JP7409952B2 - Viaduct construction method and viaduct construction equipment - Google Patents

Viaduct construction method and viaduct construction equipment Download PDF

Info

Publication number
JP7409952B2
JP7409952B2 JP2020077563A JP2020077563A JP7409952B2 JP 7409952 B2 JP7409952 B2 JP 7409952B2 JP 2020077563 A JP2020077563 A JP 2020077563A JP 2020077563 A JP2020077563 A JP 2020077563A JP 7409952 B2 JP7409952 B2 JP 7409952B2
Authority
JP
Japan
Prior art keywords
pair
viaduct
bridge
rail
precast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020077563A
Other languages
Japanese (ja)
Other versions
JP2021173051A (en
Inventor
謙二 吉武
基 船岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP2020077563A priority Critical patent/JP7409952B2/en
Publication of JP2021173051A publication Critical patent/JP2021173051A/en
Application granted granted Critical
Publication of JP7409952B2 publication Critical patent/JP7409952B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

本発明は、高架橋の構築に適用される高架橋構築工法及び高架橋構築装置に関する。 The present invention relates to a viaduct construction method and viaduct construction apparatus applied to the construction of viaducts.

高架橋を構築する場合、建設用地に隣接する場所からクレーンにより資機材を搬入する。しかしながら建設用地の隣接地が狭隘でありクレーン用地の確保が困難である場合や、上部に高圧電線等が配置されて隣接地からクレーンを用いて資機材の搬入が困難である場合は、高架橋の橋脚を構築後、橋桁やスラブを構築するために、高架橋下部の敷地全面に足場を設置する必要があった。特許文献1には、建設用地の隣接地が狭隘な場合に高架橋を構築する方法が記載されている。 When constructing a viaduct, materials and equipment are brought in using a crane from a location adjacent to the construction site. However, if the land adjacent to the construction site is narrow and it is difficult to secure land for a crane, or if there are high-voltage power lines placed above the site and it is difficult to transport materials and equipment from the adjacent land using a crane, it is necessary to After constructing the piers, it was necessary to install scaffolding across the entire site below the viaduct in order to construct the bridge girders and slabs. Patent Document 1 describes a method for constructing a viaduct when the land adjacent to the construction site is narrow.

特許文献1に記載された技術によれば、高架橋の複数の橋脚と一対の橋桁とを構築後、一対の橋桁の上面に一対のレールを敷設し、一対のレール上に移動自在なクレーン装置を載置している。その後、クレーン装置を用いて一対の橋桁上にプレキャスト床版を載置し、プレキャスト床版の上面にコンクリートを打設して床面を形成し、高架橋を構築している。 According to the technology described in Patent Document 1, after constructing a plurality of piers and a pair of bridge girders of a viaduct, a pair of rails is laid on the top surface of the pair of bridge girders, and a movable crane device is installed on the pair of rails. It is installed. Thereafter, a crane device is used to place the precast deck slabs on a pair of bridge girders, and concrete is poured on top of the precast deck slabs to form a floor surface, thereby constructing a viaduct.

特開2009-191458号公報Japanese Patent Application Publication No. 2009-191458

特許文献1に記載された技術によれば、橋桁上に設置されたレール上にクレーン装置を設置し建設用地を縮小している。しかしながら、橋桁上にはプレキャスト床版との接合のための継手となる多数の鉄筋が露出し、橋桁上に直接レールを設置できない場合がある。 According to the technology described in Patent Document 1, a crane device is installed on a rail installed on a bridge girder, thereby reducing the construction site. However, a large number of reinforcing bars that serve as joints for joining with the precast deck slab are exposed on the bridge girder, and rails may not be installed directly on the bridge girder.

本発明は、設置対象に制約がある場合でも工期を短縮すると共に、建設用地を縮小できる高架橋構築工法を提供することを目的とする。 An object of the present invention is to provide a viaduct construction method that can shorten the construction period and reduce the amount of construction land even when there are restrictions on the installation target.

上記の目的を達するために、本発明は、高架橋の構築に適用される高架橋構築工法であって、複数の橋脚に支持されると共に、前記高架橋の橋軸方向に沿って対向する一対の橋桁上に複数の架台を設置する工程と、前記一対の橋桁を架橋するように前記複数の架台の上部に複数の横断梁を設置する工程と、前記複数の横断梁上に前記高架橋の橋軸方向に沿って対向した一対のレール梁を設置する工程と、前記一対のレール梁上に一対のレールを設ける工程と、前記一対のレールに移動自在なクレーン装置を載置する工程と、を備え、前記架台は、平面視してH断面に形成された本体部と、前記本体部の上端に設けられた上板と、前記本体部の下端に設けられた下板と、前記本体部に設けられた補強板と、を備えていることを特徴とする、高架橋構築工法である。 In order to achieve the above object, the present invention is a viaduct construction method applied to the construction of a viaduct, which is supported by a plurality of piers and is mounted on a pair of bridge girders facing each other along the axial direction of the viaduct. a step of installing a plurality of cross beams on top of the plurality of cross beams so as to bridge the pair of bridge girders, and a step of installing a plurality of cross beams on the plurality of cross beams in the bridge axis direction of the viaduct. the step of installing a pair of rail beams facing each other along the rail beam, the step of providing a pair of rails on the pair of rail beams, and the step of mounting a movable crane device on the pair of rails , The frame includes a main body formed in an H cross section when viewed from above, an upper plate provided at the upper end of the main body, a lower plate provided at the lower end of the main body, and a lower plate provided at the lower end of the main body. This is a viaduct construction method that is characterized by the addition of reinforcing plates .

本発明によれば、既設の一対の橋桁上に複数の架台、複数の横断梁、一対のレール梁、一対のレールを介してクレーン装置を設置するため、足場を組む必要が無く、建設用地を大幅に縮小することができる。また、橋桁上に多数の鉄筋が露出していても架台と横断梁を介してレール梁及びレールを載置し、クレーン装置を載置できる。 According to the present invention, since the crane device is installed on a pair of existing bridge girders via a plurality of frames, a plurality of cross beams, a pair of rail beams, and a pair of rails, there is no need to set up scaffolding, and the construction site is saved. It can be significantly reduced. Further, even if a large number of reinforcing bars are exposed on the bridge girder, the rail beam and rail can be mounted via the frame and the cross beam, and the crane device can be mounted.

また、本発明は、前記クレーン装置により前記架台、前記横断梁、前記レール梁、及び前記レールが設置されていない前記一対の橋桁上の領域に床面を形成するための複数の所定数のプレキャスト床版を載置する工程を備えるように構成されていてもよい。 Further, the present invention provides a method for forming a predetermined number of precasts for forming a floor surface in an area on the pair of bridge girders where the trestle, the cross beam, the rail beam, and the rail are not installed by the crane device. It may be configured to include a step of placing a floor slab.

本発明によれば、既設の橋桁上に載置されたクレーン装置によりプレキャスト床版を橋桁上に載置できるため、建設用地を縮小すると共に、工期を大幅に低減できる。 According to the present invention, since the precast deck slab can be placed on the bridge girder using a crane device placed on the existing bridge girder, the construction site can be reduced and the construction period can be significantly reduced.

また、本発明は、前記レール上において前記クレーン装置を前記プレキャスト床版が載置された領域と反対方向に移動させる工程と、前記プレキャスト床版を載置した領域に隣接する領域から前記レール、前記レール梁、前記横断梁、及び前記架台を撤去して所定数の他の前記プレキャスト床版を設置する設置領域を形成する工程と、前記設置領域に複数の所定数の前記プレキャスト床版を載置する工程を備えるように構成されていてもよい。 The present invention also provides a step of moving the crane device on the rail in a direction opposite to the area where the precast deck is placed, and moving the rail from an area adjacent to the area where the precast deck is placed. forming an installation area in which a predetermined number of other precast floor slabs are installed by removing the rail beam, the cross beam, and the pedestal; and placing a plurality of precast floor slabs in the installation area. It may be configured to include a step of placing.

本発明によれば、橋桁上からレール、レール梁、横断梁、及び架台を撤去して形成された設置領域に所定数のプレキャスト床版を設置することで、複数のプレキャスト床版が設置完了する頃にはクレーン装置の構成が略撤収されており、工期を大幅に短縮できる。 According to the present invention, the installation of a plurality of precast deck slabs is completed by installing a predetermined number of precast deck slabs in the installation area formed by removing the rails, rail beams, cross beams, and frames from the bridge girder. By this time, most of the crane equipment had been removed, making it possible to significantly shorten the construction period.

また、本発明は、前記一対の橋桁上に載置された複数の前記プレキャスト床版同士と前記一対の橋桁とをコンクリートにより一体化すると共に、前記プレキャスト床版上にコンクリートを打設して床面を形成する工程を備えるように構成されていてもよい。 Moreover, the present invention integrates the plurality of precast deck slabs placed on the pair of bridge girders and the pair of bridge girders with concrete, and also provides a floor by pouring concrete onto the precast deck slab. The method may be configured to include a step of forming a surface.

本発明によれば、床面の形成とプレキャスト床版、橋脚、及び橋桁の一体化を同時に行い、工期を大幅に短縮できる。 According to the present invention, the formation of the floor surface and the integration of the precast deck slab, piers, and bridge girders can be performed simultaneously, and the construction period can be significantly shortened.

また、本発明は、前記一対のレール上を走行する運搬用台車を備え、前記運搬台車は、前記プレキャスト床版の一時保管場所と前記クレーン装置の近傍までの間を往復走行して前記プレキャスト床版を運搬する工程を備えるように構成されていてもよい。 Further, the present invention includes a transport trolley that runs on the pair of rails, and the transport trolley reciprocates between a temporary storage location for the precast floor slab and a vicinity of the crane device to move the precast floor slab. The method may be configured to include a step of transporting the plate.

本発明によれば、クレーン装置が一時保管場所まで移動する必要が無くなり、クレーン装置が稼働中に運搬用台車によりプレキャスト床版の運搬作業を行うことができ、工期が短縮される。 According to the present invention, there is no need for the crane device to be moved to a temporary storage location, and the precast deck can be transported using a transportation trolley while the crane device is in operation, thereby shortening the construction period.

上記の目的を達するために、本発明は、高架橋の構築に適用される高架橋構築装置であって、複数の橋脚に支持されると共に、前記高架橋の橋軸方向に沿って対向する一対の橋桁上に設置された複数の架台と、前記一対の橋桁を架橋するように前記複数の架台の上部に設置された複数の横断梁と、前記複数の横断梁上に前記高架橋の橋軸方向に沿って対向して設置された一対のレール梁と、前記一対のレール梁上に設置された一対のレールと、前記一対のレールに移動自在に載置されたクレーン装置と、を備え、前記架台は、平面視してH断面に形成された本体部と、前記本体部の上端に設けられた上板と、前記本体部の下端に設けられた下板と、前記本体部に設けられた補強板と、を備えていることを特徴とする、高架橋構築装置である。
In order to achieve the above object, the present invention is a viaduct construction device applied to the construction of a viaduct, which is supported by a plurality of piers and is mounted on a pair of bridge girders facing each other along the axial direction of the viaduct. a plurality of trestles installed at the top of the trestles, a plurality of cross beams installed at the top of the plurality of trestles so as to bridge the pair of bridge girders, and a plurality of cross beams installed along the bridge axis direction of the viaduct on the plurality of cross beams. The mount includes a pair of rail beams installed opposite to each other, a pair of rails installed on the pair of rail beams, and a crane device movably mounted on the pair of rails, A main body formed in an H cross section when viewed from above, an upper plate provided at the upper end of the main body, a lower plate provided at the lower end of the main body, and a reinforcing plate provided at the main body. This is a viaduct construction device characterized by comprising :

本発明によれば、既設の一対の橋桁上に複数の架台、複数の横断梁、一対のレール梁、一対のレールを介してクレーン装置を載置するため、足場を組む必要が無く、建設用地を大幅に縮小することができる。また、橋桁上に多数の鉄筋が露出していても架台と横断梁を介してレール梁及びレールを載置し、クレーン装置を載置できる。 According to the present invention, since the crane device is mounted on a pair of existing bridge girders via a plurality of frames, a plurality of cross beams, a pair of rail beams, and a pair of rails, there is no need to set up scaffolding, and the construction site is can be significantly reduced. Further, even if a large number of reinforcing bars are exposed on the bridge girder, the rail beam and rail can be mounted via the frame and the cross beam, and the crane device can be mounted.

本発明によれば、設置対象に制約がある場合でも工期を短縮すると共に、建設用地を縮小できることができる。 According to the present invention, even when there are restrictions on the installation target, the construction period can be shortened and the construction site can be reduced.

本発明の実施形態に係る施工対象である高架橋の構成を示す図である。BRIEF DESCRIPTION OF THE DRAWINGS It is a figure which shows the structure of the viaduct which is a construction target based on embodiment of this invention. 高架橋の橋脚と橋桁との構成を示す図である。It is a figure showing the composition of the bridge pier and the bridge girder of a viaduct. 高架橋構築装置の構成を示す正面図である。It is a front view showing the composition of a viaduct construction device. 高架橋構築装置の構成を示す側面図である。It is a side view showing the composition of a viaduct construction device. 架台の構成を示す分解斜視図である。FIG. 3 is an exploded perspective view showing the configuration of the pedestal. プレキャスト床版の構成を示す図である。It is a figure showing the composition of a precast floor slab. 高架橋構築工法の工程を示す図である。It is a figure showing the process of a viaduct construction method. 高架橋構築工法の工程を示す図である。It is a figure showing the process of a viaduct construction method. 高架橋構築工法の工程を示す図である。It is a figure showing the process of a viaduct construction method. 高架橋構築工法の工程を示す図である。It is a figure showing the process of a viaduct construction method. 高架橋構築工法の工程を示す図である。It is a figure showing the process of a viaduct construction method. 高架橋構築工法の工程を示す図である。It is a figure showing the process of a viaduct construction method. 高架橋構築工法の工程を示す図である。It is a figure showing the process of a viaduct construction method. 高架橋構築工法の工程を示す図である。It is a figure showing the process of a viaduct construction method.

以下、図面を参照しつつ、本発明に係る高架橋構築工法の実施形態について説明する。 Hereinafter, embodiments of the viaduct construction method according to the present invention will be described with reference to the drawings.

高架橋構築工法は、構築された複数の橋脚及び橋桁を利用してプレキャスト床版を設置して建設用地を縮小すると共に、工期を低減するものである。高架橋は、鉄道や道路の建設において構築される高架方式の構造物である。 The viaduct construction method uses a plurality of constructed piers and bridge girders to install precast deck slabs, thereby reducing the construction site and construction period. A viaduct is an elevated structure constructed in the construction of railways and roads.

図1に示されるように、高架橋構築工法が適用されて構築される高架橋1は、門型のラーメン構造を備える。高架橋1は、複数の橋脚10と、複数の橋脚10に支持された一対の橋桁20と、一対の橋桁20上に形成された床面30(スラブ)とを備える。橋脚10、橋桁20、床面30は、プレキャストにより形成された後述のプレキャスト床版を組み合わせて構築される。 As shown in FIG. 1, a viaduct 1 constructed by applying the viaduct construction method has a gate-shaped rigid frame structure. The viaduct 1 includes a plurality of piers 10, a pair of bridge girders 20 supported by the plurality of piers 10, and a floor surface 30 (slab) formed on the pair of bridge girders 20. The piers 10, the bridge girders 20, and the floor surface 30 are constructed by combining precast slabs, which will be described later, formed by precasting.

高架橋1の橋脚10は、矩形断面の鉄筋コンクリートの柱状体に形成されている。橋脚10は、コンクリートが打設されて構築される。橋脚10は、プレキャストにより予め形成された部材を組み合わせて構築されてもよい。橋脚10は、上部及び下部において接合部分に鉄筋(不図示)が露出している。橋脚10は、鉄筋が挿入される穴(不図示)が形成されていてもよい。鉄筋又は孔のいずれかが形成されることは設計により決定される。橋脚10の接合部分は、スラブコンクリートが打設された際に他の部材や固定対象に固定される。 The piers 10 of the viaduct 1 are formed into reinforced concrete columns with a rectangular cross section. The pier 10 is constructed by pouring concrete. The pier 10 may be constructed by combining precast members. In the bridge pier 10, reinforcing bars (not shown) are exposed at the joint portions at the upper and lower parts. The pier 10 may be formed with holes (not shown) into which reinforcing bars are inserted. Whether either reinforcing bars or holes are formed is determined by design. The joint portion of the pier 10 is fixed to other members or objects to be fixed when slab concrete is placed.

橋脚10は、所定の施工位置に固定される。複数の橋脚10は、高架橋1の長手方向の橋軸方向(図のy軸方向)に並置される。高架橋1の幅方向(図のx軸方向)には、一対の橋脚10が対向して配置されている。高架橋1の幅は、目的とする線路数、車線等に応じて設定されている。従って、高架橋1の幅方向には、幅に応じて2本以上の橋脚10が並べられていてもよい。橋脚10の上部には、橋桁20が現場打ちコンクリートにより構築される。橋桁20は、プレキャストにより予め形成された部材を組み合わせて構築されてもよい。橋桁20は、橋軸方向に複数の橋脚10の上部を架橋するように構築される。一対の橋桁20は、高架橋1の幅方向に対向して配置される。 The pier 10 is fixed at a predetermined construction position. The plurality of piers 10 are arranged in parallel in the longitudinal bridge axis direction of the viaduct 1 (the y-axis direction in the figure). A pair of piers 10 are arranged facing each other in the width direction of the viaduct 1 (the x-axis direction in the figure). The width of the viaduct 1 is set according to the intended number of tracks, lanes, etc. Therefore, two or more piers 10 may be arranged in the width direction of the viaduct 1 depending on the width. A bridge girder 20 is constructed from cast-in-place concrete on the top of the bridge pier 10. The bridge girder 20 may be constructed by combining precast members. The bridge girder 20 is constructed to bridge the upper parts of the plurality of bridge piers 10 in the bridge axis direction. The pair of bridge girders 20 are arranged to face each other in the width direction of the viaduct 1.

一対の橋桁20の上部には、床面30が形成されている。床面30は、平板状の板状体に形成されている。床面30は、後述のようにプレキャストにより予め形成された複数のプレキャスト床版を組み合わせて形成されている。 A floor surface 30 is formed on the upper part of the pair of bridge girders 20. The floor surface 30 is formed into a flat plate-like body. The floor surface 30 is formed by combining a plurality of precast floor slabs formed in advance by precasting as described below.

次に、高架橋1の構築方法について説明する。 Next, a method for constructing the viaduct 1 will be explained.

図2に示されるように、高架橋構築工法は、複数の橋脚10及び橋桁20が構築された状態から床面30を形成する工程に適用される。橋桁20の上面には、継手となる多数の鉄筋21が露出している。この鉄筋21の存在により、橋桁20の上面にクレーン装置を載置するためのレールを設置できない。そこで、高架橋構築工法は、橋桁20の上面に間接的にクレーン装置を載置する。 As shown in FIG. 2, the viaduct construction method is applied to a process of forming a floor surface 30 from a state in which a plurality of piers 10 and bridge girders 20 are constructed. A large number of reinforcing bars 21 serving as joints are exposed on the upper surface of the bridge girder 20. Due to the presence of the reinforcing bars 21, a rail for mounting a crane device cannot be installed on the upper surface of the bridge girder 20. Therefore, in the viaduct construction method, a crane device is indirectly placed on the upper surface of the bridge girder 20.

図3から図5に示されるように、高架橋構築工法に適用される高架橋構築装置100は、橋桁20の上面に設置される複数の架台22と、複数の架台22上に設置される複数の横断梁40と、複数の横断梁40上に設置される一対のレール梁50と、一対のレール梁50上に設置される一対のレールRと、一対のレールR上に載置されるクレーン装置60と、を備える。 As shown in FIGS. 3 to 5, the viaduct construction apparatus 100 applied to the viaduct construction method includes a plurality of trestles 22 installed on the upper surface of the bridge girder 20, and a plurality of cross sections installed on the plurality of trestles 22. A beam 40, a pair of rail beams 50 installed on the plurality of cross beams 40, a pair of rails R installed on the pair of rail beams 50, and a crane device 60 placed on the pair of rails R. and.

複数の架台22は、橋桁20の上面に橋桁20の長手方向(y軸方向)に沿って固定される。架台22は、橋桁20の上面に設けられた継手用の多数の鉄筋21の間に固定される。一対の架台22は、高架橋1の幅方向において橋桁20の上面に対向して配置される。一対の架台22が橋桁20の上面において橋軸方向(y軸方向)に沿って複数個配置される。架台22は、例えば、H鋼を加工して形成されている。 The plurality of frames 22 are fixed to the upper surface of the bridge girder 20 along the longitudinal direction (y-axis direction) of the bridge girder 20. The frame 22 is fixed between a large number of reinforcing bars 21 for joints provided on the upper surface of the bridge girder 20. The pair of pedestals 22 are arranged to face the upper surface of the bridge girder 20 in the width direction of the viaduct 1. A plurality of pairs of frames 22 are arranged on the upper surface of the bridge girder 20 along the bridge axis direction (y-axis direction). The frame 22 is formed by processing H steel, for example.

架台22は、平面視してH断面に形成された本体部23と、本体部23の上端に設けられた上板24と、本体部23の下端に設けられた下板25と、本体部23に設けられた補強板26,27とを備える。本体部23は、矩形の板状体に形成された梁部23Aを備える。梁部23Aの両端には、一対のフランジ部23B,23Cが設けられている。一対のフランジ部23B,23Cは、平面視して梁部23Aに直交して配置されている。一対のフランジ部23B,23Cは、矩形の板状体に形成されている。 The frame 22 includes a main body 23 formed in an H cross section when viewed from above, an upper plate 24 provided at the upper end of the main body 23 , a lower plate 25 provided at the lower end of the main body 23 , and the main body 23 The reinforcing plates 26 and 27 are provided. The main body portion 23 includes a beam portion 23A formed in a rectangular plate shape. A pair of flange parts 23B and 23C are provided at both ends of the beam part 23A. The pair of flange portions 23B and 23C are arranged perpendicularly to the beam portion 23A in plan view. The pair of flange portions 23B and 23C are formed into rectangular plate-like bodies.

上板24、下板25は、矩形の板状体に形成されている。上板24には、ボルトにより横断梁40に固定するための複数(例えば、4個)の貫通孔24Hが形成されている。下板25には、アンカーボルト用の複数(例えば、4個)の貫通孔25Hが形成されている。架台22は、橋桁20の上面に複数のアンカーボルトにより固定される。 The upper plate 24 and the lower plate 25 are formed into rectangular plate-like bodies. A plurality of (for example, four) through holes 24H are formed in the upper plate 24 for fixing to the cross beam 40 with bolts. A plurality of (for example, four) through holes 25H for anchor bolts are formed in the lower plate 25. The pedestal 22 is fixed to the upper surface of the bridge girder 20 with a plurality of anchor bolts.

高架橋1の幅方向に対向する一対の架台22の上部には、横断梁40が固定される。横断梁40と架台22とはボルト及びナットにより固定される。横断梁40は、例えば、1本のH鋼により形成されている。横断梁40は、複数の部材41が連結されることにより構成されていてもよい。部材41同士は、例えば、端部が継手プレート(不図示)等を介してボルト及びナットを用いて連結されていてもよい。 A cross beam 40 is fixed to the upper part of a pair of frames 22 that face each other in the width direction of the viaduct 1 . The transverse beam 40 and the frame 22 are fixed with bolts and nuts. The transverse beam 40 is formed of, for example, one H steel. The cross beam 40 may be configured by connecting a plurality of members 41. For example, the ends of the members 41 may be connected to each other using bolts and nuts via a joint plate (not shown) or the like.

複数の横断梁40は、長手方向が橋桁20に対して略直交方向に配置される。複数の横断梁40の上部には、一対のレール梁50が対向して固定されている。レール梁50は、横断梁40の上面において高架橋1の橋軸方向に沿って配置される。即ちレール梁50は、横断梁40に対して略直交方向に配置される。 The plurality of cross beams 40 are arranged with their longitudinal directions substantially orthogonal to the bridge girder 20. A pair of rail beams 50 are fixed to the upper portions of the plurality of cross beams 40 so as to face each other. The rail beam 50 is arranged along the bridge axis direction of the viaduct 1 on the upper surface of the cross beam 40. That is, the rail beam 50 is arranged substantially perpendicular to the cross beam 40.

レール梁50は、例えば、H鋼により形成された複数の部材51が連結されることにより構成されている。部材51同士は、例えば、端部が継手プレート53等を介してボルト及びナットを用いて連結されている。レール梁50の連結位置は、横断梁40の直上である。x軸方向において、一対のレール梁50の間の中心位置は、クレーン装置60の稼働中の重心とバランスが取れるのであれば必ずしも一対の橋脚10の間の中心位置と一致していなくてもよい。 The rail beam 50 is configured by connecting a plurality of members 51 made of, for example, H steel. For example, the ends of the members 51 are connected to each other using bolts and nuts via a joint plate 53 or the like. The connecting position of the rail beam 50 is directly above the cross beam 40. In the x-axis direction, the center position between the pair of rail beams 50 does not necessarily have to coincide with the center position between the pair of piers 10 as long as it can be balanced with the center of gravity of the crane device 60 during operation. .

レール梁50の上面には、レール梁50の長手方向に沿ってレールRが固定される。レールRは、鋼製の棒状体に形成されている。レールRは、ボルト、ナット等を用いてレール梁50に固定される。レールRは、例えば、部材51の長手方向の長さに合わせて分割されている。一対のレールRが一対のレール梁50にそれぞれ固定される。一対のレールR上には、クレーン装置60が複数の車輪62を介して載置される。 A rail R is fixed to the upper surface of the rail beam 50 along the longitudinal direction of the rail beam 50. The rail R is formed into a rod-shaped body made of steel. The rail R is fixed to the rail beam 50 using bolts, nuts, etc. The rail R is divided, for example, according to the length of the member 51 in the longitudinal direction. A pair of rails R are each fixed to a pair of rail beams 50. A crane device 60 is mounted on the pair of rails R via a plurality of wheels 62.

クレーン装置60は、走行体であるクレーン台座61を備える。クレーン台座61は、格子状に組まれた鉄骨や鉄板等の部材を用いて盤状に形成されている。クレーン台座61は複数の車輪62によりレールRに移動自在に支持されている。複数の車輪62の内の一部には、車輪62を駆動する駆動装置63が設けられている。駆動装置63により、クレーン台座61は、レールRに沿って加減速、前後退するように走行できる。クレーン台座61上には、移動対象を吊り上げるためのクレーン65が設けられている。 The crane device 60 includes a crane pedestal 61 that is a traveling body. The crane pedestal 61 is formed into a board shape using members such as a steel frame and iron plates arranged in a lattice shape. The crane pedestal 61 is movably supported by a plurality of wheels 62 on the rail R. A drive device 63 for driving the wheels 62 is provided in some of the plurality of wheels 62 . The drive device 63 allows the crane pedestal 61 to accelerate and decelerate and move forward and backward along the rail R. A crane 65 is provided on the crane pedestal 61 for lifting a moving object.

クレーン65は、クレーン台座61に対して旋回自在に設けられている。クレーン65は、アーム66と、アーム66の先端から吊り上げられたフック67とを備える。クレーン65は、クレーン台座61の位置、旋回、アーム66の傾斜角、フック67の揚程を調整し、プレキャスト床版を吊り上げ、設置位置まで運搬する。 The crane 65 is rotatably provided on the crane pedestal 61. The crane 65 includes an arm 66 and a hook 67 suspended from the tip of the arm 66. The crane 65 adjusts the position and rotation of the crane pedestal 61, the inclination angle of the arm 66, and the lifting height of the hook 67, lifts the precast floor slab, and transports it to the installation position.

図6に示されるように、プレキャスト床版31は、高架橋1の床面30を構築するための鉄筋コンクリート製の部材である。プレキャスト床版31は、床面を形成するための床版部32と、柵を形成するための壁高欄部33とを備える。床版部32は、水平方向の平板状に形成されている。壁高欄部33は、床版部32の両端から上方に起立した板状に形成されている。 As shown in FIG. 6, the precast deck slab 31 is a member made of reinforced concrete for constructing the floor surface 30 of the viaduct 1. The precast floor slab 31 includes a floor slab section 32 for forming a floor surface, and a wall balustrade section 33 for forming a fence. The floor slab portion 32 is formed into a horizontal flat plate shape. The wall railing section 33 is formed in a plate shape that stands upward from both ends of the floor slab section 32.

床版部32には、橋桁20と接合される継手部32Aが形成されている。継手部32Aには、y軸方向に並置された複数の鉄筋32Bが露出するように形成されている。プレキャスト床版31が橋桁20に載置される際、複数の鉄筋32Bは、橋桁20の多数の鉄筋21とそれぞれ互い違いになるように配置されている。プレキャスト床版31が橋桁20に載置された後、継手部32AにコンクリートCが充填される。コンクリートCが硬化するとコンクリートと複数の鉄筋32Bと橋桁20の多数の鉄筋21とが固着してプレキャスト床版31と橋桁20とが一体化する。 A joint portion 32A that is joined to the bridge girder 20 is formed in the floor slab portion 32. A plurality of reinforcing bars 32B arranged in parallel in the y-axis direction are exposed in the joint portion 32A. When the precast deck slab 31 is placed on the bridge girder 20, the plurality of reinforcing bars 32B are arranged alternately with the many reinforcing bars 21 of the bridge girder 20. After the precast deck slab 31 is placed on the bridge girder 20, the joint portion 32A is filled with concrete C. When the concrete C hardens, the concrete, the plurality of reinforcing bars 32B, and the many reinforcing bars 21 of the bridge girder 20 are fixed, and the precast deck slab 31 and the bridge girder 20 are integrated.

床版部32の一端面32Cには、ループ状に形成された継手用の多数の鉄筋Zが突出して設けられている。一端面32Cの反対側の他端面にも同様に多数の鉄筋Zが突出して設けられている。複数のプレキャスト床版31が隣接して橋桁20上に載置された際、一端面32Cの多数の鉄筋Zと他端面の多数の鉄筋とはそれぞれ互い違いになるように配置されている。 A large number of loop-shaped reinforcing bars Z for joints are provided protruding from one end surface 32C of the floor slab portion 32. A large number of reinforcing bars Z are similarly provided protruding from the other end surface opposite to the one end surface 32C. When a plurality of precast deck slabs 31 are placed adjacent to each other on the bridge girder 20, the many reinforcing bars Z on one end surface 32C and the many reinforcing bars on the other end surface are arranged alternately.

プレキャスト床版31が橋桁20に載置された後、一端面32Cの反対側の他端面との間にコンクリートが充填される。モルタルが硬化するとコンクリートと多数の鉄筋Zが固着して複数のプレキャスト床版31が一体化する。 After the precast deck slab 31 is placed on the bridge girder 20, concrete is filled between the one end surface 32C and the other end surface on the opposite side. When the mortar hardens, the concrete and a large number of reinforcing bars Z adhere to each other, and the plurality of precast floor slabs 31 are integrated.

床版部32の上面32Eには、山形状に形成された継手用の多数の鉄筋32Fがコンクリートと一体化され、複数のループが突出している。複数のプレキャスト床版31が橋桁20に載置され、床版部32の上面32EにコンクリートCが充填されると、床面30が形成される。 On the upper surface 32E of the floor slab portion 32, a large number of reinforcing bars 32F for joints formed in a mountain shape are integrated with concrete, and a plurality of loops protrude. When a plurality of precast deck slabs 31 are placed on the bridge girder 20 and the upper surface 32E of the deck section 32 is filled with concrete C, the floor surface 30 is formed.

コンクリートCは、複数のプレキャスト床版31が橋桁20上に載置された後に打設され、コンクリートCが硬化後、複数のプレキャスト床版31同士と、複数のプレキャスト床版31と橋桁20とが同時に一体化されると共に、床面30が形成される。 Concrete C is cast after the plurality of precast deck slabs 31 are placed on the bridge girder 20, and after the concrete C hardens, the plurality of precast deck slabs 31 and the plurality of precast deck slabs 31 and the bridge girder 20 are placed. At the same time, the floor surface 30 is formed.

次に、高架橋構築工法の各工程について説明する。 Next, each step of the viaduct construction method will be explained.

図7に示されるように、高架橋1の施工位置に複数の橋脚10が現場打ちコンクリートにより構築される。その後、複数の橋脚10の上部に一対の橋桁20が対向して現場打ちコンクリートにより構築される。図において簡略化のため橋桁20上の鉄筋21は省略して記載されている。 As shown in FIG. 7, a plurality of piers 10 are constructed using cast-in-place concrete at the construction location of the viaduct 1. Thereafter, a pair of bridge girders 20 are constructed with cast-in-place concrete on top of the plurality of bridge piers 10, facing each other. In the figure, reinforcing bars 21 on the bridge girder 20 are omitted for simplicity.

図8に示されるように、一対の橋桁20の上部に複数の架台22が橋桁20の長手方向に沿って設置される。この時、高架橋1の幅方向(x軸方向)において一対の架台22が対向するように設置される。この時、プレキャスト床版31が設置される設置領域Qが残されて複数の架台22が設置される。次に、上記一対の架台22を架橋するように複数の横断梁40が設置される。その後、複数の横断梁40の上部に一対のレール梁50が橋軸方向(y軸方向)に沿って対向して設置される。その後、一対のレール梁50の上部に一対のレールRが設置される。その後、一対のレールRの上部にクレーン装置60と運搬用台車70が載置される。クレーン装置60と運搬用台車70は、例えば、地表面Eからラフタークレーン(不図示)等により載置される。 As shown in FIG. 8, a plurality of frames 22 are installed above the pair of bridge girders 20 along the longitudinal direction of the bridge girders 20. At this time, the pair of frames 22 are installed to face each other in the width direction (x-axis direction) of the viaduct 1. At this time, an installation area Q is left where the precast floor slab 31 is installed, and a plurality of frames 22 are installed. Next, a plurality of cross beams 40 are installed to bridge the pair of frames 22. Thereafter, a pair of rail beams 50 are installed on top of the plurality of cross beams 40 to face each other along the bridge axis direction (y-axis direction). Thereafter, a pair of rails R are installed above the pair of rail beams 50. Thereafter, the crane device 60 and the transportation trolley 70 are placed on top of the pair of rails R. The crane device 60 and the transportation trolley 70 are mounted, for example, from the ground surface E by a rough terrain crane (not shown) or the like.

図9に示されるように、クレーン装置60を用いて設置領域Qに所定数のプレキャスト床版31が隣接して載置される。この時、隣接するプレキャスト床版31は、一端面32Cの多数のループ状の鉄筋Z(図6参照)と他端面の多数のループ状の鉄筋Zとが橋軸方向に重なる位置となるように載置される。プレキャスト床版31は、例えば、一か所に集積された一時保管場所(不図示)からラフタークレーン等により運搬用台車70に載置される。 As shown in FIG. 9, a predetermined number of precast floor slabs 31 are placed adjacent to each other in the installation area Q using a crane device 60. At this time, the adjacent precast deck slabs 31 are positioned so that the numerous loop-shaped reinforcing bars Z on one end surface 32C (see FIG. 6) and the numerous loop-shaped reinforcing bars Z on the other end surface overlap in the bridge axis direction. It will be placed. The precast floor slab 31 is placed on the transportation trolley 70 by, for example, a rough terrain crane or the like from a temporary storage area (not shown) that is accumulated in one place.

運搬用台車70は、レールR上を走行し、クレーン装置60の近傍までプレキャスト床版31を運搬する。プレキャスト床版31は、運搬用台車70からクレーン装置60により吊り上げられて設置領域Qまで運搬される。運搬用台車70は、一時保管場所とクレーン装置60の近傍までの間を往復走行してプレキャスト床版31を運搬する。これにより、クレーン装置60が一時保管場所の近傍まで移動しなくてもよく、クレーン装置60が稼働中に運搬用台車70によりプレキャスト床版31の運搬作業を行うことができ、工期が短縮される。 The transportation trolley 70 travels on the rail R and transports the precast floor slab 31 to the vicinity of the crane device 60. The precast floor slab 31 is lifted from the transportation trolley 70 by the crane device 60 and transported to the installation area Q. The transportation trolley 70 transports the precast floor slab 31 by traveling back and forth between the temporary storage location and the vicinity of the crane device 60. As a result, the crane device 60 does not need to be moved to the vicinity of the temporary storage location, and the precast floor slab 31 can be transported by the transportation trolley 70 while the crane device 60 is in operation, reducing the construction period. .

図10に示されるように、設置領域Qに所定数のプレキャスト床版31が設置された後、クレーン装置60をプレキャスト床版31が設置された位置と反対方向に移動させる。 As shown in FIG. 10, after a predetermined number of precast floor slabs 31 are installed in the installation area Q, the crane device 60 is moved in the opposite direction to the position where the precast floor slabs 31 are installed.

図11に示されるように、クレーン装置60を移動後、プレキャスト床版31が設置された位置に隣接した領域から所定数の架台22、所定数の横断梁40、所定数のレール梁50の部材51、及び所定数のレールRが撤去される。これにより、一対の橋桁20上に新たな設置領域Qが形成される。 As shown in FIG. 11, after moving the crane device 60, a predetermined number of frames 22, a predetermined number of cross beams 40, and a predetermined number of rail beams 50 are moved from the area adjacent to the position where the precast floor slab 31 is installed. 51 and a predetermined number of rails R are removed. As a result, a new installation area Q is formed on the pair of bridge girders 20.

図12に示されるように、新たな設置領域Qに所定数のプレキャスト床版31が隣接して載置される。新たな設置領域Qに所定数のプレキャスト床版31が載置された後、上記工程を繰り返す。最後に高架橋構築装置100が撤去された後、その領域にラフタークレーン(不図示)等を用いて所定数のプレキャスト床版31が隣接して載置される。 As shown in FIG. 12, a predetermined number of precast floor slabs 31 are placed adjacent to each other in the new installation area Q. After a predetermined number of precast floor slabs 31 are placed in the new installation area Q, the above steps are repeated. Finally, after the viaduct construction device 100 is removed, a predetermined number of precast deck slabs 31 are placed adjacent to the area using a rough terrain crane (not shown) or the like.

図13に示されるように、一対の橋桁20上に複数のプレキャスト床版31が隣接して載置される。その後、複数のプレキャスト床版31にスラブ配筋(不図示)が配筋される。複数のプレキャスト床版31の外側(壁高欄部33の外側:図6参照)には、型枠が取り付けられる。 As shown in FIG. 13, a plurality of precast deck slabs 31 are placed adjacent to each other on a pair of bridge girders 20. After that, slab reinforcement (not shown) is arranged on the plurality of precast floor slabs 31. Formwork is attached to the outside of the plurality of precast floor slabs 31 (outside of the wall balustrade 33: see FIG. 6).

図14に示されるように、複数のプレキャスト床版31の間、継手部32A(図6参照)、床版部32の上面にコンクリートCが打設され、コンクリートCが硬化後、複数のプレキャスト床版31と一対の橋桁20とが一体となり、型枠が取り外されて高架橋1が構築される。プレキャスト床版31は、床面30までの部分をプレキャストで形成してもよく、継手部32Aにコンクリートを打設するようにしてもよい(図6参照)。 As shown in FIG. 14, concrete C is placed between the plurality of precast floor slabs 31, on the joint part 32A (see FIG. 6), and on the upper surface of the floor slab part 32, and after the concrete C hardens, the plurality of precast floor slabs The plate 31 and the pair of bridge girders 20 are integrated, the formwork is removed, and the viaduct 1 is constructed. The precast floor slab 31 may be formed by precasting the portion up to the floor surface 30, or may be formed by pouring concrete into the joint portion 32A (see FIG. 6).

上述したように高架橋構築工法によれば、予め構築した橋桁20上にクレーン装置60を載置し、クレーン装置60を用いてプレキャスト床版31を橋桁20上に設置できるため、高架橋1の工期を大幅に短縮できる。高架橋構築工法によれば、橋桁20上にクレーン装置60を載置して作業できるため、高架橋1の施工位置を覆う足場を不要とし、建設用地を大幅に削減できる。 As described above, according to the viaduct construction method, the crane device 60 is placed on the bridge girder 20 constructed in advance, and the precast deck slab 31 can be installed on the bridge girder 20 using the crane device 60, so the construction period for the viaduct 1 can be shortened. It can be significantly shortened. According to the viaduct construction method, since the crane device 60 can be placed on the bridge girder 20 for work, there is no need for scaffolding to cover the construction position of the viaduct 1, and the amount of construction land can be significantly reduced.

高架橋構築工法によれば、一対の橋桁20上に架橋された複数の横断梁40の下の空間において資材の運搬や作業ができるので、建設用地を大幅に削減できる。高架橋構築工法によれば、橋桁20上にプレキャスト床版31を固定するための多数の鉄筋21が露出していても、架台22、横断梁40、レール梁50及びレールRを介してクレーン装置60が設置できる。 According to the viaduct construction method, materials can be transported and worked in the space under the plurality of cross beams 40 bridged on a pair of bridge girders 20, so that construction land can be significantly reduced. According to the viaduct construction method, even if a large number of reinforcing bars 21 for fixing the precast deck slab 31 on the bridge girder 20 are exposed, the crane device 60 can be installed.

以上、本発明の一実施形態について説明したが、本発明は上記の一実施形態に限定されるものではなく、その趣旨を逸脱しない範囲で適宜変更可能である。例えば、高架橋構築工法は、一段の床面を形成に適用するだけでなく、二段以上の高架橋の構築に適用してもよい。 Although one embodiment of the present invention has been described above, the present invention is not limited to the above-described one embodiment, and can be modified as appropriate without departing from the spirit thereof. For example, the viaduct construction method is not only applicable to forming a single-level floor surface, but may also be applied to constructing a viaduct with two or more levels.

1 高架橋、10 橋脚、20 橋桁、21 鉄筋、22 架台、23 本体部、23A 梁部、23B フランジ部、23C フランジ部、24 上板、24H 貫通孔、25 下板、25H 貫通孔、26 補強板、27 補強板、30 床面、31 プレキャスト床版、32 床版部、32A 継手部、32B 鉄筋、32C 一端面、32E 上面、32F 鉄筋、33 壁高欄部、40 横断梁、41 部材、50 レール梁、51 部材、53 継手プレート、60 クレーン装置、61 クレーン台座、62 車輪、63 駆動装置、65 クレーン、66 アーム、67 フック、70 運搬用台車、100 高架橋構築装置、C コンクリート、E 地表面、Q 設置領域、R レール、Z 鉄筋 1 Viaduct, 10 Pier, 20 Bridge girder, 21 Rebar, 22 Frame, 23 Main body, 23A Beam, 23B Flange, 23C Flange, 24 Upper plate, 24H Through hole, 25 Lower plate, 25H Through hole, 26 Reinforcement plate , 27 reinforcing plate, 30 floor surface, 31 precast floor slab, 32 floor slab section, 32A joint section, 32B reinforcing bar, 32C one end surface, 32E top surface, 32F reinforcing bar, 33 wall parapet, 40 cross beam, 41 member, 50 rail Beam, 51 Member, 53 Joint plate, 60 Crane device, 61 Crane pedestal, 62 Wheel, 63 Drive device, 65 Crane, 66 Arm, 67 Hook, 70 Transport trolley, 100 Elevated bridge construction device, C Concrete, E Ground surface, Q installation area, R rail, Z reinforcing bar

Claims (6)

高架橋の構築に適用される高架橋構築工法であって、
複数の橋脚に支持されると共に、前記高架橋の橋軸方向に沿って対向する一対の橋桁上に複数の架台を設置する工程と、
前記一対の橋桁を架橋するように前記複数の架台の上部に複数の横断梁を設置する工程と、
前記複数の横断梁上に前記高架橋の橋軸方向に沿って対向した一対のレール梁を設置する工程と、
前記一対のレール梁上に一対のレールを設ける工程と、
前記一対のレールに移動自在なクレーン装置を載置する工程と、を備え
前記架台は、
平面視してH断面に形成された本体部と、
前記本体部の上端に設けられた上板と、
前記本体部の下端に設けられた下板と、
前記本体部に設けられた補強板と、を備えていることを特徴とする、
高架橋構築工法。
A viaduct construction method applied to the construction of viaducts,
installing a plurality of pedestals on a pair of bridge girders supported by a plurality of piers and facing each other along the axial direction of the viaduct;
installing a plurality of cross beams on top of the plurality of frames so as to bridge the pair of bridge girders;
installing a pair of rail beams facing each other along the bridge axis direction of the viaduct on the plurality of cross beams;
providing a pair of rails on the pair of rail beams;
placing a movable crane device on the pair of rails ,
The pedestal is
A main body formed in an H cross section when viewed from above;
an upper plate provided at the upper end of the main body;
a lower plate provided at the lower end of the main body;
A reinforcing plate provided on the main body part ,
Viaduct construction method.
前記クレーン装置により前記架台、前記横断梁、前記レール梁、及び前記レールが設置されていない前記一対の橋桁上の領域に床面を形成するための複数の所定数のプレキャスト床版を載置する工程を備える、
請求項1に記載の高架橋構築工法。
Using the crane device, a predetermined number of precast deck slabs are placed on the trestle, the cross beam, the rail beam, and the pair of bridge girders where the rails are not installed to form a floor surface. Equipped with a process,
The viaduct construction method according to claim 1.
前記レール上において前記クレーン装置を前記プレキャスト床版が載置された領域と反対方向に移動させる工程と、
前記プレキャスト床版を載置した領域に隣接する領域から前記レール、前記レール梁、前記横断梁、及び前記架台を撤去して所定数の他の前記プレキャスト床版を設置する設置領域を形成する工程と、
前記設置領域に複数の所定数の前記プレキャスト床版を載置する工程を備える、
請求項2に記載の高架橋構築工法。
moving the crane device on the rail in a direction opposite to the area where the precast deck is placed;
A step of removing the rail, the rail beam, the cross beam, and the pedestal from an area adjacent to the area where the precast floor slab is placed to form an installation area in which a predetermined number of other precast floor slabs are installed. and,
comprising a step of placing a plurality of predetermined number of the precast floor slabs in the installation area;
The viaduct construction method according to claim 2.
前記一対の橋桁上に載置された複数の前記プレキャスト床版同士と前記一対の橋桁とをコンクリートにより一体化すると共に、前記プレキャスト床版上にコンクリートを打設して床面を形成する工程を備える、
請求項2又は3に記載の高架橋構築工法。
A step of integrating the plurality of precast deck slabs placed on the pair of bridge girders and the pair of bridge girders with concrete, and pouring concrete onto the precast deck slab to form a floor surface. prepare,
The viaduct construction method according to claim 2 or 3.
前記一対のレール上を走行する運搬用台車を備え、前記運搬用台車は、前記プレキャスト床版の一時保管場所と前記クレーン装置の近傍までの間を往復走行して前記プレキャスト床版を運搬する工程を備える、
請求項2又は3に記載の高架橋構築工法。
A step of transporting the precast floor slab by traveling back and forth between a temporary storage location for the precast floor slab and a vicinity of the crane device, comprising a transportation trolley that runs on the pair of rails. Equipped with
The viaduct construction method according to claim 2 or 3.
高架橋の構築に適用される高架橋構築装置であって、
複数の橋脚に支持されると共に、前記高架橋の橋軸方向に沿って対向する一対の橋桁上に設置された複数の架台と、
前記一対の橋桁を架橋するように前記複数の架台の上部に設置された複数の横断梁と、
前記複数の横断梁上に前記高架橋の橋軸方向に沿って対向して設置された一対のレール梁と、
前記一対のレール梁上に設置された一対のレールと、
前記一対のレールに移動自在に載置されたクレーン装置と、を備え
前記架台は、
平面視してH断面に形成された本体部と、
前記本体部の上端に設けられた上板と、
前記本体部の下端に設けられた下板と、
前記本体部に設けられた補強板と、を備えていることを特徴とする、
高架橋構築装置。
A viaduct construction device applied to the construction of viaducts, comprising:
a plurality of pedestals supported by a plurality of piers and installed on a pair of bridge girders facing each other along the bridge axis direction of the viaduct;
a plurality of cross beams installed on top of the plurality of frames so as to bridge the pair of bridge girders;
a pair of rail beams installed oppositely along the bridge axis direction of the viaduct on the plurality of cross beams;
a pair of rails installed on the pair of rail beams;
a crane device movably mounted on the pair of rails ,
The pedestal is
A main body formed in an H cross section when viewed from above;
an upper plate provided at the upper end of the main body;
a lower plate provided at the lower end of the main body;
A reinforcing plate provided on the main body part ,
Viaduct construction equipment.
JP2020077563A 2020-04-24 2020-04-24 Viaduct construction method and viaduct construction equipment Active JP7409952B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020077563A JP7409952B2 (en) 2020-04-24 2020-04-24 Viaduct construction method and viaduct construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020077563A JP7409952B2 (en) 2020-04-24 2020-04-24 Viaduct construction method and viaduct construction equipment

Publications (2)

Publication Number Publication Date
JP2021173051A JP2021173051A (en) 2021-11-01
JP7409952B2 true JP7409952B2 (en) 2024-01-09

Family

ID=78279366

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020077563A Active JP7409952B2 (en) 2020-04-24 2020-04-24 Viaduct construction method and viaduct construction equipment

Country Status (1)

Country Link
JP (1) JP7409952B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2023214438A1 (en) * 2022-05-05 2023-11-09 Deal S.R.L. Plant for the construction of engineering works

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001090027A (en) 1999-09-28 2001-04-03 Nkk Corp Travelling rail bearing device for form truck
JP2005163350A (en) 2003-12-02 2005-06-23 Ishikawajima Harima Heavy Ind Co Ltd Rail bearer in bridge work execution
JP2009191458A (en) 2008-02-12 2009-08-27 Jfe Engineering Corp Construction apparatus for bridge, construction method for floor slab, and construction method for bridge
JP2020002563A (en) 2018-06-26 2020-01-09 鹿島建設株式会社 Deck slab construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001090027A (en) 1999-09-28 2001-04-03 Nkk Corp Travelling rail bearing device for form truck
JP2005163350A (en) 2003-12-02 2005-06-23 Ishikawajima Harima Heavy Ind Co Ltd Rail bearer in bridge work execution
JP2009191458A (en) 2008-02-12 2009-08-27 Jfe Engineering Corp Construction apparatus for bridge, construction method for floor slab, and construction method for bridge
JP2020002563A (en) 2018-06-26 2020-01-09 鹿島建設株式会社 Deck slab construction method

Also Published As

Publication number Publication date
JP2021173051A (en) 2021-11-01

Similar Documents

Publication Publication Date Title
JP3885584B2 (en) Construction method of composite truss bridge
JP3440422B2 (en) Bridge construction method and bridge construction device
CN112320611B (en) Overweight assembled prefabricated stair hoisting device and construction method
JP2008115645A (en) Grade separated crossing structure and construction method of grade separated crossing structure
KR101127130B1 (en) A precast type pre-stress box girder bridge excution method
JP5184248B2 (en) Construction method of level crossing
JP7409952B2 (en) Viaduct construction method and viaduct construction equipment
JP2006028881A (en) Self-propelled pc floor slab erecting machine and pc floor slab erecting method
JP3991067B1 (en) Temporary bridge between railway platforms
JP6374353B2 (en) How to build a bridge
JP4977110B2 (en) Composite digit structure and composite digit construction method
JP2000045231A (en) Erection method for arch bridge
JP2003129403A (en) Block type traffic road, dividing bridge type traffic road and bridge traffic road
JP3701078B2 (en) Road slab construction method
JP2006112086A (en) Structure of bridge and method for rebuilding bridge
JP2000008304A (en) Pedestal for rail road work beam and execution method of pedestal for rail road work beam
KR101258841B1 (en) Precast concrete slab construction method of bridge
CN113652953A (en) Novel assembled overline bridge ramp
CN115427634A (en) Method for producing a road deck for a bridge
JP2000104220A (en) Erection of combined truss bridge
JPH05311617A (en) Construction method for elevated structure
CN112482316A (en) Gate dam gate machine beam construction method and gate dam gate machine beam structure
JP6678440B2 (en) Construction method of viaduct, installation method and removal method of container and support used for this
JP4030817B2 (en) Precast solid intersection
JP3999556B2 (en) Three-dimensional intersection construction method and three-dimensional intersection

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230213

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230915

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230919

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20231109

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20231121

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20231221

R150 Certificate of patent or registration of utility model

Ref document number: 7409952

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150