CN108643216A - 更换老旧隔离开关时基础不停电施工方法 - Google Patents
更换老旧隔离开关时基础不停电施工方法 Download PDFInfo
- Publication number
- CN108643216A CN108643216A CN201810393198.2A CN201810393198A CN108643216A CN 108643216 A CN108643216 A CN 108643216A CN 201810393198 A CN201810393198 A CN 201810393198A CN 108643216 A CN108643216 A CN 108643216A
- Authority
- CN
- China
- Prior art keywords
- basis
- disconnecting switch
- power failure
- power cut
- foundation bolt
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Foundations (AREA)
Abstract
本发明公开了更换老旧隔离开关时基础不停电施工方法,属于电力设施施工领域;所要解决的技术问题是提供了一种土建基础不停电施工的方法,缩短了施工停电周期,提高了作业效率,降低了停电对用户的影响;解决该技术问题采用的技术方案为:更换老旧隔离开关时基础不停电施工方法,在设备运行不停电的状态下,在不损害原有基础及基础上方的水泥柱的情况下,进行人工开挖,开挖至原基础外露,同时支设模板,同时预埋U型钢板和地脚螺栓,然后进行混凝土浇筑作为新隔离开关的独立基础,在混凝土强度达标后截断外露的水泥杆部分,将新隔离开关及钢支架与独立基础固定,安装调试完成后即完成整个施工过程;本发明可广泛应用于电力设施施工领域。
Description
技术领域
本发明更换老旧隔离开关时基础不停电施工方法,属于电力设施施工技术领域。
背景技术
随着经济的发展,用电负荷的增加,变电站原有的老旧设备不能满足新增负荷的要求,需要更换新设备来保证变电站的安全稳定运行,尤其是早起的隔离开关,支架采用水泥杆,属于未完善化产品,由于运行年久,机构卡涩、触头发热时有发生,存在极大的安全隐患。
目前,更换这种早期的隔离开关采用的施工步骤是:提前制定停电计划和施工过渡方案,然后把需要更换的隔离开关和水泥杆支架、基础停电拆除,在原位置开挖新建混凝土基础,混凝土养护周期一般不少于1周,大约1周后新设备才能就位安装调试,整个设备更换过程需要停电施工大约1周左右时间,这种施工方法存在的主要问题是停电时间长,而变电站实际运行中一般很难允许这么长的停电时间来施工,这也是当前施工中最大的问题,所以需要找到一种经济实用又高效的更换老旧隔离开关的施工方法,来解决目前施工停电时间长的问题,以满足电力系统优质服务、可靠供电的发展和要求。
发明内容
本发明服了现有技术存在的不足,提供了一种土建基础不停电施工的方法,缩短了施工停电周期,提高了作业效率,降低了停电对用户的影响。
为了解决上述技术问题,本发明采用的技术方案为:更换老旧隔离开关时基础不停电施工方法,其特征在于,包括如下步骤:
1)在设备运行不停电的状态下,在不损害原有基础及基础上方的水泥柱的情况下,进行人工开挖,开挖至原基础外露,同时支设模板;
2)在原水泥柱位于地面的高度预埋设置U型钢板和地脚螺栓;
3)对支护好的模板和预埋的U型钢板和地脚螺栓进行混凝土浇筑作为新隔离开关的独立基础,独立基础将原有基础及水泥杆包覆;
4)在独立基础养护期间做好停电前的准备工作;
5)待批准停电后,首先截断独立基础外露的水泥杆部分,将新隔离开关及钢支架与独立基础上方的地脚螺栓固定,安装调试完成后即完成整个施工过程。
所述的U型钢板圆心直径大于水泥杆直径,以便于包覆住原有的水泥杆,所述的地脚螺栓设置在U型钢板上,所述的地脚螺栓孔距与新隔离开关钢支架底板上的地脚螺栓间距一致。
所述的独立基础成型后的混凝土养护,在强度达到100%后方可以截断原有水泥杆。
本发明与现有技术相比具有以下有益效果。
1、土建基础施工阶段实现了不停电施工,不用考虑因为停电计划而影响施工的周期和进度,保证了设备更换过程的顺利实施,节约了人力和财力。
2、整个设备的更换过程停电时间只需要考虑旧设备拆除和新设备安装调试时间,停电时间只需要1天就能完成设备更换,大大缩短了施工停电周期,明显的缩短了停电对用户带来的影响。
具体实施方式
本发明更换老旧隔离开关时基础不停电施工方法,包括如下步骤:
1)在设备运行不停电的状态下,在不损害原有基础及基础上方的水泥柱的情况下,进行人工开挖,开挖至原基础外露,同时支设模板;
2)在原水泥柱位于地面的高度预埋设置U型钢板和地脚螺栓;
3)对支护好的模板和预埋的U型钢板和地脚螺栓进行混凝土浇筑作为新隔离开关的独立基础;
4)在独立基础养护期间做好停电前的准备工作;
5)待批准停电后,首先截断独立基础外露的水泥杆部分,将新隔离开关及钢支架与独立基础上方的地脚螺栓固定,安装调试完成后即完成整个施工过程。
所述的U型钢板圆心直径大于水泥杆直径,所述的地脚螺栓设置在U型钢板上,所述的地脚螺栓孔距与新隔离开关钢支架底板上的地脚螺栓间距一致。
所述的独立基础成型后的混凝土养护,在强度达到100%后方可以截断原有水泥杆。
上面对本发明的实施例作了详细说明,但是本发明并不限于上述实施例,在本领域普通技术人员所具备的知识范围内,还可以在不脱离本发明宗旨的前提下作出各种变化。
Claims (3)
1.更换老旧隔离开关时基础不停电施工方法,其特征在于,包括如下步骤:
1)在设备运行不停电的状态下,在不损害原有基础及基础上方的水泥柱的情况下,进行人工开挖,开挖至原基础外露,同时支设模板;
2)在原水泥柱位于地面的高度预埋设置U型钢板和地脚螺栓;
3)对支护好的模板和预埋的U型钢板和地脚螺栓进行混凝土浇筑作为新隔离开关的独立基础;
4)在独立基础养护期间做好停电前的准备工作;
5)待批准停电后,首先截断独立基础外露的水泥杆部分,将新隔离开关及钢支架与独立基础上方的地脚螺栓固定,安装调试完成后即完成整个施工过程。
2.根据权利要求1所述的更换老旧隔离开关时基础不停电施工方法,其特征在于:所述的U型钢板圆心直径大于水泥杆直径,所述的地脚螺栓设置在U型钢板上,所述的地脚螺栓孔距与新隔离开关钢支架底板上的地脚螺栓间距一致。
3.根据权利要求1所述的更换老旧隔离开关时基础不停电施工方法,其特征在于:所述的独立基础成型后的混凝土养护,在强度达到100%后方可以截断原有水泥杆。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810393198.2A CN108643216B (zh) | 2018-04-27 | 2018-04-27 | 更换老旧隔离开关时基础不停电施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810393198.2A CN108643216B (zh) | 2018-04-27 | 2018-04-27 | 更换老旧隔离开关时基础不停电施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108643216A true CN108643216A (zh) | 2018-10-12 |
CN108643216B CN108643216B (zh) | 2020-07-28 |
Family
ID=63747924
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810393198.2A Active CN108643216B (zh) | 2018-04-27 | 2018-04-27 | 更换老旧隔离开关时基础不停电施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108643216B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112202097A (zh) * | 2020-10-30 | 2021-01-08 | 国网河南省电力公司南阳供电公司 | 一种sw型断路器更换为lw型断路器的快速施工方法 |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1014035A (ja) * | 1996-06-25 | 1998-01-16 | Toshiba Corp | ガス遮断器の据付装置 |
EP1936071A1 (fr) * | 2006-12-18 | 2008-06-25 | Transel etude de construction de lignes de transport d'energie electrique | Procédé de remplacement d'un poteau et installation comprenant un poteau |
CN101358454A (zh) * | 2008-08-25 | 2009-02-04 | 淄博供电公司 | 220kv耐张原杆位更换角钢塔基础的施工方法 |
CN102097243A (zh) * | 2009-12-14 | 2011-06-15 | 绥化电业局 | 一种sf6气体断路器的安装方法 |
CN102403662A (zh) * | 2011-11-10 | 2012-04-04 | 沧州供电公司 | 一种断路器基础快速更换方法 |
CN104078868A (zh) * | 2014-07-10 | 2014-10-01 | 国家电网公司 | 更换隔离开关时基础改造施工方法 |
CN104453273A (zh) * | 2014-11-09 | 2015-03-25 | 淄博夸克医药技术有限公司 | 一种多领域完善的断路器基础的快速更换方法 |
CN104821497A (zh) * | 2015-04-16 | 2015-08-05 | 国家电网公司 | 一种旧断路器更换成新断路器用基础 |
-
2018
- 2018-04-27 CN CN201810393198.2A patent/CN108643216B/zh active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1014035A (ja) * | 1996-06-25 | 1998-01-16 | Toshiba Corp | ガス遮断器の据付装置 |
EP1936071A1 (fr) * | 2006-12-18 | 2008-06-25 | Transel etude de construction de lignes de transport d'energie electrique | Procédé de remplacement d'un poteau et installation comprenant un poteau |
CN101358454A (zh) * | 2008-08-25 | 2009-02-04 | 淄博供电公司 | 220kv耐张原杆位更换角钢塔基础的施工方法 |
CN102097243A (zh) * | 2009-12-14 | 2011-06-15 | 绥化电业局 | 一种sf6气体断路器的安装方法 |
CN102403662A (zh) * | 2011-11-10 | 2012-04-04 | 沧州供电公司 | 一种断路器基础快速更换方法 |
CN104078868A (zh) * | 2014-07-10 | 2014-10-01 | 国家电网公司 | 更换隔离开关时基础改造施工方法 |
CN104453273A (zh) * | 2014-11-09 | 2015-03-25 | 淄博夸克医药技术有限公司 | 一种多领域完善的断路器基础的快速更换方法 |
CN104821497A (zh) * | 2015-04-16 | 2015-08-05 | 国家电网公司 | 一种旧断路器更换成新断路器用基础 |
Also Published As
Publication number | Publication date |
---|---|
CN108643216B (zh) | 2020-07-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101864963B (zh) | 一种大断面黄土隧道施工方法 | |
CN103046933B (zh) | 一种盾构过站掘进与车站平行施工方法 | |
CN102305077A (zh) | 一种大断面连拱隧道的快速施工方法 | |
CN103225422B (zh) | 采用轻钢结构直接加层技术的既有砌体结构及其施工方法 | |
CN107989620B (zh) | 一种三洞小间距隧道的施工方法 | |
CN105297766A (zh) | 可更换式预应力锚栓风机基础 | |
CN109667587A (zh) | 采用预制装配仰拱的钻爆法隧道结构 | |
CN105350987A (zh) | 一种用于矿挖法台车上预埋槽道固定安装结构及方法 | |
CN108643216A (zh) | 更换老旧隔离开关时基础不停电施工方法 | |
CN205000979U (zh) | 一种隧道拱部钢拱架顶升支撑装置 | |
CN101294388B (zh) | 用于超大面积深基坑的支撑局部早拆施工方法 | |
CN203188229U (zh) | 一种铁塔底脚螺栓锚固装置 | |
CN205205849U (zh) | 可更换式预应力锚栓风机基础 | |
CN205172592U (zh) | 一种用于矿挖法台车上预埋槽道固定安装的结构 | |
CN208870051U (zh) | 一种超深竖井基坑的支撑体系 | |
CN207619987U (zh) | 一种环保型地下车库的预制式基坑围护结构 | |
CN109930610A (zh) | 受限环境基坑采用混凝土加钢管混合斜撑支护的施工方法 | |
CN107401142B (zh) | 现役驳坎护岸墙加高施工方法 | |
CN108035380A (zh) | 一种支吊架预埋组件及其预埋安装施工方法 | |
CN1485498A (zh) | 槽形梁预制节段纵向拼装的施工方法 | |
CN208267393U (zh) | 一种电气线管一次预留预埋成品保护装置 | |
CN207775931U (zh) | 一种支吊架预埋组件 | |
CN204738818U (zh) | 一种电缆隧道带电运行套设内衬加固结构 | |
CN206902719U (zh) | 预拼装支撑梁组合支撑体系 | |
CN206887746U (zh) | 一种混凝土圆柱墩系梁逆序施工用圆柱模板 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |