EP0102340B1 - Verfahren zur Herstellung von Stahlbetonbauten wie unterirdischen Strecken, Strassentunnels usw; vorgefertigte Betonelemente für die Herstellung solcher Bauten - Google Patents
Verfahren zur Herstellung von Stahlbetonbauten wie unterirdischen Strecken, Strassentunnels usw; vorgefertigte Betonelemente für die Herstellung solcher Bauten Download PDFInfo
- Publication number
- EP0102340B1 EP0102340B1 EP83870074A EP83870074A EP0102340B1 EP 0102340 B1 EP0102340 B1 EP 0102340B1 EP 83870074 A EP83870074 A EP 83870074A EP 83870074 A EP83870074 A EP 83870074A EP 0102340 B1 EP0102340 B1 EP 0102340B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- elements
- concrete
- prefabricated
- walls
- frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 239000004567 concrete Substances 0.000 title claims description 57
- 239000011150 reinforced concrete Substances 0.000 title claims description 14
- 238000010276 construction Methods 0.000 title description 4
- 238000004519 manufacturing process Methods 0.000 title description 3
- 238000000034 method Methods 0.000 claims description 28
- 230000002787 reinforcement Effects 0.000 claims description 24
- 230000009974 thixotropic effect Effects 0.000 claims description 19
- 239000000463 material Substances 0.000 claims description 17
- 239000000945 filler Substances 0.000 claims description 15
- 229910000831 Steel Inorganic materials 0.000 claims description 13
- 239000010959 steel Substances 0.000 claims description 13
- 238000011144 upstream manufacturing Methods 0.000 claims description 13
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 12
- 239000002184 metal Substances 0.000 claims description 11
- 239000000440 bentonite Substances 0.000 claims description 7
- 229910000278 bentonite Inorganic materials 0.000 claims description 7
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 claims description 7
- 230000000295 complement effect Effects 0.000 claims description 7
- 238000009434 installation Methods 0.000 claims description 6
- 239000004568 cement Substances 0.000 claims description 4
- 230000002093 peripheral effect Effects 0.000 claims description 3
- 238000009417 prefabrication Methods 0.000 claims description 3
- 239000004744 fabric Substances 0.000 claims description 2
- 239000011440 grout Substances 0.000 claims description 2
- 238000007373 indentation Methods 0.000 claims description 2
- 229920000728 polyester Polymers 0.000 claims description 2
- 239000000725 suspension Substances 0.000 claims description 2
- 238000011065 in-situ storage Methods 0.000 claims 2
- 239000000126 substance Substances 0.000 claims 2
- 241000282472 Canis lupus familiaris Species 0.000 claims 1
- 238000013459 approach Methods 0.000 claims 1
- 230000001186 cumulative effect Effects 0.000 claims 1
- 239000003673 groundwater Substances 0.000 claims 1
- 238000009416 shuttering Methods 0.000 claims 1
- 238000009412 basement excavation Methods 0.000 description 33
- 238000009415 formwork Methods 0.000 description 11
- 210000001367 artery Anatomy 0.000 description 3
- 239000004576 sand Substances 0.000 description 3
- 238000004873 anchoring Methods 0.000 description 2
- 230000006835 compression Effects 0.000 description 2
- 238000007906 compression Methods 0.000 description 2
- 239000000835 fiber Substances 0.000 description 2
- 239000012530 fluid Substances 0.000 description 2
- -1 gravel Substances 0.000 description 2
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 2
- 239000011178 precast concrete Substances 0.000 description 2
- 238000007789 sealing Methods 0.000 description 2
- 230000035882 stress Effects 0.000 description 2
- 239000010425 asbestos Substances 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 238000000576 coating method Methods 0.000 description 1
- 238000005056 compaction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000006355 external stress Effects 0.000 description 1
- 239000011521 glass Substances 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 238000004806 packaging method and process Methods 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 229910052895 riebeckite Inorganic materials 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/08—Lining with building materials with preformed concrete slabs
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
- E02D29/05—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/16—Arrangement or construction of joints in foundation structures
Definitions
- the present invention relates to the production of reinforced concrete structures, such as underground galleries, road tunnels, subway tunnels, etc., using prefabricated elements.
- a first object of the present invention is to remedy the difficulty set out above, to lighten as much as possible and reduce the external dimensions of these prefabricated elements while maintaining an interior finish as close as possible to the final finish and thus allow execution of the process under particularly economical conditions.
- a second object of the invention consists in achieving continuity of the structure by concreting a second phase executed on site, straddling the joints between the prefabricated elements. This continuity is fundamental both from the point of view of mechanical strength and differential settlement under the action of traffic and from the point of view of sealing.
- the process which is the subject of the invention is essentially characterized in that a frame is used for each prefabricated element, the external faces of which include reinforcements, in that one poured filler concrete covering the joints between elements and collaborating with the reinforced concrete of the elements and with the reinforcements so as to achieve in successive phases and quickly, a monolithic structure whose resistance is clearly greater than those of the prefabricated elements initially placed in place and filler concrete.
- the external reinforcements are made integral with the prefabricated element ("precadre •) before the installation of the prefabricated element.
- An essential feature of the invention is the hollow element in prefabricated reinforced concrete constituted by a frame, and in itself called "pre-frame", characterized in that the outside faces of the frame include selected outside frames so as to generate a collaboration with a filler concrete which is implemented later around the elements.
- the pre-frames In the case of a tunnel made of very large prefabricated elements, the pre-frames have congestion which exceeds the authorized dimensions in height for road transport.
- the pre-frames are made of two or more complementary elements which will then be assembled on site.
- the implementation of the elements is done either in an open excavation dry excavated, or in successive transverse excavations carried out under thixotropic mud, in particular when the work must be carried out in dense urban site in streets or arteries near the existing buildings.
- the pre-frame element is a hollow block 4 produced with the thinnest reinforced concrete walls possible, that is to say in practice from 5 to 15 cm thick (fig. 1).
- the inner face 2 of the pre-frame 4 is cast generally smooth around a mold having an appearance as close as possible to the desired finished appearance.
- the external face is made either of rough concrete 53 without external formwork, or with a formwork comprising irregularities or indentations 120 resulting in creating by molding a surface comprising asperities (fig. 2).
- the external face comprises (FIG. 4) waiting frames 54 and / or sockets anchor 55 with threaded rods 59 and / or metal plates 56 with doguets 57 and jumpers 60 which makes it possible to set up, after hardening of the concrete and formwork, prefabricated concrete of the peripheral reinforcements 5 which will be fixed on the reinforcements standby 54, on threaded rods 59 or on jumpers 60.
- This last operation is carried out in the prefabrication plant or on the site, before the elements are implemented.
- the future raft 13 of the precadre can be made in its final thickness while the other walls are made in thin thickness as explained above (fig. 2).
- the raft 13 then has protuberances 14 outside the vertical walls with vertical reinforcements 15 anchored in these same protrusions (fig. 2).
- a pre-frame 4 produced as shown in FIG. 2 will weigh heavier and be more bulky than a similar element according to FIG. 1.
- Fig. 2 shows a pre-frame 4 comprising interior finishing elements 19, in this case platform elements for a metro station, security railings and finishing coatings on floors, walls and ceilings.
- Fig. 2 also shows a pre-frame comprising a stiffening rib 8 whose thickness corresponds to the total thickness of the walls after execution of the filler concrete.
- This rib 8 is essential in the case of implementation under thixotropic mud.
- the pre-frames include two or more complementary partial elements 99, 100 and 101 (fig. 6) which will then be assembled on site.
- the joint 102 between two half-pre-frames is located approximately halfway up each pedestal.
- the advantage of such a position of the joint lies in the fact that the final moments which will stress the tunnel in its final phase generate pulls outside the filler concrete, and therefore in the additional reinforcements which are added around the pre-frame.
- the right part of FIG. 6 shows a pre-frame 4 consisting of two half-pre-frames 100 and 101.
- the height 110 of this pre-frame exceeds the authorized road gauge.
- the lower half-frame 100 may include a raft 13 prefabricated in advance, as already explained previously (FIG. 2).
- the two half-frames 100 and 101 have a rib 8 of stiffening at mid-width.
- Fig. 7 shows a lowered trailer 104 pulled by a tractor 105.
- the half-frame 101 is placed on. the trailer straddling the half-frame 100 by interposing a setting 106.
- the overall height in the lowered trailer thus remains less than the gauge 108 authorized in height for road transport.
- Fig. 8 shows a horizontal section AA in the upper half-frame.
- the width 109 of the pre-frame is also less than the authorized road gauge.
- the assembly on site of the two half-frames 100 and 101 can also be done by a steel rod 140 comprising a nut at each end and which is placed in a tubular housing 141 reserved in the ribs 8 of the sides (fig. 6) .
- This post-stress can be calculated to prevent the opening of the joints 102 inside the pre-frame under the effect of lateral thrusts on the pedestals due to the terrain, water and overloads above the tunnel.
- an injection of cement slurry can be provided in the joint 102 to make the seal on the one hand and the continuity of the concrete on the other hand to take up the compression forces resulting from the external stresses.
- we will preferably choose values such that the stresses do not generate tensile forces on the internal face of the pedestal at the location of the joint 102 between the two half-pre-frames 100 and 101. This will make it possible to avoid having to apply a post-stress as explained above.
- the assembly principles set out above are also used. (see left part of fig. 6).
- Fig. 10 shows how a pre-frame 4 can be set up in a dry excavated excavation 62, comprising a vertical wall shielded 69 by sheet piling 71 for example, and another wall 72 in fairly steep slope taking into account the cohesion of the ground.
- the pre-frame 4 is placed at the bottom 61 of the excavation 62. It is adjusted on four jacks 74 placed on the bottom of the excavation which allow d '' ensure the installation of the pre-frame with all the required precision.
- the second phase concreting 18 (fig. 10) is then undertaken by embedding these wedging elements in the mass of concrete.
- the temporary cylinders 74 can be replaced by lost bag-cylinders which are injected with a cement grout to ensure the correct setting of the pre-frame; these cylinders no longer require wedging devices and are embedded in the mass of concrete, poured on the site outside the precadre.
- the provisional cylinders 74 can also be replaced by precast concrete slabs 74 which are adjusted in advance to the required level.
- the space 121 between the slabs 74 is leveled off at the laying level with fresh stabilized sand at the time of laying or subsequently filled with very thin concrete fluid.
- the second phase concrete 18 is poured below the pre-frame, on either side of it and above it.
- Fig. 9 shows a pre-frame 4 in accordance with FIG. 2 placed at the bottom of a dig 62 comprising a fairly steep slope 72 and another slope 75 with a slight slope.
- the second phase concrete 18 will be used between this slope and the pre-frame 4.
- a vertical formwork 76 (fig. 9) is put in place with supports 71, if any, on the embankment.
- This formwork 76 can also be bolted into the ribs 8 (fig. 2) when they are provided.
- This formwork 76 is recoverable after hardening of the concrete. It can also be replaced by a lost formwork made of profiled sheet steel for example.
- Figures 1, 2, 9, 10 and 12 show rectangular frames. It is understood, however, that these pre-frames can be of any generally shape including in particular rounded parts.
- the various pre-frames are implemented on the ground 61 previously leveled and are juxtaposed so as to produce the structure as a whole.
- peripheral seals 160 of compressible material placed between the pre-frames (fig. 2 and 3).
- this type of compressible seal only withstands lateral water pressure if the seal is compressed along the longitudinal axis of the tunnel.
- the bolts 94 and the angles 95 can be dismantled and recovered for the assembly of other pre-frames.
- Filler concrete is a conventional concrete composed of sand, gravel, cement and water but it can also include fibers, tensile resistant, in steel, glass, asbestos or other material.
- the currently known technique consists of carrying out excavations or longitudinal concrete walls molded into the ground under thixotropic mud. These two techniques require the successive execution of the walls then of the roof and the raft which come to connect the longitudinal walls. The execution of such works lasts a long time and therefore considerably annoys the neighboring population for a long period which is hardly acceptable to them.
- the present invention provides an original method of rapid implementation of prefabricated elements of the future gallery without causing the aforementioned drawbacks.
- the method is essentially characterized in that, transversely to the longitudinal axis of the future tunnel, successive excavations are carried out which are substantially rectangular and contiguous; one descends in each excavation successively at least one pre-frame as defined in FIG. 2, positioning it so that it is juxtaposed with the gallery element previously produced; then concreting on the outside between the ribs 8 of the two half-pre-frames and backfilling the remaining space of excavation, by a filling material such as gravel, sand or earth.
- a filling material such as gravel, sand or earth.
- a particular advantage is that the proposed technique makes it possible to remove the sheet from the longitudinal walls.
- a guide wall 201 in reinforced concrete is first made on either side of the excavation to be excavated to a depth of one to two meters approximately.
- This guide wall is generally completed by a reinforced concrete slab 202 intended to serve as a raceway for the gantry 203 which will be installed subsequently.
- this guide wall 201 will incorporate a channel 235 (fig. 12) for urban pipes.
- the site progresses in the direction of arrow 78.
- the pre-frames 4 are prefabricated in the factory in accordance with the above indications. They are then transported to the implementation site where they are stored in sufficient numbers (fig. 11).
- additional reinforcements 5 are fixed to this pre-frame in the factory or on site. These reinforcements 5 are arranged on the upstream side of the pre-frame 4 with respect to a shoulder 8 (fig. 2) so as to cover an upstream pre-frame element already in place up to its own shoulder 8 (fig. 13).
- the thickness of the apron is possibly increased by adding concrete incorporating the additional reinforcements 5 and thus making a complement to the apron 206 made of reinforced concrete poured on the site.
- the raft 13 (fig. 2) can also be entirely prefabricated at the factory as explained above.
- the pre-frames 4 also have two flexible closing walls 207 fixed on the periphery of the pre-frame upstream and downstream.
- These walls 207 are made of a material which is essentially permeable to water but impermeable to materials suspended in water.
- a non-woven polyester material may be used.
- This flexible wall 207 can be held in place between two sufficiently rigid metal trellises 31 which are fixed to the periphery of the pre-frame 4 and on the provisional stays 30 and / or include internal reinforcements made of tensile-resistant fibers.
- pre-frame elements 4 additionally comprise a rigid waterproof wall 33 generally made of concrete. This will later isolate a section of several elements 4 upstream of another element 4.
- the pre-frame 4 generally comprises two shoulders 8 of reinforced concrete towards the outside and in the middle of the two vertical walls as well as on the roof of the element (fig. 2).
- These reinforced concrete shoulders 8 are either prefabricated in the factory at the same time as the frame 4, or are executed on site at the same time as the possible addition of slab 206, in particular if the size authorized for road transport does not allow their prefabrication. in the factory.
- shoulders 8 also allow lateral fixing of rigid steel lines 9 made up either of a metal beam, or preferably of a U-shaped steel element intended for the execution of steel foundation piles.
- rigid steel lines 9 made up either of a metal beam, or preferably of a U-shaped steel element intended for the execution of steel foundation piles.
- a tubular element 225 of flexible and permeable fabric is fixed over the entire height. This tube 225 is closed at its lower part (fig. 15).
- the lines 9 are fixed to the frame and have a sufficient length to be able to be hung and suspended from the gantry 203 of implementation.
- This hanger 9 with its assembly plate 45 can create a connection between a half-frame 100 and a half-frame 101 by means of a series of anchor sockets or anchor bolts 103 (fig. 6 and 8).
- each frame 4 has rectangular notches c 34 which will deposit the base of a cofferdam 80 which will be discussed later.
- Sheets 210 (figs. 12 and 15) perforated with round holes of small diameter, are fixed to the reinforcements 5 with spacing devices to constitute the future lost formwork wall of the sides of the tunnel to be executed, thus avoiding pollution of the concrete. contribution by possible landslides.
- This sheet 210 can possibly be profiled and collaborating.
- These sheets 210 have a length sufficient to reach at least the upper level 22 of the elements 4 used.
- the pre-frames thus prepared are ready to be used in the excavation carried out under thixotropic mud.
- This digging under thixotropic mud is carried out by transverse trenches perpendicular 87 (fig. 11 and 14) to the axis of the tunnel to be produced, using a crane 79 provided with a hydraulic grab or a special grab 70 such as those used for the execution of concrete walls molded into the ground under thixotropic mud.
- this bucket 70 will generally have dimensions significantly larger than those of the buckets currently used, and this as a result of the size of each successive search.
- a removable transverse guide wall 85 is placed in notches 86 provided in the guide walls 201.
- the excavations or trenches have a width corresponding to the distance between two guide walls 201 parallel to the longitudinal axis of the future tunnel. In practice, this width will vary from approximately five to fifteen meters.
- the length of these successive excavations along the axis of the future tunnel to be produced will be fairly reduced. In practice, this length will be about two to three meters. This reduced length must make it possible to carry out the transverse excavation without the risk of settling for the neighboring buildings 214, the foundations 215 of which may be very close to the excavation thus carried out (FIGS. 11 and 12).
- thixotropic mud generally made up of bentonite mud and this up to level 25, higher than level 36 of the water table.
- a positioning and adjustment chassis 40 is then placed above the excavation excavated under thixotropic mud and bearing on the guide walls 201 (FIGS. 12 and 13).
- This chassis 40 generally made of steel, essentially comprises two beams 41 spaced apart from one another by a horizontal distance greater than the longitudinal dimensions 42 of the pre-frame 4 with the reinforcements 5.
- Double crosspieces 43 are provided so as to frame an extension 44 bolted to the hanger 9 by means of connection plates 45 welded respectively at the head of the hanger 9 and at the bottom of the extension 44.
- the carriage 46 or a horizontal positioning device can move horizontally on the double crosspieces 43 after the pre-frame 4 has been suspended, suspended by two lines 9 on either side of the excavation.
- Cylinders 47 make it possible to assume the precise adjustment in altitude of the pre-frame 4 according to the directives which will be given by a surveyor before or during the implementation of each element 4.
- the chassis 40 can be replaced by a carriage 126 (fig. 12) comprising at least four steel wheels 125 of the railroad or grooved type which run on two longitudinal rails 123 bearing on the guide walls 201.
- the pre-frame 4 is lowered until it partially penetrates into the thixotropic mud.
- the latter is partially filled with water.
- the descent of the pre-frame 4 can then continue to a new depth less than the height of the pre-frame 4 which is again filled with water to balance the momentary pressures on either side of the flexible and permeable wall 207. This process continues until frame 4 is completely filled with water.
- the pre-frame 4 can then be lowered to the level provided but at a certain horizontal distance from the element 4 already placed upstream (fig. 13).
- the two lines 9 provided with their respective extensions 44 are then supported by the carriage 126 or the positioning chassis 40.
- the two hooks 48 of the gantry 203 can then be disconnected from the suspension orifices 49 integral with the two extensions 44.
- the pre-frame 4 is further adjusted in altitude by the jacks 47 and then moved horizontally towards the element 4 already installed using the carriage 126 or positioning device 46. This precise work is carried out according to the instructions of a surveyor.
- the juxtaposition of the new frame 4 against the element 4 already implemented implies a precise and predetermined horizontal adjustment in order to be able to correct the manufacturing and implementation tolerances of the elements 4.
- Fig. 5 shows the device generally provided at three points of the pre-frame 4 of the element 4 used.
- the pre-frame 4 already in place includes this device on its edge, in three places, generally in the middle of the raft and at the two upper angles between the roof and the uprights of the element.
- This device consists of a steel plate 50 anchored securely in the concrete by doguets 51 or other anchoring devices.
- this device consists of an adjustment screw 52 which can rotate in a threaded sleeve 63 secured to doguets or other anchoring device 64.
- a similar device 66 allows precise vertical adjustment and recovery of the pressure due to filling under the raft.
- a generally cylindrical bowl 65 is provided to completely house the head of the screw 52 when it is fully screwed.
- the three adjustment screws 52 of each new pre-frame 4 implemented are adjusted as indicated by the surveyor as a function of the actual position of the element 4 immediately adjacent upstream.
- the new pre-frame 4 is thus correctly adjusted at the bottom (fig. 14) of the excavation against the preceding element 4, a vertical cofferdam 23 made of sheet piling or beams with precast concrete panels, or by any other system, is then implemented downstream of the pre-frame 4 which has just been installed and against it (figs. 14 and 15).
- This cofferdam 23 has a height which goes from the bottom 24 of the excavation to a little above the natural level 211 of the ground, and in any case above the level 25 of the bentonite mud.
- the space between the cofferdam 23 and the vertical wall of the terrain 216 is then filled with gravel 224 submerged under the bentonite mud. This gravel filling takes place at least up to level 22 corresponding to the upper level of the element 4 in place.
- This gravel 224 exerts a significant horizontal thrust on the cofferdam 23 and on the element 4 which has just been placed, thus pressing it strongly against the preceding element 4 upstream (fig. 14) and crushing the seal. 160 in compressible material (fig. 3).
- the cofferdam 23 (fig. 14) will generally comprise jacks 110 (fig. 15) which will make it possible to exert a constant, exact and adequate horizontal force to correctly crush the seal 160.
- the tube 225 is then filled with concrete 26 so as to close off the space between the lines 9 and the ground 216 (fig. 15).
- a material 275 such as thin fluid concrete is then poured under the raft 206 of the element 4 (fig. 14). This material 275 is poured under the thixotropic mud via concreting tubes 27 which can optionally be housed in the thickness of the cofferdam 23 (fig. 15).
- concrete 18 is poured by a concreting tube between the vertical walls of the two adjoining pre-frames 4 and the sheets 210 of perforated lost formwork. As this fresh concrete rises, it partially overflows through the holes in the formwork, thus filling the space between the ground 216, the lost formwork, constituted by the sheets 210, and the flange 225 filled with concrete 26
- the concrete 18 incorporates the reinforcements 5 fixed to the elements 4.
- a second cofferdam 80 comprising a beam 81 at its top is deposited in the notch 34 located in the shoulder 8 of the element 4 previously installed.
- Gravel 83 (fig. 14) is then poured upstream of this cofferdam 80 while gradually removing an identical cofferdam 84 which was placed above the antepenultimate element.
- the bucket 70 excavates the next excavation 87 under thixotropic mud between the cofferdam 23 and a removable guide wall 85. This bucket will evacuate the gravel 224 at the same time as the ground 216 in place. The operating cycle then resumes as described above.
- Fig. 12 also shows an original and efficient device in the case of elements 4 of great range.
- Oblique metal lines 90 are fixed to metal plates 91 anchored in the roof of the frame 4.
- This device makes it possible to considerably reduce the thickness 93 of the concrete and the corresponding reinforcements of the roof of the element 4 by creating intermediate supports which shorten the span.
- These oblique lines 90 can either be fixed to the two vertical lines 9 by means of assembly plates 45 or anchored in the future embankment.
- the upper part of the excavation can be backfilled with concrete injected gravel or lean concrete 92 which completely drowns the metal lines 9 and 90.
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Architecture (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Claims (24)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
AT83870074T ATE37586T1 (de) | 1982-07-30 | 1983-07-27 | Verfahren zur herstellung von stahlbetonbauten wie unterirdischen strecken, strassentunnels usw; vorgefertigte betonelemente fuer die herstellung solcher bauten. |
Applications Claiming Priority (6)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
BE208718 | 1982-07-30 | ||
BE0/208718A BE893989A (fr) | 1982-07-30 | 1982-07-30 | Procede de realisation d'ouvrages en beton arme tels que galeries souterraines, tunnels routiers, etc. elements en beton prefabriques pour la realisation de tels ouvrages. |
BE0/209205A BE894650R (fr) | 1982-10-08 | 1982-10-08 | Procede de realisation d'ouvrages en beton arme tels que galeries souterraines, tunnels routiers etc. ; elements en beton prefabriques pour la realisation de tels ouvrages |
BE209205 | 1982-10-08 | ||
BE210257 | 1983-03-04 | ||
BE210257 | 1983-03-04 |
Publications (3)
Publication Number | Publication Date |
---|---|
EP0102340A2 EP0102340A2 (de) | 1984-03-07 |
EP0102340A3 EP0102340A3 (en) | 1985-04-17 |
EP0102340B1 true EP0102340B1 (de) | 1988-09-28 |
Family
ID=27158731
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP83870074A Expired EP0102340B1 (de) | 1982-07-30 | 1983-07-27 | Verfahren zur Herstellung von Stahlbetonbauten wie unterirdischen Strecken, Strassentunnels usw; vorgefertigte Betonelemente für die Herstellung solcher Bauten |
Country Status (5)
Country | Link |
---|---|
US (1) | US4697955A (de) |
EP (1) | EP0102340B1 (de) |
BR (1) | BR8304095A (de) |
CA (1) | CA1217349A (de) |
DE (1) | DE3378135D1 (de) |
Families Citing this family (28)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100262832B1 (ko) * | 1991-12-20 | 2000-08-01 | 그레이스 스티븐 에스. | 열성형가능한내화학성중합체블렌드 |
NL191848C (nl) * | 1993-06-15 | 1996-09-03 | Igb Bouw En Aannemingsmij | Werkwijze voor het bouwen van een tunnel. |
US5871307A (en) * | 1996-03-15 | 1999-02-16 | Trevi Icos Corporation | Pre-cast concrete panel wall |
KR100656194B1 (ko) | 2006-05-03 | 2006-12-13 | 은산토건(주) | 터널공법을 적용한 개착식 공법 |
ES2394569B1 (es) * | 2010-03-10 | 2013-12-09 | Prefabricados Tecnyconta S.L. | Metodo para la construccion de pasos inferiores y paso inferior construido con dicho metodo |
JP6232190B2 (ja) * | 2013-02-28 | 2017-11-15 | 鹿島建設株式会社 | 目地構成部材、コンクリート打設方法、コンクリート構造物 |
AT514276A1 (de) * | 2013-04-25 | 2014-11-15 | Monai Bernhard Dipl Ing | Verfahren zum Versetzen von Fertigteilen |
JP6252835B2 (ja) * | 2013-10-07 | 2017-12-27 | 清水建設株式会社 | ボックスカルバート、及びその施工方法 |
JP6400934B2 (ja) * | 2014-04-08 | 2018-10-03 | 大成建設株式会社 | プレキャスト構造物の設置方法 |
JP6310370B2 (ja) * | 2014-09-05 | 2018-04-11 | 鹿島建設株式会社 | 函体接続補助装置 |
JP6408928B2 (ja) * | 2015-02-10 | 2018-10-17 | 早川ゴム株式会社 | コンクリート製構造物用の伸縮継手設置方法 |
JP6564636B2 (ja) * | 2015-07-06 | 2019-08-21 | 大成建設株式会社 | 鉄筋コンクリート構造物の隅角部構造 |
US10378678B2 (en) * | 2016-02-23 | 2019-08-13 | Void Form Products, Inc. | Plastic void construction unit |
US10267012B2 (en) * | 2016-02-23 | 2019-04-23 | Voidform Products, Inc. | Plumbing void construction unit |
CN107218062B (zh) * | 2017-07-19 | 2019-07-05 | 中国水利水电第十一工程局有限公司 | 一种逆作法处理隧洞塌方的施工方法 |
CN107761764A (zh) * | 2017-10-24 | 2018-03-06 | 中建科技湖南有限公司 | 一种可自由组合的预制管廊体系及施工方法 |
JP7010709B2 (ja) * | 2018-01-17 | 2022-02-10 | 鹿島建設株式会社 | プレハブ構造およびコンクリート構造物の構築方法 |
CN108385721A (zh) * | 2018-02-22 | 2018-08-10 | 中铁第勘察设计院集团有限公司 | 新建地铁线车站与既有车站的施工联通体系及其施工方法 |
JP6860167B2 (ja) * | 2018-03-02 | 2021-04-14 | 旭コンクリート工業株式会社 | ボックスカルバートの構築方法、及びボックスカルバート |
CN108547316B (zh) * | 2018-04-23 | 2020-12-11 | 哈尔滨工业大学 | 用于地下综合管廊的双层波纹钢结构 |
CN108442413B (zh) * | 2018-05-30 | 2024-04-26 | 中铁二十三局集团建筑设计研究院有限公司 | 预制装配式隧道墙体水平缝加强结构及拼接方法 |
CN108661079A (zh) * | 2018-06-01 | 2018-10-16 | 西安交通大学 | 一种预制拼装管中管式结构自防水综合管廊及安装方法 |
CN109667280A (zh) * | 2018-10-01 | 2019-04-23 | 南宁市城乡规划设计研究院 | 一种板块化预制的装配式管廊及其制备方法 |
CN109914477B (zh) * | 2019-04-02 | 2021-04-20 | 成都泽瀚科技有限公司 | 地下综合管廊预制拼装管道 |
CN112523257A (zh) * | 2020-11-20 | 2021-03-19 | 中冶天工集团有限公司 | 一种多角度可调节吊点的预制管廊滑移装置及其使用方法 |
CN112832690B (zh) * | 2020-12-16 | 2023-01-24 | 宁波市政工程建设集团股份有限公司 | 上软下硬地层旋挖钻机作业平台及其施工方法 |
CN113266400B (zh) * | 2021-07-08 | 2024-06-21 | 中铁隧道局集团有限公司 | 一种用于模筑隧道清污分流水渠的台车及其施工方法 |
CN113585339A (zh) * | 2021-08-26 | 2021-11-02 | 南京钜力智能制造技术研究院有限公司 | 一种城市地下货运用装配式预制混凝土管廊及其制造方法 |
Family Cites Families (24)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA525387A (en) * | 1956-05-22 | E. Simard Joseph | Joints for tunnel lengths and the like | |
US1050320A (en) * | 1906-12-08 | 1913-01-14 | Joseph S Williams | Transportation system. |
US1441698A (en) * | 1922-04-13 | 1923-01-09 | Frederick L Cranford | Tunnel construction |
US1671679A (en) * | 1924-09-12 | 1928-05-29 | Iowa State College | Method of increasing the supporting strength of conduits |
US1910594A (en) * | 1929-05-13 | 1933-05-23 | Mare Thomas De La | System for constructing pipe |
US1837134A (en) * | 1931-01-12 | 1931-12-15 | Detroit Trust Company | Tube tunnel construction |
US3111811A (en) * | 1956-12-15 | 1963-11-26 | Nederlanden Staat | Method for the construction of a tunnel or tunnel-part and a tunnel or tunnel-part obtained by pursuing said method |
US2959197A (en) * | 1957-04-30 | 1960-11-08 | Nederlanden Staat | Tunnel or tunnel-part |
US3496727A (en) * | 1967-06-21 | 1970-02-24 | Lloyd J De Weese | Apparatus for laying pipe |
IT947389B (it) * | 1972-02-08 | 1973-05-21 | Atros Srl | Procedimento per la posa in opera di manufatti in sottosuolo median te spinta o trazione dei medesimi attraverso il terreno |
DE2210988C3 (de) * | 1972-03-07 | 1981-10-22 | Marx, Karl, Dipl.-Ing. | Vorrichtung zum Verbauen von Baugräben |
US3820345A (en) * | 1972-07-14 | 1974-06-28 | H Brecht | Apparatus for laying pipe |
IT1025608B (it) * | 1974-11-12 | 1978-08-30 | Alpina Spa | Elementi prefabbricati per la co struzione di strutture in trincea e procedimento relativo |
US4116011A (en) * | 1976-06-04 | 1978-09-26 | Pablo Girault | Method of excavating tunnels |
IT1072998B (it) * | 1976-10-07 | 1985-04-13 | Binishells Spa | Procedimento ed apparecchiatura per l'erezione di strutture edilizie sostanzialmente a cupola |
FR2379007A1 (fr) * | 1977-01-26 | 1978-08-25 | Soletanche | Perfectionnements apportes a la mise en place de canalisations enterrees |
FR2385845A1 (fr) * | 1977-03-30 | 1978-10-27 | Gecti | Procede de franchissement d'une voie par une seconde voie en remblai et ouvrage assurant ce franchissement |
DE2715127A1 (de) * | 1977-04-05 | 1978-10-19 | Lorenz Kesting | Stahlbetonfertigteil fuer rohrtunnel, insbesondere der fernwaermeversorgung |
BR7705555A (pt) * | 1977-08-19 | 1979-03-20 | Promon Engenharia Sa | Processo para construcao de uma galeria pre-moldada |
GB2014212B (en) * | 1978-02-10 | 1982-06-03 | Shaw C B | Culverts |
US4314775A (en) * | 1979-09-10 | 1982-02-09 | Johnson Delp W | Method of site casting tunnels, culverts, pressure pipes with minimum forming |
DE2949277A1 (de) * | 1979-12-07 | 1981-01-08 | Helmut Prof Dr Ing Bugarcic | Roehre fuer die anordnung des fahrweges einer stadtschnellbahn |
FR2472074A1 (fr) * | 1979-12-18 | 1981-06-26 | Lille Communaute Urbaine | Procede de realisation de galeries en fouille ouverte en terrain ebouleux et dispositif permettant d'appliquer ledit procede |
US4459063A (en) * | 1980-08-07 | 1984-07-10 | Shaw Christopher B | Building construction |
-
1983
- 1983-07-27 DE DE8383870074T patent/DE3378135D1/de not_active Expired
- 1983-07-27 EP EP83870074A patent/EP0102340B1/de not_active Expired
- 1983-07-28 CA CA000433410A patent/CA1217349A/fr not_active Expired
- 1983-07-29 BR BR8304095A patent/BR8304095A/pt unknown
- 1983-07-29 US US06/518,752 patent/US4697955A/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
US4697955A (en) | 1987-10-06 |
EP0102340A2 (de) | 1984-03-07 |
EP0102340A3 (en) | 1985-04-17 |
BR8304095A (pt) | 1984-03-07 |
CA1217349A (fr) | 1987-02-03 |
DE3378135D1 (en) | 1988-11-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP0102340B1 (de) | Verfahren zur Herstellung von Stahlbetonbauten wie unterirdischen Strecken, Strassentunnels usw; vorgefertigte Betonelemente für die Herstellung solcher Bauten | |
EP2649242B1 (de) | Verfahren zur konstruktion von strukturen, insbesondere durchgängen unter befahrenen schienen oder ähnlichem | |
CA1319261C (fr) | Structures cellulaires pour murs de soutenement | |
CH642416A5 (fr) | Procede de construction d'ouvrages souterrains a parois verticales, dispositif pour l'execution du procede et ouvrage souterrain. | |
WO2012149670A1 (zh) | 根式基础锚碇施工方法及根键式钻孔灌注桩施工方法 | |
KR20060103309A (ko) | 지하옹벽을 제거하기 위한 상향식 순차제거 및순차매립공법 | |
FR2960570A1 (fr) | Paroi formee dans un sol, comprenant un element prefabrique creux, et procede de realisation d'une telle paroi | |
EA027027B1 (ru) | Способ создания подпорной стенки | |
FR2523627A1 (fr) | Procede pour conforter des arches ou des constructions analogues | |
EP0242497B1 (de) | Tunnelbauverfahren | |
BE1001360A3 (fr) | Pont semi-prefabrique. | |
US4056154A (en) | Squaring off and reaming tool for deep elongated trench excavations | |
EP0192004B1 (de) | Verfahren und Vorrichtung zum Errichten von einem Bauwerk, wie zum Beispiel einer vorgefertigten Brücke | |
CN212375698U (zh) | 一种与预应力锚索结合的超高复合加筋土桥台 | |
FR2692298A1 (fr) | Masque d'étanchéité en béton armé préfabriqué pour barrages en béton compacté au rouleau et en enrochement et pour talus de lacs en terrains karstiques. | |
BE894650R (fr) | Procede de realisation d'ouvrages en beton arme tels que galeries souterraines, tunnels routiers etc. ; elements en beton prefabriques pour la realisation de tels ouvrages | |
FR2839990A1 (fr) | Ouvrage d'art prefabrique et procede de mise en place de l'ouvrage d'art | |
CN220266625U (zh) | 一种注浆片石挡墙墙身注浆加固结构 | |
EP3749810B1 (de) | Fundament zur bereitstellung einer punktauflage für eine struktur und verfahren zur herstellung eines solchen fundaments | |
NL2025176B1 (nl) | Kademuur en werkwijze voor het aanleggen van een kademuur | |
JPH04185816A (ja) | 地中壁に梁を構築する方法 | |
BE893989A (fr) | Procede de realisation d'ouvrages en beton arme tels que galeries souterraines, tunnels routiers, etc. elements en beton prefabriques pour la realisation de tels ouvrages. | |
WO1990001089A1 (fr) | Procede pour reparer une fondation comportant des tetes de pieux deteriorees, notamment de pieux en bois | |
CN116607562A (zh) | 一种注浆片石挡墙墙身注浆加固结构及其施工方法 | |
FR2869052A1 (fr) | Pont rail sur route et procede de construction de ce pont, en suppleance ou suppression de passage a niveau existant |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Designated state(s): AT CH DE FR GB IT LI NL SE |
|
PUAL | Search report despatched |
Free format text: ORIGINAL CODE: 0009013 |
|
AK | Designated contracting states |
Designated state(s): AT CH DE FR GB IT LI NL SE |
|
17P | Request for examination filed |
Effective date: 19851014 |
|
17Q | First examination report despatched |
Effective date: 19861216 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT CH DE FR GB IT LI NL SE |
|
ITF | It: translation for a ep patent filed |
Owner name: BARZANO' E ZANARDO MILANO S.P.A. |
|
REF | Corresponds to: |
Ref document number: 37586 Country of ref document: AT Date of ref document: 19881015 Kind code of ref document: T |
|
GBT | Gb: translation of ep patent filed (gb section 77(6)(a)/1977) | ||
REF | Corresponds to: |
Ref document number: 3378135 Country of ref document: DE Date of ref document: 19881103 |
|
RAP2 | Party data changed (patent owner data changed or rights of a patent transferred) |
Owner name: LES ENTREPRISES LOUIS DE WAELE S.A. Owner name: SPRL ETABLISSEMENTS E. RONVEAUX SOCIETE DE PERSON Owner name: DYNAMIQUE DU BATIMENT EN ABREGE DYNABAT SOCIETE |
|
RAP4 | Party data changed (patent owner data changed or rights of a patent transferred) |
Owner name: LES ENTREPRISES LOUIS DE WAELE S.A. Owner name: SPRL ETABLISSEMENTS E. RONVEAUX SOCIETE DE PERSON Owner name: DYNAMIQUE DU BATIMENT EN ABREGE DYNABAT SOCIETE |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed | ||
ITTA | It: last paid annual fee | ||
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: AT Payment date: 19930714 Year of fee payment: 11 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: SE Payment date: 19930723 Year of fee payment: 11 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AT Effective date: 19940727 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Effective date: 19940728 |
|
EUG | Se: european patent has lapsed |
Ref document number: 83870074.8 Effective date: 19950210 |
|
EUG | Se: european patent has lapsed |
Ref document number: 83870074.8 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 19950717 Year of fee payment: 13 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 19950726 Year of fee payment: 13 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: CH Payment date: 19950728 Year of fee payment: 13 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 19960726 Year of fee payment: 14 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Effective date: 19960727 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LI Effective date: 19960731 Ref country code: CH Effective date: 19960731 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: NL Payment date: 19960731 Year of fee payment: 14 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 19960727 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Effective date: 19970402 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19980201 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19980331 |
|
NLV4 | Nl: lapsed or anulled due to non-payment of the annual fee |
Effective date: 19980201 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST |