JP2000104220A - Erection of combined truss bridge - Google Patents

Erection of combined truss bridge

Info

Publication number
JP2000104220A
JP2000104220A JP28868298A JP28868298A JP2000104220A JP 2000104220 A JP2000104220 A JP 2000104220A JP 28868298 A JP28868298 A JP 28868298A JP 28868298 A JP28868298 A JP 28868298A JP 2000104220 A JP2000104220 A JP 2000104220A
Authority
JP
Japan
Prior art keywords
bridge
truss girder
concrete
steel truss
erection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP28868298A
Other languages
Japanese (ja)
Inventor
Katsuyoshi Nakanishi
克佳 中西
Nobuaki Takiguchi
伸明 滝口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
NKK Corp
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NKK Corp, Nippon Kokan Ltd filed Critical NKK Corp
Priority to JP28868298A priority Critical patent/JP2000104220A/en
Publication of JP2000104220A publication Critical patent/JP2000104220A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To shorten the term of works by hanging steel truss beams from bridge piers, mounting the moving forms on top chords and bottom coards of the beam, applying the concrete, and hanging the beam on the top chords by a crane. SOLUTION: A steel truss beam is hung by one span from a bridge piear, the moving forms are installed on the truss top chord 3 and the truss bottom chord 4 of the beam, and the concrete is applied to the forms 10 to construct the top and bottom concrete floor boards. Then a beam is hung between the span and a next span by the crane 12, and the concrete is applied to the form 10 to construct the top and bottom concrete floor boards. Then the crane 12 is moved to hang the beam of a next span by the crane 12, and the concrete is applied to the form 10 to construct the top and bottom concrete floor boards. The same processes are repeated until the spans of the bridge are combined by the beams. Further the fixed forms are installed while removing the execution equipment by the crane 12, and the concrete is applied to construct the top concrete floor board. Whereby the term of works can be shortened.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、張出し架設が可能
な複合トラス橋の構造、および架設工法に関するもので
ある。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a structure of a composite truss bridge which can be overhanged and a method of erection.

【0002】[0002]

【従来の技術】本発明に関する先行技術として、特開平
10―140525号記載の発明が知られている。
2. Description of the Related Art As a prior art relating to the present invention, Japanese Patent Application Laid-Open
The invention described in No. 10-140525 is known.

【0003】当該発明は、張り出し架設の可能な複合ト
ラス橋の一形態として、図19に示すように複数個のコ
ンクリートウェブを有する床版を、鋼トラスと接合して
構成したものがある。
In the present invention, as one form of a composite truss bridge which can be overhanged, a slab having a plurality of concrete webs is joined to a steel truss as shown in FIG.

【0004】これにより、桁が剛となり、張出し架設が
可能となる。また、従来の橋面を形成するプレストレス
トコンクリート床版とこの下面に接合したトラス上弦材
を含まない鋼トラス桁からなる橋脚と剛結されている複
合トラス桁よりも、橋の支間長が増大しても鋼材の大型
化を防止することができ、資材の輸送が便利となってい
る。
[0004] Thus, the girder becomes rigid, and it becomes possible to erection erection. In addition, the span length of the bridge is larger than that of a conventional composite truss girder that is rigidly connected to a pier consisting of a prestressed concrete slab that forms the bridge surface and a steel truss girder that does not include the truss upper chords joined to the lower surface. However, it is possible to prevent the steel material from being enlarged, and it is convenient to transport the material.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、従来技
術には以下に掲げる問題点があった。
However, the prior art has the following problems.

【0006】従来技術においては、鋼材のみでトラス構
造を形成していない。そのため、床版の剛性を大きくす
ることで桁全体の剛性を上昇させる必要が生じ、床版断
面を大型・複雑化せざるを得なくなる。また、コンクリ
ート硬化以前においてトラス構造を形成していないた
め、コンクリート床版を橋脚上のクレーンにて吊り上げ
た状態で接合、あるいは型枠を橋脚上のクレーンにて吊
り上げた状態でコンクリートを打設する必要がある。
In the prior art, a truss structure is not formed only by steel materials. Therefore, it is necessary to increase the rigidity of the entire slab by increasing the rigidity of the floor slab, and the cross section of the floor slab must be increased in size and complexity. Also, since the truss structure was not formed before concrete hardening, the concrete slab was joined with a crane above the pier and joined, or the concrete was poured while the formwork was lifted with a crane above the pier. There is a need.

【0007】したがって、単位長さ当たりの重量が大き
な従来技術においては、一度に、長い区間の床版を接合
あるいは長い区間のコンクリート打設が困難なため、工
期が長くなるという問題点があった。
Therefore, in the prior art having a large weight per unit length, there is a problem that it is difficult to join a long section of slab or to cast concrete in a long section at a time, so that the construction period becomes long. .

【0008】本発明は、斯かる問題点を鑑みてなされた
ものであり、その目的とするところは、工期を短縮する
ことができる複合トラス橋の架設方法を提供する点にあ
る。
The present invention has been made in view of such a problem, and an object of the present invention is to provide a method of erection of a composite truss bridge capable of shortening a construction period.

【0009】[0009]

【課題を解決するための手段】本発明は上記課題を解決
すべく以下に掲げる構成とした。
SUMMARY OF THE INVENTION The present invention has the following arrangement to solve the above-mentioned problems.

【0010】請求項1記載の発明の要旨は、鋼製の上弦
材、下弦材及び斜材を有する鋼トラス桁と、該鋼トラス
桁の上面に構築された橋面を形成するコンクリート床版
とを備えた複合トラス橋の架設方法であって、前記複合
トラス桁が架設される、立設された2つの橋脚から架設
方向へ鋼トラス桁を1径間張り出す工程と、張り出し
た鋼トラス桁の上弦材、および下弦材に移動型枠を設置
し、該移動型枠にコンクリートを打設して床版を構築す
る工程と、該工程と併行して、前記上弦材に、橋軸
方向へ移動可能に設置した架設用移動クレーンを用い
て、次径間の鋼トラス桁を張り出す工程とを備え、前
記鋼トラス桁が繋がるまで前記工程と前記工程とを
行うことを特徴とする複合トラス橋の架設方法に存す
る。請求項2記載の発明の要旨は、鋼製の上弦材、下弦
材及び斜材を有する鋼トラス桁と、該鋼トラス桁の上面
に構築された橋面を形成するコンクリート床版とを備え
た複合トラス橋の架設方法であって、前記複合トラス桁
が架設される、立設された2つの橋脚から架設方向へ鋼
トラス桁を1径間張り出す工程と、張り出した鋼トラ
ス桁の上弦材、および下弦材に移動型枠を設置し、該移
動型枠にコンクリートを打設して床版を構築する工程
と、前記コンクリートが硬化した後、床版にプレストレ
ス力を導入する工程と、該工程と併行して、前記上
弦材に、橋軸方向へ移動可能に設置した架設用移動クレ
ーンを用いて、次径間の鋼トラス桁を張り出す工程と
を備え、前記鋼トラス桁が繋がるまで前記工程乃至前
記工程を繰り返し行うことを特徴とする複合トラス橋
の架設方法に存する。請求項3記載の発明の要旨は、鋼
製の上弦材、下弦材及び斜材を有する鋼トラス桁と、該
鋼トラス桁の上面に構築された橋面を形成するコンクリ
ート床版とを備えた複合トラス橋の架設方法であって、
前記複合トラス桁が架設される、立設された2つの橋脚
から架設方向へ鋼トラスを1径間張り出す工程と、張
り出した鋼トラス桁の上弦材、および下弦材に移動型枠
を設置し、該移動型枠にコンクリートを打設して床版を
構築する工程と、前記コンクリートが硬化した後、床
版にプレストレス力を導入する工程と、前記工程及
び工程と併行して、前記上弦材に、橋軸方向へ移動可
能に設置した架設用移動クレーンを用いて、次径間の鋼
トラス桁を張り出す工程とを備え、前記鋼トラス桁が
繋がるまで前記工程乃至前記工程を繰り返し行うこ
とを特徴とする複合トラス橋の架設方法に存する。請求
項4記載の発明の要旨は、前記鋼トラス桁の張り出し
を、前記橋脚をはさんで左右対称に行うことを特徴とす
る請求項1乃至3に記載の複合トラス橋の架設方法に存
する。請求項5記載の発明の要旨は、請求項1乃至4に
記載の複合トラス橋の架設方法により架設されたことを
特徴とする複合トラス橋に存する。
[0010] The gist of the present invention is to provide a steel truss girder having a steel upper chord, a lower chord and a diagonal member, and a concrete slab forming a bridge surface constructed on the upper surface of the steel truss girder. A method of erection of a composite truss bridge comprising: a step of extending a steel truss girder by one span in the direction of erection from two erected piers on which the composite truss girder is erected; Installing a movable formwork on the upper chord material and the lower chord material, placing concrete in the movable formwork and constructing a floor slab, and in parallel with the step, on the upper chord material in a bridge axis direction. A step of projecting a steel truss girder of the next span using a mobile crane installed movably, and performing the steps and the steps until the steel truss girder is connected. It depends on how to build the bridge. The gist of the invention according to claim 2 includes a steel truss girder having steel upper chord, lower chord and diagonal, and a concrete slab forming a bridge surface constructed on the upper surface of the steel truss girder. A method of erection of a composite truss bridge, comprising: a step of extending a steel truss girder by one span in a direction of erection from two erected piers on which the composite truss girder is erected; , And installing a movable formwork on the lower chord material, a step of constructing a floor slab by casting concrete in the movable formwork, and a step of introducing a prestressing force to the floor slab after the concrete has hardened. In parallel with this step, a step of projecting a steel truss girder of the next diameter using an erecting moving crane installed movably in the bridge axis direction on the upper chord member is provided, and the steel truss girder is connected. Up to the above steps are repeated. In the construction method of a composite truss bridge. The gist of the invention according to claim 3 includes a steel truss girder having steel upper chord, lower chord and diagonal, and a concrete slab forming a bridge surface constructed on the upper surface of the steel truss girder. A method of erection of a composite truss bridge,
The composite truss girder is erected, a step of extending a steel truss for one span in the erection direction from the two erected piers, and installing a movable formwork on the upper chord and the lower chord of the overhanging steel truss girder. A step of placing concrete in the movable formwork to construct a floor slab; a step of introducing a prestressing force to the floor slab after the concrete is hardened; A step of projecting a steel truss girder of the next span using a erection moving crane installed movably in the bridge axis direction on the material, and repeatedly performing the above-described steps from the above until the steel truss girder is connected The present invention resides in a method for erection of a composite truss bridge. The gist of the invention according to claim 4 lies in the method of erection of a composite truss bridge according to claims 1 to 3, wherein the overhang of the steel truss girder is performed symmetrically across the pier. The gist of the invention described in claim 5 resides in a composite truss bridge which is constructed by the method for constructing a composite truss bridge according to any one of claims 1 to 4.

【0011】なお、各請求項における、、………の
数字は各請求項において同じ工程を示すものではない。
In the claims, the numerals... Do not indicate the same steps in the claims.

【0012】[0012]

【発明の実施の形態】以下、本発明の実施の形態を図面
に基づいて詳細に説明する。
Embodiments of the present invention will be described below in detail with reference to the drawings.

【0013】図1及び図2に示すように、本実施の形態
に係る複合トラス橋は、地盤Gに立設された橋脚P,P
に架設された鋼トラス桁Cと、この鋼トラス桁Cに構築
された橋面を形成する上コンクリート床版1及び下コン
クリート床版2とを備えたものである。
As shown in FIGS. 1 and 2, the composite truss bridge according to the present embodiment has piers P, P erected on the ground G.
And a concrete slab 1 and a lower concrete slab 2 forming a bridge surface constructed on the steel truss girder C.

【0014】鋼トラス桁Cは、トラス上弦材3、トラス
下弦材4及びトラス斜材5から概略構成されている。
The steel truss girder C is roughly composed of a truss upper chord 3, a truss lower chord 4, and a truss slant 5.

【0015】上コンクリート床版1及び下コンクリート
床版2は、トラス上弦材3及びトラス下弦材4の上を移
動する移動型枠10にコンクリートが打設され、トラス
上弦材3、トラス下弦材4に各別に剛結合されたもの
で、双方ともプレストレスが導入されている。図中、符
号7がプレストレスケーブルである。上面には舗装6が
施工されている。
In the upper concrete slab 1 and the lower concrete slab 2, concrete is cast into a movable form 10 which moves on the truss upper chord 3 and the truss lower chord 4, and the truss upper chord 3 and the truss lower chord 4 are laid. Each is rigidly connected, and both have a prestress. In the figure, reference numeral 7 denotes a prestress cable. Pavement 6 is constructed on the upper surface.

【0016】架設用移動クレーン12は、図13及び図
14に示すようにトラス上弦材3に敷設されたクレーン
用軌条16上を走行する。クレーン用軌条16は、図1
5及び図16に示すように、レール16aと、このレー
ル16aの下面から下方に延びる固定部16bとから構
成されている。斯かる軌条16をトラス上弦材3に固定
するには、図17及び図18に示す、トラス上弦材3に
立設された鋼管1aに固定部16aを挿入すれば良い。
なお、両図とも、軌条16を撤収した状態を示してい
る。すなわち、本実施の形態においては後述のごとく、
当該コンクリートの打設前において軌条16を敷設し、
コンクリート打設と、当該次径間の鋼トラス桁Cの構築
とを併行して行う。そして、架設用移動クレーン12の
回収後に軌条16aを撤収する。
The construction crane 12 travels on a crane rail 16 laid on the truss upper chord 3 as shown in FIGS. The crane rail 16 is shown in FIG.
As shown in FIG. 5 and FIG. 16, it is composed of a rail 16a and a fixing portion 16b extending downward from the lower surface of the rail 16a. In order to fix the rail 16 to the truss upper chord 3, the fixing portion 16 a may be inserted into a steel pipe 1 a erected on the truss upper chord 3 as shown in FIGS. 17 and 18.
Both figures show a state in which the rail 16 has been withdrawn. That is, in the present embodiment, as described later,
Before laying the concrete, lay rails 16,
The concrete placing and the construction of the steel truss girder C of the next diameter are performed in parallel. Then, the rail 16a is withdrawn after the collection mobile crane 12 is collected.

【0017】なお、図2i)は下コンクリート床版2が
ある断面、図2ii)は下コンクリート床版2がない断面
を示している。
FIG. 2i) shows a cross section with the lower concrete slab 2, and FIG. 2ii) shows a cross section without the lower concrete slab 2.

【0018】次に、図3に示す複合トラス橋Bの架設方
法を図3〜図12を用いて説明する。なお、図3に示す
複合トラス橋Bは、図1及び図2に示すものと、鋼下弦
材4がアーチ上になっている点で異なるが、他の構成要
素は同様である。
Next, a method of erection of the composite truss bridge B shown in FIG. 3 will be described with reference to FIGS. The composite truss bridge B shown in FIG. 3 is different from the composite truss bridge B shown in FIGS. 1 and 2 in that the steel lower chord 4 is on the arch, but the other components are the same.

【0019】まず、トラック9にてトラス上弦材3、ト
ラス下弦材4等を現場に搬入し、図4に示すように、立
設した橋脚Pにトラス上弦材3、及びトラス下弦材4を
クレーン車8により設置する。
First, the truss upper chord 3, the truss lower chord 4 and the like are carried into the site by the truck 9, and as shown in FIG. Installed by car 8.

【0020】次いで、図5に示すように、橋脚Pの塔柱
剛結部の架設を両側に橋軸方向へ鋼トラス桁Cを1径間
張り出す。
Then, as shown in FIG. 5, a steel truss girder C is extended by one span in the bridge axis direction on both sides of the erection of the tower column rigid connection portion of the pier P.

【0021】次いで、図6に示すように、クレーン用軌
条16を、トラス上弦材3に敷設していく。
Next, as shown in FIG. 6, the rail 16 for the crane is laid on the upper chord member 3 of the truss.

【0022】次いで、図7に示すように上コンクリート
床版1の上に架設用移動クレーン12を設置する。
Next, as shown in FIG. 7, a moving crane 12 for erection is installed on the upper concrete slab 1.

【0023】次いで、張り出した鋼トラス桁Cのトラス
上弦材3、およびトラス下弦材4に移動型枠10を設置
し、この移動型枠10にコンクリートを打設し、上コン
クリート床版1及び下コンクリート床版2を構築し、ト
ラス上弦材3とトラス下弦材4とに各別に合成させる。
以下図において同様。図中、符号11は足場である。な
お、コンクリート打設装置及び移動方枠10は、上下コ
ンクリート床版1,2において異なるものを用いてい
る。したがって、上コンクリート床版1を先に構築して
も良いし、下コンクリート床版2を先に構築しても良
い。さらに上下コンクリート床版1,2を並行して構築
することもできる。当該コンクリートが硬化した後、上
下コンクリート床版1,2にプレストレス力を導入す
る。
Next, the movable formwork 10 is installed on the truss upper chord member 3 and the truss lower chord member 4 of the overhanging steel truss girder C, and concrete is poured into the movable formwork 10 to make the upper concrete floor slab 1 and the lower concrete slab 1 lower. A concrete slab 2 is constructed and the truss upper chord 3 and the truss lower chord 4 are separately synthesized.
The same applies to the following figures. In the figure, reference numeral 11 denotes a scaffold. The concrete placing device and the moving frame 10 are different from each other in the upper and lower concrete floor slabs 1 and 2. Therefore, the upper concrete slab 1 may be constructed first, or the lower concrete slab 2 may be constructed first. Further, the upper and lower concrete slabs 1 and 2 can be constructed in parallel. After the concrete has hardened, a prestressing force is introduced into the upper and lower concrete floor slabs 1 and 2.

【0024】斯かる、コンクリートの打設と併行して図
8に示すように、次径間に鋼トラス桁Cを張り出す。
As shown in FIG. 8, a steel truss girder C is extended to the next diameter in parallel with the concrete placement.

【0025】次いで、図9に示すように、その架設用移
動クレーン12を用いて、次の2径間目の鋼トラス桁C
を張り出し、トラス上弦材3、およびトラス下弦材4に
移動型枠10を設置し、移動型枠10にコンクリート打
設し、上下コンクリート床版1,2を構築する。
Then, as shown in FIG. 9, the next second span steel truss girder C is
The movable formwork 10 is installed on the truss upper chord material 3 and the truss lower chord material 4 and concrete is poured into the movable formwork 10 to construct the upper and lower concrete floor slabs 1 and 2.

【0026】次いで、2径間目の当該コンクリートが硬
化した後、上下コンクリート床版1,2にプレストレス
力を導入し、図10に示すように、架設用移動クレーン
12を2径間目の上床版上に移動させ、その架設用移動
クレーン12を用いて、次の3径間目の鋼トラス桁Cを
張り出し、移動型枠10により上下コンクリート床版
1,2を構築する。
Next, after the concrete of the second span has hardened, a prestressing force is introduced into the upper and lower concrete slabs 1 and 2, and as shown in FIG. The steel truss girder C of the next third span is overhanged by using the moving crane 12 for erection, and the upper and lower concrete slabs 1 and 2 are constructed by the movable formwork 10.

【0027】以上を、1本あるいは複数本の橋脚柱頂部
から、同時に、複合トラス橋Bの上下コンクリート床版
1,2を打設して、合成させなければ桁の強度が保たな
い部位まで、複数回行う。
From the top of one or a plurality of pier columns, simultaneously, the upper and lower concrete slabs 1 and 2 of the composite truss bridge B are simultaneously driven into a portion where the strength of the girder cannot be maintained unless combined. Perform multiple times.

【0028】図11に示すように、鋼トラス桁Cが橋の
径間が繋がるまで繰り返し、径間が繋げる。
As shown in FIG. 11, the steel truss girder C is repeated until the span of the bridge is connected, and the span is connected.

【0029】その後、移動クレーン12が径間中央から
橋脚Pに戻りながら、図12に示すように、覆工設備1
3を撤収しつつ、上コンクリート床版1用の型枠10’
(移動型枠10ではない)を仮設していく。最後に固定
型枠10’に一気にコンクリートを打設して、上コンク
リート床版1を構築する。なお、通常の固定型枠10’
ではなく、移動型枠10を用いることもできる。
Thereafter, while the moving crane 12 returns to the pier P from the center of the span, as shown in FIG.
3 and formwork 10 'for the upper concrete slab 1
(Not the movable formwork 10). Finally, concrete is poured into the fixed formwork 10 'at a stretch, and the upper concrete floor slab 1 is constructed. In addition, the usual fixed formwork 10 '
Instead, the movable mold 10 can be used.

【0030】実施の形態に係る複合トラス橋及びその架
設方法は上記の如く構成されているので、以下に掲げる
効果を奏する。
Since the composite truss bridge and the method of erection thereof according to the embodiment are configured as described above, the following effects can be obtained.

【0031】本発明の対象とする複合トラス桁Bは、ト
ラス上弦材3を具備するため、鋼トラスC自体が大きな
剛性を有している。そのため、これに接合する床版1,
2を単純な平板構造とすることが可能であるため、施工
性が良く、工期の短縮が可能である。
Since the composite truss girder B to which the present invention is applied is provided with the truss upper chord member 3, the steel truss C itself has a large rigidity. Therefore, the floor slabs 1,
Since 2 can have a simple flat plate structure, the workability is good and the construction period can be shortened.

【0032】また、剛性のある張り出しトラスCが完成
された後、これ自体が大きな支持力を有するため、トラ
ス上弦材3に移動型枠10を設置するだけで、コンクリ
ートの打設が可能となる。
After the rigid overhang truss C is completed, the truss C itself has a large supporting force, so that the concrete can be cast only by installing the movable formwork 10 on the truss upper chord 3. .

【0033】そして、上・下床版1,2との合成以前に
おいても、鋼トラスCが高い剛性を有しているため、鋼
トラスC上に架設機器を設置することが可能である。
Since the steel truss C has high rigidity even before being combined with the upper and lower floor slabs 1 and 2, it is possible to install the erection equipment on the steel truss C.

【0034】そのため、上・下床版1,2の打設の工程
と鋼トラスBの架設の工程とが同時併行できる。すなわ
ち、工期を半分に短縮することが可能である。
Therefore, the step of placing the upper and lower floor slabs 1 and 2 and the step of erection of the steel truss B can be performed simultaneously. That is, it is possible to reduce the construction period by half.

【0035】さらに、コンクリートの打設区間を、一度
にトラス一径間分と長くとることができるため、さらな
る工期の短縮が可能である。
Further, since the concrete placing section can be made as long as one span of the truss at a time, the construction period can be further shortened.

【0036】ゆえに、本実施の形態において採用したト
ラス上弦材3の設置は、従来技術の張り出し架設に比
べ、大幅な工期の短縮化を可能にしている。
Therefore, the installation of the truss upper chord member 3 employed in the present embodiment makes it possible to greatly shorten the construction period as compared with the conventional overhang erection.

【0037】また、左右対象に鋼トラス桁Cの張り出し
を行うこともできる。
Further, the steel truss girders C can be extended to the right and left sides.

【0038】なお、本発明は上記実施の形態に係る複合
トラス橋に限定されず、本発明を適用する上で好適な橋
梁に適用することができる。
The present invention is not limited to the composite truss bridge according to the above-described embodiment, but can be applied to a bridge suitable for applying the present invention.

【0039】また、コンクリートの打設と併行して次径
間のトラス桁Cの張り出しを行ったが、プレストレスの
導入と併行して、あるいは、コンクリート打設及びプレ
ストレス導入と併行して、鋼トラス桁Cの張り出しを行
うこともできる。
Further, the truss girder C of the next diameter was overhanged in parallel with the concrete placement, but in parallel with the introduction of the prestress or in parallel with the concrete placement and the introduction of the prestress. Overhang of the steel truss girder C can also be performed.

【0040】また、軌条16aを柵等に利用することも
できる。
The rail 16a can be used for a fence or the like.

【0041】また、左右対称に桁を伸張していったが、
片持ち張り出しにも適用することができる。
The girders were expanded symmetrically.
It can also be applied to cantilever overhangs.

【0042】また、上記構成部材の数、位置、形状等は
上記実施の形態に限定されず、本発明を実施する上で好
適な数、位置、形状等にすることができる。
Further, the number, position, shape, etc. of the above-mentioned constituent members are not limited to the above-mentioned embodiment, but can be set to a suitable number, position, shape, etc. for carrying out the present invention.

【0043】なお、各図において、同一構成要素には同
一符号を付している。
In the drawings, the same components are denoted by the same reference numerals.

【0044】[0044]

【発明の効果】本発明は以上のように構成されているの
で、以下に掲げる効果を奏する。床版を構築するための
コンクリートの打設、あるいは、当該打設及びプレスト
レスの導入と、次径間への鋼トラスの張り出しを併行し
て行うので、それらを交互に行う従来技術に比べて工期
を短縮することができる。
Since the present invention is configured as described above, the following effects can be obtained. Casting concrete for constructing floor slabs, or introducing the casting and prestressing, and extending the steel truss to the next span are performed in parallel. The construction period can be shortened.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施の形態に係る複合トラス橋の側面
図である。
FIG. 1 is a side view of a composite truss bridge according to an embodiment of the present invention.

【図2】i)は図1のm−m端面図、ii)は図1のn−
n端面図である。
2] i is an end view taken along the line MM in FIG. 1, and ii) is a line n- in FIG.
It is an n end view.

【図3】本発明の他の実施の形態に係る複合トラス橋の
斜視図である。
FIG. 3 is a perspective view of a composite truss bridge according to another embodiment of the present invention.

【図4】図3に示す複合トラス橋の架設方法の工程図
(側面図)である。
FIG. 4 is a process diagram (side view) of the method of erection of the composite truss bridge shown in FIG. 3;

【図5】図3に示す複合トラス橋の架設方法の工程図
(側面図)である。
FIG. 5 is a process diagram (side view) of a method of erection of the composite truss bridge shown in FIG. 3;

【図6】図3に示す複合トラス橋の架設方法の工程図
(側面図)である。
6 is a process diagram (side view) of a method of erection of the composite truss bridge shown in FIG. 3;

【図7】図3に示す複合トラス橋の架設方法の工程図
(側面図)である。
FIG. 7 is a process diagram (side view) of the method of erection of the composite truss bridge shown in FIG. 3;

【図8】図3に示す複合トラス橋の架設方法の工程図
(側面図)である。
FIG. 8 is a process diagram (side view) of the method of erection of the composite truss bridge shown in FIG. 3;

【図9】図3に示す複合トラス橋の架設方法の工程図
(側面図)である。
9 is a process diagram (side view) of the method of erection of the composite truss bridge shown in FIG.

【図10】図3に示す複合トラス橋の架設方法の工程図
(側面図)である。
10 is a process diagram (side view) of the method of erection of the composite truss bridge shown in FIG. 3;

【図11】図3に示す複合トラス橋の架設方法の工程図
(側面図)である。
11 is a process diagram (side view) of the method of erection of the composite truss bridge shown in FIG. 3;

【図12】図3に示す複合トラス橋の架設方法の工程図
(側面図)である。
12 is a process diagram (side view) of the method of erection of the composite truss bridge shown in FIG. 3;

【図13】図7に示す架設用移動クレーンの正面図(橋
脚部分を除く)である。
FIG. 13 is a front view (excluding a pier portion) of the construction mobile crane shown in FIG. 7;

【図14】図13に示す架設用移動クレーン側面図であ
る。
14 is a side view of the mobile crane for erection shown in FIG.

【図15】図7に示す、打設された上床版の平面図であ
る。
FIG. 15 is a plan view of the installed upper slab shown in FIG. 7;

【図16】図7に示す工程図の正面図(橋脚部分を除
く)である。
FIG. 16 is a front view (excluding a pier portion) of the process diagram shown in FIG. 7;

【図17】図7に示す工程図の正面図(橋脚部分を除
く)である。
FIG. 17 is a front view (excluding a pier portion) of the process drawing shown in FIG. 7;

【図18】図7に示す工程図の正面図(橋脚部分を除
く)である。
FIG. 18 is a front view (excluding a pier portion) of the process drawing shown in FIG. 7;

【図19】従来の張出し架設が可能な複合トラス橋の橋
梁構造の断面図である。
FIG. 19 is a cross-sectional view of a conventional bridge structure of a composite truss bridge which can be overhanged.

【符号の説明】[Explanation of symbols]

B 複合トラス橋 C 鋼トラス桁 G 地盤 P 橋脚 1 上床版 2 下床版 3 トラス上弦材 4 トラス下弦材 5 トラス斜材 6 舗装 7 プレストレスケーブル 8 クレーン車 9 トラック 10 移動型枠 11 足場 12 架設用移動クレーン 13 覆工設備 14 コンクリート充填鋼管 16 クレーン用軌条 16a レール 16b 固定部 B Composite truss bridge C Steel truss girder G Ground P Pier 1 Upper deck 2 Lower deck 3 Truss upper chord 4 Truss lower chord 5 Truss diagonal 6 Pavement 7 Prestressed cable 8 Crane truck 9 Truck 10 Moving form 11 Scaffolding 12 Erecting Mobile crane 13 lining equipment 14 concrete filled steel pipe 16 rail for crane 16a rail 16b fixing part

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 鋼製の上弦材、下弦材及び斜材を有する
鋼トラス桁と、該鋼トラス桁の上面に構築された橋面を
形成するコンクリート床版とを備えた複合トラス橋の架
設方法であって、 前記複合トラス桁が架設される、立設された2つの橋脚
から架設方向へ鋼トラス桁を1径間張り出す工程と、 張り出した鋼トラス桁の上弦材、および下弦材に移動型
枠を設置し、該移動型枠にコンクリートを打設して床版
を構築する工程と、 該工程と併行して、前記上弦材に、橋軸方向へ移動可
能に設置した架設用移動クレーンを用いて、次径間の鋼
トラス桁を張り出す工程とを備え、 前記鋼トラス桁が繋がるまで前記工程と前記工程と
を行うことを特徴とする複合トラス橋の架設方法。
1. Construction of a composite truss bridge including a steel truss girder having steel upper chord, lower chord and diagonal, and a concrete slab forming a bridge surface constructed on the upper surface of the steel truss girder. A method, comprising: extending a steel truss girder by one span in the direction of erection from two erected piers, on which the composite truss girder is erected; A step of installing a movable formwork, casting concrete on the movable formwork to construct a floor slab, and, in parallel with the step, moving the erection on the upper chord member so as to be movable in a bridge axis direction. A method of erection of a steel truss girder of the next span using a crane, wherein the steps and the steps are performed until the steel truss girder is connected.
【請求項2】 鋼製の上弦材、下弦材及び斜材を有する
鋼トラス桁と、該鋼トラス桁の上面に構築された橋面を
形成するコンクリート床版とを備えた複合トラス橋の架
設方法であって、 前記複合トラス桁が架設される、立設された2つの橋脚
から架設方向へ鋼トラス桁を1径間張り出す工程と、 張り出した鋼トラス桁の上弦材、および下弦材に移動型
枠を設置し、該移動型枠にコンクリートを打設して床版
を構築する工程と、 前記コンクリートが硬化した後、床版にプレストレス力
を導入する工程と、 該工程と併行して、前記上弦材に、橋軸方向へ移動可
能に設置した架設用移動クレーンを用いて、次径間の鋼
トラス桁を張り出す工程とを備え、 前記鋼トラス桁が繋がるまで前記工程乃至前記工程
を繰り返し行うことを特徴とする複合トラス橋の架設方
法。
2. Construction of a composite truss bridge comprising a steel truss girder having steel upper chord, lower chord and diagonal, and a concrete slab forming a bridge surface constructed on the upper surface of the steel truss girder. A method, comprising: extending a steel truss girder by one span in the direction of erection from two erected piers, on which the composite truss girder is erected; Installing a movable formwork, placing concrete on the movable formwork to construct a floor slab, and introducing a prestressing force to the floor slab after the concrete has hardened; A step of projecting a steel truss girder of the next span using a erection moving crane installed movably in the bridge axis direction on the upper chord material, wherein the steel truss girder is connected until the steel truss girder is connected. Composite truss characterized by repeating the process How to build a bridge.
【請求項3】 鋼製の上弦材、下弦材及び斜材を有する
鋼トラス桁と、該鋼トラス桁の上面に構築された橋面を
形成するコンクリート床版とを備えた複合トラス橋の架
設方法であって、 前記複合トラス桁が架設される、立設された2つの橋脚
から架設方向へ鋼トラスを1径間張り出す工程と、 張り出した鋼トラス桁の上弦材、および下弦材に移動型
枠を設置し、該移動型枠にコンクリートを打設して床版
を構築する工程と、 前記コンクリートが硬化した後、床版にプレストレス力
を導入する工程と、 前記工程及び工程と併行して、前記上弦材に、橋軸
方向へ移動可能に設置した架設用移動クレーンを用い
て、次径間の鋼トラス桁を張り出す工程とを備え、 前記鋼トラス桁が繋がるまで前記工程乃至前記工程
を繰り返し行うことを特徴とする複合トラス橋の架設方
法。
3. A composite truss bridge erection comprising a steel truss girder having steel upper chords, lower chords and diagonal members, and a concrete slab forming a bridge surface formed on the upper surface of the steel truss girder. A method of extending a steel truss for one span in the direction of erection from two erected piers on which the composite truss girder is erected, and moving the overhanging steel truss girder to an upper chord and a lower chord. Installing a formwork, casting concrete on the movable formwork to construct a floor slab, after hardening the concrete, introducing a prestressing force to the floor slab; And a step of projecting a steel truss girder of the next span using a erection moving crane installed movably in the bridge axis direction on the upper chord material, wherein the steel truss girder is connected until the steel truss girder is connected. The method is characterized by repeating the above steps. How to build a joint truss bridge.
【請求項4】 前記鋼トラス桁の張り出しを、前記橋脚
をはさんで左右対称に行うことを特徴とする請求項1乃
至3に記載の複合トラス橋の架設方法。
4. The method for erection of a composite truss bridge according to claim 1, wherein the overhang of the steel truss girder is performed symmetrically across the pier.
【請求項5】 請求項1乃至4に記載の複合トラス橋の
架設方法により架設されたことを特徴とする複合トラス
橋。
5. A composite truss bridge constructed by the method for constructing a composite truss bridge according to claim 1.
JP28868298A 1998-09-28 1998-09-28 Erection of combined truss bridge Pending JP2000104220A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP28868298A JP2000104220A (en) 1998-09-28 1998-09-28 Erection of combined truss bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP28868298A JP2000104220A (en) 1998-09-28 1998-09-28 Erection of combined truss bridge

Publications (1)

Publication Number Publication Date
JP2000104220A true JP2000104220A (en) 2000-04-11

Family

ID=17733333

Family Applications (1)

Application Number Title Priority Date Filing Date
JP28868298A Pending JP2000104220A (en) 1998-09-28 1998-09-28 Erection of combined truss bridge

Country Status (1)

Country Link
JP (1) JP2000104220A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006307575A (en) * 2005-04-28 2006-11-09 Ps Mitsubishi Construction Co Ltd Overhang construction method for corrugated steel sheet web bridge and installation work vehicle
JP2008031768A (en) * 2006-07-31 2008-02-14 Ps Mitsubishi Construction Co Ltd Cantilever overhanging erection method for corrugated steel plate web box girder bridge
CN102808373A (en) * 2012-08-10 2012-12-05 南京工业大学 Rapidly assembled steel footbridge in truss string structure
CN108756243A (en) * 2018-04-17 2018-11-06 青岛博海建设集团有限公司 Girder steel and concrete ring beam, the structure-integrated construction of concrete floor
CN110424605A (en) * 2019-07-03 2019-11-08 云南联固建筑材料有限公司 A kind of steel bar girder composite floor
CN110777643A (en) * 2019-11-14 2020-02-11 中铁武汉勘察设计研究院有限公司 Large-span steel truss combined continuous beam structure and construction method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006307575A (en) * 2005-04-28 2006-11-09 Ps Mitsubishi Construction Co Ltd Overhang construction method for corrugated steel sheet web bridge and installation work vehicle
JP2008031768A (en) * 2006-07-31 2008-02-14 Ps Mitsubishi Construction Co Ltd Cantilever overhanging erection method for corrugated steel plate web box girder bridge
CN102808373A (en) * 2012-08-10 2012-12-05 南京工业大学 Rapidly assembled steel footbridge in truss string structure
CN102808373B (en) * 2012-08-10 2015-08-19 南京工业大学 Quick assembled type truss string structure People's Bank of China steel bridge
CN108756243A (en) * 2018-04-17 2018-11-06 青岛博海建设集团有限公司 Girder steel and concrete ring beam, the structure-integrated construction of concrete floor
CN110424605A (en) * 2019-07-03 2019-11-08 云南联固建筑材料有限公司 A kind of steel bar girder composite floor
CN110777643A (en) * 2019-11-14 2020-02-11 中铁武汉勘察设计研究院有限公司 Large-span steel truss combined continuous beam structure and construction method thereof

Similar Documents

Publication Publication Date Title
JP5045214B2 (en) Column head construction method
JP2008038449A (en) Bridge girder constructing method
JP2004092078A (en) Structure and construction method for bridge
KR101127130B1 (en) A precast type pre-stress box girder bridge excution method
JP3844743B2 (en) Box girder bridge structure and its construction method
JPH11181725A (en) Method for constructing horizontal beam of main tower made of concrete
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN108316150B (en) Construction system and construction method for main tower and steel anchor beam of cable-stayed bridge
JP3701250B2 (en) Cable stayed bridge and its construction method
JPH0643686B2 (en) Construction method of arch bridge by precast members
JP2001348815A (en) Cantilever type installing construction method of bridge
JP2000017613A (en) Connection of corrugated steel plate web girder
JPH10339033A (en) Concrete multistory building construction device and construction method for concrete oblique post
JP2000104220A (en) Erection of combined truss bridge
JP2000104221A (en) Combined truss bridge and erection method of the same
JP2001200510A (en) Method for constructing overhangingly erected bridge using corrugated steel plate web
JP3877995B2 (en) How to build a string string bridge
JPH09125318A (en) Construction device of bridge girder
JP4351523B2 (en) Column head construction method
JP6889010B2 (en) Bridge construction method
JP3701078B2 (en) Road slab construction method
JP2000104219A (en) Erection of combined truss bridge
JP2003193424A (en) Composite truss bridge and its construction method
JP7134133B2 (en) Bridge railing construction method
CN115506634B (en) Assembled platform canopy and construction method thereof