CN108316313A - 基坑支护拆撑过程中汽车坡道换撑方法 - Google Patents
基坑支护拆撑过程中汽车坡道换撑方法 Download PDFInfo
- Publication number
- CN108316313A CN108316313A CN201810203117.8A CN201810203117A CN108316313A CN 108316313 A CN108316313 A CN 108316313A CN 201810203117 A CN201810203117 A CN 201810203117A CN 108316313 A CN108316313 A CN 108316313A
- Authority
- CN
- China
- Prior art keywords
- wall
- ramp
- basement
- steel pipe
- foundation pit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
本发明涉及一种基坑支护拆撑过程中汽车坡道换撑方法,包括步骤一:对地下室外墙和坡道侧壁进行钢筋绑扎;二:在地下室外墙和基坑支护墙体之间设置换撑结构钢筋施工;三:在地下室外墙和坡道侧壁内侧分别埋设钢板预埋件;四:对地下室外墙、坡道侧壁、换撑结构及楼板进行支模并浇筑混凝土;五:模板拆除后在每个钢板预埋件上左右两侧及下侧焊接钢板;六:准备钢管,钢管两侧上部焊接耳板;七:将钢管装到坡道中间,钢管两侧均卡在钢板预埋件上焊接的三块钢板中间;八:将三块钢板与钢管的接触面进行焊接。本发明施工速度快,减少最后的拆除和清理工序;钢管可回收利用,节约成本;加快施工进度,保证基坑安全,减少地下室外墙漏水。
Description
技术领域
本发明涉及一种汽车坡道换撑方法,具体的说是基坑支护拆撑过程中汽车坡道换撑方法。
背景技术
目前,混凝土内支撑体系因其对周边环境要求低、施工方便已越来越多应用在深基坑支护工程中,在地下室结构施工中,必须逐步拆除内支撑,为了保证基坑安全,必须通过换撑,对水平力进行转换后,方可进行支撑拆除。由于地下室坡道板为斜面,而地下室外侧每道换撑均与楼板中心对齐,支撑水平力传递到楼板上时,在坡道处不能有效的将水平力继续传递,特别是坡道侧壁与地下室外墙重合的情况下,如不采取措施,地下室外墙相当于悬臂结构,在上部水平力作用下,很可能出现裂缝导致外墙渗漏水。
发明内容
本发明旨在克服现有技术的缺陷,提供一种基坑支护拆撑过程中汽车坡道换撑方法,
为了解决上述技术问题,本发明是这样实现的:
一种基坑支护拆撑过程中汽车坡道换撑方法,其特征在于它包括如下步骤:
步骤一:对地下室外墙和坡道侧壁进行钢筋绑扎;
步骤二:在地下室外墙和基坑支护墙体之间设置换撑结构钢筋施工;
步骤三:在地下室外墙和坡道侧壁内侧分别埋设钢板预埋件,钢板预埋件间隔设置,与楼板中心线对齐,钢板预埋件上有九根锚筋穿孔塞焊;
步骤四:对地下室外墙、坡道侧壁、换撑结构及楼板进行支模并浇筑混凝土;
步骤五:模板拆除后,在每个钢板预埋件上左右两侧及下侧分别焊接钢板;
步骤六:在加工场准备钢管,钢管两侧上部分别焊接耳板,耳板上开孔;
步骤七:利用塔吊或吊车将钢管装到坡道中间,钢管两侧均卡在钢板预埋件上焊接的三块钢板中间;
步骤八:将三块钢板与钢管的接触面进行焊接。
所述的基坑支护拆撑过程中汽车坡道换撑方法,其特征在于:步骤一中所述的坡道侧壁为墙。
所述的基坑支护拆撑过程中汽车坡道换撑方法,其特征在于:步骤二中所述的换撑结构为换撑梁或换撑板,在基坑支护墙体上进行植筋。
所述的基坑支护拆撑过程中汽车坡道换撑方法,其特征在于:步骤三中所述的钢板预埋件每隔2000-2500mm设置一道。
本发明的有益效果是:在地下室外墙和坡道另一侧壁混凝土浇筑前,按照2m-2.5m一道齐平相应楼层板预埋500*500*15mm钢板埋件,结构施工完毕,进行换撑施工时,在坡道内采用Q345B钢管进行支撑,钢管与预埋件连接,将支护水平力通过钢管传递到楼板上,解决了坡道处基坑支护水平力无法传递的问题。
本发明施工简单、方便,简单易懂;相比采用混凝土结构换撑,施工速度快,减少最后的拆除和清理工序;钢管可回收利用,节约成本;加快施工进度,保证基坑安全,减少地下室外墙漏水。
附图说明
下面结合附图和实施方式对本发明作进一步的详细说明:
图1为本发明的结构示意图。
图2为钢板预埋件的结构示意图。
图3为图2的侧视图。
具体实施方式
如图1-3所示:一种基坑支护拆撑过程中汽车坡道换撑方法,它包括如下步骤:
步骤一:对地下室外墙1和坡道侧壁2进行钢筋绑扎;所述坡道侧壁为墙。
步骤二:在地下室外墙和基坑支护墙体3之间设置换撑结构4钢筋施工;所述的换撑结构为换撑梁或换撑板,如设计要求配置钢筋,需进行植筋到支护墙体上;
步骤三:在地下室外墙和坡道侧壁内侧分别埋设600*600*10mm钢板预埋件5,钢板预埋件每隔2000-2500mm设置一道,与楼板6中心线对齐,钢板预埋件上有九根20mm锚筋10穿孔塞焊;
步骤四:对地下室外墙、坡道侧壁、换撑结构及楼板进行支模并浇筑混凝土;
步骤五:模板拆除后,在每个钢板预埋件上左右两侧及下侧分别焊接钢板7;
步骤六:在加工场准备钢管8,钢管两侧上部分别焊接耳板9,耳板上开孔91作为吊点;
步骤七:利用塔吊或吊车将钢管装到坡道中间,钢管两侧均卡在钢板预埋件上焊接的三块钢板中间;
步骤八:将三块钢板与钢管的接触面进行焊接。
Claims (4)
1.一种基坑支护拆撑过程中汽车坡道换撑方法,其特征在于它包括如下步骤:
步骤一:对地下室外墙和坡道侧壁进行钢筋绑扎;
步骤二:在地下室外墙和基坑支护墙体之间设置换撑结构钢筋施工;
步骤三:在地下室外墙和坡道侧壁内侧分别埋设钢板预埋件,钢板预埋件间隔设置,与楼板中心线对齐,钢板预埋件上有九根锚筋穿孔塞焊;
步骤四:对地下室外墙、坡道侧壁、换撑结构及楼板进行支模并浇筑混凝土;
步骤五:模板拆除后,在每个钢板预埋件上左右两侧及下侧分别焊接钢板;
步骤六:在加工场准备钢管,钢管两侧上部分别焊接耳板,耳板上开孔;
步骤七:利用塔吊或吊车将钢管装到坡道中间,钢管两侧均卡在钢板预埋件上焊接的三块钢板中间;
步骤八:将三块钢板与钢管的接触面进行焊接。
2.根据权利要求1所述的基坑支护拆撑过程中汽车坡道换撑方法,其特征在于:步骤一中所述的坡道侧壁为墙。
3.根据权利要求1所述的基坑支护拆撑过程中汽车坡道换撑方法,其特征在于:步骤二中所述的换撑结构为换撑梁或换撑板,在基坑支护墙体上进行植筋。
4.根据权利要求1所述的基坑支护拆撑过程中汽车坡道换撑方法,其特征在于:步骤三中所述的钢板预埋件每隔2000-2500mm设置一道。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810203117.8A CN108316313A (zh) | 2018-03-13 | 2018-03-13 | 基坑支护拆撑过程中汽车坡道换撑方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810203117.8A CN108316313A (zh) | 2018-03-13 | 2018-03-13 | 基坑支护拆撑过程中汽车坡道换撑方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108316313A true CN108316313A (zh) | 2018-07-24 |
Family
ID=62901784
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810203117.8A Pending CN108316313A (zh) | 2018-03-13 | 2018-03-13 | 基坑支护拆撑过程中汽车坡道换撑方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108316313A (zh) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102720201A (zh) * | 2012-07-02 | 2012-10-10 | 中建三局第二建设工程有限责任公司 | 一种利用建筑物主体结构换撑施工的建造方法 |
CN103015432A (zh) * | 2012-12-07 | 2013-04-03 | 天津住宅集团建设工程总承包有限公司 | 一种坡道基坑钢管撑换撑施工方法 |
CN204570416U (zh) * | 2015-04-27 | 2015-08-19 | 中建三局第二建设工程有限责任公司 | 一种可拆卸式汽车坡道型钢换撑装置 |
CN206360431U (zh) * | 2017-01-03 | 2017-07-28 | 无锡市天宇民防建筑设计研究院有限公司 | 一种地下室汽车坡道 |
-
2018
- 2018-03-13 CN CN201810203117.8A patent/CN108316313A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102720201A (zh) * | 2012-07-02 | 2012-10-10 | 中建三局第二建设工程有限责任公司 | 一种利用建筑物主体结构换撑施工的建造方法 |
CN103015432A (zh) * | 2012-12-07 | 2013-04-03 | 天津住宅集团建设工程总承包有限公司 | 一种坡道基坑钢管撑换撑施工方法 |
CN204570416U (zh) * | 2015-04-27 | 2015-08-19 | 中建三局第二建设工程有限责任公司 | 一种可拆卸式汽车坡道型钢换撑装置 |
CN206360431U (zh) * | 2017-01-03 | 2017-07-28 | 无锡市天宇民防建筑设计研究院有限公司 | 一种地下室汽车坡道 |
Non-Patent Citations (2)
Title |
---|
冯云: "汽车坡道悬臂墙换撑施工技术", 《天津建设科技》 * |
刘训臣: "深基坑工程中支撑体系的换撑施工技术", 《南通职业大学学报》 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104746892B (zh) | 托梁拆墙装置及托梁拆墙施工方法 | |
CN104947681B (zh) | 一种超大超深地下室基坑的施工方法 | |
CN103669866B (zh) | 地下室钢筋混凝土柱节点连接结构的施工方法 | |
CN110331727B (zh) | 灌注桩和地下连续墙相结合的支护结构及施工方法 | |
CN103422674A (zh) | 装配式混凝土结构现浇段混凝土施工方法 | |
CN103643973A (zh) | 一种crd工法隧道防水施工方法 | |
CN206298900U (zh) | 一种地下连续墙预埋式钢围檩堵头体系 | |
CN104131704A (zh) | 一种钢管柱混凝土的侧浇方法及所用的钢管柱结构 | |
CN106150523A (zh) | 一种高速铁路隧道水沟电缆槽整体模板施工工法 | |
CN102518300B (zh) | 预埋锥形承载接头式钢结构支座及其施工方法 | |
CN107524461A (zh) | 一种提高隧道二次衬砌环向止水带防水效果的装置及方法 | |
CN110029674A (zh) | 一种用于深基坑的内支撑拆除及地下室施工方法 | |
CN103161155A (zh) | 沉管压灌桩专用桩机及其使用方法和应用 | |
CN204552136U (zh) | 托梁拆墙装置 | |
CN112431208A (zh) | 深基坑支护采用构件式传力带的施工方法 | |
CN103122642A (zh) | 一种竖向支柱换撑的施工方法 | |
CN108316313A (zh) | 基坑支护拆撑过程中汽车坡道换撑方法 | |
CN108457190A (zh) | 锚碇前锚室顶板施工方法 | |
CN207760803U (zh) | 一种预制双联型护面块体钢模板 | |
CN102061702A (zh) | 一种带有抗震槽的混凝土预制桩接头 | |
CN208472763U (zh) | 一种顶管施工用后背墙 | |
CN205711786U (zh) | 大断面多孔超长现浇箱涵支模体系 | |
CN108396961A (zh) | 一种双重墙间施工缝模板支设方法 | |
CN210622366U (zh) | 一种受损钢筋混凝土柱体的托换处理装置 | |
CN209479705U (zh) | 一种顶管施工管头加固用运输车 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180724 |