Improvements in or relating to pilesInfo
- Publication number
- GB796262A GB796262A GB3036756A GB3036756A GB796262A GB 796262 A GB796262 A GB 796262A GB 3036756 A GB3036756 A GB 3036756A GB 3036756 A GB3036756 A GB 3036756A GB 796262 A GB796262 A GB 796262A
- Authority
- GB
- United Kingdom
- Prior art keywords
- shaft
- shoe
- concrete
- cement
- oct
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/62—Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
- E02D5/30—Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
796,262. Concrete piles. MUELLER, L. Oct. 5,1956 [Oct. 7, 1955], No. 30367/56: Class 68(2) A method of producing a concrete pile comprises driving into the ground a shaft 61 provided with a shoe 62, open at the top and of greater cross-section than the shaft, forcing liquid cement or concrete under pressure from the lower part of the shaft, or if the shaft is solid from a pipe outside the shaft, through the hollow shoe 62 into the space 71, sealing the space 71, as the driving-in is completed, with a bell 70 and thereafter forcing in the cement or concrete at increased pressure. A chisel 63 is set in the shoe with its point projecting below the end of the shoe and the shoe is attached to the shaft by plates 64. Cement or concrete is supplied through a feed tube 68 and outlets 65 may be provided in the shaft 61.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB3036756A GB796262A (en) | 1956-10-05 | 1956-10-05 | Improvements in or relating to piles |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB3036756A GB796262A (en) | 1956-10-05 | 1956-10-05 | Improvements in or relating to piles |
Publications (1)
Publication Number | Publication Date |
---|---|
GB796262A true GB796262A (en) | 1958-06-11 |
Family
ID=6710914
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
GB3036756A Expired GB796262A (en) | 1956-10-05 | 1956-10-05 | Improvements in or relating to piles |
Country Status (1)
Country | Link |
---|---|
GB (1) | GB796262A (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3084518A (en) * | 1958-07-18 | 1963-04-09 | Hochstrasser Robert | Tubular pile with driving cap |
US3222873A (en) * | 1961-07-31 | 1965-12-14 | Chester I Williams | Groutable rock anchor |
EP0065340A1 (en) * | 1981-05-12 | 1982-11-24 | Fundamentum B.V. | Method for making a foundation pile |
GB2234774A (en) * | 1989-08-12 | 1991-02-13 | Roxbury Ltd | Piling and underpinning method |
GB2246590A (en) * | 1990-07-25 | 1992-02-05 | Lu Hsi Huan | Forming piles in situ |
US5145291A (en) * | 1990-08-13 | 1992-09-08 | Roger Bullivant Of Texas, Inc. | Method for forming a piling beneath a structure |
US5320453A (en) * | 1991-04-11 | 1994-06-14 | Roger Bullivant Of Texas, Inc. | Composite sectional concrete piles |
US5771518A (en) * | 1989-06-16 | 1998-06-30 | Roberts; Michael Lee | Precast concrete bridge structure and associated rapid assembly methods |
WO2000036226A2 (en) * | 1998-12-14 | 2000-06-22 | Rautaruukki Oyj | A tubular pile encased in concrete and a method for driving the tubular pile into the soil and encasing it in concrete |
WO2007138150A1 (en) * | 2006-05-30 | 2007-12-06 | Turun Ammattikorkeakoulu | Method for forming a sheet pile structure, sheet pile element, sheet pile structure and use of a sheet pile structure for damping vibration |
CN108179743A (en) * | 2018-02-09 | 2018-06-19 | 浙江大学城市学院 | A kind of synchronous grouting pile for prestressed pipe and construction method |
CN108824421A (en) * | 2018-07-26 | 2018-11-16 | 淮海工学院 | A kind of corrosion resisting steel tubular pole and pile making method |
CN109457695A (en) * | 2018-11-14 | 2019-03-12 | 佛山市高明顺高木业有限公司 | A kind of cement steel-pipe pile |
-
1956
- 1956-10-05 GB GB3036756A patent/GB796262A/en not_active Expired
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3084518A (en) * | 1958-07-18 | 1963-04-09 | Hochstrasser Robert | Tubular pile with driving cap |
US3222873A (en) * | 1961-07-31 | 1965-12-14 | Chester I Williams | Groutable rock anchor |
EP0065340A1 (en) * | 1981-05-12 | 1982-11-24 | Fundamentum B.V. | Method for making a foundation pile |
US5771518A (en) * | 1989-06-16 | 1998-06-30 | Roberts; Michael Lee | Precast concrete bridge structure and associated rapid assembly methods |
GB2234774B (en) * | 1989-08-12 | 1994-01-12 | Roxbury Ltd | Improvements in or relating to piling methods |
GB2234774A (en) * | 1989-08-12 | 1991-02-13 | Roxbury Ltd | Piling and underpinning method |
GB2246590A (en) * | 1990-07-25 | 1992-02-05 | Lu Hsi Huan | Forming piles in situ |
US5145291A (en) * | 1990-08-13 | 1992-09-08 | Roger Bullivant Of Texas, Inc. | Method for forming a piling beneath a structure |
US5320453A (en) * | 1991-04-11 | 1994-06-14 | Roger Bullivant Of Texas, Inc. | Composite sectional concrete piles |
WO2000036226A2 (en) * | 1998-12-14 | 2000-06-22 | Rautaruukki Oyj | A tubular pile encased in concrete and a method for driving the tubular pile into the soil and encasing it in concrete |
WO2000036226A3 (en) * | 1998-12-14 | 2004-11-18 | Rautaruukki Oyj | A tubular pile encased in concrete and a method for driving the tubular pile into the soil and encasing it in concrete |
WO2007138150A1 (en) * | 2006-05-30 | 2007-12-06 | Turun Ammattikorkeakoulu | Method for forming a sheet pile structure, sheet pile element, sheet pile structure and use of a sheet pile structure for damping vibration |
CN108179743A (en) * | 2018-02-09 | 2018-06-19 | 浙江大学城市学院 | A kind of synchronous grouting pile for prestressed pipe and construction method |
CN108824421A (en) * | 2018-07-26 | 2018-11-16 | 淮海工学院 | A kind of corrosion resisting steel tubular pole and pile making method |
CN109457695A (en) * | 2018-11-14 | 2019-03-12 | 佛山市高明顺高木业有限公司 | A kind of cement steel-pipe pile |
WO2020098041A1 (en) * | 2018-11-14 | 2020-05-22 | 佛山市高明顺高木业有限公司 | Cement steel pipe pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
GB796262A (en) | Improvements in or relating to piles | |
GB1147434A (en) | Method and apparatus for forming concrete bodies | |
GB1465554A (en) | Method and apparatus for driving one or more pile members into the ground | |
GB1434964A (en) | Pile driving | |
GB862630A (en) | Method of and apparatus for the construction of piles cast in situ from concrete | |
GB703654A (en) | Method of pre-stressing the soil more especially for foundations and preferably in a horizontal direction | |
GB1030619A (en) | A process for the production of piles | |
GB369816A (en) | Improvements in and relating to the making of concrete piles in situ | |
GB880467A (en) | A method of and apparatus for making subaqueous foundations | |
GB654039A (en) | Improvements in and relating to pile sinking | |
GB628795A (en) | Improvements in or relating to piles | |
JPS57209325A (en) | Concrete-steel pipe composite pile | |
JPS56135621A (en) | Sand pile construction work in underwater ground | |
GB699615A (en) | Improved two part foundation pile | |
GB644258A (en) | Method and equipment for the making of piles of concrete in situ | |
FR2246167A5 (en) | Vibratory compactor probe - works at its natural frequency and has rigid extension tubes | |
GB902687A (en) | Method of and means for driving in piles or sheet piling | |
GB933187A (en) | Improvements in and relating to the manufacture of tubed foundation piles | |
GB866664A (en) | A new or improved method of fabricating foundations and foundations so produced | |
GB386857A (en) | A method of and apparatus for making piles and similar foundation structures | |
GB847260A (en) | Improvements in or relating to the production of concrete piles | |
GB880466A (en) | Improvements relating to foundation piles | |
JPS5216372A (en) | Device for pouring and diluting agricultural chemicals and the like | |
GB215177A (en) | Improved method and means for the driving in of tube-work for foundations | |
ES215337A3 (en) | A procedure and apparatus for the execution of fundaciºn pilots molded in the soil (Machine-translation by Google Translate, not legally binding) |