JP2006112086A - Structure of bridge and method for rebuilding bridge - Google Patents

Structure of bridge and method for rebuilding bridge Download PDF

Info

Publication number
JP2006112086A
JP2006112086A JP2004299157A JP2004299157A JP2006112086A JP 2006112086 A JP2006112086 A JP 2006112086A JP 2004299157 A JP2004299157 A JP 2004299157A JP 2004299157 A JP2004299157 A JP 2004299157A JP 2006112086 A JP2006112086 A JP 2006112086A
Authority
JP
Japan
Prior art keywords
girder
bridge
road
construction
new
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2004299157A
Other languages
Japanese (ja)
Other versions
JP4477467B2 (en
Inventor
Tadayoshi Ishibashi
忠良 石橋
Shigeki Watanabe
繁樹 渡辺
Shigemi Sato
茂美 佐藤
Hiromichi Sugawara
広道 菅原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tekken Corp
Original Assignee
Tekken Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tekken Corp filed Critical Tekken Corp
Priority to JP2004299157A priority Critical patent/JP4477467B2/en
Publication of JP2006112086A publication Critical patent/JP2006112086A/en
Application granted granted Critical
Publication of JP4477467B2 publication Critical patent/JP4477467B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To bring about suitability for the rebuilding of a railway bridge, or the expansion of a space under the bridge or the widening of a road; to enable construction work for them to be performed under a live wire; to utilize a track girder and a supporting beam for temporary construction as construction girders in that case; to eliminate the irrationality of demolition or removal of them by utilizing them as structural members of a newly built bridge after the utilization of them; to achieve the rationalization of construction, the shortening of a construction period and a reduction in construction cost; to reduce the weight of the newly built bridge by simplifying a constitution; and to facilitate and reduce the securement of a girder production yard or an erection yard. <P>SOLUTION: This structure of the bridge comprises newly installed over-road girders 25 and 26 for the newly built bridge 43, and main girders 34 and 35 which are arranged outside the over-road girders 25 and 26. The structure of the bridge is equipped with girder materials 21 and 38 which are laid between the main girders 34 and 35 and which can support the over-road girders 25 and 26. The newly installed over-road girders 25 and 26 are utilized as a construction girder for the newly built bridge 43. Additionally, the girder materials 21 and 38 can be utilized as the supporting beam for the newly constructed over-road girders 25 and 26. After the utilization of them, they are left to constitute the newly built bridge 43. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、例えば鉄道橋梁の架け替えまたは橋梁下スペ−スの拡張ないし道路の拡幅に好適で、それらの工事を活線下で行なえ、かつその際軌道桁や仮設時の受梁を工事桁として利用し、利用後は新設橋梁の構造部材として利用して、それらの解体・撤去の不合理を解消し、施工の合理化と工期の短縮化並びに工費の低減を図るとともに、構成を簡潔化して新設橋梁の軽量化を図り、更に桁製作ヤ−ドまたは架設ヤ−ドの確保を容易かつ縮小し得るようにした、橋梁の構造およびその架け替え方法に関する。   The present invention is suitable for, for example, replacement of a railway bridge, expansion of a space under a bridge, or widening of a road. After use, it will be used as a structural member of a newly constructed bridge to eliminate the unreasonableness of dismantling and removal, streamline construction, shorten the construction period, reduce construction costs, and simplify the configuration. The present invention relates to a structure of a bridge and a method for replacing the bridge, which can reduce the weight of a new bridge, and can easily and reduce the securing of a girder manufacturing yard or a construction yard.

例えば老朽化や輸送量増加等によって鉄道橋の架け替えの必要を生じた場合、その架け替え工事は、代替輸送路の確保が困難な場合が多いため、鉄道の運行を確保しながら行なわれることが多い。
そのような架け替え工事の手法として、一般的に仮線施工や桁横取架設工法等が採られる。このうち、仮線施工は現在線の側部に仮線路を設置し、該仮線路に鉄道車両を迂回させて運行し、現在線を撤去して橋梁を新設施工し、また桁横取架設工法は現在線の側部で橋桁を製作し、橋桁の完成後、現在線を撤去し、新設の橋梁を横取架設するようにしている。
For example, when it becomes necessary to replace a railway bridge due to aging or an increase in transportation volume, it is often difficult to secure an alternative transportation route. There are many.
As a method of such replacement work, generally, temporary line construction, girder horizontal construction method, etc. are adopted. Among these, temporary line construction is to install a temporary track on the side of the current track, operate the detour by detouring the railroad vehicle, remove the current track, install a new bridge, and install the horizontal girder construction method. Manufactures a bridge girder on the side of the current line, removes the current line after the bridge girder is completed, and installs a new bridge horizontally.

しかし、仮線施工は、仮線用地の確保が困難であったり、用地の借料や買収等に伴なって工費が嵩み、また桁横取架設工法は、桁製作ヤ−ドの確保と桁横取設備を要して、工費が増大するという問題がある。   However, it is difficult to secure temporary land for construction of temporary lines, and the construction costs increase due to the rent and acquisition of the land. There is a problem that the construction cost increases due to the need for a horizontal installation facility.

一方、架け替え工事の他の手法として、工事桁や仮設橋脚を用いて鉄道線路を支持しながら、橋桁や橋脚を順次架け替えていく方法がある。
例えば、レンガア−チ橋をコンクリ−ト橋へ架け替える方法として、工事桁をレンガア−チ橋のスパン方向に施工し、鉄道線路を支持するとともに、レンガア−チ橋の橋脚を残して工事桁を支持し、既設の橋桁部を切断・撤去する一方、新設橋脚を施工し、該新設橋脚の間に仮設橋脚を施工し、これら新設および仮設橋脚で工事桁を支持し、既設橋脚を解体・撤去するとともに、新設橋桁を施工し、該橋桁の施工後に工事桁を解体・撤去して鉄道線路を新設橋桁に据え付け、橋の完成後、仮設橋脚を解体・撤去して、鉄道橋の架け替えを行なうようにしたものがある(例えば、特許文献1参照)。
On the other hand, as another method of the replacement work, there is a method of sequentially replacing the bridge girder and the pier while supporting the railway track using the construction girder and the temporary pier.
For example, as a method of replacing a brick-arch bridge with a concrete bridge, construct the construction girder in the span direction of the brick-arch bridge, support the railroad track, and leave the pier of the brick-arch bridge to replace the construction girder. Supporting, cutting and removing the existing bridge girder, constructing new piers, constructing temporary piers between the new piers, supporting the construction girders with these new and temporary piers, dismantling and removing existing piers At the same time, construct a new bridge girder, disassemble and remove the construction girder after the construction of the bridge girder, install the railroad track on the new bridge girder, disassemble and remove the temporary pier after the bridge is completed, and replace the railway bridge Some have been made (for example, see Patent Document 1).

こうして施工した鉄道橋の新設橋脚によるスパンは、レンガア−チ橋の既設橋脚によるスパンよりも長くなっており、それだけ橋下スペ−スを拡張し橋下の道路を拡幅し得るが、既設の橋桁部を切断・撤去後、新設橋桁を施工するまでの間、工事桁の強度が不足するため、新設橋脚の間に仮設橋脚の施工を要し、それだけ工期が長期化し工費が高騰する不合理がある。   The span of the newly constructed pier of the railway bridge thus constructed is longer than the span of the existing pier of the brick arch bridge, so that the space under the bridge can be expanded and the road under the bridge can be widened. Since the strength of the construction girder is insufficient until the construction of the new bridge girder after cutting and removal, it is necessary to construct a temporary pier between the newly constructed piers, and there is an unreasonable increase in the construction period and the construction cost.

そこで、工事桁をレンガア−チ橋のスパン方向に施工し、鉄道線路を支持するとともに、レンガア−チ橋の既設橋脚を残して工事桁を支持し、既設の橋桁部を切断・撤去する一方、新設橋脚を施工し、該新設橋脚と既設橋脚とで工事桁を支持する。
次に、鉄道線路の両側に主桁をスパン方向に配置し、該主桁を新設橋脚に支持させるとともに、主桁の間に多数の横桁を架設し、工事桁を横桁で支持させた後、既設橋脚を解体・撤去し、主桁と横桁と新設橋脚とをコンクリ−トで一体化し、橋桁を形成後、工事桁を解体・撤去して鉄道線路を橋桁に据え付けるようにしている(例えば、特許文献1参照)
Therefore, while constructing the construction girder in the span direction of the brick arch bridge and supporting the railway track, supporting the construction girder leaving the existing pier of the brick arch bridge, cutting and removing the existing bridge girder part, A new pier is constructed, and the construction girder is supported by the new pier and the existing pier.
Next, the main girder was placed in the span direction on both sides of the railroad track, and the main girder was supported on the newly constructed pier, and a large number of horizontal girders were installed between the main girders, and the construction girder was supported by the horizontal girder. Later, the existing bridge piers were dismantled and removed, and the main girder, the horizontal girder, and the new pier were integrated into the concrete. After the bridge girder was formed, the construction girder was dismantled and removed to install the railroad track on the bridge girder. (For example, see Patent Document 1)

しかし、前記改善した架け替え方法は、工事桁とその施工および撤去作業、並びに多数の横桁とその架設作業を要し、作業が煩雑で工期の長期化と工費の高騰および橋梁の重量化を招き、また主桁と横桁と新設橋脚とをコンクリ−トを打設して一体化するため、工期の長期化と工費の高騰を助長し、一方、橋梁の構造も主桁の中間位置に新設橋脚を配置しているため、橋下スペ−スが半減され、その拡張や橋下道路の拡幅が制約されるという問題があった。   However, the improved replacement method requires a work girder and its construction and removal work, as well as a large number of cross girders and its installation work, which is cumbersome, lengthening the construction period, increasing the construction cost, and increasing the weight of the bridge. In addition, the construction of the main girder, horizontal girder, and new pier is integrated by concreting, which contributes to a longer construction period and higher construction costs. On the other hand, the structure of the bridge is also in the middle of the main girder Since the new bridge piers are arranged, the space under the bridge is halved, and there is a problem that the expansion and the widening of the road under the bridge are restricted.

一方、橋桁のスパンを大きくする方法として、複数の主桁を幅方向に接合し、これらを横ケ−ブルで連結して橋桁を形成するとともに、前記主桁は鉄骨を内臓したコンクリ−ト製の複数の桁材を長さ方向に接合し、これらをプリストレスを付与した内ケ−ブルで連結して構成し、桁高を抑制し橋桁の自重を減少させることによって、スパンを大きくさせるようにした桁橋がある(例えば、特許文献2参照)。   On the other hand, as a method of increasing the span of the bridge girder, a plurality of main girders are joined in the width direction and these are connected by a horizontal cable to form a bridge girder, and the main girder is made of a concrete containing a steel frame. A plurality of girders are joined together in the length direction, and these are connected by a prestressed inner cable to suppress the girder height and reduce the weight of the bridge girder, thereby increasing the span. There is a girder bridge (see, for example, Patent Document 2).

しかし、前記桁橋は複数の主桁に多数の横ケ−ブルと内外ケ−ブルとを貫挿して連結するため、工事が煩雑で工費の高騰を助長するとともに、長さ方向に接合した複数の主桁を、鉄骨を介し内外ケ−ブルで連結する構造上、橋の利用を確保しながら架け替えを行なうことが難しく、しかも曲げモ−メントに対する強度上の不安があって、その利用は低荷重用の小形桁橋に限られる問題があった。   However, since the girder bridge is connected to a plurality of main girders through a large number of horizontal cables and inner and outer cables, the construction is cumbersome and the construction cost is increased, and the plurality of girder bridges joined in the length direction. The main girder is connected by a steel frame with an internal and external cable, so it is difficult to replace the bridge while securing the use of the bridge, and there are concerns about strength against bending moments. There was a problem limited to small girder bridges for low loads.

特開2002−97608号公報JP 2002-97608 A 特開2003−184029号公報JP 2003-184029 A

本発明はこのような問題を解決し、例えば鉄道橋梁の架け替えまたは橋梁下スペ−スの拡張ないし道路の拡幅に好適で、それらの工事を活線下で行なえ、かつその際軌道桁や仮設時の受梁を工事桁として利用し、利用後は新設橋梁の構造部材として利用して、それらの解体・撤去の不合理を解消し、施工の合理化と工期の短縮化並びに工費の低減を図るとともに、構成を簡潔化して新設橋梁の軽量化を図り、更に桁製作ヤ−ドまたは架設ヤ−ドの確保を容易かつ縮小し得るようにした、橋梁の構造およびその架け替え方法を提供することを目的とする。   The present invention solves such a problem, and is suitable for, for example, replacement of a railway bridge or expansion of a space under a bridge or widening of a road. Use the current beam as a construction girder and use it as a structural member for the newly constructed bridge to eliminate the unreasonableness of dismantling / removing them, streamlining construction, shortening the construction period, and reducing construction costs. In addition, a structure of a bridge and a method of replacing the bridge are provided, which simplifies the configuration to reduce the weight of a newly-built bridge, and further facilitates and reduces the securing of a girder manufacturing yard or an erection yard. With the goal.

請求項1の発明は、新設橋梁の新設架道桁と、該架道桁の外側に配置する主桁と、該主桁の間に架設し、かつ前記架道桁を支持可能な桁材と、を備えた橋梁の構造において、新設架道桁を新設橋梁の工事桁として、また前記桁材を新設架道桁の受梁としてそれぞれ利用可能にするとともに、それらの利用後は残置して新設橋梁を構成し、それらの利用後の解体・撤去の不合理を解消するとともに、その有効利用を図って、工期の短縮と工費の低減を図るようにしている。
請求項2の発明は、左右一対の新設架道桁を連結継手を介して連結し、新設架道を構成することで、新設架道の組み立ての容易化と、その小形軽量化を図るようにしている。
請求項3の発明は、前記新設架道桁を桁材上に載架し、それらの間の構成部材の介在をなくして構成を簡潔化し、橋梁の小形軽量化を図るようにしている。
The invention of claim 1 is a newly installed girder of a new bridge, a main girder arranged outside the girder, and a girder constructed between the main girder and capable of supporting the girder. In the structure of the bridge with, the newly constructed girder can be used as a construction girder for the newly constructed bridge, and the girder material can be used as a receiving beam for the newly constructed girder. Bridges are constructed to eliminate the unreasonableness of dismantling and removal after their use, and to make effective use of them, shortening the construction period and reducing construction costs.
According to the second aspect of the present invention, a pair of left and right newly installed road girders are connected via a connecting joint to form a new road, thereby facilitating the assembly of the new road and reducing its size and weight. ing.
According to a third aspect of the present invention, the newly constructed road girder is mounted on a girder, and the configuration is simplified by eliminating the interposition of components between them, thereby reducing the size and weight of the bridge.

請求項4の発明は、前記新設架道桁のスパン方向の端部を前記桁材で支持し、該桁材と前記主桁とを連結するとともに、前記主桁を新設架道桁よりも長尺に形成し、該主桁をスパン方向の最外側端部で支持して、桁材の使用個数を低減し、その設置の手間を軽減して、工期の短縮化と工費の低減並びに軽量化を図るとともに、桁材を架設する仮橋脚の使用個数とその設置の手間を軽減し、その分主桁下の橋台または橋脚スパンを拡張して、当該スペ−スの利用を促し、例えば新設橋梁下の道路等の拡幅に応じられるようにしている。
請求項5の発明は、前記桁材と主桁とをPC桁またはRC桁で構成し、これらを堅牢かつ安価に製作するようにしている。
請求項6の発明は、前記新設架道桁を軌道桁とし、前記新設架道桁に直接レ−ルを敷設し、枕木の敷設を省略し、その分工期の短縮化と工費の低減を図るとともに、新設橋梁の軽量化を図るようにしている。
The invention of claim 4 supports the end of the newly installed road girder in the span direction with the girder, connects the girder and the main girder, and makes the main girder longer than the newly installed girder. It is formed into a scale, and the main girder is supported at the outermost end in the span direction to reduce the number of girders used, reduce the labor of installation, shorten the construction period, reduce the construction cost, and reduce the weight. In addition to reducing the number of temporary piers used to install girders and the time and effort of installing them, the abutment or pier span under the main girder is expanded accordingly, and the use of the space is promoted. It is adapted to the widening of the roads below.
According to the invention of claim 5, the girder material and the main girder are constituted by PC girder or RC girder, and these are made robust and inexpensive.
The invention of claim 6 uses the newly installed road girder as a track girder, lays a rail directly on the newly installed road girder, omits the laying of sleepers, and shortens the work period and reduces the construction cost. At the same time, the new bridge will be lightened.

請求項7の発明は、既設構造物に沿って仮橋脚を立設後、新設架道桁を施工し、該新設架道桁を前記仮橋脚に支持させた後、前記既設構造物を解体・撤去し、前記新設架道桁に沿って橋台または橋脚を立設し、これらの間に主桁を架設するとともに、該主桁に新設架道桁を支持させた後、前記仮橋脚を解体・撤去する橋梁の架け替え方法において、前記仮橋脚を新設架道桁の端部に立設し、該仮橋脚に架設した桁材に前記新設架道桁を支持し、該桁材を受梁として利用し、その利用後に新設橋梁の構成部材として残置するとともに、前記新設架道桁を新設橋梁の工事桁として利用し、その利用後に新設橋梁の構成部材として残置し、仮橋脚の立設数を低減し、立設工事の手間を軽減するとともに、新設架道桁と桁材の合理的な利用を図って、工期の短縮化と工費の低減を図る一方、施工区間の仮橋脚を撤去して、撤去後のスペ−スの拡張とその有効利用を促し、例えば新設橋梁下の道路等の拡幅に応じられるようにしている。   In the invention of claim 7, after the temporary bridge pier is erected along the existing structure, a new road girder is constructed, and after the new road girder is supported by the temporary bridge pier, the existing structure is dismantled. Removed, installed abutments or piers along the newly constructed girder, installed a main girder between them, and supported the newly constructed girder on the main girder, then dismantled the temporary pier In the method of replacing the bridge to be removed, the temporary bridge pier is erected at the end of the new road girder, the new road girder is supported by the girder built on the temporary bridge pier, and the girder is used as a receiving beam. The new bridge girder is used as a construction girder for the new bridge, and after that, the new girder girder is used as the construction girder for the new bridge. To reduce the amount of time and effort required for erection work, and to make rational use of newly constructed road girders and girders. While shortening the construction period and reducing construction costs, the temporary bridge piers in the construction section are removed to promote the expansion of the space after removal and its effective use, for example, to respond to the widening of the road under the new bridge, etc. I have to.

請求項8の発明は、前記既設構造物を撤去後、新設架道桁の外側で、かつ前記施工区間の両端部に橋台または橋脚を立設し、該橋台または橋脚間に前記主桁を架設し、該主桁に桁材の両端部を連結し、主桁に新設架道桁を支持させた後、前記施工区間の仮橋脚を解体・撤去し、橋台または橋脚の立設数を低減し、その立設工事の手間を軽減して、工期の短縮化と工費の低減を図るとともに、施工区間の仮橋脚を解体・撤去して、撤去後のスペ−スの拡張とその有効利用を促し、当該スペ−スの利用範囲を拡大して、例えば新設橋梁下の道路等の拡幅に応じられるようにしている。   In the invention of claim 8, after the existing structure is removed, an abutment or a pier is erected outside the newly installed girder and at both ends of the construction section, and the main girder is installed between the abutment or the pier After connecting both ends of the girder to the main girder and supporting the newly installed girder to the main girder, dismantle and remove the temporary piers in the construction section to reduce the number of standing abutments or piers In addition to reducing the work required for the installation work, the construction period is shortened and the construction cost is reduced, and the temporary bridge piers in the construction section are dismantled and removed to promote the expansion and effective use of the space after removal. The range of use of the space is expanded so that, for example, it can respond to the widening of the road under the new bridge.

請求項9の発明は、単一の仮橋脚に二つの桁材を架設し、該桁材に隣接する新設架道桁の端部を支持させ、仮橋脚の立設数を低減し、その立設工事の手間を軽減して、工期の短縮化と工費の低減を図るようにしている。
請求項10の発明は、前記既設構造物を撤去後、その撤去スペ−スを桁製作ヤ−ドまたは桁材の架設ヤ−ドの利用を図るようにして、施工現場での桁製作ヤ−ドまたは架設ヤ−ドの確保を容易にし、工費の低減を図るとともに、施工現場での主桁等の製作や架設を促すようにしている。
In the invention of claim 9, two girder members are erected on a single temporary bridge pier, and the end of a new road girder adjacent to the girder member is supported to reduce the number of erected piers. The effort of installation work is reduced to shorten the construction period and reduce the construction cost.
According to the invention of claim 10, after the existing structure is removed, the removal space is used for a girder production yard or a girder erection yard, and a girder production yard at a construction site. In addition to facilitating the securing of the door or the erection yard, the construction cost is reduced, and the production and erection of the main girder and the like are promoted at the construction site.

請求項1の発明は、新設架道桁を新設橋梁の工事桁として、また前記桁材を新設架道の受梁としてそれぞれ利用可能にするとともに、それらの利用後は残置して新設橋梁を構成したから、それらの利用後の解体・撤去の不合理を解消するとともに、その有効利用を図って、工期の短縮と工費の低減を図ることができる。
請求項2の発明は、左右一対の新設架道桁を連結継手を介して連結し、新設架道を構成したから、新設架道の組み立ての容易化と、その小形軽量化を図ることができる。
請求項3の発明は、前記新設架道桁を桁材上に載架したから、それらの間の構成部材の介在をなくして構成を簡潔化し、橋梁の小形軽量化を図ることができる。
The invention of claim 1 makes it possible to use a newly constructed girder as a construction girder for a newly built bridge and the girder material as a receiving beam for a newly constructed road, and to construct a newly constructed bridge by leaving them after use. Therefore, it is possible to eliminate the unreasonableness of dismantling / removal after use and to make effective use thereof, thereby shortening the construction period and reducing the construction cost.
In the invention of claim 2, since the pair of left and right newly installed road girders are connected via a coupling joint to constitute the newly installed road, it is possible to facilitate the assembly of the newly installed road and to reduce the size and weight thereof. .
In the invention of claim 3, since the newly installed road girder is mounted on the girder, it is possible to simplify the configuration by eliminating the interposition of the constituent members therebetween, and to reduce the size and weight of the bridge.

請求項4の発明は、前記新設架道桁のスパン方向の端部を前記桁材で支持し、該桁材と前記主桁とを連結するとともに、前記主桁を新設架道桁よりも長尺に形成し、該主桁をスパン方向の最外側端部で支持したから、桁材の使用個数を低減し、その設置の手間を軽減して、工期の短縮化と工費の低減並びに軽量化を図るとともに、桁材を架設する仮橋脚の使用個数とその設置の手間を軽減し、その分主桁下の橋台または橋脚スパンを拡張して、当該スペ−スの利用を促し、例えば新設橋梁下の道路等の拡幅に応じられる効果がある。
請求項5の発明は、前記桁材と主桁とをPC桁またはRC桁で構成したから、これらを堅牢かつ安価に製作することができる。
請求項6の発明は、前記新設架道桁を軌道桁とし、前記新設架道桁に直接レ−ルを敷設したから、枕木の敷設を省略し、その分工期の短縮化と工費の低減を図れるとともに、新設橋梁の軽量化を図ることができる。
The invention of claim 4 supports the end of the newly installed road girder in the span direction with the girder, connects the girder and the main girder, and makes the main girder longer than the newly installed girder. Since it is formed into a scale and the main girder is supported at the outermost end in the span direction, the number of girder materials used is reduced, the labor of installation is reduced, the construction period is shortened, the construction cost is reduced, and the weight is reduced. In addition to reducing the number of temporary piers used to install girders and the time and effort of installing them, the abutment or pier span under the main girder is expanded accordingly, and the use of the space is promoted. There is an effect corresponding to the widening of the road below.
In the invention of claim 5, since the girder and the main girder are constituted by PC girder or RC girder, these can be manufactured robustly and inexpensively.
In the invention of claim 6, since the newly installed road girder is a track girder and a rail is laid directly on the newly installed road girder, the laying of sleepers is omitted, and the construction period is shortened and the construction cost is reduced. It is possible to reduce the weight of the new bridge.

請求項7の発明は、仮橋脚を新設架道桁の端部に立設し、該仮橋脚に架設した桁材に前記新設架道桁を支持し、該桁材を受梁として利用し、その利用後に新設橋梁の構成部材として残置するとともに、前記新設架道桁を新設橋梁の工事桁として利用し、その利用後に新設橋梁の構成部材として残置するから、仮橋脚の立設数を低減し、立設工事の手間を軽減するとともに、新設架道桁と桁材の合理的な利用を図って、工期の短縮化と工費の低減を図る一方、施工区間の仮橋脚を撤去後のスペ−スの拡張とその有効利用を促し、例えば新設橋梁下の道路等の拡幅に応じられる効果がある。   The invention of claim 7 erected a temporary pier at the end of a newly installed girder, supported the newly installed girder on a girder constructed on the temporary pier, and used the girder as a receiving beam. After being used, it is left as a component of a new bridge, and the new road girder is used as a construction girder for a new bridge, and after it is used, it is left as a component of a new bridge. In addition to reducing the time and labor required for erection work, rational use of newly constructed road girders and girders is aimed at shortening the construction period and reducing construction costs, while at the same time removing the temporary piers in the construction section. For example, there is an effect that it can respond to the widening of the road under the new bridge.

請求項8の発明は、前記既設構造物を撤去後、新設架道桁の外側で、かつ前記施工区間の両端部に橋台または橋脚を立設し、該橋台または橋脚間に前記主桁を架設し、該主桁に桁材の両端部を連結し、主桁に新設架道桁を支持させた後、前記施工区間の仮橋脚を解体・撤去するから、橋台または橋脚の立設数を低減し、その立設工事の手間を軽減して、工期の短縮化と工費の低減を図るとともに、施工区間の仮橋脚を解体・撤去して、撤去後のスペ−スの拡張とその有効利用を促し、当該スペ−スの利用範囲を拡大して、例えば新設橋梁下の道路等の拡幅に応じられる効果がある。   According to the invention of claim 8, after the existing structure is removed, an abutment or a pier is erected outside the newly installed girder and at both ends of the construction section, and the main girder is installed between the abutment or the pier After connecting both ends of the girder to the main girder and supporting the newly constructed girder to the main girder, the temporary piers in the construction section are disassembled and removed, so the number of standing abutments or piers is reduced. In addition to reducing the time and effort of the installation work, the construction period is shortened and the construction cost is reduced, and the temporary piers in the construction section are dismantled and removed, so that the space after removal can be expanded and effectively used. This has the effect of expanding the range of use of the space and responding to the widening of the road under the new bridge, for example.

請求項9の発明は、単一の仮橋脚に二つの桁材を架設し、該桁材に隣接する新設架道桁の端部を支持させるから、仮橋脚の立設数を低減し、その立設工事の手間を軽減して、工期の短縮化と工費の低減を図ることができる。
請求項10の発明は、前記既設構造物を撤去後、その撤去スペ−スを桁製作ヤ−ドまたは桁材の架設ヤ−ドの利用を図るようにしたから、施工現場での桁製作ヤ−ドまたは架設ヤ−ドの確保を容易にし、工費の低減を図れるとともに、施工現場での主桁等の製作や架設を促すことができる。
In the invention of claim 9, since two girder members are erected on a single temporary pier and the end of a newly installed girder adjacent to the girder is supported, the number of erected piers is reduced, It can reduce the time and labor required for the erection work, shorten the construction period and reduce the construction cost.
In the invention of claim 10, since the existing structure is removed, the removal space is used for a girder manufacturing yard or a girder erection yard. -It is possible to easily secure the door or the erection yard, reduce the construction cost, and promote the production and erection of the main girder and the like at the construction site.

以下、本発明を地上構造物である鉄道用高架橋の架け替えおよび高架橋下の道路の拡幅に適用した図示の実施形態について説明すると、図1乃至図3は本発明の施工前における高架橋の状況を示している。
同図において1は地上構造物である既設の鉄道用の橋梁で、該橋梁1は地盤2上に左右一対に立設された複数の既設の橋脚3と、該橋脚3の上端部に架設された横梁4と、隣接する横梁4間を連結する橋桁5と、横梁4上に支持されたRC製、つまり鉄筋コンクリ−ト製の既設の架道桁である床版6とで構成され、該床版6上に既設の架道である軌道7が敷設されている。
Hereinafter, the illustrated embodiment in which the present invention is applied to the replacement of a railway viaduct as a ground structure and the widening of a road under the viaduct will be described. FIGS. 1 to 3 show the situation of the viaduct before construction of the present invention. Show.
In FIG. 1, reference numeral 1 denotes an existing railway bridge which is a ground structure, and the bridge 1 is installed on a plurality of existing piers 3 standing on the ground 2 in a pair of left and right sides, and at the upper end of the pier 3. A horizontal girder 4, a bridge girder 5 connecting the adjacent cross beams 4, and a floor slab 6 which is an existing road girder made of RC, that is, made of reinforced concrete, supported on the cross beam 4, A track 7, which is an existing overhead road, is laid on the floor slab 6.

前記既設の軌道7は図3のように、砕石や砂利等を盛り上げた道床8と、該道床8上に配置した枕木9と、該枕木9に締結具10を介して取り付けたレ−ル11とで構成されている。
前記橋梁1の中間部の橋脚3a,3aの間隔は、他の橋脚3の間隔よりも若干幅広に形成され、それらの横梁4,4に掛止片12,12が突設され、該掛止片12,12間に既設の架橋桁13が架設されている。
図中、14は前記橋脚3a,3a間の地盤2上に形成された車道で、その両側にガ−ドレ−ル等の防護材15を介して、歩道16が設けられている。
As shown in FIG. 3, the existing track 7 includes a roadbed 8 that swells crushed stone and gravel, a sleeper 9 disposed on the roadbed 8, and a rail 11 that is attached to the sleeper 9 via a fastener 10. It consists of and.
The distance between the piers 3a, 3a in the middle part of the bridge 1 is slightly wider than the distance between the other piers 3, and the latching pieces 12, 12 project from the lateral beams 4, 4, and the An existing bridge girder 13 is installed between the pieces 12 and 12.
In the figure, reference numeral 14 denotes a roadway formed on the ground 2 between the piers 3a, 3a, and sidewalks 16 are provided on both sides of the roadway via protective materials 15 such as guard rails.

図4および図5は本発明を施工した高架橋の完成状況を示し、図6乃至図15は本発明に用いた新設の架道桁と、新設橋梁43の施工手順を示している。
本発明による新設橋梁43の架け替えは、鉄道の活線状態を確保しながら施工され、これは前記橋脚3a,3aの略4倍広い施工区間Zにおける既設軌道7の撤去と、同区間Zにおける新設橋梁43の架け替えと、道路14の拡幅とを含んでいる。
前記施工区間Zにおける既設軌道7の撤去に際しては、先ず既設の橋脚3,3の間に杭17を打ち込み、杭17上に型鋼を枠組みした仮橋脚18を立設し、また施工区間Zの両端部に埋設した基礎アンカ−19上に、仮支柱20を立設している。
4 and 5 show the completion status of the viaduct constructed according to the present invention, and FIGS. 6 to 15 show the construction procedure of the newly installed road girder and the new bridge 43 used in the present invention.
The replacement of the new bridge 43 according to the present invention is carried out while ensuring the live state of the railway, which is the removal of the existing track 7 in the construction section Z approximately four times wider than the piers 3a, 3a, This includes the replacement of the new bridge 43 and the widening of the road 14.
When removing the existing track 7 in the construction section Z, first, the pile 17 is driven between the existing piers 3 and 3, and the temporary pier 18 framing the steel frame is erected on the pile 17. The temporary support column 20 is erected on the foundation anchor 19 embedded in the section.

一方、前記仮橋脚18および仮支柱20の立設と前後して、それらの直上に位置する床版6の対応位置に貫通穴(図示略)を形成し、各貫通穴に仮橋脚18および仮支柱20の上端部を挿入し、かつその上端部を床版6上に突出させ、その上端部にPC製または型鋼製の桁材である受梁21,22を同高位置に架設している。
このうち、PC製の受梁21の長さは、後述の新設架道桁の幅員よりも長尺に形成され、その両端部が架道桁の外側に突出し、その突出端部に受梁21の配筋(図示略)が表出しており(図9参照)、また型鋼製の受梁22は橋梁1の架け替え後に仮支柱20と一緒に撤去するようにしている。図中、23は仮橋脚18の上端部に架設した型鋼製の架枠である。
On the other hand, before and after the temporary pier 18 and the temporary support 20 are erected, through holes (not shown) are formed at the corresponding positions of the floor slab 6 located immediately above them, and the temporary piers 18 and the temporary piers 18 are provided in the respective through holes. Insert the upper end of the support column 20 and project the upper end of the column 20 onto the floor slab 6, and support beams 21 and 22, which are girders made of PC or steel, are installed at the same height on the upper end. Yes.
Among these, the length of the receiving beam 21 made of PC is formed longer than the width of the new road girder described later, and both ends of the receiving beam 21 protrude outside the road girder, and the receiving beam 21 is projected to the protruding end. The bar arrangement (not shown) is exposed (see FIG. 9), and the steel beam receiving beam 22 is removed together with the temporary support 20 after the bridge 1 is replaced. In the figure, reference numeral 23 denotes a steel frame frame constructed on the upper end of the temporary pier 18.

このような状況の下で、床版6上の既設軌道7の枕木9と締結装置11を撤去するとともに、重機(図示略)を介して枕木跡の道床8の中央部を開削し、その掘削穴24に軌道桁である架道桁25,26を向き合わせて収容し、これを前記受梁21,22で支持している。
前記架道桁25,26は、図6のように略L字形断面の左右一対のPC桁、つまりPC鋼材27によってプリストレスを付与した鉄筋コンクリ−トで構成され、その段部25a,26aに前記レ−ル11を直接敷設し、枕木9を省略している。
実施形態では、複数の架道桁25,26を施工区間Zに亘って連結して敷設しているが、これを長尺な単体で構成しても良く、そのようにすることで連結の手間が軽減する。
Under such circumstances, the sleepers 9 and the fastening devices 11 of the existing track 7 on the floor slab 6 are removed, and the central part of the roadbed 8 of the sleeper traces is excavated through heavy equipment (not shown), and the excavation is performed. The road girders 25 and 26 which are track girders are accommodated facing each other in the hole 24 and supported by the receiving beams 21 and 22.
As shown in FIG. 6, the road girders 25 and 26 are formed of a pair of left and right PC girders having a substantially L-shaped cross section, that is, rebar concrete to which prestress is applied by a PC steel material 27. The rail 11 is directly laid and the sleepers 9 are omitted.
In the embodiment, the plurality of road girders 25 and 26 are connected and laid over the construction section Z, but this may be configured as a single unit, and by doing so, the labor of connection is reduced. Is reduced.

前記架道桁25,26は若干離間して対向配置され、その対向端面の間に複数の連結継手28を等間隔に配置している。
前記連結継手28は図6のように、I型鋼の両側に側板29を溶接して略箱形に形成され、該側板29にPC鋼材30を挿入可能な透孔(図示略)を形成し、該側板29にPC鋼材30,30の一端を掛け止め、かつその他端を架道桁25,26の外端部に配置し、そのネジ部にナット(共に図示略)をねじ込んで緊締し、架道桁25,26を連結している。
The road girders 25 and 26 are opposed to each other with a slight gap, and a plurality of coupling joints 28 are arranged at equal intervals between the opposed end faces.
As shown in FIG. 6, the connecting joint 28 is formed in a substantially box shape by welding side plates 29 on both sides of the I-shaped steel, and through holes (not shown) into which the PC steel material 30 can be inserted are formed in the side plates 29. One end of the PC steel materials 30 and 30 is hooked on the side plate 29, and the other end is arranged at the outer end of the road girders 25 and 26. A nut (not shown) is screwed into the threaded portion and tightened. The road beams 25 and 26 are connected.

前記架道桁25,26にレール11を敷設後、施工区間Zにおける床版6上の残りの砂利を除去し、既設構造物を構成する橋脚3、床版6および橋桁5を解体・撤去し、仮橋脚18の周辺に桁製作ヤ−ドないし桁の架設ヤ−ドを確保し、主桁34,35を製作し架設するようにしている。
そして、前記架道桁25,26の敷設と前後し、または前記床版6および橋桁5の解体・撤去後、仮支柱20,20より内側の地盤2に杭31を打ち込んでいる。
前記杭31上に基礎アンカ−32を構築し、該アンカ−32上に橋台33,33を立設し、その上端部を架道桁25,26の前後側端部直下に位置付け、それらの間に左右一対のPC製の主桁34,35を支持している。
After laying the rail 11 on the road girders 25 and 26, the remaining gravel on the floor slab 6 in the construction zone Z is removed, and the pier 3, the floor slab 6 and the bridge girder 5 constituting the existing structure are dismantled and removed. The girder production yard or the girder construction yard is secured around the temporary bridge pier 18, and the main girder 34, 35 is produced and erected.
The pile 31 is driven into the ground 2 on the inner side of the temporary support columns 20 and 20 before and after the installation of the road girders 25 and 26, or after the floor slab 6 and the bridge girder 5 are disassembled and removed.
A foundation anchor 32 is constructed on the pile 31, and abutments 33 and 33 are erected on the anchor 32, and the upper end portions thereof are positioned directly below the front and rear end portions of the road girders 25 and 26. A pair of left and right PC main girders 34 and 35 are supported.

前記主桁34,35は略縦長矩形断面に形成され、その長さは架道桁25,26の略3倍で、橋台33,33間のスパンと略同長に形成されていて、その外側面の中間部に凹溝34a,35aが形成されている。
前記主桁34,35の桁高Hは架道桁25,26の桁高の略3倍に形成され、その剛性を増大させるとともに、その上端部を架道桁25,26の上端部と略同高に配置している
The main girders 34 and 35 are formed in a substantially vertically long rectangular cross section, the length of which is substantially three times that of the road girders 25 and 26, and the length of the span between the abutments 33 and 33 is substantially the same. Grooves 34a and 35a are formed in the middle part of the side surface.
The girder height H of the main girders 34 and 35 is formed to be approximately three times the girder height of the road girders 25 and 26 to increase the rigidity thereof, and the upper end thereof is substantially the same as the upper ends of the road girders 25 and 26. Located at the same height

前記主桁34,35の前後端部と、PC製の受梁21と桁材である横梁38の対向位置に、略矩形の大小の連結窓36,37が形成され、これらの連結窓36,37に主34,35の配筋(図示略)が縦横に表出している。
そして、前記連結窓36,37の配筋(図示略)に、前記受梁21の端部に表出した配筋(図9参照)と、横梁38の両端部に表出した配筋(図示略)とを係合し、かつ各連結窓36,37にコンクリ−トを打設して、主桁34,35間にPC製の受梁21と横梁38とを連結している。
At the front and rear end portions of the main girders 34 and 35, the PC receiving beam 21 and the cross beam 38 which is a beam member, opposed rectangular beams 36 and 37 are formed. In FIG. 37, bar arrangements (not shown) of the main 34 and 35 are shown vertically and horizontally.
Then, in the reinforcing bars (not shown) of the connection windows 36 and 37, the reinforcing bars (see FIG. 9) exposed at the end of the receiving beam 21 and the reinforcing bars (shown in FIG. 9) exposed at both ends of the lateral beam 38 are shown. The PC receiving beam 21 and the cross beam 38 are connected between the main girders 34 and 35 by engaging the connecting windows 36 and 37 with concrete.

この場合の連結状況は図10および図11のようで、新設軌道を構成する架道桁25,26が主桁34,35の上部に位置する上路構造であるが、施工条件に応じて中路または下路構造を採用することも可能である。
図中、39は架道桁25,26と受梁21および横梁38との間に介挿した緩衝板、40は横梁38と橋台33との間に介挿した緩衝板である。
The connection situation in this case is as shown in FIG. 10 and FIG. 11 and is an upper road structure in which the overhead girders 25 and 26 constituting the newly installed track are located above the main girders 34 and 35. It is also possible to adopt a downway structure.
In the figure, 39 is a buffer plate interposed between the road beams 25 and 26 and the receiving beam 21 and the horizontal beam 38, and 40 is a buffer plate interposed between the horizontal beam 38 and the abutment 33.

こうして、主桁34,35に受梁21と横梁38とを連結し、主桁34,35の荷重を橋台33に受け渡したところで、前記施工区間の仮橋脚18と仮支柱20と架枠23とを解体・撤去し、主桁34,35直下の橋梁下スペ−ス41を開放かつ拡張する。
実施形態では橋脚3a,3aの間隔の略4倍に拡張し、当該スペ−ス41を道路スペ−スに充当し、該スペ−スに二車線の車道14と歩道16とを建設している。
この他、図中42は鉄道車両ないし建築限界、43は新設橋梁である。
なお、この実施形態では地上構造物として橋梁1を採用しているが、橋梁1の代わりに盛土(図示略)を採用し、該盛土上に軌道7を敷設した既設構造物に本発明を適用することも可能である。
Thus, when the receiving beam 21 and the transverse beam 38 are connected to the main girders 34 and 35 and the load of the main girders 34 and 35 is transferred to the abutment 33, the temporary pier 18, the temporary support 20 and the frame 23 of the construction section are Is dismantled and removed, and the space 41 under the bridge just below the main girders 34 and 35 is opened and expanded.
In the embodiment, the distance between the piers 3a and 3a is expanded to about four times the space 41, the space 41 is allocated to the road space, and the two-lane roadway 14 and the sidewalk 16 are constructed in the space. .
In addition, in the figure, 42 is a railway vehicle or a building limit, and 43 is a new bridge.
In this embodiment, the bridge 1 is adopted as the ground structure. However, the present invention is applied to an existing structure in which embankment (not shown) is adopted instead of the bridge 1 and the track 7 is laid on the embankment. It is also possible to do.

このように構成した本発明の橋梁の架け替え方法によって、実際に新設橋梁43を架け替える場合は、鉄道の活線状態を確保しながら施工する。
前記施工方法は、施工区間Zにおける既設軌道7の撤去と、同区間Zにおける新設橋梁43の架け替えと、橋梁下スペ−ス41の道路14の拡幅とを含んでいる。
先ず、施工区間Zの既設軌道7の撤去に際しては、既設の橋脚3,3の間に杭17を打ち込み、杭17上に型鋼を枠組みした仮橋脚18を立設し、また施工区間Zの両端部に埋設した基礎アンカ−19上に、仮支柱20を立設する。
When the newly constructed bridge 43 is actually replaced by the bridge replacement method of the present invention configured as described above, the construction is performed while securing the live line state of the railway.
The construction method includes the removal of the existing track 7 in the construction section Z, the replacement of the new bridge 43 in the section Z, and the widening of the road 14 in the space 41 under the bridge.
First, when the existing track 7 in the construction section Z is removed, the pile 17 is driven between the existing piers 3 and 3, and the temporary piers 18 that frame the steel frame are erected on the pile 17. The temporary support column 20 is erected on the foundation anchor 19 embedded in the section.

一方、前記仮橋脚18および仮支柱20の立設と前後して、それらの直上に位置する床版6の対応位置に所定の貫通穴(図示略)を形成し、各貫通穴に仮橋脚18に架設した架枠23と仮支柱20の上端部とを挿入し、これらを床版6上に突出する。
そして、それらの上端部に床版6の上方から、工事桁としてPC製または型鋼製の受梁21,22を同高位置に架設し、架設後、当該部周辺を一旦埋め戻し、鉄道車両42の走行に備える。
On the other hand, a predetermined through hole (not shown) is formed at a corresponding position of the floor slab 6 located immediately above the temporary bridge pier 18 and the temporary support column 20 upright, and the temporary pier 18 is formed in each through hole. The frame 23 and the upper end portion of the temporary support column 20 are inserted, and these are projected on the floor slab 6.
And, from the upper part of the floor slab 6 to the upper end of them, PC or mold steel receiving beams 21 and 22 are installed at the same height position as construction girders. Prepare for 42 runs.

前記PC製の受梁21の長さは、架道桁25,26の幅員よりも長尺で、その端部に受梁21の配筋が図9ように表出し、該受梁21は後述のように架け替え後の新設橋梁43の構成部材として使用され、一方、前記受梁22は新設橋梁43の架け替え後に仮支柱20と一緒に撤去される。   The length of the receiving beam 21 made of PC is longer than the width of the road girders 25 and 26, and the bar arrangement of the receiving beam 21 is exposed at the end as shown in FIG. As described above, the receiving bridge 22 is removed together with the temporary support column 20 after the new bridge 43 is replaced.

この場合、受梁21,22は各架道桁25,26の両端部に配置され、中間部に配置されていないから、多数の受梁を設置する従来の工法に比べて、受梁21の数量と設置の手間並びに重量を低減するとともに、隣接する一対の受梁21を仮橋脚18で支持しているから、仮橋脚18の設置数とその立設の手間が低減され、その分仮橋脚18,18のスパンが広がって後述する桁製作ヤ−ドの確保が容易になる。   In this case, since the receiving beams 21 and 22 are disposed at both ends of the road girders 25 and 26 and are not disposed at the intermediate portion, the receiving beams 21 are compared with the conventional method of installing a large number of receiving beams. The number and installation effort and weight are reduced, and the adjacent pair of receiving beams 21 are supported by the temporary bridge piers 18, so that the number of temporary piers 18 and the installation effort thereof are reduced. As a result, the span of 18 and 18 is widened, so that it becomes easy to secure a girder manufacturing yard described later.

このような状況の下で、既設軌道7を撤去する場合は、床版6上の既設軌道7の枕木9と締結装置11を撤去し、また枕木9を撤去後の道床8の中央部を重機(図示略)で開削し、その掘削穴24に重機を用いて架道桁25,26を個々に収容し、かつこれらを互いに向き合わせ、これを前記受梁21,22で支持する。この状況は図7のようである。   Under these circumstances, when the existing track 7 is to be removed, the sleepers 9 and the fastening devices 11 of the existing track 7 on the floor slab 6 are removed, and the central portion of the road bed 8 after the sleepers 9 are removed is heavy equipment. Cutting (not shown) is performed, and the road girders 25 and 26 are individually accommodated in the excavation hole 24 by using a heavy machine, and these are opposed to each other and supported by the receiving beams 21 and 22. This situation is as shown in FIG.

前記架道桁25,26は、図6のように略L字形断面の左右一対のPC桁で構成され、その段部25a,26aに前記レ−ル11を、架道桁25,26に設けた締結装置10を介して直接敷設する。
この状況は図8のようで、実施形態では、複数の架道桁25,26を施工区間Zに亘って連結して敷設しているが、これを長尺な単体で構成しても良く、そのようにすることで連結の手間が削減する。
As shown in FIG. 6, the overhead girder 25, 26 is composed of a pair of left and right PC girder having a substantially L-shaped cross section, and the rail 11 is provided in the step girder 25a, 26a. Laying directly through the fastening device 10.
This situation is as shown in FIG. 8, and in the embodiment, a plurality of road girders 25 and 26 are connected and laid over the construction section Z, but this may be configured as a single unit, By doing so, the time and effort of connection is reduced.

前記架道桁25,26は若干離間して対向配置され、その対向端面の間に複数の連結継手28を等間隔に配置する。
前記連結継手28は図6のように、I型鋼の両側に側板29を溶接して略箱形に形成され、該側板29にPC鋼材30を挿入可能な透孔(図示略)を形成しており、該側板29にPC鋼材30,30の一端を掛け止め、かつその他端を架道桁25,26の外端部に配置し、そのネジ部にナット(共に図示略)をねじ込んで緊締し、架道桁25,26を連結する。
The road girders 25 and 26 are opposed to each other with a slight distance therebetween, and a plurality of connecting joints 28 are arranged at equal intervals between the opposed end faces.
As shown in FIG. 6, the connecting joint 28 is formed in a substantially box shape by welding side plates 29 on both sides of the I-shaped steel, and through holes (not shown) through which the PC steel material 30 can be inserted are formed in the side plates 29. One end of the PC steel materials 30 and 30 is hooked on the side plate 29 and the other end is arranged at the outer end of the road girder 25 and 26. A nut (not shown) is screwed into the screw portion and tightened. , The road girders 25 and 26 are connected.

こうして、架道桁25,26にレール11を敷設し、これらを受梁21,22に受け渡し後、床版6上の道床8の砂利、砕石等を除去し、施工区間Zに位置する既設構造物である床版6と橋桁5、橋脚3、(盛土がある場合は盛土)を解体・撤去したところで、仮橋脚18の周辺に桁製作ヤ−ドまたはその架設ヤ−ドを確保し、主桁34,35を製作する
この場合、施工現場で前記ヤ−ドを確保できない場合は、その近接位置または工場等で主桁34,35を製作し、これを施工現場へ搬送する。
Thus, the rail 11 is laid on the road girders 25 and 26, and these are transferred to the receiving beams 21 and 22, and then the gravel, crushed stones and the like of the road bed 8 on the floor slab 6 are removed, and the existing structure located in the construction section Z After dismantling and removing the floor slab 6, bridge girder 5, pier 3, and (filling if there is embankment), secure a girder manufacturing yard or its construction yard around the temporary pier 18 In this case, when the yarn cannot be secured at the construction site, the main girders 34 and 35 are produced at the close position or at a factory or the like and transported to the construction site.

そして、前記架道桁25,26の敷設と前後し、または前記床版6および橋桁5の解体・撤去後、仮支柱20,20より内側の地盤2に杭31を打ち込む。
前記杭31上に基礎アンカ−32を構築し、該アンカ−32上に橋台33,33を立設し、その上端部を架道桁25,26の前後側端部直下に位置付け、それらの間に左右一対のPC製の主桁34,35を支持する。
Then, the pile 31 is driven into the ground 2 on the inner side of the temporary support columns 20 and 20 after the construction of the road girders 25 and 26, or after the floor slab 6 and the bridge girder 5 are disassembled and removed.
A foundation anchor 32 is constructed on the pile 31, and abutments 33 and 33 are erected on the anchor 32, and the upper end portions thereof are positioned directly below the front and rear end portions of the road girders 25 and 26. A pair of left and right PC main girders 34 and 35 are supported.

前記桁製作ヤ−ドで主桁34,35を製作後、その架設ヤ−ドにおいて重機で吊り上げまたはジャッキアップし、受梁21および横桁38の外端部に位置付ける。この状況は図9のようである。
前記主桁34,35は略縦長矩形断面に形成され、その中間部の外面に凹溝34a,35aが形成され、その桁高Hは架道桁25,26の桁高の略3倍に形成され、その剛性を増大させるとともに、その長さは架道桁25,26の略3倍長で、橋台33,33間のスパンと略同長に形成し、その上端部を架道桁25,26の上端部と略同高に配置している
After the main girders 34 and 35 are produced by the girder production yarn, they are lifted or jacked up by heavy machinery at the installation yard and positioned at the outer ends of the receiving beam 21 and the horizontal girder 38. This situation is as shown in FIG.
The main girders 34 and 35 are formed in a substantially vertically long rectangular cross section, and concave grooves 34a and 35a are formed on the outer surface of the intermediate portion thereof. The girder height H is formed to be approximately three times the girder height of the road girders 25 and 26. In addition to increasing the rigidity thereof, the length thereof is approximately three times the length of the bridge girders 25 and 26, and is formed to be approximately the same length as the span between the abutments 33 and 33, and the upper end thereof is formed on the road girders 25 and 26. 26 is arranged at substantially the same height as the upper end of 26.

前記主桁34,35は、その前後端部と受梁21の対向位置に略矩形の大小の連結窓36,37が形成され、これらの連結窓36,37に主桁34,35の配筋(図示略)が縦横に表出し、一方、受梁21と横梁38の両端部に配筋が表出している。   The main girders 34 and 35 are formed with substantially rectangular connecting windows 36 and 37 at positions opposite to the front and rear ends thereof and the receiving beam 21, and the reinforcing bars of the main girders 34 and 35 are arranged in these connecting windows 36 and 37. (Not shown) is exposed vertically and horizontally, while reinforcing bars are exposed at both ends of the receiving beam 21 and the horizontal beam 38.

そこで、主桁34,35に受梁21と横梁38とを連結する場合は、連結窓36,37の配筋(図示略)に、受梁21の端部に表出した配筋(図9参照)と、横梁38の両端部に表出した配筋(図示略)とを係合し、かつ各連結窓36,37にコンクリ−トを打設して、これらを一体に連結する。   Therefore, when the receiving beam 21 and the horizontal beam 38 are connected to the main girders 34 and 35, the reinforcing bars (not shown) of the connecting windows 36 and 37 are arranged at the end of the receiving beam 21 (FIG. 9). And a bar arrangement (not shown) exposed at both ends of the cross beam 38, and a concrete is placed in each of the connecting windows 36 and 37 to connect them together.

前記連結状況は図10および図11のようで、軌道7を構成する架道桁25,26が主桁34,35の上部に位置する上路構造であるが、施工条件に応じて中路または下路構造を採用することも可能である。   The connection state is as shown in FIG. 10 and FIG. 11 and is an upper road structure in which the road girders 25 and 26 constituting the track 7 are positioned above the main girders 34 and 35, but depending on the construction conditions, the middle road or the lower road It is also possible to adopt a structure.

こうして、主桁34,35に受梁21と横梁38とを連結し、主桁34,35の荷重を橋台33に受け渡したところで、前記施工区間Zの仮橋脚18と仮支柱20と架枠23とを解体・撤去し、主桁34,35直下の橋梁下スペ−ス41を開放かつ拡張する。
この場合、実施形態では主桁34,35の両端部を橋台33で支持し、その中間部に橋脚や橋台を配置していないから、その分橋梁下スペ−ス41が有効に拡張される。
実施形態では、橋梁下スペ−ス41が架け替え前の橋脚3a,3aの間隔の略4倍に拡張され、当該スペ−ス41を道路スペ−スに充当して、該スペ−スに二車線の車道14と歩道16とが建設される。
In this way, the receiving beam 21 and the lateral beam 38 are connected to the main girders 34 and 35, and when the loads of the main girders 34 and 35 are transferred to the abutment 33, the temporary pier 18, the temporary support 20 and the frame 23 in the construction zone Z are obtained. Are disassembled and removed, and the space 41 under the bridge just below the main girders 34 and 35 is opened and expanded.
In this case, in the embodiment, both ends of the main girders 34 and 35 are supported by the abutment 33, and no bridge pier or abutment is arranged in the middle thereof, so that the space 41 below the bridge is effectively expanded correspondingly.
In the embodiment, the space 41 under the bridge is expanded to about four times the distance between the piers 3a and 3a before the replacement, and the space 41 is allocated to the road space, and the space is added to the space. A lane road 14 and a sidewalk 16 are constructed.

このように本発明の橋梁の架け替えは、レ−ル11を現位置に存置したまま、既設の橋梁1を、架道桁25,26、受梁21、横桁38、主桁34,35等で構成する新たな橋梁に架け替えているから、従来の仮線施工や桁横取架設工法を採ることなく、施工時における鉄道車両42の運行を確保でき、しかも仮線施工や桁横取架設工法における仮線用地の確保や、広大な桁製作ヤ−ドおよび架設ヤ−ドの確保を要せず、工費の高騰と設備費の低減を図れる。   As described above, the bridge replacement according to the present invention is performed by replacing the existing bridge 1 with the bridge girder 25, 26, the receiving beam 21, the cross beam 38, and the main girder 34, 35 with the rail 11 remaining at the current position. Since it has been replaced with a new bridge composed of, etc., it is possible to secure the operation of the railway vehicle 42 at the time of construction without adopting the conventional temporary line construction and girder horizontal construction method. It is not necessary to secure a temporary line site in the construction method, and to secure a large girder manufacturing and construction yard, so that the construction cost can be increased and the equipment cost can be reduced.

しかも、前記架け替えに際しては、軌道桁である架道桁25,26を仮設工事桁として利用するから、新たな工事桁を要せず合理的かつ安価に施工できるとともに、架け替え後は橋梁の構成部材として利用するため、従来の工事桁のように架け替え後の解体・撤去を要さず、その分工期を短縮し工費を低減できる。   In addition, since the road girders 25 and 26, which are track girders, are used as temporary construction girders, the construction can be carried out rationally and inexpensively without the need for new construction girders. Because it is used as a component, it does not require dismantling / removal after replacement, unlike conventional construction girders, thereby shortening the construction period and reducing construction costs.

こうして架け替えた新設橋梁43は、架道を構成する架道桁25,26と、受梁21および横桁38と、主桁34,35と、橋台33とで構成され、前記主桁34,35のスパン方向の端部に受梁21,22と横桁38とを架設し、これらを一体に連結するとともに、前記主桁34,35のスパン方向の最外側端部のみ橋台33または橋脚で支持している   The newly constructed bridge 43 thus replaced is composed of the road girders 25 and 26 constituting the roadway, the receiving beam 21 and the horizontal girder 38, the main girders 34 and 35, and the abutment 33, and the main girder 34, The spans 21 and 22 and the cross girder 38 are installed at the ends in the span direction of 35, and these are integrally connected, and only the outermost end in the span direction of the main girders 34 and 35 is connected to the abutment 33 or the pier. Supporting

したがって、桁材である受梁21,22と横桁38の使用個数を低減し、その設置の手間を軽減して、工期の短縮化と工費の低減並びに軽量化を図れるとともに、受梁21を架設する仮橋脚18の使用個数とその設置の手間を軽減し、また主桁下の橋台33または橋脚スパンを拡張して、当該スペ−スの利用範囲を拡大して、例えば主桁下の道路等の拡幅に応じられる。
なお、前述の実施形態は受梁21,22と主桁34,35とをPC桁で構成し、それらを前述のように連結しているが、受梁21,22と主桁34,35とをRC桁で構成し、それらを連結金具とボルト・ナット等を用いて連結することも可能である。
Accordingly, the number of receiving beams 21 and 22 and the horizontal beams 38, which are girders, can be reduced, the labor of installation can be reduced, the construction period can be shortened, the construction cost can be reduced, and the weight can be reduced. The number of temporary piers 18 to be installed and the labor of installing them are reduced, and the abutment 33 or pier span under the main girder is expanded to expand the range of use of the space, for example, the road under the main girder. It can be adapted to widening such as.
In the above-described embodiment, the receiving beams 21 and 22 and the main girders 34 and 35 are configured by PC girders and are connected as described above. However, the receiving beams 21 and 22 and the main girders 34 and 35 are connected to each other. It is also possible to configure the RC girder and connect them using a connecting bracket and bolts / nuts.

このように本発明の橋梁の構造およびその架け替え方法は、例えば工事を活線下で行なえ、かつその際軌道桁や仮設時の受梁を工事桁として利用し、利用後は新設橋梁の構造部材として利用して、それらの解体・撤去の不合理を解消し、施工の合理化と工期の短縮化並びに工費の低減を図るとともに、構成を簡潔化して新設橋梁の軽量化を図り、更に桁製作ヤ−ドまたは架設ヤ−ドの確保を容易かつ縮小し得るようにしたから、例えば鉄道橋梁の架け替えまたは橋梁下スペ−スの拡張ないし道路の拡幅に好適である。   As described above, the structure of the bridge of the present invention and the method of replacing the bridge, for example, can be performed under a live line, and the track girder or the temporary receiving beam is used as the construction girder. It is used as a member to eliminate the unreasonableness of dismantling and removal, streamline construction, shorten construction period and reduce construction costs, simplify the structure and reduce the weight of the new bridge, and manufacture girders Since the securing of the yard or the erection yard can be easily and reduced, it is suitable for, for example, replacement of a railway bridge, expansion of a space under the bridge, or widening of a road.

本発明の施工前の既設橋梁の状況を示す正面図である。It is a front view which shows the condition of the existing bridge before construction of this invention. 図1の平面図で、若干拡大して示している。In the plan view of FIG. 1, it is shown slightly enlarged. 本発明の施工前の軌道の要部を示す断面図である。It is sectional drawing which shows the principal part of the track | orbit before construction of this invention. 本発明を施工した新設橋梁の状況を示す正面図である。It is a front view which shows the condition of the new bridge which constructed this invention. 図4の平面図で、若干拡大して示している。In the plan view of FIG. 4, it is shown slightly enlarged. 本発明に適用した架道桁の組み立て状態を示す斜視図である。It is a perspective view which shows the assembly state of the road girder applied to this invention.

本発明による施工状態を示す断面図で、既設軌道を撤去し、同位置に受梁を敷設し、新設軌道の架道桁を設置している状況を示している。It is sectional drawing which shows the construction state by this invention, and has shown the condition where the existing track was removed, the receiving beam was laid in the same position, and the road girder of the new track was installed. 本発明による施工状態を示す断面図で、既設軌道を撤去し、同位置に受梁を敷設し、新設軌道の架道桁を設置後、レ−ルを敷設している状況を示している。In sectional drawing which shows the construction state by this invention, the existing track is removed, the receiving beam is laid in the same position, and the state where the rail is laid is shown after installing the road girder of the new track. 本発明による施工状態を示す断面図で、既設軌道を撤去し、同位置に受梁を敷設し、新設軌道の架道桁を設置しレ−ルを敷設後、受梁に主桁を連結する状況を示している。In the sectional view showing the construction state according to the present invention, the existing track is removed, the receiving beam is installed at the same position, the road girder of the new track is installed, the rail is installed, and the main beam is connected to the receiving beam. Indicates the situation. 図5のA−A線に沿う拡大断面図である。It is an expanded sectional view which follows the AA line of FIG.

図5のB−B線に沿う拡大断面図である。It is an expanded sectional view which follows the BB line of FIG. 図10のC−C線に沿う部分断面図である。It is a fragmentary sectional view which follows the CC line of FIG. 本発明による施工状態を示す正面図で、施工区間に複数の仮橋脚を立設し、既設橋梁を撤去し、新設橋梁の架道桁を敷設している状況を示している。It is the front view which shows the construction state by this invention, and has shown the condition where several temporary bridge piers are erected in the construction section, the existing bridge is removed, and the bridge girder of the new bridge is laid. 本発明による施工状態を示す正面図で、施工区間に複数の仮橋脚を立設し、既設橋梁を撤去し、新設橋梁の架道桁を敷設後、仮支柱と橋台とを立設している状況を示している。In the front view showing the construction state according to the present invention, a plurality of temporary piers are erected in the construction section, the existing bridge is removed, and the bridge girder of the new bridge is laid, and then the temporary support column and the abutment are erected. Indicates the situation. 本発明による施工状態を示す正面図で、施工区間に複数の仮橋脚を立設し、既設橋梁を撤去し、新設橋梁の架道桁を敷設後、仮支柱と橋台とを立設し、橋台間に主桁を架設している状況を示している。In the front view showing the construction state according to the present invention, a plurality of temporary piers are erected in the construction section, the existing bridges are removed, and the bridge girder of the new bridge is laid, then the temporary columns and abutments are erected, It shows the situation where the main girder is installed between them.

符号の説明Explanation of symbols

1 地上構造物(既設橋梁)
3 既設橋脚
5 既設橋桁
6 既設架道桁(床版)
7 既設架道(軌道)
11 レ−ル
21 桁材(受梁)
25,26 新設架道桁
28 連結継手
33 橋台
34,35 主桁
38 桁材(横桁)
43 新設橋梁
Z 施工区間
1 Ground structure (existing bridge)
3 Existing pier 5 Existing bridge girder 6 Existing road girder (floor)
7 Existing roadway (track)
11 Rail 21 Girder (receiving beam)
25, 26 Newly installed girder 28 Connection joint 33 Abutment 34, 35 Main girder 38 Girder material (horizontal girder)
43 New Bridge Z Construction Section

Claims (10)

新設橋梁の新設架道桁と、該架道桁の外側に配置する主桁と、該主桁の間に架設し、かつ前記架道桁を支持可能な桁材と、を備えた橋梁の構造において、新設架道桁を新設橋梁の工事桁として、また前記桁材を新設架道桁の受梁としてそれぞれ利用可能にするとともに、それらの利用後は残置して新設橋梁を構成したことを特徴とする橋梁の構造。   A bridge structure comprising a newly installed road girder of a new bridge, a main girder arranged outside the road girder, and a girder constructed between the main girder and capable of supporting the road girder The new bridge girder can be used as a construction girder for the new bridge girder, and the girder material can be used as a receiving girder for the new road girder, and the new bridge girder can be left behind to form a new bridge. Bridge structure. 左右一対の新設架道桁を連結継手を介して連結し、新設架道を構成した請求項1記載の橋梁の構造。   The bridge structure according to claim 1, wherein a pair of left and right newly installed road girders are connected via a connecting joint to form a new road. 前記新設架道桁を桁材上に載架した請求項1記載の橋梁の構造。   The bridge structure according to claim 1, wherein the newly installed road girder is mounted on a girder. 前記新設架道桁のスパン方向の端部を前記桁材で支持し、該桁材と前記主桁とを連結するとともに、前記主桁を新設架道桁よりも長尺に形成し、該主桁をスパン方向の最外側端部で支持した請求項1記載の橋梁の構造。   The end of the new road girder in the span direction is supported by the girder, the girder and the main girder are connected, and the main girder is formed longer than the new road girder. The bridge structure according to claim 1, wherein the girder is supported at the outermost end portion in the span direction. 前記桁材と主桁とをPC桁またはRC桁で構成した請求項1記載の橋梁の構造。   The bridge structure according to claim 1, wherein the girder and the main girder are PC girder or RC girder. 前記新設架道桁を軌道桁とし、前記新設架道桁に直接レ−ルを敷設した請求項1記載の橋梁の構造。   The bridge structure according to claim 1, wherein the new road girder is a track girder, and a rail is directly laid on the new road girder. 既設構造物に沿って仮橋脚を立設後、新設架道桁を施工し、該新設架道桁を前記仮橋脚に支持させた後、前記既設構造物を解体・撤去し、前記新設架道桁に沿って橋台または橋脚を立設し、これらの間に主桁を架設するとともに、該主桁に新設架道桁を支持させた後、前記仮橋脚を解体・撤去する橋梁の架け替え方法において、前記仮橋脚を新設架道桁の端部に立設し、該仮橋脚に架設した桁材に前記新設架道桁を支持し、該桁材を受梁として利用し、その利用後に新設橋梁の構成部材として残置するとともに、前記新設架道桁を新設橋梁の工事桁として利用し、その利用後に新設橋梁の構成部材として残置することを特徴とする橋梁の架け替え方法。   After the temporary bridge pier is erected along the existing structure, a new road girder is constructed, and after the new road girder is supported by the temporary bridge pier, the existing structure is disassembled and removed, and the new road A method of replacing a bridge in which an abutment or pier is erected along a girder, a main girder is installed between them, and a new road girder is supported by the main girder, and then the temporary pier is disassembled and removed. In this case, the temporary bridge pier is erected at the end of a newly installed bridge girder, the newly installed road girder is supported by a girder built on the temporary bridge pier, and the girder is used as a receiving beam. A method for replacing a bridge, wherein the bridge is left as a structural member of the bridge, and the new road girder is used as a construction girder of the new bridge and left as a structural member of the new bridge after the use. 前記既設構造物を撤去後、新設架道桁の外側で、かつ前記施工区間の両端部に橋台または橋脚を立設し、該橋台または橋脚間に前記主桁を架設し、該主桁に桁材の両端部を連結し、主桁に新設架道桁を支持させた後、前記施工区間の仮橋脚を解体・撤去する請求項7記載の橋梁の架け替え方法。   After removing the existing structure, abutments or piers are erected outside the newly constructed girder and at both ends of the construction section, the main girder is installed between the abutments or piers, and the girder is installed on the main girder. The bridge replacement method according to claim 7, wherein both ends of the material are connected, and the new girder girder is supported by the main girder, and then the temporary pier of the construction section is disassembled and removed. 単一の仮橋脚に二つの桁材を架設し、該桁材に隣接する新設架道桁の端部を支持させる請求項7記載の橋梁の架け替え方法。   The bridge replacement method according to claim 7, wherein two girder members are installed on a single temporary pier, and an end portion of a new road girder adjacent to the girder material is supported. 前記既設構造物を撤去後、その撤去スペ−スを桁製作ヤ−ドまたは桁材の架設ヤ−ドに利用する請求項7記載の橋梁の架け替え方法。   8. The method of replacing a bridge according to claim 7, wherein after the existing structure is removed, the removed space is used as a girder manufacturing yard or a girder erection yard.
JP2004299157A 2004-10-13 2004-10-13 Bridge structure and its replacement method Active JP4477467B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004299157A JP4477467B2 (en) 2004-10-13 2004-10-13 Bridge structure and its replacement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004299157A JP4477467B2 (en) 2004-10-13 2004-10-13 Bridge structure and its replacement method

Publications (2)

Publication Number Publication Date
JP2006112086A true JP2006112086A (en) 2006-04-27
JP4477467B2 JP4477467B2 (en) 2010-06-09

Family

ID=36380837

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004299157A Active JP4477467B2 (en) 2004-10-13 2004-10-13 Bridge structure and its replacement method

Country Status (1)

Country Link
JP (1) JP4477467B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007321473A (en) * 2006-06-01 2007-12-13 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Rebuilding method for bridge
JP2009052306A (en) * 2007-08-28 2009-03-12 Kajima Corp Construction method for replacing bridge girder
CN103938512A (en) * 2014-04-30 2014-07-23 陕西运通公路设计咨询有限公司 Reverse construction method of newly built road with existing expressway in underneath penetrating manner

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485270A (en) * 2013-10-11 2014-01-01 北京交通大学 Setting technology of second-phase pre-stressed tendons in straddle type single-traffic-track girder bridge
CN104264591B (en) * 2014-10-30 2016-05-11 中铁六局集团有限公司 In the construction method of top, the larger region of circuit discrepancy in elevation bridge
CN104652299B (en) * 2015-02-05 2016-05-11 中铁六局集团有限公司 Construction method is shifted out in the whole hole of a kind of existing bridges and culverts of electric railway
CN106758886B (en) * 2016-11-24 2018-07-24 沈阳铁道勘察设计院有限公司 A kind of method of the existing bridges and culverts structure of novel dismounting

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007321473A (en) * 2006-06-01 2007-12-13 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Rebuilding method for bridge
JP4671912B2 (en) * 2006-06-01 2011-04-20 三菱重工鉄構エンジニアリング株式会社 Bridge replacement method
JP2009052306A (en) * 2007-08-28 2009-03-12 Kajima Corp Construction method for replacing bridge girder
CN103938512A (en) * 2014-04-30 2014-07-23 陕西运通公路设计咨询有限公司 Reverse construction method of newly built road with existing expressway in underneath penetrating manner

Also Published As

Publication number Publication date
JP4477467B2 (en) 2010-06-09

Similar Documents

Publication Publication Date Title
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
KR101344063B1 (en) The construction method of steel-concrete underpass
JP6180376B2 (en) Main girder provision method in composite girder floor slab replacement method, composite girder floor slab replacement method, and main girder provision structure in composite girder floor slab replacement method
JP5405337B2 (en) Construction method of railway RC ramen structure viaduct
KR100891961B1 (en) The construction infrastructure the use road the martial art as a matter of bridge of the bridge which is old in the railroad or the railroad respects the induction event a method of construction which shifts the bridge and the system
JP3844743B2 (en) Box girder bridge structure and its construction method
JP2004137686A (en) Composite panel structure, panel bridge structure and construction method for continuous composite girder bridge
CN108547209B (en) Single-hole prefabricated hollow slab bridge without expansion joint and construction method thereof
JP4477467B2 (en) Bridge structure and its replacement method
JP3737475B2 (en) Box girder bridge structure and construction method
KR102105230B1 (en) Railroad bridge construction method for keeping preexistence railroad track and rail service
JP2020090785A (en) Widening structural body, widening structure, floor slab widening construction method, and floor slab renewal method
KR20040004819A (en) Method for changing steel bridge of supporting rail into concreat bridge
JPH083937A (en) Repair method for existing bridge
KR101187282B1 (en) Railway bridge constructing method using 2 post type abutment structure
JP4901178B2 (en) Steel / concrete composite rigid frame bridge construction method
KR101270947B1 (en) Deck repairing construction method of bridge using precast concrete slab
JP5043879B2 (en) How to install width expansion materials for road bridges
JP4585614B1 (en) Method for constructing synthetic steel slab bridge, ribbed steel slab, and synthetic steel slab bridge
JP4685341B2 (en) Viaduct construction method
JP4540632B2 (en) Erection girder
JP2000008304A (en) Pedestal for rail road work beam and execution method of pedestal for rail road work beam
JP2018178588A (en) Bridge construction method
JP2014134060A (en) Floor slab replacement method
JP4627383B2 (en) Replaced steel deck bridge

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070821

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090618

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090630

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090826

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20091215

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100212

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20100309

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20100311

R150 Certificate of patent or registration of utility model

Ref document number: 4477467

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130319

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140319

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313532

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250