EP0243789A2 - Procédé de fabrication de lingotières pour les machines de coulée continue - Google Patents
Procédé de fabrication de lingotières pour les machines de coulée continue Download PDFInfo
- Publication number
- EP0243789A2 EP0243789A2 EP87105533A EP87105533A EP0243789A2 EP 0243789 A2 EP0243789 A2 EP 0243789A2 EP 87105533 A EP87105533 A EP 87105533A EP 87105533 A EP87105533 A EP 87105533A EP 0243789 A2 EP0243789 A2 EP 0243789A2
- Authority
- EP
- European Patent Office
- Prior art keywords
- mandrel
- pipe section
- die
- tube
- following
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B22—CASTING; POWDER METALLURGY
- B22D—CASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
- B22D11/00—Continuous casting of metals, i.e. casting in indefinite lengths
- B22D11/04—Continuous casting of metals, i.e. casting in indefinite lengths into open-ended moulds
- B22D11/057—Manufacturing or calibrating the moulds
Definitions
- the present invention relates to a process for the production of continuous molds for continuous casting machines, in which a pipe piece made of copper or a copper alloy is molded onto a mandrel having the inside gauge and / or shape of the mold to be produced by external force and after the molding process Mandrel is removed from the mold tube.
- the invention is therefore based on the object of making the production of continuous molds of any dimensions and cross-sectional shapes more rational and therefore more cost-effective, and at the same time increasing the quality of the end product, regardless of the pipe cross-section, the wall thickness and the degrees of hardness of the mold materials used .
- these process steps permit rational production with improved quality of the end product. This applies in particular to the manufacture of mold tubes with larger spatial dimensions adapted to the requirements and from harder mold materials.
- the production process can be controlled semi-automatically or fully automatically according to the order, making the process independent of manual handling errors.
- the method proposed according to the invention allows an optional order processing within a given delivery program, whereby significant interruptions due to changeovers are avoided.
- a prerequisite for the proper execution of the production program is the primary material store, which contains the number of primary tubes necessary for processing, possibly of different dimensions.
- these front pipes can be straight, but also pre-curved pipe sections.
- Drawn pipe lengths are advantageously used as the starting material, from which the pipe sections are cut to length, but rolled or cast pipe lengths are also used, which are used as basic materials for the pipe sections to be machined according to the invention.
- an abutment for the mandrel to be inserted is first provided at one end of the pipe section.
- Such an abutment can be a mandrel passed through the end of the pipe section, but one end of the pipe section can also be pointed accordingly in order to prevent the mandrel from being pushed or pulled through the pipe section when it is inserted.
- it has proven to be particularly advantageous to couple one end of the pipe section for this purpose. Hitching here is understood to mean flanging the edges of the end of the pipe section inwards.
- the forming of the tube piece to the mold tube, and in particular the cold forming to achieve the required mold qualities, such as dimensional accuracy, surface quality of the inner surfaces forming the mold cavity, hardness of the tube walls, by means of a mandrel having the inside dimensions of the mold tube .
- the mandrel will be pressed into the pipe section, this also applies if e.g. Bent mold tubes are to be produced and straight tube pieces are to be removed from the primary material store, into which a curved mandrel is to be inserted.
- a matrix is decisive for the invention, by means of which the thickened piece of pipe (mandrel-pipe-stucco combination) is ironed onto the mandrel, that is to say it is molded onto a mechanical surface.
- the flared pipe section can be pushed or pulled through the die, but in a further development of the invention one can also proceed in such a way that the die is moved over the fixed, flared pipe section for the purpose of pipe forming.
- the tight pressing of the inner surface of the pipe piece onto the mandrel enables the production of straight or curved, conical or partially conical mold pipes, which are characterized by a particularly high degree of dimensional accuracy, a high surface quality and a hardness sufficient for use in steel continuous casting, the method according to the invention being used ensures constant mold quality in a cost-effective way of working.
- the die is continuously adjusted to the respective working position for the mandrel or tool surface as a function of the radius of curvature of the mandrel or the tool surfaces during the relative movement between the tube piece and the die during the shaping process, this measure leads despite higher forming forces, e.g. when forming a flared piece of pipe onto the calibration mandrel, to a uniform material decrease in the process sequence and thus to a uniform wall thickness that is free of internal mechanical stresses. These properties which can be achieved by the invention lead to a substantial extension of the service life.
- the die is regulated continuously in the normal position to the mandrel or die surface as a function of the radius of curvature of the mandrel or the tool surfaces during the relative movement between the tube piece and the die during the shaping process.
- the continuous adjustment of the die into the respective working position enables the die to be set in a targeted manner during the forming process, for example to compensate for wall thicknesses of non-uniform pipe pieces that are supplied as primary material to the forming device. Any angle settings, for example to the mandrel center axis, can be achieved.
- Known devices DE-PS 21 54 226) and methods (EP-PS 0 060 820) do not offer these possibilities.
- the automatic infeed of the die in the direction of the curved mandrel can lead to uneven material removal and to the uneven wall of the mold tube.
- the pulling of the pipe section over an externally adjacent curved tool surface does not lead here either; in particular, the required dimensional accuracy of the inner surfaces of the mold tube cannot be achieved with this.
- a particularly advantageous embodiment of the invention is obtained if, as already indicated, a curved mandrel having the inside dimensions and / or shape of the mold tube to be produced is introduced into the tube piece and the flared tube piece is molded onto the mandrel by a pivotably mounted die.
- the fact that at any point in time of the relative movement between the thickened pipe section and the die is normal to the radius of curvature of the mandrel ensures a uniform deformation of the pipe wall. Because the forming process when "ironing" the pipe onto the mandrel is actively influenced at all times.
- the relative movement between the pipe section, in particular the thickened pipe section, and the die is essential for the forming process according to the invention. Therefore, it is basically irrelevant for the forming process whether the pipe section is pressed through or pulled through the die. If there is a mandrel in the pipe section which has the inside gauge and / or shape of the mold to improve the dimensional accuracy of the shaping interior, then it can often be expedient to guide the die in the axial direction of the mandrel over the flared pipe section.
- the raw material used e.g. Drawn pipes, which are then cut to pieces, generally have a certain tolerance with regard to the eccentricity of the wall thickness.
- the die itself is guided, for example, in a so-called die holder.
- the continuous adjustment to the normal position to the mandrel surface takes place by the force acting on the die holder, which is rotatably or pivotably mounted and holds the die in a stable position relative to the die holder.
- the die holder which is rotatably or pivotably mounted and holds the die in a stable position relative to the die holder.
- adjust the die holder hydraulically into the respective working position, for example in the normal position to the radius of curvature of the mandrel or the tool surfaces.
- the setting movement of the die in the respective working position to the surface of the mandrel or the tool surfaces takes place via a freely programmable control.
- the setting in the working position for the respective radius of curvature runs automatically according to a predetermined program.
- Another advantageous possibility for carrying out the invention is that if the setting movement of the die into the normal position or into any other working position, which includes any setting angle between die and mandrel surface or tool surfaces, by an automatic control depending on a force measurement between the die holder and the machine frame he follows.
- the calibration mandrel is now made from the molded mold tube pushed out or pulled out. Possibly. the mold tube (calibrated pipe section) is cut to the final dimension and the attached pipe end, for example, is also cut off.
- the mold tube thus finished can then either be packaged and made ready for dispatch after the quality control has been carried out, but it can also be made up by mechanical processing before the quality control, i.e. for example the end faces of the mold tube can still be mechanically processed or retaining grooves can be milled into the tube wall from the outside.
- the method according to the invention can be applied to any mold cross-sectional shapes, the prerequisite being a mandrel shape corresponding to the desired cross-sectional shape of the mold.
- circular, rectangular, square or polygonal shapes can be achieved in cross-section, as can T, double-T, U- or L-shaped cross-sectional profiles.
- the mandrel required for the shaping in accordance with the desired cross-sectional shape can also be conically shaped in the implementation of the invention, one or more times, in order to ensure the conicity of the mold cavity that may be required.
- the mandrel can also be bent in order to ensure the use of tubular molds produced according to the invention also for continuous arc casting machines.
- the different profile of the mold cavity can lead to undercuts in the shape of the calibration mandrel.
- the division of the mandrel can be longitudinal and / or transverse to the axial direction of the mold.
- FIGS. 1 to 6 show the procedural sequence of the invention, while FIGS. 3 to 6 illustrate the specific case of regulating the die into the working position.
- the tube piece 1 suitable for a given mold type is selected from a store of cut-to-length tube pieces SR, possibly of different dimensions and / or cross-sectional shapes, and fed to station I for coupling.
- This coupling ie flanging the pipe end 2 expediently takes place after the supplied pipe section 1 has been clamped into a suitable press device by upsetting the one pipe end.
- the coupled pipe section 1 is conveyed to station II by means of a suitable transport device, and at the same time the calibration mandrel 3 predetermined by the order becomes removed from the mandrel stock SD and also fed to the station II, in which it is pressed in a kind of press bench, for example, into the still straight pipe section 1.
- the flared pipe section 1 inevitably takes on approximately the mandrel shape.
- Another possibility is to take the already curved pipe section 4 from the storage stock SR, to couple it in station I and then to insert the curved mandrel 3 in station II, i.e. depending on the shape and size of the mandrel to slide in or push it into the pipe section.
- the pipe section 1 is ironed onto the mandrel 3 with the aid of the die 5.
- the thorned pipe section (1/3) is pressed through the die in the direction of the arrow, the inner surface 6 of the pipe section 1 being pressed tightly onto the mandrel surface.
- the mandrel 3 is removed from the mold tube 1 ⁇ in station IV. This is done, for example, as shown in the figure, by means of a scraper 7, which serves as an abutment for the mold tube 1 ⁇ when the mandrel 3 is pressed out of the mold tube 1 ⁇ in the direction of the arrow.
- mandrel 3 After the mechanical separation of mandrel 3 and mold tube 1 ⁇ , as indicated in station V, mandrel 3 is again fed to station II or returned to mandrel storage SD after completion of a production batch.
- the transport section 8 is used for this purpose. If straight tube molds or tube molds with double-T profiles are provided in further production lots, the mandrel 9 or the mandrel is used accordingly use version 10.
- the calibrated pipe section 1 now the mold pipe 1 ⁇ , the coupled end 2 is separated and the pipe, if the ends have not yet been machined or cut to a required final dimension, is fed to the test station P.
- the mold tube 1 ⁇ can then be packed and made ready for dispatch.
- FIG. 2 illustrates the work system according to the invention in a type of block diagram.
- the work specification e.g. Production-free tubular mold, format X-Y square, material CuCrZr, partially conical, controlled
- a suitable piece of pipe is removed from the storage tank SR and fed to station I for coupling.
- the mandrel corresponding to the production batch defined according to the work specification arrives from the mandrel storage SD at station II and is inserted into the coupled pipe section brought up by station I.
- the tube-mandrel combination then arrives in station III for tightly pressing the pipe section onto the mandrel surface and finally for separating the mandrel and now calibrated pipe section (pipe mold) to station IV.
- the calibrated pipe section is fed to the test station P, if necessary after prior finishing, cutting to length, etc., and the mandrel first arrives at the control station ST, which, depending on the scope of the production lot (number of the same mold type), either ensures that the The mandrel arrives again in station II or is returned to the memory SD when the mold type to be manufactured is subsequently changed.
- FIGS. 3 to 6 Details of the forming process are shown in FIGS. 3 to 6 on an enlarged scale compared to FIGS. 1 and 2.
- the raw material used for forming a tube piece into the mold tube is the bright drawn straight copper tube 11, for example made from an extruded round tube by tube drawing, with a Brinell hardness of, for example, HB 55-75.
- This tube is cut to the desired mold length, taking into account a machining allowance.
- FIG. 3 the According to the internal dimensions of the mold to be produced, for example, a hard-chromed mandrel 12, which is deformed in accordance with the curvature of the circular arc continuous casting machine, is pressed (thorned) into the tube 11, as illustrated in FIG. 4.
- the copper tube 11 can of course already be pre-bent according to the mandrel shape in order to facilitate the insertion of the mandrel. Likewise, a sufficient clearance between the mandrel surface and the inner tube surface can be selected for the same purpose.
- the copper tube 11 will conveniently be coupled to the end 13, i.e. flare the pipe end inwards to create an abutment for the inserted mandrel for the subsequent forming.
- the abutment can also be created by a bolt extending transversely through the end of the copper tube or simply by tapering the end of the tube 13.
- the thorned copper pipe 11 is then fed to the forming device 14, which essentially consists of the machine frame 15 and the die holder 17, which is mounted on the machine frame 15 by means of the schematically indicated rotating or pivoting device 16 and which contains the die 18 contains. With 19 against the machine frame 15 supporting hydraulic cylinders are designated, which pivot the die holder 17, as indicated by arrows, relative to the machine frame 15 when actuating a corresponding control.
- the ideal position ie the normal position of the die to the mandrel surface, for example at any time when the thickened copper tube 11 is being passed (pulled or pressed) through the die 18.
- the ongoing forming process of tightly pressing or ironing the copper tube 11 onto the mandrel 12 can thus be actively influenced in the sense of a uniform wall thickness and in the sense of a uniform stress distribution and improvement of the mold life. This option is particularly useful when one goes to larger dimensions and harder mold materials.
- the respective position of the die 18 relative to the mandrel surface can be regulated with the aid of force measuring devices 20, which are arranged at different locations on the die holder 17 between die holder 17 and machine frame 15.
- the differences between the measured forces occurring are evaluated in data processing 21, for example via microprocessors known per se, and converted into control commands for regulating the die into the normal position.
Landscapes
- Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Mechanical Engineering (AREA)
- Metal Extraction Processes (AREA)
- Shaping Metal By Deep-Drawing, Or The Like (AREA)
- Continuous Casting (AREA)
- Bending Of Plates, Rods, And Pipes (AREA)
- Forging (AREA)
- Length Measuring Devices With Unspecified Measuring Means (AREA)
Applications Claiming Priority (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DE3615004 | 1986-05-02 | ||
DE19863615004 DE3615004A1 (de) | 1986-05-02 | 1986-05-02 | Verfahren zur umformung von abgelaengten rohrstuecken zu gebogenen kokillenrohren |
DE19863615079 DE3615079A1 (de) | 1986-05-03 | 1986-05-03 | Verfahren zur herstellung von durchlaufkokillen fuer stranggussmaschinen |
DE3615079 | 1986-05-03 |
Publications (3)
Publication Number | Publication Date |
---|---|
EP0243789A2 true EP0243789A2 (fr) | 1987-11-04 |
EP0243789A3 EP0243789A3 (en) | 1989-07-12 |
EP0243789B1 EP0243789B1 (fr) | 1992-08-19 |
Family
ID=25843444
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP87105533A Expired - Lifetime EP0243789B1 (fr) | 1986-05-02 | 1987-04-14 | Procédé de fabrication de lingotières pour les machines de coulée continue |
Country Status (8)
Country | Link |
---|---|
US (1) | US5018378A (fr) |
EP (1) | EP0243789B1 (fr) |
JP (1) | JP2587054B2 (fr) |
BR (1) | BR8702153A (fr) |
CA (1) | CA1299838C (fr) |
DE (1) | DE3781194D1 (fr) |
FI (1) | FI91131C (fr) |
IN (1) | IN168961B (fr) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6444219A (en) * | 1987-08-08 | 1989-02-16 | Okuda Kinzoku Kk | Production of curved pipe |
CN1047548C (zh) * | 1992-11-23 | 1999-12-22 | 张福兴 | 纵长形体无缝钢模的成型方法 |
JP3129009B2 (ja) * | 1992-12-25 | 2001-01-29 | 福興 張 | 縦長状の継目無し鋼製型具の成型方法 |
CN100341637C (zh) * | 2005-11-23 | 2007-10-10 | 大连冶金结晶器有限公司 | 一种具有特殊横截面的香蕉弧形结晶器铜管的加工方法 |
WO2008096449A1 (fr) * | 2007-02-09 | 2008-08-14 | Daikin Industries, Ltd. | Procédé d'un traitement de cintrage et appareil de traitement de cintrage |
DE102011106313A1 (de) * | 2011-06-27 | 2012-12-27 | Kme Germany Ag & Co. Kg | Verfahren zur Herstellung eines Kokillenrohrs |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1189135A (en) * | 1967-05-18 | 1970-04-22 | Battelle Development Corp | Method and apparatus for producing Tapered Metal Tubing |
DE2154226A1 (de) * | 1971-10-30 | 1973-05-03 | Kabel Metallwerke Ghh | Anordnung zur herstellung von kreisbogenfoermig gekruemmten kokillen fuer stranggussmaschinen |
EP0060820A1 (fr) * | 1981-03-13 | 1982-09-22 | Santrade Ltd. | Procédé et appareil pour la fabrication de tubes |
GB2151162A (en) * | 1983-12-14 | 1985-07-17 | Tubi Italia Spa | Method for preparing tubular chills for continuous steel casting plants |
GB2156719A (en) * | 1984-04-03 | 1985-10-16 | Kabel Metallwerke Ghh | Continuous casting moulds |
GB2160808A (en) * | 1984-06-27 | 1986-01-02 | Outokumpu Oy | Method and apparatus for manufacturing moulds formed of metal tubes, to be used in continuous casting machines for billets and blooms |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2134620A (en) * | 1936-07-30 | 1938-10-25 | Wellman Seaver Rolling Mill Co | Tubular article manufacture |
JPS59202141A (ja) * | 1983-04-28 | 1984-11-15 | Kobe Steel Ltd | わん曲連鋳鋳型の製造装置 |
JPS59202140A (ja) * | 1983-04-28 | 1984-11-15 | Kobe Steel Ltd | 連続鋳造用鋳型の製造方法 |
-
1987
- 1987-04-14 EP EP87105533A patent/EP0243789B1/fr not_active Expired - Lifetime
- 1987-04-14 DE DE8787105533T patent/DE3781194D1/de not_active Expired - Fee Related
- 1987-04-29 FI FI871891A patent/FI91131C/fi not_active IP Right Cessation
- 1987-04-30 IN IN354/CAL/87A patent/IN168961B/en unknown
- 1987-04-30 BR BR8702153A patent/BR8702153A/pt not_active IP Right Cessation
- 1987-05-01 JP JP62106482A patent/JP2587054B2/ja not_active Expired - Lifetime
- 1987-05-04 US US07/046,128 patent/US5018378A/en not_active Expired - Lifetime
- 1987-05-04 CA CA000536264A patent/CA1299838C/fr not_active Expired - Lifetime
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1189135A (en) * | 1967-05-18 | 1970-04-22 | Battelle Development Corp | Method and apparatus for producing Tapered Metal Tubing |
DE2154226A1 (de) * | 1971-10-30 | 1973-05-03 | Kabel Metallwerke Ghh | Anordnung zur herstellung von kreisbogenfoermig gekruemmten kokillen fuer stranggussmaschinen |
EP0060820A1 (fr) * | 1981-03-13 | 1982-09-22 | Santrade Ltd. | Procédé et appareil pour la fabrication de tubes |
GB2151162A (en) * | 1983-12-14 | 1985-07-17 | Tubi Italia Spa | Method for preparing tubular chills for continuous steel casting plants |
GB2156719A (en) * | 1984-04-03 | 1985-10-16 | Kabel Metallwerke Ghh | Continuous casting moulds |
GB2160808A (en) * | 1984-06-27 | 1986-01-02 | Outokumpu Oy | Method and apparatus for manufacturing moulds formed of metal tubes, to be used in continuous casting machines for billets and blooms |
Also Published As
Publication number | Publication date |
---|---|
FI91131C (fi) | 1994-05-25 |
JPS62275526A (ja) | 1987-11-30 |
JP2587054B2 (ja) | 1997-03-05 |
US5018378A (en) | 1991-05-28 |
BR8702153A (pt) | 1988-02-09 |
DE3781194D1 (de) | 1992-09-24 |
IN168961B (fr) | 1991-07-27 |
FI91131B (fi) | 1994-02-15 |
EP0243789B1 (fr) | 1992-08-19 |
FI871891A0 (fi) | 1987-04-29 |
CA1299838C (fr) | 1992-05-05 |
EP0243789A3 (en) | 1989-07-12 |
FI871891A (fi) | 1987-11-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP1796859B1 (fr) | Procede et dispositif pour produire un profile creux a soudure longitudinale | |
DE10050919B4 (de) | Verfahren zum Biegen von Metallrohren mit geringem Durchmesser und Vorrichtung hierfür | |
EP2127775A1 (fr) | Procédé et maschine de fluotournage pour la fabrication de pièces | |
DE3050452C2 (fr) | ||
DE19829050A1 (de) | Verfahren und Vorrichtung zur Herstellung eines Rings | |
DE3019593C2 (fr) | ||
EP0243789B1 (fr) | Procédé de fabrication de lingotières pour les machines de coulée continue | |
DE3432443A1 (de) | Schlauchpresshuelse | |
DE4124715A1 (de) | Verfahren und vorrichtung zum biegen einer metallrohrleitung geringen durchmessers | |
EP0955110B1 (fr) | Procédé et dispositif pour le fluotournage | |
DE102018211311B4 (de) | Erweiterte Regelung JCO-Formpresse | |
EP1035936B1 (fr) | Appareil et procédé pour le cracking de pièces | |
EP2077166A1 (fr) | Dispositif de traitement de bord longitudinal pour tôles | |
DE4104707C2 (de) | Vorrichtung zum Anstauchen von flanschartigen Verdickungen an Rohren | |
EP1551577A1 (fr) | Procede et dispositif pour produire une jante pour pneumatiques | |
DE10317312A1 (de) | Vorrichtung zum Halten wenigstens einer Walze einer Walzmaschine | |
EP1484123B1 (fr) | Procédé et dispositif pour fabriquer un profilé cintré | |
DE19725453A1 (de) | Verfahren zur Herstellung einer Hohlwelle | |
DE3615079A1 (de) | Verfahren zur herstellung von durchlaufkokillen fuer stranggussmaschinen | |
DE19801491A1 (de) | Verfahren und Vorrichtung zur Herstellung von Hohlkörpern durch Querwalzen | |
DE3412486C2 (de) | Verfahren zur Herstellung von Durchlaufkokillen für Stranggußmaschinen | |
DE3615004A1 (de) | Verfahren zur umformung von abgelaengten rohrstuecken zu gebogenen kokillenrohren | |
DE2754686C3 (de) | Einrichtung zum Richten von Flanschspulen | |
WO2013091973A1 (fr) | Dispositif modulaire de soudage de tube et procédé de fabrication d'un tube | |
DE102012200395B4 (de) | Werkstück aus einem länglichen Rohling oder Zwischenprodukt und Verfahren zu dessen Herstellung |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A2 Designated state(s): CH DE FR GB IT LI SE |
|
PUAL | Search report despatched |
Free format text: ORIGINAL CODE: 0009013 |
|
RAP1 | Party data changed (applicant data changed or rights of an application transferred) |
Owner name: KM-KABELMETAL AKTIENGESELLSCHAFT |
|
AK | Designated contracting states |
Kind code of ref document: A3 Designated state(s): CH DE FR GB IT LI SE |
|
17P | Request for examination filed |
Effective date: 19891214 |
|
17Q | First examination report despatched |
Effective date: 19900820 |
|
ITTA | It: last paid annual fee | ||
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): CH DE FR GB IT LI SE |
|
ET | Fr: translation filed | ||
GBT | Gb: translation of ep patent filed (gb section 77(6)(a)/1977) | ||
REF | Corresponds to: |
Ref document number: 3781194 Country of ref document: DE Date of ref document: 19920924 |
|
ITF | It: translation for a ep patent filed |
Owner name: STUDIO TORTA SOCIETA' SEMPLICE |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed | ||
EAL | Se: european patent in force in sweden |
Ref document number: 87105533.1 |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: IF02 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: SE Payment date: 20050406 Year of fee payment: 19 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20050407 Year of fee payment: 19 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 20050408 Year of fee payment: 19 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20050413 Year of fee payment: 19 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: CH Payment date: 20050415 Year of fee payment: 19 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20060414 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20060415 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20060430 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20060430 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: IT Payment date: 20060430 Year of fee payment: 20 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20061101 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
EUG | Se: european patent has lapsed | ||
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20060414 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST Effective date: 20061230 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20060502 |