KR100603901B1 - Girder bridge construction make use of a part existing girder and that execution method - Google Patents

Girder bridge construction make use of a part existing girder and that execution method Download PDF

Info

Publication number
KR100603901B1
KR100603901B1 KR1020050128906A KR20050128906A KR100603901B1 KR 100603901 B1 KR100603901 B1 KR 100603901B1 KR 1020050128906 A KR1020050128906 A KR 1020050128906A KR 20050128906 A KR20050128906 A KR 20050128906A KR 100603901 B1 KR100603901 B1 KR 100603901B1
Authority
KR
South Korea
Prior art keywords
girder
bridge
slab
concrete
plate
Prior art date
Application number
KR1020050128906A
Other languages
Korean (ko)
Inventor
민경주
Original Assignee
한국철도시설산업 (주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한국철도시설산업 (주) filed Critical 한국철도시설산업 (주)
Priority to KR1020050128906A priority Critical patent/KR100603901B1/en
Application granted granted Critical
Publication of KR100603901B1 publication Critical patent/KR100603901B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 강교로 이루어진 철도교의 노후화 및 설계기준의 변경으로 교량의 안전성 확보를 위해 기존 거더를 활용하여 강성을 향상시켜 설치하는 것으로,The present invention is to install and improve the rigidity by utilizing the existing girder to ensure the safety of the bridge by the aging and change of design standards of the railway bridge made of steel bridge,

더욱 상세하게는 기존 거더의 강재를 활용하여 박스 형태의 경량 구조로 제작하여 교각 보강 등을 최소화하며 콘크리트로 매립된 거더의 피로수명에 영향을 받지 않는 경제적인 구조의 기존 거더를 활용한 판형교 유도상 구조 및 시공방법에 관한 것이다.More specifically, it is manufactured in a box-shaped lightweight structure using steel of the existing girder to minimize the reinforcement of bridges, and induces the plate-shaped bridge using the existing girder of economical structure that is not affected by the fatigue life of concrete-embedded girders. It relates to the phase structure and construction method.

이러한 본 발명은 I형 빔의 상측면에 천공구멍을 형성하여 횡 철근과 쉬스관을 설치하고 I형 빔의 전체면에 다수의 관통홀을 형성하여 철근을 배근하는 기존 거더와; 상기 기존 거더의 하측으로 교량 받침과 접착제가 도포되어 하부를 보강하는 바닥 보강판과;The present invention comprises a conventional girder to form a perforated hole in the upper side of the I-beam to install transverse reinforcement and sheath pipe and to form a plurality of through holes in the entire surface of the I-beam to reinforce the reinforcement; A bottom reinforcing plate for reinforcing a lower portion of the existing girder by applying a bridge bearing and an adhesive;

상기 돌출 거더의 경계면에 홈부가 형성되며 일체형으로 성형되는 하부 슬래브 및 상부 슬래브와;A lower slab and an upper slab formed with a groove on an interface of the protruding girder and integrally formed;

상기 기존 거더를 제거하고 상부 슬래브에 자갈과 침목 및 레일이 설치됨을 특징으로 하는 것이다.Removing the existing girder is characterized in that the gravel and sleepers and rails are installed on the upper slab.

철도 판형교, 철근콘크리트, 슬래브, PC 강선, PC합성형교, 판형교 유도상화 Railway plate bridge, reinforced concrete, slab, PC steel wire, PC composite bridge, plate bridge bridge

Description

기존 거더의 일부를 활용한 판형교 유도상 구조 및 시공방법{Girder bridge construction make use of a part existing girder and that execution method}Girder bridge construction make use of a part existing girder and that execution method}

도 1 은 기존 거더에 대한 설치상태 정면도1 is a front view of the installation state for the existing girder

도 2 는 기존 거더에 대한 설치상태 측면도Figure 2 is a side view of the installation state for the existing girder

도 3 는 기존 거더에 대한 설치상태 사시도3 is a perspective view of the installation state for the existing girder

도 4 는 본 발명중 거더의 천공 및 보강에 대한 정면도4 is a front view of the perforation and reinforcement of the girder of the present invention

도 5 는 본 발명중 거더의 천공 및 보강에 대한 측면도Figure 5 is a side view of the perforation and reinforcement of the girder of the present invention

도 6 은 본 발명중 거더의 천공 및 보강에 대한 사시도Figure 6 is a perspective view of the perforation and reinforcement of the girder of the present invention

도 7 은 본 발명중 기존거더에 철근을 배근한 상태의 정면도Figure 7 is a front view of the state reinforcement to the existing girder in the present invention

도 8 은 본 발명중 철근을 배근한 상태의 측면도Figure 8 is a side view of the reinforcement state in the present invention

도 9 는 본 발명중 철근을 배근한 상태의 사시도9 is a perspective view of the reinforcement state in the present invention

도 10 은 본 발명중 슬래브를 완성한 상태의 정면 단면도10 is a front sectional view of a completed slab in the present invention;

도 11 은 본 발명중 슬래브를 완성한 상태의 측면도Figure 11 is a side view of the completed state of the slab of the present invention

도 12 는 본 발명중 슬래브를 완성한 상태의 사시도12 is a perspective view of a completed slab in the present invention

도 13 은 본 발명중 돌출 거더를 제거하고 에폭시를 코팅한 상태의 정면도13 is a front view of a state in which the protruding girder is removed and the epoxy is coated in the present invention;

도 14 는 본 발명중 돌출 거더를 제거하고 에폭시를 코팅한 상태의 측면도Figure 14 is a side view of a state in which the protruding girder is removed and the epoxy coating in the present invention

도 15 는 본 발명중 돌출 거더를 제거하고 에폭시를 코팅한 상태의 사시도Figure 15 is a perspective view of a state in which the protruding girder is removed and the epoxy coating in the present invention

도 16 은 본 발명의 완성상태를 나타낸 정면도16 is a front view showing a completed state of the present invention;

도 17 은 본 발명의 완성상태를 나타낸 측면도17 is a side view showing a completed state of the present invention

도 18 은 본 발명의 완성상태를 나타낸 사시도18 is a perspective view showing a completed state of the present invention

[도면의 주요 부분에 대한 부호의 설명][Description of Symbols for Main Parts of Drawing]

10 : 기존 거더 11 : 침목10: Original girder 11: sleepers

12 : 레일 13 : I형 빔12: rail 13: I-beam

14 : 천공구멍 15 : 수직 보강판14 hole punch 15 vertical reinforcement plate

16 : 교량 받침 17 : 교좌장치16: bridge bearing 17: bridge device

18 : 측면 보강판 19 : 철근 관통홀18: side reinforcement plate 19: rebar through hole

20 : 횡 철근 21 : 바닥 보강판20: horizontal rebar 21: floor reinforcement plate

22 : 거푸집 23 : 철근22: formwork 23: rebar

24 : 복부 25 : 하부슬래브24 abdomen 25 lower slab

26 : 공간 27 : 쉬스관26: space 27: sheath tube

28 : 상부 슬래브 29 : 외벽28: upper slab 29: outer wall

30 : 홈부 31 : 돌출 거더30: groove 31: protrusion girder

32 : 접착제 33 : 에폭시32: adhesive 33: epoxy

34 : 상부슬래브 바닥판 35 : 교측보도34: upper slab bottom plate 35: bridge sidewalk

36 : 도상 자갈36: icon gravel

본 발명은 강교로 이루어진 철도교의 노후화 및 설계기준의 변경으로 교량의 안전성 확보를 위해 기존 거더를 활용하여 강성을 향상시켜 설치하는 것으로,The present invention is to install and improve the rigidity by utilizing the existing girder to ensure the safety of the bridge by the aging and change of design standards of the railway bridge made of steel bridge,

더욱 상세하게는 기존 거더의 강재를 활용하여 박스 형태의 경량 구조로 제작하여 교각 보강 등을 최소화하며 콘크리트로 매립된 거더의 피로수명에 영향을 받지 않는 경제적인 구조의 기존 거더를 활용한 판형교 유도상 구조 및 시공방법에 관한 것이다.More specifically, it is manufactured in a box-shaped lightweight structure using steel of the existing girder to minimize the reinforcement of bridges, and induces the plate-shaped bridge using the existing girder of economical structure that is not affected by the fatigue life of concrete-embedded girders. It relates to the phase structure and construction method.

일반적으로 철도교는 철근콘크리트교에 비하여 유지관리가 어려운 무도상궤도 형태의 강교가 다수 존재하고 있으며, 이러한 강교를 개량하는 공사가 다년간 진행되어왔다. 이러한 개량방법으로는 유도상화 또는 강교를 보강하고 궤도를 개량하는 공법들이 있다.In general, there are a lot of steel bridges in the form of ballistic tracks, which are difficult to maintain, compared to reinforced concrete bridges. Railway bridges have been under construction for many years. Such improvement methods include methods of reinforcing induced ignition or steel bridges and improving tracks.

유도상이란, 철도교에 있어서 레일 및 이를 받치고 있는 침목과 자갈이 깔려있는 상태를 말한다. 무도상은 상기에서 자갈이 깔려 있지 않은 상태를 말한다.An induction phase refers to a state in which a rail, a sleeper and gravel supporting the rail are laid in a railway bridge. A ballless phase refers to a state in which gravel is not laid in the above.

일반적으로 과거에 시공된 철도교는 강교로써 하천을 지나거나 계곡 사이를 지나는 등 지반에 설치되지 않은 대부분의 철도교는 도 1 과 같이 무도상 강교로 건설되어 있다.In general, railroad bridges constructed in the past are steel bridges that pass through rivers or valleys, and most railway bridges that are not installed on the ground are constructed as martial arts steel bridges as shown in FIG.

종래의 철도교는 평행하게 길이방향으로 설치된 한 쌍의 레일(12)이 일정한 간격의 폭 방향으로 설치되는 침목(11)이 받침하고, 이 침목의 하부로는 기존 거더(10)가 길이 방향으로 받침되며, 이 기존 거더(10)의 교대 또는 교각의 상부 위치에는 교좌장치(17)가 설치되어 있다.Conventional railway bridges are supported by a sleeper (11) in which a pair of rails (12) are installed in the longitudinal direction in parallel in the width direction at regular intervals, the existing girder (10) is supported in the longitudinal direction at the bottom of the sleeper In the upper position of the alternating or pier of the existing girder 10, the bridge device 17 is installed.

이러한 종래의 철도교는 거더 바탕면을 그라인딩하여 콘크리트와의 부착을 좋게 하기 위한 개량작업을 하고, 거더에 철근배근을 위한 구멍을 뚫고, 상기 천공된 구멍을 통하여 철근을 배근하고 슬래브 거푸집을 설치하되, 교각 하부의 지면 고르기 및 걸림돌 철거 등의 단계 및 동바리 서포터를 지지설치하며, 상기 슬래브 거푸집에 콘크리트를 타설하고, 양생 후 서포터 및 거푸집의 탈형 후 슬래브 상부로 노출된 거더 돌출부를 절단해내어 그 자리에 슬래브의 방수처리를 하고, 자갈로 슬래브 상에 유도상화하여 완성한다.Such a conventional railway bridge is to improve the adhesion to the concrete by grinding the base surface of the girder, drill holes for reinforcement in the girder, reinforce the reinforcement through the perforated holes and install the slab formwork, It supports the steps of leveling the ground and removing stumbling blocks under the pier, and supports the grouping supporters.Place concrete on the slab formwork, cut the girder protrusion exposed to the top of the slab after demolding the supporter and formwork after curing, Waterproofing of the slab is completed by induction ignition on the slab with gravel.

그러나 이러한 종래의 구조에 따른 방법은, 슬래브의 타설 및 양생 중에도 철로 위로 차량이 운행되어야만 하기 때문에 슬래브의 균열 및 재료 분리에 따른 구조적 강성에 문제가 발생할 수 있다.However, this conventional structure method may cause problems in structural stiffness due to cracking and material separation of the slab because the vehicle must be driven over the railroad during slab casting and curing.

이러한 결점을 방지하기 위하여 특허 제415768호(2004. 1. 16. 공고)와 같이, 유도상화 시공 중에 열차의 동 하중에 의한 진동 충격을 방지하면서 시공되게 하며, 지면으로부터 동바리 설치에 대한 문제점을 해소하기 위해 교각 상에 설치되는 조립식 브래킷 동바리에 의한 시공을 한 것이고, 조립/분해 가능한 가설구조로써 유도상화를 위해 단계별로 이동하면서 시스템 이동식으로 그 시공이 양호하게 한 것이다.In order to prevent such defects, as in Patent No. 415768 (January 16, 2004), the construction is performed while preventing the vibration impact caused by the dynamic load of the train during the induction burn construction, and solves the problem of installing the club from the ground. The construction is done by the prefabricated brackets installed on the piers, and the construction is good by moving the system while moving step by step for the induction as an assembly / disassembly hypothesis structure.

이러한 종래의 구조를 구체적으로 설명하면, 평행하게 길이방향으로 설치된 한 쌍의 레일은 일정 간격의 폭 방향으로 설치되는 목재 침목이 받침하고, 이 침목의 하부 길이방향으로는 거더가 받침 되고, 이 거더와 교대 또는 교각 상부에는 교좌장치가 개재되어 있는 통상의 철도교에 있어서, 기존 거더를 철거하되,Specifically, the conventional structure of a pair of rails installed in parallel in the longitudinal direction is supported by a wooden sleeper installed in a width direction at a predetermined interval, and a girder is supported in the lower longitudinal direction of the sleeper. In the ordinary railway bridge with a bridge device intersects with or on the upper part of the bridge, the existing girder is to be removed,

각각의 교대 또는 교각상에 설치되는 유압잭 받침용 브래킷;Hydraulic jack support brackets installed on each shift or piers;

상기 브래킷의 양측 상부면에 높이 보강재를 개재하여 설치되는 제1유압잭;First hydraulic jacks installed on both upper surfaces of the bracket via height reinforcing members;

상기 제1유압잭이 설치된 각각의 교각 간격 정도의 길이를 갖고, 제1유압잭 상부에 얹어지는 한 쌍의 열차 하중 지지용 제2거더;A pair of second girders for supporting a train load having a length of each pier interval in which the first hydraulic jacks are installed and mounted on an upper portion of the first hydraulic jacks;

상기 제2거더의 상부에 일정간격을 가지며 폭 방향으로 설치하되, 상기 각각의 목재침목 사이에 위치하여 레일 저면에 개재되어 제2거더에 조립 고정되는 강재 침목;Steel sleepers which have a predetermined interval on the upper portion of the second girder and are installed in the width direction, interposed between the respective wooden sleepers and interposed on the bottom of the rail and assembled and fixed to the second girder;

상기 브래킷의 양측 단차면으로 안착되는 제2유압잭;A second hydraulic jack seated on both sides of the bracket;

상기 제2유압잭이 설치된 각각의 교각 간격 정도의 길이를 갖고 상기 제2유압잭 상부에 얹어지는 한 쌍의 종부재와;A pair of longitudinal members mounted on the second hydraulic jack and having a length about the respective bridge gaps in which the second hydraulic jacks are installed;

이 종부재 상면의 폭방향 일정간격으로 설치되는 횡부재로 조립되는 격자형 공중 동바리;A lattice type aerial club assembled with a transverse member provided at regular intervals in a width direction of the upper surface of the longitudinal member;

상기 공중 동바리로 지지가 되는 거푸집에 의해 양생 된 슬래브; 및A slab cured by formwork supported by the aerial club; And

침목과 슬래브 사이에 자갈 메우기를 하여 유도상화한 구조로 된 것으로 특징으로 한다.It is characterized in that the structure is induced by the gravel filling between the sleepers and the slab.

그러나 이러한 종래의 구조는 교각을 이용하여 설치되는 공중 동바리를 추가로 설치해야 하기 때문에 공중 동바리의 설치 및 해체를 위한 시간이 소모된다.However, this conventional structure is time-consuming for the installation and disassembly of aerial clubs because it is necessary to install additional aerial clubs that are installed using the bridge.

이러한 유도상 슬래브교량은 단면의 역학적 효율성이 감소되어 기존판형교량의 중량보다 약 10~20배정도의 중량구조가 되기 때문에 시공성이 저하되고, 교량의 하부구조인 교각이나 기초에 대한 보강이 필요한 경우가 많으므로 하부구조 보강비 등의 시공비가 더 소요될 수 있다.Such inductive slab bridge is reduced in mechanical efficiency of the cross-section, which is about 10 to 20 times the weight of the existing plate-shaped bridge, so the workability is reduced, and reinforcement of the bridge or foundation, which is the substructure of the bridge, is necessary. Since much construction cost such as reinforcement of the lower structure may be more expensive.

본 발명은 이러한 종래의 결점을 해소하기 위하여 안출된 것으로, 판형의 기존 거더의 강재 하부를 활용하여 강성을 높이고 내구성과 사용성을 높이도록 함을 목적으로 한다.The present invention has been made to solve such a conventional drawback, and aims to increase the rigidity and increase the durability and usability by utilizing the lower part of the steel plate of the existing girder of the plate shape.

본 발명은 기존 거더의 I형 빔에 의하여 분리되는 슬래브 콘크리트로 일체화시켜 안전성 및 내구성을 증진시키도록 함을 목적으로 한다.An object of the present invention is to integrate the slab concrete separated by the I-beam of the existing girder to promote safety and durability.

본 발명은 박스형 거더의 경량 구조로 제작하며 오히려 강성이 크게 되어 거더의 피로수명에 영향을 받지 않도록 함을 목적으로 한다.The present invention aims to produce a lightweight structure of the box-type girders and rather to increase the rigidity so as not to be affected by the fatigue life of the girder.

본 발명은 I형 빔의 상측면에 천공구멍을 형성하여 횡 철근과 쉬스관을 설치하고 I형 빔의 전체면에 다수의 관통홀을 형성하여 철근을 배근하는 기존 거더와;The present invention comprises a conventional girder to form a perforated hole in the upper side of the I-beam to install transverse reinforcement and sheath pipe and to form a plurality of through holes in the entire surface of the I-beam to reinforce the reinforcement;

상기 기존 거더의 하측으로 교량 받침과 접착제가 도포되어 하부를 보강하는 바닥 보강판과;A bottom reinforcing plate for reinforcing a lower portion of the existing girder by applying a bridge bearing and an adhesive;

상기 돌출 거더의 경계면에 홈부가 형성되며 일체형으로 성형되는 하부 슬래브, 복부, 상부 슬래브 및 외벽과;A lower slab, an abdomen, an upper slab and an outer wall which are formed integrally with a groove at an interface of the protruding girder;

상기 기존 거더를 제거하고 상부 슬래브에 자갈과 침목 및 레일이 설치됨을 특징으로 하는 것이다.Removing the existing girder is characterized in that the gravel and sleepers and rails are installed on the upper slab.

이하에서 본 발명의 바람직한 실시예를 첨부한 도면에 따라 상세하게 설명하기로 한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

본 발명은 도 1 내지 도 3 에 도시한 바와 같이 I형 빔(13)으로 이루어진 상측으로 침목(11)이 일정한 간격에 연결되어 있으며 그 상측으로 한 쌍의 레일(12)이 설치된 기존 거더(10)로 이루어져 있다.In the present invention, as shown in FIGS. 1 to 3, the girder 11 is connected to the upper side of the I-shaped beam 13 at regular intervals and a pair of rails 12 are installed on the upper side of the existing girder 10. )

이러한 기존 거더(10)의 I형 빔(13) 표면에 되어 있는 도장은 콘크리트의 부착력을 저하시키게 되므로 I형 빔(13)의 표면 도장을 제거하고 이곳에 신구접착제를 도포한다.Since the coating on the surface of the existing I-beam 13 of the existing girder 10 reduces the adhesion of concrete, the surface-painting of the I-beam 13 is removed and the new adhesive is applied thereto.

도장이 제거된 기존 거더(10)의 I형 빔(13)에는 도 4 내지 도 5, 도 6 에 도시한 바와 같이, 측면 상측으로 일정한 간격을 절단하여 사각형이나 원형의 천공구멍(14)을 설치하고, 이 천공구멍(14)의 양측에는 세로방향으로 수직 보강판(15)을 설치한다.In the I-beam 13 of the existing girder 10, from which the painting is removed, as shown in FIGS. 4 to 5 and 6, a predetermined interval is cut to the upper side and a rectangular or circular drilling hole 14 is installed. In addition, vertical reinforcement plates 15 are provided on both sides of the drilling hole 14 in the longitudinal direction.

상기 천공구멍(14)에는 상부 슬래브(28)가 타설될 위치에 횡 철근(20)을 다수 배치하여 배근한다.The perforated hole 14 is arranged by placing a plurality of transverse reinforcing bar 20 in the position where the upper slab 28 is to be placed.

상기 천공구멍(14)이 형성되지 않은 I형 빔(13)에는 다수의 철근 관통홀(19)을 천공하여 이곳에 철근(23)을 관통시켜 복부(24)가 타설될 위치에 배근한다.The I-beam 13, in which the perforation hole 14 is not formed, drills a plurality of rebar through holes 19 and penetrates the reinforcing bar 23 therein, and reinforces the position where the abdomen 24 is to be placed.

상기 I형 빔(13)의 양쪽 선단에는 외측으로 측면 보강판(18)을 설치하고, 교량 하부에는 PC 또는 FREP(섬유보강에폭시패널, Fiber Reinforced Epoxy Panel) 등의 보강판(21)으로 둘러싸고 이곳에 무수축몰탈 또는 에폭시 등과 같은 접착제(32)를 충진한다.Side end reinforcement plates 18 are installed on both ends of the I-beam 13 on the outside, and under the bridge, they are surrounded by reinforcement plates 21 such as PC or FREP (Fiber Reinforced Epoxy Panel). Is filled with an adhesive 32 such as anhydrous mortar or epoxy.

또한, 기존 거더(10)의 내측으로 공간(26)이 중앙에 형성되도록 하고 거푸집(22)의 내부에서 상부 슬래브(28)가 위치하는 부분에서 횡 방향으로 쉬스관(27)을 설치하여 포스트텐션용 PC 강선을 배치한다.In addition, the space 26 is formed in the center of the existing girder 10 and the post tension is provided by installing the sheath pipe 27 in the transverse direction at the portion where the upper slab 28 is located inside the formwork 22. Place the PC steel wire.

콘크리트 타설 후 기존 거더(10)와 콘크리트의 접합을 위하여 절단되지 않은 I형 빔(13)의 일부분에 홈부(30)가 형성되도록 스티로폼 등을 삽입하여 이곳에 콘크리트가 타설되지 않도록 한다.After the concrete is placed, a styrofoam is inserted into a portion of the I-shaped beam 13 that is not cut to join the existing girder 10 and concrete, so that the concrete is not poured there.

거푸집(22)에 의하여 복부(24), 하부 슬래브(25), 상부 슬래브(28) 및 외벽(29)이 일체형으로 콘크리트에 의하여 양생 된 후 거푸집(22)을 제거하는 한편, 홈부(30)로 돌출된 돌출 거더(31)를 절단하여 제거시킨다.The abdomen 24, the lower slab 25, the upper slab 28 and the outer wall 29 are integrally cured by concrete by the formwork 22, and then the formwork 22 is removed, while the groove portion 30 is removed. The protruding protruding girder 31 is cut and removed.

돌출 거더(31)가 제거되면 홈부(30)만 남게 되므로 이 홈부(30)에 콘크리트의 일체화 및 I형 빔(13)에 의한 누수를 방지하지 위하여 에폭시(33)를 충진한다.When the protruding girder 31 is removed, only the groove part 30 remains, and thus the epoxy part 33 is filled in the groove part 30 so as to prevent the integration of concrete and the leakage caused by the I-beam 13.

돌출 거더(31)를 제거하는 경우에는 궤도 설치공사(차단공사)시에 제거한다.When the projecting girders 31 are removed, they are removed at the time of the track installation work (blocking work).

상기 콘크리트의 타설 후 건조수축 등으로 인한 기존 거더(10)의 강판과 콘크리트의 분리가 일어나지 않도록 팽창 콘크리트를 사용하며, 양생시 균열 등이 발 생치 않도록 유의한다.After placing the concrete, expansion concrete is used to prevent separation of the steel plate and concrete of the existing girder 10 due to dry shrinkage, etc., and care should be taken to prevent cracking during curing.

콘크리트의 양생이 완료된 후 쉬스관(27)을 통과하는 PC 강선을 긴장시켜 상부 슬래브(28)에 긴장력을 형성한다.After curing of concrete is completed, the PC steel wire passing through the sheath pipe 27 is tensioned to form a tension force in the upper slab 28.

이와 같이 PC를 긴장시킨 이후에 궤도 설치공사(차단공사)를 실시하는 것으로,In this way, after the PC is tense, the track installation construction (blocking construction) is carried out,

기존에 설치된 레일(12)과 침목(11)을 제거하고 돌출 거더(31)의 제거작업을 수행하고 절단된 홈부(30)에 에폭시(33)를 주입하여 내외부를 일체화하며, 상부 슬래브(28)의 상측 바닥에 에폭시(33)를 살포하고 우레탄판 또는 FREP판(34) 등을 부착하여 누수방지와 진동 저감효과를 도모한다.Remove the existing rail 12 and the sleeper 11 and remove the projecting girder 31 and inject the epoxy 33 into the cut groove 30 to integrate the inside and outside, the upper slab 28 Epoxy 33 is sprayed on the bottom of the upper surface and urethane plate or FREP plate 34 is attached to prevent leakage and reduce vibration.

상부 슬래브(28)의 상측에는 자갈(36)을 살포하고 침목(11) 및 레일(12)을 설치하고 뒷정리를 통하여 궤도설치공사를 종료한다.On the upper side of the upper slab 28, the gravel 36 is sprayed and the sleepers 11 and the rails 12 are installed, and the track installation work is finished through rearranging.

그리고 외벽(29)의 한쪽 또는 양쪽에는 교측보도(35)를 추가로 설치할 수 있는 것이다.And one side or both sides of the outer wall 29 can be further provided with a bridge sidewalk (35).

이러한 본 발명은 기존 거더(10)의 I형 빔(13)을 그대로 설치한 상태에서 활용하여 강성을 높이고 내구성과 사용성을 높인 구조를 제공하는 것이다.The present invention is to provide a structure to increase the rigidity and increase the durability and usability by utilizing in the state of installing the I-beam 13 of the existing girder 10 as it is.

공사중에는 궤도설치공사 외에 열차 서행 및 차단 등이 필요하지 않고, 기존 거더(10)에 의하여 하부 슬래브(25), 복부(24), 상부 슬래브(28) 및 외벽(29)을 일체화시켜 안전성 및 내구성을 증진시키는 것이다.During construction, trains do not need to slow down or block other than the track installation, and the lower slab 25, the abdomen 24, the upper slab 28 and the outer wall 29 are integrated by the existing girder 10 for safety and durability. To promote it.

콘크리트 슬래브의 쉬스관(27)에 설치되는 PC 강선으로 포스트텐션하여 슬래 브 콘크리트에 횡 방향 인장력이 발생하지 않도록 한다.Post-tension with a PC steel wire installed in the sheath pipe 27 of the concrete slab to prevent the transverse tension in the slab concrete.

I형 빔(13)의 내부에 천공구멍(14)을 형성하고, 이곳을 보강하기 위하여 양측으로 수직 보강판(15)을 설치하여 횡 철근(20)의 배근을 통하여 횡 방향으로 슬래브를 일체화시키며, 선로 양도에 대비하여 슬래브(24, 25, 28)의 높이에 여유를 두는 것이다.A perforated hole 14 is formed inside the I-beam 13, and vertical reinforcement plates 15 are installed on both sides to reinforce the slab, and the slab is integrated in the transverse direction through the reinforcement of the transverse steel 20. In preparation for the transfer of tracks, the slabs (24, 25, 28) are allowed to leave the height.

슬래브(24, 25, 28, 29)를 박스형으로 성형하여 경량구조로 제작하므로 교각 보강 등을 최소화할 수 있으며, 비틀림 저항 및 열차의 사행운동에 효과적으로 저항할 수 있도록 한다.Since the slab (24, 25, 28, 29) is formed into a box-shaped lightweight structure can minimize the bridge reinforcement, and can effectively resist torsional resistance and meandering movement of the train.

기존 거더(10)가 슬래브(24, 25, 28)의 내부에 위치하게 되므로 도장 등 유지관리가 필요 없으며, 유도상 슬래브 거더보다 경량이면서 강성은 오히려 크게 되어 콘크리트로 매립된 기존 거더(10)의 피로수명에 영향을 받지 않는 경제적인 구조를 제공하는 것이다.Since the existing girder 10 is located inside the slabs 24, 25 and 28, there is no need for maintenance, such as painting, and it is lighter than the slab girder in induction and the rigidity is rather large so that the existing girder 10 is embedded with concrete. It provides an economical structure that is not affected by fatigue life.

상부 슬래브(28)는 PC 강선을 통하여 긴장시킨 것이어서 강성 저하시 재긴장시키는 것이 가능하며, 거더 설치를 위한 가설도로, 작업장, 대형크레인, 밀어넣기 위한 가벤트공사 등이 필요 없고, 거더 설치공사가 필요 없으므로 획기적으로 공사비를 절감시킬 수 있다.The upper slab 28 is tensioned through the PC steel wire, it is possible to re-tension when the rigidity is reduced, there is no need for a temporary road for the installation of girder, workshop, large cranes, the construction work for pushing, etc. Since it is not necessary, the construction cost can be drastically reduced.

이하에서 본 발명을 구체적인 실시예를 통하여 상세하게 설명하기로 한다.Hereinafter, the present invention will be described in detail through specific examples.

[실시예]EXAMPLE

(1). 기존 거더 도장제거 단계(One). Existing girder removal step

기존 거더(10)의 I형 빔(13)과 콘크리트의 부착력을 높이기 위하여 표면의 도장을 제거하고 이곳에 신구접착제를 도포한다.In order to increase the adhesion of the I-beam 13 and the concrete of the existing girder 10, the surface of the coating is removed and a new adhesive is applied thereto.

(2). 빔 천공 단계(2). Beam drilling step

I형 빔(13)의 측면을 천공하여 다수의 철근 관통홀(19)을 형성하여 이곳에 철근(23)을 배근한다.A side of the I-beam 13 is drilled to form a plurality of rebar through holes 19 to reinforce the reinforcing bar 23.

(3). 빔 천공 및 보강 단계(3). Beam drilling and reinforcement steps

하부 슬래브(25), 복부(24) 및 상부 슬래브(28)를 일체화하기 위하여 상부 슬래브(28)가 타설될 위치에 천공구멍(14)을 성형하고 그 양측으로 보강을 위하여 수직 보강판(15)을 설치하며 천공구멍(14)에 다수의 횡 철근(20)과 쉬스관(27)을 관통시켜 횡 철근(20)을 배근한다.In order to integrate the lower slab 25, the abdomen 24 and the upper slab 28, the perforated holes 14 are formed at the position where the upper slab 28 is to be cast and the vertical reinforcement plate 15 for reinforcement on both sides thereof. And install a plurality of transverse reinforcing bar 20 and the sheath pipe 27 through the drilling hole 14 to reinforce the transverse reinforcing bar 20.

(4). 거더의 하부 보강 단계(4). Lower reinforcement stage of the girder

기존 거더(10)의 하측에 PC 또는 FREP 등으로 이루어진 바닥 보강판(21)과 교량 받침(16)으로 둘러싸고 이곳에 무수축몰탈 또는 에폭시 등을 충진하여 하측을 보강하고 기존 거더(10)의 유지보수가 필요 없도록 한다.The bottom side of the existing girder 10 is surrounded by a bottom reinforcement plate 21 made of PC or FREP, etc. and the bridge support 16, and filled with non-contraction mortar or epoxy therein to reinforce the lower side and maintain the existing girder 10. No maintenance is required.

(5). 거푸집 설치 단계(5). Formwork Installation Steps

도 7에서와 같이 공간(26)을 갖는 박스 형태로 설치되도록 하고 상부 슬래브(28), 외벽(29) 및 복부(24)가 일체형으로 성형하도록 거푸집(22)을 설치한다.As shown in FIG. 7, the mold 22 is installed so that the upper slab 28, the outer wall 29, and the abdomen 24 are integrally molded.

(6). 콘크리트 타설 단계(6). Concrete pouring steps

홈부(30)가 형성되도록 스티로폼 등을 삽입하고 거푸집(22)의 내부에 콘크리트를 타설하여 양생시킨다.Styrofoam or the like is inserted to form the groove part 30 and the concrete is poured into the mold 22 to cure.

콘크리트는 타설 후 건조수축 등으로 인한 I형 빔(13)과의 분리가 일어나지 않도록 팽창 콘크리트를 사용하며, 양생시 균열 등이 발생하지 않도록 유의한다.The concrete uses expanded concrete to prevent separation from the I-beam 13 due to dry shrinkage, etc. after casting, and care should be taken to prevent cracking during curing.

(7). 긴장력 도입 단계(7). Tension Introduction Stage

콘크리트의 양생이 완료된 후 PC 강선을 긴장시켜 상부 슬래브(28)에 긴장력을 도입한다.After curing of concrete is completed, tension is applied to the upper slab 28 by tensioning the PC steel wire.

(8). 돌출 거더 제거 단계(8). Extruded girder removal steps

거푸집(22)을 제거하고 콘크리트에 매입되지 않고 돌출된 돌출 거더(31)를 절단하여 침목(11)과 레일(12)을 함께 제거하는 것이다.Removing the formwork 22 and cutting the protruding girder 31 protruding without being embedded in concrete to remove the sleepers 11 and the rail 12 together.

(9). 상부 슬래브 마감 단계(9). Upper slab finishing stage

홈부(30)에 에폭시(33)를 주입하여 내외부를 일체화하며, 상부 슬래브(28)의 내부 바닥에 에폭시를 살포하고, 그 위에 우레탄판 또는 FREP판(34) 등을 부착하여 누수방지와 I형 빔(13)의 진동 저감효과를 도모한다.Inject epoxy 33 into the groove 30 to integrate the inside and outside, spray epoxy on the inner bottom of the upper slab 28, and attach urethane plate or FREP plate 34 on it to prevent leakage and I type The vibration reduction effect of the beam 13 is aimed at.

(10). 자갈, 침목 및 레일 설치 단계(10). Steps for installing gravel, sleepers and rails

상부 슬래브(28)의 상측 내부에 자갈(36)을 살포하고 침목(11)과 레일(12)을 설치하고 종료한다.The gravel 36 is sprayed into the upper side of the upper slab 28, and the sleeper 11 and the rail 12 are installed and finished.

본 발명은 기존 거더를 그대로 활용하여 강성을 높이고 내구성과 사용성을 높이는 효과를 제공하는 것이다.The present invention is to utilize the existing girder as it is to provide the effect of increasing the rigidity and durability and usability.

본 발명은 공사중에는 궤도설치공사 외에 열차 서행 및 차단 등이 필요하지 않고, 기존 거더에 의하여 슬래브를 일체화시켜 안전성 및 내구성을 증진시키는 효과를 제공하는 것이다.The present invention does not need to slow down and block trains other than the track installation work, and provides an effect of increasing safety and durability by integrating the slab by the existing girder.

본 발명은 슬래브를 이루는 콘크리트 내부의 쉬스관에 설치되는 PC 강선으로 포스트텐션하여 슬래브 콘크리트에 횡 방향 인장력이 발생하지 않도록 하는 효과를 제공한다.The present invention provides the effect of preventing the transverse tension in the slab concrete by post-tensioning with a PC steel wire installed in the sheath tube of the concrete forming the slab.

본 발명은 빔 내부에 천공구멍을 형성하고, 이곳을 보강하기 위하여 양측으로 수직 보강판을 설치하여 횡 철근의 배근을 통하여 횡 방향으로 슬래브를 일체화시키며, 선로 양도에 대비하여 슬래브의 높이에 여유를 두는 효과를 제공한다.The present invention forms a perforated hole in the beam, and in order to reinforce the vertical reinforcement plate on both sides to reinforce the slab in the transverse direction through the reinforcement of the transverse reinforcement, to provide a margin to the height of the slab in preparation for the transfer of the track Positioning effect.

본 발명은 슬래브를 박스형으로 성형하여 경량구조로 제작하므로 교각 보강 등을 최소화할 수 있으며, 비틀림 저항 및 열차의 사행운동에 효과적으로 저항할 수 있도록 한다.The present invention can be manufactured in a lightweight structure by molding the slab into a box-shaped structure to minimize the bridge reinforcement, and to effectively resist torsional resistance and meandering motion of the train.

본 발명은 기존 거더가 슬래브의 내부에 위치하게 되므로 도장 등 유지관리가 필요 없으며, 유도상 슬래브 거더보다 경량이면서 강성은 오히려 크게 되어 콘크리트로 매립된 기존 거더의 피로수명에 영향을 받지 않는 경제적인 구조를 제공하는 것이다.The present invention does not require maintenance, such as painting because the existing girder is located in the interior of the slab, economical structure that is lighter than the slab girder in induction and rigidity is rather large and is not affected by the fatigue life of the existing girder embedded in concrete To provide.

본 발명은 슬래브 내부에서 PC 강선을 통하여 긴장시킨 것이어서 강성 저하시 재긴장시키는 것이 가능하며, 거더 설치를 위한 가설도로, 작업장, 대형크레인, 밀어넣기 위한 가벤트공사 등이 필요 없고, 거더 설치공사가 필요 없으므로 획기적으로 공사비를 절감시킬 수 있는 발명인 것이다.The present invention is tensioned through the PC steel wire inside the slab, it is possible to re-tension when the rigidity is lowered, there is no need for a construction road for the girder installation, workshop, large-scale crane, the construction for pushing, etc. It is an invention that can significantly reduce construction costs because it is not necessary.

Claims (4)

(삭제)(delete) 기존 거더(10)의 I형 빔(13)과 콘크리트의 부착력을 높이기 위하여 표면의 도장을 제거하고 신구접착제를 도포하는 기존 거더 도장제거 단계;Removing the existing girder coating step of removing the coating of the surface and applying a new adhesive agent in order to increase the adhesion of the I-beam 13 and the concrete of the existing girder 10; I형 빔(13)의 측면을 천공하여 다수의 철근 관통홀(19)을 형성하여 이곳에 철근(23)을 배근하는 빔 천공 단계;A beam drilling step of drilling a side of the I-beam 13 to form a plurality of rebar through holes 19 to reinforce the reinforcing bar 23 therein; 하부 슬래브(25), 복부(24) 및 상부 슬래브(28)를 일체화하기 위하여 상부 슬래브(28)가 타설될 위치의 I형 빔(13)에 천공 구멍(14)을 성형하고 양측으로 수직 보강판(15)을 설치하며 천공 구멍(14)에 다수의 횡 철근(20)과 쉬스관(27)을 관통시켜 횡 철근(20)을 배근하는 빔 천공 및 보강 단계와;In order to integrate the lower slab 25, the abdomen 24, and the upper slab 28, a perforation hole 14 is formed in the I-beam 13 at the position where the upper slab 28 is to be cast and the vertical reinforcement plate on both sides. A beam drilling and reinforcing step of installing 15 and reinforcing the transverse bars 20 by passing the plurality of transverse bars 20 and the sheath pipe 27 through the boring holes 14; 기존 거더(10)의 하측에 바닥 보강판(21)과 교량 받침(16)으로 둘러싸고 이곳에 접착제(32)를 도포하여 하측을 보강하는 거더의 하부 보강 단계;A lower reinforcing step of the girder to surround the bottom reinforcement plate 21 and the bridge support 16 on the lower side of the existing girder 10 and to apply the adhesive 32 to the lower side of the girder; 하부 슬래브(25)와 복부(24)가 공간(26)을 갖는 박스 형태로 설치되도록 하고 상부 슬래브(28)와 일체형으로 성형하도록 거푸집(22)을 설치하는 단계;Installing the formwork 22 such that the lower slab 25 and the abdomen 24 are installed in the form of a box having a space 26 and integrally molded with the upper slab 28; 홈부(30)가 형성되도록 스티로폼 등을 삽입하고 거푸집(22)의 내부에 콘크리트를 타설하여 양생시키는 콘크리트 타설 단계;Inserting styrofoam or the like so that the groove 30 is formed, and placing the concrete in the mold 22 to cure the concrete; 콘크리트의 양생이 완료된 후 PC 강선을 긴장시켜 상부 슬래브(28)에 긴장력을 도입하는 단계:After the curing of the concrete is completed, the PC steel wire is tensioned to introduce tension to the upper slab 28: 거푸집(22)을 제거하고 콘크리트에 매입되지 않은 돌출 거더(31)를 절단하여 침목(11)과 레일(12)을 함께 제거하는 돌출 거더 제거 단계;Removing the formwork 22 and cutting the protruding girder 31 which is not embedded in concrete to remove the sleeper 11 and the rail 12 together; 홈부(30)에 에폭시(33)를 주입하여 내외부를 일체화하며, 상부 슬래브(28)의 내부 바닥에 에폭시를 살포하고, 그 위에 우레탄판 또는 FREP판(34) 등을 부착하여 누수방지와 I형 빔(13)의 진동 저감하는 단계; 및Inject epoxy 33 into groove 30 to integrate the inside and outside, spray epoxy on the inner bottom of upper slab 28, and attach urethane plate or FREP plate 34 on it to prevent leakage and I type Reducing vibration of the beam 13; And 상부 슬래브(28)의 상측 내부에 자갈(36)을 살포하고 침목과 레일을 설치는 단계를 포함하는 것을 특징으로 하는 기존 거더를 활용한 판형교 유도상 시공방법.Spreading gravel (36) in the upper side of the upper slab 28 and the plate-shaped bridge guided construction method using the existing girder, characterized in that it comprises the step of installing a sleeper and a rail. (삭제)(delete) (삭제)(delete)
KR1020050128906A 2005-12-23 2005-12-23 Girder bridge construction make use of a part existing girder and that execution method KR100603901B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050128906A KR100603901B1 (en) 2005-12-23 2005-12-23 Girder bridge construction make use of a part existing girder and that execution method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050128906A KR100603901B1 (en) 2005-12-23 2005-12-23 Girder bridge construction make use of a part existing girder and that execution method

Publications (1)

Publication Number Publication Date
KR100603901B1 true KR100603901B1 (en) 2006-07-24

Family

ID=37184436

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050128906A KR100603901B1 (en) 2005-12-23 2005-12-23 Girder bridge construction make use of a part existing girder and that execution method

Country Status (1)

Country Link
KR (1) KR100603901B1 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100775053B1 (en) 2007-04-23 2007-11-08 매일종합건설(주) The original seat concrete ballast method of construction and its structure for which existence steel girder was utilized
KR100806711B1 (en) 2007-04-30 2008-02-27 조광현 The structure and the construction method which are changed in nothing ballast plate girder bridge to a ballast steel composition reinforced concrete slab bridge
KR101131628B1 (en) 2010-01-07 2012-04-12 삼표이앤씨 주식회사 expansion joint for bridge tracks and this construction technique
CN103395119A (en) * 2013-07-29 2013-11-20 中铁四局集团第三建设有限公司 Combined moving pedestal for road hollow-slab beams
CN104631302A (en) * 2015-02-13 2015-05-20 济南轨道交通集团有限公司 Perforated thin-wall precast channel beam for rail transit and precast method of perforated thin-wall precast channel beam for rail transit
CN109868691A (en) * 2017-12-01 2019-06-11 中铁二院工程集团有限责任公司 It is a kind of to deform adjustable High Speed Railway Subgrade and construction method and sedimentation and deformation method of adjustment
CN110080044A (en) * 2019-04-09 2019-08-02 中国铁路设计集团有限公司 A kind of vertical lattice type prefabricated assembled segment and its assembled high-speed rail roadbed
CN111608094A (en) * 2020-05-28 2020-09-01 中铁六局集团有限公司 Construction method for polishing and repairing beam surface of high-speed railway cast-in-place box beam

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000041822A (en) * 1998-12-23 2000-07-15 하진규 Complex bridge composed of represtressed box girder
KR20010045640A (en) * 1999-11-05 2001-06-05 장승필 Precast Reinforced Concrete Slab, Composite Continuous Bridge Having Such Slab, and Constructing Method thereof

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000041822A (en) * 1998-12-23 2000-07-15 하진규 Complex bridge composed of represtressed box girder
KR20010045640A (en) * 1999-11-05 2001-06-05 장승필 Precast Reinforced Concrete Slab, Composite Continuous Bridge Having Such Slab, and Constructing Method thereof

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100775053B1 (en) 2007-04-23 2007-11-08 매일종합건설(주) The original seat concrete ballast method of construction and its structure for which existence steel girder was utilized
KR100806711B1 (en) 2007-04-30 2008-02-27 조광현 The structure and the construction method which are changed in nothing ballast plate girder bridge to a ballast steel composition reinforced concrete slab bridge
KR101131628B1 (en) 2010-01-07 2012-04-12 삼표이앤씨 주식회사 expansion joint for bridge tracks and this construction technique
CN103395119A (en) * 2013-07-29 2013-11-20 中铁四局集团第三建设有限公司 Combined moving pedestal for road hollow-slab beams
CN104631302A (en) * 2015-02-13 2015-05-20 济南轨道交通集团有限公司 Perforated thin-wall precast channel beam for rail transit and precast method of perforated thin-wall precast channel beam for rail transit
CN109868691A (en) * 2017-12-01 2019-06-11 中铁二院工程集团有限责任公司 It is a kind of to deform adjustable High Speed Railway Subgrade and construction method and sedimentation and deformation method of adjustment
CN109868691B (en) * 2017-12-01 2024-01-05 中铁二院工程集团有限责任公司 Deformation-adjustable high-speed railway roadbed structure, construction method and settlement deformation adjustment method
CN110080044A (en) * 2019-04-09 2019-08-02 中国铁路设计集团有限公司 A kind of vertical lattice type prefabricated assembled segment and its assembled high-speed rail roadbed
CN111608094A (en) * 2020-05-28 2020-09-01 中铁六局集团有限公司 Construction method for polishing and repairing beam surface of high-speed railway cast-in-place box beam

Similar Documents

Publication Publication Date Title
KR100603901B1 (en) Girder bridge construction make use of a part existing girder and that execution method
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
KR100603906B1 (en) Pc girder bridge of u-type
EP1700954A2 (en) Prefabricated modular member, permanent railway for tramways and subways including said member, and process for laying the same
KR100891961B1 (en) The construction infrastructure the use road the martial art as a matter of bridge of the bridge which is old in the railroad or the railroad respects the induction event a method of construction which shifts the bridge and the system
CN110761119A (en) Cold-pressed longitudinal-connection-containing assembly type ballastless track structure of vibration reduction section and assembly method
CN112941975B (en) Combined track slab, prefabricated slab track system and installation and construction method thereof
CN108914715B (en) Assembly type ballastless track structure for vibration reduction zone and assembly method
KR100454405B1 (en) Method for changing steel bridge of supporting rail into concreat bridge
KR101127130B1 (en) A precast type pre-stress box girder bridge excution method
KR100556219B1 (en) A method for changing plate-girder bridge of railway bridge into slab bridge by using temporary construction bents.
CN110396919B (en) Assembled steel structure-concrete combined bridge and construction method thereof
KR100775053B1 (en) The original seat concrete ballast method of construction and its structure for which existence steel girder was utilized
CN105133493A (en) Embedded track structure suitable for middle-span and small-span bridge and construction method
CN108914713B (en) Wet-connection type assembling method for ballastless track of vibration reduction zone
JP4689272B2 (en) Construction method of fixed track for railway transportation
JP2002227101A (en) Sleeper-integrated concrete ballast structure for railway line
KR100415768B1 (en) Process and frame for substituting steel girder of a railway bridge for concrete slab
KR101187282B1 (en) Railway bridge constructing method using 2 post type abutment structure
JP4162291B2 (en) Railway work girder cradle and rail work girder cradle construction method
KR100613862B1 (en) Light weight pc-steelgirder bridge construction
JP4858850B2 (en) Installation method for vibration-proof track of existing track
KR100729842B1 (en) Repair work of railroad bridge and that structure
JP4020918B2 (en) Bridge structure of girder bridge
KR100638578B1 (en) Method for carrying out replacement of an upper structure of a railway bridge

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130527

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20140617

Year of fee payment: 9

LAPS Lapse due to unpaid annual fee