CN101864963B - 一种大断面黄土隧道施工方法 - Google Patents

一种大断面黄土隧道施工方法 Download PDF

Info

Publication number
CN101864963B
CN101864963B CN 201010184783 CN201010184783A CN101864963B CN 101864963 B CN101864963 B CN 101864963B CN 201010184783 CN201010184783 CN 201010184783 CN 201010184783 A CN201010184783 A CN 201010184783A CN 101864963 B CN101864963 B CN 101864963B
Authority
CN
China
Prior art keywords
excavation
concrete
tunnel
construction
inverted arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 201010184783
Other languages
English (en)
Other versions
CN101864963A (zh
Inventor
丁维军
李治强
董凤杰
朱华平
黎龙强
樊建国
周川岭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd
Original Assignee
Third Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd filed Critical Third Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd
Priority to CN 201010184783 priority Critical patent/CN101864963B/zh
Publication of CN101864963A publication Critical patent/CN101864963A/zh
Application granted granted Critical
Publication of CN101864963B publication Critical patent/CN101864963B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明公开了一种大断面黄土隧道施工方法,首先将整个断面分成上部、中部、下部以及底部四部分,其中,中部又分为中部左侧区域、中部右侧区域和中部中间区域,下部也分为下部左侧区域、下部右侧区域和下部中间区域,对这四部分进行台阶法错台开挖,开挖过程中,上部超前中部3~5m,中部超前下部3~5m,下部超前底部10m,逐级掘进开挖。本发明适合湿陷性黄土地区,施工安全可靠,且节省了大量的临时支撑钢架,由于弧形导坑法开挖尽快成环,对围岩扰动小,初期支护稳固,将传统施工方法进一步改进为“两台阶四部开挖法”,施工循环时间短,可以加快工程进度,缩短工期,降低工程费用。

Description

一种大断面黄土隧道施工方法
技术领域
本发明涉及一种隧道的开挖施工方法,尤其涉及一种大断面黄土隧道施工方法。
背景技术
随着我国高速铁路建设的进行,大断面铁路隧道施工全面展开,其特点是开挖断面大,因而施工难度大为增加,尤其是在湿陷性黄土地区,修建大断面客运专线隧道是隧道施工的一个难题。而现有技术中,有十一部法、九部法、以及六部法,然后采用多台阶分部开挖,但因分块较多,所需临时支撑较多,施工成本投入较大,同时造成各步序施工相互干扰较大,施工进度较慢。
发明内容
本发明的目的在于提供一种大断面黄土隧道施工方法,以解决现有技术施工复杂、进度缓慢以及成本较高的问题。
为了实现上述目的,本发明采用的技术方案是这样的:一种大断面黄土隧道施工方法,将整个断面分成上部、中部、下部以及底部四部分,其中,中部又分为中部左侧区域、中部右侧区域和中部中间区域,下部也分为下部左侧区域、下部右侧区域和下部中间区域,对这四部分进行台阶法错台开挖,开挖过程中,上部超前中部3~5m,中部超前下部3~5m,下部超前底部10m,逐级掘进开挖,对各部按如下步骤进行:
第一步:上部环行开挖、出碴及上部初期支护:
首先对上部区域进行超前支护,然后采用弧形导坑法对上部区域进行环形开挖,开挖后立即对上部区域初喷4cm厚混凝土和架立型钢钢架,并钻设锁脚锚管,钻设径向锚杆后复喷混凝土至设计厚度;
第二步:中部及下部开挖、出碴及其初期支护:
依次开挖中部左侧区域、下部左侧区域,中部右侧区域、下部右侧区域,两侧区域采用左右错台开挖,开挖后均初喷4cm厚混凝土并接长型钢钢架,钻设锁脚锚管,并在底部钢架基础垫设槽钢或混凝土垫块,钻设径向锚杆后复喷混凝土至设计厚度,最后开挖中部中间区域和下部中间区域,即预留核心土开挖;
第三步:底部开挖、出碴及底部初期支护:
开挖隧底剩余部分,并施工初喷4cm混凝土及隧底钢架,使支护体系及时封闭成环;
第四步:按照上述步骤循环开挖,直到隧道完成;
最后:进行仰拱衬砌及仰拱填充施工,完成后进行二衬施工。
更进一步地,上、中两部每循环进尺为0.8m,下部利用上部超前支护作业的时间一次进尺1.6m,底部在上部进行超前支护时进行开挖,一次开挖长度为3~6m。
更进一步地,利用仰拱栈桥灌筑边墙基础和拱部以及隧底填充混凝土,仰拱每部分6米施工,在隧底初期支护施工完成后,绑扎仰拱钢筋,安装仰拱环向止水带、纵向止水带,浇筑仰拱混凝土,仰拱施工完后安装填充挡头板,浇筑填充混凝土。
与现有技术相比,本发明的优点在于:
1、适合湿陷性黄土地区,采用弧形导坑法施工,施工安全可靠,且节省了大量的水平、竖向、斜向的临时支撑钢架,每米节约型钢约1.9t;
2、工程质量可靠,由于弧形导坑法开挖尽快成环,对围岩扰动小,初期支护稳固,与二次衬砌结合紧密;
3、将传统施工方法进一步改进为“两台阶四部开挖法”,施工循环时间短,可以加快工程进度,缩短工期,降低工程费用。
附图说明
图1为本发明施工工序图。
具体实施方式
下面将结合附图对本发明作进一步说明。
实施例:参见图1,本发明首先将整个断面分成上部1、中部、下部以及底部四部分,其中,中部又分为中部左侧区域2、中部右侧区域4和中部中间区域6,下部也分为下部左侧区域3、下部右侧区域5和下部中间区域7,对这四部分进行台阶法错台开挖,开挖过程中,上部1超前中部3~5m,中部超前下部3~5m,下部超前底部8的长度为10m,逐级掘进开挖,对各部按如下步骤进行:
第一步:上部1环行开挖、出碴及上部1初期支护:
首先对上部1区域进行超前支护,然后采用弧形导坑法对上部1区域进行环形开挖,开挖后立即对上部1区域初喷4cm厚混凝土和架立型钢钢架,并钻设锁脚锚管,钻设径向锚杆后复喷混凝土至设计厚度;
第二步:中部及下部开挖、出碴及其初期支护:
依次开挖中部左侧区域2、下部左侧区域3,中部右侧区域4、下部右侧区5域,其中,两侧区域采用左右错台开挖,开挖过程中保持左右错开3m,开挖后均初喷4cm厚混凝土并接长型钢钢架,钻设锁脚锚管,并在底部钢架基础垫设槽钢或混凝土垫块,钻设径向锚杆后复喷混凝土至设计厚度,最后开挖中部中间区域6和下部中间区域7,即预留核心土开挖;
第三步:底部8开挖、出碴及底部8初期支护:
开挖隧底剩余部分,并施工初喷4cm混凝土及隧底钢架,使支护体系及时封闭成环;其中,底部8采用全幅分段施工,并在上面铺设栈桥;
第四步:按照上述步骤循环开挖,直到隧道完成;其中,上、中两部每循环进尺为0.8m,下部利用上部1超前支护作业的时间一次进尺1.6m,底部8在上部1进行超前支护时进行开挖,一次开挖长度为3~6m。
最后:进行仰拱衬砌及仰拱填充施工,完成后进行二衬施工;利用仰拱栈桥灌筑边墙基础和拱部以及隧底填充混凝土,仰拱每部分6米施工,在隧底初期支护施工完成后,绑扎仰拱钢筋,安装仰拱环向止水带、纵向止水带,浇筑仰拱混凝土,仰拱施工完后安装填充挡头板,浇筑填充混凝土,最后进行二衬,二衬利用衬砌模板台车一次性衬砌边墙和拱部。
本发明适合湿陷性黄土地区,采用弧形导坑法施工,施工安全可靠,且节省了大量的水平、竖向、斜向的临时支撑钢架,每米节约型钢约1.9t;工程质量可靠,由于弧形导坑法开挖尽快成环,对围岩扰动小,初期支护稳固,与二次衬砌结合紧密;将传统施工方法进一步改进为“两台阶四部开挖法”,施工循环时间短,可以加快工程进度,缩短工期,降低工程费用。

Claims (3)

1.一种大断面黄土隧道施工方法,其特征在于:将整个断面分成上部、中部、下部以及底部四部分,其中,中部又分为中部左侧区域、中部右侧区域和中部中间区域,下部也分为下部左侧区域、下部右侧区域和下部中间区域,对这四部分进行台阶法错台开挖,开挖过程中,上部超前中部3~5m,中部超前下部3~5m,下部超前底部10m,逐级掘进开挖,对各部按如下步骤进行:
第一步:上部环行开挖、出碴及上部初期支护:
首先对上部区域进行超前支护,然后采用弧形导坑法对上部区域进行环形开挖,开挖后立即对上部区域初喷4cm厚混凝土和架立型钢钢架,并钻设锁脚锚管,钻设径向锚杆后复喷混凝土至设计厚度;
第二步:中部及下部开挖、出碴及其初期支护:
依次开挖中部左侧区域、下部左侧区域,中部右侧区域、下部右侧区域,两侧区域采用左右错台开挖,开挖后均初喷4cm厚混凝土并接长型钢钢架,钻设锁脚锚管,并在底部钢架基础垫设槽钢或混凝土垫块,钻设径向锚杆后复喷混凝土至设计厚度,最后开挖中部中间区域和下部中间区域,预留核心土开挖;
第三步:底部开挖、出碴及底部初期支护:
开挖隧底剩余部分,并施工初喷4cm混凝土及隧底钢架,使支护体系及时封闭成环;
第四步:按照上述步骤循环开挖,直到隧道完成;
最后:进行仰拱衬砌及仰拱填充施工,完成后进行二衬施工。
2.根据权利要求1所述的一种大断面黄土隧道施工方法,其特征在于:上、中两部每循环进尺为0.8m,下部利用上部超前支护作业的时间一次进尺1.6m,底部在上部进行超前支护时进行开挖,一次开挖长度为3~6m。
3.根据权利要求1所述的一种大断面黄土隧道施工方法,其特征在于:利用仰拱栈桥灌筑边墙基础和拱部以及隧底填充混凝土,仰拱每部分6米施工,在隧底初期支护施工完成后,绑扎仰拱钢筋,安装仰拱环向止水带、纵向止水带,浇筑仰拱混凝土,仰拱施工完后安装填充挡头板,浇筑填充混凝土。
CN 201010184783 2010-05-26 2010-05-26 一种大断面黄土隧道施工方法 Active CN101864963B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010184783 CN101864963B (zh) 2010-05-26 2010-05-26 一种大断面黄土隧道施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010184783 CN101864963B (zh) 2010-05-26 2010-05-26 一种大断面黄土隧道施工方法

Publications (2)

Publication Number Publication Date
CN101864963A CN101864963A (zh) 2010-10-20
CN101864963B true CN101864963B (zh) 2013-04-10

Family

ID=42956869

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010184783 Active CN101864963B (zh) 2010-05-26 2010-05-26 一种大断面黄土隧道施工方法

Country Status (1)

Country Link
CN (1) CN101864963B (zh)

Families Citing this family (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102071947B (zh) * 2011-01-21 2013-02-06 中交四航局第一工程有限公司 大跨度隧道洞口软弱围岩段施工方法
CN102140918A (zh) * 2011-04-01 2011-08-03 长安大学 黄土隧道的施工方法
CN102134998B (zh) * 2011-04-27 2012-11-07 中铁二局股份有限公司 一种风积沙隧道的施工方法
CN102383856A (zh) * 2011-07-12 2012-03-21 中铁隧道集团二处有限公司 大坡度平导施工运输方法
CN102392651B (zh) * 2011-11-30 2014-10-22 中铁五局(集团)有限公司 全风化花岗岩隧道开挖施工方法
CN102587924A (zh) * 2012-03-26 2012-07-18 中铁十三局集团第四工程有限公司 浅埋高含水量粘性土隧道施工方法
CN103244146A (zh) * 2013-05-14 2013-08-14 中铁二十一局集团第四工程有限公司 隧道锚喷支护钢架连接的施工方法
CN103410527B (zh) * 2013-08-29 2015-05-20 中南大学 围岩中含湿陷性黄土和软岩的隧道初期支护施工方法
CN103775094B (zh) * 2014-01-22 2015-12-30 安徽水安建设集团股份有限公司 砂砾土地层中型断面输水隧洞两台阶三步开挖施工方法
CN103775095B (zh) * 2014-02-26 2015-10-28 中铁第一勘察设计院集团有限公司 山岭软基隧道超前双导洞及其施工方法
CN104165056A (zh) * 2014-03-11 2014-11-26 中交一公局厦门工程有限公司 一种富水浅埋暗挖隧道的开挖施工方法
CN104047623B (zh) * 2014-06-06 2016-07-13 同济大学 一种大跨洞室开挖施工方法
CN104074524B (zh) * 2014-06-30 2016-03-16 中南大学 一种浅埋下穿高速公路大断面隧道的施工方法
CN105114098A (zh) * 2015-06-08 2015-12-02 中国电建集团贵阳勘测设计研究院有限公司 引水隧洞不良地质洞段处理方法及大直径引水隧洞结构
CN105298524A (zh) * 2015-09-14 2016-02-03 中铁二十五局集团第四工程有限公司 溶洞隧道初支变形加固方法
CN106246190B (zh) * 2016-08-12 2018-05-15 中铁二十局集团第四工程有限公司 一种隧道双侧壁九部导坑施工方法
CN106988757A (zh) * 2017-04-14 2017-07-28 中铁四局集团有限公司 预留岩柱及锚杆吊挂组合的双侧壁导坑施工工艺
CN107130967B (zh) * 2017-06-08 2019-01-01 重庆工程职业技术学院 特大断面深埋隧道及附属结构的施工方法
CN107560510A (zh) * 2017-08-25 2018-01-09 中铁十二局集团有限公司 一种隧道大断面段施工方法及其断面爆破布置
CN108286442B (zh) * 2018-01-08 2020-01-31 中铁十二局集团有限公司 适用于软弱围岩隧道两台阶一次快速封闭成环的开挖方法
CN108256243B (zh) * 2018-01-23 2021-02-26 成都希盟泰克科技发展有限公司 基于bim技术的隧道开挖两台阶方法
CN110630285A (zh) * 2019-10-08 2019-12-31 甘肃恒路交通勘察设计院有限公司 一种大断面软岩隧道锚索—钢架支护及施工方法
CN113417662B (zh) * 2021-08-06 2022-11-04 广东水电二局股份有限公司 一种隧洞开挖支护方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5090325A (en) * 1991-06-14 1992-02-25 Sato Kogyo Co., Ltd. Tunnel driving method
JP2002021467A (ja) * 2000-07-05 2002-01-23 Sato Kogyo Co Ltd トンネル掘削方法
CN101105131A (zh) * 2007-08-17 2008-01-16 中铁十二局集团有限公司 一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法
CN101614125A (zh) * 2009-07-23 2009-12-30 中铁九局集团有限公司 V级围岩隧道施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5090325A (en) * 1991-06-14 1992-02-25 Sato Kogyo Co., Ltd. Tunnel driving method
JP2002021467A (ja) * 2000-07-05 2002-01-23 Sato Kogyo Co Ltd トンネル掘削方法
CN101105131A (zh) * 2007-08-17 2008-01-16 中铁十二局集团有限公司 一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法
CN101614125A (zh) * 2009-07-23 2009-12-30 中铁九局集团有限公司 V级围岩隧道施工方法

Also Published As

Publication number Publication date
CN101864963A (zh) 2010-10-20

Similar Documents

Publication Publication Date Title
CN101864963B (zh) 一种大断面黄土隧道施工方法
CN106337686B (zh) 岩质地层暗挖三层地铁车站伞盖结构及施工方法
CN101614125B (zh) V级围岩隧道施工方法
CN104653197B (zh) 超大变断面隧道施工方法
CN102758632B (zh) 岩质地层双初支分层法修建大型地下结构的方法
CN105041349A (zh) 一种在地铁区间盾构隧道基础上扩挖车站的暗挖施工方法
CN105201516B (zh) 一种地铁车站主体结构及其四联拱pba暗挖施工方法
CN204729099U (zh) 岩质地层暗挖三层地铁车站伞盖结构
CN104405399A (zh) 一种穿越流沙地层隧道开挖支护体工法
CN105064397A (zh) 一种在地铁区间盾构隧道基础上扩挖车站的明挖施工方法
CN201991017U (zh) 基于拱盖法施工成型的地铁大跨度车站主体结构
CN102650212B (zh) 一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法
CN103244130A (zh) 人字形隧道断面快速挖扩施工方法
CN109707399B (zh) 隧道出洞支护构造及其施工方法
CN104405411B (zh) 超大变断面隧道支护结构
CN101539021B (zh) 公路隧道开挖方法
CN104947681A (zh) 一种超大超深地下室基坑的施工方法
CN113062354A (zh) 明挖桩撑体系预制装配式地铁车站拼装方法
CN203879506U (zh) 一种岩质地层大断面深竖井的支护结构体系
CN105089670A (zh) 一种在并行区间盾构隧道基础上扩挖地铁车站施工方法
CN109056810A (zh) 既有建筑下方明挖或盖挖地下主体结构的横向扩挖构造及其施工方法
CN205036380U (zh) 一种四联拱pba暗挖地铁车站主体结构
CN104120739A (zh) 一种多导洞开挖一次成拱的施工方法
CN205036388U (zh) 一种四联拱pba暗挖地铁车站的扣拱施工结构
CN218439399U (zh) 一种隧道仰拱施工用的辅助支撑装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant