WO2020098041A1 - Cement steel pipe pile - Google Patents

Cement steel pipe pile Download PDF

Info

Publication number
WO2020098041A1
WO2020098041A1 PCT/CN2018/121140 CN2018121140W WO2020098041A1 WO 2020098041 A1 WO2020098041 A1 WO 2020098041A1 CN 2018121140 W CN2018121140 W CN 2018121140W WO 2020098041 A1 WO2020098041 A1 WO 2020098041A1
Authority
WO
WIPO (PCT)
Prior art keywords
pile
plate
steel pipe
pile body
cement steel
Prior art date
Application number
PCT/CN2018/121140
Other languages
French (fr)
Chinese (zh)
Inventor
梁兆镛
Original Assignee
佛山市高明顺高木业有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 佛山市高明顺高木业有限公司 filed Critical 佛山市高明顺高木业有限公司
Publication of WO2020098041A1 publication Critical patent/WO2020098041A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/50Piles comprising both precast concrete portions and concrete portions cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/62Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes

Definitions

  • the invention relates to the technical field of building materials, in particular to a concrete steel pipe pile.
  • Wooden houses are very popular in North America, and in the context of the new era and new trends, young people in China are pursuing the enjoyment and experience of beauty, and wooden houses are also gradually popular in China. Most of the wooden houses are built in the places near the mountains and the water, suitable for self-cultivation, leisure, entertainment, and relaxation. Whether on the hillside or plain grass, a variety of wooden cabin styles can be built. The design is flexible and diverse.
  • the wooden house is lighter in weight. Therefore, in order to improve the stability of the wooden house, it is not easy to be blown down by the strong wind.
  • the pile is driven into the ground below the wooden house, and then the wooden house is fixed on the pile.
  • the piles used are all of the structure shown in Figure 1.
  • the pile is composed of a steel tube in the upper section and a screw-shaped section in the lower section. This pile is planted on the ground by screw driving, but this structure exists
  • the shortcoming is that the external tension of the pile depends entirely on the frictional force of the steel pipe wall and the surface of the steel plate in contact with the soil, but the surface of the steel pipe of the pile is smooth, the friction is limited, and it is easy to be pulled up.
  • the soil will enter the inside of the steel cylinder or eventually emerge from the top of the steel cylinder, causing the inside of the steel cylinder to form a blockage, or the emerging soil will affect the external drive into the equipment.
  • the present invention overcomes the shortcomings of the prior art, and provides a cement steel pipe pile with a stable structure and a cross-shaped design of the pile mouth, which has strong rigidity, and the deflector can prevent the hard soil from entering the pile during the process of planting into the ground ⁇ Body inside.
  • a cement steel pipe pile includes a pile body, the pile body is a hollow design pipe body, a pile cap is provided above the pile body, a feed inlet is reserved on the pile cap, and the pile body A pile spout is also provided below, the feed inlet is in communication with the pile body, the pile body is in communication with the pile spout, and a spoiler is provided on the pile spout.
  • the spout includes a first plate and a second plate, the first plate and the second plate are arranged in a cross shape, and the first plate and the second plate have the same thickness, A first slot is provided on the first plate, a second slot is provided on the second plate, and the first slot of the first plate is inserted into the second slot of the second plate
  • the groove can fix the first plate and the second plate to each other.
  • the angle formed by the extension lines of the two hypotenuses on the outer side of the lower end of the first plate and the sharpest angle of the lowermost end of the second plate are acute angles, so as to facilitate insertion into the ground.
  • the deflector is provided at an angle formed by the intersection of the first and second plates, and the opening formed by the deflector and the first and second plates surrounds on.
  • both the first and second plates are provided with a first assembling groove and a second assembling groove, and the first assembling groove and the second assembling groove on the first or second plate The distance between them is consistent with the pipe diameter of the pile body, and the lower end of the pile body is connected and installed on the first installation groove and the second installation groove.
  • the first plate and the second plate are also provided with clamping positions on both sides.
  • the pile cap is further provided with a mounting groove.
  • the thickness of the deflector is 3 to 5 mm.
  • the outer surfaces of the pile body, pile cap, pile nozzle and deflector are all provided with anti-rust paint.
  • the pile mouth of the invention adopts a cross-shaped design, which has strong rigidity, and is not easy to deform during the process of planting into the ground, and a deflector is provided at the pile mouth to block large pieces of soil and hard objects from entering the pile body;
  • the external high-pressure cement pump is used to inject the prepared cement mortar from the inlet of the pile cap.
  • the cement mortar encounters the deflector block, it will change from a vertical fall motion to a lateral expansion motion.
  • the cement mortar is more concentrated around the pile mouth, forming an effective cement block structure, maximizing the forming volume of the cement block under the pile body, on the one hand, because the interior of the pile body is also filled with cement mortar, it increases
  • the cement block formed in turn firmly locks the pile mouth, so that the pile is solidified in the depth of the ground surface, and it is not easy to shake or be pulled away.
  • the wooden house is locked on the pile through the installation groove on the pile cap, and the fall resistance is strong.
  • Figure 1 is a schematic diagram of the structure of the pile currently used in the wooden house
  • FIG. 2 is a schematic structural view of the new type of cement steel pipe pile of the present invention.
  • 3 is a plan view of the pile nozzle and the pile body after separation
  • Fig. 6 is a plan view of the pile cap.
  • FIG. 1 it is a schematic diagram of the structure of a pile currently used in a wooden house.
  • the pile is composed of a steel tube in the upper section and a screw-shaped structure in the lower section.
  • This pile is planted on the ground by screw driving, but
  • the shortcoming of this structure is that the external tension of the pile depends entirely on the frictional force of the steel tube wall and the surface of the steel plate in contact with the soil, but the surface of the steel tube of the pile is smooth, the frictional force is limited, and it is easy to be pulled up and carried. Not strong enough.
  • a cement steel pipe pile As shown in FIGS. 2 to 6, a cement steel pipe pile according to the present invention includes a pile body 1, which is a hollow design pipe body, which is made of stainless steel and welded above the pile body 1 There is a pile cap 2, a feed inlet 21 is reserved on the pile cap 2, a pile nozzle 3 is also provided below the pile body 1, the feed port 231 communicates with the pile body 1, and the pile body 1 communicates with the pile nozzle 2, so from The feeding port 231 is filled with cement mortar, and it will fall directly along the pile body 1 to the pile nozzle 2.
  • the deflector 4 is provided on the pile nozzle 3, and the deflector 4 is welded and fixed on the pile nozzle 3;
  • the pile nozzle 3 includes
  • the first plate 31 and the second plate 32, the first plate 31 and the second plate 32 are arranged in a cross shape, and this cross-shaped cross arrangement achieves the function of strengthening the overall structure of the spout 3 and improving the Impact resistance, the first plate 31 and the second plate 32 have the same thickness, and a first slot 311 is provided on the first plate 31, a second slot 321 is provided on the second plate 32, The first slot 311 of the first plate 31 is inserted into the second slot 321 of the second plate 32, and the first plate 31 and the second plate 32 can be fixed to each other.
  • first plate 31 and the second plate 32 In addition, during production, It is necessary to weld the intersection of the first plate 31 and the second plate 32 with a welding machine, so that the first plate 31 and the second plate 32 are fixed and integrated, and it is not easy to separate; in addition, the first plate
  • the angle formed by the extension lines of the two oblique sides outside the lower end of the sheet 31 and the lowermost sharp angle of the second plate 32 are both acute angles. In this embodiment, the angle between the included angle and the sharp angle is 45 °, which is set to an acute angle. Conducive to planting in the mud during construction.
  • the deflector 4 is welded at four angles formed by the intersection of the first plate 31 and the second plate 32, and the opening formed by the deflector 4 and the first plate 31 and the second plate 32 is upward,
  • the purpose of the deflector 4 is that when the present invention is planted in the mud, it has a certain blocking effect on large pieces of soil and hard objects, so that they cannot enter the interior of the pile 1; when pouring into the pile of the present invention
  • the thickness of the deflector 4 can be 3 to 5mm, in this embodiment, the thickness is 4mm; as shown in Figure 3, in this embodiment, the deflector 4
  • the number is 4 pieces, and the diameter formed by the 4 deflectors 4 is slightly larger than the diameter and width of the pile body 1 to achieve the blocking effect.
  • the first mounting groove 5 and the second mounting groove 6 are provided on both the first plate 31 and the second plate 32, and the first mounting groove 5 and the second mounting groove on the first plate 31 or the second plate 32
  • the distance between 6 and the diameter of the pile body 1 is the same. Therefore, in production, the lower end of the pile body 1 is directly inserted into the first installation groove 5 and the second installation groove 6, and then the pile body 1
  • the joint between the lower end of the first mounting groove 5 and the second mounting groove 6 is welded with a welding machine, and the pile nozzle 3 and the pile body 1 can be welded together.
  • the first plate 31 and the second plate 32 are also provided with a clamping position 7 on both sides.
  • the clamping position 7 serves as a clamping position, which helps to enhance the pull-out resistance of the present invention.
  • the outer surfaces of the pile body 1, pile cap 2, pile mouth 3 and deflector 4 are all provided with anti-rust paint, which can be selected from polyurethane anti-rust paint. And the deflector 4 has an anti-rust effect to avoid corrosion and oxidation and prolong the service life.
  • the pile cap 2 is also provided with an installation slot 22 for installing bolts with the bottom of the wooden house to fix the wooden house.
  • the working principle of the present invention is that the pile head 4 faces downwards, and the invention is driven into the mud ground. Due to the arrangement of the deflector 4, it has a blocking effect on large pieces of soil and hard objects, so the pile body 1 is basically maintained In the hollow state, the external high-pressure cement pump is used to inject the prepared cement mortar from the inlet 21 of the pile cap 2. When the cement mortar encounters the deflector 4, it will change from a vertical fall motion to a lateral expansion motion, so that Cement mortar gathers more around the pile mouth 4 to form an effective cement block structure, which maximizes the formation volume of the cement block under the pile body 1.
  • the pile body is also filled with cement mortar, so it increases The pile bearing force and gravity, on the other hand, the cement block formed in turn firmly locks the pile mouth 4, so that the pile is solidified in the depth of the ground surface, and it is not easy to shake or be pulled away.
  • the wooden house is locked on the pile through the installation groove 22 on the pile cap 2 and has strong anti-falling ability.
  • the structure in which the spout 4 is welded and formed by a multi-discriminating triangular piece also falls within the protection scope of the present invention.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

Disclosed is a cement steel pipe pile, comprising a pile body (1), wherein the pile body (1) is a hollow pipe body, a pile cap (2) is arranged above the pile body (2), the pile cap (2) has a feed inlet (21) reserved thereon, a pile shoe (3) is provided below the pile body (1), the feed inlet (21) is in communication with the pile body (1), the pile body (1) is in communication with the pile shoe (3), and a flow guide plate (4) is provided on the pile shoe (3). The cement steel pipe pile has a stable structure, the pile shoe (3) has a cross-shaped design, the flow guide plate can prevent hard soil from entering the pile body (1) in the process of putting the cement steel pipe pile into soil, and after cement mortar is poured into the pile body (1) and sets, a lower end of the pile body (1) can be locked in a set cement block from the outside, thereby generating a larger cross section in order to enhance the bearing capacity thereof.

Description

一种水泥钢管桩Cement steel pipe pile 技术领域Technical field
本发明涉及建筑材料技术领域,尤其是一种水泥钢管桩。The invention relates to the technical field of building materials, in particular to a concrete steel pipe pile.
背景技术Background technique
木屋在北美十分流行,而在新时代新潮流的背景下,我国年轻人都在追求美的享受与体验,木屋在我国也逐步流行。木屋多数建造在依山傍水的地方,适合修身养性、休闲娱乐、放松身心的去处,无论是在山坡上还是平原草地,都能建造出多种多样的木制木屋风格,设计灵活、风格多样、抗震性强、隔热隔音、冬暖夏凉、健康环保、可起到天然调节湿度的作用,木材本身就是原生态环保材料,加上现代科技加工形成一种防腐、防潮、防蛀、防霉等良好作用,人们居住在原木搭建的木制木屋里面可以尽情的享受原木散发出来的清香,亲身体验回归原生态的自然感受。Wooden houses are very popular in North America, and in the context of the new era and new trends, young people in China are pursuing the enjoyment and experience of beauty, and wooden houses are also gradually popular in China. Most of the wooden houses are built in the places near the mountains and the water, suitable for self-cultivation, leisure, entertainment, and relaxation. Whether on the hillside or plain grass, a variety of wooden cabin styles can be built. The design is flexible and diverse. Strong shock resistance, thermal insulation and sound insulation, warm in winter and cool in summer, healthy and environmentally friendly, can play a natural role in adjusting humidity, wood itself is the original ecological environmental protection material, plus modern technology processing to form a kind of anti-corrosion, moisture-proof, moth-proof, mildew-proof For good effect, people living in wooden log cabins made of logs can enjoy the fragrance of the logs and experience the natural feeling of returning to the original ecology.
与水泥建筑相比,由于木屋质量较轻,因此,为了提高木屋的稳定性,不容易被大风吹倒,通常要在木屋的下方土地处打入桩,然后将木屋固定在桩上,目前木屋所使用的桩都是如图1所示的结构,该桩由上段部分是钢筒、下段部分是螺杆状的结构构成,此桩是采用螺旋打入的方式种在地面上,但此结构存在的缺陷在于,该桩承受外界的拉力完全取决于钢筒的管壁和钢板表面与泥土接触的摩擦力,但该桩的钢筒表面光滑,摩擦力有限,容易被拔起;其次,在打入的过程中,泥土会进入到钢筒的内部或最终从钢筒的顶端冒出,使钢筒内部形成堵塞,或冒出的泥土会对外部打入设备造成影响。Compared with cement buildings, the wooden house is lighter in weight. Therefore, in order to improve the stability of the wooden house, it is not easy to be blown down by the strong wind. Usually, the pile is driven into the ground below the wooden house, and then the wooden house is fixed on the pile. The piles used are all of the structure shown in Figure 1. The pile is composed of a steel tube in the upper section and a screw-shaped section in the lower section. This pile is planted on the ground by screw driving, but this structure exists The shortcoming is that the external tension of the pile depends entirely on the frictional force of the steel pipe wall and the surface of the steel plate in contact with the soil, but the surface of the steel pipe of the pile is smooth, the friction is limited, and it is easy to be pulled up. During the process of entering, the soil will enter the inside of the steel cylinder or eventually emerge from the top of the steel cylinder, causing the inside of the steel cylinder to form a blockage, or the emerging soil will affect the external drive into the equipment.
发明内容Summary of the invention
本发明克服了现有技术中的缺点,提供一种水泥钢管桩,结构稳固,桩嘴是十字形设计,刚性强,并且在种入土地的过程中导流板能阻挡坚硬泥土进入至桩体内部。The present invention overcomes the shortcomings of the prior art, and provides a cement steel pipe pile with a stable structure and a cross-shaped design of the pile mouth, which has strong rigidity, and the deflector can prevent the hard soil from entering the pile during the process of planting into the ground体内。 Body inside.
为了解决上述技术问题,本发明是通过以下技术方案实现的:In order to solve the above technical problems, the present invention is achieved through the following technical solutions:
一种水泥钢管桩,包括桩体,所述桩体是一中空设计的管体,所述桩体的上方设置有桩帽,所述桩帽上预留有进料口,所述桩体的下方还设置有桩嘴,所述进料口与所述桩体连通,所述桩体与所述桩嘴连通,所述桩嘴上设置有导流板。A cement steel pipe pile includes a pile body, the pile body is a hollow design pipe body, a pile cap is provided above the pile body, a feed inlet is reserved on the pile cap, and the pile body A pile spout is also provided below, the feed inlet is in communication with the pile body, the pile body is in communication with the pile spout, and a spoiler is provided on the pile spout.
优选地,所述桩嘴包括第一板片和第二板片,所述第一板片和第二板片呈十字形交叉设置,所述第一板片和第二板片的厚度相同,所述第一板片上设置有第一插槽,所述第二板片 上设置有第二插槽,将所述第一板片的第一插槽插入至所述第二板片的第二插槽,能将所述第一板片与第二板片进行相互固定。Preferably, the spout includes a first plate and a second plate, the first plate and the second plate are arranged in a cross shape, and the first plate and the second plate have the same thickness, A first slot is provided on the first plate, a second slot is provided on the second plate, and the first slot of the first plate is inserted into the second slot of the second plate The groove can fix the first plate and the second plate to each other.
优选地,所述第一板片下端外侧两斜边延长线形成的夹角以及第二板片的最下端尖角均是锐角,以利于插入土地。Preferably, the angle formed by the extension lines of the two hypotenuses on the outer side of the lower end of the first plate and the sharpest angle of the lowermost end of the second plate are acute angles, so as to facilitate insertion into the ground.
优选地,所述导流板设置在所述第一板片和第二板片相交形成的夹角处,所述导流板与所述第一板片、第二板片包围形成的开口朝上。Preferably, the deflector is provided at an angle formed by the intersection of the first and second plates, and the opening formed by the deflector and the first and second plates surrounds on.
优选地,所述第一板片和第二板片上均设置有第一装配槽和第二装配槽,所述第一板片或第二板片上的第一装配槽与所述第二装配槽之间的距离尺寸与所述桩体的管径尺寸一致,所述桩体的下端连接安装在所述第一安装槽和第二安装槽上。Preferably, both the first and second plates are provided with a first assembling groove and a second assembling groove, and the first assembling groove and the second assembling groove on the first or second plate The distance between them is consistent with the pipe diameter of the pile body, and the lower end of the pile body is connected and installed on the first installation groove and the second installation groove.
优选地,所述第一板片和第二板片的两侧还设置有卡位。Preferably, the first plate and the second plate are also provided with clamping positions on both sides.
优选地,所述桩帽上还设置有安装槽。Preferably, the pile cap is further provided with a mounting groove.
优选地,所述导流板的厚度是3至5mm。Preferably, the thickness of the deflector is 3 to 5 mm.
优选地,所述桩体、桩帽、桩嘴以及导流板的外表面均设置有防锈漆。Preferably, the outer surfaces of the pile body, pile cap, pile nozzle and deflector are all provided with anti-rust paint.
与现有技术相比,本发明的有益效果是:Compared with the prior art, the beneficial effects of the present invention are:
本发明的桩嘴是采用十字形设计,刚性强,种入土地过程中不容易发生变形,并且在桩嘴处设置有导流板,能阻挡大块的泥土和硬物进入至桩体内部;当将本发明种入至土地后,采用外部的高压水泥泵从桩帽的进料口注入调配好的水泥砂浆,当水泥砂浆遇到导流板阻挡时会由垂直下落运动改为横向扩张运动,从而使水泥砂浆更多地集聚在桩嘴的周围,形成有效的水泥块结构,最大限度地增加桩体下方水泥块的成形体积,一方面由于桩体内部也灌满水泥浆砂,因此增加了该桩承托力和重力,另一方面所形成的水泥块反过来又牢牢地锁住桩嘴,使该桩整体凝固在地表面的深处,不容易发生晃动或被抽离,最后将木屋通过桩帽上的安装槽锁定在该桩上,抗倒能力强。The pile mouth of the invention adopts a cross-shaped design, which has strong rigidity, and is not easy to deform during the process of planting into the ground, and a deflector is provided at the pile mouth to block large pieces of soil and hard objects from entering the pile body; When the present invention is planted into the ground, the external high-pressure cement pump is used to inject the prepared cement mortar from the inlet of the pile cap. When the cement mortar encounters the deflector block, it will change from a vertical fall motion to a lateral expansion motion. , So that the cement mortar is more concentrated around the pile mouth, forming an effective cement block structure, maximizing the forming volume of the cement block under the pile body, on the one hand, because the interior of the pile body is also filled with cement mortar, it increases In addition to the supporting force and gravity of the pile, on the other hand, the cement block formed in turn firmly locks the pile mouth, so that the pile is solidified in the depth of the ground surface, and it is not easy to shake or be pulled away. The wooden house is locked on the pile through the installation groove on the pile cap, and the fall resistance is strong.
附图说明BRIEF DESCRIPTION
附图用来提供对本发明的进一步理解,与本发明的实施例一起用于解释本发明,并不构成对本发明的限制,在附图中:The drawings are used to provide a further understanding of the present invention, and are used to explain the present invention together with the embodiments of the present invention, and do not constitute a limitation on the present invention. In the drawings:
图1是目前木屋所使用的桩的结构示意图;Figure 1 is a schematic diagram of the structure of the pile currently used in the wooden house;
图2是本发明的新型水泥钢管桩的结构示意图;2 is a schematic structural view of the new type of cement steel pipe pile of the present invention;
图3是所述桩嘴与所述桩体分离后的俯视图;3 is a plan view of the pile nozzle and the pile body after separation;
图4是所述第一板片的结构示意图;4 is a schematic structural view of the first plate;
图5是所述第二板片的结构示意图;5 is a schematic structural view of the second plate;
图6是所述桩帽的俯视图。Fig. 6 is a plan view of the pile cap.
图中:1-桩体,2-桩帽,21-进料口,22-安装槽,3-桩嘴,31-第一板片,311-第一插槽,32-第二板片,321-第二插槽,4-导流板,5-第一装配槽,6-第二装配槽,7-卡位。In the picture: 1-pile body, 2-pile cap, 21-inlet, 22-mounting slot, 3-pile nozzle, 31-first plate, 311-first slot, 32-second plate, 321-Second slot, 4-Guard plate, 5-First assembly slot, 6-Second assembly slot, 7-position.
具体实施方式detailed description
以下结合附图对本发明的优选实施例进行说明,应当理解,此处所描述的优选实施例仅用于说明和解释本发明,并不用于限定本发明。承载力也不足;The following describes preferred embodiments of the present invention with reference to the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, but not to limit the present invention. The bearing capacity is also insufficient;
如图1所示,是目前木屋所使用的桩的结构示意图,该桩由上段部分是钢筒、下段部分是螺杆状的结构构成,此桩是采用螺旋打入的方式种在地面上,但此结构存在的缺陷在于,该桩承受外界的拉力完全取决于钢筒的管壁和钢板表面与泥土接触的摩擦力,但该桩的钢筒表面光滑,摩擦力有限,容易被拔起,承载力也不足。As shown in Figure 1, it is a schematic diagram of the structure of a pile currently used in a wooden house. The pile is composed of a steel tube in the upper section and a screw-shaped structure in the lower section. This pile is planted on the ground by screw driving, but The shortcoming of this structure is that the external tension of the pile depends entirely on the frictional force of the steel tube wall and the surface of the steel plate in contact with the soil, but the surface of the steel tube of the pile is smooth, the frictional force is limited, and it is easy to be pulled up and carried. Not strong enough.
图2至6所示,本发明所述一种水泥钢管桩,包括桩体1,桩体1是一中空设计的管体,管体采用不锈钢材料制作而成,在桩体1的上方焊接有桩帽2,桩帽2上预留有进料口21,桩体1的下方还设置有桩嘴3,进料口231与桩体1连通,桩体1与桩嘴2连通,因此从进料口231灌入水泥砂浆,会沿着桩体1直接落下至桩嘴2,桩嘴3上设置有导流板4,导流板4是焊接固定在桩嘴3上;桩嘴3包括第一板片31和第二板片32,第一板片31和第二板片32呈十字形交叉设置,此十字形交叉设置达到增强桩嘴3整体结构的作用,并且提高桩嘴3的抗冲击强度,第一板片31和第二板片32的厚度相同,并且在第一板片31上设置有第一插槽311,第二板片32上设置有第二插槽321,将第一板片31的第一插槽311插入至第二板片32的第二插槽321中,能将第一板片31与第二板片32进行相互固定,此外,在生产时,还需要将第一板片31与第二板片32的相交相接处用焊机焊死,使第一板片31与第二板片32固接一体,不容易发生分离;另外,第一板片31下端外侧两斜边延长线形成的夹角以及第二板片32的最下端尖角均是锐角,在本实施例中,该夹角和尖角的角度是45°,设置成锐角,有利于施工时种入泥地中。导流板4是焊接在第一板片31和第二板片32相交形成的四个夹角处,导流板4与第一板片31、第二板片32包围形成的开口朝上,导流板4的用处是,当本发明种入泥地时,对大块的泥土和硬物有一定的阻挡作用,使它们不能进入到桩体1的内部;当往本发明桩体内部灌入水泥浆砂时,有一定的承接作用,导流板4的厚度可以是3至5mm,在本实施例中,厚度是4mm;如图3所示,在本实施例中,导流板4的数量是4块,4块导流板4包围形成的口径要稍微大于桩体1的直径宽度,以达到阻挡的作用。As shown in FIGS. 2 to 6, a cement steel pipe pile according to the present invention includes a pile body 1, which is a hollow design pipe body, which is made of stainless steel and welded above the pile body 1 There is a pile cap 2, a feed inlet 21 is reserved on the pile cap 2, a pile nozzle 3 is also provided below the pile body 1, the feed port 231 communicates with the pile body 1, and the pile body 1 communicates with the pile nozzle 2, so from The feeding port 231 is filled with cement mortar, and it will fall directly along the pile body 1 to the pile nozzle 2. The deflector 4 is provided on the pile nozzle 3, and the deflector 4 is welded and fixed on the pile nozzle 3; the pile nozzle 3 includes The first plate 31 and the second plate 32, the first plate 31 and the second plate 32 are arranged in a cross shape, and this cross-shaped cross arrangement achieves the function of strengthening the overall structure of the spout 3 and improving the Impact resistance, the first plate 31 and the second plate 32 have the same thickness, and a first slot 311 is provided on the first plate 31, a second slot 321 is provided on the second plate 32, The first slot 311 of the first plate 31 is inserted into the second slot 321 of the second plate 32, and the first plate 31 and the second plate 32 can be fixed to each other. In addition, during production, It is necessary to weld the intersection of the first plate 31 and the second plate 32 with a welding machine, so that the first plate 31 and the second plate 32 are fixed and integrated, and it is not easy to separate; in addition, the first plate The angle formed by the extension lines of the two oblique sides outside the lower end of the sheet 31 and the lowermost sharp angle of the second plate 32 are both acute angles. In this embodiment, the angle between the included angle and the sharp angle is 45 °, which is set to an acute angle. Conducive to planting in the mud during construction. The deflector 4 is welded at four angles formed by the intersection of the first plate 31 and the second plate 32, and the opening formed by the deflector 4 and the first plate 31 and the second plate 32 is upward, The purpose of the deflector 4 is that when the present invention is planted in the mud, it has a certain blocking effect on large pieces of soil and hard objects, so that they cannot enter the interior of the pile 1; when pouring into the pile of the present invention When entering the cement mortar, there is a certain bearing effect, the thickness of the deflector 4 can be 3 to 5mm, in this embodiment, the thickness is 4mm; as shown in Figure 3, in this embodiment, the deflector 4 The number is 4 pieces, and the diameter formed by the 4 deflectors 4 is slightly larger than the diameter and width of the pile body 1 to achieve the blocking effect.
在第一板片31和第二板片32上均设置有第一装配槽5和第二装配槽6,第一板片31或第二板片32上第一装配槽5与第二装配槽6之间的距离尺寸与桩体1的管径尺寸一致,因此,在生产时,将桩体1的下端直接插入安装在第一安装槽5和第二安装槽6上,然后将桩体1的下端与第一安装槽5、第二安装槽6的相接处用焊机焊死,即可将桩嘴3与桩体1焊接一体。The first mounting groove 5 and the second mounting groove 6 are provided on both the first plate 31 and the second plate 32, and the first mounting groove 5 and the second mounting groove on the first plate 31 or the second plate 32 The distance between 6 and the diameter of the pile body 1 is the same. Therefore, in production, the lower end of the pile body 1 is directly inserted into the first installation groove 5 and the second installation groove 6, and then the pile body 1 The joint between the lower end of the first mounting groove 5 and the second mounting groove 6 is welded with a welding machine, and the pile nozzle 3 and the pile body 1 can be welded together.
在第一板片31和第二板片32的两侧还设置有卡位7,卡位7起到卡位作用,有助于增强本发明的抗拔性。The first plate 31 and the second plate 32 are also provided with a clamping position 7 on both sides. The clamping position 7 serves as a clamping position, which helps to enhance the pull-out resistance of the present invention.
在桩体1、桩帽2、桩嘴3以及导流板4的外表面均设置有防锈漆,该防锈漆可以选用聚氨酯防锈油漆,对桩体1、桩帽2、桩嘴3以及导流板4有防锈作用,避免发生腐蚀氧化,延长使用寿命。The outer surfaces of the pile body 1, pile cap 2, pile mouth 3 and deflector 4 are all provided with anti-rust paint, which can be selected from polyurethane anti-rust paint. And the deflector 4 has an anti-rust effect to avoid corrosion and oxidation and prolong the service life.
在桩帽2上还设置有安装槽22,用于与木屋的底部安装螺栓,对木屋进行固定。The pile cap 2 is also provided with an installation slot 22 for installing bolts with the bottom of the wooden house to fix the wooden house.
本发明的工作原理是,桩嘴4朝下,将本发明的打入到泥地中,由于导流板4的设置,对大块的泥土和硬物有阻挡作用,因此桩体1基本保持中空状态,然后用外部的高压水泥泵从桩帽2的进料口21注入调配好的水泥砂浆,当水泥砂浆遇到导流板4阻挡时会由垂直下落运动改为横向扩张运动,从而使水泥砂浆更多地聚集在桩嘴4的周围,形成有效的水泥块结构,最大限度地增加桩体1下方水泥块的形成体积,一方面由于桩体内部也灌满水泥浆砂,因此增加了该桩承托力和重力,另一方面所形成的水泥块反过来又牢牢地锁住桩嘴4,使该桩整体凝固在地表面的深处,不容易发生晃动或被抽离,最后将木屋通过桩帽2上的安装槽22锁定在该桩上,抗倒能力强。The working principle of the present invention is that the pile head 4 faces downwards, and the invention is driven into the mud ground. Due to the arrangement of the deflector 4, it has a blocking effect on large pieces of soil and hard objects, so the pile body 1 is basically maintained In the hollow state, the external high-pressure cement pump is used to inject the prepared cement mortar from the inlet 21 of the pile cap 2. When the cement mortar encounters the deflector 4, it will change from a vertical fall motion to a lateral expansion motion, so that Cement mortar gathers more around the pile mouth 4 to form an effective cement block structure, which maximizes the formation volume of the cement block under the pile body 1. On the one hand, the pile body is also filled with cement mortar, so it increases The pile bearing force and gravity, on the other hand, the cement block formed in turn firmly locks the pile mouth 4, so that the pile is solidified in the depth of the ground surface, and it is not easy to shake or be pulled away. The wooden house is locked on the pile through the installation groove 22 on the pile cap 2 and has strong anti-falling ability.
在本发明桩嘴4构思的启发下,桩嘴4采用多辨形三角片焊接成型的结构也属于本发明的保护范围之内。Inspired by the concept of the spout 4 of the present invention, the structure in which the spout 4 is welded and formed by a multi-discriminating triangular piece also falls within the protection scope of the present invention.
最后应说明的是:以上仅为本发明的优选实施例而已,并不用于限制本发明,尽管参照实施例对本发明进行了详细的说明,对于本领域的技术人员来说,其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换,但是凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。Finally, it should be noted that the above are only preferred embodiments of the present invention and are not intended to limit the present invention. Although the present invention has been described in detail with reference to the embodiments, for those skilled in the art, it can still The technical solutions described in the embodiments are modified, or some of the technical features are equivalently replaced, but any modification, equivalent replacement, improvement, etc. made within the spirit and principles of the present invention should be included in the present invention Within the scope of protection.

Claims (9)

  1. 一种水泥钢管桩,其特征在于,包括桩体,所述桩体是一中空设计的管体,所述桩体的上方设置有桩帽,所述桩帽上预留有进料口,所述桩体的下方还设置有桩嘴,所述进料口与所述桩体连通,所述桩体与所述桩嘴连通,所述桩嘴上设置有导流板。A cement steel pipe pile is characterized by including a pile body, the pile body is a hollow design pipe body, a pile cap is provided above the pile body, and a feed inlet is reserved on the pile cap, A pile spout is also provided below the pile body, the feed inlet communicates with the pile body, the pile body communicates with the pile spout, and a deflector plate is provided on the pile spout.
  2. 根据权利要求1所述的一种水泥钢管桩,其特征在于,所述桩嘴包括第一板片和第二板片,所述第一板片和第二板片呈十字形交叉设置,所述第一板片和第二板片的厚度相同,所述第一板片上设置有第一插槽,所述第二板片上设置有第二插槽,将所述第一板片的第一插槽插入至所述第二板片的第二插槽,能将所述第一板片与第二板片进行相互固定。The cement steel pipe pile according to claim 1, wherein the pile nozzle includes a first plate and a second plate, the first plate and the second plate are arranged in a cross shape, The first plate and the second plate have the same thickness. The first plate is provided with a first slot, and the second plate is provided with a second slot. A slot is inserted into the second slot of the second plate to fix the first plate and the second plate to each other.
  3. 根据权利要求2所述的一种水泥钢管桩,其特征在于,所述第一板片下端外侧两斜边延长线形成的夹角以及第二板片的最下端尖角均是锐角,以利于插入土地。The cement steel pipe pile according to claim 2, wherein the angle formed by the extension lines of the two oblique sides outside the lower end of the first plate and the lowermost sharp angle of the second plate are acute angles, Conducive to inserting land.
  4. 根据权利要求2所述的一种水泥钢管桩,其特征在于,所述导流板设置在所述第一板片和第二板片相交形成的夹角处,所述导流板与所述第一板片、第二板片包围形成的开口朝上。The cement steel pipe pile according to claim 2, wherein the deflector is disposed at an angle formed by the intersection of the first and second plates, and the deflector and the The opening formed by the first plate and the second plate is upward.
  5. 根据权利要求2至4所述的一种水泥钢管桩,其特征在于,所述第一板片和第二板片上均设置有第一装配槽和第二装配槽,所述第一板片或第二板片上的第一装配槽与所述第二装配槽之间的距离尺寸与所述桩体的管径尺寸一致,所述桩体的下端连接安装在所述第一安装槽和第二安装槽上。A cement steel pipe pile according to claims 2 to 4, characterized in that both the first plate and the second plate are provided with a first assembling groove and a second assembling groove, and the first plate Or the distance between the first assembly groove on the second plate and the second assembly groove is the same as the pipe diameter of the pile body, and the lower end of the pile body is connected to the first installation groove and the first Two on the installation slot.
  6. 根据权利要求5所述的一种水泥钢管桩,其特征在于,所述第一板片和第二板片的两侧还设置有卡位。The cement steel pipe pile according to claim 5, wherein the first plate and the second plate are further provided with clamping positions on both sides.
  7. 根据权利要求1所述的一种水泥钢管桩,其特征在于,所述桩帽上还设置有安装槽。The cement steel pipe pile according to claim 1, wherein the pile cap is further provided with an installation groove.
  8. 根据权利要求1所述的一种水泥钢管桩,其特征在于,所述导流板的厚度是3至5mm。The cement steel pipe pile according to claim 1, wherein the thickness of the deflector is 3 to 5 mm.
  9. 根据权利要求1所述的一种水泥钢管桩,其特征在于,所述桩体、桩帽、桩嘴以及导流板的外表面均设置有防锈漆。A cement steel pipe pile according to claim 1, characterized in that the outer surfaces of the pile body, pile cap, pile nozzle and deflector are all provided with anti-rust paint.
PCT/CN2018/121140 2018-11-14 2018-12-14 Cement steel pipe pile WO2020098041A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201811351663.2A CN109457695A (en) 2018-11-14 2018-11-14 A kind of cement steel-pipe pile
CN201811351663.2 2018-11-14

Publications (1)

Publication Number Publication Date
WO2020098041A1 true WO2020098041A1 (en) 2020-05-22

Family

ID=65610380

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2018/121140 WO2020098041A1 (en) 2018-11-14 2018-12-14 Cement steel pipe pile

Country Status (2)

Country Link
CN (1) CN109457695A (en)
WO (1) WO2020098041A1 (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB796262A (en) * 1956-10-05 1958-06-11 Mueller Ludwig Improvements in or relating to piles
CN101245598A (en) * 2007-02-16 2008-08-20 夏传清 Combined construction technique for driven cast-in-place pile and driven pile tip and driven pipe
CN102677666A (en) * 2012-05-03 2012-09-19 山东鸿泰建设集团有限公司 Concrete piling process and drilling machine special for same
CN202595729U (en) * 2012-05-03 2012-12-12 山东鸿泰建设集团有限公司 Drilling machine special for concrete pile forming process
CN106013098A (en) * 2016-07-14 2016-10-12 淮海工学院 Miniature steel pipe pile and grouting reinforcement method
CN205822174U (en) * 2016-07-14 2016-12-21 淮海工学院 Miniature steel pipe pile

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN209941671U (en) * 2018-11-14 2020-01-14 佛山市高明顺高木业有限公司 Novel cement steel pipe pile

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB796262A (en) * 1956-10-05 1958-06-11 Mueller Ludwig Improvements in or relating to piles
CN101245598A (en) * 2007-02-16 2008-08-20 夏传清 Combined construction technique for driven cast-in-place pile and driven pile tip and driven pipe
CN102677666A (en) * 2012-05-03 2012-09-19 山东鸿泰建设集团有限公司 Concrete piling process and drilling machine special for same
CN202595729U (en) * 2012-05-03 2012-12-12 山东鸿泰建设集团有限公司 Drilling machine special for concrete pile forming process
CN106013098A (en) * 2016-07-14 2016-10-12 淮海工学院 Miniature steel pipe pile and grouting reinforcement method
CN205822174U (en) * 2016-07-14 2016-12-21 淮海工学院 Miniature steel pipe pile

Also Published As

Publication number Publication date
CN109457695A (en) 2019-03-12

Similar Documents

Publication Publication Date Title
CN207092014U (en) A kind of novel ecological building block
WO2020098041A1 (en) Cement steel pipe pile
CN208702357U (en) A kind of bridge construction dust-collecting type drilling equipment
CN208734016U (en) A kind of reverse-filling ventilation shaft
CN207363390U (en) A kind of gardens guardrail
CN212405189U (en) Slope support composite construction
CN112695946A (en) Roof structure for assembled building anti-seismic support
CN209941671U (en) Novel cement steel pipe pile
CN210684669U (en) Foundation precipitation reinforcing uplift pile device
CN207452933U (en) A kind of building aseismicity pile foundation
CN210315493U (en) Foundation structure
CN207452673U (en) A kind of gardens float plank road
CN210288575U (en) Courtyard fire pool
CN205454806U (en) Flowerpot that can make up
CN203902109U (en) Large landscape screen wall
CN209194546U (en) A kind of Foundation Supported with Composite Soil Nailing
CN209053454U (en) A kind of architectural engineering sandy soil radical occlusion device
CN206968944U (en) A kind of leisure fishing wayside pavilion waterborne
CN207672603U (en) A kind of greening soil blocking wall in structure sponge city
CN207080000U (en) Antidetonation log cabin
CN207260065U (en) It is a kind of can over-water construction pile foundation board plug type flow blocking wall construction
CN201228338Y (en) Novel grass planting brick
CN205134346U (en) Building pile foundation structure
CN217791179U (en) Gardens high altitude medicine sprinkler for nursery stock
CN205116769U (en) Guardrail for building site

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 18939971

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 18939971

Country of ref document: EP

Kind code of ref document: A1