CN110281009A - 一种汽车玻璃升降器装配线工艺 - Google Patents
一种汽车玻璃升降器装配线工艺 Download PDFInfo
- Publication number
- CN110281009A CN110281009A CN201910604736.2A CN201910604736A CN110281009A CN 110281009 A CN110281009 A CN 110281009A CN 201910604736 A CN201910604736 A CN 201910604736A CN 110281009 A CN110281009 A CN 110281009A
- Authority
- CN
- China
- Prior art keywords
- wiring technology
- finished product
- semi
- automobile glass
- product processing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23P—METAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
- B23P21/00—Machines for assembling a multiplicity of different parts to compose units, with or without preceding or subsequent working of such parts, e.g. with programme control
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G49/00—Conveying systems characterised by their application for specified purposes not otherwise provided for
- B65G49/05—Conveying systems characterised by their application for specified purposes not otherwise provided for for fragile or damageable materials or articles
- B65G49/06—Conveying systems characterised by their application for specified purposes not otherwise provided for for fragile or damageable materials or articles for fragile sheets, e.g. glass
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Automobile Manufacture Line, Endless Track Vehicle, Trailer (AREA)
- Automatic Assembly (AREA)
Abstract
本发明公开了一种汽车玻璃升降器装配线工艺,涉及汽车玻璃升降器生产技术领域,包括半成品加工线工艺和成品加工线工艺,所述半成品加工线工艺和成品加工线工艺衔接平衡,形成流畅的装配线工艺,本发明的汽车玻璃升降器装配线工艺,装配线安排合理,不仅节省用人量,且有效的均衡了各工序的生产节拍,使得生产工作协调,半成品加工线工艺和成品加工线工艺衔接平衡,降低了成品加工线工艺中的皮带线出现产品堆积等现象的发生,生产工序流畅,提高了生产效率,保证了产品质量。
Description
技术领域
本发明涉及汽车玻璃升降器生产技术领域,特别涉及一种汽车玻璃升降器装配线工艺。
背景技术
随着汽车工业的发展,对于生产效率和产品质量要求越来越高,因此,为了节约生产成本,提高生产效率和产品质量,合理优化装配线工艺,是一种重要手段。
然而,现有的汽车玻璃升降器装配线工艺,由于装配线安排不合理,导致装配线上某一个或几道工序上出现生产工作的不协调,不流畅,从而导致装配线的失衡,使生产效率低下,生产成本提高,以及产品质量都受到影响。
发明内容
本发明所要解决的技术问题是提供一种汽车玻璃升降器装配线工艺,以解决现有技术中导致的装配线安排不合理,导致装配线上某一个或几道工序上出现生产工作的不协调,不流畅,从而导致装配线的失衡,使生产效率低下,生产成本提高,以及产品质量都受到影响等上述多项缺陷。
为实现上述目的,本发明提供以下的技术方案:一种汽车玻璃升降器装配线工艺,包括半成品加工线工艺和成品加工线工艺,所述半成品加工线工艺和成品加工线工艺衔接平衡,形成流畅的装配线工艺。
优选的,所述半成品加工线工艺无皮带线进行传输,所述成品加工线工艺采用皮带线进行传输。
优选的,所述半成品加工线工艺,包括以下六道工序:
工序一,人工进行滑轮涂油,码放滑轮;
工序二,采用自动涂油设备对卡管涂润滑脂;
工序三,对导轨及滑轮配合面涂润滑脂,人工进行导轨铆接滑轮;
工序四,人工进行导轨涂润滑脂;
工序五,人工安装导轨滑块、涂润滑脂;
工序六,采用自动涂油设备对丝轮涂润滑脂。
优选的,所述成品加工线工艺,包括以下五道工序:
工序一,安装卡管及玻璃托架,组装上、中、下钢丝绳;
工序二,绕装丝轮、安装绕线卡管;
工序三,对电机进行涂润滑脂、安装电机;
工序四,终检检测;
工序五,挂架。
优选的,所述半成品加工线工艺,因无皮带线进行传输,因此,1个操作人员可以完成几道工序的生产任务,因此,配备2-3个操作人员,所述成品加工线工艺,因使用皮带线进行传输作业,因此,每道工序至少配备1名操作人员。
与现有技术相比,本发明具有以下有益效果:
本发明的汽车玻璃升降器装配线工艺,装配线安排合理,不仅节省用人量,且有效的均衡了各工序的生产节拍,使得生产工作协调,半成品加工线工艺和成品加工线工艺衔接平衡,降低了成品加工线工艺中的皮带线出现产品堆积等现象的发生,生产工序流畅,提高了生产效率,保证了产品质量。
具体实施方式
下面说明本发明的优选实施方式。
一种汽车玻璃升降器装配线工艺,包括半成品加工线工艺和成品加工线工艺,所述半成品加工线工艺和成品加工线工艺衔接平衡,形成流畅的装配线工艺。
本实施例中,所述半成品加工线工艺无皮带线进行传输,所述成品加工线工艺采用皮带线进行传输。
所述半成品加工线工艺,包括以下六道工序:
工序一,人工进行滑轮涂油,码放滑轮;
工序二,采用自动涂油设备对卡管涂润滑脂;
工序三,对导轨及滑轮配合面涂润滑脂,人工进行导轨铆接滑轮;
工序四,人工进行导轨涂润滑脂;
工序五,人工安装导轨滑块、涂润滑脂;
工序六,采用自动涂油设备对丝轮涂润滑脂。
所述成品加工线工艺,包括以下五道工序:
工序一,安装卡管及玻璃托架,组装上、中、下钢丝绳;
工序二,绕装丝轮、安装绕线卡管;
工序三,对电机进行涂润滑脂、安装电机;
工序四,终检检测;
工序五,挂架。
值得注意的是,所述半成品加工线工艺,因无皮带线进行传输,因此,1个操作人员可以完成几道工序的生产任务,因此,配备2-3个操作人员,所述成品加工线工艺,因使用皮带线进行传输作业,因此,每道工序至少配备1名操作人员。
以我司生产的T18WR防夹型汽车玻璃升降器总成装配为例,具体见改进前的T18WR防夹型玻璃升降器总成工时定额表(表1)和改进后的T18WR防夹型玻璃升降器总成工时定额表(表2),
表1:
表2:
由表1和表2可知,改进前,单班产能为397套,半成品加工工序,因无皮带线进行传输,因此1个操作人员可以完成几道工序的生产任务,因此,按照单班产能(每天按照7.5小时计算)来计算用工人数,成品加工工序,因使用皮带线进行传输作业,因此每道工序最少配备1名操作人员。按照单班397套产能,共计需要操作人员7.65人(终检检测工序人员属于质量部,不计算在内)。其中,终检检测工序为瓶颈工序。
改进后,从改进后的装配线工艺可以看出,按照单班397套产能,共计需要操作人员7.36人(终检检测工序人员属于质量部,不计算在内),这样共计节约0.29人。在产能不变的情况下,用工成本按照1名操作人员月薪5000元计算,1年可以节约成本17400元。
另外我司同类型绳轮式双轨玻璃升降器CX62WR(前门)、S51EVWR、A19WR(前门)、T18WR(普通型)等项目均适用于此方案,节约了大量的生产成本。
另外,改进后的成品加工工序中的安装卡管及玻璃托架,组装上、中、下钢丝绳单件生产节拍为32秒,而终检检测工序为瓶颈工序,单件生产节拍为34秒,从而有效的均衡了各工序的生产节拍,降低了皮带线出现产品堆积等现象的发生,保证了产品质量。
综上,由改进前后的T18WR防夹型玻璃升降器总成工时定额表可知,本发明的汽车玻璃升降器装配线工艺,装配线安排合理,不仅节省用人量,节约生产成本,且有效的均衡了各工序的生产节拍,使得生产工作协调,半成品加工线工艺和成品加工线工艺衔接平衡,降低了成品加工线工艺中的皮带线出现产品堆积等现象的发生,生产工序流畅,提高了生产效率,保证了产品质量。
以上所述的仅是本发明的优选实施方式,应当指出,对于本领域的普通技术人员来说,在不脱离本发明创造构思的前提下,还可以做出若干变形和改进,这些都属于本发明的保护范围。
Claims (5)
1.一种汽车玻璃升降器装配线工艺,其特征在于:包括半成品加工线工艺和成品加工线工艺,所述半成品加工线工艺和成品加工线工艺衔接平衡,形成流畅的装配线工艺。
2.根据权利要求1所述的汽车玻璃升降器装配线工艺,其特征在于:所述半成品加工线工艺无皮带线进行传输,所述成品加工线工艺采用皮带线进行传输。
3.根据权利要求2所述的汽车玻璃升降器装配线工艺,其特征在于:所述半成品加工线工艺,包括以下六道工序:
工序一,人工进行滑轮涂油,码放滑轮;
工序二,采用自动涂油设备对卡管涂润滑脂;
工序三,对导轨及滑轮配合面涂润滑脂,人工进行导轨铆接滑轮;
工序四,人工进行导轨涂润滑脂;
工序五,人工安装导轨滑块、涂润滑脂;
工序六,采用自动涂油设备对丝轮涂润滑脂。
4.根据权利要求3所述的汽车玻璃升降器装配线工艺,其特征在于:所述成品加工线工艺,包括以下五道工序:
工序一,安装卡管及玻璃托架,组装上、中、下钢丝绳;
工序二,绕装丝轮、安装绕线卡管;
工序三,对电机进行涂润滑脂、安装电机;
工序四,终检检测;
工序五,挂架。
5.根据权利要求4所述的汽车玻璃升降器装配线工艺,其特征在于:所述半成品加工线工艺,因无皮带线进行传输,因此,1个操作人员可以完成几道工序的生产任务,因此,配备2-3个操作人员,所述成品加工线工艺,因使用皮带线进行传输作业,因此,每道工序至少配备1名操作人员。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910604736.2A CN110281009B (zh) | 2019-07-05 | 2019-07-05 | 一种汽车玻璃升降器装配线工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910604736.2A CN110281009B (zh) | 2019-07-05 | 2019-07-05 | 一种汽车玻璃升降器装配线工艺 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110281009A true CN110281009A (zh) | 2019-09-27 |
CN110281009B CN110281009B (zh) | 2020-08-04 |
Family
ID=68021911
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910604736.2A Active CN110281009B (zh) | 2019-07-05 | 2019-07-05 | 一种汽车玻璃升降器装配线工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110281009B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113118756A (zh) * | 2021-04-13 | 2021-07-16 | 温州职业技术学院 | 汽车玻璃升降器组装方法 |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1255182A (zh) * | 1997-05-06 | 2000-05-31 | 布罗泽汽车部件制造有限公司 | 用于将零件与汽车的支承件连接的装置和方法 |
US20030011209A1 (en) * | 2000-10-17 | 2003-01-16 | Lear Corporation | Method for making vehicle door |
JP2007210061A (ja) * | 2006-02-08 | 2007-08-23 | Hi-Lex Corporation | ウインドレギュレータの搬送用固定具、ウインドレギュレータ組立セットおよびその取り付け方法 |
CN104148926A (zh) * | 2014-08-06 | 2014-11-19 | 温州天球电器有限公司 | 一种车窗玻璃升降器的组装生产线 |
CN104440051A (zh) * | 2014-10-30 | 2015-03-25 | 芜湖莫森泰克汽车科技有限公司 | 汽车后门玻璃绳轮式升降器的生产方法 |
CN204827006U (zh) * | 2015-06-27 | 2015-12-02 | 芜湖莫森泰克汽车科技有限公司 | 一种车门玻璃升降器 |
CN105201322A (zh) * | 2015-09-06 | 2015-12-30 | 芜湖莫森泰克汽车科技有限公司 | 汽车叉臂式电动玻璃升降器总成件生产工艺 |
CN107097617A (zh) * | 2016-02-19 | 2017-08-29 | 马自达汽车株式会社 | 汽车的车门构造及其组装方法 |
-
2019
- 2019-07-05 CN CN201910604736.2A patent/CN110281009B/zh active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1255182A (zh) * | 1997-05-06 | 2000-05-31 | 布罗泽汽车部件制造有限公司 | 用于将零件与汽车的支承件连接的装置和方法 |
US20030011209A1 (en) * | 2000-10-17 | 2003-01-16 | Lear Corporation | Method for making vehicle door |
JP2007210061A (ja) * | 2006-02-08 | 2007-08-23 | Hi-Lex Corporation | ウインドレギュレータの搬送用固定具、ウインドレギュレータ組立セットおよびその取り付け方法 |
CN104148926A (zh) * | 2014-08-06 | 2014-11-19 | 温州天球电器有限公司 | 一种车窗玻璃升降器的组装生产线 |
CN104440051A (zh) * | 2014-10-30 | 2015-03-25 | 芜湖莫森泰克汽车科技有限公司 | 汽车后门玻璃绳轮式升降器的生产方法 |
CN204827006U (zh) * | 2015-06-27 | 2015-12-02 | 芜湖莫森泰克汽车科技有限公司 | 一种车门玻璃升降器 |
CN105201322A (zh) * | 2015-09-06 | 2015-12-30 | 芜湖莫森泰克汽车科技有限公司 | 汽车叉臂式电动玻璃升降器总成件生产工艺 |
CN107097617A (zh) * | 2016-02-19 | 2017-08-29 | 马自达汽车株式会社 | 汽车的车门构造及其组装方法 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113118756A (zh) * | 2021-04-13 | 2021-07-16 | 温州职业技术学院 | 汽车玻璃升降器组装方法 |
CN113118756B (zh) * | 2021-04-13 | 2022-04-15 | 温州职业技术学院 | 汽车玻璃升降器组装方法 |
Also Published As
Publication number | Publication date |
---|---|
CN110281009B (zh) | 2020-08-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110281009A (zh) | 一种汽车玻璃升降器装配线工艺 | |
CN105834349B (zh) | 链条压盖铆头机 | |
CN211806134U (zh) | 一种小型丝杠电机一体式钢带密封型模组 | |
CN205996072U (zh) | 一种铝焊丝光亮矫直切断机 | |
CN205642285U (zh) | 一种智能手机内尺寸检测设备 | |
CN103454094B (zh) | 拖拉机底盘自重负荷式磨合净化试验台及其磨合净化工艺 | |
CN209424957U (zh) | 一种便于润滑的门导轨 | |
CN209162501U (zh) | 在线加润滑油的捻股装置 | |
CN209867835U (zh) | 一种自动化对揉设备 | |
CN208438299U (zh) | 一种汽车线束装配工作台 | |
CN208161990U (zh) | 一种自动涂润滑油脂机 | |
CN207521452U (zh) | 一种整平机 | |
CN205529054U (zh) | 一种方管镀锌自动酸洗装置 | |
CN205616393U (zh) | 一种电梯门导向用滚动门靴 | |
CN201543657U (zh) | 热连轧机主传动故障的过渡传动辊道装置 | |
CN205628971U (zh) | 一种新型水箱拉丝机放线架 | |
CN211888826U (zh) | 一种零件加工用搓丝机 | |
CN219296412U (zh) | 吊挂进站装置 | |
CN219933676U (zh) | 一种agv驱动润滑结构 | |
CN209255521U (zh) | 一种钢带平整机 | |
CN209335276U (zh) | 一种安全性能高的机械手拉丝装置 | |
CN217619737U (zh) | 一种零件自动化打磨抛光生产线 | |
CN215032402U (zh) | 一种用于铜线中拉机的张力架 | |
CN210269206U (zh) | 一种减速机下线检测系统的可调节加载装置 | |
CN216066338U (zh) | 一种用于整流器自动装配检测的装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |