CN103225422B - 采用轻钢结构直接加层技术的既有砌体结构及其施工方法 - Google Patents
采用轻钢结构直接加层技术的既有砌体结构及其施工方法 Download PDFInfo
- Publication number
- CN103225422B CN103225422B CN201310127584.4A CN201310127584A CN103225422B CN 103225422 B CN103225422 B CN 103225422B CN 201310127584 A CN201310127584 A CN 201310127584A CN 103225422 B CN103225422 B CN 103225422B
- Authority
- CN
- China
- Prior art keywords
- steel
- masonry structure
- newly
- roof
- existing masonry
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 124
- 239000010959 steel Substances 0.000 title claims abstract description 124
- 238000010276 construction Methods 0.000 title claims abstract description 83
- 238000005516 engineering process Methods 0.000 title claims abstract description 28
- 230000002787 reinforcement Effects 0.000 claims abstract description 49
- 239000000725 suspension Substances 0.000 claims description 25
- 230000003014 reinforcing effect Effects 0.000 claims description 24
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 6
- 239000004568 cement Substances 0.000 claims description 3
- 238000002513 implantation Methods 0.000 claims description 3
- 238000009434 installation Methods 0.000 claims description 3
- 229910052742 iron Inorganic materials 0.000 claims description 3
- 230000008901 benefit Effects 0.000 abstract description 5
- 238000004078 waterproofing Methods 0.000 abstract 1
- 239000000463 material Substances 0.000 description 3
- 230000009466 transformation Effects 0.000 description 3
- 230000001154 acute effect Effects 0.000 description 2
- 239000003795 chemical substances by application Substances 0.000 description 2
- 238000011161 development Methods 0.000 description 2
- 230000018109 developmental process Effects 0.000 description 2
- 238000005265 energy consumption Methods 0.000 description 2
- 239000007943 implant Substances 0.000 description 2
- 239000000126 substance Substances 0.000 description 2
- 230000032683 aging Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000007596 consolidation process Methods 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 239000012467 final product Substances 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 231100000252 nontoxic Toxicity 0.000 description 1
- 230000003000 nontoxic effect Effects 0.000 description 1
- 239000000843 powder Substances 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 238000012797 qualification Methods 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 238000009418 renovation Methods 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 230000035882 stress Effects 0.000 description 1
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
Description
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310127584.4A CN103225422B (zh) | 2013-04-10 | 2013-04-10 | 采用轻钢结构直接加层技术的既有砌体结构及其施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310127584.4A CN103225422B (zh) | 2013-04-10 | 2013-04-10 | 采用轻钢结构直接加层技术的既有砌体结构及其施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103225422A CN103225422A (zh) | 2013-07-31 |
CN103225422B true CN103225422B (zh) | 2015-07-01 |
Family
ID=48836044
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310127584.4A Active CN103225422B (zh) | 2013-04-10 | 2013-04-10 | 采用轻钢结构直接加层技术的既有砌体结构及其施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103225422B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106121267A (zh) * | 2016-07-20 | 2016-11-16 | 邱炎新 | 变电站集中检修仓储库房施工方法 |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103669598B (zh) * | 2013-12-30 | 2015-12-02 | 安徽天筑建设(集团)有限公司 | 一种多层混凝土框架结构顶部的加层钢框架柱脚节点的施工方法 |
CN103726669B (zh) * | 2013-12-31 | 2016-03-02 | 江苏建筑职业技术学院 | 采用钢筋混凝土板在原有建筑物上增加隔层的方法 |
CN103981955B (zh) * | 2014-06-03 | 2016-08-17 | 上海域邦建设工程有限公司 | 用于新老建筑柱顶、柱脚对接的对接装置及对接方法 |
CN104775631A (zh) * | 2015-02-16 | 2015-07-15 | 中交一航局第一工程有限公司 | 一种后增混凝土立柱施工方法 |
CN106567554A (zh) * | 2016-10-19 | 2017-04-19 | 北京城建北方建设有限责任公司 | 砌体结构建筑物的加固施工方法 |
CN110984211A (zh) * | 2019-12-12 | 2020-04-10 | 西安长庆科技工程有限责任公司 | 一种利用已建人防节点的铰接柱脚结构及构造方法 |
CN111472503B (zh) * | 2020-04-16 | 2021-07-20 | 南京大学建筑规划设计研究院有限公司 | 一种既有建筑屋顶隔音屏结构及施工方法 |
CN114293802B (zh) * | 2021-12-22 | 2023-06-09 | 上海建工二建集团有限公司 | 既有建筑墙体单面加固体系及施工方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3921362A (en) * | 1974-03-18 | 1975-11-25 | Pablo Cortina Ortega | Method of and means for multi-story building construction |
CN102587684A (zh) * | 2011-12-31 | 2012-07-18 | 北京筑福建设工程有限责任公司 | 既有框架建筑采用并联隔震支座加固的安装托换方法 |
CN203201172U (zh) * | 2013-04-10 | 2013-09-18 | 北京筑福建设工程有限责任公司 | 采用轻钢结构直接加层技术的既有砌体结构 |
-
2013
- 2013-04-10 CN CN201310127584.4A patent/CN103225422B/zh active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3921362A (en) * | 1974-03-18 | 1975-11-25 | Pablo Cortina Ortega | Method of and means for multi-story building construction |
CN102587684A (zh) * | 2011-12-31 | 2012-07-18 | 北京筑福建设工程有限责任公司 | 既有框架建筑采用并联隔震支座加固的安装托换方法 |
CN203201172U (zh) * | 2013-04-10 | 2013-09-18 | 北京筑福建设工程有限责任公司 | 采用轻钢结构直接加层技术的既有砌体结构 |
Non-Patent Citations (2)
Title |
---|
既有建筑顶部钢结构加层的结构设计;张涛;《中国优秀硕士学士论文全文数据库》;20070415(第4期);C038-90 * |
轻钢加层引起的下部砖混结构加固与设计;张涛;《低温建筑技术》;20050628(第3期);第32-34页 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106121267A (zh) * | 2016-07-20 | 2016-11-16 | 邱炎新 | 变电站集中检修仓储库房施工方法 |
CN106121267B (zh) * | 2016-07-20 | 2018-11-16 | 江苏源清环保科技有限公司 | 变电站集中检修仓储库房施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN103225422A (zh) | 2013-07-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103225422B (zh) | 采用轻钢结构直接加层技术的既有砌体结构及其施工方法 | |
CN103924711B (zh) | 装配式网格剪力墙结构体系的施工工艺 | |
Reddy | Sustainable building technologies | |
CN101914925B (zh) | 利用优化复合预制拱墙作外墙的地下室 | |
US7882669B2 (en) | Composite concrete shear wall for heat insulation | |
CN102251607B (zh) | 钢筋混凝土叠合墙体节点连接结构及施工方法 | |
CN103397660B (zh) | 一种地下建筑的装配施工方法 | |
CN104895089B (zh) | 地下室楼板与支护桩共同工作的永久支护体系的施工方法 | |
CN103993679B (zh) | 低层装配式复合墙体房屋螺栓连接节点结构 | |
CN207211428U (zh) | 一种装配式剪力墙板及其墙板连接构造 | |
CN202945622U (zh) | 一种地下室钢筋混凝土底板裂缝的复合修补结构 | |
CN101424106A (zh) | 钢板再生混合墙及其施工方法 | |
CN106149937B (zh) | 装配式混凝土梁及其干式连接方法 | |
CN207776149U (zh) | 一种预制钢管混凝土边框剪力墙 | |
CN107605065A (zh) | 一种装配式剪力墙板、墙板连接构造及其施工方法 | |
CN104947684B (zh) | 一种基于装配式可回收工艺土钉墙支护的施工方法 | |
CN101418569A (zh) | 预制拱片、支护与主体结构结合的优化复合拱墙 | |
CN108589982A (zh) | 一种基于钢筋间接焊接连接的装配式复合墙结构及其施工方法 | |
CN104818728A (zh) | 一种地下室楼板与支护桩共同工作的永久支护体系 | |
CN104790675A (zh) | 一种配筋砌块砌体结构装配化施工方法 | |
CN105714678A (zh) | 一种复合式重力锚碇 | |
CN203201172U (zh) | 采用轻钢结构直接加层技术的既有砌体结构 | |
CN211115052U (zh) | 一种井筒式地下立体车库结构 | |
CN211689844U (zh) | 一种利用高强灌浆料的波纹钢加强拱 | |
CN104947662A (zh) | 一种基于装配式可回收工艺的土钉墙支护体系 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
ASS | Succession or assignment of patent right |
Owner name: BEIJING BLESS BUILDING CO., LTD. Free format text: FORMER OWNER: BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY CO., LTD. Effective date: 20150728 |
|
C41 | Transfer of patent application or patent right or utility model | ||
TR01 | Transfer of patent right |
Effective date of registration: 20150728 Address after: 100043 Shijingshan District, Yang Yang Street, No. 69, No. 1, building an international Park, Fu International Patentee after: Beijing Bless Building Co., Ltd. Address before: 100043, Beijing, Shijingshan District, 166 Fu Shi Road, 2 floor, Chak Yang Building Patentee before: Beijing Aeido International Engineering Technology Co., Ltd. |
|
TR01 | Transfer of patent right |
Effective date of registration: 20171201 Address after: 225300 Jiangsu province Taizhou High Port District Xu Zhuang Street Qiao Yang Community Patentee after: Beijing Yong Bo Science and Technology Ltd. Address before: 100043 Shijingshan District, Yang Yang Street, No. 69, No. 1, building an international Park, Fu International Patentee before: Beijing Bless Building Co., Ltd. |
|
TR01 | Transfer of patent right | ||
CB03 | Change of inventor or designer information |
Inventor after: Peng Dehuang Inventor before: Dong You Inventor before: Ju Shusen Inventor before: Xie Jianming Inventor before: Wan Zhao |
|
CB03 | Change of inventor or designer information | ||
TR01 | Transfer of patent right |
Effective date of registration: 20180129 Address after: 517400 A of S3 massif in side Tangtong District of Linjiang Zhendong Ring Road in Jiangdong new area, Heyuan, Guangdong Patentee after: Heyuan guest Assembly Building Co., Ltd. Address before: 225300 Jiangsu province Taizhou High Port District Xu Zhuang Street Qiao Yang Community Patentee before: Beijing Yong Bo Science and Technology Ltd. |
|
TR01 | Transfer of patent right |