CN107152145A - A kind of stone material flooring construction method - Google Patents

A kind of stone material flooring construction method Download PDF

Info

Publication number
CN107152145A
CN107152145A CN201710421162.6A CN201710421162A CN107152145A CN 107152145 A CN107152145 A CN 107152145A CN 201710421162 A CN201710421162 A CN 201710421162A CN 107152145 A CN107152145 A CN 107152145A
Authority
CN
China
Prior art keywords
plate
stone material
stone
paving
skirting board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710421162.6A
Other languages
Chinese (zh)
Inventor
吴永乐
冯忠发
侯国栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin City Source Municipal Engineering Co Ltd
Original Assignee
Tianjin City Source Municipal Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin City Source Municipal Engineering Co Ltd filed Critical Tianjin City Source Municipal Engineering Co Ltd
Priority to CN201710421162.6A priority Critical patent/CN107152145A/en
Publication of CN107152145A publication Critical patent/CN107152145A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • E04F15/08Flooring or floor layers composed of a number of similar elements only of stone or stone-like material, e.g. ceramics, concrete; of glass or with a top layer of stone or stone-like material, e.g. ceramics, concrete or glass
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F19/00Other details of constructional parts for finishing work on buildings
    • E04F19/02Borders; Finishing strips, e.g. beadings; Light coves
    • E04F19/04Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F19/00Other details of constructional parts for finishing work on buildings
    • E04F19/02Borders; Finishing strips, e.g. beadings; Light coves
    • E04F19/04Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings
    • E04F19/0459Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings characterised by the fixing method
    • E04F19/0477Plinths fixed by means of adhesive
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F19/00Other details of constructional parts for finishing work on buildings
    • E04F19/02Borders; Finishing strips, e.g. beadings; Light coves
    • E04F19/04Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings
    • E04F2019/0404Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings characterised by the material
    • E04F2019/0418Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings characterised by the material of stone or stone like material, e.g. ceramics, concrete; of glass

Abstract

The invention discloses a kind of stone material flooring construction method, belong to the realm of building construction, its technical scheme is as follows, by preparation of construction, clear up basic unit, look for absolute altitude, snap the line, examination is spelled and examination row, paving screed-coat mortar, paving stone plate, the cementation of fissures, wiping seam, maintenance, patch skirting board, waxing are effectively constructed to stone material flooring, it is efficiently modified arrangement and method for construction, effect is connected with improving, the advantage of service life is improved.

Description

A kind of stone material flooring construction method
Technical field
The present invention relates to the realm of building construction, more particularly to a kind of stone material flooring construction method.
Background technology
Stone material flooring refers to the flooring that its surface material is done by stone material, and it is also belong to block flooring one Kind;The scope of block flooring is relatively wide, such as stone material, colored glaze floor tile, Anti-slid floor tile;Their main distinction is Block flooring be refer to and stone material, colored glaze floor tile, Anti-slid floor tile etc. general designation, and stone material flooring directly refers to its surface layer Material material therefor.
The today constantly lifted in current people's daily life level, decorated and selected in building now using stone material flooring Increasingly favored in selecting.
But stone material bottom plate and stone material skirting board installation effect are poor when the construction overall in construction at present, especially Stone material skirting board is larger due to weight itself, and due to stone material meta-alkalescence, causes connection effect poor, when connection effect is bad Very easy generation comes off, and causes stone material flooring using effect poor.
The content of the invention
It is an object of the invention to provide a kind of stone material flooring construction method, it, which has, improves integrated connection effect, improves The advantage of service life.
A kind of stone material flooring construction method, comprises the following steps:
Step one:Preparation of construction:Stone plate, building material, construction equipment, instrument processing prepare;
Step 2:Clear up basic unit:Substrate surface debris is cleared up, and skin patching is smooth;
Step 3:Look for absolute altitude, snap the line:Elevation line is introduced in from passageway unification toward each room, is played on room bed course orthogonal Control cross hairs, and lead to metope bottom, be used as check and control stone material Board position criterion;
Step 4:Examination is spelled and examination row:Examination spelling is carried out to the stone plate in each room before laying, and is numbered successively;
Step 5:Spread screed-coat mortar:Surface layer screed-coat thickness is made by horizontal line, cross hairs has been drawn, lay cement mortar levelling Layer;
Using 1:3 dry cement mortar, denseness until pinch agglomerating with hand, it is not loose untill;Watering moistening bed course, sweeps before paving The ratio of mud for 0.4~0.5 plain-water slurry once, then big thick stick is scraped after completing, is made real toward the mortar that paves at doorway from inner, use Trowel is levelling, and its thickness is higher by by the fixed 1~2mm of screed-coat thickness of horizontal line;
Step 6:Spread stone plate:First indulging paving and horizontal paving in room inwards from doorway by line position, several make standard, and then subregion is by row Row, line position are paved;
Step 7:The cementation of fissures, wiping seam:After plate has paved 1~2h start, first by the color of sheet material be tuned into white cement and pigment with Sheet material tone it is close 1:1 thin cement slurry, loading smallmouth kettle, which blows slowly, to be poured into the gap between plate, and the slurries flowed in tape edge are used In ox horn scraper feeding seam, untill full;
After 1~2h, then slurry wiping seam is dipped in cotton yarn group to plain smooth, the slurries sticked in plate face are cleaned with wet loose thread conveniently;
Joint gap the greater, first with 1:Then 1 cement mortar or fine sand joint filling reuse the water of same color to 2/3 thickness of slab Mud mill base is embedding to wipe closely knit, and cleans the mortar in plate face with wet loose thread;
Step 8:Maintenance:After the complete 24h of wiping seam of being in the milk, covered using the sawdust totally moistened, wet curing is no less than 7d;
Step 9:Paste skirting board:By the pre-brush water moistening of skirt back, dry;
The rendering layer of metope is struck off, until base putty layer, metope clean it up;
Strike off discharging base putty layer, it is ensured that the flatness of base putty layer surface;
Stone material skirting board and metope use structure glue, and structure glue thickness is slightly less than or equal to depth of plastering;
Between stone material skirting board, and between stone material skirting board and metope, marble glue is used;
Interim good support, supporting time at least 24 hours are fixed away from metope side to stone material skirting board;
Step 10:Waxing:When binder course strength of cement mortar reaches requirement, each procedure completion no longer upper people, waxed, Comprise the following steps:
Pickling is entered to stone plate, stone material skirting board;
To the stone plate after pickling, stone material skirting board, progress, which is dried, cleans;
Wax, kerosene are pressed 1:4 weight ratio is put into heating in bucket, melted at a temperature of 120~130 DEG C, after incorporation rosin It is tuned into scattered paste shape standby;
Wax is stained with cloth or clean flax silk and is evenly coated in stone plate, on stone material skirting board, after wax is dry, with being surrounded by burlap or fine canvas Wooden unit replace oilstone, polished on the mill of stone mill, until terrazzo surface it is smooth it is clean it is bright untill, strike-on of laying equal stress on Wax, polishing one time.
By using above-mentioned technical proposal, structure glue passes through mica to the good connecting effect of stone material during bonding Glue and outside are directly preliminary more than the progress of stone material skirting board to be connected, and enables structure glue to have longer time holding initial Connection status so that later stage structure glue solidification after can keep preferable connection status for a long time, effectively raise connection Effect, improve service life.
Further, step 2:The dust stratification of substrate surface, greasy dirt, laitance and debris are cleaned out, to local convex-concave not Prosposition is put, and by convex chipping, recess uses 1:3 mortar filling-in.
By using above-mentioned technical proposal, effectively scraggly position is quickly handled, it is overall without carrying out Whole reparations, improves the efficiency of construction.
Further, step 4:The gap between plate, verification plate and the phase at metope, post, hole etc. are examined in examination after spelling Mutual position, then the once row of being tried, spread dry sand band in room, and thickness is not less than 30mm, stone plate is sequenced, and examination is numbered after sequencing Pile up neatly, and remove abrasive band.
By using above-mentioned technical proposal, arrangement for the first time is effectively spliced into pattern by stone plate, effective to improve Aesthetic measure, and the modification in later stage is reduced, efficiency of construction is improved, and effectively marked, it is easy to later stage rearrangement, and again Carry out second to arrange, effective simulation concrete bonds the state after stone plate, be convenient for modification, improve construction effect.
Further, step 6:Paving before plate is soaked in advance dry in the shade after it is standby, by line position first from doorway inwards indulge paving with In room it is horizontal paving several make standard, then subregion by ranks, line position pave;When there is middle colonnade interior, first colonnade is completed, then Outwards laid along colonnade both sides;
Plate corner is lain on the levelling cement sand bed of dry completed simultaneously during paving, after first examination paving is suitable, plate is opened Block pours the plain-water slurry that one layer of ratio of mud is 0.5 in cement mortar, and plate is lightly then directed to original position and put down, rubber is used The sheeting caps that hammer or wooden mallet touch are put on plate makes plate plain, levelling with iron spirit level according to horizontal line, makes plate corner smooth, Opposite joint, to flower meet the requirements;After having spread, then spread to both sides and direction of retreat order edge, untill having spread, between stone plate Gap width be not more than 1mm.
By using above-mentioned technical proposal, the installation effect of stone plate is effectively raised, the flatness after construction is improved, Gap is reduced, the service life in later stage is improved.
Further, step 6:It was found that space, stone plate is started with row laying again after mortar mending reality.
By using above-mentioned technical proposal, the effective connection space for reducing stone plate, it is ensured that energy after stone plate is fixed There is good support, improve service life.
Further, step 9:When skirting board at external corner is at 45 ° intersecting, plate one end should be cut in a pre-installation at 45 ° Angle.
By using above-mentioned technical proposal, it is easy to the skirting board at balcony to be installed.
In summary, the invention has the advantages that:
1st, Optimizing Construction Scheme effectively raises the efficiency of construction;
2nd, stone plate and skirt board mounting structure firmly, stably, effectively improve service life;
Change, made up conveniently when the 3rd, constructing, improve efficiency of construction.
Brief description of the drawings
Fig. 1 is the construction process figure of the present embodiment.
Embodiment
The present invention is described in further detail below in conjunction with accompanying drawing.
A kind of stone material flooring construction method, comprises the following steps:
Step one:Preparation of construction:Stone plate, building material, construction equipment, instrument processing prepare, and are effectively easy to people to carry out The construction in later stage, improves efficiency of construction.
Step 2:Clear up basic unit:Substrate surface debris is cleared up, and skin patching is smooth, by the dust stratification of substrate surface, greasy dirt, Laitance and debris are cleaned out, and to local rough and uneven in surface position, by convex chipping, recess uses 1:3 mortar filling-in;
Effectively scraggly position is quickly handled, without carrying out overall whole reparation, the efficiency of construction is improved, Avoiding the surface of out-of-flatness causes stone plate installation unstable.
Step 3:Look for absolute altitude, snap the line:Elevation line is introduced in from passageway unification toward each room, bullet is mutual on room bed course Vertical control cross hairs, and metope bottom is led to, it is used as the criterion for checking and controlling stone material Board position.
Step 4:Examination is spelled and examination row:Examination spelling is carried out to the stone plate in each room before laying, and is numbered successively, just Arranged in design and later stage;
The gap between plate, verification plate and the mutual alignment at metope, post, hole etc. are examined in examination after spelling, then are once tried Row, the paving dry sand band in room, thickness is not less than 30mm, stone plate is sequenced, and numbering is piled up neatly after examination is sequenced, and removes sand Band;
Arrangement is effectively spliced into pattern by stone plate for the first time, effectively improves aesthetic measure, and the modification in reduction later stage, Efficiency of construction is improved, and is effectively marked, is easy to later stage rearrangement, and carries out second of arrangement, effective simulation again State after concrete binding stone plate, is convenient for modification, improves construction effect.
Step 5:Spread screed-coat mortar:Surface layer screed-coat thickness is made by horizontal line, cross hairs has been drawn, lay cement mortar Screed-coat.
Using 1:3 dry cement mortar, denseness until pinch agglomerating with hand, it is not loose untill;Watering moistening pad before paving Layer, was sweeping plain-water slurry that the ratio of mud is 0.4~0.5 once, then from inner toward the mortar that paves at doorway, big thick stick, bat is scraped after completing Real, levelling with trowel, its thickness is higher by by the fixed 1~2mm of screed-coat thickness of horizontal line;
Effectively raise levelling effect, it is ensured that surface can keep smooth when laying, be easy to stone plate effectively to be spread If improving the efficiency of construction in later stage.
Step 6:Spread stone plate:First indulging paving and horizontal paving in room inwards from doorway by line position, several make standard, and then subregion is pressed Ranks, line position are paved;
Paving before plate is soaked in advance dry in the shade after it is standby, by line position first from doorway inwards indulge paving and room in it is horizontal spread several make standard, Then subregion is paved by ranks, line position;When there is middle colonnade interior, first colonnade is completed, then outwards laid along colonnade both sides, Arranged by rule, be convenient for people to be arranged, improved arrangement efficiency, and also allow for people and changed in real time, improved Laying effect;
Plate corner is lain on the levelling cement sand bed of dry completed simultaneously during paving, after first examination paving is suitable, plate is opened Block pours the plain-water slurry that one layer of ratio of mud is 0.5 in cement mortar, and plate is lightly then directed to original position and put down, rubber is used The sheeting caps that hammer or wooden mallet touch are put on plate makes plate plain, levelling with iron spirit level according to horizontal line, makes plate corner smooth, Opposite joint, to flower meet the requirements;After having spread, then spread to both sides and direction of retreat order edge, untill having spread, between stone plate Gap width be not more than 1mm;
The installation effect of stone plate is effectively raised, the flatness after construction is improved, gap is reduced, the use longevity in later stage is improved Life;
It was found that space, stone plate is started with row laying again after mortar mending reality;
The effective connection space for reducing stone plate, it is ensured that stone plate can have good support after fixing, and improve and use the longevity Life.
Step 7:The cementation of fissures, wiping seam:Start after plate has paved 1~2h, first adjusted by the color white cement and pigment of sheet material Into close with sheet material tone 1:1 thin cement slurry, loading smallmouth kettle, which blows slowly, to be poured into the gap between plate, flows the slurry in tape edge Liquid is with ox horn scraper feeding seam, untill full;
After 1~2h, then slurry wiping seam is dipped in cotton yarn group to plain smooth, the slurries sticked in plate face are cleaned with wet loose thread conveniently;
Joint gap the greater, first with 1:Then 1 cement mortar or fine sand joint filling reuse the water of same color to 2/3 thickness of slab Mud mill base is embedding to wipe closely knit, and cleans the mortar in plate face with wet loose thread;
Ensure that the gap between stone plate keeps less situation, improve the effect of laying, improve service life, and it is also effective Improve effect attractive in appearance.
Step 8:Maintenance:After the complete 24h of wiping seam of being in the milk, covered using the sawdust totally moistened, wet curing is no less than 7d, Effective maintenance stone plate, improves laying effect.
Step 9:Paste skirting board:By the pre-brush water moistening of skirt back, dry;
The rendering layer of metope is struck off, until base putty layer, metope clean it up;
Strike off discharging base putty layer, it is ensured that the flatness of base putty layer surface;
Stone material skirting board and metope use structure glue, and structure glue thickness is slightly less than or equal to depth of plastering;
Between stone material skirting board, and between stone material skirting board and metope, marble glue is used;
Interim good support, supporting time at least 24 hours are fixed away from metope side to stone material skirting board;
Structure glue is directly more than stone material skirt during bonding to the good connecting effect of stone material by mica glue and outside Plate progress is preliminary to be connected, and enables structure glue to have longer time to keep initial connection status, so that in later stage structure Preferable connection status can be kept for a long time after gelling is solid, the effect of connection is effectively raised, and improve service life;
When skirting board at external corner is at 45 ° intersecting, plate one end should be cut into 45° angle in a pre-installation, be easy to the skirt at balcony Plate is installed.
Step 10:Waxing:When binder course strength of cement mortar reaches requirement, each procedure completion no longer upper people, carry out Waxing, comprises the following steps:
Pickling is entered to stone plate, stone material skirting board;
To the stone plate after pickling, stone material skirting board, progress, which is dried, is cleaned, and the effective alkaline environment for neutralizing stone plate is improved The service life in later stage, improves bond effect;
Wax, kerosene are pressed 1:4 weight ratio is put into heating in bucket, melted at a temperature of 120~130 DEG C, after incorporation rosin It is tuned into scattered paste shape standby;
Wax is stained with cloth or clean flax silk and is evenly coated in stone plate, on stone material skirting board, after wax is dry, with being surrounded by burlap or fine canvas Wooden unit replace oilstone, polished on the mill of stone mill, until terrazzo surface it is smooth it is clean it is bright untill, strike-on of laying equal stress on Wax, polishing one time, it is ensured that the finish of stone material plate surface, improve decorative effect.
This specific embodiment is only explanation of the invention, and it is not limitation of the present invention, people in the art Member can make the modification without creative contribution to the present embodiment as needed after this specification is read, but as long as at this All protected in the right of invention by Patent Law.

Claims (6)

1. a kind of stone material flooring construction method, it is characterized in that:Comprise the following steps:
Step one:Preparation of construction:Stone plate, building material, construction equipment, instrument processing prepare;
Step 2:Clear up basic unit:Substrate surface debris is cleared up, and skin patching is smooth;
Step 3:Look for absolute altitude, snap the line:Elevation line is introduced in from passageway unification toward each room, is played on room bed course orthogonal Control cross hairs, and lead to metope bottom, be used as check and control stone material Board position criterion;
Step 4:Examination is spelled and examination row:Examination spelling is carried out to the stone plate in each room before laying, and is numbered successively;
Step 5:Spread screed-coat mortar:Surface layer screed-coat thickness is made by horizontal line, cross hairs has been drawn, lay cement mortar levelling Layer;
Using 1:3 dry cement mortar, denseness until pinch agglomerating with hand, it is not loose untill;Watering moistening bed course, sweeps before paving The ratio of mud for 0.4~0.5 plain-water slurry once, then big thick stick is scraped after completing, is made real toward the mortar that paves at doorway from inner, use Trowel is levelling, and its thickness is higher by by the fixed 1~2mm of screed-coat thickness of horizontal line;
Step 6:Spread stone plate:First indulging paving and horizontal paving in room inwards from doorway by line position, several make standard, and then subregion is by row Row, line position are paved;
Step 7:The cementation of fissures, wiping seam:After plate has paved 1~2h start, first by the color of sheet material be tuned into white cement and pigment with Sheet material tone it is close 1:1 thin cement slurry, loading smallmouth kettle, which blows slowly, to be poured into the gap between plate, and the slurries flowed in tape edge are used In ox horn scraper feeding seam, untill full;
After 1~2h, then slurry wiping seam is dipped in cotton yarn group to plain smooth, the slurries sticked in plate face are cleaned with wet loose thread conveniently;
Joint gap the greater, first with 1:Then 1 cement mortar or fine sand joint filling reuse the water of same color to 2/3 thickness of slab Mud mill base is embedding to wipe closely knit, and cleans the mortar in plate face with wet loose thread;
Step 8:Maintenance:After the complete 24h of wiping seam of being in the milk, covered using the sawdust totally moistened, wet curing is no less than 7d;
Step 9:Paste skirting board:By the pre-brush water moistening of skirt back, dry;
The rendering layer of metope is struck off, until base putty layer, metope clean it up;
Strike off discharging base putty layer, it is ensured that the flatness of base putty layer surface;
Stone material skirting board and metope use structure glue, and structure glue thickness is slightly less than or equal to depth of plastering;
Between stone material skirting board, and between stone material skirting board and metope, marble glue is used;
Interim good support, supporting time at least 24 hours are fixed away from metope side to stone material skirting board;
Step 10:Waxing:When binder course strength of cement mortar reaches requirement, each procedure completion no longer upper people, waxed, Comprise the following steps:
Pickling is entered to stone plate, stone material skirting board;
To the stone plate after pickling, stone material skirting board, progress, which is dried, cleans;
Wax, kerosene are pressed 1:4 weight ratio is put into heating in bucket, melted at a temperature of 120~130 DEG C, after incorporation rosin It is tuned into scattered paste shape standby;
Wax is stained with cloth or clean flax silk and is evenly coated in stone plate, on stone material skirting board, after wax is dry, with being surrounded by burlap or fine canvas Wooden unit replace oilstone, polished on the mill of stone mill, until terrazzo surface it is smooth it is clean it is bright untill, strike-on of laying equal stress on Wax, polishing one time.
2. a kind of stone material flooring construction method according to claim 1, it is characterized in that:Step 2:By substrate surface Dust stratification, greasy dirt, laitance and debris are cleaned out, and to local rough and uneven in surface position, by convex chipping, recess uses 1:3 mortar filling-in.
3. a kind of stone material flooring construction method according to claim 2, it is characterized in that:Step 4:Inspection panel after examination is spelled Gap between block, verification plate and the mutual alignment at metope, post, hole etc., then the once row of being tried, spread dry sand in room Band, thickness is not less than 30mm, and stone plate is sequenced, and numbering is piled up neatly after examination is sequenced, and removes abrasive band.
4. a kind of stone material flooring construction method according to claim 3, it is characterized in that:Step 6:It is before paving that plate is pre- First soak it is standby after drying in the shade, by line position first from doorway inwards indulge paving and room in it is horizontal paving several make standard, then subregion press ranks, line Pave position;When there is middle colonnade interior, first colonnade is completed, then outwards laid along colonnade both sides;
Plate corner is lain on the levelling cement sand bed of dry completed simultaneously during paving, after first examination paving is suitable, plate is opened Block pours the plain-water slurry that one layer of ratio of mud is 0.5 in cement mortar, and plate is lightly then directed to original position and put down, rubber is used The sheeting caps that hammer or wooden mallet touch are put on plate makes plate plain, levelling with iron spirit level according to horizontal line, makes plate corner smooth, Opposite joint, to flower meet the requirements;After having spread, then spread to both sides and direction of retreat order edge, untill having spread, between stone plate Gap width be not more than 1mm.
5. a kind of stone material flooring construction method according to claim 4, it is characterized in that:Step 6:It was found that space, by stone Material plate is started with row laying again after mortar mending reality.
6. a kind of stone material flooring construction method according to claim 5, it is characterized in that:Step 9:Skirt at external corner When plate is at 45 ° intersecting, plate one end should be cut into 45° angle in a pre-installation.
CN201710421162.6A 2017-06-07 2017-06-07 A kind of stone material flooring construction method Pending CN107152145A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710421162.6A CN107152145A (en) 2017-06-07 2017-06-07 A kind of stone material flooring construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710421162.6A CN107152145A (en) 2017-06-07 2017-06-07 A kind of stone material flooring construction method

Publications (1)

Publication Number Publication Date
CN107152145A true CN107152145A (en) 2017-09-12

Family

ID=59794856

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710421162.6A Pending CN107152145A (en) 2017-06-07 2017-06-07 A kind of stone material flooring construction method

Country Status (1)

Country Link
CN (1) CN107152145A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107663053A (en) * 2017-10-24 2018-02-06 河北晨阳工贸集团有限公司 A kind of soft and graceful soft rock is attached to the construction technology in the decoration of flooring
CN107859283A (en) * 2017-10-11 2018-03-30 詹焕辉 A kind of building(Ground)The construction method of face skirting waterproof
CN108385932A (en) * 2018-03-09 2018-08-10 北京市建筑工程装饰集团有限公司 The laying method of macroplate stone material
CN109017109A (en) * 2018-07-27 2018-12-18 苏州金螳螂文化发展股份有限公司 A kind of water knife parquets board manufacturing method and water knife parquets pavement construction method
CN109826404A (en) * 2019-01-29 2019-05-31 台州铭星装饰工程股份有限公司 A kind of wall decoration technique
CN110130642A (en) * 2019-05-27 2019-08-16 西安市鑫龙建筑装饰工程(集团)有限公司 A kind of stone floor construction technology
CN111203987A (en) * 2020-01-20 2020-05-29 深圳市奇信集团股份有限公司 Stone floor construction method
CN113494163A (en) * 2021-07-29 2021-10-12 杭州良工装饰有限公司 Indoor ground construction method
CN113833230A (en) * 2021-10-18 2021-12-24 中国建筑第四工程局有限公司 Shale brick terrace construction process in koji making and fermentation room
CN114293733A (en) * 2021-12-07 2022-04-08 苏州金螳螂文化发展股份有限公司 Surface wax baking treatment process for decorative floor

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1093137A (en) * 1993-04-02 1994-10-05 王有忠 Flooring and polishing technology of granite and marble floor
CN102505831A (en) * 2011-12-22 2012-06-20 深圳市深装总装饰工程工业有限公司 Construction method for paving plasters on ground and manmade stone
CN104047410A (en) * 2014-06-11 2014-09-17 江南园林有限公司 Stone paving construction method
CN105178559A (en) * 2015-10-08 2015-12-23 哈尔滨世纪天诚装饰工程有限公司 Novel construction method for granite ground
CN106760366A (en) * 2016-11-11 2017-05-31 袁云秀 Based on the construction technology for improving marble hybrid procedure in furniture exhibition room

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1093137A (en) * 1993-04-02 1994-10-05 王有忠 Flooring and polishing technology of granite and marble floor
CN102505831A (en) * 2011-12-22 2012-06-20 深圳市深装总装饰工程工业有限公司 Construction method for paving plasters on ground and manmade stone
CN104047410A (en) * 2014-06-11 2014-09-17 江南园林有限公司 Stone paving construction method
CN105178559A (en) * 2015-10-08 2015-12-23 哈尔滨世纪天诚装饰工程有限公司 Novel construction method for granite ground
CN106760366A (en) * 2016-11-11 2017-05-31 袁云秀 Based on the construction technology for improving marble hybrid procedure in furniture exhibition room

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107859283A (en) * 2017-10-11 2018-03-30 詹焕辉 A kind of building(Ground)The construction method of face skirting waterproof
CN107663053A (en) * 2017-10-24 2018-02-06 河北晨阳工贸集团有限公司 A kind of soft and graceful soft rock is attached to the construction technology in the decoration of flooring
CN107663053B (en) * 2017-10-24 2020-07-31 河北晨阳工贸集团有限公司 Construction process for pasting soft and beautiful soft stone in indoor floor decoration
CN108385932A (en) * 2018-03-09 2018-08-10 北京市建筑工程装饰集团有限公司 The laying method of macroplate stone material
CN108385932B (en) * 2018-03-09 2023-08-25 北京市建筑工程装饰集团有限公司 Paving method for large plate stone
CN109017109A (en) * 2018-07-27 2018-12-18 苏州金螳螂文化发展股份有限公司 A kind of water knife parquets board manufacturing method and water knife parquets pavement construction method
CN109826404A (en) * 2019-01-29 2019-05-31 台州铭星装饰工程股份有限公司 A kind of wall decoration technique
CN110130642A (en) * 2019-05-27 2019-08-16 西安市鑫龙建筑装饰工程(集团)有限公司 A kind of stone floor construction technology
CN111203987A (en) * 2020-01-20 2020-05-29 深圳市奇信集团股份有限公司 Stone floor construction method
CN113494163A (en) * 2021-07-29 2021-10-12 杭州良工装饰有限公司 Indoor ground construction method
CN113833230A (en) * 2021-10-18 2021-12-24 中国建筑第四工程局有限公司 Shale brick terrace construction process in koji making and fermentation room
CN114293733A (en) * 2021-12-07 2022-04-08 苏州金螳螂文化发展股份有限公司 Surface wax baking treatment process for decorative floor

Similar Documents

Publication Publication Date Title
CN107152145A (en) A kind of stone material flooring construction method
CN107254954A (en) Ground paving ceramic tile construction technology
CN109838065A (en) A kind of ground brick flooring paving construction method
CN101565997A (en) Construction method for large-area irregular floor tile
CN105178559A (en) Novel construction method for granite ground
CN109797920B (en) Indoor decoration construction method
CN109826396A (en) A kind of construction method of A grades of fire prevention artistic floors
CN108343203A (en) A kind of metope anticracking batch embedding technology
CN103174274A (en) Stone material seamless polishing construction method
CN107130766A (en) One kind crystallization envelope seamless stone floor construction method of glaze
CN110656753A (en) Concrete grindstone terrace
CN104120855A (en) Construction method for paving ground tile floor
CN108625252A (en) Urban road laying construction method
CN108797943A (en) A kind of laying process of solid wooden floor board
CN104120860A (en) Construction method for cement mortar ground leveling
CN108385932A (en) The laying method of macroplate stone material
CN109138423A (en) External wall thermal insulation/decoration integration board construction technology
CN207194343U (en) The tapestry brick paving structure of autoclave aerated concrete building block exterior wall
CN209509431U (en) A kind of facing paving structure of wet area
CN111962348A (en) Concrete floor construction process
CN102094494A (en) Construction process for paving S-shaped tiles on roof with slope of more than 60 degrees
CN203834826U (en) Novel staircase water drip tank
CN109025109A (en) A kind of construction technology coating inner wall of building face
CN111255191A (en) Semi-pre-pasted ceramic tile and paving method thereof
CN211949245U (en) Roof stone flashing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170912

RJ01 Rejection of invention patent application after publication