口部が既存建築物の室内外の出入口となっている場合には、既存建築物を補強した後でも、人の出入りに支障が生じ難くなる。また、既存柱梁フレームの開口部に設置された窓や戸から、既存建築物の室内に採り込まれる太陽光が、補強ユニットによって遮断されるのを抑制することができる。さらに、既存柱梁フレームの開口部に設置された窓や戸の開閉に、補強ユニットによって支障を来す虞が生じなくなる。
 上記の態様においては、前記梁補強増打部の高さは、前記既存梁の梁せいの1/2以下の高さであること、が好ましい。
 この態様によれば、一対のL型補強ピースのうち、既存梁に沿う一辺(補強ユニットの一辺)となる補強ピースが、上梁側の既存梁下面から既存柱梁フレームの開口部に向けてせり出すのを抑えることができる。そのため、例えば、既存建築物が集合住宅等であり、ベランダと室内との境にある柱梁フレームにおいて、既存梁の桁行き方向のスパンが大きい構造体の既存建築物を対象に、耐震補強を施す場合には、補強ユニットによる居住性、機能性、及び採光性への影響が小さく抑えられ、既存建築物を効果的に耐震補強できる。特に、集合住宅の住人等からの顧客ニーズとして近年、このような居住性、機能性、及び採光性が十分に確保できる耐震補強技術の開発が要望されており、上記の態様の耐震補強工法は、このような顧客ニーズを十分に満たすことができる。
 上記の態様においては、前記梁補強増打部は、排気用スリーブが配設されている部位に対応する箇所に空間部を備えること、が好ましい。
 この態様によれば、排気用スリーブは、梁補強増打部によって閉塞されず、既存建築物の室内からの排気を、排気用スリーブを通して室外に排出させる機能をそのまま維持でき、既存建築物の機能性は維持される。また、排気用スリーブが配設されている部位はごく限られた大きさであるため、空間部により、梁補強増打部の一部に増し打ちされない部分が存在していても、補強ユニットにより耐震補強された既存建築物は、十分な耐震強度を確保することができる。
 上記の態様においては、前記一対のL型補強ピースと前記一対のI型補強ピースは何れも、心材である鋼材と、コンクリートとを一体成形したプレキャストコンクリート部材であり、前記スタッドは前記鋼材に固着されていること、が好ましい。
 この態様によれば、既存建築物の耐震補強現場でスタッドを鋼材に固着しようとすると、スペース上、制約が多く、スタッドの固着作業が効率良くできないが、補強ピースの製造工場にある専用設備で、スタッドを固着すれば、スタッド固着の生産性が向上するため、補強ユニットのコストが低減できる。また、スタッドを鋼材に溶接で固着する場合には、スタッドを鋼材に溶接するためだけに、溶接機や養生シートを、耐震補強現場に持ち込む必要がない。加えて、スタッドを鋼材に溶接するためだけに、溶接技術の有資格者を、耐震補強現場に人員配置する必要がなくなる。さらに、本発明の耐震補強工法は、接着剤の強度発現に至るまでに一定の所要時間を必要とする接着接合の工法とは異なり、上記一定の所要時間を一切必要としない。そのため、スタッドが前もって工場で鋼材に固着されていれば、耐震補強現場に搬入されたスタッド付の補強ピースに対し、次の補強ピース組立工程に向けた準備に、すぐに取りかかることができるため、耐震補強工事の工期短縮に貢献することができる。
 本発明に係る耐震補強工法によれば、補強後の建築物の居住性、機能性、採光に対する影響が十分に小さくなる。
実施形態1の実施例1において、補強ユニットの概略正面を示した図である。 実施形態1の実施例1において、補強ユニットを構成する補強ピースの概略正面図である。 実施形態1の実施例1において、既設仕上げ撤去を行うことを示す図である。 実施形態1の実施例1において、既存柱と既存梁に対してアンカー穿孔などを行うことを示す図である。 実施形態1の実施例1において、増し打ち予定部に目荒らしと配筋を行うことを示す図である。 実施形態1の実施例1において、増し打ち予定部にコンクリート打設を行うことを示す図である。 実施形態1の実施例1において、柱補強増打部と梁補強増打部にアンカー穿孔を行うことを示す図である。 実施形態1の実施例1において、左側のI型補強ピースを取り付けることを示す図である。 実施形態1の実施例1において、左側のL型補強ピースを取り付けることを示す図である。 図9の図面左側から柱補強増打部を透視して継手部のフランジ部を見たときの図である。 実施形態1の実施例1において、右側のI型補強ピースを取り付けることを示す図である。 実施形態1の実施例1において、右側のL型補強ピースを取り付けることなどを示す図である。 実施形態1の実施例1において、柱補強増打部と補強ユニットとの間や梁補強増打部と補強ユニットとの間にエポキシ樹脂を注入することを示す図である。 実施形態1の実施例1において、I型補強ピースとL型補強ピースとの継手部などにグラウトを注入することを示す図である。 実施形態1の実施例1の耐震補強工法による耐震補強工事の完了後の柱補強増打部と梁補強増打部と補強ユニット、およびそれらの周辺の概略正面図である。 図15のA-A断面図である。 図15のB-B断面図である。 I型補強ピースとL型補強ピースとの配置位置を変更した例において、図16に対応する断面図である。 I型補強ピースとL型補強ピースとの配置位置を変更した例において、図17に対応する断面図である。 実施形態1の実施例2の耐震補強工法による耐震補強工事の完了後の柱補強増打部と梁補強増打部と補強ユニット、およびそれらの周辺の概略正面図である。 実施形態1の変形例1の補強ユニットの概略正面を示した図である。 実施形態1の変形例2に係る耐震補強工法を説明する図であり、図15に相当する概略正面図である。 図22のF-F矢視断面図である。 図22のG-G矢視断面図である。 実施形態2のうち、実施例1に係る補強ユニットを概略的に示す正面図であり、補強ピースが組み立てられた状態で示す図である。 図25に示す補強ユニットの正面図であり、補強ピースが分解された状態で示す図である。 実施形態2のうち、実施例1に係る補強ユニットを構成する補強ピースの断面図であり、図26中、H-H矢視断面、I-I矢視断面に相当する断面図である。 既存柱及び既存梁において、増し打ち予定部で既設仕上げの撤去を行う第1工程図である。 既存柱及び既存梁において、増し打ち予定部でアンカー孔の穿孔と目荒らしを行う第2工程図である。 実施形態2のうち、実施例1に係る耐震補強工法の補強ピース組立工程の工程図であり、左側のI型補強ピースを配置した様子を示す第3工程図である。 図30に続く工程図であり、左側のI型補強ピースと左側のL型補強ピースとを接合しようとする様子を示す第4工程図である。 実施形態2のうち、実施例1に係る補強ユニットで、補強ピース同士を繋ぐ継手部を説明する図であり、図31中、J矢視位置からH型鋼の既存柱側のフランジ部を見たときの図である。 図31に続く工程図であり、左側のI型補強ピースと左側のL型補強ピースとを接合した後、右側のI型補強ピースを配置した様子を示す第5工程図である。 図33に続く工程図であり、右側のL型補強ピースを、右側のI型補強ピースと、左側のI型補強ピースと接合した左側のL型補強ピースとに、それぞれ接合しようとする様子を示す第6工程図である。 図34に続く工程図であり、左右のI型補強ピースと左右のL型補強ピースとが接合されて門型形状に形成された様子を示す第7工程図である。 図35に続く工程図であり、実施形態2のうち、実施例1に係る耐震補強工法の柱補強配筋工程及び梁補強配筋工程を説明する第8工程図である。 図36に続く工程図であり、実施形態2のうち、実施例1に係る耐震補強工法の補強ユニット固定工程を説明する第9工程図である。 図37に続く工程図であり、補強ピース同士を繋ぐ継手部をグラウトで埋めた様子を示す第10工程図である。 図38に続く工程図であり、補強ユニットと増し打ち部に表面仕上げを施して耐震補強工事が完了した様子を示す第11工程図である。 図39中、K-K矢視断面図である。 図39中、L-L矢視断面図である。 実施形態2のうち、実施例1に係る補強ユニットを既存柱梁フレームに配置する位置を変更した第1の場合を示す説明図であり、図39中、K-K矢視位置に相当する断面図である。 図42と同じ場合の説明図であり、図39中、L-L矢視位置に相当する断面図である。 実施形態2のうち、実施例1に係る補強ユニットを既存柱梁フレームに配置する位置を変更した第2の場合を示す説明図であり、図39中、K-K矢視位置に相当する断面図である。 実施形態2のうち、実施例2に係る耐震補強工法により、耐震補強された既存建築物を概略的に示す正面図であり、図39に相当する説明図である。 実施形態2のうち、実施例1,2の変形例に係る補強ユニットを概略的に示す正面図であり、図25に相当する説明図である。
 次に、本発明に係る耐震補強工法を具体化した実施形態1,2について、図面を参照して説明する。説明では、実施形態1において実施例1,2、及び変形例1,2を挙げ、実施形態2において、実施例1,2、及び変形例を挙げる。
 (実施形態1)
<実施例1>
 まず、実施例1について説明する。そこで、まず、補強ユニット10について説明する。ここで、図1は、補強ユニット10の概略正面を示した図である。また、図2は、補強ユニット10を構成する補強ピースの概略正面図である。
 補強ユニット10は、図1と図2に示すように、直交する2辺で構成される2つのL型補強ピース12と、この2つのL型補強ピース12の各々の一辺を延長するように接続される2つのI型補強ピース14とを備えている。そして、補強ユニット10は、前記の2つのL型補強ピース12の他の一辺の先端同士が接続されるように左右対称に接合することで、門型状に構成されている。この補強ユニット10は、鉄骨にコンクリートを巻いた補強部材である。
 L型補強ピース12は、L字状に形成されている。このL型補強ピース12は、後述する梁補強増打部64(図6など参照)に配置される上辺部16と、該上辺部16に直交し後述する柱補強増打部62(図6など参照)に配置される縦柱部18と、を備えている。
 I型補強ピース14は、角柱状に形成されている。このI型補強ピース14は、耐震補強の施工時にて、柱補強増打部62に配置され、上端が前記のL型補強ピース12の縦柱部18の下端に接続される。そして、I型補強ピース14は、下端にて、後述するバルコニースラブ36(図3など参照)に載置されるベースプレート20を備えている。
 L型補強ピース12とI型補強ピース14は、各々、鋼材を骨としてその周囲にコンクリートが巻かれている、所謂鉄骨コンクリートである。鋼材にはH型鋼が用いられており、その周りに巻かれているコンクリートは一般的なSRC(Steel Reinforced Concrete)造に用いられるようなものでも良いし、繊維補強コンクリートのようなものでも良い。このL型補強ピース12の骨となるH型鋼22は、直交するように溶接された2辺からなるものである。また、I型補強ピース14の骨となるH型鋼24は、直線状のものである。
 また、I型補強ピース14のH型鋼24の下端にはベースプレート20が、該ベースプレート20上にH型鋼24の下端部が当接するように載置され、溶接により固定されている。
 さらに、L型補強ピース12のH型鋼22の端部とI型補強ピース14のH型鋼24の端部とには、各々、ボルト穴26が設けられている。なお、ボルト穴26の位置や数は特に限定されない。
 次に、実施例1の耐震補強工法の内容について説明する。実施例1の耐震補強工法は、大きく分けて、増し打ち工程と補強ピース固定工程を有する。
(増し打ち工程)
 まず、増し打ち工程について説明する。この増し打ち工程では、まず、既設仕上げ撤去を行う。具体的には、図3に示すように、既存建築物1の既存柱30と既存梁32とから構成される既存柱梁フレーム34の仕上げ部材(例えば、タイルなどの外壁材や塗装など)を撤去する。さらに詳しくは、既存柱30について、外側(図3の紙面手前側)の面にてバルコニースラブ36を除いた部分の増し打ち予定部38における仕上げ部材を撤去する。また、既存梁32について、外側(図3の紙面手前側)の面にて、増し打ち予定部40における仕上げ部材を撤去する一方で、既存柱梁フレーム34の開口部42側の部分44と排気用スリーブ46の周辺の部分における仕上げ部材は撤去しない。ここで、増し打ち予定部40とは、既存梁32において、バルコニースラブ36側にある部分であって、排気用スリーブ46の周辺を除いた部分である。
 次に、鉄筋探査やアンカー穿孔などを行う。具体的には、既存柱30と既存梁32の内部の鉄筋を探査して、既存柱30と既存梁32の内部の鉄筋を避けながら、図4に示すように、アンカー用の孔48を形成する。さらに詳しくは、既存柱30の増し打ち予定部38と既存梁32の増し打ち予定部40に、複数のアンカー用の孔48を形成する。また、このとき、バルコニースラブ36に、当該バルコニースラブ36の板厚方向(図4の上下方向)に貫通する貫通孔50を形成する。
 次に、目荒らしと配筋を行う。具体的には、既存柱30の増し打ち予定部38や既存梁32の増し打ち予定部40におけるアンカー用の孔48(図4参照)に、各種の鉄筋を配置する。図5に示すように、詳細には、増し打ち予定部38に、既存柱30に平行に配置される鉄筋の柱補強主筋52と、前記の柱補強主筋52の直交方向に巻かれる鉄筋の補強帯筋54とを配置する。また、増し打ち予定部40に、既存梁32と平行に配置される梁補強主筋56と、前記の梁補強主筋56の直交方向に巻かれる補強肋筋58とを配置する。
 また、既存柱30の増し打ち予定部38と既存梁32の増し打ち予定部40に対し、目荒らしを行う。ここで、「目荒らし」とは、あとで打ち継ぐ新しいコンクリートとの一体性を向上させるために、旧コンクリートの表面に凹凸を形成して粗く仕上げる作業である。さらに、バルコニースラブ36の貫通孔50の下部にシース管60を設置する。
 次に、コンクリート打設を行う。具体的には、図6に示すように、既存柱30の増し打ち予定部38(図5参照)と既存梁32の増し打ち予定部40(図5参照)に、コンクリートを打ち込んで、柱補強増打部62と梁補強増打部64を形成する。このとき、既存梁32のうち、排気用スリーブ46が配設されている部位に対応する箇所には、梁補強増打部64を形成しないように空間部66を形成する。
 このようにして、増し打ち工程では、既存柱30の外側(図6の図面手前側)に、柱補強主筋52と補強帯筋54とを内設した柱補強増打部62をアンカーにより増し打ちする柱増し打ち工程を行う。また、増し打ち工程では、既存梁32の外側(図6の図面手前側)に、梁補強主筋56と補強肋筋58とを内設した梁補強増打部64をアンカーにより増し打ちする梁増し打ち工程も行う。但し、梁増し打ち工程において、梁補強増打部64に空間部66を形成することにより、既存梁32のうち、排気用スリーブ46が配設されている部位に対応する箇所には、梁補強増打部64を増し打ちしないようにする。
 また、増し打ち工程では、既存梁32の一部の増し打ち予定部40にコンクリートを打ち込んで梁補強増打部64を形成する。そして、このようにして、梁補強増打部64の高さ(上下方向の幅)を、既存梁32の高さ(上下方向の幅)よりも小さくする。より詳しくは、図6や後述する図16に示すように、梁補強増打部64の高さhを、既存梁32におけるバルコニースラブ36よりも下側の部分の高さHよりも小さくする。以上のようにして、増し打ち工程を行う。
(補強ピース固定工程)
 次に、補強ピース固定工程について説明する。この補強ピース固定工程では、まず、柱補強増打部62と梁補強増打部64にアンカー穿孔を行う。具体的には、図7に示すように、柱補強増打部62と梁補強増打部64にコンクリートドリルでアンカー用の孔68を形成する。図7に示す例においては、左右の柱補強増打部62と、梁補強増打部64とに各々、4つのアンカー用の孔68を形成しているが、アンカー用の孔68の数は特に限定されない。また、このとき、貫通孔50とシース管60の内部に貫通ボルト70を配置する。なお、このとき、下の階にて既に補強ユニット10の施工が完了していることが好ましい。
 次に、左側のI型補強ピース14を取り付ける。具体的には、図8に示すように、I型補強ピース14を左側の柱補強増打部62に寄せてベースプレート20にて貫通ボルト70を仮締めすることにより、I型補強ピース14を取り付ける。
 次に、左側のL型補強ピース12を取り付ける。具体的には、図9に示すように、L型補強ピース12を、I型補強ピース14の上側にて、左側の柱補強増打部62と梁補強増打部64に寄せて配置する。そして、L型補強ピース12の継手部71(H型鋼22)とI型補強ピース14の継手部72(H型鋼24)にて、プレート74を介してボルトを仮締めする。このとき、継手部71のフランジ部73Aと継手部72のフランジ部75Aにおいても、プレート77を介してボルトを仮締めする。また、継手部71のフランジ部73Bと継手部72のフランジ部75Bにおいても、プレート79を介してボルトを仮締めする。これにより、L型補強ピース12を取り付ける。なお、このとき、L型補強ピース12をサポート部材76で支えておく。
 なお、図9の図面左側から柱補強増打部62を透視して継手部71のフランジ部73Bと継手部72のフランジ部75Bを見たときの図を、図10に示す。図10に示すように、継手部71のフランジ部73Bと継手部72のフランジ部75Bの左側(室内側)には、後述するアンカー固着を行うための孔81が形成されている。
 次に、右側のI型補強ピース14を取り付ける。具体的には、図11に示すように、新たなI型補強ピース14を右側の柱補強増打部62に寄せてベースプレート20にて貫通ボルト70を仮締めすることにより、I型補強ピース14を取り付ける。
 次に、右側のL型補強ピース12を取り付けて、継手部のボルト本締めとアンカー固着を行う。具体的には、図12に示すように、新たなL型補強ピース12を、右側のI型補強ピース14の上側にて、右側の柱補強増打部62と梁補強増打部64に寄せて配置する。このとき、L型補強ピース12をサポート部材76で支えておく。
 そして、左側のL型補強ピース12の継手部71と左側のI型補強ピース14の継手部72にて、プレート74を介してボルトを本締めする。このとき、継手部71のフランジ部73Aと継手部72のフランジ部75Aにおいても、プレート77を介してボルトを本締めする。また、継手部71のフランジ部73Bと継手部72のフランジ部75Bにおいても、プレート79を介してボルトを本締めする。また、右側のL型補強ピース12の継手部71と右側のI型補強ピース14の継手部72にて、プレート74を介してボルトを本締めする。このとき、継手部71のフランジ部73Aと継手部72のフランジ部75Aにおいても、プレート77を介してボルトを本締めする。また、継手部71のフランジ部73Bと継手部72のフランジ部75Bにおいても、プレート79を介してボルトを本締めする。また、右側のL型補強ピース12の継手部78(H型鋼22)と左側のL型補強ピース12の継手部78にて、プレート80を介してボルトを本締めする。
 なお、L型補強ピース12同士およびL型補強ピース12とI型補強ピース14との固定方法としては、溶接も考えられ、その様な接合方法を否定するものではないが、耐震補強という目的を前提と考えれば、補強ユニット10は一体的に構成される方が強度を上げることができるので、機械的に接合する方が望ましい。溶接を行う場合は、現地で溶接機や電源を必要とするため、余分にコストがかかるなどの問題もあるため、ボルト等で容易に締結できる方がメリットは大きい。
 また、前記のように一対のL型補強ピース12と一対のI型補強ピース14とから構成された補強ユニット10を、柱補強増打部62と梁補強増打部64に接着系アンカーにて固着させる。具体的には、柱補強増打部62と梁補強増打部64に形成したアンカー用の孔68に、ケミカルと一緒に寸切ボルト82を継手部71のフランジ部73Bと継手部72のフランジ部75Bの孔81(図10参照)を介して埋め込んだ後、前記のケミカルを硬化させる。ここで、アンカーの種類は特に限定されるものではなく、ホールインアンカーやケミカルアンカー等、柱や梁に突起状の物体を一体的に施工できるものであればよい。
 また、柱補強増打部62と補強ユニット10との間の隙間や梁補強増打部64と補強ユニット10との間の隙間に、後述するようにエポキシ樹脂を注入するためにエポキシ樹脂パテ材によりシールをする。
 次に、接着用樹脂であるエポキシ樹脂の注入を行う。具体的には、図13に示すように、柱補強増打部62と補強ユニット10との間の隙間や梁補強増打部64と補強ユニット10との間の隙間にエポキシ樹脂パテ材によりシールをし、エポキシ樹脂を注入する。これにより、柱補強増打部62と梁補強増打部64の三方に樹脂部84を形成する。なお、I型補強ピース14のベースプレート20の下にもエポキシ樹脂を注入する場合がある。
 次に、継手部へのグラウトの注入を行う。具体的には、L型補強ピース12の継手部71(図13参照)およびI型補強ピース14の継手部72(図13参照)と、左右のL型補強ピース12の間の継手部78(図13参照)と、左右のI型補強ピース14の下端の継手部86(図13参照)とに、図14に示すように、グラウト88を注入する。グラウト88は、無収縮モルタルで構成しても良いが、本実施例では、補強ユニット10の強度をより強くするため、繊維補強コンクリートを使用している。
 次に、仕上げを行う。具体的には、図15に示すように、柱補強増打部62と梁補強増打部64と補強ユニット10の表面に、仕上げ部材を取り付けたり塗装を施したりして、外壁の仕上げを行う。これにより、柱補強増打部62と梁補強増打部64と補強ユニット10とを目立たなくすることで、外観上も耐震補強している建築物であることが気にならなくなる。
 ここで、図15のA-A断面図を図16に示し、図15のB-B断面図を図17に示す。図16に示すように、L型補強ピース12は、梁補強増打部64の内側に、樹脂部84を介して、寸切ボルト82と補強プレート90とを用いてアンカー止めされている。図17に示すように、I型補強ピース14は、柱補強増打部62の内側に、樹脂部84を介して、寸切ボルト82と補強プレート92とを用いてアンカー止めされている。なお、図17にて既存梁32の位置を仮想線で示すとおり、既存柱30の外側(室外側、図17の下側)の面31は、既存梁32の外側(室外側、図17の下側)の面33と面一にしている。
 このようにして、補強ピース固定工程では、柱補強増打部62と梁補強増打部64に対して、一対のL型補強ピース12と一対のI型補強ピース14とをアンカー止めし、柱補強増打部62と梁補強増打部64と、一対のL型補強ピース12と一対のI型補強ピース14との間にエポキシ樹脂を注入する。以上により、本実施例の耐震補強工法が完了する。
 以上のような実施例1では、以下の効果を得ることができる。実施例1では、既存建築物1の既存柱30と既存梁32から構成される既存柱梁フレーム34を補強するユニットにより耐震補強する工法であって、一対のL型補強ピース12と、一対のI型補強ピース14とボルトで結合させて門型の補強ユニット10を組み立てる耐震補強工法において、既存柱30の外側に、既存柱30に平行に配置される柱補強主筋52と、柱補強主筋52の直交方向に巻かれる補強帯筋54とを内設した柱補強増打部62をアンカーにより増し打ちする柱増し打ち工程と、既存梁32の外側に、既存梁32と平行に配置される梁補強主筋56と、梁補強主筋56の直交方向に巻かれる補強肋筋58とを内設した梁補強増打部64をアンカーにより増し打ちする梁増し打ち工程と、柱補強増打部62と梁補強増打部64に対して、一対のL型補強ピース12と一対のI型補強ピース14とをアンカー止めし、柱補強増打部62と梁補強増打部64と、一対のL型補強ピース12と一対のI型補強ピース14との間にエポキシ樹脂を注入する補強ピース固定工程と、を有する。
 このように、柱補強増打部62と梁補強増打部64と補強ユニット10によって、既存建築物1の柱と梁の曲げ耐力およびせん断耐力を増加させることで、既存建築物1の耐力と靭性を向上させることができる。
 そして、既存柱30の外側に増し打ちする柱補強増打部62と既存梁32の外側に増し打ちする梁補強増打部64に対して一対のL型補強ピース12と一対のI型補強ピース14とからなる門型状の補強ユニット10を固定するので、補強ユニット10によって既存柱梁フレーム34の開口部42の開口面積が小さくなることを抑制できる。そのため、既存柱梁フレーム34の開口部42が既存建築物1への出入口のような場合に、人の出入りに支障が生じ難い。また、既存柱梁フレーム34の開口部42に設置される窓や戸から既存建築物1の室内に採り込まれる太陽光が補強ユニット10によって遮断されることを抑制できる。さらに、既存柱梁フレーム34の開口部42に設置される窓や戸の開閉に支障を来たすおそれがなくなる。したがって、補強後の既存建築物1の居住性、機能性、採光に対する影響が十分に小さくなる。
 また、梁補強増打部64は、排気用スリーブ46が配設されている部位に対応する箇所に空間部66を備える。すなわち、既存梁32のうち、排気用スリーブ46が配設されている部位に対応する空間部66には、梁補強増打部64を増し打ちしない。これにより、排気用スリーブ46が梁補強増打部64により閉塞されないので、排気用スリーブ46を通して既存建築物1の室内から排気を問題なく既存建築物1の外部に排出することができる。そのため、既存建築物1の機能性を維持することができる。そして、このように梁補強増打部64の一部に増し打ちされない部分が存在していても、前記のように既存柱30の外側に柱補強主筋52と補強帯筋54とを内設した柱補強増打部62と既存梁32の外側に梁補強主筋56と補強肋筋58とを内設した梁補強増打部64を増し打ちした構造下にて補強ユニット10のH型鋼22やH型鋼24が耐震強度を保っており、また、排気用スリーブが配設されている部位はごく限られた大きさなので、十分な耐震補強の強度を確保することができる。このことは、後述するように、耐震強度の評価実験で実証されている。
 また、梁補強増打部64の高さhを既存梁32の高さHよりも小さくするので、補強ユニット10によって既存柱梁フレーム34の開口部42の開口面積が小さくなることを確実に抑制できる。そのため、より確実に、補強後の既存建築物1の居住性、機能性、採光に対する影響が十分に小さくなる。
 また、補強ユニット10はL型補強ピース12とI型補強ピース14に分割できるので、搬入がし易くなり、特別にL型補強ピース12とI型補強ピース14の搬入経路を確保しなくても済むようになる可能性が高い。
 なお、L型補強ピース12とI型補強ピース14を配置する位置は、適宜変更可能である。例えば、図18に示すようにL型補強ピース12を既存梁32に接触させて、かつ、図19に示すようにI型補強ピース14を既存柱30と柱補強増打部62とに対してアンカー止めするようにして、L型補強ピース12とI型補強ピース14を配置してもよい。なお、このとき、図19にて既存梁32の位置を仮想線で示すとおり、既存柱30の外側の面31は、既存梁32の外側の面33よりも外側(室外側、図19の下側)に突出している。
<実施例2>
 また、実施例2として、図20に示すように、既存梁32に排気用スリーブ46が形成されておらず、梁補強増打部64に前記の空間部66を形成していない実施例も考えられる。この実施例2によれば、前記の実施例1の効果に加えて、耐震強度をさらに向上させる効果を得ることができる。
<変形例1>
 その他、変形例1として、補強ユニット10を図21に示すような形状にしてもよい。図21に示す変形例では、L型補強ピース12について、そのL字の内側を肉厚とし、既存柱30に平行な方向(図21の上下方向)のL型補強ピース12の幅を大きくしている。
<変形例2>
 図22は、実施形態1のうちの変形例2に係る耐震補強工法を説明する図であり、図15に相当する概略正面図である。図23は、図22のF-F矢視断面図であり、図24は、図22中、L型補強ピースとI型補強ピースとの接続部付近に相当するG-G矢視断面図である。
 変形例2では、図22~図24に示すように、既存建築物1Aにおいて、梁補強増打部64が、既存梁32の外側の面33とバルコニースラブ36下面とに接して設けられ、L型補強ピース12(補強ユニット10)が、H型鋼22のフランジ部を挿通した寸切ボルト82により、梁補強増打部64下面に、樹脂部84を介して固定されている。また、柱補強増打部62が、既存柱30の外側の面31に接して設けられ、I型補強ピース14(補強ユニット10)のH型鋼22のフランジ部75Aと、L型補強ピース12の開口部42内側のフランジ部を繋ぐプレート77とが、ボルト締めされている。また、このI型補強ピース14のフランジ部75Bと、L型補強ピース12の開口部42外側のフランジ部を繋ぐプレート79とが、ボルト締めされている。そして、フランジ部75Aの屋内側(図24中、上側)を挿通した寸切ボルト82により、I型補強ピース14が、柱補強増打部62側面に、樹脂部84を介して固定されている。
<耐震強度の評価>
 以上のような本発明の耐震補強工法により補強した建築物について、水平載荷試験を行って、その耐震強度の評価を行った。当該評価は、本発明の耐震補強工法を施工していない既存建築物1と同等な構造からなる既存構造試験体と、本発明の耐震補強工法を施工した前記の実施例1と同等な構造からなる第1構造試験体と、本発明の耐震補強工法を施工した前記の実施例2と同等な構造からなる第2構造試験体と、を使用して行った。
 このような評価の結果、耐えうる最大層せん断力は、既存構造試験体が235.5kNであったのに対して、第1構造試験体が420.0kNとなり、第2構造試験体が524.5kNとなった。すなわち、耐えうる最大層せん断力の値が、既存構造試験体に対して、第1構造試験体は約80%増加し、第2構造試験体は約123%増加した。このように、本発明の耐震補強工法によれば、十分な耐震補強の強度が得られることが分かった。なお、前記の梁補強増打部64に空間部66が存在する構造の第1構造試験体においても十分な耐震補強の強度が得られたのは、補強ユニット10の鉄枠(H型鋼22やH型鋼24)が耐震強度を保つためと考えられる。
 (実施形態2)
 次に、本発明に係る耐震補強工法を具体化した実施形態2を、実施例1,2と、その変形例とを挙げて図面を参照して説明する。
<実施例1>
 まず、本発明に係る耐震補強工法に用いる補強ユニットについて説明する。図25は、実施形態2のうち、実施例1に係る補強ユニットを概略的に示す正面図であり、補強ピースが組み立てられた状態で示す図である。図26は、図25に示す補強ユニットの正面図であり、補強ピースが分解された状態で示す図である。
 補強ユニット110は、図25及び図26に示すように、直交する2辺で構成される2つのL型補強ピース112と、この2つのL型補強ピース112の各々の一辺を延長するように接続される2つのI型補強ピース114とを備えている。そして、補強ユニット110は、2つのL型補強ピース112の他の一辺の先端同士が接続されるように左右対称に接合することで、門型状に構成されている。この補強ユニット110は、L型補強ピース112とI型補強ピース114とも、鋼材を骨としてその周囲にコンクリートを被覆した、所謂鉄骨コンクリート製の補強部材からなる。図27は、実施形態2のうち、実施例1に係る補強ユニットを構成する補強ピースの断面図であり、図26中、H-H矢視断面、I-I矢視断面に相当する断面図である。
 具体的には、L型補強ピース112は、L字型形状に形成されている。このL型補強ピース112は、図27に示すように、心材であるH型鋼122と、コンクリート123とを一体成形したプレキャストコンクリート部材である。L型補強ピース112では、H型鋼122は、2つの鋼材をL字型形状に直交させて溶接した二辺からなり、このH型鋼122の端部にはそれぞれ、複数のボルト穴126が穿孔されている。また、H型鋼122のフランジ部173Bには、複数の頭付スタッド113(頭付スタッド113H,113V)が、一定間隔を持って2列状に、溶接により固着されている。L型補強ピース112は、後述するように、梁補強増打部164で固定される上辺部116と、柱補強増打部162で固定され、この上辺部116に直交する縦柱部118と、を備えている(図36等参照)。なお、後述する左側のL型補強ピース112では、頭付スタッド113Hと、既存建築物101の排気用スリーブ146との干渉を避けるため、図26に示すように、スタッド欠落部117が設けられている。
 一方、I型補強ピース114は、角柱状に形成されている。このI型補強ピース114は、図27に示すように、心材であるH型鋼124と、コンクリート125とを一体成形したプレキャストコンクリート部材である。I型補強ピース114では、H型鋼124は、一辺からなる直線状の鋼材であり、このH型鋼124の上端部に、複数のボルト穴126が穿孔されている。H型鋼124のフランジ部175Bには、複数の頭付スタッド115が、一定間隔を持って2列状に、溶接により固着されている。I型補強ピース114は、耐震補強の施工時に、上端をL型補強ピース112の縦柱部18下端と接合され、柱補強増打部162で固定される。また、このI型補強ピース114は、下端に、後述する既存建築物101のバルコニースラブ136に固定させるベースプレート120を備え、このベースプレート120は、H型鋼124の下端部と当接して、溶接により固着されている(図30等参照)。
 なお、L型補強ピース112とI型補強ピース114では、H型鋼122,124の周りに被覆したコンクリート123,125は、繊維補強コンクリート等である。また、本実施形態2では、図25等に図示されたL型補強ピース112において、上辺部116の高さ方向寸法(図26中、上下方向の大きさ)が、縦柱部118の幅方向寸法(図26中、左右方向の大きさ)より小さくなっているが、高さ方向寸法と幅方向寸法との大小関係は、既存建築物101で必要とされる耐震補強に応じて、決定されるものである。よって、高さ方向寸法と幅方向寸法との大小関係は、幅方向寸法と高さ方向寸法が同じ場合もあり得る等、特に限定されるものではない。また、H型鋼122,124の端部に設けるボルト穴126の位置や数は、特に限定されるものではない。
 次に、実施形態2の耐震補強工法について説明する。実施形態2では、耐震補強工法は、大別して、増し打ち準備工程、補強ピース組立工程、柱補強配筋工程、梁補強配筋工程、補強ユニット固定工程、及び補強ユニット仕上げ工程を有する。
(増し打ち準備工程)
 はじめに、増し打ち準備工程について、図28及び図29を用いて説明する。増し打ち準備工程は、まず増し打ち予定部における既設仕上げを撤去し、鉄筋探査やアンカー穿孔等を行った後、撤去した既設仕上げ部分の目荒らしを行う。図28は、既存柱及び既存梁において、増し打ち予定部で既設仕上げの撤去を行う第1工程図である。図29は、既存柱及び既存梁において、増し打ち予定部でアンカー孔の穿孔と目荒らしを行う第2工程図である。
 具体的には、図28に示すように、既存建築物101において、既存柱130と既存梁132とから構成される既存柱梁フレーム134で、既存柱130のうち、バルコニースラブ136を除く外側(図28の紙面手前側)の外面131に施されている仕上げ部材(例えば、タイルなどの外壁材や塗装等)を撤去する。この仕上げ部材を撤去した既存柱130の外面131が増し打ち予定部138である。また、この既存柱梁フレーム134で、既存梁132の外側(図28の紙面手前側)である外面133のうち、下端側外面部144と排気用スリーブ46の周辺部を除く部分で、バルコニースラブ136に近接する側(既存梁132の上端側)に施されている仕上げ部材を撤去する。既存梁132の外面133で、この仕上げ部材を撤去した部分が、増し打ち予定部140である。
 次に、鉄筋探査やアンカー穿孔等を行う。具体的には、既存柱130と既存梁132とにそれぞれ内設されている鉄筋を探査し、これらの鉄筋を避けながら、図29に示すように、既存柱130の増し打ち予定部138と既存梁132の増し打ち予定部140にそれぞれ、複数のアンカー用孔148を穿孔する。また、バルコニースラブ136に、当該バルコニースラブ136の板厚方向(図29中、上下方向)に貫通する貫通孔150を穿孔する。この貫通孔150は、I型補強ピース114のベースプレート120を、バルコニースラブ136に固定させるのに用いるアンカーやボルトを挿通するために穿孔される。
 本実施形態2では、シース管160が、バルコニースラブ136の下部に、この貫通孔150と連通して設けられている。そして、後述する固定ボルト170が、I型補強ピース114のベースプレート120のボルト挿通孔(不図示)から貫通孔150を通じて挿通され、シース管160内に設けた雌ネジ(不図示)と螺合する。このとき、貫通ボルト70を、貫通孔150とシース管160の内部に配置するにあたり、下階において、補強ユニット10の施工が既に完了していることが好ましい。なお、固定ボルト170は、接着剤と共に用いる寸切ボルトでも良く、接着剤を硬化させて寸切ボルトを固定しても良い。また、固定ボルト170及び雌ネジに代えてアンカーを用いて良い。このアンカーの種類は特に限定されるものではなく、ホールインアンカーやケミカルアンカー等、I型補強ピース114のベースプレート120をバルコニースラブ136と一体的に施工できるものであれば良い。あるいは、I型補強ピース114のベースプレート120を、バルコニースラブ136に接着剤で固定しても良く、この場合には、貫通孔150が不要になる。
 次いで、既存柱130の増し打ち予定部138と既存梁132の増し打ち予定部140に、目荒らしを行う。「目荒らし」とは、旧コンクリートの表面に凹凸を形成することにより、この表面を粗くし、旧コンクリートの表面と、後に打ち継ぐ新しいコンクリートとの一体性を向上させるために行う作業である。
(補強ピース組立工程)
 次に、本発明の補強ピース組立工程について、図30~図34を用いて説明する。図30は、実施形態2のうち、実施例1に係る耐震補強工法の補強ピース組立工程の工程図であり、左側のI型補強ピースを配置した様子を示す第3工程図である。図31は、図30に続く工程図であり、左側のI型補強ピースと左側のL型補強ピースとを接合しようとする様子を示す第4工程図である。図32は、図31中、J矢視位置からH型鋼の既存柱側のフランジ部を見たときの図である。図33は、図31に続く工程図であり、左側のI型補強ピースと左側のL型補強ピースとを接合した後、右側のI型補強ピースを配置した様子を示す第5工程図である。図34は、図33に続く工程図であり、右側のL型補強ピースを、右側のI型補強ピースと、左側のI型補強ピースと接合した左側のL型補強ピースとに、それぞれ接合しようとする様子を示す第6工程図である。
 補強ピース組立工程は、既存柱130の外側(図30の紙面手前側で、既存建築物101の屋外側)で、一対のI型補強ピース114を既存柱130に沿う位置に配置すると共に、既存梁132の外側(図30の紙面手前側で、既存建築物101の屋外側)で、一対のL型補強ピース112を既存柱130と既存梁132に沿う位置に配置し、一対のI型補強ピース114と一対のL型補強ピース112とを組み立てる。
 本実施形態2では、一つ目のピースとして、はじめに左側のI型補強ピース114を、既存柱梁フレーム134の左側の既存柱130に沿う位置に配置して設置する。具体的には、図30に示すように、左側の既存柱130のうち、開口部142に面する側の側面(図30中、右側側面)と、I型補強ピース114のH型鋼124のフランジ部175Bとが面一となる位置まで、I型補強ピース114を左側の既存柱130に寄せ、I型補強ピース114のベースプレート120をバルコニースラブ136上に載置する。そして、固定ボルト170を、ベースプレート120、貫通孔150に挿通して仮締めすることにより、I型補強ピース114が設置される。
 次に、一つ目のピースとして、左側のL型補強ピース112を、左側のI型補強ピース114の上方に、既存柱梁フレーム134の左側の既存柱130に沿う位置に配置すると共に、既存梁132の左側に寄せて配置して設置する。具体的には、図31に示すように、左側の既存柱130のうち、開口部142に面する側の側面(図30中、右側側面)と、左側のL型補強ピース112のH型鋼122のフランジ部173Bとが面一となる位置まで、L型補強ピース112を左側の既存柱130に寄せて配置する。このとき、L型補強ピース112の上辺部116と、床側のバルコニースラブ136との間をサポート部材176で支えておく。
 そして、左側のL型補強ピース112のH型鋼122と、左側のI型補強ピース114のH型鋼124とにおいて、継手部171と継手部172とをプレート174で繋ぎ合わせ、プレート174と継手部171とを、及びプレート174と継手部172とを、それぞれボルトで仮締めする。また、この継手部171のフランジ部173Aと、この継手部172のフランジ部175Aとをプレート177で繋ぎ合わせて、プレート177とフランジ部173Aとを、及びプレート177とフランジ部175Aとを、それぞれボルトで仮締めする。また、継手部171のフランジ部173Bと、継手部172のフランジ部175Bとをプレート179で繋ぎ合わせて、プレート179とフランジ部173Bとを、及びプレート179とフランジ部175Bとを、それぞれボルトで仮締めする。なお、プレート179は、図32に示すように、継手部171及び継手部172において、屋外側(図32中、左側)と屋内側(図32中、右側)の両側に、それぞれ配置される。
 次に、もう一つのピースとして、右側のI型補強ピース114を、既存柱梁フレーム134の右側の既存柱130に沿う位置に配置して設置する。具体的には、図33に示すように、右側の既存柱130のうち、開口部142に面する側の側面(図33中、左側側面)と、I型補強ピース114のH型鋼124のフランジ部175Bとが面一となる位置まで、I型補強ピース114を右側の既存柱130に寄せ、I型補強ピース114のベースプレート120をバルコニースラブ136上に載置する。そして、固定ボルト170を、ベースプレート120、貫通孔150に挿通して仮締めすることにより、I型補強ピース114が設置される。
 次に、もう一つのピースとして、右側のL型補強ピース112を、右側のI型補強ピース114の上方に、既存柱梁フレーム134の右側の既存柱130に沿う位置に配置すると共に、既存梁132の右側に寄せて配置して設置する。具体的には、図34に示すように、右側の既存柱130のうち、開口部142に面する側の側面(図34中、右側側面)と、右側のL型補強ピース112のH型鋼122のフランジ部173Bとが面一となる位置まで、L型補強ピース112を右側の既存柱130に寄せて配置する。このとき、右側のL型補強ピース112の上辺部116と、床側のバルコニースラブ136との間をサポート部材176で支えておく。
 そして、左側のL型補強ピース112のH型鋼122の継手部171と、左側のI型補強ピース114のH型鋼124の継手部172とにおいて、プレート174と継手部171とを、及びプレート174と継手部172とを、それぞれボルトを本締めして接合する。また、プレート177とフランジ部173Aとを、及びプレート177とフランジ部175Aとを、それぞれボルトを本締めして接合する。また、プレート179とフランジ部173Bとを、及びプレート179とフランジ部175Bとを、それぞれボルトを本締めして接合する。
 その一方で、右側のL型補強ピース112のH型鋼122と、右側のI型補強ピース114のH型鋼124とにおいて、継手部171と継手部172とをプレート174で繋ぎ合わせ、プレート174と継手部171とを、及びプレート174と継手部172とを、それぞれボルトを本締めして接合する。また、この継手部171のフランジ部173Aと、この継手部172のフランジ部175Aとをプレート177で繋ぎ合わせて、プレート177とフランジ部173Aとを、及びプレート177とフランジ部175Aとを、それぞれボルトを本締めして接合する。また、屋外側(図32中、左側)と屋内側(図32中、右側)で、継手部171のフランジ部173Bと、継手部172のフランジ部175Bとをプレート179で繋ぎ合わせて、プレート179とフランジ部173Bとを、及びプレート179とフランジ部175Bとを、それぞれボルトを本締めして接合する。さらに、図34及び図35に示すように、左側のL型補強ピース112のH型鋼122の継手部178と、右側のL型補強ピース112のH型鋼122の継手部178とを、プレート180で繋ぎ合わせて、プレート180を介して双方の継手部178を、それぞれボルトで本締めして接合する。また、左右両側のI型補強ピース114において、固定ボルト170を本締めして、各I型補強ピース114を固定する。
 かくして、左右両側のL型補強ピース112と、左右両側のI型補強ピース114とが、門型形状に組み立てられ、補強ユニット110にとして形成される。ところで、補強ユニット110では、図35に示すように、L型補強ピース112の頭付スタッド113VとI型補強ピース114の頭付スタッド115が、既存柱130の増し打ち予定部138に対向する位置に配置される。また、L型補強ピース112の頭付スタッド113Hが既存梁132の増し打ち予定部140に対向する位置に配置される。このとき、頭付スタッド113V,113H,115が、アンカー用孔148との干渉を回避した位置に配置されていないと、柱補強配筋工程で、柱補強主筋152と補強帯筋154を配筋するためのアンカー止めや、梁補強配筋工程で梁補強主筋156と補強肋筋158を配筋するためのアンカー止めができない。このことを回避するため、アンカー用孔148の穿孔位置を決定するのにあたり、注意を払う必要がある。
 なお、L型補強ピース112同士の固定、及びL型補強ピース112とI型補強ピース114との固定では、ボルト締めのほか、溶接構造も考えられる。しかしながら、既存建築物101の耐震補強が目的と考えれば、補強ユニット110自体が一体的に構成されると、補強ユニット110の強度を上げることができるので、上述した補強ピース同士の固定を、溶接構造とするよりも、機械的に接合する方が好ましい。そのほか、溶接構造の場合は、耐震補強工事現場に溶接機や電源を必要とするため、余分にコストがかかるなどの問題や、溶接では火を使うため、安全性の確保が困難となる場合が生じる虞もあるため、ボルト等で容易に締結できる方がメリットは大きい。
(柱補強配筋工程、及び梁補強配筋工程)
 次に、本発明の柱補強配筋工程及び梁補強配筋工程について、図36を用いて説明する。柱補強配筋工程と梁補強配筋工程とは、補強ピース組立工程後に行われる。図36は、図35に続く工程図であり、実施形態2のうち、実施例1に係る耐震補強工法の柱補強配筋工程及び梁補強配筋工程を説明する第8工程図である。
 図36に示すように、柱補強配筋工程では、一対のI型補強ピース114の頭付スタッド115と、一対のL型補強ピース112のうち、既存柱130に沿う縦柱部118の頭付スタッド113Vとが内設するよう、柱補強主筋152を既存柱130の外面131側に配筋し、柱補強主筋152に補強帯筋154を直交させて巻いた柱補強配筋部155を形成する。また、梁補強配筋工程では、一対のL型補強ピース112のうち、既存梁132に沿う上辺部116の頭付スタッド113Hが内設するよう、梁補強主筋156を既存梁132の外面133側に配筋し、梁補強主筋156に補強肋筋158を直交させて巻いた梁補強配筋部159を形成する。
 具体的には、既存柱130の増し打ち予定部138、及び既存梁132の増し打ち予定部140に穿孔した複数のアンカー用孔148に、各種の鉄筋を配置する。詳細には、図36に示すように、増し打ち予定部138に、既存柱130に平行に配置される柱補強主筋152(鉄筋)と、この柱補強主筋152と直交する方向に巻かれる鉄筋の補強帯筋154とが配置される。また、増し打ち予定部140に、既存梁132と平行に配置される梁補強主筋156(鉄筋)と、この梁補強主筋156の直交する方向に巻かれる補強肋筋158とが配置される。
(補強ユニット固定工程)
 次に、本発明の補強ユニット固定工程について、図37を用いて説明する。柱補強配筋工程、及び梁補強配筋工程の後、補強ユニット固定工程が行われる。補強ユニット固定工程は、柱補強配筋部155に打設して既存柱130の増し打ち予定部138を増し打ちすると共に、梁補強配筋部159に打設して既存梁132の増し打ち予定部140を増し打ちすることにより、補強ユニット110を固定する。図37は、図36に続く工程図であり、実施形態2のうち、実施例1に係る耐震補強工法の補強ユニット固定工程を説明する第9工程図である。
 具体的には、図37に示すように、既存柱130の増し打ち予定部138(図36参照)にコンクリートを打ち込み、柱補強配筋部155を内設させて打設することにより、柱補強増打部162を形成する。また、既存梁132の増し打ち予定部140(図36参照)にコンクリートを打ち込み、梁補強配筋部159を内設させて打設することにより、梁補強増打部164を形成する。
 これにより、L型補強ピース112の頭付スタッド113VとI型補強ピース114の頭付スタッド115が柱補強増打部162に、及びL型補強ピース112の頭付スタッド113Hが梁補強増打部164に、それぞれ内設した状態で固定される。そのため、補強ユニット110が、アンカー止めや接着剤を用いずに、柱補強増打部162と梁補強増打部164に固定させることができる。
 なお、本実施例1では、排気用スリーブ146が既存梁132に配設されている。そのため、梁補強増打部164は、排気用スリーブ146が配設されている部位に対応する箇所に空間部166を備えている。すなわち、排気用スリーブ146の配設位置に対応する箇所に空間部166を設けることにより、排気用スリーブ146を避けて梁補強増打部164が形成されている。
 ここで、梁補強増打部164について、後述する図41を用いて説明する。図39は、図38に続く工程図であり、補強ユニットと増し打ち部に表面仕上げを施して耐震補強工事が完了した様子を示す第11工程図であり、図39中、L-L矢視断面図を図41に示す。但し、図41は、図を見易くするため、梁補強配筋部のうちの梁補強主筋と補強肋筋とを省略して図示されている。
 梁補強配筋部159に打設された梁補強増打部164は、既存梁132の上端側(図41中、上側)に寄せ、バルコニースラブ136の下面と既存梁132の外面133とに接して設けられ、梁補強増打部164の高さH3が、既存梁132の高さ(梁せい)H1より小さくなっている。具体的には、梁補強増打部164の高さH3が、既存梁132において、バルコニースラブ136より下側部分の高さH2よりも小さく、梁補強増打部164の高さH3は、既存梁132の梁せいH1の1/2以下の高さである。すなわち、既存梁132の下面(開口部142に面する側の側面)(図41中、下側側面)から、開口部142側(図41中、下側)にせり出すL型補強ピース112の下面までのせり出し量h1が、既存建築物101の屋内にいる人にとって、居住性、機能性、及び採光性の影響をほとんど与えない大きさとなっている。
(補強ユニット仕上げ工程)
 次に、補強ユニット仕上げ工程について、図37~図39を用いて説明する。図38は、図37に続く工程図であり、補強ピース同士を繋ぐ継手部をグラウトで埋めた様子を示す第10工程図である。補強ユニット仕上げ工程では、グラウト188の注入と補強ユニット110の表面仕上げを行う。
 具体的には、柱補強増打部162と梁補強増打部164により固定された補強ユニット110で、L型補強ピース112とI型補強ピース114との縦柱接合部128(図37参照)と、L型補強ピース112同士の上辺接合部127(図37参照)と、左右のI型補強ピース114下端の支持部186とに、図38に示すように、グラウト188を注入する。グラウト188は、本実施例1では、補強ユニット110の強度をより強くするため、繊維補強グラウトが使用されているが、無収縮モルタルで構成しても良い。
 次いで、表面仕上げを行う。具体的には、図39に示すように、柱補強増打部162と梁補強増打部164と補強ユニット110の表面に、仕上げ部材の取り付け、または塗装を施すことにより、外壁の仕上げを行う。かくして、本実施例の耐震補強工法による耐震補強工事が完了する。図39に示すように、耐震補強後の既存建築物101では、柱補強増打部162と梁補強増打部164と補強ユニット110が目立たなく仕上げられているため、外観上も耐震補強している建築物であることが気にならなくなる。
 ところで、既存建築物101の既存柱梁フレーム134に補強ユニット110を配設するのにあたり、既存柱梁フレーム134の形態の違いによって、補強ユニット110の配設方法が異なる。そこで、補強ユニット110の配設方法のバリエーションについて、一例を挙げて説明する。図40は、図39中、K-K矢視断面図である。図42は、実施形態2のうち、実施例1に係る補強ユニットを既存柱梁フレームに配置する位置を変更した第1の場合を示す説明図であり、図39中、K-K矢視位置に相当する断面図である。図43は、図42と同じ場合の説明図であり、図39中、L-L矢視位置に相当する断面図である。図44は、実施形態2のうち、実施例1に係る補強ユニットを既存柱梁フレームに配置する位置を変更した第2の場合を示す説明図であり、図39中、K-K矢視位置に相当する断面図である。なお、図40~図44は、図を見易くするため、柱補強配筋部のうちの柱補強主筋と補強帯筋と、梁補強配筋部のうちの梁補強主筋と補強肋筋とを省略して図示されている。
(既存柱の外面と既存梁の外面が面一の既存柱梁フレームの場合)(実施例1の場合)
 図40及び図41に示すように、既存柱130の外面131と既存梁132の外面133とが面一の既存柱梁フレーム134では、柱補強増打部162が既存柱130の外面131の面上のみに形成され、I型補強ピース114が、既存柱130の奥行方向(図40中、上下方向)に外面131と隙間を持って配設されている。梁補強増打部164が、図41に示すように、バルコニースラブ136の下面と既存梁132の外面133に接して形成され、L型補強ピース112が、既存梁132の奥行方向(図41中、左右方向)に外面133と隙間を持って配設されている。そして、このような位置に配設されたI型補強ピース114とL型補強ピース112とが、それぞれ2つ門型形状に接合されている。
(既存柱の外面と既存梁の外面に段差を有する既存柱梁フレームの場合)(第1の場合)
 図42に示すように、既存梁132の外面133が、既存柱130の奥行方向(図42中、上下方向)に、既存柱130の外面131より屋内側(図42中、上側)にある既存柱梁フレーム134では、柱補強増打部162が既存柱130の外面131の面上のみに形成される。ここで用いるI型補強ピース114(L型補強ピース112)では、頭付スタッド115(頭付スタッド113V)が複数、所定ピッチ間隔で単列状に、H型鋼124のフランジ部175B(H型鋼122のフランジ部173B)に溶接で固着されている。但し、隣り合う頭付スタッド115(頭付スタッド113V)のピッチ間隔が、前述したように、頭付スタッド115(頭付スタッド113V)を2列状に配設する場合に比べ、例えば、1/2以下のピッチ等、小さくなっている。柱補強増打部162との一体的な強度を十分に得るためである。その一方で、梁補強増打部164が、図43に示すように、バルコニースラブ136の下面と既存梁132の外面133に接して形成され、L型補強ピース112が、既存梁132の外面133に近接して配設されている。そして、このような位置に配設されたI型補強ピース114とL型補強ピース112とが、それぞれ2つ門型形状に接合されている。
(柱補強増打部が既存柱外面に十分な奥行で形成できない制約がある場合)(第2の場合)
 既存梁132の外面133が、既存柱130の奥行方向(図44中、上下方向)に、既存柱130の外面131より屋内側(図44中、上側)に位置すると共に、既存梁132の外面133から屋外側(図43中、左側)にバルコニースラブ136のせり出しが小さい等の制約がある場合がある。この場合には、柱補強増打部162を配設するのにあたり、既存柱130の外面131からの奥行が十分にとれないため、図44に示すように、柱補強増打部162は、既存柱130の外面131の面上以外に、既存柱130の開口部側内面130aより開口部142(図39参照)内側に向けてせり出すと共に、既存梁132の外面133側(屋内側)にもせり出す形態で形成される。そして、I型補強ピース114(L型補強ピース112の縦柱部118)が、この柱補強増打部162のうちの、既存柱130の外面131に対向していない部分で、頭付スタッド115(頭付スタッド113V)を内設させて固定される。
 上記構成を有する本実施形態2のうちの実施例1の耐震補強工法の作用・効果について説明する。
 実施例1の耐震補強工法では、既存建築物101に対し、既存柱130と既存梁132とから構築される既存柱梁フレーム134を、補強ユニット110により耐震補強する工法であって、一対のL型補強ピース112と、一対のI型補強ピース114とを結合させて門型の補強ユニット110を組み立てる耐震補強工法において、一対のL型補強ピース112と一対のI型補強ピース114には、頭付スタッド113,115がそれぞれ設けられていること、既存柱130の外側で、一対のI型補強ピース114を既存柱132に沿って配置すると共に、既存梁132の外側で、一対のL型補強ピース112を既存柱130と既存梁132に沿って配置し、一対のI型補強ピース114と一対のL型補強ピース112とを組み立てる補強ピース組立工程と、補強ピース組立工程後、一対のI型補強ピース114のスタッド115と、一対のL型補強ピース112のうち、既存柱130に沿う一辺の縦柱部118のスタッド113V(113)とが内設するよう、柱補強主筋152を既存柱130の外側に配筋し、柱補強主筋152に補強帯筋154を直交させて巻いた柱補強配筋部155を形成する柱補強配筋工程と、一対のL型補強ピース112のうち、既存梁132に沿う一辺の上辺部116のスタッド113H(113)が内設するよう、梁補強主筋156を既存梁132の外側に配筋し、梁補強主筋156に補強肋筋158を直交させて巻いた梁補強配筋部159を形成する梁補強配筋工程と、柱補強配筋部155に打設して既存柱130を増し打ちすると共に、梁補強配筋部159に打設して既存梁132を増し打ちすることにより、補強ユニット110を固定する補強ピース固定工程と、を有すること、を特徴とするので、補強ユニット110が、既存柱130の外側で柱補強配筋部155に打設された柱補強増打部162と、既存梁132の外側で梁補強配筋部159に打設された梁補強増打部164とにより固定されることで、既存柱梁フレーム134における曲げ耐力、及び剪断耐力が増大し、既存建築物101の耐力と靭性が増大するため、既存建築物101の耐震性が向上する。
 また、このような耐震性の向上と共に、既存柱梁フレーム134の開口部142において、開口面積の減少を抑制することができる。そのため、耐震補強後の既存建築物101では、居住性、機能性、及び採光への影響を十分に小さく抑えることができる。また、補強ユニット110を既存柱130と既存梁132とに固定させるのに、既存柱130の増し打ち部分や既存梁132の増し打ち部分に、補強ユニットをアンカー止めすることや、接着剤等で固定させる工程が不要となり、耐震補強工事全体の工程数が削減できるため、工期が短縮でき、工事コストが低減できる。
 従って、本実施例1の耐震補強工法によれば、補強後の既存建築物101の居住性、機能性、採光への影響を十分に小さくすることができると共に、耐震補強工事のコストが抑制できる、という優れた効果を奏する。
 また、実施例1の耐震補強工法では、梁補強配筋部159に打設された梁補強増打部164は、既存梁132の上端側(バルコニースラブ136に近接する側)に寄せて設けられ、梁補強増打部164の高さH3が、既存梁132の高さH1より小さいこと、を特徴とするので、補強ユニット110により、既存柱梁フレーム134の開口部142の開口面積がより小さくなるのを確実に抑制でき、居住性、機能性、及び採光への影響を十分に抑えることができる。すなわち、既存柱梁フレーム134の開口部142が既存建築物101の室内外の出入口となっている場合には、既存建築物101を補強した後でも、人の出入りに支障が生じ難くなる。また、既存柱梁フレーム134の開口部142に設置された窓や戸から、既存建築物101の室内に採り込まれる太陽光が、補強ユニット110によって遮断されるのを抑制することができる。さらに、既存柱梁フレーム134の開口部142に設置された窓や戸の開閉に、補強ユニット110によって支障を来す虞が生じなくなる。
 また、実施例1の耐震補強工法では、梁補強増打部164の高さH3は、既存梁132の梁せいH1の1/2以下の高さであること、を特徴とするので、図41に示すように、一対のL型補強ピース112のうち、既存梁132に沿う一辺(補強ユニットの一辺)となる上辺部116が、上梁側の既存梁132下面から既存柱梁フレーム134の開口部142に向けたせり出し量h1を抑えることができる。そのため、例えば、既存建築物101が集合住宅等であり、ベランダと室内との境にある柱梁フレーム(既存柱梁フレーム134)において、既存梁132の桁行き方向のスパンが大きい構造体の既存建築物を対象に、耐震補強を施す場合には、補強ユニット110による居住性、機能性、及び採光性への影響が小さく抑えられ、既存建築物101を効果的に耐震補強できる。特に、集合住宅の住人等からの顧客ニーズとして近年、このような居住性、機能性、及び採光性が十分に確保できる耐震補強技術の開発が要望されており、本実施例1の耐震補強工法は、このような顧客ニーズを十分に満たすことができる。
 また、実施例1の耐震補強工法では、梁補強増打部164は、排気用スリーブ146が配設されている部位に対応する箇所に空間部166を備えること、を特徴とするので、排気用スリーブ146は、梁補強増打部164によって閉塞されず、既存建築物101の室内からの排気を、排気用スリーブ164を通して室外に排出させる機能をそのまま維持でき、既存建築物101の機能性は維持される。また、排気用スリーブ146が配設されている部位はごく限られた大きさであるため、空間部166により、梁補強増打部164の一部に増し打ちされない部分が存在していても、補強ユニット110により耐震補強された既存建築物101は、十分な耐震強度を確保することができる。
 また、実施例1の耐震補強工法では、一対のL型補強ピース112と一対のI型補強ピース114は何れも、心材であるH型鋼122,124と、コンクリート123,125とを一体成形したプレキャストコンクリート部材であり、頭付スタッド113,115はH型鋼122,124に固着されていること、を特徴とするので、既存建築物101の耐震補強現場でスタッドを鋼材に固着しようとすると、スペース上、制約が多く、スタッドの固着作業が効率良くできないが、補強ピースの製造工場にある専用設備で、スタッドを固着すれば、スタッド固着の生産性が向上するため、補強ユニット110のコストが低減できる。また、スタッドを鋼材に溶接で固着する場合には、スタッドを鋼材に溶接するためだけに、溶接機や養生シートを、耐震補強現場に持ち込む必要がない。加えて、頭付スタッド113,115をH型鋼122,124に溶接するためだけに、溶接技術の有資格者を、既存建築物101の耐震補強現場に人員配置する必要がなくなる。さらに、実施例1の耐震補強工法は、接着剤の強度発現に至るまでに一定の所要時間を必要とする接着接合の工法とは異なり、上記一定の所要時間を一切必要としない。そのため、頭付スタッド113,115が前もって工場でH型鋼122,124に固着されていれば、耐震補強現場に搬入されたスタッド付の補強ピース、すなわちL型補強ピース112とI型補強ピース114に対し、次の補強ピース組立工程に向けた準備に、すぐに取りかかることができるため、耐震補強工事の工期短縮に貢献することができる。
 また、補強ユニット110は、L型補強ピース112とI型補強ピース114に分割された補強ピースを組み立てて構成するものであるため、L型補強ピース112とI型補強ピース114は、既存建築物101の耐震補強現場に搬入し易く、特段L型補強ピース112とI型補強ピース114の搬入経路を確保する必要性が低く抑えられる。
<実施例2>
 また、実施形態2のうちの実施例2として、図45に示すように、既存梁132に排気用スリーブ146(図39参照)が形成されておらず、梁補強増打部164に空間部166を形成していない実施例も考えられる。この実施例2によれば、前述した実施例1の効果に加えて、耐震強度をさらに向上させる効果を得ることができる。実施例2の耐震補強工法では、補強ユニット110が、剛性の高い強固な構造となるため、特に既存構造物の水平方向の耐力が向上し、既存建築物101の耐震強度がさらに向上する。
<変形例>
 その他、実施形態2のうちの実施例1,2の変形例として、補強ユニット110を図46に示すような形状にしても良い。図46に示す変形例では、L型補強ピース112について、そのL字の内側を肉厚とし、既存柱130に平行な方向(図46中、上下方向)のL型補強ピース112の幅を大きくしている。
 以上において、本発明を、実施形態1では、実施例1,2及び変形例1,2を挙げて説明し、実施形態2では、実施例1,2及び変形例を挙げて説明したが、上記した実施の形態1,2は単なる例示にすぎず、本発明は上記実施形態1,2に限定されるものではなく、その要旨を逸脱しない範囲で、適宜変更して適用できる。
(1)例えば、実施形態1,2では、補強ユニット10,110を門型状に構成したが、補強ユニットの形状は四角枠状でも良い。
(2)また、実施形態2では、L型補強ピース112とI型補強ピース114の配置位置について、図40~図44に例示して説明したが、L型補強ピースとI型補強ピースの配置位置は、実施形態2で例示した配置位置に限定されるものではなく、適宜変更可能である。
(3)また、実施形態2では、L型補強ピースとI型補強ピースにおいて、スタッドの数、配置位置、隣り合うスタッド同士の間隔(ピッチ)は、実施形態2で例示した配置位置に限定されるものではなく、適宜変更可能である。
 以上の説明から明らかなように、本発明によれば、現行の建築構造基準を満たして建てられていない既存建築物では、耐震性が向上する共に、既存柱梁フレーム内の開口部における開口面積の減少が抑制でき、居住性、機能性、及び採光性を、従来の耐震補強工法と比較して、より一層向上させた耐震補強後の既存建築物が提供できる。
1,1A,101 既存建築物
10,110 補強ユニット
12,112 L型補強ピース
113,113H,113V,115 頭付スタッド(スタッド)
14,114 I型補強ピース
116 上辺部(既存柱に沿う一辺)
122,124 H型鋼(鋼材)
123,125 コンクリート
30,130 既存柱
131 外面(既存柱の外側)
32,132 既存梁
133 外面(既存梁の外側)
34,134 既存柱梁フレーム
36 バルコニースラブ
38 増し打ち予定部
40 増し打ち予定部
42 開口部
46,146 排気用スリーブ
62 柱補強増打部
64,164 梁補強増打部
66,166 空間部
84 樹脂部
152 柱補強主筋
154 補強帯筋
155 柱補強配筋部
156 梁補強主筋
158 補強肋筋
159 梁補強配筋部
H,H1 既存梁の高さ(既存梁の梁せい)
H3 梁補強増打部の高さ
h (梁補強増打部の)高さ
 

Claims (8)

  1.  既存建築物の既存柱と既存梁から構成される既存柱梁フレームを補強するユニットにより耐震補強する工法であって、一対のL型補強ピースと、一対のI型補強ピースとボルトで結合させて門型の補強ユニットを組み立てる耐震補強工法において、
     前記既存柱の外側に、柱に平行に配置される柱補強主筋と、前記柱補強主筋の直交方向に巻かれる補強帯筋とを内設した柱補強増打部をアンカーにより増し打ちする柱増し打ち工程と、
     前記既存梁の外側に、梁と平行に配置される梁補強主筋と、前記梁補強主筋の直交方向に巻かれる補強肋筋とを内設した梁補強増打部をアンカーにより増し打ちする梁増し打ち工程と、
     前記柱補強増打部と前記梁補強増打部に対して、前記一対のL型補強ピースと前記一対のI型補強ピースとをアンカー止めし、前記柱補強増打部と前記梁補強増打部と、前記一対のL型補強ピースと前記一対のI型補強ピースとの間に接着用樹脂を注入する補強ピース固定工程と、を有すること、
    を特徴とする耐震補強工法。
  2.  請求項1に記載する耐震補強工法において、
     前記梁補強増打部は、排気用スリーブが配設されている部位に対応する箇所に空間部を備えること、
    を特徴とする耐震補強工法。
  3.  請求項1または請求項2に記載する耐震補強工法において、
     前記梁補強増打部の高さを前記既存梁の高さよりも小さくすること、
    を特徴とする耐震補強工法。
  4.  既存建築物に対し、既存柱と既存梁とから構築される既存柱梁フレームを、補強ユニットにより耐震補強する工法であって、一対のL型補強ピースと、一対のI型補強ピースとを結合させて門型の補強ユニットを組み立てる耐震補強工法において、
     前記一対のL型補強ピースと前記一対のI型補強ピースには、スタッドがそれぞれ設けられていること、
     前記既存柱の外側で、前記一対のI型補強ピースを前記既存柱に沿って配置すると共に、前記既存梁の外側で、前記一対のL型補強ピースを前記既存柱と前記既存梁に沿って配置し、前記一対のI型補強ピースと前記一対のL型補強ピースとを組み立てる補強ピース組立工程と、
     前記補強ピース組立工程後、前記一対のI型補強ピースの前記スタッドと、前記一対のL型補強ピースのうち、前記既存柱に沿う一辺の前記スタッドとが内設するよう、柱補強主筋を前記既存柱の外側に配筋し、前記柱補強主筋に補強帯筋を直交させて巻いた柱補強配筋部を形成する柱補強配筋工程と、
     前記一対のL型補強ピースのうち、前記既存梁に沿う一辺の前記スタッドが内設するよう、梁補強主筋を前記既存梁の外側に配筋し、前記梁補強主筋に補強肋筋を直交させて巻いた梁補強配筋部を形成する梁補強配筋工程と、
     前記柱補強配筋部に打設して前記既存柱を増し打ちすると共に、前記梁補強配筋部に打設して前記既存梁を増し打ちすることにより、前記補強ユニットを固定する補強ユニット固定工程と、を有すること、
    を特徴とする耐震補強工法。
  5.  請求項4に記載する耐震補強工法において、
     前記梁補強配筋部に打設された梁補強増打部は、前記既存梁の上端側に寄せて設けられ、前記梁補強増打部の高さが、前記既存梁の高さより小さいこと、
    を特徴とする耐震補強工法。
  6.  請求項5に記載する耐震補強工法において、
     前記梁補強増打部の高さは、前記既存梁の梁せいの1/2以下の高さであること、
    を特徴とする耐震補強工法。
  7.  請求項5または請求項6に記載する耐震補強工法において、
     前記梁補強増打部は、排気用スリーブが配設されている部位に対応する箇所に空間部を備えること、
    を特徴とする耐震補強工法。
  8.  請求項4乃至請求項7のいずれか1つに記載する耐震補強工法において、
     前記一対のL型補強ピースと前記一対のI型補強ピースは何れも、心材である鋼材と、コンクリートとを一体成形したプレキャストコンクリート部材であり、前記スタッドは前記鋼材に固着されていること、
    を特徴とする耐震補強工法。
     
     
PCT/JP2013/070109 2012-08-20 2013-07-24 耐震補強工法 WO2014030483A1 (ja)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN201380042929.4A CN104541006B (zh) 2012-08-20 2013-07-24 抗震加强施工方法
KR20157006858A KR20150033749A (ko) 2012-08-20 2013-07-24 내진 보강 공법
KR1020157003554A KR101587387B1 (ko) 2012-08-20 2013-07-24 내진 보강 공법

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2012181840A JP5324688B1 (ja) 2012-08-20 2012-08-20 耐震補強工法
JP2012-181840 2012-08-20

Publications (1)

Publication Number Publication Date
WO2014030483A1 true WO2014030483A1 (ja) 2014-02-27

Family

ID=49595895

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2013/070109 WO2014030483A1 (ja) 2012-08-20 2013-07-24 耐震補強工法

Country Status (4)

Country Link
JP (1) JP5324688B1 (ja)
KR (2) KR101587387B1 (ja)
CN (2) CN104541006B (ja)
WO (1) WO2014030483A1 (ja)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015218561A (ja) * 2014-05-21 2015-12-07 株式会社竹中工務店 耐震補強構造、及び耐震補強方法
JP2016044391A (ja) * 2014-08-19 2016-04-04 宇部興産株式会社 補強構造物の製造方法

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5548808B1 (ja) * 2013-07-22 2014-07-16 名工建設株式会社 耐震補強工法
KR20200140552A (ko) 2019-06-07 2020-12-16 주식회사 동양디엔피 음식물 저장용기
CN110984609B (zh) * 2019-11-25 2021-12-21 山东建筑大学 一种提高建筑物砌体抗震性能的方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4445007B2 (ja) * 2007-07-23 2010-04-07 名工建設株式会社 耐震補強工法及び補強ピース
JP4446401B2 (ja) * 2008-08-25 2010-04-07 名工建設株式会社 耐震補強工法及び補強ピース
JP2011214261A (ja) * 2010-03-31 2011-10-27 Ube Industries Ltd 耐震補強構造及び耐震補強方法

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
IT1232076B (it) * 1988-04-05 1992-01-23 Ortega Beltran Jorge Metodo per mettere sotto carico successivo o rideformare e rinforzare o scaricare strutture costruttive sostanziali gia'esistenti
JP3766940B2 (ja) * 1997-08-18 2006-04-19 株式会社竹中工務店 既存建築物の耐震補強方法
JP4400833B2 (ja) 2006-06-20 2010-01-20 名工建設株式会社 耐震補強工法及び補強ピース
CN201133090Y (zh) * 2007-07-09 2008-10-15 李树林 一种房屋增层时使用的框架柱抗震结构
CN201474320U (zh) * 2009-08-28 2010-05-19 河南杭萧钢构有限公司 一种钢骨梁柱补强结构
CN101736909A (zh) * 2009-12-07 2010-06-16 广州大学 一种底部框架柱震损房屋建筑的修复方法
CN101864846B (zh) * 2010-06-18 2011-07-27 北京工业大学 抗震加固用内嵌式减震钢框架

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4445007B2 (ja) * 2007-07-23 2010-04-07 名工建設株式会社 耐震補強工法及び補強ピース
JP4446401B2 (ja) * 2008-08-25 2010-04-07 名工建設株式会社 耐震補強工法及び補強ピース
JP2011214261A (ja) * 2010-03-31 2011-10-27 Ube Industries Ltd 耐震補強構造及び耐震補強方法

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015218561A (ja) * 2014-05-21 2015-12-07 株式会社竹中工務店 耐震補強構造、及び耐震補強方法
JP2016044391A (ja) * 2014-08-19 2016-04-04 宇部興産株式会社 補強構造物の製造方法

Also Published As

Publication number Publication date
JP2014037750A (ja) 2014-02-27
JP5324688B1 (ja) 2013-10-23
CN104541006B (zh) 2016-04-06
KR101587387B1 (ko) 2016-01-20
CN104541006A (zh) 2015-04-22
CN105133848A (zh) 2015-12-09
KR20150021592A (ko) 2015-03-02
KR20150033749A (ko) 2015-04-01

Similar Documents

Publication Publication Date Title
KR101253519B1 (ko) 콘크리트 충전 강관기둥을 이용한 기존 건축물의 내진보강 공법
JP4445007B2 (ja) 耐震補強工法及び補強ピース
KR101150392B1 (ko) 내진 보강용 철골 구조물의 접합구조 및 접합공법
WO2014030483A1 (ja) 耐震補強工法
AU2017203291A1 (en) Stronger wall system
JP2009046966A5 (ja)
JP4400833B2 (ja) 耐震補強工法及び補強ピース
JP4942475B2 (ja) 既存柱の補強方法及び補強構造
JP2008002091A5 (ja)
JP2010159543A (ja) 耐震補強構造
JP4999435B2 (ja) 既存建物の躯体と耐震補強材との接合構造
JP5548808B1 (ja) 耐震補強工法
KR101715359B1 (ko) 콘크리트 충전 강관기둥을 이용한 기존 건축물의 내진보강 공법
JP4446401B2 (ja) 耐震補強工法及び補強ピース
JP2016089488A (ja) 既存建物補強方法
JPH11193639A (ja) 既設鉄筋コンクリート製建築物の耐震補強工法
KR20130117204A (ko) 건축물용 내진 보강 구조물 및 이를 이용한 건축물 내진 보강 공법
KR102321433B1 (ko) 건물 외부 장착 방식의 내진 보강 구조체
JP3776330B2 (ja) 既存建物の耐震壁およびその構築方法
JP5726675B2 (ja) 既存建物の補強構造
JP5690771B2 (ja) 胴縁ブレース耐震壁
JP5871544B2 (ja) 耐震補強工法及び補強ピース
JP3909488B2 (ja) 既存建物の耐震補強構造及びその施工方法
JP3235716B2 (ja) 既存建物の耐震改修工法
CN217106286U (zh) 一种采用外加角钢钢架角柱加固砌体结构

Legal Events

Date Code Title Description
WWE Wipo information: entry into national phase

Ref document number: 201380042929.4

Country of ref document: CN

121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 13831555

Country of ref document: EP

Kind code of ref document: A1

ENP Entry into the national phase

Ref document number: 20157003554

Country of ref document: KR

Kind code of ref document: A

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 13831555

Country of ref document: EP

Kind code of ref document: A1