JPH11181725A - Method for constructing horizontal beam of main tower made of concrete - Google Patents
Method for constructing horizontal beam of main tower made of concreteInfo
- Publication number
- JPH11181725A JPH11181725A JP35361897A JP35361897A JPH11181725A JP H11181725 A JPH11181725 A JP H11181725A JP 35361897 A JP35361897 A JP 35361897A JP 35361897 A JP35361897 A JP 35361897A JP H11181725 A JPH11181725 A JP H11181725A
- Authority
- JP
- Japan
- Prior art keywords
- horizontal beam
- tower
- girder
- main tower
- horizontal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000004567 concrete Substances 0.000 title claims description 33
- 238000000034 method Methods 0.000 title claims description 28
- 238000010276 construction Methods 0.000 claims abstract description 26
- 238000003780 insertion Methods 0.000 claims description 6
- 230000037431 insertion Effects 0.000 claims description 6
- 238000002360 preparation method Methods 0.000 claims description 4
- 238000000926 separation method Methods 0.000 claims description 2
- 206010038743 Restlessness Diseases 0.000 claims 1
- 239000011150 reinforced concrete Substances 0.000 abstract description 6
- 239000000853 adhesive Substances 0.000 abstract description 3
- 230000001070 adhesive effect Effects 0.000 abstract description 3
- 239000000725 suspension Substances 0.000 description 10
- 229910000831 Steel Inorganic materials 0.000 description 7
- 239000011178 precast concrete Substances 0.000 description 7
- 239000010959 steel Substances 0.000 description 7
- 239000000470 constituent Substances 0.000 description 5
- 238000010586 diagram Methods 0.000 description 4
- 239000000463 material Substances 0.000 description 4
- 239000011347 resin Substances 0.000 description 4
- 229920005989 resin Polymers 0.000 description 4
- 238000009415 formwork Methods 0.000 description 3
- 230000003014 reinforcing effect Effects 0.000 description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 2
- 239000004593 Epoxy Substances 0.000 description 1
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 239000003562 lightweight material Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 238000003908 quality control method Methods 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、コンクリート製主
塔の水平梁の施工法に関し、更に詳細には吊り橋や斜張
橋の主塔に設けられる水平梁の施工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a horizontal beam of a concrete main tower, and more particularly to a method of constructing a horizontal beam provided on a main tower of a suspension bridge or a cable-stayed bridge.
【0002】[0002]
【従来の技術】吊り橋のケーブルを空中高く支持するた
めの主塔や斜め直線状に張られる斜張橋のケーブルによ
って桁を支間の中間でつる主塔は、一般に塔柱と水平梁
で構成されている。即ち、主塔は基礎の上部に所定の間
隙を有した塔柱と、この塔柱間に掛け渡される上下方向
に所定の間隙をおいた複数の水平梁とを有している。2. Description of the Related Art A main tower for supporting a suspension bridge cable high in the air or a main tower for hanging a girder in the middle of a span by a cable of a cable-stayed bridge stretched diagonally in a straight line generally comprises a tower column and a horizontal beam. ing. That is, the main tower has a column having a predetermined gap in the upper part of the foundation, and a plurality of horizontal beams with a predetermined gap in the vertical direction spanned between the columns.
【0003】塔柱間に水平梁を設ける方法として既にい
ろいろな施工法が提案されている。例えば、図7はその
第1の施工法を示す図であり、同図(a)は主塔1の正
面図を示し、同図に示すように、クレーン9を用いて2
本の塔柱5の上部に仮設されたブラケット13に支保工
桁61を架設し、同図(b)に示すように、この支保工
桁61の上部に鉄筋工、型枠工、コンクリート工等を行
なって2本の塔柱5間の所定の部位に水平梁7を設け
る。そして、同図(c)に示すように、支保工桁61を
吊りおろすジャッキ11をこの水平梁7に設置した後に
支保工桁61をこの水平梁7の下方の既設水平梁7の上
部に吊り降ろす。Various construction methods have already been proposed as methods for providing horizontal beams between tower columns. For example, FIG. 7 is a view showing the first construction method, and FIG. 7A shows a front view of the main tower 1 and, as shown in FIG.
A supporting girder 61 is erected on a bracket 13 temporarily provided on the upper part of the tower column 5, and as shown in FIG. Is performed to provide a horizontal beam 7 at a predetermined position between the two tower columns 5. Then, as shown in FIG. 8C, after the jack 11 for hanging the support girder 61 is installed on the horizontal beam 7, the support girder 61 is hung above the existing horizontal beam 7 below the horizontal girder 7. take down.
【0004】そして、図(d)は図(c)に示す主塔1
の側面図を示し、同図に示すように、支保工桁61をク
レーン(図示せず)で吊ることができる程度に解体した
後に水平梁7の側壁よりも外側方向であって2本の塔柱
5の側壁よりも外側に移動させる。尚、支保工桁61の
解体は支保工桁61を移動させた後でもよい。FIG. 1D shows the main tower 1 shown in FIG. 1C.
As shown in the figure, the support girder 61 is dismantled to such an extent that it can be hung by a crane (not shown), and is located outside the side wall of the horizontal beam 7 and has two towers. The column 5 is moved outside the side wall. The support girders 61 may be disassembled after the support girders 61 are moved.
【0005】そして、図(e)に示すように、解体され
た支保工桁61aをクレーン(図示せず)で所定の部位
まで吊り上げる。また、図8は既に提案されている水平
梁7の第2の施工法を示す図であり、同図(a)は主塔
1の正面図を示し、同図(b)は図(a)に示す主塔1
の側面図を示す。同図(a),(b)に示すように、2
本の塔柱5に張り出し桁63を仮設し、この張り出し桁
63にジャッキ11を設け、このジャッキ11により支
保工桁61と型枠と鉄筋を吊り上げる。そして、これら
を所定の部位に横移動させる。[0005] Then, as shown in Fig. 1 (e), the dismantled support girder 61a is lifted to a predetermined position by a crane (not shown). FIG. 8 is a diagram showing a second construction method of the horizontal beam 7 already proposed, wherein FIG. 8A shows a front view of the main tower 1, and FIG. 8B shows a diagram (a). Main tower 1 shown
FIG. As shown in FIGS.
An overhanging girder 63 is temporarily provided on the tower pillar 5, and a jack 11 is provided on the overhanging girder 63. The jack 11 lifts the support girder 61, the formwork, and the reinforcing bar. Then, these are laterally moved to a predetermined portion.
【0006】次に、同図(c)に示すように、支保工桁
61の上部で鉄筋工等を行なって2本の塔柱5間の所定
の部位に水平梁7を設ける。そして、同図(d),
(e)に示すように、水平梁7に設けられたジャッキ1
1により支保工桁61を下方の既設水平梁7の上部に吊
り降ろしその場所で横移動させる。尚、支保工桁61を
現状の高さで横移動させてもよい。Next, as shown in FIG. 1C, a horizontal beam 7 is provided at a predetermined position between the two tower columns 5 by performing a reinforcing work or the like on an upper part of the support girder 61. Then, FIG.
As shown in (e), the jack 1 provided on the horizontal beam 7
In step 1, the support girder 61 is hung above the existing horizontal beam 7 below and moved laterally there. Note that the support girder 61 may be moved laterally at the current height.
【0007】そして、同図(f)に示すように、上方に
仮設した張り出し桁63に設けられたジャッキ11によ
り支保工桁61を所定の高さまで吊り上げる。また、図
9は既に提案されている水平梁の第3の施工法を示す図
であり、同図(a)は主塔1の正面図を示し、同図
(b)は図(a)に示す主塔1の側面図を示す。同図
(a),(b)に示すように、塔柱5の上部に張り出し
桁63を仮設し、この張り出し桁63にジャッキ11を
設け、このジャッキ11を用いて支保工桁61を所定の
高さまで吊り上げた後に所定の部位に横移動させる。そ
して、同図(c)に示すように、この支保工桁61を水
平梁7の一部としてコンクリートの中に埋め込んで、所
定の水平梁7を形成する。[0007] Then, as shown in Fig. 1 (f), the supporting girder 61 is lifted to a predetermined height by the jack 11 provided on the overhanging girder 63 temporarily provided above. FIG. 9 is a diagram showing a third method of constructing a horizontal beam which has already been proposed. FIG. 9 (a) shows a front view of the main tower 1, and FIG. 9 (b) shows a diagram of FIG. 1 shows a side view of the main tower 1 shown. As shown in FIGS. 7A and 7B, an overhang girder 63 is temporarily provided at the upper part of the tower post 5, and a jack 11 is provided on the overhang girder 63. After being lifted to the height, it is moved laterally to a predetermined site. Then, as shown in FIG. 3C, the supporting girder 61 is embedded in concrete as a part of the horizontal beam 7 to form a predetermined horizontal beam 7.
【0008】さらに、図10は既に提案されている水平
梁の第4の施工法を示す図であり、同図(a)は主塔1
の正面図を示し、同図(b)は図(a)に示す主塔1の
側面図を示す。同図(a),(b)に示すように、張り
出し桁63に設けられたジャッキ11により水平梁7を
架設する所定の部位までプレキャストコンクリート部材
65を上方に吊上げて横移動させた後に、同図(c)に
示すように、ブラケット67の上部にプレキャストコン
クリート部材65を仮置きし、このプレキャストコンク
リート部材65の両端外側と塔柱5の側壁との間の間隙
69にコンクリートを打設して水平梁7を形成し、前記
コンクリートが硬化した後にこの水平梁7の全体にプレ
ストレスを与えてプレキャストコンクリート部材65と
硬化したコンクリートを締め付けて一体化する。FIG. 10 is a view showing a fourth method of constructing a horizontal beam which has already been proposed, and FIG.
FIG. 2B shows a side view of the main tower 1 shown in FIG. As shown in FIGS. 7A and 7B, the precast concrete member 65 is lifted upward by a jack 11 provided on the overhanging beam 63 to a predetermined portion where the horizontal beam 7 is erected, and is laterally moved. As shown in FIG. 5C, a precast concrete member 65 is temporarily placed on the upper part of the bracket 67, and concrete is poured into a gap 69 between the outer ends of both ends of the precast concrete member 65 and the side wall of the tower 5. After the horizontal beam 7 is formed and the concrete is hardened, a prestress is applied to the entire horizontal beam 7 so that the precast concrete member 65 and the hardened concrete are tightened and integrated.
【0009】[0009]
【発明が解決しようとする課題】しかしながら、従来の
第1及び第2の水平梁の施工法によれば、水平梁を施工
した後にさらにその上方に別の新たな水平梁を施工する
場合、支保工桁をそのまま上方に移動させると施工した
水平梁が邪魔をして所定の部位に支保工桁を移動させる
ことができない。However, according to the conventional first and second horizontal beam construction methods, when a new horizontal beam is constructed further above the horizontal beam after the construction of the horizontal beam, If the work girder is moved upward as it is, the constructed horizontal beam hinders the movement of the support girder to a predetermined position.
【0010】従って、支保工桁を所定の部位に移動させ
るには支保工桁を横移動させる必要がある。また、水平
梁は所定の部位で型枠工・鉄筋工・コンクリート工・養
生をする場所打ち施工を行なうので、工期が長期にな
る。Therefore, in order to move the shoring girder to a predetermined portion, it is necessary to laterally move the shoring girder. In addition, since the horizontal beam is subjected to cast-in-place construction for formwork, reinforcing steel work, concrete work, and curing at a predetermined portion, the construction period is long.
【0011】さらに、従来の第3の水平梁の施工法によ
れば、水平梁にはそれぞれの支保工桁が必要になるの
で、支保工桁の転用ができない、という問題が生じる。
また、従来の第4の水平梁の施工法によれば、プレキャ
ストコンクリート部材を上方に吊り上げるための仮設用
の張り出し桁が必要になり、プレキャストコンクリート
部材の重量が大きいためこの張り出し桁が大型になり張
り出し桁を塔柱に固定する固定手段も大規模になる、と
いう問題が生じる。Further, according to the third conventional method for constructing a horizontal beam, since each supporting beam is required for the horizontal beam, there is a problem that the supporting beam cannot be diverted.
Further, according to the fourth conventional method of constructing a horizontal beam, a temporary overhang girder for lifting the precast concrete member upward is required, and since the weight of the precast concrete member is large, the overhang girder becomes large. There is a problem in that the fixing means for fixing the overhanging girder to the tower pillar also becomes large-scale.
【0012】本発明は、前記事項に鑑みてなされたもの
であり、支保工桁の転用が可能であり、支保工桁を上方
に移動させる際に横移動させることなく所定の高さに移
動させることができ、プレキャストコンクリート部材を
支える桁を小型にし、且つこれを塔柱に固定する固定手
段を小規模なものにできるコンクリート製主塔の水平梁
の施工法を提供することを課題とする。[0012] The present invention has been made in view of the above-mentioned matters, and can be diverted to a support girder, and moves the support girder to a predetermined height without moving laterally when moving the support girder upward. It is an object of the present invention to provide a method of constructing a horizontal beam of a concrete main tower in which a girder supporting a precast concrete member can be reduced in size and a fixing means for fixing the girder to a tower column can be reduced in size.
【0013】[0013]
【課題を解決するための手段】本発明は前記課題を解決
するために、以下の手段を採用した。本発明は、基礎上
に立設する塔柱間の上下方向に所定の間隙をおいた水平
梁を複数個(n個)設けてコンクリート製主塔を築造す
るコンクリート製主塔の水平梁の施工法において、
(イ)前記水平梁を施工する際に利用される部材を前記
塔柱の所定の部位に搬送する部材搬送工程と、(ロ)前
記部材搬送工程で搬送された部材を組み立てて所定の部
位に支保工桁を設けて水平梁の施工の準備をする水平梁
施工準備工程と、(ハ)水平梁を構成する複数の構成ブ
ロックを所定の部位に吊り上げ、これらの構成ブロック
間を接着させて塔柱間の離間寸法よりも小さい長さを有
する梁を形成し、この梁の両端部と塔柱の側壁との間の
間隙に塔柱と梁とを連設する連設部を設けて塔柱間に水
平梁を架設した後にこの水平梁に圧縮荷重を作用させて
プレストレスを有する水平梁とする水平梁架設工程と、
(ニ)前記水平梁架設工程で架設された水平梁よりも上
方の所定の部位に前記支保工桁を移動させた後に水平梁
架設工程を行なうサイクルを(nー1)回繰り返す水平
梁増設工程と、を備えたことを特徴とするコンクリート
製主塔の水平梁の施工法である。The present invention has the following features to attain the object mentioned above. The present invention relates to the construction of a horizontal beam of a concrete main tower in which a concrete main tower is constructed by providing a plurality (n) of horizontal beams at predetermined intervals in a vertical direction between tower columns erected on a foundation. In the law,
(A) a member transporting step of transporting a member used when constructing the horizontal beam to a predetermined portion of the tower column; and (b) assembling the member transported in the member transporting step to a predetermined portion. A horizontal beam construction preparation step of preparing a horizontal beam by providing a shoring girder; and (c) lifting a plurality of constituent blocks constituting the horizontal beam to a predetermined portion and bonding these constituent blocks together to form a tower. A beam having a length smaller than the distance between the columns is formed, and a continuous portion for continuously connecting the column and the beam is provided in a gap between both ends of the beam and the side wall of the column. A horizontal beam erection step of applying a compressive load to this horizontal beam after laying a horizontal beam between the horizontal beams and having a prestressed horizontal beam,
(D) A horizontal beam extension process in which a cycle of performing the horizontal beam erection process after moving the support girder to a predetermined position above the horizontal beam erected in the horizontal beam erection process is repeated (n-1) times And a horizontal beam for the concrete main tower.
【0014】主塔に形成される水平梁の数は2以上であ
ればよい。即ち、「n個」のnとは2以上の自然数をい
う。支保工桁は塔柱の外側に上下移動可能に設けられる
ので、支保工桁を上方に移動させる際に、構築された水
平梁が邪魔をして支保工桁の上方の移動を妨げることは
ない。The number of horizontal beams formed on the main tower may be two or more. That is, "n" n is a natural number of 2 or more. Since the shoring girder is provided so as to be able to move up and down outside the tower pillar, when moving the shoring girder upward, the constructed horizontal beam does not hinder the upward movement of the shoring girder. .
【0015】また、前記水平梁架設工程における連設部
を樹脂製の隙間挿入部材からなるようにしてもよい。梁
の両端部と塔柱の側壁との間の間隙が小さい場合に樹脂
製の隙間挿入部材を充填することで、梁を塔柱に簡易に
接続させることができる。Further, the continuous portion in the horizontal beam erection step may be formed of a resin gap insertion member. When the gap between both ends of the beam and the side wall of the column is small, the beam can be easily connected to the column by filling the gap insertion member made of resin.
【0016】[0016]
【発明の実施の形態】以下、本発明に係るコンクリート
製主塔の水平梁の施工法(以下、「水平梁の施工法」と
記す。)の一実施の形態を、図1から図6に基づいて説
明する。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of a method for constructing a horizontal beam of a concrete tower according to the present invention (hereinafter referred to as "method of constructing a horizontal beam") according to the present invention is shown in FIGS. It will be described based on the following.
【0017】本実施の形態は吊り橋や斜張橋の主塔の塔
柱間に設けられる水平梁の施工法を示す態様である。最
初に、本発明の水平梁の施工法を使用して築造される主
塔を図1,図2に基づいて説明する。The present embodiment is an embodiment showing a method of constructing a horizontal beam provided between columns of a main tower of a suspension bridge or a cable-stayed bridge. First, a main tower constructed using the horizontal beam construction method of the present invention will be described with reference to FIGS.
【0018】図1(a)は主塔1の正面図を示し、同図
(b)は主塔1の側面図を示す。同図(a),(b)に
示すように、鉄筋コンクリート製の基礎3の上部に左右
方向に一定の間隙を有して配置された2本の鉄筋コンク
リート製の塔柱5が立設されている。2本の塔柱5の間
であって基礎3の上部には所定の離間寸法を有して配置
された鉄筋コンクリート製の水平梁7が5つ架設されて
いる。FIG. 1A is a front view of the main tower 1, and FIG. 1B is a side view of the main tower 1. As shown in FIGS. 1A and 1B, two reinforced concrete tower columns 5 are provided upright on a reinforced concrete foundation 3 with a certain gap left and right. . Five horizontal beams 7 made of reinforced concrete are arranged between the two tower columns 5 and on the upper part of the foundation 3 with a predetermined spacing.
【0019】図2(a)は水平梁7の正面図を示し、同
図(b)は同図(a)のA−A矢視の断面図を示してい
る。同図(a),(b)に示すように、水平梁7は内部
に貫通孔8を有して直方体形状をなしている。FIG. 2A is a front view of the horizontal beam 7, and FIG. 2B is a sectional view taken along the line AA of FIG. 2A. As shown in FIGS. 7A and 7B, the horizontal beam 7 has a through-hole 8 inside and has a rectangular parallelepiped shape.
【0020】次に、本発明の水平梁7の施工法を図3か
ら図6を用いて説明する。水平梁7の施工法は部材搬送
工程と水平梁施工準備工程と水平梁架設工程と水平梁増
設工程とを備えている。Next, a method of constructing the horizontal beam 7 according to the present invention will be described with reference to FIGS. The construction method of the horizontal beam 7 includes a member transporting process, a horizontal beam construction preparation process, a horizontal beam erection process, and a horizontal beam extension process.
【0021】最初に、図3(a)は主塔1の正面図を示
し、同図に示すように、基礎3の上部の縁部に上方に延
設自在なクレーン9を設置し、このクレーン9を利用し
てクレーン9の側方に一定の間隙を有した2本の鉄筋コ
ンクリート製の塔柱5を立設する。塔柱5は下から1段
目の水平梁7が設けられる部位よりも高い高さを有して
いる。尚、塔柱5の高さを数段分の水平梁7が架設され
る高さに立設してから1段目の水平梁7の施工を開始し
てもよい。First, FIG. 3 (a) shows a front view of the main tower 1, and as shown in FIG. 3, a crane 9 which can be extended upward is installed at the upper edge of the foundation 3, and this crane 9 is installed. The two reinforced concrete tower columns 5 having a certain gap are provided on the side of the crane 9 by using the crane 9. The tower column 5 has a height higher than a portion where the first horizontal beam 7 from the bottom is provided. In addition, the construction of the first stage horizontal beam 7 may be started after the height of the tower column 5 is erected at the height where the horizontal beam 7 for several stages is erected.
【0022】次に、部材搬送工程を行なう。即ち、塔柱
5の上部に設けられたジャッキ11を用いてブラケット
13と支保工桁15と複数の型枠17とを第1段目の水
平梁7が設けられる部位まで吊り上げる。Next, a member conveying step is performed. That is, the bracket 13, the support girder 15, and the plurality of molds 17 are lifted up to the position where the first-stage horizontal beam 7 is provided by using the jack 11 provided on the upper part of the tower column 5.
【0023】次に、水平梁施工準備工程を行なう。即
ち、図3(b)は主塔1の側面図を示し、同図に示すよ
うに、塔柱5の側壁5a,5bにブラケット13を設
け、塔柱5の同一方向の側壁に設けられたブラケット1
3の上部に支保工桁15を架設する。Next, a horizontal beam construction preparation process is performed. That is, FIG. 3B shows a side view of the main tower 1, and as shown in FIG. 3, brackets 13 are provided on the side walls 5 a and 5 b of the tower 5, and provided on the side walls of the tower 5 in the same direction. Bracket 1
A shoring girder 15 is erected on the upper part of 3.
【0024】図4は図3(a)のB−B矢視に相当する
部分の側面図を示し、同図に示すように、側面形状が略
Y字状を有する支持部13aとこの支持部13aの上部
に設けられる板状の載置部13bとを有するブラケット
13の前記支持部13aの下方端部を塔柱5の側壁5
a,5bに支承し、塔柱5の左右両側に配置された載置
部13b間に塔柱5を貫通する複数のPC鋼材19を接
続し、このPC鋼材19を緊張してブラケット13を塔
柱5に固定する。FIG. 4 is a side view of a part corresponding to the view taken in the direction of arrows BB in FIG. 3 (a). As shown in FIG. 4, a support portion 13a having a substantially Y-shaped side surface and a support portion 13a The lower end of the support portion 13a of the bracket 13 having a plate-shaped mounting portion 13b provided on the upper portion of the
a, 5b, a plurality of PC steel members 19 penetrating through the tower column 5 are connected between the mounting portions 13b arranged on both left and right sides of the tower column 5, and the PC steel members 19 are tensioned to mount the bracket 13 on the tower. Fix to pillar 5.
【0025】そして、載置部13bの上部であって塔柱
5の外側に鉄製で箱状の支保工桁15を延設する。支保
工桁15は前記箱状の他、2本のI型桁を平行に並べた
ものや2本のトラスを平行に並べたものでもよい。Then, a box-shaped support girder 15 made of iron is extended above the mounting portion 13b and outside the tower post 5. In addition to the box shape, the support girder 15 may be a structure in which two I-type girders are arranged in parallel or a structure in which two trusses are arranged in parallel.
【0026】次に、水平梁架設工程を行なう。即ち、水
平梁7の構成部分となる予め作製されたプレキャストブ
ロック(構成ブロック)21を2本のロープ23を介し
て吊り桁25に接続し、この吊り桁25に別のロープ2
7を接続する。ロープ23は鋼棒を使用してもよい。Next, a horizontal beam erection step is performed. That is, a precast block (constituting block) 21 which is a component part of the horizontal beam 7 is connected to a suspension girder 25 via two ropes 23, and another rope 2 is attached to the suspension girder 25.
7 is connected. The rope 23 may use a steel bar.
【0027】ここで、プレキャストブロック21は板状
であってその中央部には矩形状の孔29が設けられ、プ
レキャストブロック21の上部にはロープ23を挿通す
る上下方向に形成された孔31が設けられている。ま
た、プレキャストブロック21の上部壁面と下部の内側
壁面あるいは鉛直側壁内面にはプレキャストブロック2
1を一体化する仮設PC鋼棒49を挿通するための挿通
孔35が形成されている。このプレキャストブロック2
1を複数連設することで内部に貫通孔8を有する直方体
形状の梁37が形成される。Here, the precast block 21 is plate-shaped, and a rectangular hole 29 is provided at the center thereof, and a hole 31 formed in a vertical direction through which the rope 23 is inserted is provided above the precast block 21. Is provided. The precast block 2 is provided on the upper wall surface and the lower inner wall surface of the precast block 21 or the inner surface of the vertical side wall.
1 is formed with an insertion hole 35 for inserting a temporary PC steel rod 49 for integrating the same. This precast block 2
By arranging a plurality of 1s, a rectangular parallelepiped beam 37 having a through hole 8 therein is formed.
【0028】また、吊り桁25は棒状をなし、その中央
上部にはクレーン9に接続されたロープ27を掛止する
ための掛止部39が形成され、この掛止部39よりも左
右の両外側の一定の離間寸法を有した部位にプレキャス
トブロック21に接続されたロープ23を固定するため
の孔41が設けられている。吊り桁25の両端部の下部
には台車43が設けられている。The hanging girder 25 has a rod shape, and a hook portion 39 for hanging the rope 27 connected to the crane 9 is formed at the upper center thereof. A hole 41 for fixing the rope 23 connected to the precast block 21 is provided at an outer portion having a certain separation dimension. A bogie 43 is provided below the both ends of the suspension girder 25.
【0029】台車43は支保工桁15の上部に載置され
支保工桁15上を移動して塔柱5間の任意の位置に吊り
桁25を移動させることができる。次に、ロープ27を
クレーン9のフック45に掛止し、クレーン9を操作し
て吊り桁25の下方にプレキャストブロック21が吊り
下げられた状態で吊り桁25の下方の両端部に設けられ
た台車43を支保工桁15の上部に載置する。 そし
て、図5に示すように、左側の塔柱5の内側側壁から所
定の間隔Wを有する間隙47を有した部位にプレキャス
トブロック21が来るように吊り桁25を移動させる。The carriage 43 is mounted on the support girder 15 and can move on the support girder 15 to move the suspension girder 25 to any position between the tower columns 5. Next, the rope 27 was hooked on the hook 45 of the crane 9, and the crane 9 was operated to provide the precast block 21 under the hanging girder 25 at the both ends below the hanging girder 25 in a suspended state. The truck 43 is placed on the support girder 15. Then, as shown in FIG. 5, the suspension girder 25 is moved so that the precast block 21 comes to a portion having a gap 47 having a predetermined interval W from the inner side wall of the left column 5.
【0030】次に、このプレキャストブロック21より
も右側の所定の部位に前記プレキャストブロック21と
同様の手順で他のプレキャストブロック21を配置す
る。そして、これらのプレキャストブロック21の相対
向する壁面に接着剤を塗布した後に、後から配置したプ
レキャストブロック21を台車43を介して左側に移動
させて先行設置されているプレキャストブロック21の
壁面に接触させた後に、プレキャストブロック21の上
部と下部あるいは側面に設けられた挿通孔35に仮設P
C鋼棒49を挿入し緊張して隣接するプレキャストブロ
ック21を一体化する。Next, another precast block 21 is arranged at a predetermined position on the right side of the precast block 21 in the same procedure as that for the precast block 21. Then, after applying an adhesive to opposing wall surfaces of these precast blocks 21, the precast block 21 disposed later is moved to the left side via the carriage 43 to contact the wall surface of the pre-installed precast block 21. After that, the temporary P is inserted into the insertion holes 35 provided in the upper and lower portions or the side surfaces of the precast block 21.
The C steel bar 49 is inserted and tightened to integrate the adjacent precast blocks 21.
【0031】壁面に塗布する接着剤の可使時間が長い材
料を使用する場合には、プレキャストブロック21を一
度に数個まとめて一体化することができる。そして、こ
の一体化したプレキャストブロック21の右側に前述し
た方法と同様の手段でプレキャストブロック21を配置
して、直方体形状の梁37を形成する。この梁37の右
側端部と右側の塔柱5の内壁面との間には所定の間隙4
7が設けられている。When using a material having a long pot life of the adhesive applied to the wall surface, several precast blocks 21 can be integrated at once at a time. Then, the precast block 21 is arranged on the right side of the integrated precast block 21 by the same method as described above, and the rectangular parallelepiped beam 37 is formed. A predetermined gap 4 is provided between the right end of the beam 37 and the inner wall surface of the right column 5.
7 are provided.
【0032】次に、梁37の左側と右側の両間隙47に
梁37と塔柱5間を連設する連設部51を形成するいわ
ゆる間詰工を行なう。即ち、間隙47内に型枠17を組
み立て、この組み立てられた型枠17の内側に鉄筋を配
筋して枠組みを形成し、この枠組み内に塔柱5と梁37
との間を連通するシース53を設ける。そして、枠組み
内にコンクリートを打設した後に養生して型枠17を取
り除き連設部51を形成する。Next, in a gap 47 on both the left side and the right side of the beam 37, a so-called filling work is performed in which a continuous portion 51 for continuously connecting the beam 37 and the tower 5 is formed. That is, the form 17 is assembled in the gap 47, and a reinforcing bar is arranged inside the assembled form 17 to form a frame.
And a sheath 53 communicating between the sheath 53. Then, after the concrete is poured into the frame, the concrete is cured and the mold 17 is removed to form the continuous portion 51.
【0033】連設部51は前述した鉄筋コンクリート製
に限らず、間隙47内に樹脂製の隙間挿入部材を充填し
て形成することもできる。樹脂製の隙間挿入部材は、例
えば、エポキシモルタルを例示できる。The connecting portion 51 is not limited to the above-described reinforced concrete, but may be formed by filling the gap 47 with a resin gap inserting member. An example of the resin gap insertion member is epoxy mortar.
【0034】次に、ストランド55を一方の塔柱5に貫
通させ、一方の連設部51のシース53内を挿通し梁3
7を挿通した後に他方の連設部53のシース53内を挿
通し他方の塔柱5に貫通させる。ストランド55は複数
本設けられ、水平梁7の底部の他に上部にも設けられて
いる(図示せず)。また、側壁にも設けられる場合もあ
る。Next, the strand 55 is made to penetrate the one column 5, and the inside of the sheath 53 of the one connecting portion 51 is inserted through the beam 3.
7 is inserted into the sheath 53 of the other connecting portion 53 so as to penetrate the other column 5. A plurality of strands 55 are provided and provided not only at the bottom but also at the top of the horizontal beam 7 (not shown). Also, it may be provided on the side wall.
【0035】そして、このストランド55を緊張して水
平梁7に圧縮荷重を与えてプレストレスを有する1段目
の水平梁7とする。次に、図6(a),(b)に示すよ
うに、プレキャストブロック21に接続されたロープ2
3の固定を解除し、吊り桁25と台車43と吊り桁25
に接続されたロープ23とをクレーン9で引き上げた後
にこれら23,25,43を地上に吊り降ろす解除工程を
行なう。Then, the strand 55 is tensioned to apply a compressive load to the horizontal beam 7 to form the first-stage horizontal beam 7 having prestress. Next, as shown in FIGS. 6A and 6B, the rope 2 connected to the precast block 21
3 is released, and the suspension girder 25, the trolley 43 and the suspension girder 25 are released.
After lifting up the rope 23 connected to the ground by the crane 9, a release step of hanging these 23, 25, 43 on the ground is performed.
【0036】次に、水平梁増設工程を行なう。即ち、図
6(c)に示すように、ブラケット13間を連結するP
C鋼材19の緊張を解き、支保工桁15の塔柱5への連
結を解除して、1段目の水平梁7の上方の所定の部位に
ブラケット13と支保工桁15を移動させる。これらの
移動は1段目の水平梁7よりも上方の塔柱5に設けられ
たジャッキ11により行なわれる。そして、前記水平梁
架設工程を行なう。Next, a horizontal beam extension step is performed. That is, as shown in FIG. 6C, P
The tension of the C steel material 19 is released, the connection of the support girder 15 to the tower 5 is released, and the bracket 13 and the support girder 15 are moved to a predetermined position above the first-stage horizontal beam 7. These movements are performed by jacks 11 provided on the tower 5 above the horizontal beams 7 of the first stage. Then, the horizontal beam erection step is performed.
【0037】尚、支保工桁15等の移動は塔柱5の両側
に配置された支保工桁15等を同時に移動させてもよい
し、いずれか一方を移動させてから他方を移動させても
よい。The support girder 15 and the like may be moved by moving the support girder 15 and the like arranged on both sides of the tower 5 at the same time, or by moving one of them and then moving the other. Good.
【0038】この解除工程と水平梁増設工程からなるサ
イクルを4回繰り返して、第1の水平梁7の上方に上下
方向に所定の間隙を有した水平梁7を塔柱5間に4個架
設し、全体で5個の水平梁7を塔柱5間に設ける。The cycle consisting of the releasing step and the horizontal beam extension step is repeated four times, and four horizontal beams 7 having a predetermined gap in the vertical direction above the first horizontal beam 7 are installed between the tower columns 5. Then, a total of five horizontal beams 7 are provided between the tower columns 5.
【0039】次に、前記解除工程を行なった後にブラケ
ット13間を連結するPC鋼材19の緊張を解き、支保
工桁15の塔柱5への連結を解除して、これらをジャッ
キ13により地上に吊り降ろす。Next, after performing the releasing step, the tension of the PC steel material 19 connecting the brackets 13 is released, the connection of the support girder 15 to the tower 5 is released, and these are placed on the ground by the jack 13. Hang it down.
【0040】[0040]
【発明の効果】以上説明したように、本発明によれば、
支保工桁は塔柱の外側に上下移動可能に設けられるの
で、支保工桁を上方に移動させる際に、新たに構築され
た水平梁が邪魔をしてその移動を妨げることはなく、ま
た、支保工桁等を一括して上方に移動できる。As described above, according to the present invention,
Since the shoring girder is provided to be able to move up and down on the outside of the tower post, when moving the shoring girder upward, the newly constructed horizontal beam does not disturb and hinder the movement, The support girders and the like can be moved upward collectively.
【0041】従って、支保工桁の横移動は不要になり、
支保工桁を上方に移動させるための架設用の張り出し桁
や横移動用の張り出し桁の架設工が不要になり、また、
これらの架設工のアクセス用足場工や作業用足場工が不
要になるので高所作業がより少なくなって安全性がさら
に向上し、水平梁の施工期間が短縮して主塔施工の全体
の施工期間が短縮し、仮設材が従来技術と比較して少な
くてすむ。Therefore, the lateral movement of the shoring girder becomes unnecessary,
Eliminating the construction of the overhanging girder for moving the shoring girder upward and the overhanging girder for lateral movement becomes unnecessary.
Eliminating the need for access scaffolding and work scaffolding for these erection works reduces the need for work at heights and further improves safety, shortens the construction period of horizontal beams, and reduces the overall construction of the main tower. The period is shortened and the number of temporary materials is reduced as compared with the prior art.
【0042】また、最上段の水平梁の施工後に支保工桁
の横移動をせずに地上に吊り降ろすことができるので撤
去作業が極めて容易である。さらに、支保工桁は各水平
梁の施工に利用されるものであり、支保工桁をコンクリ
ートに埋設して水平梁の一部とする従来技術と比較し
て、支保工桁の転用が可能になる。Further, since the support girder can be hung on the ground without laterally moving after the uppermost horizontal beam is constructed, the removal work is extremely easy. Furthermore, the shoring girder is used for the construction of each horizontal beam, and the shoring girder can be diverted compared to the conventional technology in which the shoring girder is buried in concrete and part of the horizontal beam. Become.
【0043】また、水平梁は複数の構成ブロックを有し
この構成ブロックは軽量の材質で形成されているので、
構成ブロックをクレーンで吊り上げることができ、大型
のプレキャスト部材を仮設するための梁とこの梁を塔柱
に固定するための大型の固定手段が不要になる。Further, since the horizontal beam has a plurality of constituent blocks and these constituent blocks are formed of a lightweight material,
The building block can be lifted by a crane, and a beam for temporarily installing a large precast member and a large fixing means for fixing the beam to the tower are not required.
【0044】また、構成ブロックはプレキャスト部材な
ので、品質管理が容易であり高品質のコンクリート部材
を作製でき、また、高所でのコンクリート打設工が少な
くなり、コンクリートの供給管理が容易になる。Further, since the constituent blocks are precast members, quality control is easy and a high-quality concrete member can be manufactured, and concrete placing work at a high place is reduced, and the supply control of concrete is facilitated.
【図1】 本発明の一実施の形態におけるコンクリート
製主塔の水平梁の施工法を使用して築造される主塔を示
し、同図(a)は主塔の正面図であり、同図(b)は主
塔の側面図である。FIG. 1 shows a main tower constructed by using a method of constructing a horizontal beam of a concrete main tower according to an embodiment of the present invention, and FIG. 1 (a) is a front view of the main tower. (B) is a side view of the main tower.
【図2】 本発明の一実施の形態におけるコンクリート
製主塔の水平梁の施工法により架設される水平梁を示
し、同図(a)は水平梁の正面図であり、同図(b)は
同図(a)のA−A矢視の断面図である。FIG. 2 shows a horizontal beam erected by a method of constructing a horizontal beam of a concrete main tower according to an embodiment of the present invention. FIG. 2 (a) is a front view of the horizontal beam, and FIG. FIG. 2 is a sectional view taken along the line AA in FIG.
【図3】 本発明の一実施の形態におけるコンクリート
製主塔の水平梁の施工法の一工程を示す図であり、同図
(a)は第1段目の水平梁の施工を示す正面図であり、
同図(b)は同図(a)の側面図である。FIG. 3 is a view showing one step of a method of constructing a horizontal beam of a concrete main tower in one embodiment of the present invention, and FIG. 3 (a) is a front view showing construction of a first-stage horizontal beam; And
FIG. 2B is a side view of FIG.
【図4】 本発明の一実施の形態におけるコンクリート
製主塔の水平梁の施工法の図3(a)のB−B矢視に相
当する部分の側面図である。FIG. 4 is a side view of a part corresponding to the direction of arrow BB in FIG. 3 (a) of the method for constructing a horizontal beam of a concrete main tower in one embodiment of the present invention.
【図5】 本発明の一実施の形態におけるコンクリート
製主塔の水平梁の施工法の水平梁架設工程を示す正面図
である。FIG. 5 is a front view showing a horizontal beam erection step of the method of constructing a horizontal beam of a concrete main tower in one embodiment of the present invention.
【図6】 本発明の一実施の形態におけるコンクリート
製主塔の水平梁の施工法の水平梁増設工程の一部を示す
図である。FIG. 6 is a view showing a part of a horizontal beam extension step in a method of constructing a horizontal beam of a concrete main tower according to an embodiment of the present invention.
【図7】 従来技術のコンクリート製主塔の水平梁の施
工法を示す図である。FIG. 7 is a view showing a construction method of a horizontal beam of a concrete main tower according to the prior art.
【図8】 従来技術のコンクリート製主塔の水平梁の施
工法を示す図である。FIG. 8 is a view showing a method of constructing a horizontal beam of a conventional concrete main tower.
【図9】 従来技術のコンクリート製主塔の水平梁の施
工法を示す図である。FIG. 9 is a view showing a method of constructing a horizontal beam of a concrete main tower according to the prior art.
【図10】 従来技術のコンクリート製主塔の水平梁の
施工法を示す図である。FIG. 10 is a view showing a construction method of a horizontal beam of a concrete main tower according to the related art.
1 主塔(コンクリート製主塔) 3 基礎 5 塔柱 7 水平梁 13 ブラケット(部材) 15 支保工桁(部材) 17 型枠(部材) 21 プレキャストブロック(構成ブロック) 37 梁 51 連設部 DESCRIPTION OF SYMBOLS 1 Main tower (concrete main tower) 3 Foundation 5 Tower pillar 7 Horizontal beam 13 Bracket (member) 15 Supporting girder (member) 17 Formwork (member) 21 Precast block (composition block) 37 Beam 51 Connecting part
Claims (2)
定の間隙をおいた水平梁を複数個(n個)設けてコンク
リート製主塔を築造するコンクリート製主塔の水平梁の
施工法において、(イ)前記水平梁を施工する際に利用
される部材を前記塔柱の所定の部位に搬送する部材搬送
工程と、(ロ)前記部材搬送工程で搬送された部材を組
み立てて所定の部位に支保工桁を設けて水平梁の施工の
準備をする水平梁施工準備工程と、(ハ)水平梁を構成
する複数の構成ブロックを所定の部位に吊り上げ、これ
らの構成ブロック間を接着させて塔柱間の離間寸法より
も小さい長さを有する梁を形成し、この梁の両端部と塔
柱の側壁との間の間隙に塔柱と梁とを連設する連設部を
設けて塔柱間に水平梁を架設した後にこの水平梁に圧縮
荷重を作用させてプレストレスを有する水平梁とする水
平梁架設工程と、(ニ)前記水平梁架設工程で架設され
た水平梁よりも上方の所定の部位に前記支保工桁を移動
させた後に水平梁架設工程を行なうサイクルを(nー
1)回繰り返す水平梁増設工程と、 を備えたことを特徴とするコンクリート製主塔の水平梁
の施工法。A concrete main tower is constructed by constructing a concrete main tower by providing a plurality (n) of horizontal beams at predetermined intervals in the vertical direction between tower columns erected on a foundation. In the construction method, (a) a member transporting step of transporting a member used when constructing the horizontal beam to a predetermined portion of the tower post; and (b) assembling the member transported in the member transporting step. A horizontal beam construction preparation step of providing a support girder at a predetermined location to prepare for the construction of a horizontal beam; and (c) lifting a plurality of component blocks constituting the horizontal beam at a predetermined location, and A beam having a length smaller than the separation dimension between the tower columns is formed by bonding, and a connecting portion for continuously connecting the tower column and the beam to the gap between both ends of the beam and the side wall of the column is formed. After installing a horizontal beam between the tower columns, a compressive load is applied to this horizontal beam to A horizontal beam erection step of forming a horizontal beam having a restless; and (d) a horizontal beam erection step after moving the support girder to a predetermined portion above the horizontal beam erected in the horizontal beam erection step. A horizontal beam extension step of repeating a cycle to be performed (n-1) times, and a method of constructing a horizontal beam of a concrete main tower, comprising:
脂製の隙間挿入部材からなることを特徴とする請求項1
記載のコンクリート製主塔の水平梁の施工法。2. The connecting part in the horizontal beam erection step is made of a resin-made gap insertion member.
The construction method of the horizontal beam of the concrete main tower described.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP35361897A JPH11181725A (en) | 1997-12-22 | 1997-12-22 | Method for constructing horizontal beam of main tower made of concrete |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP35361897A JPH11181725A (en) | 1997-12-22 | 1997-12-22 | Method for constructing horizontal beam of main tower made of concrete |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| JPH11181725A true JPH11181725A (en) | 1999-07-06 |
Family
ID=18432073
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP35361897A Pending JPH11181725A (en) | 1997-12-22 | 1997-12-22 | Method for constructing horizontal beam of main tower made of concrete |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPH11181725A (en) |
Cited By (21)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103352428A (en) * | 2013-07-06 | 2013-10-16 | 中交路桥建设有限公司 | Suspension bridge cable bent tower beam non-support construction method |
| CN103866697A (en) * | 2014-04-10 | 2014-06-18 | 中铁二局股份有限公司 | Pier and horizontal tie beam bracket support synchronization construction method |
| CN108166396A (en) * | 2017-12-27 | 2018-06-15 | 中交路桥华南工程有限公司 | Prestressed Steel Wire Tension Installation, Construction Method and Steel Frame Structure of Tower Column on Cable Tower |
| CN109252447A (en) * | 2018-09-28 | 2019-01-22 | 东莞理工学院 | Prepressing operation method of high-altitude tower column cross beam support |
| CN109338900A (en) * | 2018-11-28 | 2019-02-15 | 中国铁建大桥工程局集团有限公司 | A kind of construction method of beam under main tower |
| CN110172915A (en) * | 2019-05-20 | 2019-08-27 | 中交路桥华东工程有限公司 | A kind of high tower shaped form crossbeam Joint Re-bar Construction |
| CN110318344A (en) * | 2019-06-28 | 2019-10-11 | 中交二航局第四工程有限公司 | A kind of No. 0 block bracket of novel steel box-girder and No. 0 block erection construction method |
| CN110804952A (en) * | 2019-11-14 | 2020-02-18 | 贵州省公路工程集团有限公司 | Suspension bridge beam prefabrication and assembly construction process |
| CN111005302A (en) * | 2019-12-30 | 2020-04-14 | 中交路桥华南工程有限公司 | Steel anchor beam installation method |
| CN112144412A (en) * | 2020-09-25 | 2020-12-29 | 四川交投建设工程股份有限公司 | Construction method of prefabricated assembled intercolumnar tie beam |
| CN112627048A (en) * | 2021-01-07 | 2021-04-09 | 中铁十六局集团第三工程有限公司 | Comprehensive prepressing method and device for tied arch bridge beam suspension construction beam lattice system |
| CN112900269A (en) * | 2021-01-12 | 2021-06-04 | 中铁七局集团武汉工程有限公司 | Construction process of cable tower cross beam |
| CN113026573A (en) * | 2021-04-01 | 2021-06-25 | 中铁二十三局集团第三工程有限公司 | Tie beam construction method of multi-beam cable tower |
| CN113494047A (en) * | 2021-07-30 | 2021-10-12 | 贵州路桥集团有限公司 | Steel-concrete composite beam cable-stayed bridge |
| CN113969547A (en) * | 2021-11-11 | 2022-01-25 | 无锡金诚工程技术服务有限公司 | U-shaped manned hanging basket type maintenance platform for large bridge tower |
| CN114086478A (en) * | 2021-11-25 | 2022-02-25 | 中铁广州工程局集团桥梁工程有限公司 | Main tower lower cross beam construction system and method with corbels serving as temporary supports |
| CN114855631A (en) * | 2022-05-26 | 2022-08-05 | 中交路桥建设有限公司 | Method for installing multi-beam steel cable tower |
| CN115341472A (en) * | 2022-08-04 | 2022-11-15 | 中铁四局集团有限公司 | Construction method for lower cross beam of main tower of highway-railway dual-purpose river-crossing A-type cable-stayed bridge |
| CN115506261A (en) * | 2022-10-31 | 2022-12-23 | 长安大学 | Bridge bent cap safety construction equipment |
| CN115573261A (en) * | 2022-10-21 | 2023-01-06 | 山西四建集团有限公司 | Construction method for embedded part of cast-in-place beam bracket of double-limb thin-wall pier |
| CN118516916A (en) * | 2024-05-15 | 2024-08-20 | 中国铁建港航局集团有限公司 | Bridge tower beam skeleton integrated lifting construction method |
-
1997
- 1997-12-22 JP JP35361897A patent/JPH11181725A/en active Pending
Cited By (27)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103352428A (en) * | 2013-07-06 | 2013-10-16 | 中交路桥建设有限公司 | Suspension bridge cable bent tower beam non-support construction method |
| CN103866697A (en) * | 2014-04-10 | 2014-06-18 | 中铁二局股份有限公司 | Pier and horizontal tie beam bracket support synchronization construction method |
| CN103866697B (en) * | 2014-04-10 | 2015-10-21 | 中铁二局股份有限公司 | A kind of bridge pier and straining beam calf support method for synchronously constructing |
| CN108166396A (en) * | 2017-12-27 | 2018-06-15 | 中交路桥华南工程有限公司 | Prestressed Steel Wire Tension Installation, Construction Method and Steel Frame Structure of Tower Column on Cable Tower |
| CN108166396B (en) * | 2017-12-27 | 2023-08-18 | 中交路桥华南工程有限公司 | Prestressed Steel Wire Tension Installation, Construction Method and Steel Frame Structure of Tower Column on Cable Tower |
| CN114277694B (en) * | 2017-12-27 | 2023-04-07 | 中交路桥华南工程有限公司 | Prestressed steel strand construction method for tower column on cable tower |
| CN114277694A (en) * | 2017-12-27 | 2022-04-05 | 中交路桥华南工程有限公司 | Prestressed steel strand construction method for tower column on cable tower |
| CN109252447B (en) * | 2018-09-28 | 2020-07-28 | 东莞理工学院 | Prepressing operation method of high-altitude tower column cross beam support |
| CN109252447A (en) * | 2018-09-28 | 2019-01-22 | 东莞理工学院 | Prepressing operation method of high-altitude tower column cross beam support |
| CN109338900A (en) * | 2018-11-28 | 2019-02-15 | 中国铁建大桥工程局集团有限公司 | A kind of construction method of beam under main tower |
| CN110172915A (en) * | 2019-05-20 | 2019-08-27 | 中交路桥华东工程有限公司 | A kind of high tower shaped form crossbeam Joint Re-bar Construction |
| CN110318344B (en) * | 2019-06-28 | 2024-04-19 | 中交二航局第四工程有限公司 | Novel steel box girder No. 0 block support and No. 0 block erection construction method |
| CN110318344A (en) * | 2019-06-28 | 2019-10-11 | 中交二航局第四工程有限公司 | A kind of No. 0 block bracket of novel steel box-girder and No. 0 block erection construction method |
| CN110804952A (en) * | 2019-11-14 | 2020-02-18 | 贵州省公路工程集团有限公司 | Suspension bridge beam prefabrication and assembly construction process |
| CN111005302A (en) * | 2019-12-30 | 2020-04-14 | 中交路桥华南工程有限公司 | Steel anchor beam installation method |
| CN112144412A (en) * | 2020-09-25 | 2020-12-29 | 四川交投建设工程股份有限公司 | Construction method of prefabricated assembled intercolumnar tie beam |
| CN112627048A (en) * | 2021-01-07 | 2021-04-09 | 中铁十六局集团第三工程有限公司 | Comprehensive prepressing method and device for tied arch bridge beam suspension construction beam lattice system |
| CN112900269A (en) * | 2021-01-12 | 2021-06-04 | 中铁七局集团武汉工程有限公司 | Construction process of cable tower cross beam |
| CN113026573A (en) * | 2021-04-01 | 2021-06-25 | 中铁二十三局集团第三工程有限公司 | Tie beam construction method of multi-beam cable tower |
| CN113494047A (en) * | 2021-07-30 | 2021-10-12 | 贵州路桥集团有限公司 | Steel-concrete composite beam cable-stayed bridge |
| CN113969547A (en) * | 2021-11-11 | 2022-01-25 | 无锡金诚工程技术服务有限公司 | U-shaped manned hanging basket type maintenance platform for large bridge tower |
| CN114086478A (en) * | 2021-11-25 | 2022-02-25 | 中铁广州工程局集团桥梁工程有限公司 | Main tower lower cross beam construction system and method with corbels serving as temporary supports |
| CN114855631A (en) * | 2022-05-26 | 2022-08-05 | 中交路桥建设有限公司 | Method for installing multi-beam steel cable tower |
| CN115341472A (en) * | 2022-08-04 | 2022-11-15 | 中铁四局集团有限公司 | Construction method for lower cross beam of main tower of highway-railway dual-purpose river-crossing A-type cable-stayed bridge |
| CN115573261A (en) * | 2022-10-21 | 2023-01-06 | 山西四建集团有限公司 | Construction method for embedded part of cast-in-place beam bracket of double-limb thin-wall pier |
| CN115506261A (en) * | 2022-10-31 | 2022-12-23 | 长安大学 | Bridge bent cap safety construction equipment |
| CN118516916A (en) * | 2024-05-15 | 2024-08-20 | 中国铁建港航局集团有限公司 | Bridge tower beam skeleton integrated lifting construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH11181725A (en) | Method for constructing horizontal beam of main tower made of concrete | |
| JP3940211B2 (en) | Construction method of horizontal beams for concrete main tower. | |
| JP2003193430A (en) | Construction method of composite truss bridge | |
| JP2008274637A (en) | Construction method for continuous viaduct | |
| JPH08504009A (en) | Arch construction method | |
| CN115387234A (en) | Template system of lower beam of ultrahigh rhombic tower pier and construction method | |
| JP3940212B2 (en) | Construction method of horizontal beams for concrete main tower. | |
| JP2000045231A (en) | Arch bridge erection method | |
| JPH02503099A (en) | Cable supported bridge and construction method | |
| JP6449637B2 (en) | Building construction method | |
| CN110761165B (en) | Steel web box girder installation system and construction method thereof | |
| JPH0657956A (en) | Construction of concrete structure | |
| JP7339477B2 (en) | Concrete column formwork construction device and concrete column formwork construction method using the same | |
| CN112681150A (en) | Prefabricated hoisting system for box-type arch bridge and construction method | |
| JPH09195228A (en) | Build-up trestle for bridge pier reinforcing work and its using method | |
| JP4375788B2 (en) | Construction method of upper-floor type suspension floor slab bridge | |
| JP2006207209A (en) | Construction method of upper-floor type suspension floor slab bridge | |
| CN211312154U (en) | Steel web box girder installation system | |
| JPH10266134A (en) | Construction method of bridge utilizing stretched cable | |
| JP2000257264A (en) | Cast-in-place method for PC structure | |
| KR20220112000A (en) | Descent apparatus downward construction system method using thereof | |
| JPH11323838A (en) | Bridge construction method | |
| CN119083577B (en) | Truss layer of super high-rise reinforced concrete structure and construction method | |
| JPH03125755A (en) | Constructing method for cylindrical multistoried structure | |
| CN114645515B (en) | Casting equipment and casting method for concrete segmental box girder |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Effective date: 20040903 Free format text: JAPANESE INTERMEDIATE CODE: A621 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20070327 |
|
| A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20070821 |