KR101177342B1 - Precast end segmet girder for continuous bridge, girder making method and bridge construction method using the same - Google Patents
Precast end segmet girder for continuous bridge, girder making method and bridge construction method using the same Download PDFInfo
- Publication number
- KR101177342B1 KR101177342B1 KR1020100118556A KR20100118556A KR101177342B1 KR 101177342 B1 KR101177342 B1 KR 101177342B1 KR 1020100118556 A KR1020100118556 A KR 1020100118556A KR 20100118556 A KR20100118556 A KR 20100118556A KR 101177342 B1 KR101177342 B1 KR 101177342B1
- Authority
- KR
- South Korea
- Prior art keywords
- girder
- segment
- precast
- continuous
- end portion
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
- E01D2101/28—Concrete reinforced prestressed
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
교량용 빔(거더)을 제작함에 있어서, 양 단부는 정착장치 및 긴장재에 의한 하중이 집중되기 때문에 프리캐스트 방식으로 먼저 제작하고, 양 단부 사이의 중앙부는 먼저 제작된 프리캐스트 단부 세그먼트를 단부 거푸집으로 이용하여 제작하되, 교각과 같은 지점부에 있어 연결재를 이용하여 인접한 거더를 용이하게 연결시킬 수 있도록 함과 더불어 특히 중앙부 세그먼트 제작에 있어 보다 효율적인 거푸집 이용이 가능하여 거더 연장길이에 따른 제작의 효율성을 증진시킬 수 있으며, 단부와 중앙부 콘크리트 강도에 차이를 두어 품질관리가 용이한 연속교용 프리캐스트 단부 세그먼트 및 이를 이용한 교량용 거더와 그 제작 및 시공방법에 대한 것이다.In manufacturing the beams (girders) for bridges, both ends are prefabricated first because the load by the fixing device and the tension member is concentrated, and the center part between the both ends is the precast end segment that is first manufactured by the end formwork. It can be manufactured by using the connecting material at the point such as the pier, so that adjacent girders can be easily connected by using the connecting material, and more efficient formwork can be used especially for the production of the center segment. The present invention relates to a precast end segment for continuous bridges, a bridge girder using the same, and a method of fabricating and constructing the same, which can be improved, and which is easy to control by varying the strength of the end and the center concrete.
Description
본 발명은 연속교용 프리캐스트 단부 세그먼트, 이를 단부거푸집으로 이용하는 거더 제작방법 및 이를 이용한 교량시공방법에 관한 것이다. 더욱 구체적으로 교량용 빔(거더)를 제작함에 있어서, 긴장재에 의한 하중이 집중되고 정착장치로 인해 형상이 복잡하기 때문에 양 단부는 정착장치 및 긴장재에 의한 하중이 집중되기 때문에 프리캐스트 방식으로 먼저 제작하고, 양 단부 사이의 중앙부는 먼저 제작된 프리캐스트 단부 세그먼트를 단부 거푸집으로 이용하여 제작하되, 교각과 같은 지점부에 있어 연결재를 이용하여 인접한 거더를 용이하게 연결시킬 수 있도록 함과 더불어 특히 중앙부 세그먼트 제작에 있어 보다 효율적인 거푸집 이용이 가능하여 거더 연장길이에 따른 제작의 효율성을 증진시킬 수 있으며, 단부와 중앙부 콘크리트 강도에 차이를 두어 품질관리가 용이한 연속교용 프리캐스트 단부 세그먼트 및 이를 이용한 교량용 거더와 그 제작 및 시공방법에 대한 것이다.The present invention relates to a precast end segment for a continuous bridge, a girder fabrication method using the same as an end formwork, and a bridge construction method using the same. More specifically, in the fabrication of bridge beams (girders), the load by the tension member is concentrated and the shape is complicated by the fixing device, so both ends are precasted first because the load by the fixing device and the tension material is concentrated. In addition, the center portion between both ends is manufactured by using the precast end segment manufactured as the end form first, and in the same point portion as the pier, it is possible to easily connect adjacent girders using a connecting material, in particular, the center segment The more efficient formwork can be used to increase the efficiency of the fabrication according to the girder extension length, and the precast end segment for continuous bridges for easy quality control by varying the strength of the end and the center concrete and the girder for bridges using the same And how to manufacture and construct them.
일반적으로 교량이라 함은 하천, 해협, 만, 운하, 저지 또는 다른 교통로나 구축물 위를 건널 수 있도록 만든 고가 구조물로서, 그 구조형식에 따라서 거더교, 트러스트교, 아치교, 현수교, 라멘교 등이 있다.In general, bridges are expensive structures made to cross rivers, straits, bays, canals, lowlands, or other traffic routes or structures. Depending on the type of structure, there are girder bridges, trust bridges, arch bridges, suspension bridges, and ramen bridges.
한편 거더교(Girder Bridge)(1)는 거더(10)를 주체로 하는 교량으로서 도 1a에 도시된 바와 같이, 교각(20)의 상부면에 거치된 I형 단면의 거더(10)에 의해서 그 상부의 바닥판(30)을 지지하는 구조로서, 교량 제작시 교각(20)과 교각(20) 사이를 다수의 거더(10)가 거치된 후에 거더(10)의 상부면에 콘크리트가 타설됨으로써 거더(10)의 상부면에 바닥판(30)이 일체적으로 형성되는 구조이다.On the other hand, the
그리고 이와 같은 거더교(1)는 교각(20) 상에 올려진 다수의 거더(10)들에 직교하는 방향으로 다수의 가로보(40)들이 설치되어 다수의 거더들을 구조적으로 횡방향 연결시키게 된다.And the
도 1b는 상기 거더(10)를 제작하기 위한 거푸집(50)과 거푸집 탈형에 의한 완성된 거더(10)의 일부사시도이다.Figure 1b is a partial perspective view of the completed
이러한 거푸집(50)은 통상 강재(강판 및 다수의 앵글)로 제작되는데 먼저 바닥부재(51)를 양 측면 부재(52)에 설치하고, 상기 측면부재(52)의 상부에 다수의 타이바(53)들을 볼트(54)로서 고정하여 세팅되며,The
상기 거푸집 성형공간의 내부에 콘크리트(C)를 타설하는 방식으로 거더(10)가 제작된다.The
도 1c는 일정한 길이를 가진 거더(10)를 제작함에 있어 거더를 길이방향으로 다수 분할시킨 세그먼트를 이용하되 이러한 세그먼트들을 서로 결합시켜 제작하는 예를 도시한 것이다.FIG. 1C illustrates an example of manufacturing the
즉 소정의 길이를 가진 거더(10)는 장지간 교량에 사용되는 경우 운반 및 시공에 있어 작업성 및 시공성이 매우 떨어지게 되므로 다수개의 세그먼트로 제작한 다음, 이를 결합시키는 방식으로 거더를 제작하는 것이다.That is, when the
즉, 도 1c에 의하면 거더(10)를 3개의 세그먼트로 제작하여 서로 결합시키는 데, 특히 중앙부 세그먼트(12)와 양 단부 세그먼트(11,13)는 접합블록(14)을 이용하여 서로 먼저 전단키(A)를 이용하여 접합되도록 한 후, 긴장재를 이용하여 서로 압착 연결되도록 하는 방법으로 거더를 제작하고 있음을 알 수 있다.That is, according to FIG. 1c, the
이때, 상기 접합블록(14)은 중앙부 세그먼트(12)에 제작에 있어 특히 양 단부거푸집으로 이용할 수 있도록 함을 알 수 있으며, 중앙부 세그먼트(12)의 압축강도보다 더 큰 압축강도를 가진 콘크리트로 제작되도록 하고 있음을 알 수 있다.At this time, the
이때, 접합블록(14)을 별도로 제작하고, 이를 단부거푸집으로 이용하여 중앙부 세그먼트(12)와 일체로 제작하고, 나머지 양 단부 세그먼트(11,13)는 일단에 접합블록(14)을 단부거푸집으로 이용하여 일체로 제작하여 완성된 세그먼트(11,12,13)를 일체화 하여 거더를 완성하게 함을 알 수 있는데 이럴 경우 다음과 같은 문제점이 발생하게 된다.At this time, the
먼저 거더를 PSC 거더로 제작할 경우 내부에 배치되는 긴장재에 의하여 프리스트레스가 양 단부에 집중될 수 밖에 없는데, 고강도의 콘크리트를 적용한 접합블록(14)의 적용으로 세그먼트(11,12,13) 간 연결부의 시공품질 및 성능은 향상되지만, 프리스트레스가 집중되는 정착부에는 고강도의 콘크리트가 적용되지 않아 시공품질 향상과 단면 효율 향상에 의한 단면 크기 및 중량 저감에 한계가 있다.First, when the girder is manufactured as a PSC girder, the prestress is inevitably concentrated at both ends by a tension member disposed therein. The connection between the
이에, 정착부의 단면 효율을 향상시키기 위해서 양 단부 세그먼트(11,13)에 접합블록(14)에 적용한 것과 같은 고강도의 콘크리트를 적용하게 되면 정착부의 효율은 향상되지만 너무 많은 양의 고강도 콘크리트의 적용으로 재료비가 크게 증가하는 단점이 있다.Therefore, when high strength concrete such as that applied to the
또한, 서로 다른 강도를 가진 콘크리트를 동시에 타설하여 합성시키는 경우 서로의 경화속도가 다를 경우가 대부분이므로 이러한 강도가 상이한 콘크리트를 동시에 타설하여 연결되도록 하는 것은 강도가 다른 콘크리트 경계면 상의 재료분리의 우려가 발생할 수 있다는 문제점이 있었다.In addition, when the concrete having different strengths is poured at the same time to synthesize them, the hardening speed of each other is different. Therefore, when the concrete having different strengths is poured at the same time, the connection of concrete with different strengths may cause material separation on the concrete interface having different strengths. There was a problem that could be.
또한, 접합블록(14)을 이용하여 제작하는 중앙부 세그먼트(12)와 양 단부 세그먼트(11,13)의 형상이 다르기 때문에 형상이 다른 거푸집을 각각 별도로 제작해야 하는 단점이 있다.In addition, since the shape of the
즉, 교량마다 거더의 길이는 다양할 수 밖에 없으므로 실제 다양한 길이에 맞추어 거더를 도 1c와 같이 제작하려면 거더 초기 제작비용이 너무 많이 소요될 수 밖에 없다는 문제점이 있었다.That is, since the length of the girder for each bridge can be varied, there is a problem that the initial production cost of the girder must be too much to manufacture the girder according to the actual various lengths as shown in FIG. 1C.
따라서, 거더(빔)을 제작하기 위한 거푸집의 소요량을 가장 효과적으로 감소시킬 수 있으면서도, 거더의 연장길이에 효과적으로 대응할 수 있는 거더 제작방법 특히 거푸집의 활용측면에서 효율적인 기술개발의 필요성이 요구될 수 밖에 없었다.Therefore, the necessity of efficient technology development in terms of the use of the girder manufacturing method, especially in terms of the use of the formwork, which can effectively reduce the requirement of the formwork for manufacturing the girders (beams), is required. .
도 1d는 특히 PSC 거더(10)를 길이방향으로 분할된 세그먼트로 연결시킬 때, 양 거더(10)가 전단키 형태로 접하도록 설치하고, 강봉과 같은 연결재(60)를 사용하는 예가 도시되어 있다.FIG. 1D shows an example in which both
하지만 이러한 연결재(60)는 분할된 각각의 세그먼트가 직육면체 형태로 형성되어 있을 때 1개의 거더를 구성하는 세그먼트와 세그먼트를 연결하는 방식일 뿐만 아니라 인접한 세그먼트의 인접단부를 블럭아웃시키는 방식이므로 단면 손실이 발생할 수 밖에 없다는 문제점이 있었다.However, the connecting
이에 본 발명은 특히 연속교에 있어 서로 인접한 거더를 간단하게 연속화시킬 수 있도록 제작하되 다양한 길이를 가진 거더로 제작함에 있어 거더용 거푸집의 이용효율성을 높일 수 있도록 하여 거더의 연장길이에 따른 거더의 제작 효율성 및 경제성을 증진시키고, 프리스트레스가 집중되는 거더 양 단부에 대한 보강을 통하여 품질관리가 효율적인 연속교용 프리캐스트 단부 세그먼트 및 이를 단부거푸집으로 이용하는 거더 제작방법 및 상기 방법으로 제작된 거더를 이용한 연속교 시공방법 제공을 해결하고자 하는 기술적 과제로 한다.In this regard, the present invention is to produce a girder according to the extension length of the girder to increase the efficiency of the girder formwork in the manufacture of girder having a variety of lengths, but in particular to make the girder adjacent to each other in the continuous bridge simply. Precast end segment for continuous bridges for efficient quality control through reinforcement on both ends of girders where prestress is concentrated and the girder fabrication method using them as end formwork and continuous bridge construction using the girder manufactured by the above method The technical problem to solve the method provision.
이에 본 발명은 예컨대 거더의 양 단부는 소정의 길이를 가진 연속교용 프리캐스트 단부 세그먼트로 먼저 제작하되 연속교의 지점부에 설치되어 연속교용 프리캐스트 단부 세그먼트들 끼리 서로 간단하게 연결될 수 있도록 함으로써 거더의 연속화가 가능하도록 하고,Therefore, the present invention, for example, both ends of the girder is made of precast end segments for continuous bridges having a predetermined length, but are installed at the points of the continuous bridges so that the continuous bridge precast end segments can be easily connected to each other. Make it possible,
또한 상기 연속교용 프리캐스트 단부 세그먼트를 거더의 양 단부거푸집으로 이용하여 중앙부 세그먼트와 일체화 시키기 위하여 대차 및 레일을 이용하게 된다.In addition, a bogie and a rail are used to integrate the precast end segment for continuous bridges as both end formwork of the girder and to integrate the center segment.
이를 통해 거더의 연장길이에 따른 연속교용 프리캐스트 단부 세그먼트의 세팅작업이 정밀해지고, 이에 따라 중앙부 세그먼트용 거푸집을 1M, 2M와 같이 단위길이를 가지도록 제작된 것을 효율적으로 이용할 수 있게 된다.Through this, the setting work of the precast end segment for the continuous bridge according to the extension length of the girder is precise, and thus, the formwork for the central segment can be efficiently used to have unit lengths such as 1M and 2M.
이때, 연속교용 프리캐스트 단부 세그먼트의 저면이 중앙부 세그먼트용 거푸집의 단부 양 상면에 세팅되도록 함으로써 거더 전체 길이에 따른 거푸집 활용이 효율적으로 진행될 수 있게 된다.At this time, the bottom surface of the continuous bridge precast end segment is set on the upper surface of both ends of the formwork for the center segment, the formwork along the entire length of the girder can be efficiently carried out.
이를 위해 본 발명은To this end,
수평판 형태의 상부플랜지; 상기 상부플랜지 저면에 하방으로 연장되어 외측단부와 외측단부보다 폭이 좁게 형성된 내측단부가 서로 일체로 형성된 것으로써, 상기 외측단부의 외측단부면은 전단키 형태로 단차져 형성되고 상기 내측단부의 내측단부면은 연결철근이 돌출 연장되어 형성된 복부; 및 상기 복부를 구성하는 외측단부를 거더 길이방향으로 관통하도록 형성되어 강봉을 포함하는 연결재가 삽입되어 장착되는 연결홀;을 포함하며 고강도 콘크리트를 이용하여 미리 프리캐스트로 제작된 연속교용 프리캐스트 단부 세그먼트를 제공한다.An upper flange in the form of a horizontal plate; An inner end portion formed downwardly on the bottom surface of the upper flange and having a width smaller than that of the outer end portion and the outer end portion is formed integrally with each other. The outer end portion of the outer end portion is formed stepped in the form of a shear key and the inner end portion of the inner end portion. The abdomen includes: an abdomen formed by protruding connecting bars; And a connecting hole formed to penetrate the outer end portion of the abdomen in the longitudinal direction of the girder in such a manner that a connecting member including a steel rod is inserted and mounted therein. The precast end segment for a continuous bridge made of precast using high strength concrete in advance. To provide.
또한 바람직하게는 상기 연속교용 프리캐스트 단부 세그먼트는 Also preferably the precast end segment for continuous bridges is
거더 길이방향으로 서로 이격되어 배치된 양 연속교용 프리캐스트 단부 세그먼트 사이에 연속교용 프리캐스트 단부 세그먼트에 사용된 고강도 콘크리트보다 작은 강도의 콘크리트로 제작되는 중앙부 세그먼트가 더 형성되도록 하되, 상기 중앙부 세그먼트에는 내부철근이 형성되어 상기 내부철근과 연속교용 프리캐스트 단부 세그먼트의 연결철근이 서로 겹침이음 방식으로 서로 연결된 상태로 연속교용 프리캐스트 단부 세그먼트와 중앙부 세그먼트가 서로 일체화되어 거더로 제작되도록 하는 연속교용 프리캐스트 단부 세그먼트를 제공한다.Between the two continuous bridge precast end segments spaced apart from each other in the longitudinal direction of the girder, a center segment made of concrete of less strength than the high-strength concrete used in the continuous bridge precast end segment is formed. Continuous bridge precast end for continuous bridge precast end segment and center segment integrated with each other in a state where reinforcing bars are formed so that the connecting bars of the internal reinforcement and the continuous bridge precast end segment are overlapped with each other so as to be integrated with each other to be manufactured as a girder Provide a segment.
또한 바람직하게는 상기 프리캐스트 단부 세그먼트와 중앙부 세그먼트에 의하여 일체화된 거더는 프리스트레스 철근콘크리트 거더로써 내부에 미리 설치된 쉬스를 통해 설치된 긴장재에 의하여 프리스트레스가 도입되도록 하는 연속교용 프리캐스트 단부 세그먼트를 제공한다.Also preferably, the girder integrated by the precast end segment and the central segment provides a continuous cross precast end segment in which prestress is introduced by a tension member installed through a sheath preinstalled therein as a prestressed reinforced concrete girder.
또한 바람직하게는 정착장치에 의한 프리스트레스가 집중되는 거더의 양 단부 세그먼트를 고강도 콘크리트를 이용하여 수평판 형태의 상부플랜지; 상기 상부플랜지 저면에 하방으로 연장되어 외측단부와 외측단부보다 폭이 좁게 형성된 내측단부가 서로 일체로 형성된 것으로써, 상기 외측단부의 외측단부면은 전단키 형태로 단차져 형성되고 상기 내측단부의 내측단부면은 연결철근이 돌출 연장되어 형성된 복부; 및 상기 복부를 구성하는 외측단부를 거더 길이방향으로 관통하도록 형성되어 강봉을 포함하는 연결재가 삽입되어 장착되는 연결홀;을 포함하는 연속교용 프리캐스트 단부 세그먼트로 먼저 제작하고,In addition, preferably the upper flange of the horizontal plate form the both ends of the girder in which the prestress by the fixing device is concentrated using high-strength concrete; An inner end portion formed downwardly on the bottom surface of the upper flange and having a width smaller than that of the outer end portion and the outer end portion is formed integrally with each other. The outer end portion of the outer end portion is formed stepped in the form of a shear key and the inner end portion of the inner end portion. The abdomen includes: an abdomen formed by protruding connecting bars; And a connecting hole formed to penetrate the outer end portion of the abdomen in the longitudinal direction of the girder to be inserted and mounted with a connecting member including a steel rod.
거더 제작길이에 대응하여 제작할 거더의 양 단부에 위치하도록 상기 프리캐스트 단부 세그먼트를 거더의 길이방향으로 서로 이격 배치하고,The precast end segments are spaced apart from each other in the longitudinal direction of the girder so as to be located at both ends of the girder to be manufactured corresponding to the girder fabrication length,
상기 프리캐스트 단부 세그먼트 사이에 중앙부 거푸집을 세팅하여 중앙부 세그먼트를 제작하되, 상기 중앙부 거푸집은 양 프리캐스트 단부 세그먼트의 저면이 중앙부 거푸집 양 단부 상면에 배치되도록 하고,The central formwork is set between the precast end segments to produce a central segment, wherein the central formwork is disposed so that the bottoms of both precast end segments are disposed on the upper ends of the central formwork,
상기 중앙부 거푸집 내부에 콘크리트를 타설하여 양생시킨 후, 상기 중앙부 거푸집을 탈형하는 단계를 포함하는 연속교용 프리캐스트 단부 세그먼트를 단부거푸집으로 이용하는 거더 제작방법을 제공한다.After pouring concrete into the central formwork to cure, and provides a girder manufacturing method using the precast end segment for continuous bridges comprising the step of demolding the formwork.
또한 바람직하게는 상기 연속교용 프리캐스트 단부 세그먼트는 미리 제작되어 적치된 상태에서, 양 단부 받침대차가 레일에 의하여 길이방향으로 이동가능한 상태에서 거더 제작길이에 대응하여 제작할 거더의 양 단부에 위치하도록 세팅하고, 상기 레일 상부에 중앙부 거푸집을 세팅되도록 하는 연속교용 프리캐스트 단부 세그먼트를 단부거푸집으로 이용하는 거더 제작방법을 제공한다.Preferably, the continuous precast end segment for the continuous bridge is set to be positioned at both ends of the girder to be manufactured in correspondence with the girder fabrication length in a state in which both end pedestals are movable in the longitudinal direction by rails. It provides a girder fabrication method using a continuous bridge precast end segment for setting the center formwork on the rail top as an end formwork.
또한 바람직하게는 상기 프리캐스트 단부 세그먼트와 중앙부 세그먼트는, 프리캐스트 단부 세그먼트의 양 단부면으로부터 길이방향으로 미리 연장되도록 돌출 형성시된 연결철근과 중앙부 세그먼트용 내부철근을 서로 겹침이음방식으로 서로 연결시킨 후, 콘크리트를 타설하여 양생시켜 서로 일체화되도록 하는 연속교용 프리캐스트 단부 세그먼트를 단부거푸집으로 이용하는 거더 제작방법을 제공한다.Also preferably, the precast end segment and the central segment may be formed by connecting the connecting reinforcing bar and the inner reinforcing bar for the middle segment to each other in an overlapping manner. After that, it provides a girder manufacturing method using the continuous precast end segment for continuous bridges to pour and cure concrete to be integrated with each other.
또한 바람직하게는 상기 프리캐스트 단부 세그먼트와 중앙부 세그먼트에 의하여 일체화된 거더는 프리스트레스 철근콘크리트 거더로써 내부에 미리 설치된 쉬스를 통해 설치된 긴장재에 의하여 프리스트레스를 도입시키는 단계가 더 포함되도록 하는 연속교용 프리캐스트 단부 세그먼트를 단부거푸집으로 이용하는 거더 제작방법을 제공한다.Also preferably, the girder integrated by the precast end segment and the center segment further includes the step of introducing the prestress by a tension member installed through a sheath preinstalled therein as the prestressed reinforced concrete girder. It provides a girder manufacturing method using the end formwork.
또한 바람직하게는 수평판 형태의 상부플랜지; 상기 상부플랜지 저면에 하방으로 연장되어 외측단부와 외측단부보다 폭이 좁게 형성된 내측단부가 서로 일체로 형성된 것으로써, 상기 외측단부의 외측단부면은 전단키 형태로 단차져 형성되고 상기 내측단부의 외측단부면은 연결철근이 돌출 연장되어 형성된 복부; 및 상기 복부를 구성하는 외측단부를 거더 길이방향으로 관통하도록 형성되어 강봉을 포함하는 연결재가 삽입되어 장착되는 연결홀;을 포함하며 고강도 콘크리트를 이용하여 미리 프리캐스트로 제작된 연속교용 프리캐스트 단부 세그먼트가 중앙 세그먼트 일측 또는 양측 단부에 일체로 형성된 내부지점부 거더를 교량하부구조에 연속교용 프리캐스트 단부 세그먼트가 서로 접하도록 설치하고,Also preferably the upper flange in the form of a horizontal plate; An inner end portion formed downwardly on the bottom surface of the upper flange and having a width smaller than that of the outer end portion and the outer end portion is formed integrally with each other. The outer end portion of the outer end portion is stepped in the form of a shear key and the outer end portion of the inner end portion. The abdomen includes: an abdomen formed by protruding connecting bars; And a connecting hole formed to penetrate the outer end portion of the abdomen in the longitudinal direction of the girder in such a manner that a connecting member including a steel rod is inserted and mounted therein. The precast end segment for a continuous bridge made of precast using high strength concrete. The inner point girders integrally formed at one or both ends of the center segment are installed in the bridge substructure such that the precast end segments for continuous bridge contact each other.
상기 서로 접하도록 설치된 프리캐스트 단부 세그먼트들의 연결홀에 통해 강봉을 포함하는 연결재를 삽입시킨 후 연결재의 양 단부를 정착시켜 연속 설치된 프리캐스트 단부 세그먼트들을 서로 연결시키는 단계를 포함하는 연속교용 프리캐스트 단부 세그먼트를 이용한 교량시공방법을 제공한다.And inserting a connecting member including a steel rod through the connecting holes of the precast end segments provided to be in contact with each other, and then fixing both ends of the connecting member to connect the continuously installed precast end segments to each other. Provide bridge construction method using
또한 바람직하게는 상기 중앙부 세그먼트는 거더 길이방향으로 서로 이격되어 설치하여 배치된 양 연속교용 프리캐스트 단부 세그먼트 사이에 연속교용 프리캐스트 단부 세그먼트에 사용된 고강도 콘크리트보다 작은 강도의 콘크리트로 제작되며, 내부철근이 형성되어 상기 내부철근과 연속교용 프리캐스트 단부 세그먼트의 연결철근이 서로 겹침이음방식으로 서로 연결된 상태로 연속교용 프리캐스트 단부 세그먼트와 서로 일체화되도록 하는 연속교용 프리캐스트 단부 세그먼트를 이용한 교량시공방법을 제공한다.In addition, the center segment is preferably made of concrete of less strength than the high-strength concrete used in the precast end segment for continuous bridges between the two precast end segments for continuous bridges disposed spaced apart from each other in the longitudinal direction of the girder, and internal reinforcement The bridge construction method using the continuous bridge precast end segment is formed so that the connecting reinforcement of the internal reinforcement and the continuous bridge precast end segment is connected to each other by the overlapping joint method and integrated with the continuous bridge precast end segment do.
또한 바람직하게는 상기 프리캐스트 단부 세그먼트와 중앙부 세그먼트에 의하여 일체화된 거더는 프리스트레스 철근콘크리트 거더로써 내부에 미리 설치된 쉬스를 통해 설치된 긴장재에 의하여 프리스트레스를 도입시키는 단계가 더 포함되도록 하는 연속교용 프리캐스트 단부 세그먼트를 이용한 교량시공방법을 제공한다.Also preferably, the girder integrated by the precast end segment and the center segment further includes the step of introducing the prestress by a tension member installed through a sheath preinstalled therein as the prestressed reinforced concrete girder. Provide bridge construction method using
본 발명에 의하여 양 단부 즉, 연속교용 프리캐스트 단부 세그먼트를 미리 제작하여 놓은 상태에서 거더 전체를 제작하므로 거더 제작을 위한 거푸집 활용을 효율화시켜 거더 제작에 따른 비용을 절감할 수 있을 뿐만 아니라,According to the present invention, since the entire girder is manufactured in a state in which both ends, that is, a precast end segment for continuous bridges, are manufactured in advance, the use of formwork for girder efficiency can be reduced, thereby reducing the cost of girder fabrication.
거더의 양 단부를 프리캐스트화 하여 제작하되 고강도 콘크리트를 이용하여 제작하므로 정착장치에 의한 프리스트레스 도입에 따른 국부하중의 집중에 효과적으로 저항할 수 있게 되고,Both ends of the girder are manufactured by precasting, but using high-strength concrete, it is possible to effectively resist the concentration of local load due to the introduction of prestress by the fixing device.
또한 거더의 연장길이에 따른 거더 제작이 용이하여 공장에서의 품질관리에 만전을 기할 수 있게 된다.In addition, it is easy to manufacture girders according to the extension length of the girders to ensure full quality control in the factory.
또한 교각과 같은 지점부에 있어서 연속교용 프리캐스트 단부 세그먼트에 의한 거더 연결시공이 용이하여 효율적인 연속교 시공이 가능하게 된다.In addition, the girder connection construction by the precast end segment for continuous bridges is easy at the same point portion as the bridge piers, which enables efficient continuous bridge construction.
본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is shown by the following claims rather than the above description, and all changes or modifications derived from the meaning and scope of the claims and their equivalents should be construed as being included in the scope of the present invention. do.
도 1a는 종래 거더교의 시공사시도,
도 1b는 종래 거더용 거푸집과 탈형후 거더의 일부사시도,
도 1c는 종래 세그먼트화 된 거더의 제작사시도,
도 1d는 종래 세그먼트화 된 거더의 결합사시도,
도 2a는 본 발명의 연속교용 프리캐스트 단부 세그먼트의 사시도,
도 2b, 도 2c 및 도 2d는 본 발명에 의한 연속교용 프리캐스트 단부 세그먼트 및 중앙부 세그먼트의 결합사시도,
도 3a, 도 3b, 도 3c 및 도 3d는 본 발명에 의한 거더의 제작방법의 순서도,
도 4a 및 도 4b는 본 발명에 의한 교량시공사시도이다.Figure 1a is a construction attempt of the conventional girder bridge,
Figure 1b is a partial perspective view of the girder after the formwork and demolding for the conventional girder,
Figure 1c is a manufacturing perspective view of a conventional segmented girder,
1D is a perspective view of a conventional segmented girder,
2A is a perspective view of a precast end segment of a continuous bridge of the present invention;
2b, 2c and 2d is a perspective view of the combination of the continuous bridge precast end segment and the center segment according to the present invention,
Figure 3a, 3b, 3c and 3d is a flow chart of the manufacturing method of the girder according to the present invention,
4a and 4b is a bridge construction attempt according to the present invention.
아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.DETAILED DESCRIPTION Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art may easily implement the present invention. The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. In the drawings, parts irrelevant to the description are omitted in order to clearly describe the present invention, and like reference numerals designate like parts throughout the specification.
< 연속교용 프리캐스트 단부 세그먼트(110) ><
먼저, 본 발명의 거더(100)는 크게 연속교용 프리캐스트 단부 세그먼트(110)과 중앙부 세그먼트(120)로 크게 구분된다.First, the
이에 먼저 도 2a를 기준으로 본 발명에 의한 연속교용 프리캐스트 단부 세그먼트(110)를 살펴보도록 한다.First, the continuous bridge precast
먼저, 상기 연속교용 프리캐스트 단부 세그먼트(110)는 거더의 단면형태에 따라 결정되는데 거더는 통상 I형 단면 또는 T형 단면으로 제작된다. 단지 본 발명은 특히 T형 단면으로 제작되는 거더를 기준으로 살펴본다.First, the continuous
이에 상기 연속교용 프리캐스트 단부 세그먼트(110)는 수평판 형태의 상부플랜지(111); 상기 상부플랜지 저면에 하방으로 연장되어 형성된 외측단부(115)와 외측단부(115)보다 폭이 좁게 형성된 내측단부(116)가 서로 일체로 형성된 것으로써, 상기 외측단부(115)의 외측단부면은 전단키(A) 형태로 단차져 형성되고 상기 내측단부(116)의 내측단부면은 연결철근(114)이 돌출 연장되어 형성된 복부(112); 및 상기 복부를 구성하는 외측단부를 거더 길이방향으로 관통하도록 형성되어 강봉을 포함하는 연결재(117)가 삽입되어 장착되는 연결홀(118);로 크게 구성된다.Accordingly, the continuous bridge precast
먼저, 상기 상부플랜지(111) 저면으로부터 하부로 연장되는 복부(112)의 경우 외측단부(115)와 내측단부(116)로 크게 구성되도록 하는데 이는 외측단부(115)의 경우 연결홀(118)이 형성되므로 보다 큰 외측단부면 면적이 필요하고, 이러한 연결홀(118)에는 연결재(117)가 삽입되어 장착되므로 정착력에 의한 하중집중에 보다 큰 단면으로 저항할 수 있도록 하기 위함이다.First, in the case of the abdomen 112 extending downward from the bottom of the
이러한 외측단부(115)에 있어 그 외측단부면에는 전단키(A)가 형성되어 있는데 이는 다른 연속교용 프리캐스트 단부 세그먼트(110)의 전단키(A)와 서로 맞물려지도록 단차지도록 형성시키게 된다.In the
또한 내측단부(116)는 외측단부(115)와 대비하여 폭이 작고 내측단부면은 연결철근(114)이 거더의 길이방향으로 돌출되어 연장 형성되어 있다. 이러한 연결철근(114)에 대하여는 후술된다.In addition, the
이러한 연속교용 프리캐스트 단부 세그먼트(110)는 프리스트레스 철근콘크리트로 제작되며 외측단부(115)에 있어 그 외측단부면에는 거더에 프리스트레스를 도입하기 위한 정착장치(113)가 다수 설치된다.The
이러한 정착장치(113)는 미도시된 긴장재를 수용하는 쉬스(SHEATH), 쉬스의 단부가 연결되고 PC 강연선과 같은 긴장재가 관통되는 쐐기홀이 다수 형성된 앵커체, 긴장재를 정착하기 위한 쐐기 및 정착판을 포함하여 구성되며 통상의 PC 강연선용 정착장치를 의미한다.The fixing
이러한 정착장치(113)는 연속교용 프리캐스트 단부 세그먼트(110) 외부에서 보면 정착판 및/또는 쉬스만이 노출되고, 앵커체는 연속교용 프리캐스트 단부 세그먼트(110)에 매립되고 긴장재 및 쐐기 등은 실제 긴장재를 긴장 및 정착할 때 이용된다.When the fixing
이에 도 2a에 의하면 다수의 정착장치(113)가 연속교용 프리캐스트 단부 세그먼트(110)의 복부(112)의 양 외측단부면에 형성되어 있음을 알 수 있는데 이러한 정착장치는 각각 4개가 설치되어 있음을 알 수 있으나 이보다 많을 수도 있고 적을 수도 있다.2a shows that a plurality of fixing
하지만 장경간의 거더를 제작하는 경우 소요의 긴장재가 많아 다발형태의 긴장재를 이용한다 할지라도 연속교용 프리캐스트 단부 세그먼트(110)의 양 단부면에는 많은 정착장치(113)가 형성될 수 밖에 없다.However, when the long span girders are manufactured, many fixing
또한 이러한 정착장치(113) 부위에는 실제 긴장재가 긴장후 정착되는 부위이므로 프리스트레스 도입에 따른 국부응력이 집중되기 때문에 이러한 국부응력에 저항할 수 있는 단면적 및 피복두께를 확보해야 하지만 거더 단면이 슬림화되는 최근 경향에 맞추다 보면 이러한 정착장치를 전부 수용할 수 있는 단부면을 가진 연속교용 프리캐스트 단부 세그먼트(110)를 제작하기 어렵다는 문제점이 발생하게 된다.In addition, since the local tension is concentrated in the
또한 상기 국부응력에 충분히 저항하기 위해서는 고강도 콘크리트를 사용해야 하지만, 프리캐스트 단부 세그먼트(110)의 단부만 고강도 콘크리트로 형성시키고, 단부 사이의 중앙부는 상기 고강도 콘크리트 보다 작은 강도의 콘크리트를 혼용하는 경우 강도가 다른 콘크리트 경계면에 추후 하중 집중에 의한 슬라이딩이 발생할 우려가 있다.In addition, in order to sufficiently resist the local stress, high-strength concrete should be used, but only the end of the
이에 강도가 다른 2가지 콘크리트를 한꺼번에 타설하는 것은 바람직하지 않지만 먼저 1가지 강도에 의한 콘크리트 부재를 제작하되 일체성을 확보할 수 있는 연결철근을 미리 제작된 부재로부터 연장시키고, 다른 강도를 가지는 콘크리트 부재의 내부철근을 상기 연결철근에 서로 연결시킨 상태에서 별도의 거푸집과 다른 강도의 콘크리트를 거푸집에 타설하여 다른 강도를 가지는 콘크리트 부재를 먼저 제작된 콘크리트 부재와 일체화시키면 이러한 문제점을 방지할 수 있게 된다.Therefore, it is not desirable to pour two concretes with different strengths at once, but first, a concrete member made of one strength should be manufactured, but the connecting reinforcing bar which can secure the integrity can be extended from the prefabricated member, and the concrete member having different strengths. This problem can be prevented by integrating a concrete member having a different strength with a concrete having different strength by pouring concrete of different formwork and different strength into the formwork while connecting the internal reinforcing bars to each other.
이에 본 발명은 연속교용 프리캐스트 단부 세그먼트(110)를 제작함에 있어 고강도 콘크리트를 이용하여 먼저 제작하게 된다.Accordingly, the present invention is to produce the first using a high-strength concrete in the production of the continuous bridge precast end segment (110).
이와 같이 먼저 제작된 연속교용 프리캐스트 단부 세그먼트(110)는 소정의 길이를 가지도록 제작되는데 이러한 길이는 제작후 운반 등을 고려하여 되도록 작은 길이를 가지도록 함이 바람직하며, 내측단부를 구성하는 외측단부면에는 연결철근(114)이 다수 길이방향으로 연장되도록 돌출 형성되어 있음을 알 수 있다.The
이러한 연결철근(114)은 연속교용 프리캐스트 단부 세그먼트(110)의 상부플랜지(111)와 복부(112) 전체에 걸쳐 연장되도록 하여야 일체화되는 중앙부 세그먼트(120)의 내부철근(124)과 연결되어 서로의 일체성을 충분히 확보할 수 있게 된다.These connecting
이러한 연속교용 프리캐스트 단부 세그먼트(110)는 프리캐스트 단부 세그먼트(110)용 거푸집을 미리 제작하여 공장에서 제작하게 되며 엄격한 품질관리를 적용하여 제작할 수 있게 된다.The continuous bridge precast
< 연속교용 프리캐스트 단부 세그먼트(110)와 중앙부 세그먼트(120)에 의한 거더(100) ><
도 2b, 도 2c 및 도 2d는 본 발명에 의한 연속교용 프리캐스트 단부 세그먼트(110) 및 중앙부 세그먼트(120)의 결합에 의한 거더의 사시도들을 도시한 것이다.2B, 2C and 2D show perspective views of the girder by engagement of the continuous bridge precast
이러한 본 발명의 거더(100)는 크게 연속교용 프리캐스트 단부 세그먼트(110)과 중앙부 세그먼트(120)로 크게 구분된다.The
먼저, 상기 연속교용 프리캐스트 단부 세그먼트(110)는 앞서 살펴본 바와 같고, 도 2b와 같이 중앙부 세그먼트(120)의 일측에 설치되거나, 도 2c 및 도 2d와 같이 양측 모두에 설치될 수 있다.First, the continuous
즉, 도 2b는 2경간 교량(교대 사이에 교각이 있어 교대와 교각 사이에 거더가 각각 설치되는 경우)에 있어 교각과 같은 지점부에서 거더가 연결되어야 하므로 연속교용 프리캐스트 단부 세그먼트(110)는 각 거더의 중앙부 세그먼트(120) 일 단부에만 형성시켜 연속교용 프리캐스트 단부 세그먼트(110)에 다른 거더의 연속교용 프리캐스트 단부 세그먼트(110)가 연결홀 및 연결재에 의하여 서로 연결시키게 됨을 보인 것이고,That is, Figure 2b is a continuous bridge precast
도 2c의 경우에는 도 2b에 있어 거더의 타 단부에도 연속교용 프리캐스트 단부 세그먼트(110)가 형성되어 각각 다른 거더의 연속교용 프리캐스트 단부 세그먼트(110)가 연결홀 및 연결재에 의하여 서로 연결시키게 됨을 보인 것이고,In the case of FIG. 2C, the continuous bridge precast
도 2d의 경우에는 예컨대 교각과 같은 지점부 양 측방으로 거더가 각각 연결시키는 방식으로 시공할 경우에 해당되는 것으로 복부의 저면이 중앙부로 갈수록 커지는 아치단면 형태의 중앙부 세그먼트(120)의 양 단부에 연속교용 프리캐스트 단부 세그먼트(110)가 각각 형성되고, 이러한 연속교용 프리캐스트 단부 세그먼트(110)에 다른 거더들이 각각 연속교용 프리캐스트 단부 세그먼트(110)가 연결홀 및 연결재에 의하여 서로 연결되도록 함을 보인 것이다.In the case of FIG. 2D, for example, when the girders are connected to both sides of a point portion such as a piers, respectively, the bottom surface of the abdomen is continuous at both ends of the
이에 본 발명의 거더는 중앙부 세그먼트(120)의 일단부 또는 양 단부에 거더의 전체 길이방향으로 연장되는 길이에 따라 중앙부 세그먼트(120)가 일체화되도록 형성됨을 알 수 있다.Accordingly, it can be seen that the girder of the present invention is formed so that the
이러한 중앙부 세그먼트(120)의 연장길이에 따라 역시 별도의 중앙부 세그먼트용 거푸집을 이용하여 형성시킬 수 있게 되며, 중요한 점은 도 2b, 도 2c 및 도 2d와 같이 연속교용 프리캐스트 단부 세그먼트(110)의 연결철근(114)과 중앙부 세그먼트(120)의 내부철근(124)은 반드시 연결되도록 해야 한다는 것이다.According to the extension length of the
이는 연속교용 프리캐스트 단부 세그먼트(110)와 중앙부 세그먼트(120)의 구조적 일체화를 위해 매우 중요하기 때문이다.This is because it is very important for the structural integration of the continuous cross
이를 위해 중앙부 세그먼트(120)는 하중 저항에 필요한 내부철근(124)을 배근할 때 상기 프리캐스트 단부 세그먼트(110)의 연결철근(114)의 연결을 고려하여 연결철근(114)의 위치에 대응하는 내부철근(124)을 중앙부 세그먼트에 배근되도록 하게 된다.For this purpose, the
이에 상기 연결철근(114)과 내부철근(124)이 서로 연결된 상태에서 중앙부 세그먼트용 거푸집 내부에 콘크리트를 타설하여 중앙부 세그먼트와 프리캐스트 단부 세그먼트(110)를 일체화 시키게 되면,When the connecting
최종 도 2b, 도 2c 및 도 2d와 같이 본 발명의 프리캐스트 단부 세그먼트(110)를 단부거푸집으로 이용하는 거더(100)가 완성된다.As shown in FIGS. 2B, 2C and 2D, the
이와 같이 최종 완성된 거더는 프리스트레스가 도입되게 되는데 앞서 살펴본 정착장치를 구성하는 쉬스가 프리캐스트 단부 세그먼트와 미도시된 중앙부 세그먼트에 서로 연통되도록 하고, 상기 쉬스에 PC 강연선과 같은 긴장재를 삽입 한 후, 긴장재의 양 단부를 프리캐스트 단부 세그먼트의 정착장치(113)에 긴장후 정착하게 되면, 본 발명의 거더(100)에 프리스트레스가 도입된다.Thus, the final girder is introduced to the prestress, and the sheath constituting the fixing device described above is in communication with the precast end segment and the center segment not shown, and after inserting a tension member such as a PC strand into the sheath, When both ends of the tension member are tensioned and fixed to the
이러한 프리스트레스 도입에 의하여 거더 전체에 소요의 압축응력이 발생하게 되며, 이러한 압축응력을 크게 형성시키더라도 프리캐스트 단부 세그먼트는 고강도로 제작되어 있기 때문에 국부응력에 의한 프리캐스트 단부 세그먼트의 저항성능을 충분히 확보할 수 있게 된다.This prestressing introduces the necessary compressive stress in the entire girder. Even if the compressive stress is large, the precast end segment is made of high strength, thus sufficiently securing the resistance performance of the precast end segment due to local stress. You can do it.
<프리캐스트 단부 세그먼트를 단부거푸집으로 이용하는 거더(100) 제작방법><Method of
도 3a 내지 도 3d는 본 발명에 의한 거더 제작방법을 개략적인 순서로 도시한 것이다.3A to 3D show the girder manufacturing method according to the present invention in a schematic order.
먼저, 도 3a는 특히 도 2b에 의한 본 발명에 의한 거더(100)를 제작하기 위한 레일부(210)와 대차(220)를 정면도로 도시한 것이다.First, FIG. 3A shows the
상기 레일부(210)는 적어도 소정의 길이를 가진 거더(100)를 제작하기 위한 길이보다 더 연장된 길이를 가지도록 지반에 세팅하게 되며 이러한 레일부는 지반에 레일을 횡방향으로 이격시켜 설치하여 후술되는 대차(220)가 슬라이딩 하면서 위치를 이동할 수 있도록 하는 가이드역할을 하게 된다.The
또한 상기 대차(220)는 앞서 살펴본 본 발명의 프리캐스트 단부 세그먼트(110)가 얹어져 레일부(210)를 따라 이동할 수 있는 받침대차로써 적어도 2개가 각각 설치되도록 하되, 프리캐스트 단부 세그먼트(110)가 싣어질 수 있는 면적을 가지도록 제작된 것이 이용된다.In addition, the
이에 상기 대차는 크게 상부판과 상부판 저면에 레일부를 따라 이동하는 바퀴를 포함하여 구성될 수 있을 것이다.Accordingly, the bogie may be configured to include wheels that move along the rails on the top and bottom of the top plate.
이러한 프리캐스트 단부 세그먼트(110)가 얹어진 대차(220)는 레일부(210)를 따라 서로 종방향으로 이격되어 거더의 전체 연장길이(L)에서 양 프리캐스트 단부 세그먼트(110)의 연장길이(L1)를 제외한 만큼만 이격(L-L1=L2)되도록 하게 된다.The
이에 상기 이격된 거리(L2)에 해당하는 중앙부 세그먼트용 거푸집을 세팅하여 거더 제작을 위한 거푸집의 제작 및 설치를 규격화 할 수 있게 되며 이에 대하여는 후술한다.Accordingly, by setting the formwork for the central portion corresponding to the distance (L2) spaced apart it is possible to standardize the production and installation of formwork for girder fabrication will be described later.
이에 양 대차(220)에 의하여 종방향으로 이격된 프리캐스트 단부 세그먼트(110) 사이에는 중앙부 세그먼트용 거푸집(230)이 통상의 거푸집 받침대(240)에 의하여 설치되도록 하게 된다.Thus, between the
이러한 중앙부 세그먼트용 거푸집(230)은 도 1b와 같은 강재 거푸집을 다수 조립하여 연장시켜 사용할 수 있는데, 중요한 것은 미리 제작된 프리캐스트 단부 세그먼트(110)의 저면이 중앙부 세그먼트용 거푸집(230) 양 단부 상면에 세팅되도록 하게 된다는 점이다.The
즉, 본 발명의 프리캐스트 단부 세그먼트(110)는 거더 전체 길이에 따라 변하는 길이를 가지도록 제작하는 것이 아니라 일률적인 길이를 가지도록 미리 제작하게 되며 운반 및 설치를 위하여 되도록 2m 이내의 작은 길이를 가지도록 미리 제작하게 된다.That is, the
반면 이러한 프리캐스트 단부 세그먼트(110)와 일체화 되는 중앙부 세그먼트(120)는 거더 전체 연장길이에 따라 다양한 길이를 가지게 되므로 이를 위한 중앙부 세그먼트용 거푸집(230)도 다양할 연장길이를 가질 수 밖에 없다.On the other hand, since the
하지만 이러한 중앙부 세그먼트용 거푸집(230)도 1m, 2m와 같이 단위길이를 가진 거푸집을 미리 제작하여 서로 연결시켜 가면서 설치하게 되므로 원하는 길이를 가진 중앙부 세그먼트용 거푸집(230)은 프리캐스트 단부 세그먼트(110)의 이격거리에 정확하게 맞출 수 없게 되는 것이 일반적이다.However, such a
예컨대 중앙부 세그먼트(120)의 길이가 25.5M일 경우 1M짜라 거푸집 26개를 사용할 경우 0.5M가 남게 된다.For example, when the length of the
이에 본 발명은 도 3b와 같이 프리캐스트 단부 세그먼트(110)의 저면이 중앙부 세그먼트용 거푸집(230)의 양 단부 상면에 얹어지도록 할 경우 중앙부 세그먼트용 거푸집(230)의 세팅길이가 프리캐스트 단부 세그먼트(110)의 이격길이에 맞지 않는다 할지라도 중앙부 세그먼트용 거푸집(230)의 내부로 프리캐스트 단부 세그먼트(110)를 소정의 길이만큼 삽입하여 설치함으로써 필요로 하는 이격거리를 맞출 수 있게 된다.Accordingly, in the present invention, when the bottom surface of the
다음으로는 상기 프리캐스트 단부 세그먼트(110)의 연결철근(114)과 중앙부 세그먼트(120)의 내부철근(124)을 거푸집 내부에 배근하게 되며 미도시된 쉬스도 프리캐스트 단부 세그먼트(110)의 쉬스에 대응하여 배치시키게 된다.Next, the connecting
다음으로 상기 연결철근과 내부철근은 겹이음방식으로 서로 겹쳐지도록 한 상태에서, 서로를 가는 철선등을 이용하여 서로 연결시키게 된다.Next, the connecting reinforcing bars and the internal reinforcing bars are connected to each other by using thin wires, etc., in a state of overlapping each other in a lap joint manner.
이때 도 3c와 같이 상기 프리캐스트 단부 세그먼트(110)의 단부면은 중앙부 세그먼트(120)의 단부거푸집 역할도 하게 되므로 프리캐스트 단부 세그먼트용 거푸집(230) 내부에 콘크리트(C)를 타설하게 된다.At this time, the end surface of the
이에 최종 타설된 콘크리트가 양생되면, 프리캐스트 단부 세그먼트(110)와 중앙부 세그먼트(120)는 서로 일체화됨을 알 수 있다.As the final poured concrete is cured, it can be seen that the
다음으로는 도 3d와 같이 상기 중앙부 세그먼트용 거푸집(230)을 탈형함과 더불어 서로 일체화된 프리캐스트 단부 세그먼트(110)와 중앙부 세그먼트(120)에 의한 본 발명의 거더(100)를 인양하여 적치시켜 놓아 최종 제작을 완성시킬 수 있게 된다.Next, as shown in FIG. 3D, the
다음으로 상기 거더(100)는 내부에 서로 연통된 쉬스가 배치되어 있으므로 공장에서 미리 긴장재 및 앵커체를 포함하는 정착장치를 이용하여 거더에 프리스트레스에 의한 압축응력이 도입되도록 할 수도 있고, 현장에 거치된 상태에서 상기 압축응력을 도입시키거나 압축응력은 제작 및 시공상의 공종에 따라 1회 또는 복수회에 걸쳐 도입시킬 수 있을 것이다.Next, since the sheaths are arranged in communication with each other inside the
<연속교용 프리캐스트 단부 세그먼트를 단부거푸집으로 이용하는 거더(100)를 이용한 교량시공방법><Bridge construction
도 4a 및 도 4b는 특히 도 2b 및 도 2d에 의한 본 발명의 거더를 이용한 연속교 시공사시도이다.4A and 4B are views of the construction of a continuous bridge using the girder of the present invention, in particular by FIGS. 2B and 2D.
먼저 도 4a를 기준으로 하면, 특히 2경간 교량에 있어 연속교용 프리캐스트 단부 세그먼트(110)가 일측에 형성된 거더(100)를 제작하게 된다.First, referring to FIG. 4A, a
연속교용 프리캐스트 단부 세그먼트(110)가 일측에 형성된 거더(100)는 이미 앞서 살펴본 바와 같으며, 이러한 거더는 교대 사이에 설치된 교각(410)에 거치되도록 하게 된다.The
이때 상기 거더(100)는 긴장재를 이용하여 이미 프리스트레스가 도입된 것을 이용하게 되며, 각 거더(100)에 있어 연속교용 프리캐스트 단부 세그먼트(110)의 연결철근(114)과 중앙부 세그먼트(120)의 내부철근(124)은 서로 겹침이음방식으로 서로 연결되어 있으며, 연속교용 프리캐스트 단부 세그먼트(110)는 중앙부 세그먼트(120)보다 강도가 큰 고강도 콘크리트로 형성되어 있게 된다.At this time, the
물론 이러한 거더(100)는 미도시된 교량받침을 이용하여 교량하부구조인 교대, 교각에 거치하게 될 것이다.Of course, such a
통상 연속교는 거더의 연속화가 전제되어야 하므로 교량하부구조에 거치된 거더(100)는 연속교용 프리캐스트 단부 세그먼트(110)가 서로 접하도록 하게 된다.In general, the continuous bridge is to be continuity of the girder, so the
즉, 연속교용 프리캐스트 단부 세그먼트(110)의 외측단부면은 각각 전단키(A)가 형성되어 있으므로 서로 맞물리도록 거치할 수 있다.That is, the outer end surface of the continuous
다음으로 각 거더(100)를 서로 연속화시키게 된다. 이를 위해 연속교용 프리캐스트 단부 세그먼트(110)를 구성하는 외측단부(115)의 연결홀(118)에 강봉과 같은 연결재(117)를 삽입하고, 연결재(117) 단부를 외측단부에 정착시켜 각 거더를 구조적으로 연속화 시키게 된다.Next, each
물론 교각(410)에 있어 횡방향으로 이격된 각 거더들도 마찬가지로 연속화시키게 된다.Of course, each girder laterally spaced in the
다음으로 각 거더를 횡방향으로 구속하는 가로보를 설치하여 가로보에 의하여 거더들이 횡방향으로 구속되도록 하게 된다.Next, by installing horizontal beams that restrain each girder in the transverse direction, the girders are constrained in the transverse direction by the horizontal beams.
다음으로 상기 거더 상부에 슬래브(300)를 형성시켜 최종 거더교가 완성될 수 있도록 하게 된다.Next, the
다음으로 도 4b를 기준으로 하면, 교대와 교각(410)을 먼저 시공함은 동일하고, 특히 거더(100)는 도 2a 및 도 2d에 의한 거더(100)가 이용됨을 알 수 있다.Next, referring to FIG. 4B, the construction of the alternation and the
즉, 교각(410)에는 복부의 저면이 중앙부로 갈수록 커지는 아치단면 형태의 중앙부 세그먼트(120)의 양 단부에 연속교용 프리캐스트 단부 세그먼트(110)가 각각 형성되어 있음을 알 수 있다.That is, the
이에 상기 교각에 설치된 도 2d에 의한 거더(100)의 양 단부에는 도 2a에 의한 거더(100) 즉, 일 단부에 연속교용 프리캐스트 단부 세그먼트(110)가 각각 형성된 거더(100)가 연결된다.Thus, both ends of the
역시 연속교는 거더의 연속화가 전제되어야 하므로 교량하부구조에 거치된 거더(100)는 연속교용 프리캐스트 단부 세그먼트(110)가 서로 접하도록 하게 된다.In addition, the continuous bridge is a premise of the girder continuation of the
즉, 각 연속교용 프리캐스트 단부 세그먼트(110)의 외측단부면은 각각 전단키(A)가 형성되어 있으므로 서로 맞물리도록 거치할 수 있다.That is, the outer end surface of each of the continuous bridge precast
다음으로 각 거더(100)를 서로 연속화시키게 된다. 이를 위해 역시 연속교용 프리캐스트 단부 세그먼트(110)를 구성하는 외측단부(115)의 연결홀(118)에 강봉과 같은 연결재(117)를 삽입하고, 연결재(117) 단부를 외측단부에 정착시켜 각 거더를 구조적으로 연속화 시키게 된다.Next, each
역시 교각(410)에 있어 횡방향으로 이격된 각 거더들도 마찬가지로 연속화시키게 된다.Also In the
다음으로 각 거더를 횡방향으로 구속하는 가로보를 설치하여 가로보에 의하여 거더들이 횡방향으로 구속되도록 하게 되며, 상기 거더 상부에 슬래브(300)를 형성시켜 최종 거더교가 완성될 수 있도록 하게 된다.Next, by installing horizontal beams that restrain each girder in the transverse direction, the girders are constrained in the transverse direction by the horizontal beams, and the
100: 거더
110: 프리캐스트 단부 세그먼트
111: 상부플랜지 112: 복부
113: 정착장치 114: 연결철근
115: 외측단부 116: 내측단부
117: 연결재 118: 연결홀
120: 중앙부 세그먼트 124:내부철근
210: 레일부 220:대차
230:중앙부 세그먼트용 거푸집 240:거푸집 받침대
300:슬래브 410:교각
C: 콘크리트100: girder
110: precast end segment
111: upper flange 112: abdomen
113: fixing device 114: connecting rebar
115: outer end 116: inner end
117: connecting member 118: connecting hole
120: center segment 124: internal reinforcement
210: rail portion 220: cart
230: formwork for the center part segment 240: formwork support
300: Slab 410: Pier
C: concrete
Claims (10)
상기 상부플랜지 저면에 하방으로 연장되어 외측단부와 외측단부보다 폭이 좁게 형성된 내측단부가 서로 일체로 형성된 것으로써, 상기 외측단부의 외측단부면은 전단키 형태로 단차져 형성되고 상기 내측단부의 내측단부면은 연결철근이 돌출 연장되어 형성된 복부; 및
상기 복부를 구성하는 외측단부를 거더 길이방향으로 관통하도록 형성되어 강봉을 포함하는 연결재가 삽입되어 장착되는 연결홀;을 포함하며 고강도 콘크리트를 이용하여 미리 프리캐스트로 제작된 연속교용 프리캐스트 단부 세그먼트.An upper flange in the form of a horizontal plate;
An inner end portion formed downwardly on the bottom surface of the upper flange and having a width smaller than that of the outer end portion and the outer end portion is formed integrally with each other. The outer end portion of the outer end portion is formed stepped in the form of a shear key and the inner end portion of the inner end portion. The abdomen includes: an abdomen formed by protruding connecting bars; And
And a connection hole formed to penetrate the outer end portion of the abdomen in a girder longitudinal direction and having a connection member including a steel rod inserted thereinto. The precast end segment for a continuous bridge including a high strength concrete.
거더 길이방향으로 서로 이격되어 배치된 양 연속교용 프리캐스트 단부 세그먼트 사이에 연속교용 프리캐스트 단부 세그먼트에 사용된 고강도 콘크리트보다 작은 강도의 콘크리트로 제작되는 중앙부 세그먼트가 더 형성되도록 하되, 상기 중앙부 세그먼트에는 내부철근이 형성되어 상기 내부철근과 연속교용 프리캐스트 단부 세그먼트의 연결철근이 서로 겹침이음방식으로 서로 연결된 상태로 연속교용 프리캐스트 단부 세그먼트와 중앙부 세그먼트가 서로 일체화되어 거더로 제작되도록 하는 것을 특징으로 하는 연속교용 프리캐스트 단부 세그먼트.The method of claim 1, wherein the continuous bridge precast end segment
Between the two continuous bridge precast end segments spaced apart from each other in the longitudinal direction of the girder, a center segment made of concrete of less strength than the high-strength concrete used in the continuous bridge precast end segment is formed. Reinforcement is formed continuous continuous precast end segment and the center portion of the continuous bridge is characterized in that the connection between the reinforcing bars and the precast end segment for continuous bridge connected to each other in the overlapping manner to be integrated with each other to be manufactured as a girder Alternate precast end segment.
거더 제작길이에 대응하여 제작할 거더의 양 단부에 위치하도록 상기 프리캐스트 단부 세그먼트를 거더의 길이방향으로 서로 이격 배치하고,
상기 프리캐스트 단부 세그먼트 사이에 중앙부 거푸집을 세팅하여 중앙부 세그먼트를 제작하되, 상기 중앙부 거푸집은 양 프리캐스트 단부 세그먼트의 저면이 중앙부 거푸집 양 단부 내측바닥판 상면에 배치되도록 하고,
상기 중앙부 거푸집 내부에 콘크리트를 타설하여 양생시킨 후, 상기 중앙부 거푸집을 탈형하는 단계를 포함하는 것을 특징으로 하는 연속교용 프리캐스트 단부 세그먼트를 단부거푸집으로 이용하는 거더 제작방법.An upper flange in the form of a horizontal plate using both high strength concrete on both end segments of the girder where prestress by the fixing device is concentrated; An inner end portion formed downwardly on the bottom surface of the upper flange and having a width smaller than that of the outer end portion and the outer end portion is formed integrally with each other. The outer end portion of the outer end portion is formed stepped in the form of a shear key and the inner end portion of the inner end portion. The abdomen includes: an abdomen formed by protruding connecting bars; And a connecting hole formed to penetrate the outer end portion of the abdomen in the longitudinal direction of the girder to be inserted and mounted with a connecting member including a steel rod.
The precast end segments are spaced apart from each other in the longitudinal direction of the girder so as to be located at both ends of the girder to be manufactured corresponding to the girder fabrication length,
The central form is set between the precast end segments to form a central segment, wherein the central form is such that bottoms of both precast end segments are disposed on the upper surface of the inner bottom plate at both ends of the central formwork,
And casting the concrete inside the central formwork to cure, and then demolding the central formwork. The method of manufacturing a girder using the precast end segment for continuous bridges as end formwork.
상기 프리캐스트 단부 세그먼트와 중앙부 세그먼트는, 프리캐스트 단부 세그먼트의 양 단부면으로부터 길이방향으로 미리 연장되도록 돌출 형성된 연결철근과 중앙부세그먼트용 내부철근을 서로 겹침이음방식으로 서로 연결시킨 후, 콘크리트를 타설하여 양생시켜 서로 일체화되도록 하는 것을 특징으로 하는 연속교용 프리캐스트 단부 세그먼트를 단부거푸집으로 이용하는 거더 제작방법.6. The method of claim 5,
The precast end segment and the center segment are connected to each other by overlapping joints of the connecting reinforcing bar and the inner reinforcing bar for the middle segment, which are formed to extend in the longitudinal direction from both end faces of the precast end segment, and then cast concrete. A method for manufacturing a girder using precast end segments for continuous bridges as end formwork, characterized in that the curing is integrated with each other.
상기 서로 접하도록 설치된 프리캐스트 단부 세그먼트들의 연결홀에 통해 강봉을 포함하는 연결재를 삽입시킨 후 연결재의 양 단부를 정착시켜 연속 설치된 프리캐스트 단부 세그먼트들을 서로 연결시키는 단계를 포함하는 것을 특징으로 하는 연속교용 프리캐스트 단부 세그먼트를 이용한 교량시공방법.An upper flange in the form of a horizontal plate; An inner end portion formed downwardly on the bottom surface of the upper flange and having a width smaller than that of the outer end portion and the outer end portion is formed integrally with each other. The outer end portion of the outer end portion is stepped in the form of a shear key and the outer end portion of the inner end portion. The abdomen includes: an abdomen formed by protruding connecting bars; And a connecting hole formed to penetrate the outer end portion of the abdomen in the longitudinal direction of the girder in such a manner that a connecting member including a steel rod is inserted and mounted therein. The precast end segment for a continuous bridge made of precast using high strength concrete in advance. The inner point girders integrally formed at one or both ends of the center segment are installed in the bridge substructure including the bridge so that the precast end segments for continuous bridges are in contact with each other.
And inserting a connecting member including a steel rod through the connecting holes of the precast end segments installed to be in contact with each other, and then fixing both ends of the connecting member to connect the precast end segments continuously installed to each other. Bridge construction method using precast end segment.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100118556A KR101177342B1 (en) | 2010-11-26 | 2010-11-26 | Precast end segmet girder for continuous bridge, girder making method and bridge construction method using the same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100118556A KR101177342B1 (en) | 2010-11-26 | 2010-11-26 | Precast end segmet girder for continuous bridge, girder making method and bridge construction method using the same |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20120057021A KR20120057021A (en) | 2012-06-05 |
KR101177342B1 true KR101177342B1 (en) | 2012-08-30 |
Family
ID=46608974
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020100118556A KR101177342B1 (en) | 2010-11-26 | 2010-11-26 | Precast end segmet girder for continuous bridge, girder making method and bridge construction method using the same |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101177342B1 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2016148526A1 (en) * | 2015-03-17 | 2016-09-22 | (주)길교이앤씨 | U-shaped pc girder having broad stem portion |
CN106498859A (en) * | 2016-12-22 | 2017-03-15 | 云南大力神金属构件有限公司 | Be applicable to the support system of assembled architecture and bridge construction |
KR102188663B1 (en) * | 2020-03-24 | 2020-12-09 | 주식회사 길교이앤씨 | Precast end block, psc girder with the same, bridge with the psc girder and construction method of the psc girder using the same |
KR102241713B1 (en) * | 2020-07-28 | 2021-04-20 | 주식회사 길교이앤씨 | Precast end block, concrete girder for rahmen with the same, bridge with the concrete girder for rahmen and construction method of the concrete girder for rahmen using the same |
Families Citing this family (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101335446B1 (en) * | 2012-06-07 | 2013-12-02 | 한국건설기술연구원 | Manufacturing method of fiber reinforced concrete member using perforated panel |
CZ2015619A3 (en) * | 2015-09-11 | 2016-11-23 | Hynek Siedek | Prefabricated prestressed girder, intended especially for precise building |
CN107806015B (en) * | 2017-10-09 | 2019-03-22 | 中国十七冶集团有限公司 | A kind of unit construction bridge beam flange plate formwork for placing concrete system and construction method |
CN108951398A (en) * | 2018-09-19 | 2018-12-07 | 安徽省交通规划设计研究总院股份有限公司 | A kind of beam sections for adding horizontal distribution reinforcing bar |
CN109162192A (en) * | 2018-09-19 | 2019-01-08 | 同济大学 | A kind of beam sections for adding steel pipe and horizontal distribution reinforcing bar |
CN109629421B (en) * | 2018-11-20 | 2020-11-27 | 同济大学 | Construction method for segment beam additionally provided with steel pipe and horizontally distributed steel bars |
CN109610321A (en) * | 2018-11-22 | 2019-04-12 | 安徽省交通规划设计研究总院股份有限公司 | A kind of subsection beam construction method for adding horizontal distribution reinforcing bar |
CN110318469A (en) * | 2019-07-17 | 2019-10-11 | 河南城建学院 | Fabricated construction connector |
CN111424524A (en) * | 2019-09-05 | 2020-07-17 | 湖南工业大学 | Modular ultrahigh-performance concrete prefabricated assembled beam suitable for different spans |
KR102534104B1 (en) * | 2022-04-13 | 2023-05-18 | 김상효 | Girder having continuous structure and construction method using the same |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100510254B1 (en) | 2005-04-13 | 2005-08-26 | 주식회사 인터컨스텍 | Precasting method of spliced prestressed concrete girder segment and the segment precasted by above method |
KR100976847B1 (en) | 2008-02-18 | 2010-08-20 | (주)써포텍 | Precast concrete deck structure |
-
2010
- 2010-11-26 KR KR1020100118556A patent/KR101177342B1/en active IP Right Grant
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100510254B1 (en) | 2005-04-13 | 2005-08-26 | 주식회사 인터컨스텍 | Precasting method of spliced prestressed concrete girder segment and the segment precasted by above method |
KR100976847B1 (en) | 2008-02-18 | 2010-08-20 | (주)써포텍 | Precast concrete deck structure |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2016148526A1 (en) * | 2015-03-17 | 2016-09-22 | (주)길교이앤씨 | U-shaped pc girder having broad stem portion |
CN106498859A (en) * | 2016-12-22 | 2017-03-15 | 云南大力神金属构件有限公司 | Be applicable to the support system of assembled architecture and bridge construction |
KR102188663B1 (en) * | 2020-03-24 | 2020-12-09 | 주식회사 길교이앤씨 | Precast end block, psc girder with the same, bridge with the psc girder and construction method of the psc girder using the same |
KR102241713B1 (en) * | 2020-07-28 | 2021-04-20 | 주식회사 길교이앤씨 | Precast end block, concrete girder for rahmen with the same, bridge with the concrete girder for rahmen and construction method of the concrete girder for rahmen using the same |
Also Published As
Publication number | Publication date |
---|---|
KR20120057021A (en) | 2012-06-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101177342B1 (en) | Precast end segmet girder for continuous bridge, girder making method and bridge construction method using the same | |
KR101196874B1 (en) | Girder making methos for precast end seggement using end mold and girder therewith | |
KR101394193B1 (en) | Incremental launching apparatus for launching concrete slab for composite bridge using form of buried type | |
CN104929034A (en) | Small modularized steel-concrete rapid-construction box girder bridge and construction method thereof | |
KR101318773B1 (en) | T-shaped composite girder segment integrated by i-shaped girder filled with concrete and slab and construction method of slab by prefabrication of the t-shaped composite girder segment | |
KR101084397B1 (en) | A composite steel box girder using precast concrete for continuous bridges and thereof manufacturing method | |
KR101693256B1 (en) | Construction method of prefabricated psc bridge | |
KR101107826B1 (en) | Slab-type box girder made by precast concrete and method constructing the bridge therewith | |
CN110924287A (en) | Semi-fabricated large-span combined box girder and construction method thereof | |
KR101075756B1 (en) | A manufacturing process for the Truss Half Precast Prestressed Concrete Panel | |
KR20140120481A (en) | Nodular Box Girder, and Nodular Box Girder Bridge and Constructing Method thereof | |
KR101242842B1 (en) | Construction method for corrugated steel plate web-psc composite beam | |
KR101127130B1 (en) | A precast type pre-stress box girder bridge excution method | |
JP5004880B2 (en) | Concrete member joint structure | |
KR101034973B1 (en) | Bridge and its construction method using tide arch hybrid girders by connecting precast blocks | |
KR100785634B1 (en) | Continuation structure of prestressed concrete composite beam bridge and method thereof | |
KR20130090709A (en) | Construction method for corrugated steel plate web-psc composite beam | |
KR101340507B1 (en) | Pretension type composite girder and the bridge construction method therewith | |
KR100631029B1 (en) | Precasted concrete plate assembly and the construction method using thereof | |
KR101038714B1 (en) | Composite Girder Bridge with Tide Arch Shape Using Precast Slab and Its Construction Method | |
KR100583671B1 (en) | Prestressed concrete beam manufactured by installing steel anchorage devices to various positions and reinforcing member to the upper and lower flanges, and construction method of bridge using the concrete beam | |
KR200407182Y1 (en) | Precasted concrete plate | |
KR102327700B1 (en) | Girder structure and construction method for continuity of supporting portion of girder using the same | |
JPH11315511A (en) | Construction of cast-in-place concrete slab for bridge | |
KR101402620B1 (en) | Construction method of slab type rahmen birdge using Half-PC slab for slab bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20150804 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20170106 Year of fee payment: 5 |
|
FPAY | Annual fee payment |
Payment date: 20170821 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20180821 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20190923 Year of fee payment: 8 |