EP0384112B1 - Grue à tour, de préférence grue tournant au haut de la tour - Google Patents
Grue à tour, de préférence grue tournant au haut de la tour Download PDFInfo
- Publication number
- EP0384112B1 EP0384112B1 EP90100643A EP90100643A EP0384112B1 EP 0384112 B1 EP0384112 B1 EP 0384112B1 EP 90100643 A EP90100643 A EP 90100643A EP 90100643 A EP90100643 A EP 90100643A EP 0384112 B1 EP0384112 B1 EP 0384112B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- tower crane
- trolley
- boom
- slewing tower
- assembly
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 239000000969 carrier Substances 0.000 claims description 3
- 230000015572 biosynthetic process Effects 0.000 claims description 2
- 230000005484 gravity Effects 0.000 claims description 2
- 239000002184 metal Substances 0.000 claims 1
- 230000008878 coupling Effects 0.000 description 6
- 238000010168 coupling process Methods 0.000 description 6
- 238000005859 coupling reaction Methods 0.000 description 6
- 230000000712 assembly Effects 0.000 description 3
- 238000000429 assembly Methods 0.000 description 3
- 235000004443 Ricinus communis Nutrition 0.000 description 2
- 240000000528 Ricinus communis Species 0.000 description 2
- 238000005452 bending Methods 0.000 description 2
- 238000010616 electrical installation Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 239000007787 solid Substances 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 1
- 239000002131 composite material Substances 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/18—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
- B66C23/26—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail
Definitions
- the invention relates to a tower crane according to the preamble of claim 1.
- a top-rotating tower crane of this type which meets the requirements of a quick and easy and space-saving assembly and disassembly and a disassembly into easy-to-transport assembly and transport units, is known from DE-PS 35 10 116.
- an essential assembly and transport unit consists of a rail piece connected to the rotating platform, on which the trolley and a carriage provided with the fixed point of the lifting rope and the deflection roller for the trolley traveling rope can be moved so that these together with the rotating platform, form an assembly unit that can be transported by road.
- This way of combining the turntable with the counter jib, the guying jib, the trolley and the head-end station into one assembly and transport unit has proven very successful with smaller cranes.
- the object of the invention is therefore to provide a tower crane according to the preamble of claim 1, which can be disassembled, quickly and even in confined spaces, street-appropriate assembly and transport units if it is of a larger design.
- the supporting structure or platform carrying the machine unit can thus only be combined with the trolley, the sheared load hook and the head station to form an assembly unit that can be transported by road.
- This type of combination enables the formation of a transport unit that does not exceed the weights and dimensions permitted for road transport and assembly.
- an assembly unit is created which is already stranded and installed in the factory, so that after or during assembly there is no need for complex and cumbersome stranding and installation work.
- the lifting and trolley ropes are completely reeved in the factory, all limit switches and safety devices, namely the Lift limit switches, the winding limit switch, the trolley travel limit switches and the overload protection devices are preset in the factory.
- the assembly and transport unit according to the invention can also additionally contain all electrical installations in preassembled form, so that the assembly is also considerably simplified in this respect.
- the basic supporting frame which can be connected to the upper end of the tower and which is connected to the rotating platform by means of a rotating mechanism provided with the rotating platform, forms an assembly unit with the crane driver's cab hinged to the rotating platform. Since the crane operator's cab is located to the side of the turntable during crane operation, it can be folded in front of the turntable to form a transport unit, whereby the folded-in transport position and the unfolded operating position can be locked by means of appropriate safety bolts.
- the turntable expediently has, on its side facing the counter jib, upstanding supporting supports, with the upper regions of which the upper straps of the support structure carrying the winches and the lower straps of the trolley boom can be connected.
- the bearing points of the supporting structure and the trolley bracket only need to be hooked into the corresponding receptacles, so that there is firstly an easy-to-carry out pre-assembly and the further bolting or securing can then be carried out.
- the towering supports are expediently stiffened by V-shaped supports.
- the lower chords of the support structure carrying the winches can be bolted to the base frame of the rotating platform.
- the support structure for the winches expediently exists and the machine unit from a triangular beam assembly with a lower bar of the base beam that can be bolted to the rotating platform.
- the counter jib can consist of a box section girder, which is to be connected to the base frame of the rotating platform directly or via the lower cross member to the base girder frame of the support structure carrying the winches.
- the counter jib can also be connectable to the rear end of the supporting structure that carries the winches and the machine unit.
- the counter jib bracing is expediently articulated on the counter jib in the area of the rear ballasting. In this way, the bending moments acting on the counter jib can be kept small.
- the bracing of the counter jib consists of a counter jib guy rod, it is provided in a further embodiment of the invention that it can be locked in its mounting position by a mounting bolt.
- the counter jib rod can then be raised and bolted in its assembly position with the counter jib still lying on the floor, so that difficult assembly work can be omitted with the counter jib raised in its assembly position.
- the counter jib tensioning rod can expediently be bolted to the machine cantilevered tip of the triangular beam assembly.
- the guy bracket which is articulated at the boom articulation point, has an articulated rear holding rod and the guy bracket with a Swing-out support is provided, which fixes the mounting position of the handrail.
- This configuration also makes it possible to set and fix the angle corresponding to the mounting position between the guy stand and the rear support rod on the ground.
- the guy stand is also expediently connected to the upper boom of the trolley jib after erection and is thus held in the appropriate mounting position.
- the guy stand is raised, the boom support linkage is unfolded and held in the correct assembly or functional position.
- the trolleys of the trolley are mounted on trolley carriers which are pivotally mounted on the trolley frame and can be bolted to the trolley frame in their pivoted-in driving position. In this way, the trolley can be easily moved into its driving position on the running rail formed by the lower straps of the trolley boom. A laborious postponement, which will often not be possible, is no longer necessary.
- the head station consists of a sleeve-like part with locking bolts which can be pushed onto a holding part connected to the trolley frame to form the assembly and transport unit and can be inserted into a pocket-shaped receiving part at the outer end of the trolley arm and can be locked on this.
- One side of a catwalk is expediently connected to the triangular structure and the other side of the catwalk is connected to the counter jib. Since the catwalks would widen the construction to an extent permissible for road transport, the triangular structure can be combined with one in this embodiment Place the catwalk and the counter jib with the other side of the catwalk overlapping one another on a transport vehicle in such a way that the permissible width for road transport is maintained.
- the catwalk located in the area of the revolving platform and leading to the crane driver's cab is expediently foldable onto the catwalk part of the triangular structure.
- the counterweight plates are provided with lateral locking bolts which are supported on inclined edges by holding plates connected to the counterjib, so that the counterweight plates are self-tensioning.
- the tower 1 which basically consists of a telescopic tower, is supported on a foundation cross 2 or an undercarriage known as such. With the upper end of the tower 1, the base support frame 3 is connected, to which the rotating platform 5 is connected via the slewing ring 4.
- the rotating platform 5 consists of a lower support frame 6, which is provided at its rear end facing the counter jib with two upstanding supports 7, 8 which are stiffened with respect to the frame 6 by oblique beams 9, 10.
- the supports 7, 8 are welded at their upper end to coupling plates 11, 12 to which the rear lower end of the trolley arm and the upper flange 13 of the supporting structure for the lifting and trolley winch winches, which consist of a triangular support structure, are coupled.
- the support structure for the trolley winch 15 and the hoist winch 16 consists of the two supports 17, 18 of the upper chord 13 and the two supports of the lower chord 19, which are welded to the support tube 20 with their rear ends.
- the front ends of the upper and lower straps 13, 19 of the triangular composite are welded to a base frame 21.
- the base frame 21 carries in the area of its lower cross member connecting plates 25 which are connected by bolts 26 to the base frame 6 of the rotating platform.
- the driver's cab 33 is articulated to the left front corner of the base frame 6 of the rotating platform according to FIG.
- the driver's cab 33 is bolted to the base frame 6 in its swiveled-out position shown in FIG. 3 with further securing bolts.
- the driver's cab 33 In the transport position, the driver's cab 33 is pivoted in front of the rotating platform in the manner indicated by dash-dotted lines 33 'and bolted to it in this position by means of securing bolts.
- the boom is articulated to the coupling pieces 11, 12 of the supports 7, 8 and the guy stand 36 is articulated through the articulation bolts 35.
- the guy stand 36 can be supported at the fixed point 37 of the upper chord 38 of the trolley boom 39 for mounting so that it does not tip forward before the counter jib guy rod 47 is tensioned.
- the rear support rod 40 and the front boom guy rod 41 are articulated.
- the guy bracket 36 is provided in its upper area with a pivotable and in its pivoted position lockable auxiliary support 43 which fixes the rear support rod 40 in the pivoted position shown during assembly.
- the rear support rod 40 is articulated in the joint 46 to the support tube 20.
- a further counter jib tension rod 47 is articulated, which with the counter jib 30 in the area approximately through the center of gravity of the counterweight 48 extending line is articulated.
- the articulated connection located in the area of the counterweight 48 consists of a tab 51 which is articulated to the counter jib by the articulation pin 50 and which can be coupled to the bearing plates by an auxiliary pin 52 for assembly purposes in such a way that the counter jib tensioning rod 47 is held in its assembly position, so that the coupling with the articulated connection of the support tube 20 after lifting the counter jib 30 can be effected without cumbersome manipulations.
- the counterweight plates 56 are held on the rear crossbeams 55 of the counterjib 30 in the manner shown in FIG. 11 on both sides of the counterjib.
- the cross members 55 are provided with sheets with oblique sliding planes 57, on which support bolts 58 of the counterweight plates 56 are supported in such a way that they are clamped together under their weight.
- the trolley 100 consists of a frame 60 in which the deflecting rope pulleys 61, 62 for the lifting rope carrying the crane hook 63 and the bottle 64 are guided in the manner shown in FIG.
- Lateral supports 65 are articulated to the frame 60 of the trolley and carry the castors 66 at their upper ends.
- the carriers 65 can be pivoted from a pivoted-out position into a pivoted-in position indicated by dashed lines in FIG. 6 and bolted to the frame 60 in this position. In this swiveled-in position, the castors 66 are located on the lower chords 68 of the boom 39 forming the travel rails.
- the frame 60 of the trolley 100 is connected to the base support 21 of the support structure for the winches via corresponding holding plates 70, 71.
- the connection consists of holding bolts reaching into elongated holes 73, so that the undercarriage frame 60 is connected to the supporting structure 13,19 has a certain pivotability.
- the front end of the chassis frame 60 is connected to a mandrel-like holding device 75, onto which the sleeve-shaped head station 76 is pushed in the assembly and transport position.
- This sleeve-shaped head station 76 is provided with the fixed point 77 for the hoisting rope 78 and a lateral deflection roller 79 for the trolley rope 80.
- the head station 76 has been moved forward by the trolley 100 until it snaps into its seat at the front end of the boom, which consists of a pocket-shaped receptacle 82 and a spring-loaded locking lever 83.
- the catwalk part 86 is connected to the lower area of the support structure 13, 19, 21, which consists of a triangular beam assembly.
- the opposite catwalk 85 is connected to the counter jib 30.
- the catwalk part 88 which bridges the rotating platform, is articulated to the catwalk 85 by the articulated connection 87 and can thus be folded onto the catwalk 85 of the counter-jib for transport purposes. Further details of the crane, in particular the individual articulated bolt connections, are not described in more detail because these can be easily understood by the person skilled in the art from the illustration of the drawing.
- the ropes leading to the trolley winch 15 run over the deflection pulleys 90.91.
- the hoisting rope 78 is guided over the hoisting rope deflection roller 92 in the rear area of the counter jib so that there is sufficient distance to wind the hoisting rope drum evenly over its width.
- a transport and assembly unit forms the turntable with a slewing ring support and slewing ring, pantograph, turntable frame with connections for the machine unit and boom, slewing gear and cab.
- the cab is pivotally connected to the revolving platform for road transport.
- the cantilever head station with hoist rope fixed point and trolley rope guide pulley, the trolley with load hook, the hoist and trolley chassis with all safety devices and the switchgear are combined to form an assembly and transport unit, in a fully installed, adjusted and stranded form.
- a holding frame can be provided or the trolley chassis frame can be used.
- the support structure for the machine unit is only connected to a pedestal on one side.
- the counter jib essentially consists of a solid wall section beam, which is articulated at the front near the rotating platform to the support structure for the machine unit.
- the counter jib like the jib, is only simply braced, which means that only one guy rod is provided at a time.
- the bracing of the counter jib is directed exactly towards the heavy weight of the counterweight arrangement, so that no additional bending moments arise in the solid wall profile beam due to the counterweight arrangement and the articulation of the guy rod. This allows a favorable dimensioning.
- the counterweights are evenly arranged on both sides of the longitudinal beam of the counterjib and are self-tensioning due to their own weight.
- the catwalk is attached to the side in the front area of the counter jib.
- the turntable, machine unit and counter jib can be loaded offset on one vehicle for transport, so that both in the assembled state the permissible transport width is exceeded in accordance with the crane size, but the permissible transport mass can still be maintained during road transport.
- the electrical installation is hidden at the separation points of the tower and rotating platform on the one hand and the rotating platform and machine unit on the other.
- the jib and counter jib are therefore without any installation.
- the revolving platform is first placed on the tower with the cab swung out during operation and connected to it.
- the supporting structure with the machine unit, the trolley, the load hook and the head station is then hung in a quick-release bearing on the top of the rotating platform and bolted in a tab connection at the bottom. The connection points can be reached safely from the rotating platform.
- the hoist rope is then unwound somewhat and, after the cable reel bearing has been opened, is inserted into the deflection roller 92 at the rear end of the counter jib 30. Since the assemblies are bolted together to form transport and assembly units, only one assembly stroke is required.
- the boom 39 is then assembled in a known manner from its individual sections with the associated guy rods.
- the handrail 40 is opened with the mobile crane and held in its assembly position by means of the pivotable and lockable support 43. This happens while the boom guy stand 36 is still on the boom link. Then the guy stand and the boom guy linkage are erected and brought into the functional position. Here too, the correct mounting position is determined by the support 37.
- the boom and its holding device are lifted to the rotating platform with the help of a mobile crane and hooked into a quick-release connection here. Now the boom is inclined so far that the trolley roller carrier 65 with its rollers 66 over the lower belts 68, which form the running rails, pivoted and bolted in their operating position to the frame of the trolley or can be locked on this.
- the boom is raised again to about the horizontal.
- the bolts that connect the ready-wired assemblies, the trolley, the load hook and the jib head station to the machine unit during transport and assembly can then be removed.
- the pin bearings are designed as elongated holes, so that no precise boom position must be maintained during this assembly process and damage is avoided when lifting the boom.
- the load unit which consists of trolley, load hook and jib head station, is manually pushed out over the rotating platform so that the jib can be lowered again and the load unit can roll to the jib tip on the resulting incline.
- the boom head station is then automatically locked with the boom tip in a manner that is already known per se from DE-PS 35 10 116.
- the head station is mounted with its hollow body carrier on a carrier arranged at the front of the trolley and is held in this position by the hoisting cable.
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Transportation (AREA)
- Mechanical Engineering (AREA)
- Jib Cranes (AREA)
- Leg Units, Guards, And Driving Tracks Of Cranes (AREA)
Claims (18)
- Grue sur tour avec des treuils (15, 16) pour un câble de levage (78) et un câble de chariot (80) et avec un chevalet tendeur supérieur (36) auquel sont fixés les câbles ou tringleries tendeurs (40, 41) pour une flèche de chariot (39) et une contre-flèche (30), une construction de support supportant les treuils (15, 16) pour le câble de levage (78) et le câble de chariot (80), un chariot (100), un crochet de levage (63) et une station de tête (76) avec un point fixe (77) du câble de levage (78) et du galet de renvoi (79) pour le câble de chariot (80) constituant des parties d'une unité de montage et de transport, caractérisée en ce que l'unité de montage et de transport est constituée de la construction de support (17, 18, 19, 21) pour les treuils (15, 16) à laquelle est fixé par brides le côté arrière du châssis (60) du chariot (100) ainsi que de la station de tête (76) qui est pourvue d'un dispositif de retenue (75) prévue au côté avant du châssis (60) du chariot (100).
- Grue sur tour selon la revendication 1, caractérisée en ce que dans une grue sur tour tournant en haut, le châssis de support de base (3) pouvant être relié à l'extrémité supérieure de la tour et qui est relié par une couronne d'orientation (4) pourvue d'un mécanisme tournant au plateau tournant (5), constitue avec la cabine de conduit (33) articulée au plateau tournant (5) une unité de montage.
- Grue sur tour selon la revendication 1 ou 2, caractérisée en ce que le plateau tournant (5) présente à son côté orienté vers la contre-flèche (30) des montants de support (7, 8) latéraux debout, avec les zones supérieures (11, 12) desquels les brins supérieurs (13) de la construction de support supportant les treuils (15, 16) et les brins inférieurs (68) de la flèche de chariot (39) peuvent être reliés directement ou indirectement.
- Grue sur tour selon l'une des revendications 1 à 3, caractérisée en ce que les brins inférieurs (19) de la construction de support (17, 18, 19, 21) supportant les treuils (15, 16) peuvent être boulonnés au châssis de base (6) du plateau tournant (5).
- Grue sur tour selon l'une des revendications 1 à 4, caractérisée en ce que la construction de support (16, 17, 18, 19, 21) pour les treuils (15, 16) est constituée d'un assemblage de supports triangulaires avec un longeron transversal inférieur pouvant être relié par des boulons au plateau tournant (5) du châssis de base (21).
- Grue sur tour selon l'une des revendications 1 à 5, caractérisée en ce que la contre-flèche (30) est constituée d'un support en profil de caisson qui peut être assemblé par des boulons au châssis de base (6) du plateau tournant (5) directement ou par le longeron transversal inférieur du châssis de base (21) de la construction de support (17, 18, 19, 21) supportant les treuils (15, 16).
- Grue sur tour selon l'une des revendications 1 à 6, caractérisée en ce que la contre-flèche (30) peut être assemblée par des boulons avec l'extrémité arrière de la construction de support (17, 18, 19, 21) supportant les treuils (15, 16).
- Grue sur tour selon l'une des revendications 1 à 7, caractérisée en ce que la barre de tension de contre-flèche (47) est articulée à la contre-flèche (30) au voisinage du centre de gravité du ballastage arrière (48).
- Grue sur tour selon l'une des revendications 1 à 8, caractérisée en ce que la barre de tension de contre-flèche (47) peut être arrêtée par un boulon de montage (50) dans sa position de montage.
- Grue sur tour selon l'une des revendications 1 à 6 ou 8 ou 9, caractérisée en ce qu'une barre de tension de contre-flèche (47) peut être reliée par des boulons à la pointe en saillie vers l'arrière de l'assemblage de supports triangulaires (13, 21).
- Grue sur tour selon l'une des revendications 1 à 10, caractérisée en ce qu'il est articulé au chevalet tendeur (36) relié de façon articulée au point d'articulation de flèche de façon articulée une tige de retenue arrière (40) qui est fixée par un support pivotant (43) disposé de façon articulée au chevalet tendeur (36) dans la bonne position angulaire de montage de celle-ci.
- Grue sur tour selon l'une des revendications 1 à 11, caractérisée en ce que le chevalet tendeur (36) peut prendre appui sur le brin supérieur ou les brins supérieurs (38) du chariot (39).
- Grue sur tour selon l'une des revendications 1 à 12, caractérisée en ce que les rouleaux de déplacement (66) du chariot (100) sont logés dans des supports de rouleaux de déplacement (65) qui sont logés de façon pivotante au châssis de chariot (60) et qui, dans leur position pivoté vers l'intérieur, peuvent être reliés par des boulons à celui-ci.
- Grue sur tour selon l'une des revendications 1 à 13, caractérisée en ce que la station de tête (76) est constituée d'une partie en forme de manchon avec des boulons d'arrêt, qui peut être poussée sur un dispositif de retenue (75) relié au châssis de chariot (60) pour former l'unité de montage et de transport et que lors du montage, une pièce de réception en forme de poche (82) peut être poussée dans l'extrémité externe de la flèche de chariot 39 et peut être arrêtée sur celle-ci.
- Grue sur tour selon l'une des revendications 1 à 6 ou 8 à 14, caractérisée en ce que sont reliés à l'assemblage triangulaire (13, 19, 21) pour l'unité de machines un côté d'une passerelle (85 ou 86) et à la contre-flèche (30) l'autre côté de la passerelle (86 ou 85).
- Grue sur tour selon la revendication 15, caractérisée en ce que la passerelle (88) se trouvant au voisinage du plateau tournant (5) et menant vers la cabine de conduite (33) peut être rabattue sur la partie de passerelle (85) de l'assemblage triangulaire ou de la contre-flèche.
- Grue sur tour selon l'une des revendications 1 à 16, caractérisée en ce que la cabine de conduite (33) est reliée de façon pivotante à une zone angulaire du châssis porteur (6) du plateau tournant (5) et peut être reliée par des boulons à celui-ci dans une position de transport pivotée vers l'intérieur et une position de fonctionnement pivotée vers l'extérieur.
- Grue sur tour selon l'une des revendications 1 à 17, caractérisée en ce que les plaques de contrepoids (56) sont pourvues de boulons de retenue latéraux (58) qui prennent appui sur les arêtes inclinées de tôles de retenue d'un support transversal (55) se trouvant à l'extrémité arrière de la contre-flèche.
Applications Claiming Priority (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE3905323 | 1989-02-21 | ||
DE3905323 | 1989-02-21 | ||
DE3911868 | 1989-04-11 | ||
DE3911868A DE3911868A1 (de) | 1989-02-21 | 1989-04-11 | Turmdrehkran, vorzugsweise oben drehender turmdrehkran |
Publications (3)
Publication Number | Publication Date |
---|---|
EP0384112A2 EP0384112A2 (fr) | 1990-08-29 |
EP0384112A3 EP0384112A3 (fr) | 1991-10-23 |
EP0384112B1 true EP0384112B1 (fr) | 1994-11-30 |
Family
ID=25878028
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP90100643A Expired - Lifetime EP0384112B1 (fr) | 1989-02-21 | 1990-01-12 | Grue à tour, de préférence grue tournant au haut de la tour |
Country Status (3)
Country | Link |
---|---|
EP (1) | EP0384112B1 (fr) |
DE (2) | DE3911868A1 (fr) |
ES (1) | ES2064494T3 (fr) |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4344733A1 (de) * | 1993-12-27 | 1995-06-29 | Liebherr Werk Biberach Gmbh | Turmdrehkran |
DE102014225336A1 (de) | 2014-12-09 | 2016-06-09 | Wobben Properties Gmbh | Turmdrehkran zum Errichten einer Windenergieanlage, sowie Verfahren zum Errichten des Turmdrehkrans |
CN104809948A (zh) * | 2015-02-02 | 2015-07-29 | 青岛港湾职业技术学院 | 一种门座式起重机模型 |
CN105329787B (zh) * | 2015-11-10 | 2017-05-03 | 王亚 | 一种随升或内爬式自卸塔臂 |
CN107140558B (zh) * | 2017-06-22 | 2018-10-19 | 广东精铟海洋工程股份有限公司 | 一种高强度的海上吊臂及使用其的起重机 |
DE202017107301U1 (de) * | 2017-09-01 | 2018-12-07 | Liebherr-Werk Biberach Gmbh | Turmdrehkran |
CN111847309B (zh) * | 2020-07-28 | 2021-09-28 | 上海振华重工(集团)股份有限公司 | 集装箱起重机上大车行走机构的整体拆卸安装装置及方法 |
FR3114581B1 (fr) * | 2020-09-25 | 2022-12-09 | Manitowoc Crane Group France | Elément de grue formant pivot pour grue à montage par éléments |
WO2022095056A1 (fr) * | 2020-11-07 | 2022-05-12 | 山东圣得宝儿童用品股份有限公司 | Grue à tour à neige pour le divertissement des enfants |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3250400A (en) * | 1964-10-26 | 1966-05-10 | Robert F Bennett | Rotary crane with split race bull wheel |
FR2193772B1 (fr) * | 1972-07-26 | 1976-08-13 | Ts Kon Truktors | |
DE3510116A1 (de) * | 1984-04-25 | 1985-10-31 | Liebherr-Werk Biberach Gmbh, 7950 Biberach | Oben drehender turmkran |
-
1989
- 1989-04-11 DE DE3911868A patent/DE3911868A1/de active Granted
-
1990
- 1990-01-12 EP EP90100643A patent/EP0384112B1/fr not_active Expired - Lifetime
- 1990-01-12 DE DE59007786T patent/DE59007786D1/de not_active Expired - Fee Related
- 1990-01-12 ES ES90100643T patent/ES2064494T3/es not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
DE59007786D1 (de) | 1995-01-12 |
EP0384112A3 (fr) | 1991-10-23 |
DE3911868C2 (fr) | 1991-06-13 |
EP0384112A2 (fr) | 1990-08-29 |
ES2064494T3 (es) | 1995-02-01 |
DE3911868A1 (de) | 1990-09-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP0156304B1 (fr) | Dispositif pour l'inspection des parties inférieures des ponts | |
WO2006058751A2 (fr) | Grue automotrice | |
DE2556882A1 (de) | System (anordnung) und verfahren zum selbsttaetigen entstauen und verstauen eines kranauslegers | |
AT523097B1 (de) | Fahrzeugkran mit einem teleskopausleger und fahrzeugkransystem sowie verfahren zur montage einer abspannvorrichtung an den teleskopausleger eines fahrzeugkrans | |
EP2900587B1 (fr) | Grue pivotante sur pylône | |
EP0370314A2 (fr) | Installation d'antenne mobile avec un mât télescopique | |
EP0384112B1 (fr) | Grue à tour, de préférence grue tournant au haut de la tour | |
EP2848574B1 (fr) | Petite grue démontable et déplaçable pour utilisation sur les chantiers | |
DE2133111A1 (de) | Freistehender Kran | |
EP0433283B1 (fr) | Chargeur ou dechargeur de navire | |
DE29723710U1 (de) | Hebevorrichtung | |
EP1508472B1 (fr) | Véhicule avec un écran déployable | |
DE3337163C2 (de) | Aufhängung einer Führerkabine an einem Turmdrehkran | |
DE3401094C2 (de) | Kran mit teleskopierbarem Turm | |
DE102009030741B4 (de) | Vorrichtung und Verfahren zur Montage und/oder Demontage eines Kranauslegers und Kran mit einer derartigen Vorrichtung | |
EP3943438A1 (fr) | Grue mobile pourvu de châssis divisible | |
DE2319560A1 (de) | Zusammenklappbarer, von einem fahrzeug transportierbarer kran und verfahren zur schnellmontage des krans in seine arbeitsstellung | |
DE8205723U1 (de) | Drehkran | |
DE1175838B (de) | Fahrbarer und umklappbarer Bauaufzug | |
DE3715056C1 (en) | Ship loader or unloader | |
DE29916410U1 (de) | Gelenkig miteinander verbundene, im Querschnitt dreieckige Gitterträger | |
DE9312431U1 (de) | Fahrbare Arbeitsbühne | |
DE2161258B1 (de) | Verfahren zum zusammenklappen eines krans in seine transportlage sowie kran, insbesondere baukran | |
DE202021103604U1 (de) | Transportabler Portalkran | |
DE1952447A1 (de) | Turmdrehkran |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A2 Designated state(s): DE ES FR IT |
|
PUAL | Search report despatched |
Free format text: ORIGINAL CODE: 0009013 |
|
AK | Designated contracting states |
Kind code of ref document: A3 Designated state(s): DE ES FR IT |
|
17P | Request for examination filed |
Effective date: 19910925 |
|
17Q | First examination report despatched |
Effective date: 19921014 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): DE ES FR IT |
|
REF | Corresponds to: |
Ref document number: 59007786 Country of ref document: DE Date of ref document: 19950112 |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FG2A Ref document number: 2064494 Country of ref document: ES Kind code of ref document: T3 |
|
ET | Fr: translation filed | ||
ITF | It: translation for a ep patent filed | ||
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed | ||
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: ES Payment date: 20060113 Year of fee payment: 17 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 20060120 Year of fee payment: 17 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20060123 Year of fee payment: 17 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: IT Payment date: 20060131 Year of fee payment: 17 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20070801 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST Effective date: 20070930 |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FD2A Effective date: 20070113 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20070131 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20070113 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20070112 |