EP0613980B1 - Ballast levelling machine - Google Patents

Ballast levelling machine Download PDF

Info

Publication number
EP0613980B1
EP0613980B1 EP94890028A EP94890028A EP0613980B1 EP 0613980 B1 EP0613980 B1 EP 0613980B1 EP 94890028 A EP94890028 A EP 94890028A EP 94890028 A EP94890028 A EP 94890028A EP 0613980 B1 EP0613980 B1 EP 0613980B1
Authority
EP
European Patent Office
Prior art keywords
machine
ballast
frame
machine according
frame part
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
EP94890028A
Other languages
German (de)
French (fr)
Other versions
EP0613980A2 (en
EP0613980A3 (en
Inventor
Josef Theurer
Herbert Wörgötter
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Franz Plasser Bahnbaumaschinen Industrie GmbH
Original Assignee
Franz Plasser Bahnbaumaschinen Industrie GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Franz Plasser Bahnbaumaschinen Industrie GmbH filed Critical Franz Plasser Bahnbaumaschinen Industrie GmbH
Publication of EP0613980A2 publication Critical patent/EP0613980A2/en
Publication of EP0613980A3 publication Critical patent/EP0613980A3/en
Application granted granted Critical
Publication of EP0613980B1 publication Critical patent/EP0613980B1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B27/00Placing, renewing, working, cleaning, or taking-up the ballast, with or without concurrent work on the track; Devices therefor; Packing sleepers
    • E01B27/02Placing the ballast; Making ballastway; Redistributing ballasting material; Machines or devices therefor; Levelling means
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/02Removing or re-contouring ballast
    • E01B2203/025Suction
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/02Removing or re-contouring ballast
    • E01B2203/027Sweeping
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/04Cleaning or reconditioning ballast or ground beneath
    • E01B2203/042Cleaning or reconditioning ballast or ground beneath in situ,e.g. vacuum-cleaners
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/04Cleaning or reconditioning ballast or ground beneath
    • E01B2203/045Cleaning or reconditioning ballast or ground beneath the ballast having been taken up
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/06Placing ballast
    • E01B2203/065Re-use of ballast
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/08Levelling ballast or ground beneath
    • E01B2203/083Ploughs
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/08Levelling ballast or ground beneath
    • E01B2203/086Rotating brooms
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/14Way of locomotion or support
    • E01B2203/141Way of locomotion or support on the track to be treated

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)
  • Soil Working Implements (AREA)
  • Separation By Low-Temperature Treatments (AREA)
  • Catching Or Destruction (AREA)
  • Crushing And Pulverization Processes (AREA)
  • Other Liquid Machine Or Engine Such As Wave Power Use (AREA)
  • Revetment (AREA)
  • Low-Molecular Organic Synthesis Reactions Using Catalysts (AREA)
  • Arrangement Of Elements, Cooling, Sealing, Or The Like Of Lighting Devices (AREA)
  • Circuit Arrangements For Discharge Lamps (AREA)
  • Cleaning In General (AREA)

Abstract

A ballast levelling machine (1) with a machine frame (4) supported on rail running gear (5) is equipped with a ballast plough (11) which is height-adjustable by means of drives (8), a height-adjustable and rotatable sweeping brush (18), a suction arrangement (17) having a vacuum generator (16), as well as with a driver's cab (19). The machine frame (4) consists of a first frame part (2) having the ballast plough (11) at the front in the travelling direction, and of a further, second frame part (3) which is articulatedly connected to the first frame part and has the vacuum generator (16) and the sweeping brush (18). The suction arrangement (17) has a suction nozzle (20) which projects beyond the machine end (21) at the rear with respect to the travelling direction, is connected to the vacuum generator (16) by a flexible suction pipe (22) and to a drive (40) and which is adjustable by means of a control device (23) located in the adjoining driver's cab (19). <IMAGE>

Description

Die Erfindung betrifft eine Schotterplaniermaschine mit einem auf Schienenfahrwerken abgestützten Maschinenrahmen, einem durch Antriebe höhenverstellbaren Schotterpflug, einer höhenverstell- und rotierbaren Kehrbürste, einer einen Unterdruckerzeuger aufweisenden Sauganordnung sowie mit einer Fahrkabine.The invention relates to a ballast leveling machine with a machine frame supported on rail bogies, a ballast plow that is height-adjustable by drives, a height-adjustable and rotatable sweeping brush, a suction arrangement that has a vacuum generator, and with a driving cabin.

Die EP 0 418 428 A1 beschreibt eine derartige Schotterplaniermaschine zum Profilieren der Schotterbettung eines Gleises, wobei die Kehrbürste in einem mit dem Unterdruckerzeuger verbundenen Saugkasten angeordnet ist. Damit kann der beim Arbeitseinsatz der Kehrbürste auftretende Staub sofort abgesaugt und dessen die Umwelt beeinträchtigender Austritt weitgehend vermieden werden.EP 0 418 428 A1 describes such a ballast leveling machine for profiling the ballast bedding of a track, the sweeping brush being arranged in a suction box connected to the vacuum generator. This means that the dust that occurs when the sweeping brush is in use can be vacuumed off immediately and its discharge, which has an adverse effect on the environment, can be largely avoided.

Durch die DE 21 36 306 A ist auch eine gleisverfahrbare Vorrichtung zum Ausheben von Schotter aus Gleisanlagen bekannt. Dazu ist auf einem Fahrzeug ein mit einem Saugrohr verbundener und verschwenkbarer Ausleger vorgesehen. Das Saugrohr ist über eine endseitige Fahrkabine vorkragend angeordnet und am düsenseitigen Ende mit vibrierbaren Werkzeugen zum Lockern des abzusaugenden Schotters verbunden.From DE 21 36 306 A a track-traveling device for lifting ballast from track systems is also known. For this purpose, a pivotable boom connected to a suction pipe is provided on a vehicle. The intake manifold is cantilevered over an end cab and is connected at the nozzle end to vibratable tools for loosening the ballast to be extracted.

Weitere derartige, über ein Fahrzeugende vorkragende Saugrohre zum Absaugen von Gleisschotter sind außerdem noch durch die DE 91 11 238 U1, DE 90 00 529 U1 und EP 0 485 810 A1 bekannt.Further such suction pipes projecting over a vehicle end for suctioning track ballast are also known from DE 91 11 238 U1, DE 90 00 529 U1 and EP 0 485 810 A1.

Außerdem ist noch durch die US 5 052 132 ein aus zwei gelenkig miteinander verbundenen Rahmenteilen zusammengesetzter Maschinenrahmen bekannt, wobei dem in Fahrtrichtung vorderen ein höhenverstellbarer Schotterpflug sowie ein Schottersilo und dem hinteren Rahmenteil eine Kehrbürste zugeordnet sind.In addition, a machine frame composed of two articulated frame parts is known from US Pat. No. 5,052,132, with a height-adjustable ballast plow in front in the direction of travel and a ballast silo and a rear brush part being assigned to the rear frame part.

Die Aufgabe der vorliegenden Erfindung liegt nun in der Schaffung einer Schotterplaniermaschine der eingangs beschriebenen Art, mit der auch in - den Einsatz des Schotterpfluges bzw. der Kehrbürste einschränkenden - Problembereichen eine gewünschte Profilierung der Schotterbettung durchführbar ist.The object of the present invention is to create a ballast leveling machine of the type described in the introduction, with which a desired profiling of the ballast bed can also be carried out in problem areas restricting the use of the ballast plow or the sweeping brush.

Diese Aufgabe wird durch die im kennzeichnenden Teil des Anspruches 1 angeführten Merkmale gelöst. Aus dieser Merkmalskombination ergibt sich der besondere Kombinationseffekt, daß im Rahmen einer einzigen Arbeitsdurchfahrt sofort im Anschluß an eine ordnungsgemäße und leistungsmäßig uneingeschränkte Reprofilierung durch den Schotterpflug auch in den genannten Problembereichen des Gleises durch eine gezielte und damit sehr wirksame Schotterabsaugung eine vorschriftsmäßige Schotterverteilung durchführbar ist. Durch die über das hintere Maschinenende vorkragende Saugdüse ist diese unter uneingeschränkter Beobachtung von der Fahrkabine aus gezielt und rasch zu den Absaugbereichen verstellbar, um dort überschüssigen Schotter bzw. auch angesammelten Schmutz ohne Beeinträchtigung der kontinuierlichen Arbeitsvorfahrt der Schotterplaniermaschine absaugen zu können. Mit der zweiteiligen Rahmenausbildung kann einerseits die Kehrbürste unter Vermeidung eines das hintere Schienenfahrwerk übergreifenden Überhanges des Maschinenrahmens zwischen den Schienenfahrwerken angeordnet und andererseits auch problemlos am hinteren Maschinenende eine Fahrkabine zur genauen Beobachtung der Saugdüsenpositionierung vorgesehen werden.This object is achieved by the features stated in the characterizing part of claim 1. The special combination results from this combination of features Combination effect that within the scope of a single work passage immediately after a proper and performance-free reprofiling by the ballast plow, a prescribed and thus very effective ballast extraction can also be carried out in the problem areas of the track by means of a targeted and therefore very effective ballast extraction. Thanks to the suction nozzle protruding over the rear end of the machine, it can be quickly and precisely adjusted from the driver's cab to the extraction areas so that excess ballast or accumulated dirt can be extracted without impairing the continuous work approach of the ballast leveling machine. With the two-part frame design, on the one hand the sweeping brush can be arranged between the rail undercarriages while avoiding an overhang of the machine frame that overlaps the rear rail undercarriage, and on the other hand a driving cabin can be easily provided at the rear end of the machine for precise observation of the suction nozzle positioning.

Die Weiterbildung nach Anspruch 2 schafft die vorteilhafte Möglichkeit, den aus dem Gleis aufgenommenen überschüssigen Schotter auf der Maschine zu speichern und mitzuführen, um damit bei Bedarf Gleisbereiche mit einem Mangel an Schotter wieder auffüllen zu können.The development according to claim 2 creates the advantageous possibility of storing the excess ballast picked up from the track on the machine and carrying it in order to be able to replenish track areas with a lack of ballast if necessary.

Die Merkmale gemäß den Ansprüchen 3 und 4 gewährleisten sowohl eine die Überstellfahrt nicht störende Lagerung der Saugdüse in ihrer Außerbetriebstellung als auch eine sehr vielseitige Verstellbarkeit der Düse im Arbeitseinsatz in bezug auf den Maschinenrahmen, um Schotteranhäufungen unabhängig von deren Lage bzw. der Lage des Problembereiches, z. B. eines Linienleiters, absaugen zu können.The features according to claims 3 and 4 ensure both a storage trip of the suction nozzle in its decommissioning position, which does not interfere with the transfer travel, as well as a very versatile adjustability of the nozzle in use in relation to the machine frame, in order to accumulate ballast regardless of its location or the location of the problem area, e.g. B. a line conductor to be able to suction.

Die Weiterbildung nach den Ansprüchen 5 und 6 erlaubt ein einfaches und problemloses Ausscheiden des angesaugten Schotters aus dem Saugluftstrom und Transportieren des Schotters zum Schottersilo zwecks allfälligen Wiederabwurfs ins Gleis bei Bedarf. Hierbei erweist sich weiters die Ausbildung gemäß den Ansprüchen 7 und 8 als besonders vorteilhaft, da auf diese Weise der bei der Ansaugung entstehende Staub umweltschonend ausgefiltert und - bei Stillstand der Maschine - entsorgt werden kann.The further development according to claims 5 and 6 allows a simple and problem-free separation of the suctioned ballast from the suction air flow and transporting the ballast to the ballast silo for the purpose of possible re-throwing into the track if necessary. Here, the design according to claims 7 and 8 also proves to be particularly advantageous, since in this way the dust produced during the suction can be filtered out in an environmentally friendly manner and disposed of when the machine is at a standstill.

Die in Anspruch 9 beschriebene Anordnung des Schottersilos hinter dem Schotterpflug schafft den Vorteil, daß die Bedienungsperson ungehinderten Einblick auf den Pflug behält und diesen während des Arbeitseinsatzes optimal steuern kann.The arrangement of the ballast silo behind the ballast plow, as described in claim 9, creates the advantage that the operator has an unobstructed view of the plow and can optimally control it during work.

Das Merkmal nach Anspruch 10 bietet die Möglichkeit, Kehrbürsten in verschiedener Breite auf der Maschine mitzuführen und - je nach Erfordernissen - rasch gegeneinander auszutauschen, um so z. B. einen Weichen- oder Kreuzungsbereich vollständig über dessen gesamte Breite kehren zu können.The feature according to claim 10 offers the possibility to carry sweeping brushes in different widths on the machine and - depending on requirements - quickly exchange them, so z. B. to be able to sweep a switch or crossing area completely over its entire width.

Schließlich ermöglicht noch eine Variante gemäß den Ansprüchen 11 und 12 eine zusätzliche Erweiterung der Einsatzmöglichkeiten der erfindungsgemäßen Maschine. Mit dem Schotterspeicher können nun relativ große Schottermengen auf der Maschine mitgeführt werden, um in Gleisbereichen mit stark erhöhtem Schotterbedarf abgeworfen zu werden. Über das Bodenförderband ist der Schotter zu diesem Zweck problemlos dem Schottersilo bzw. dessen Auslaßschurren zuführbar.Finally, a variant according to claims 11 and 12 enables an additional expansion of the possible uses of the machine according to the invention. With the ballast storage, relatively large amounts of ballast can now be carried on the machine in order to be thrown off in track areas with greatly increased ballast demand. For this purpose, the ballast can easily be fed to the ballast silo or its outlet chutes via the floor conveyor belt.

Im folgenden wird die Erfindung anhand zweier in der Zeichnung dargestellter Ausführungsbeispiele näher beschrieben.The invention is described in more detail below with reference to two exemplary embodiments shown in the drawing.

Es zeigen:

  • Fig. 1 eine Seitenansicht einer Schotterplaniermaschine mit einem zweiteilig ausgebildeten Maschinenrahmen und einer endseitig an diesem befestigten Saugdüse,
  • Fig. 2 eine Ansicht der Maschine gemäß Pfeil II, wobei die Saugdüse für den Arbeitseinsatz abgesenkt ist,
  • Fig. 3 eine Ansicht der Maschine wie in Fig. 2, wobei jedoch die Saugdüse in eine Verriegelungsstellung für die Überstellfahrt angehoben ist, und
  • Fig. 4 eine Seitenansicht einer anderen Variante der erfindungsgemäßen Maschine mit einem dreiteilig ausgebildeten Maschinenrahmen.
Show it:
  • 1 is a side view of a ballast leveling machine with a two-part machine frame and a suction nozzle attached to the end thereof,
  • 2 is a view of the machine according to arrow II, with the suction nozzle lowered for work,
  • Fig. 3 is a view of the machine as in Fig. 2, but with the suction nozzle raised to a locking position for the transfer travel, and
  • Fig. 4 is a side view of another variant of the machine according to the invention with a three-part machine frame.

Eine in Fig. 1 dargestellte Schotterplaniermaschine 1 weist einen aus zwei Rahmenteilen 2,3 gebildeten Maschinenrahmen 4 auf, der über insgesamt drei Schienenfahrwerke 5 auf einem Gleis 6 abgestützt und in einer durch einen Pfeil 7 angegebenen Fahrtrichtung verfahrbar ist. Die beiden in Maschinenlängsrichtung hintereinander angeordneten Rahmenteile 2,3 sind im Bereich des mittleren Schienenfahrwerks 5 über eine Kupplung 12 gelenkig miteinander verbunden. Auf dem bezüglich der Fahrtrichtung vorderen, ersten Rahmenteil 2 befindet sich ein über Antriebe 8 höhenverstellbarer, aus Mittelpflug 9 und Flankenpflug 10 bestehender Schotterpflug 11, der unmittelbar hinter einer am vorderen Ende des Rahmenteils 2 vorgesehenen Fahrkabine 13 bzw. in deren Sichtbereich angeordnet ist. Ein Schottersilo 14 mit zum Gleis 6 gerichteten Auslaßschurren 15 ist - von der Fahrkabine 13 in Maschinenlängsrichtung distanziert - am hinteren Ende des Rahmenteils 2 befestigt.A ballast leveling machine 1 shown in FIG. 1 has a machine frame 4 formed from two frame parts 2, 3, which is supported on a track 6 via a total of three rail bogies 5 and can be moved in a direction of travel indicated by an arrow 7. The two frame parts 2, 3 arranged one behind the other in the longitudinal direction of the machine are in the area of the middle rail carriage 5 articulated to one another via a coupling 12. On the front of the first frame part 2 with respect to the direction of travel there is a ballast plow 11 which is height-adjustable via drives 8 and consists of a middle plow 9 and side plow 10, which is arranged directly behind a driver's cabin 13 provided at the front end of the frame part 2 or in its field of vision. A ballast silo 14 with outlet chutes 15 directed towards the track 6 is fastened to the rear end of the frame part 2 at a distance from the driving cabin 13 in the machine longitudinal direction.

Der hintere, zweite Rahmenteil 3 des Maschinenrahmens 4 ist mit einer einen Unterdruckerzeuger 16 aufweisenden Sauganordnung 17, einer höhenverstell- und rotierbaren Kehrbürste 18 sowie einer am hinteren Rahmenteilende befindlichen weiteren Fahrkabine 19 ausgestattet. Die Sauganordnung 17 ist mit einer Saugdüse 20 versehen, die über das bezüglich der Fahrtrichtung hintere Maschinenende 21 vorkragt und die mittels eines flexiblen Absaugrohrs 22 mit dem Unterdruckerzeuger 16 verbunden ist. Die Saugdüse 20 ist anhand von - in den Fig. 2 und 3 noch genauer zu beschreibenden - Antrieben 40,41,44 über eine in der angrenzenden Fahrkabine 19 befindliche Steuereinrichtung 23 verstellbar ausgebildet. Weiters ist am zweiten Rahmenteil 3 ein in Maschinenlängsrichtung verlaufendes Förderband 24 vorgesehen, dessen tiefer gelegenes, aufnahmeseitiges Ende der Kehrbürste 18 und dessen höher gelegenes, abwurfseitiges Ende dem am ersten Rahmenteil 2 angeordneten Schottersilo 14 zugeordnet ist, wobei die Kehrbürste 18 noch zusätzlich mit einem Querförderband 25 zum seitlichen Schotterabwurf ausgestattet ist.The rear, second frame part 3 of the machine frame 4 is equipped with a suction arrangement 17 having a vacuum generator 16, a height-adjustable and rotatable sweeping brush 18 and a further driving cabin 19 located at the rear end of the frame part. The suction arrangement 17 is provided with a suction nozzle 20 which projects beyond the rear end 21 of the machine with respect to the direction of travel and which is connected to the vacuum generator 16 by means of a flexible suction pipe 22. The suction nozzle 20 is designed to be adjustable by means of drives 40, 41, 44 - to be described in more detail in FIGS. 2 and 3 - via a control device 23 located in the adjacent driving cabin 19. Furthermore, a conveyor belt 24 running in the longitudinal direction of the machine is provided on the second frame part 3, the lower, receiving end of the sweeping brush 18 and the higher, discharge-side end of which is assigned to the ballast silo 14 arranged on the first frame part 2, the sweeping brush 18 additionally having a cross conveyor belt 25 is equipped for lateral ballast discharge.

Die Sauganordnung 17 weist zwischen der Saugdüse 20 und dem Unterdruckerzeuger 16 einen in das Absaugrohr 22 eingebundenen Zyklonabscheider 26 auf, dessen im unteren Endbereich gelegener Auslaßöffnung 27 eine Schleusenkammer 28 mit einer fernsteuerbaren Entladeöffnung 29 nachgeordnet ist. Diese befindet sich direkt oberhalb des Förderbandes 24 und steht somit mit dem Schottersilo 14 in Verbindung. Der aus dem Zyklonabscheider 26 kommende Saugluftstrom wird über das Absaugrohr 22 in eine Feinstaubfiltereinheit 30 geleitet, in der der ausgefilterte Staub in einem V-förmigen Speicher 31 gesammelt wird, um bedarfsweise über eine in dessen unterem Endbereich befindliche Förderschnecke 32 entladen zu werden.The suction arrangement 17 has, between the suction nozzle 20 and the vacuum generator 16, a cyclone separator 26 integrated in the suction pipe 22, the outlet opening 27 located in the lower end region of which is followed by a lock chamber 28 with a remotely controllable discharge opening 29. This is located directly above the conveyor belt 24 and is thus connected to the ballast silo 14. The suction air flow coming from the cyclone separator 26 is passed via the suction pipe 22 into a fine dust filter unit 30, in which the filtered-out dust is collected in a V-shaped storage device 31 in order to be discharged if necessary via a screw conveyor 32 located in its lower end region.

In einer mit dem Maschinenrahmen 4 bzw. dem zweiten Rahmenteil 3 verbundenen Halterung 33 ist eine zusätzliche Kehrbürste 34 lösbar gelagert und anhand eines Antriebes 35 höhenverstellbar ausgebildet bzw. ins Gleis 6 absenkbar. Ein Motor 36 dient der Energieversorgung eines Fahrantriebes 37 sowie sämtlicher anderer Antriebe der Schotterplaniermaschine 1.In a holder 33 connected to the machine frame 4 or the second frame part 3, an additional sweeping brush 34 is detachably mounted and by means of a Drive 35 height adjustable or lowerable into the track 6. A motor 36 serves to supply energy to a traction drive 37 and all other drives of the ballast leveling machine 1.

Wie nun in Fig. 2 und 3 ersichtlich, ist die Saugdüse 20 auf einer Parallelogrammanlenkung 38 fixiert, die ihrerseits mit einem Tragkörper 39 verbunden ist. Über den Antrieb 40 ist die Parallelogrammanlenkung 38 mitsamt der Saugdüse 20 höhenverstellbar, während der weitere Antrieb 41 eine Verschwenkung der Parallelogrammanlenkung 38 zum Tragkörper 39 um eine vertikale Achse 42 bewirkt. Der Tragkörper 39 ist auf senkrecht zur Maschinenlängsrichtung und horizontal verlaufenden Führungsholmen 43 mittels des Antriebes 44 querverschiebbar. In Fig. 2 ist die Saugdüse 20 in der für den Arbeitseinsatz abgesenkten Arbeitsstellung dargestellt, um im Bereich eines Linienleiters 45 befindliche Schotteranhäufungen 46 kontinuierlich abzusaugen. Dabei ragt die Saugdüse 20 derart über das Stirnende des Maschinenrahmens 4 bzw. des zweiten Rahmenteils 3 vor, daß eine in der Fahrkabine 19 befindliche Bedienungsperson ungehinderten Einblick auf die im Einsatz abgesenkte Saugdüse hat. Die Länge der beiden Führungsholme 43 für die Querverschiebung des Tragkörpers 39 bzw. der Saugdüse 20 ist etwas länger als die Spurweite des Gleises 6 ausgebildet. Damit besteht die Möglichkeit, die Saugdüse 20 gegebenenfalls auch zur Absaugung von im Schwellenvorkopfbereich befindlichen Schotteranhäufungen zu verwenden.As can now be seen in FIGS. 2 and 3, the suction nozzle 20 is fixed on a parallelogram linkage 38, which in turn is connected to a support body 39. The height of the parallelogram linkage 38 together with the suction nozzle 20 can be adjusted via the drive 40, while the further drive 41 causes the parallelogram linkage 38 to be pivoted relative to the support body 39 about a vertical axis 42. The support body 39 can be transversely displaced by means of the drive 44 on guide rails 43 running perpendicular to the longitudinal direction of the machine and horizontally. 2, the suction nozzle 20 is shown in the lowered working position for work, in order to continuously suck up accumulations of ballast 46 located in the area of a line conductor 45. The suction nozzle 20 protrudes over the front end of the machine frame 4 or the second frame part 3 in such a way that an operator located in the driving cabin 19 has an unobstructed view of the suction nozzle which is lowered in use. The length of the two guide bars 43 for the transverse displacement of the support body 39 or the suction nozzle 20 is somewhat longer than the track width of the track 6. This makes it possible to use the suction nozzle 20, if appropriate, also for suctioning up ballast accumulations located in the area of the sleeper head.

Für den Arbeitseinsatz sind der Mittelpflug 9 und die beiden Flankenpflüge 10 sowie die Kehrbürste 18 auf das Gleis 6 abgesenkt. Sollte stellenweise zu wenig Schotter vorhanden sein, besteht mit Hilfe des im Schottersilo 14 gespeicherten Schotters die Möglichkeit, bedarfsweise eine Einschotterung des Gleises 6 durchzuführen. Der von der Kehrbürste 18 nicht erfaßte Schotter im Bereich des Linienleiters 45 wird parallel zum Arbeitseinsatz des Schotterpfluges 11 mit Hilfe der am hinteren Maschinenende 21 befindlichen Saugdüse 20 abgesaugt. Dabei erfolgt eine entsprechende Positionierung der Saugdüse 20 durch Beaufschlagung der Antriebe 40,41 und 44 von der Fahrkabine 19 aus. Sollten zusätzlich zu dieser Schotteranhäufung 46 im Linienleiterbereich weitere Schotteranhäufungen, beispielsweise im Bereich eines Gleismagneten, festgestellt werden, so können auch diese zusätzlichen Schotteranhäufungen jederzeit durch entsprechendes Verschwenken der Saugdüse 20 abgesaugt werden. Der abgesaugte Schotter wird über die Entladeöffnung 29 auf das Förderband 24 und in weiterer Folge in den Schottersilo 14 abgeworfen.The middle plow 9 and the two side plows 10 and the sweeping brush 18 are lowered onto the track 6 for work. If there is not enough ballast in places, the ballast stored in the ballast silo 14 can be used to perform a ballast of the track 6 if necessary. The ballast not caught by the sweeping brush 18 in the area of the line conductor 45 is sucked off parallel to the work of the ballast plow 11 with the aid of the suction nozzle 20 located at the rear end 21 of the machine. A corresponding positioning of the suction nozzle 20 takes place by acting on the drives 40, 41 and 44 from the driving cabin 19. If, in addition to this ballast accumulation 46, further ballast accumulations are found in the line conductor area, for example in the area of a track magnet, these additional ballast accumulations can also be suctioned off at any time by swiveling the suction nozzle 20 accordingly. The extracted ballast is discharged via the unloading opening 29 onto the conveyor belt 24 and subsequently into the ballast silo 14.

In Fig. 3 ist die Saugdüse 20 mittels der Antriebe 40, 41 und 44 in eine Verriegelungsstellung bzw. Außerbetriebstellung angehoben und in eine seitliche Lage verschwenkt, in der sich die Saugdüse ober dem bzw. seitlich neben dem hinteren Maschinenende 21 unmittelbar hinter der Fahrkabine 19 innerhalb des Lichtraumprofiles befindet. Damit ist eine Überstellfahrt der Maschine 1 möglich, ohne daß die Sicht der in der Fahrkabine 19 befindlichen Bedienungsperson beeinträchtigt ist.3, the suction nozzle 20 is raised by means of the drives 40, 41 and 44 into a locking position or inoperative position and pivoted into a lateral position in which the suction nozzle rises above or to the side of the rear machine end 21 directly behind the driving cabin 19 located within the clearance profile. A transfer travel of the machine 1 is thus possible without the view of the operator in the driving cabin 19 being impaired.

Die in Fig. 4 dargestellte Schotterplaniermaschine 47 ist eine Variante der Maschine nach Fig. 1, wobei übereinstimmende bzw. funktionsgleiche Teile der Einfachheit halber zum Teil mit den gleichen Bezugszeichen versehen sind. Die Maschine 47 weist einen Maschinenrahmen 48 auf, der zusätzlich zum vorderen, ersten Rahmenteil 49 und hinteren, zweiten Rahmenteil 50 mit einem weiteren, zwischen diesen angeordneten und gelenkig mit diesen verbundenen mittleren, dritten Rahmenteil 51 ausgestattet ist. Dieser ist auf zwei Drehgestellfahrwerken 5 gelagert und mit einem Motor 52 und Fahrantrieb 53 versehen, während der auf jeweils nur einem einzelnen Schienenfahrwerk 5 abgestützte erste und zweite Rahmenteil 49,50 trailerartig endseitig daran angelenkt sind. Am dritten Rahmenteil 51 ist ein Schotterspeicher 54 angeordnet, dessen Bodenbereich durch ein Bodenförderband 55 mit tieferliegendem Aufnahmeende 56 und höherliegendem Abwurfende 57 gebildet ist.The ballast leveling machine 47 shown in FIG. 4 is a variant of the machine according to FIG. 1, for the sake of simplicity, parts that match or have the same function are partially provided with the same reference numerals. The machine 47 has a machine frame 48 which, in addition to the front, first frame part 49 and the rear, second frame part 50, is equipped with a further middle third frame part 51 arranged between them and articulatedly connected to them. This is mounted on two bogie bogies 5 and provided with a motor 52 and travel drive 53, while the first and second frame parts 49, 50, which are supported on only a single rail bogie 5, are articulated on the end thereof in the manner of a trailer. A ballast accumulator 54 is arranged on the third frame part 51, the bottom area of which is formed by a floor conveyor belt 55 with a lower receiving end 56 and a higher discharge end 57.

Das Abwurfende 57 befindet sich oberhalb des auf dem vorderen, ersten Rahmenteil 49 befestigten Schottersilos 14. Das bezüglich der Fahrtrichtung hinten angeordnete Aufnahmeende 56 liegt unterhalb des Abwurfbereiches eines Steilförderbandes 58, das zwischen dem Schotterspeicher 54 und der Kehrbürste 18 vorgesehen ist und das den von dieser aus dem Gleis 6 aufgenommenen Schotter sowie den aus der Entladeöffnung 29 der Schleusenkammer 28 kommenden Schotter in den Schotterspeicher 54 transportiert.The discharge end 57 is located above the ballast silo 14 fastened to the front, first frame part 49. The receiving end 56, which is arranged at the rear with respect to the direction of travel, lies below the discharge region of a steep conveyor belt 58, which is provided between the ballast store 54 and the sweeping brush 18 and that of the latter transported from the track 6 ballast and the ballast coming from the discharge opening 29 of the lock chamber 28 into the ballast storage 54.

Im Bereich zwischen dem hintersten Schienenfahrwerk 5 und der Kehrbürste 18 sind ferner zwei weitere Kehrbürsten 59 zu sehen, die über eine Halterung 60 am Maschinenrahmen 48 befestigt sind und mittels eines Antriebes 61 wahlweise ins Gleis 6 abgesenkt werden können, um gegen die Kehrbürste 18 ausgetauscht zu werden.In the area between the rearmost rail undercarriage 5 and the sweeping brush 18, two further sweeping brushes 59 can also be seen, which are fastened to the machine frame 48 via a holder 60 and can optionally be lowered into the track 6 by means of a drive 61 in order to be exchanged for the sweeping brush 18 will.

Claims (12)

  1. A ballast grading machine comprising a machine frame (4;48) supported on on-track undercarriages (5), a ballast plough (11) designed for vertical adjustment by means of drives (8), a vertically adjustable and rotatable sweeping brush (18), a suction arrangement (17) having a vacuum generator (16), and a driver's cab (19), characterized in that the machine frame (4;48) is composed of a front, first frame part (2;49) in the direction of travel which has the ballast plough (11), and at least one other, second frame part (3;50) joined to the said first frame part in an articulated manner and having the vacuum generator (16) and the sweeping brush (18), and in that the suction arrangement (17) has a suction nozzle (20) projecting over the rear machine end (21), with respect to the direction of travel, and connected by means of a flexible suction pipe (22) to the vacuum generator (16) and connected to drives (40,41,44), the said suction nozzle being adjustable by means of a control unit (23) located in the adjacent driver's cab (19).
  2. A machine according to claim 1, characterized in that on the second frame part (3) is provided a conveyor belt (24) which extends in the longitudinal direction of the machine and of which the lower, intake end is assoicated with the sweeping brush (18) and the elevated, discharge end is associated with a ballast hopper (14) situated on the first frame part (2).
  3. A machine according to claim 1 or 2, characterized in that the suction nozzle (20) is adjustable by means of the drives (40,41,44) into an inoperative position above or laterally adjacent to the rear machine end (21) and immediately following the driver's cab (19) (Fig. 3).
  4. A machine according to one of claims 1, 2 or 3, characterized in that the suction nozzle (20) is attached to a vertically adjustable parallelogram linkage (38) which is connected to a support body (39) for pivoting about a vertical axis (42), the support body (39) being transversely adjustable by means of a drive (44) perpendicularly to the longitudinal direction of the machine and horizontally.
  5. A machine according to one of claims 1 to 4, characterized in that the suction nozzle (20) is connected by the suction pipe (22) to a cyclone separator (26), of which the outlet opening (27) located in the lower end region is followed by a lock chamber (28) with a remotely controllable discharge opening (29).
  6. A machine according to claim 5, characterized in that the discharge opening (29) of the lock chamber (28) is arranged above the conveyor belt (24) or is associated therewith.
  7. A machine according to claim 5, characterized in that the suction nozzle (20) is connected by the suction pipe (22) to a fine dust filter unit (30).
  8. A machine according to claim 7, characterized in that associated with the fine dust filter unit (30) is a store (31), of which the lower end region has a screw conveyor (32).
  9. A machine according to one of claims 1 to 8, characterized in that the ballast plough (11) is arranged with respect to the direction of travel immediately following a driver's cab (13) situated at the front end of the machine frame (4;48) within visual range thereof or between the said driver's cab and the ballast hopper (14).
  10. A machine according to one of claims 1 to 9, characterized in that in a holder (33;60) designed for vertical adjustment by means of a drive (35;61) another sweeping brush (34;59) is mounted on the machine frame (4;48) and is detachably secured thereto.
  11. A machine according to one of claims 1 to 10, characterized in that provided between the front, first and rear, second frame part (49,50) of the machine frame (48) is another, central or third frame part (51) which is joined in an articulated manner to both frame parts and on which there is arranged a ballast store (54) with a base conveyor belt (55) forming the base area thereof and extending to above the ballast hopper (14).
  12. A machine according to claim 11, characterized in that the third frame part (51) is designed as a self-propelling hopper wagon provided with bogie undercarriages (5) and a motive drive (53), to which the first and second frame parts (49,50), each having only one on-track undercarriage (5), are linked in trailer-like fashion.
EP94890028A 1993-03-04 1994-02-02 Ballast levelling machine Expired - Lifetime EP0613980B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
AT42193 1993-03-04
AT421/93 1993-03-04

Publications (3)

Publication Number Publication Date
EP0613980A2 EP0613980A2 (en) 1994-09-07
EP0613980A3 EP0613980A3 (en) 1994-11-17
EP0613980B1 true EP0613980B1 (en) 1997-01-02

Family

ID=3490180

Family Applications (1)

Application Number Title Priority Date Filing Date
EP94890028A Expired - Lifetime EP0613980B1 (en) 1993-03-04 1994-02-02 Ballast levelling machine

Country Status (13)

Country Link
US (1) US5452528A (en)
EP (1) EP0613980B1 (en)
JP (1) JP3162568B2 (en)
CN (1) CN1057361C (en)
AT (1) ATE147113T1 (en)
AU (1) AU662675B2 (en)
CA (1) CA2116887C (en)
CZ (1) CZ279538B6 (en)
DE (1) DE59401436D1 (en)
FI (1) FI107819B (en)
PL (1) PL173799B1 (en)
RU (1) RU2087612C1 (en)
SK (1) SK280758B6 (en)

Families Citing this family (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0608679B1 (en) * 1993-01-29 1997-07-09 Franz Plasser Bahnbaumaschinen-Industriegesellschaft m.b.H. Machine for taking up ballast from a ballast bed under suction
AT403810B (en) * 1994-04-13 1998-05-25 Plasser Bahnbaumasch Franz MACHINE FOR PROCESSING THE GRAVEL BED OF A TRACK WITH A SUCTION BRUSH
ATE173777T1 (en) * 1994-04-18 1998-12-15 Plasser Bahnbaumasch Franz SUCTION MACHINE
US5664633A (en) * 1995-09-04 1997-09-09 Franz Plasser Bahnbaumaschinen-Industriegesellschaft M.B.H. Machine for treating a ballast bed
US5709001A (en) * 1996-02-05 1998-01-20 Franz Plasser Bahnbaumaschinen Industriegesellschaft M.B.H. Track work machine
NO312541B1 (en) * 1999-11-03 2002-05-27 Gto Subsea As Method and apparatus for moving rocks and loose masses under water
AT3655U3 (en) 2000-02-29 2001-02-26 Plasser Bahnbaumasch Franz STAMPING MACHINE WITH A GRAVEL EXTRACTION NOZZLE
NO311639B1 (en) * 2000-04-05 2001-12-27 Gto Subsea As Method and apparatus for moving rocks and loose masses under water
WO2003027402A1 (en) * 2001-09-24 2003-04-03 Disab Vacuum Technology Ab Apparatus and method for suction and discharge of material
AT5030U3 (en) * 2001-11-09 2002-09-25 Plasser Bahnbaumasch Franz TRACK CONSTRUCTION MACHINE FOR THE INSERTION OF GRAVITY UNDER A TRACK
CN102154959A (en) * 2010-02-11 2011-08-17 襄樊金鹰轨道车辆有限责任公司 Operating mechanism for extracting rail ballast
AT11972U1 (en) * 2010-08-02 2011-08-15 Plasser Bahnbaumasch Franz APPENDIX FOR CLEANING A SHOCK
CN101974890A (en) * 2010-09-28 2011-02-16 济南轨道交通装备有限责任公司 Track bed cleaning device
CN104264620B (en) * 2014-09-13 2016-05-11 芜湖市恒浩机械制造有限公司 A kind of cleaning crushing all-in-one machine vibrating device
CN104532780B (en) * 2014-12-31 2016-05-11 中国铁路总公司 The railway ballast car that removes sand
CN106609504B (en) * 2015-10-27 2018-05-04 中国铁建高新装备股份有限公司 A kind of railway roadbed inhales coal equipment
CN105332357B (en) * 2015-10-27 2017-06-13 中国铁建高新装备股份有限公司 Railway tunnel railway roadbed coal powder collection device
CN105442488B (en) * 2015-11-23 2017-06-09 中国铁建高新装备股份有限公司 A kind of railway tunnel railway roadbed inhales coal car group
CN105714725B (en) * 2016-02-24 2017-08-25 中国铁建高新装备股份有限公司 A kind of track suction-type sewer scavenger pressure-vaccum equipment
CH712375A1 (en) * 2016-04-19 2017-10-31 Hürlimann Bautenschutz Ag Apparatus and method for discharging multicomponent adhesives to a granular mixture.
CN106638431A (en) * 2016-12-01 2017-05-10 张铁民 Arrangement method of cab and operating chamber on equipment
AT519784B1 (en) * 2017-03-17 2019-11-15 Plasser & Theurer Export Von Bahnbaumaschinen Gmbh Machine and method for profiling and distributing gravel of a track
CN106939535A (en) * 2017-03-28 2017-07-11 乌鲁木齐铁路局库尔勒工务段 Cutting is cleared up and unloading rock ballast integrated apparatus
PL244943B1 (en) * 2018-01-12 2024-04-02 Przemyslowy Instytut Masz Rolniczych Central plough of a road power grader, preferably for automotive vehicles
CN110172945B (en) * 2019-05-31 2021-04-23 中国铁建高新装备股份有限公司 Track bed sand removing vehicle
AT523621B1 (en) 2020-03-06 2024-06-15 System 7 Ballast Regulator Gmbh Ploughing device for a track-mounted ballast levelling machine

Family Cites Families (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3957000A (en) * 1969-12-18 1976-05-18 Franz Plasser Bahnbaumaschinen-Industrie-Gesellschaft M.B.H. Ballast treating method
AT370798B (en) * 1980-04-16 1983-05-10 Plasser Bahnbaumasch Franz TRACK CONSTRUCTION MACHINE WITH A BULLET BED ROOM AND PLANER
DE3318756C2 (en) * 1983-05-24 1994-12-08 Schneider Walter Gmbh Co Kg Mobile device for picking up waste, in particular from ballast beds of a track system
IT1181182B (en) * 1984-06-07 1987-09-23 Danieli Off Mecc PROFILING GROUP FOR TRANSFERING MACHINES FOR MASS
AT384446B (en) * 1985-03-14 1987-11-10 Plasser Bahnbaumasch Franz TRACKABLE MACHINE FOR SUCTIONING THE GRAVEL FROM A GRAVEL BED
IT1220110B (en) * 1987-07-22 1990-06-06 Danielli & C Off Mecc Spa SCREENING MACHINE FOR MASSWORKS AND PLATFORMS
AT389334B (en) * 1987-07-23 1989-11-27 Plasser Bahnbaumasch Franz TRACKABLE DEVICE OR PLANNING THE GRAVEL OF A TRACK WITH CROSS SLEEPERS
DE8913287U1 (en) * 1989-09-16 1990-01-11 Hermann Wiebe Grundstuecks- Und Maschinenanlagen Kg, 2800 Bremen Rail vehicle with cleaning device
AT398213B (en) * 1989-10-31 1994-10-25 Plasser Bahnbaumasch Franz MACHINE FOR RECEIVING AND DISTRIBUTING THE BEDGING BALL
DE59000696D1 (en) * 1990-01-10 1993-02-11 Plasser Bahnbaumasch Franz TRACKING MACHINE.
AT400160B (en) * 1990-03-21 1995-10-25 Plasser Bahnbaumasch Franz MACHINE FOR DISTRIBUTING AND PLANNING BEDS
AT395876B (en) * 1990-03-21 1993-03-25 Plasser Bahnbaumasch Franz TRACKABLE MACHINE FOR DISTRIBUTING AND PROFILING THE BEDGING BALL
AT404039B (en) * 1990-03-21 1998-07-27 Plasser Bahnbaumasch Franz MACHINE FOR DISTRIBUTING AND PLANNING THE BED

Also Published As

Publication number Publication date
SK280758B6 (en) 2000-07-11
JP3162568B2 (en) 2001-05-08
FI941017A (en) 1994-09-05
CZ25094A3 (en) 1995-05-17
FI941017A0 (en) 1994-03-03
PL173799B1 (en) 1998-05-29
FI107819B (en) 2001-10-15
JPH06294101A (en) 1994-10-21
RU2087612C1 (en) 1997-08-20
CA2116887C (en) 2004-07-06
EP0613980A2 (en) 1994-09-07
CZ279538B6 (en) 1995-05-17
SK16494A3 (en) 1995-03-08
CN1057361C (en) 2000-10-11
DE59401436D1 (en) 1997-02-13
PL302387A1 (en) 1994-09-05
AU662675B2 (en) 1995-09-07
US5452528A (en) 1995-09-26
EP0613980A3 (en) 1994-11-17
CA2116887A1 (en) 1994-09-05
AU5750894A (en) 1994-09-08
CN1100161A (en) 1995-03-15
ATE147113T1 (en) 1997-01-15

Similar Documents

Publication Publication Date Title
EP0613980B1 (en) Ballast levelling machine
EP0635082B1 (en) Machine for sucking up rail ballast
EP0426004B1 (en) Machine for collecting and redistributing ballast
EP0621371B1 (en) Railway track renewing or laying machine
EP3418450A1 (en) Tunnel cleaning device
EP1162312B1 (en) Machine for renewing a railway track
EP0633355B1 (en) Track sweeping machine
EP1253246A2 (en) Railway ballast cleaning machine
EP1253247B1 (en) Railway ballast cleaning machine
EP0603149B1 (en) Vacuum machine
EP2703562A2 (en) Tram rail cleaning machine
EP0824164B1 (en) Track maintenance machine for removing the ballast
EP0824163B1 (en) Track maintenance machine for removing the ballast
EP0771909B1 (en) Machine for dismantling old and installing new railway tracks
EP0416135B1 (en) Track-mobile machine for distributing and profiling the bedding ballast of a railway track
DE4108673A1 (en) Process for continuous cleaning of railway ballast - involves using hood equipped with compressed air and high pressure water jets, attached to constantly moving vehicle
DE4341240C2 (en) Suction machine for suctioning ballast from a ballast bed
DE9213041U1 (en) Gravel plow
EP0665331B1 (en) Ballast tamping machine for railways
EP1195468A2 (en) Machine for renewing a railway track
CH652428A5 (en) GRADLE PLANING MACHINE DRIVABLE ON THE TRACK.
EP0663472B1 (en) Machine for cleaning the ballast of a railway track
EP0761880B1 (en) Machine for working the ballast bed of a track
DE19622236A1 (en) Rail vehicle for cleaning surface of rail track
EP1130163A2 (en) Tamping machine with ballast suction pipe

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): AT CH DE FR GB IT LI NL SE

PUAL Search report despatched

Free format text: ORIGINAL CODE: 0009013

AK Designated contracting states

Kind code of ref document: A3

Designated state(s): AT CH DE FR GB IT LI NL SE

17P Request for examination filed

Effective date: 19940922

GRAG Despatch of communication of intention to grant

Free format text: ORIGINAL CODE: EPIDOS AGRA

GRAH Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOS IGRA

17Q First examination report despatched

Effective date: 19960624

GRAH Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOS IGRA

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT CH DE FR GB IT LI NL SE

REF Corresponds to:

Ref document number: 147113

Country of ref document: AT

Date of ref document: 19970115

Kind code of ref document: T

REG Reference to a national code

Ref country code: CH

Ref legal event code: NV

Representative=s name: DIPL.-ING. ETH H. R. WERFFELI PATENTANWALT

Ref country code: CH

Ref legal event code: EP

ITF It: translation for a ep patent filed
GBT Gb: translation of ep patent filed (gb section 77(6)(a)/1977)

Effective date: 19970102

REF Corresponds to:

Ref document number: 59401436

Country of ref document: DE

Date of ref document: 19970213

ET Fr: translation filed
PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed
REG Reference to a national code

Ref country code: GB

Ref legal event code: IF02

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20080202

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: CH

Payment date: 20120120

Year of fee payment: 19

Ref country code: FR

Payment date: 20120201

Year of fee payment: 19

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: IT

Payment date: 20120224

Year of fee payment: 19

Ref country code: SE

Payment date: 20120120

Year of fee payment: 19

Ref country code: GB

Payment date: 20120103

Year of fee payment: 19

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20120425

Year of fee payment: 19

Ref country code: NL

Payment date: 20120120

Year of fee payment: 19

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: AT

Payment date: 20120111

Year of fee payment: 19

REG Reference to a national code

Ref country code: NL

Ref legal event code: V1

Effective date: 20130901

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

REG Reference to a national code

Ref country code: SE

Ref legal event code: EUG

REG Reference to a national code

Ref country code: AT

Ref legal event code: MM01

Ref document number: 147113

Country of ref document: AT

Kind code of ref document: T

Effective date: 20130228

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20130202

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130901

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130228

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130228

Ref country code: SE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130203

Ref country code: AT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130228

REG Reference to a national code

Ref country code: FR

Ref legal event code: ST

Effective date: 20131031

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 59401436

Country of ref document: DE

Effective date: 20130903

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130202

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130903

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130202

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20130228