KR101127130B1 - A precast type pre-stress box girder bridge excution method - Google Patents

A precast type pre-stress box girder bridge excution method Download PDF

Info

Publication number
KR101127130B1
KR101127130B1 KR1020080063785A KR20080063785A KR101127130B1 KR 101127130 B1 KR101127130 B1 KR 101127130B1 KR 1020080063785 A KR1020080063785 A KR 1020080063785A KR 20080063785 A KR20080063785 A KR 20080063785A KR 101127130 B1 KR101127130 B1 KR 101127130B1
Authority
KR
South Korea
Prior art keywords
girder
girders
lower flange
bridge
construction
Prior art date
Application number
KR1020080063785A
Other languages
Korean (ko)
Other versions
KR20100003791A (en
Inventor
최영환
박진상
고용석
Original Assignee
두산건설 주식회사
주식회사동일기술공사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 두산건설 주식회사, 주식회사동일기술공사 filed Critical 두산건설 주식회사
Priority to KR1020080063785A priority Critical patent/KR101127130B1/en
Publication of KR20100003791A publication Critical patent/KR20100003791A/en
Application granted granted Critical
Publication of KR101127130B1 publication Critical patent/KR101127130B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 교량의 프리케스트 거더교 시공방법에 관한 것으로서, 크레인 가설을 위해 박스형 거더를 2개로 분할된 빔형태의 거더로 미리 제작한 후 가설할 수 있도록 함으로서 공사기간 및 시공비용을 절감시키기 위한 것이다.The present invention relates to a bridge construction method of precast girder bridge, and to reduce the construction period and construction cost by allowing the box-type girders to be pre-fabricated after beam beam girders divided into two for the construction of cranes.

이를 실현하기 위한 본 발명은, 수직부(11)와, 상기 수직부(11)의 하단에서 일측으로 돌출 구비된 형태를 이루는 하부플랜지부(12)와, 상기 수직부(11)의 상단에서 증가된 폭을 이루는 상부지지부(13) 구조를 이룸과 함께 양생 후 1차 긴장을 실시하여 개별적인 거더(10)를 제작하는 거더 제작단계;(ST 1) 상기 제작된 각각의 거더(10)를 크레인을 이용하여 교각(20) 사이에 안착 설치하되, 2개의 거더(10)가 쌍을 이루며 상호 대향되는 형태를 이루도록 설치하는 거더운반단계;(ST 2) 상기 쌍을 이루는 거더간 하부 플랜지부 상호간의 연결을 위해 거푸집을 이용하여 콘크리트를 타설하는 하부플랜지 이음부 타설단계;(ST 3) 상기 쌍을 이루는 거더의 상부지지부 사이를 연결시키기 위한 바닥판 슬래브(41) 콘크리트를 타설함으로서 양측 거더(10)가 하나의 일체형 박스 구조를 이루도록 하는 바닥판 슬래브 타설단계;(ST 4) 를 포함하는 것을 특징으로 한다.The present invention for achieving this, the vertical portion 11, the lower flange portion 12 having a shape protruding to one side from the lower end of the vertical portion 11, and increased from the upper end of the vertical portion (11) The girder manufacturing step of producing a separate girder 10 by performing a first tension after curing and the upper support portion 13 forming a structure of the width; (ST 1) each of the girder 10 produced above the crane Girdle carrying step to install between the pier 20, the two girders 10 to form a pair to form a mutually opposite form; (ST 2) the connection between the lower flange between the pair of girders Lower flange joint placing step of pouring concrete for the formwork for; (ST 3) by placing the bottom plate slab 41 concrete for connecting between the upper support of the paired girder both side girders (10) One integral box A floor slab casting step to achieve; characterized in that it comprises a (ST 4).

교량, 프리스트레스트, PSC, 박스, 거더, 고속철도 Bridge, Prestress, PSC, Box, Girder, High Speed Rail

Description

교량의 프리케스트 합성형 프리스트레스트 박스 거더교 시공방법{A PRECAST TYPE PRE-STRESS BOX GIRDER BRIDGE EXCUTION METHOD}Construction method of pre-cast composite prestress box girder bridge of bridge {A PRECAST TYPE PRE-STRESS BOX GIRDER BRIDGE EXCUTION METHOD}

본 발명은 교량의 박스 거더교 시공방법에 관한 것으로서, 더욱 상세하게는 박스형 거더교의 구조물의 시공 및 설치작업이 용이하게 이루어질 수 있도록 함으로서 시공기간 및 소요비용을 절감시킬 수 있도록 하기 위한 것이다.The present invention relates to a method for constructing a box girder bridge of a bridge, and more particularly, to reduce construction time and cost by making the construction and installation work of the structure of a box-type girder bridge easy.

일반적으로 교량이란 하천, 호수, 해협, 만(灣), 운하, 저지 또는 다른 교통로나 구축물(構築物)위를 건너갈 수 있도록 건설되는 고가구조물이다. 이러한 교량은 재질이나 구조 또는 제조공법 등에 따라 다양한 종류로 구분되는데, 특히 근래에 들어 교량을 통한 소통량이 많아지고, 상부 슬라브 콘크리트의 면적이 넓어짐에 따라 그 시공 및 보수 유지에 유리한 장점과 함께 강도 등의 여러 가지 우수한 특징을 가지고 있는 다양한 공법이 개발되었는데, 이중 하나의 방법으로 거더(girder)교가 있다.In general, bridges are expensive structures that can be constructed to cross rivers, lakes, straits, bays, canals, lowlands, or other traffic or structures. These bridges are classified into various types according to materials, structures, or manufacturing methods. Especially, in recent years, the traffic flows through bridges, and the area of upper slab concrete is enlarged. A variety of constructions have been developed that have many of the best features of Girder.

통상 빔(beam)이라 불리기도 하는 거더(Girder)는, 교량이나 고가도로의 교각과 교각사이에 걸쳐 놓여져, 교량 상판 슬라브를 지지하는 구조물을 일컫는 말로써, 통상 프리스트레스트 콘크리트(Pre-Stressed Concrete : 이하 PSC 라 한다.) 재질이 사용된다.Girders, commonly referred to as beams, refer to structures that are placed between bridges or overpass piers and bridges to support bridge slabs. PSC) Material is used.

한편, 고속철도 운행 구간의 경우에는 열차운행의 안정성을 위해 거더 단면의 도심을 기준으로 강체회전거동이 가능한 박스 구조물 형태의 PSC 박스 거더교가 시공되어지게 된다.On the other hand, in the case of the high-speed railway operation section, a PSC box girder bridge in the form of a box structure capable of rigid body rotational behavior based on the center of the girder cross section is constructed for the stability of train operation.

그러나, 종래에는 PSC 박스 구조물의 가설을 위해서는 시공위치가 대부분 높은 위치이기 때문에 거푸집을 받쳐주기 위한 구조물로 특수장비를 필요로 하기 때문에 시공이 어려움과 함께 시공 비용이 상승되는 문제점이 있었다.However, in the related art, since the construction position is mostly high for the construction of the PSC box structure, special equipment is required as a structure to support the formwork.

본 발명은 상기한 종래 박스 거더교의 시공과정에서 문제점을 개선하기 위해 제안된 것으로서, 박스 구조물을 이루기 위한 기초거더를 미리 지상에서 양생시킨 후 크래인 장비를 이용하여 운반 및 설치하고 현장에서 이음부 타설이 이루어질 수 있는 시공방법을 제공함으로서 고속철도 교량의 시공이 보다 용이하게 이루어질 수 있도록 하는데 목적이 있다.The present invention has been proposed to improve the problems in the construction process of the conventional box girder bridge as described above, after curing the ground girders for forming the box structure in advance on the ground transport and installation using the crane equipment and the site of the joint is placed By providing a construction method that can be made is an object to make the construction of high-speed railway bridge more easily.

상기 목적을 이루기 위한 본 발명의 시공방법은, 수직부와, 상기 수직부의 하단에서 일측으로 돌출 구비된 형태를 이루는 하부플랜지부와, 상기 수직부의 상단에서 증가된 폭을 이루는 상부지지부 구조를 이루는 개별적인 거더를 제작하는 거더 제작단계; 상기 제작된 각각의 거더를 크레인을 이용하여 교각 상단부에 안착 설치하되, 2개의 거더가 쌍을 이루어 상호 대향되는 형태를 이루도록 설치하는 거더운반단계; 상기 쌍을 이루는 거더간 하부 플랜지부 상호간의 연결을 위해 거푸집을 이용하여 콘크리트를 타설하는 하부플랜지 이음부 타설단계; 상기 쌍을 이루는 거더의 상부지지부 사이를 연결시키기 위한 바닥판 슬래브 콘크리트를 타설하는 바닥판 슬래브 타설단계;를 포함하는 것을 특징으로 한다.The construction method of the present invention for achieving the above object, the vertical portion, the lower flange portion forming a shape provided protruding to one side from the lower end of the vertical portion, and the individual forming an upper support portion structure of the increased width at the upper end of the vertical portion Girder production step of manufacturing the girder; A girder carrying step of installing each of the girder seats by using a crane and installing the girder, wherein the two girders are paired and formed to face each other; A lower flange joint placing step of placing concrete using formwork for connection between the pair of girder lower flanges; And a bottom plate slab casting step of placing bottom plate slab concrete for connecting between the upper support portions of the paired girders.

이러한 본 발명은, 박스 거더교를 시공함에 있어 미리 지상에서 제작되어진 빔 형태의 2개의 개별 거더를 크레인 등의 장비를 이용하여 교각 상부로 이동시킨 후 현장에서 개별 거더간의 연결을 위한 이음부 현장타설을 실시함으로서 가설 구조물이 필요 없어 공사기간 및 시공비용을 크게 절감할 수 있는 효과를 나타낼 수 있게 된다.In the present invention, in the construction of the box girder bridge, two individual girders in the form of beams made on the ground in advance are moved to the upper part of the piers using equipment such as cranes, and then the site casting for connecting the individual girders in the field is performed. By doing so, it is possible to exhibit an effect that a construction structure and a construction cost can be greatly reduced because a temporary structure is not required.

특히, 현장타설 작업시 양측 거더간의 임시적인 연결상태를 이룰 수 있도록 함으로서 작업과정에서 보다 안정적인 지지상태가 유지되어질 수 있는 이점을 나타내게 된다.In particular, it is possible to achieve a temporary connection between the two girders during the site casting work, showing the advantage that a more stable support state can be maintained during the work process.

이와 같이 시공이 이루어진 거더교는 비틀림 강성이 극대화 되어지는 박스형태를 이룸으로서 고속철도의 운행 안전성을 극대화 할 수 있게 된다.In this way, the construction of the girder bridge can maximize the torsional rigidity by maximizing the torsional rigidity.

이하, 본 발명의 구체적인 실시예를 첨부 도면을 참조하여 상세히 살펴보기로 한다.Hereinafter, specific embodiments of the present invention will be described in detail with reference to the accompanying drawings.

먼저, 본 실시 예에 따른 고속철도 교량용 PSC 박스 거더교 시공과정을 살펴보면 다음과 같다.First, the construction process of the PSC box girder bridge for the high-speed railway bridge according to the present embodiment is as follows.

<제1단계(ST 1): 거더제작 및 1차긴장><First Stage (ST 1): Girder Production and 1st Tension>

먼저, 도 1에서와 같이 박스 구조물을 이루기 위한 개별적인 거더(10)를 제작하는 거더 제작단계가 실시된다.First, a girder manufacturing step of manufacturing individual girders 10 for forming a box structure as shown in FIG. 1 is performed.

즉 이때에는, 거푸집 형틀 내에 콘크리트를 타설함으로서 도 1의 A-A단면에서와 같은 단면구조를 이루는 거더(10)를 제작하게 되는데, 제작된 거더(10)는 단면으로 도시된 바와 같이 수직부(11)를 기준으로 하부 일측에는 하부 플랜지부(12)가 형성되며 상부에는 상부지지부(13)가 더욱 증가된 폭을 형성하는 일체형 구조를 이루고 있음을 확인할 수 있다.That is, at this time, by pouring concrete in the formwork to produce a girder 10 having the same cross-sectional structure as in section AA of Figure 1, the girder 10 is a vertical portion 11 as shown in the cross section On the basis of the lower side, the lower flange portion 12 is formed and the upper support portion 13 can be seen to form an integral structure forming a further increased width.

한편, 상기에서 콘크리트 타설전에 형틀 내에는 거더(10)의 수직부(11) 및 하부플랜지부(12)에서 철근(2)이 노출되어지도록 배근시킨 상태에서 콘크리트 타설을 수행함으로서, 완성된 거더(10)에는 철근(2)이 노출되어지도록 함이 바람직하다.On the other hand, the above-mentioned concrete girder in the mold before the concrete part 11 and the lower flange portion 12 by placing the reinforcement so as to expose the reinforcing bar (2) to expose the completed girder ( 10) it is preferable to expose the rebar (2).

또한, 거더(10)의 하부 모서리측에는 일정 간격으로 긴장 정착구(15; 1도에는 미도시)를 형성시킴으로서 후 공정에서 2차긴장 작업이 수행되어지도록 함이 바람직하다.In addition, it is preferable to form a tension fixing device 15 (not shown in FIG. 1) at regular intervals on the lower edge side of the girder 10 so that the secondary tensioning operation may be performed in a later process.

미설명 부호 14는 긴장재(1)가 삽입되어지는 통공을 나타낸다.Reference numeral 14 denotes a through hole into which the tension member 1 is inserted.

이와 같이 제작이 이루어진 본 발명의 거더(10)는 양생 후 긴장재(1)를 이용하여 1차 긴장을 실시하게 된다.The girder 10 of the present invention made as described above is subjected to the primary tension by using the tension member 1 after curing.

<제2단계(ST 2): 거더운반 및 설치><Second Stage (ST 2): Girder Transport and Installation>

이후, 상기 과정에서 제작되어진 거더(10)는 도 2에서와 같이 크레인을 이용하여 교각(20) 사이에 올려놓는 운반 및 설치작업을 실시하게 된다.Then, the girder 10 manufactured in the above process is carried out carrying and installation work between the piers 20 using a crane as shown in FIG.

이때에는 B-B 단면도에 나타내어진 바와 같이 2개의 거더(10)가 상호 대칭 형태를 이루어 양측 하부 플랜지부(12)가 일정 간격 이격되도록 설치하게 되며, 이때 각 교각(20) 상부에는 각각의 거더(10)를 받쳐주기 위한 교좌장치(50)가 별도의 가설받침대(51)와 함께 안착되어짐으로서 거더(10)를 안정적인 수평상태로 지지할 수 있게 된다.At this time, as shown in the cross-sectional view of the BB two girders 10 are formed symmetrical with each other so that the lower flange portion 12 on both sides are installed to be spaced apart at regular intervals, wherein each girder 20, each girder (10) The support device 50 for supporting) is mounted with a separate temporary support 51 to support the girder 10 in a stable horizontal state.

상기 가설받침대(51)는 교좌장치(50)와 동일한 높이를 이루는 것으로서, 본 과정에서 임시 설치가 이루어진 후, 후공정에서 바닥판 슬래브 타설작업 및 양생 후에는 제거되어지게 된다.The temporary support 51 is formed at the same height as the chair apparatus 50, and after the temporary installation is made in the present process, it is removed after the slab slab work and curing in the later process.

특히, 이와 함께 양측 하부 플랜지부(12)에서 노출되어진 철근(2)을 상호간을 용접하여 연결되어지도록 하거나 또는 후크형태로 변형시켜 상호간에 연결시킴으로서 양측 거더(10) 하단부가 연결된 상태를 이루도록 한다.In particular, the rebar (2) exposed at both lower flange portion 12 with this to be connected to each other by welding or by deforming in the form of hooks to be connected to each other to achieve a state in which the lower end of both girders 10 are connected.

또한, 거더(10)의 상부에는 L형강 등과 같은 별도의 연결대(40) 다수개를 가설 브레이징 하여 양측에 임시 고정시킨다.In addition, the upper part of the girder 10 by temporarily brazing a plurality of separate connecting table 40, such as L-shaped steel and temporarily fixed to both sides.

즉, 연결대(40)에 의해 양측 거더(10)의 상부지지부(13)가 상호간에 임시적으로 일정간격으로 하여 연결된 상태를 이루도록 함으로서 거더(10)의 안정적인 지지상태가 이루어질 수 있도록 함이 바람직 하다.That is, it is preferable to achieve a stable support state of the girder 10 by forming a state in which the upper support portion 13 of the both girders 10 are connected to each other by a predetermined interval temporarily by the connecting table 40.

<제3단계(ST 3): 하부플랜지 이음부 현장타설><Step 3 (ST 3): cast in place of lower flange joint part>

그리고, 제3단계에서는 거더(10)의 양측 하부 플랜지부(12) 저면 이음부에 거푸집(30)을 대고 콘크리트 타설을 실시함으로서 플랜지 연결부(31)가 형성되어지도록 하게 된다.In the third step, the concrete connection is performed by placing the formwork 30 on the bottom seam of both lower flange portions 12 of the girder 10 so that the flange connection portion 31 is formed.

이와 같이 형성된 플랜지 연결부(31)로 인해 양측의 거더(10)는 하부 플랜지부(12)가 연결되어진 일체형 구조물을 이루게 되는 것이다.Due to the flange connection portion 31 formed as described above, both girders 10 form an integral structure in which the lower flange portion 12 is connected.

<제4단계(ST 4): 바닥판 슬래브 타설><Step 4: Slab slab casting>

이후, 양측 거더(10)의 상부를 일체로 연결하기 위한 바닥판 슬래브 타설작업을 실시하게 된다.Then, the bottom plate slab pouring work for connecting the upper side of both girders 10 integrally.

이를 위해서는 양측 상부지지부(13)에 임시적으로 연결되어져 있던 연결 대(40)를 제거한 후, 거푸집(미도시)을 설치하게 되며, 이후 바닥판 슬래브 콘크리트를 타설함으로서 일정 두께의 바닥판 슬래브(41)가 형성되어지게 된다.To this end, after removing the connecting table 40 that is temporarily connected to both the upper support portion 13, a formwork (not shown) is installed, and the bottom plate slab 41 of a predetermined thickness by pouring the bottom plate slab concrete. Will be formed.

이와 같이 형성되어진 바닥판 슬래브(41)로 인하여 양측 거더(10)의 상부가 연결된 형태를 이룸으로서 전체적으로 일체형 구조를 이루는 박스타입의 거더 구조물이 완성되어지게 되는 것이다.The bottom plate slab 41 formed as described above forms a form in which the upper portions of both side girders 10 are connected, thereby completing a box-type girder structure as a whole.

<제5단계(ST 5): 2차긴장><Step 5 (ST 5): Second Tension>

이와 같이 박스 거더가 완성되어지면 다시한번 거더(10) 하부 모서리측에 형성되어져 있는 긴장 정착구(15)를 통한 2차긴장을 실시하며, 긴장작업 후에는 블럭아웃 부위에 몰탈을 채워서 긴장 정착구(15)를 보호하도록 함이 바람직하다.When the box girder is completed as described above, the second tension is performed through the tension fixing unit 15 formed at the lower edge side of the girder 10, and after the tensioning operation, the tension fixing unit 15 is filled with mortar on the block-out part. ) Is desirable.

<제6단계(ST 6): 궤도부설>Sixth Stage (ST 6): Orbital Installation

그리고, 최종적으로 도 6의 단면도에서와 같이 고속철도용 궤도(52)를 부설함과 함께 각종 부대시설물을 설치함으로서 고속철도 교량의 시공이 완성되어지게 되는 것이다.Finally, the construction of the high speed railway bridge is completed by laying the high speed rail track 52 and installing various auxiliary facilities as in the cross-sectional view of FIG. 6.

상기와 같은 시공과정을 통해 시공되어진 본 발명의 PSC 박스 거더교는 미리 제작되어진 거더를 교각위로 운반한 상태에서 박스형 구조물을 이루기 위한 현장타설이 이루어지게 됨으로 공사기간 및 시공비용을 크게 절감시킬 수 있게 됨을 알 수 있다.PSC box girder bridge of the present invention constructed through the construction process as described above will be able to significantly reduce the construction period and construction cost by the on-site casting to achieve the box-type structure in the state of carrying the girder prepared in advance to the pier Able to know.

그리고, 상기에서 본 발명의 특정한 실시예가 설명 및 도시되었지만 본 발명의 거더교 시공방법이 당업자에 의해 다양하게 변형되어 실시될 수 있음은 자명한 일이다.In addition, although specific embodiments of the present invention have been described and illustrated above, it is obvious that the construction method of the girder bridge of the present invention may be variously modified and implemented by those skilled in the art.

예를 들면, 상기 실시 예에서는 고속철도용 교량 시공에 적용된 상태로 설명 및 도시되었으나, 일반 도로 교량의 시공에도 적용되어질 수 있게 된다.For example, in the above embodiment has been described and shown in the state applied to the construction of the high-speed railway bridge, it can be applied to the construction of the general road bridge.

따라서, 이와 같은 변형된 실시예들은 본 발명의 기술적 사상이나 범위로부터 개별적으로 이해되어져서는 안되며, 이와 같은 변형된 실시예들은 본 발명의 첨부된 특허청구범위 내에 포함된다 해야 할 것이다.Therefore, such modified embodiments should not be understood individually from the spirit or scope of the present invention, such modified embodiments will be included within the appended claims of the present invention.

도 1은 본 발명의 시공1단계에서 제작된 거더의 구조도.1 is a structural diagram of the girder produced in the first stage of construction of the present invention.

도 2는 본 발명 시공2단계에 의한 거더 운반 및 설치상태도.Figure 2 is a girder transport and installation state according to the second stage construction of the present invention.

도 3은 본 발명 시공3단계에 의한 하부플랜지 이음부 현장타설 상태도.Figure 3 is a site cast state of the lower flange joint according to the three steps of the present invention construction.

도 4는 본 발명 시공4단계에 의한 바닥판 슬래브 타설 상태도.Figure 4 is a slab slab pouring state diagram according to the fourth stage of the present invention construction.

도 5는 본 발명 시공5단계에 의한 2차긴장 상태도.Figure 5 is a secondary tension state by the fifth stage of the present invention construction.

도 6은 본 발명 시공6단계에 의한 궤도부설시 상태도.Figure 6 is a state diagram at the time of laying the track according to the six steps of the present invention construction.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

1 : 긴장재 2 : 철근1: tension material 2: rebar

10 : 거더 11 : 수직부10 girder 11: vertical portion

12 : 하부 플랜지부 13 : 상부지지부12: lower flange portion 13: upper support portion

15 : 긴장 정착구 20 : 교각15: tension anchor 20: pier

30 : 거푸집 31 : 플랜지 연결부30: formwork 31: flange connection

40 : 연결대 41 : 바닥판 슬래브40: connecting rod 41: bottom plate slab

50 : 교좌장치 51 : 가설받침대50: teaching device 51: temporary support

52 : 궤도52: orbit

Claims (6)

수직부(11)와, 상기 수직부(11)의 하단에서 일측으로 돌출 구비된 형태를 이루는 하부플랜지부(12)와, 상기 수직부(11)의 상단에서 증가된 폭을 이루는 상부지지부(13) 구조를 이룸과 함께 양생 후 1차 긴장을 실시한 개별적인 거더(10)를 제작하되, 내부에 배근되어진 철근(2)이 거더(10)의 하부플랜지부(12)에서 외부로 노출되어지도록 제작이 이루어지는 거더 제작단계;(ST 1)Vertical portion 11, the lower flange portion 12 is formed to protrude to one side from the lower end of the vertical portion 11, and the upper support portion 13 to form an increased width at the upper end of the vertical portion (11) ) The individual girder 10 which is subjected to the first tension after curing together with the structure is produced, but the reinforcing bar 2 disposed inside is exposed to the outside from the lower flange portion 12 of the girder 10. Girder manufacturing step made; (ST 1) 상기 제작된 각각의 거더(10)를 크레인을 이용하여 교각(20) 사이에 안착 설치하되, 2개의 거더(10)가 쌍을 이루며 상호 대향되는 형태를 이루도록 설치하며, 운반되어 상호 대향되는 형태로 설치되어진 2개의 거더 하부플랜지부(12)에 각각 노출되어져 있는 철근(2) 상호간을 용접하여 연결시킴으로서 양측 거더(10)가 연결된 상태를 이루도록 하고, 양측 거더(10)의 전도 방지를 위하여 교좌장치(50)와 쌍을 이루는 별도의 가설받침대(51)를 교각(20) 상면에 상호 일정거리 이격된 위치에 안착 구비시킴과 함께 양측의 상부지지부(13) 사이를 임시로 연결하는 연결대(40)를 설치하는 거더운반단계;(ST 2)Each manufactured girders 10 are installed between the piers 20 by using a crane, and the two girders 10 are installed in pairs to form a form opposite to each other, and are transported to face each other. The two girders 10 are connected to each other by welding and connecting the reinforcing bars 2 exposed to each of the two girder lower flange portions 12 to be installed, and a stair device for preventing the fall of both girders 10. Connecting stand 40 for providing a temporary temporary support (51) paired with the (50) at a position spaced apart from each other on the upper surface of the piers 20, and temporarily connecting between the upper support portion 13 on both sides Girder carrying step to install; (ST 2) 상기 쌍을 이루는 거더간 하부 플랜지부 상호간의 연결을 위해 거푸집을 이용하여 콘크리트를 타설하는 하부플랜지 이음부 타설단계;(ST 3)A lower flange joint placing step of placing concrete using formwork for connecting the lower flange portions of the paired girders; (ST 3) 상기 쌍을 이루는 거더의 상부지지부 사이를 연결시키기 위한 바닥판 슬래브(41) 콘크리트를 타설함으로서 양측 거더(10)가 하나의 일체형 박스 구조를 이루도록 하는 바닥판 슬래브 타설단계;(ST 4)Bottom plate slab casting step of placing the two side girders 10 to form a one-piece box structure by placing the bottom plate slab 41 concrete for connecting between the upper support of the pair of girders; (ST 4) 이후 슬래브 경화 후 양측 거더(10)의 2차 긴장 정착구를 통해 2차적인 긴장을 실시하는 2차긴장단계;(ST 5)After the slab hardening secondary tension step of performing a secondary tension through the secondary tension anchorage of both girders (10); (ST 5) 바닥판 슬래브(41) 위에 철로용 궤도(52)를 부설하는 궤도부설단계;(ST 6)Track laying step of laying the track rail 52 for the bottom plate slab 41; (ST 6) 가 순차적으로 실시되어짐 특징으로 하는 교량의 프리케스트 합성형 프리스트레스트 박스 거더교 시공방법.Method for constructing a pre-cast composite prestressed box girder bridge of the bridge characterized in that is carried out sequentially. 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete
KR1020080063785A 2008-07-02 2008-07-02 A precast type pre-stress box girder bridge excution method KR101127130B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080063785A KR101127130B1 (en) 2008-07-02 2008-07-02 A precast type pre-stress box girder bridge excution method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080063785A KR101127130B1 (en) 2008-07-02 2008-07-02 A precast type pre-stress box girder bridge excution method

Publications (2)

Publication Number Publication Date
KR20100003791A KR20100003791A (en) 2010-01-12
KR101127130B1 true KR101127130B1 (en) 2012-03-20

Family

ID=41813498

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080063785A KR101127130B1 (en) 2008-07-02 2008-07-02 A precast type pre-stress box girder bridge excution method

Country Status (1)

Country Link
KR (1) KR101127130B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200132341A (en) * 2019-05-17 2020-11-25 에스오씨기술지주 주식회사 Innovative PSC simple bridge construction method

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102261042B (en) * 2011-06-09 2013-03-06 四川川交路桥有限责任公司 Cantilever diagonal bracing bracket for casting bridge pier cover beam
WO2016162881A2 (en) * 2015-04-07 2016-10-13 Naresh Kumar Mohan Precast segments for elevated transit rail station
CN106522096A (en) * 2016-10-09 2017-03-22 张小东 Curved incremental launching construction technology for 48m-long-span railway simply-supported box girders and high piers
KR102080492B1 (en) 2017-08-04 2020-02-24 한국도로공사 Construction method for cantilever in steel composite girder bridge
CN111041966A (en) * 2019-11-21 2020-04-21 江苏永联精筑建设集团有限公司 Construction method of bridge prestressed continuous box girder
CN111155432A (en) * 2019-12-31 2020-05-15 中交路桥华南工程有限公司 Concrete pouring construction method for cast-in-situ box girder

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200294568Y1 (en) * 2002-07-25 2002-11-13 주식회사 보현 composite bridge using a bottom plate between piers and/or abuts
JP2004183433A (en) * 2002-12-06 2004-07-02 Oriental Construction Co Ltd Box girder bridge structure and its construction method
KR20060021734A (en) * 2004-09-04 2006-03-08 영 제 박 Prestressed concrete girder with lower flange concrete connected laterally and its manufacturing method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200294568Y1 (en) * 2002-07-25 2002-11-13 주식회사 보현 composite bridge using a bottom plate between piers and/or abuts
JP2004183433A (en) * 2002-12-06 2004-07-02 Oriental Construction Co Ltd Box girder bridge structure and its construction method
KR20060021734A (en) * 2004-09-04 2006-03-08 영 제 박 Prestressed concrete girder with lower flange concrete connected laterally and its manufacturing method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200132341A (en) * 2019-05-17 2020-11-25 에스오씨기술지주 주식회사 Innovative PSC simple bridge construction method
KR102259140B1 (en) * 2019-05-17 2021-06-01 에스오씨기술지주 주식회사 Innovative PSC simple bridge construction method

Also Published As

Publication number Publication date
KR20100003791A (en) 2010-01-12

Similar Documents

Publication Publication Date Title
KR100958014B1 (en) Construction method of steel composite girder bridge
US7461427B2 (en) Bridge construction system and method
KR101127130B1 (en) A precast type pre-stress box girder bridge excution method
KR101177342B1 (en) Precast end segmet girder for continuous bridge, girder making method and bridge construction method using the same
JP5045214B2 (en) Column head construction method
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
KR101703798B1 (en) Prestressed Concrete Beam with curve implementation possible connection structure and Constructing Method thereof
KR101242842B1 (en) Construction method for corrugated steel plate web-psc composite beam
KR100603901B1 (en) Girder bridge construction make use of a part existing girder and that execution method
KR20120053869A (en) Bridge construction method using precast end-block with girder connection member
KR100785634B1 (en) Continuation structure of prestressed concrete composite beam bridge and method thereof
JP2003253620A (en) Cable stayed bridge and its construction method
KR20120111506A (en) Girder making methos for precast end seggement using end mold and girder therewith
KR100631029B1 (en) Precasted concrete plate assembly and the construction method using thereof
KR20080099061A (en) Psc beam for connection steel width step of psc bridges
KR101038714B1 (en) Bridge and its construction method using tide arch hybrid girders having precast slabs
KR100889140B1 (en) The assembly type hollow slab
KR100613862B1 (en) Light weight pc-steelgirder bridge construction
KR20130090709A (en) Construction method for corrugated steel plate web-psc composite beam
JP2000104221A (en) Combined truss bridge and erection method of the same
JP7409952B2 (en) Viaduct construction method and viaduct construction equipment
JP2000045229A (en) Constructing method of bridge
JP2000104220A (en) Erection of combined truss bridge
KR100622449B1 (en) Hybrid pier and continuity execution method using the hybrid pier
CN115506634B (en) Assembled platform canopy and construction method thereof

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150303

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20160307

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20170309

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20180307

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20190225

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20200225

Year of fee payment: 9