CN109826404A - A kind of wall decoration technique - Google Patents
A kind of wall decoration technique Download PDFInfo
- Publication number
- CN109826404A CN109826404A CN201910086585.6A CN201910086585A CN109826404A CN 109826404 A CN109826404 A CN 109826404A CN 201910086585 A CN201910086585 A CN 201910086585A CN 109826404 A CN109826404 A CN 109826404A
- Authority
- CN
- China
- Prior art keywords
- skirting board
- metope
- glue
- wall
- layer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
The invention discloses a kind of wall decoration techniques, are related to house ornamentation technology, for solving the problems, such as the foot of a wall vulnerable to being stained, comprising the following steps: early-stage preparations cut skirting board;Preparation of construction, scribing skirt wire casing dig line;Metope cleaning, digs skirt wire casing;Skirting board installation, skirting board is glued in skirt wire casing;Metope is whitewashed;The present invention has the following advantages and effects: skirting board latter aspect is installed at the foot of a wall to provide protection to metope; also the skirting board of corresponding color can be selected to do transition to the color difference between floor and metope according to the color on floor simultaneously; visible change impact is reduced, to achieve the purpose that improve metope aesthetics.
Description
Technical field
The present invention relates to house ornamentation technology, in particular to a kind of wall decoration technique.
Background technique
With the improvement of living standards, requirement of the people for living environment is also higher and higher, so the wind of interior decoration
Lattice are also more prone to the requirement such as warmth, beauty.
Currently, the Chinese invention patent that Authorization Notice No. is CN103883094B discloses a kind of environmentally friendly house ornamentation upfitter
Skill carries out as follows, foundation construction early period: standard component base support;Stress point location, installation site setting-out;Main body knot
Structure frame: suspended ceiling device installation;Large-scale combined module is installed;Install wall on wall cloth, fixation wall cloth wood moulding and its
It is his decorative bud, with a tight waist;Mounting decoration panel;Cleaning, completion.
People generally require first to sweeping within doors, arrive between floor and the foot of a wall when sweeping before moving in the new home
When joint, when broom or mop encounter the metope painted, it is easy for spot to be infected with onto metope, and due to lime metope
Good penetrability, these spots penetrate into metope after be difficult to wipe, thus cause house ornamentation aesthetics decline.
Summary of the invention
The object of the present invention is to provide a kind of wall decoration techniques, protection can be provided to metope, so that people are sweeping
It is not easy that metope is caused to be stained during room, to achieve the purpose that improve metope aesthetics.
Above-mentioned technical purpose of the invention has the technical scheme that a kind of wall decoration technique, packet
Include following steps:
(1) early-stage preparations: needing first to measure the length in corner before starting installation, is carried out according to the length in corner to skirting board
It cuts;
(2) preparation of construction: according to decorating scheme, crossing on metope, and the distance between the line drawn and floor are skirting board
Fitting limit reserve the mounting height on floor and during scribing line;
(3) metope is cleared up: metope being located at dashed part pulverized limestone brush layer below and is scalped, skirt wire casing is formed, cuts wall in shovel
Trim lines are shoveled during face and want smooth, and shovel polishes to the metope shoveled out until exposing masonry, then with sand paper;
(4) skirting board is installed: the installation needs of skirting board carry out after floor is completed, during installation, first in the wall shoveled
Then skirting board is packed into skirt wire casing and ajusts, puts jail, and skirting board is made to fit with floor by spreading glue on face;
(5) metope is whitewashed, and is filled repairing to the gap between skirting board and wall plaster layer.
By using above scheme, first scribing line can control the size of skirt wire casing more accurately before proceeding, and
And makes to cut sideline and more tend to be smooth;It is shoveled when clearing up metope to masonry is exposed, then be mainly in view of skirting board
Installation fastness when there are cement or lkd layer in masonry basis outside, is made not in place if it is antiseepage work, metope is frequent
Peeling is easy to happen after dampness, such skirting board is easy for falling off, and the masonry structure of skirting board and wall is connected directly
If, the connection structure between skirting board and wall will be than stronger, so that skirting board is more durable;There is skirting board
Block protective effect after, people are just not easy to be stained metope during cleaning shelter, while this inner cavity is concealed
Skirting board, which is not allowed to be also easy to produce, yet to be fallen grey dust accumulation and stops being bonded between furniture and metope, improves metope aesthetics to reach
Purpose.
The further setting of the present invention are as follows: in step (1) scribing line when between floor at a distance from need to increase by 1 ~ 2cm.
Floor or skirting board necessarily have installation error during installation, if floor install after height lower than setting
Meter absolute altitude is not bad, and skirting board can also be normally packed into skirt wire casing, and the height after floor installs is greater than designed elevation, that
Skirting board can not be just mounted with, by using above scheme, this reserved partial distance can for floor installation error into
Row is offset, and so that the width of skirt wire casing is greater than the width of skirting board, so that skirting board can go on smoothly installation.
The further setting of the present invention are as follows: in step (3) after polishing metope, it is also necessary to metope be carried out clear
It is clean, clean method are as follows: using the length of 50cm or so as primary wiping trip segment, be then applied to skirt wire casing with wet towel
It is interior, and pressed along the direction perpendicular to metope to wet towel with hand, later along same in the trip segment of this 50cm or so
One direction is wiped repeatedly metope 3 ~ 5 times, after the trip segment for having cleaned all skirt wire casings, then with hair dryer by skirt wire casing
Interior moisture drying, and also need to clean skirt wire casing with hairbrush during drying, after completing drying operation
Next-step operation can be carried out after 30min or more need to be stood.
Metope is certain to adhere to many dust on metope after digging out skirt wire casing and polishing, these dust can be serious
The cohesive force between glue and wall is influenced, by using above scheme, wet towel wiping can be by the tension of water by dust
It erases, and why be wiped repeatedly along the same direction from metope, is then infected with because of on the wet towel for smearing metope
Dust, these dust again can be attached on metope during wet towel is returned and smeared, and only be wiped in one direction, then
The dust on wet towel can be reduced as far as possible to adhere again on skirt wire casing inner wall, to keep the cleaning of metope more thorough
Bottom;After being smeared by wet towel, be certain to be attached with moisture on the inner wall of skirt wire casing, these moisture can also seriously affect glue with
Cohesive force between metope is blowed skirt wire casing with hair dryer, can remove these moisture, make the interior of skirt wire casing
Wall keeps drying as far as possible, to enable the stronger of skirting board gluing.
The further setting of the present invention are as follows: the smearing step of glue in step (4) are as follows: one layer of knot is brushed first on wall
Then structure glue sticks one layer of screen cloth, brush one layer of structure glue on screen cloth later, and structure glue needs completely to soak screen cloth, then
One layer of filter cloth is pasted again, skirting board could be finally packed into skirt wire casing after one layer of structure glue of filter cloth surface brush again.
After glue curing, it can become fragile, can all there be a child in many families, and child inevitably can be to kicking during fighting in jest or for fun
Sole generates shock, may result in glue and is crushed, then skirting board is just easy to fall off from wall, by using above-mentioned side
Case, in glue after interior leaching screen cloth and filter cloth, since screen cloth and filter cloth are all flexible materials, and the still good material of permeability
Material, so glue can be allowed to be impregnated with completely during glue is smeared, the intensity after such glue curing is unaffected,
Meanwhile screen cloth and filter cloth can hold glue fragment after cured glue is broken, keep its separated but still in each other's thoughts, as long as there are also glue in this way
Water is clung with walling glue, then skirting board is just not easy to fall off from wall, is firmly installed to reach and improve skirting board
The purpose of degree.
The further setting of the present invention are as follows: glue is after the completion of smearing, with iron nail on the surface of glue with spot distribution
Form stabs out the pit of three rows or more, and during stabbing pit, pays attention to that filter cloth cannot be involved.
Glue generally will be first stirred before smearing, so that each component in glue can be uniformly dispersed, and be stirred
The process mixed can allow glue to generate bubble, these bubbles will form cavity after glue curing, the intensity of gluing be influenced, by adopting
With above scheme, the effect that pit is stabbed on glue has two aspects, first is that can stab some bubbles during stabbing pit
Broken, the bubble after rupture again can be because of the automatic equating of the mobility of glue itself, and colloid has a feature, when the surface of colloid
When having pit, the gas inside colloid can be slowly close towards pit under the action of colloid flows row, and finally by pit
Release, can accelerate the precipitation of colloid internal gas, and after gas evolution, the mobility of colloid can make glue again in this way
Surface tends to levelling, skirting board is obtained with glue-contact more abundant, so that the gluing of skirting board is stronger.
The further setting of the present invention are as follows: the smearing overall thickness of the structure glue is 3 ~ 5mm.
By using above scheme, the smearing thickness of glue cannot be excessive, because glue intensity is lower than skirting board, smears too thick
It is easy to rupture because of impact, if smearing excessively thin, then the cohesive force between skirting board and wall is again inadequate, so 3 ~ 5mm is
One compromise smearing thickness, can either guarantee the adhesion strength of skirting board, at the same not easily lead to again the glue after solidifying by
Hit rupture.
The further setting of the present invention are as follows: skirting board needs before fitting with structure glue first with air-heater to structure
Glue carries out hot baking, must move back and forth air-heater when heat is dried, be heated evenly structure glue, until when structure glue is in leather hard
Skirting board is sticked again, and is gently compacted.
The principle that glue can play adhesive action is because the intermolecular force in glue between macromolecule is compared commonly
Substance wants much better than, and these macromolecules by it is closer, external attraction is stronger, and according to the law of universal gravitation, this
Kind of active force regardless of substance, so glue almost can gluing any object, once and it is aqueous in glue, will lead to these height
Molecule is dispersed, then the adhesive tension of glue will decline naturally, so this is why all glue are all to do it
The reason of substance can just be cemented afterwards, by using above scheme, first structure glue is dried before loading onto skirting board, it can
The moisture in glue is reduced, mitigates water to the weakening effect of glue adhesive tension, so that skirting board can glue stronger.
The further setting of the present invention are as follows: the skirting board, which needs to be separated by between pulverized limestone brush layer after mounting, to be formed with
The filling irrigating sealant of 1 ~ 2cm.
By using above scheme, filling irrigating sealant here with it is exactly aforementioned in mentioned increase scribing line height as a result,
If not reserved filling irrigating sealant, the expansion on floor may result in skirting board and generate extruding to the rendering layer on wall, causes rendering layer
Fragmentation, and after filling irrigating sealant is set, the deformation on floor and the solidification offset of skirting board can gradually tend towards stability, then again to filling irrigating sealant
Process the problem of just can be avoided rendering layer fragmentation.
The further setting of the present invention are as follows: fill skirting board and lime plaster after structure glue solidifies completely, then with lime
Gap between layer, and the lime newly filled is smoothed out, make the lateral surface flush between skirting board and wall plaster layer.
By using above scheme, after structure glue solidifies completely, skirting board is just not likely to generate and offset by, at this time again to filling out
Fill if seam is filled, would not cause rendering layer be squeezed fragmentation the case where, further increase metope beauty to reach
The purpose of degree.
In conclusion the invention has the following advantages:
1. protection can either be provided to metope by installing skirting board latter aspect at the foot of a wall, while also can be according to the color on floor
To select the skirting board of corresponding color to do transition, reduction visible change impact, to reach to the color difference between floor and metope
To the purpose for improving metope aesthetics;
2. cleaning treatment can sweep off the dust in skirt wire casing, keeps contact of the glue with metope more abundant, mentioned to reach
The purpose of high skirting board gluing firmness;
3. the interior leaching screen cloth, filter cloth processing and stamp pit processing during gluing can either improve the cracking resistance of glue itself,
The precipitation that glue underwater bubble can also be promoted simultaneously, enables skirting board preferably to be combined with glue, kicks to further increase
The purpose of sole gluing firmness.
Detailed description of the invention
Fig. 1 is process flow chart of the invention.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
A kind of wall decoration technique, as shown in Figure 1, comprising the following steps:
(1) early-stage preparations: needing first to measure the length in corner before starting installation, is carried out according to the length in corner to skirting board
It cuts, to do 45 ° of chamfering process, to the end of skirting board when cutting to facilitate pair of corner's adjacent both ends skirting board
It closes.
(2) preparation of construction: according to decorating scheme, crossing on metope, scribing line when between floor at a distance from need to increase
Add 1 ~ 2cm, as the correction amount of floor installation error, the distance between this line and floor for drawing are the installation of skirting board
Range, and during scribing line, the distance between line and floor need the mounting height plus floor.
(3) metope is cleared up: metope being located at dashed part pulverized limestone brush layer below and is scalped, skirt wire casing is formed, is shoveling
Trim lines are shoveled during cutting metope and want smooth, and shovel polishes to the metope shoveled out until exposing masonry, then with sand paper.
After metope is polished, it is also necessary to be cleaned to metope, clean method are as follows: using the length of 50cm or so as one
Secondary wiping trip segment, is then applied in skirt wire casing with wet towel, and with hand along perpendicular to metope direction to wet towel into
Row pressure, is later wiped repeatedly metope 3 ~ 5 times along same direction in the trip segment of this 50cm or so, all having cleaned
After the trip segment of skirt wire casing, then with hair dryer by the moisture drying in skirt wire casing, and also needed during drying
Skirt wire casing is cleaned with hairbrush, needs standing 30min or more that can carry out next-step operation after completing drying operation.
(4) skirting board is installed: the installation needs of skirting board carry out after floor is completed, and during installation, are shoveling first
Metope on spreading glue, the smearing step of glue are as follows: first on wall brush one layer of structure glue, then stick one layer of net
Cloth brushes one layer of structure glue on screen cloth later, and structure glue needs completely to soak screen cloth, then pastes one layer of filter cloth again, then again
In one layer of structure glue of filter cloth surface brush, the smearing of glue is completed.
After the completion of glue is smeared, it is also necessary to processing, bleeding be exhausted are as follows: with iron nail on the surface of glue with dotted
The form of distribution stabs out the pit of three rows or more, and the stamp of pit, which moves depth, which is subject to, cannot involve filter cloth.
Above step all after the completion of, it is also necessary to do rubberizing pre-treatment, concrete operations are as follows: first carried out with air-heater to structure glue
Heat is dried, and must be moved back and forth air-heater when heat is dried, is heated evenly structure glue, the glue of same place position be heated wind when
Between no more than 5 seconds, avoid glue dries from excessively losing viscosity, until structure glue again sticks skirting board when being in leather hard
Go, ajust, put jail after be gently compacted.
(5) metope is whitewashed, and during installing skirting board, needs to allow the lower part of skirting board to fit with floor, so
Will form filling irrigating sealant between rendering layer on skirting board and metope, after structure glue thoroughly dry after, then with lime to filling irrigating sealant into
Row filling, and smooth out until making skirting board and rendering layer flush with each other, to guarantee metope aesthetics.
This specific embodiment is only explanation of the invention, is not limitation of the present invention, those skilled in the art
Member can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but as long as at this
All by the protection of Patent Law in the scope of the claims of invention.
Claims (9)
1. a kind of wall decoration technique, it is characterised in that: the following steps are included:
(1) early-stage preparations: needing first to measure the length in corner before starting installation, is carried out according to the length in corner to skirting board
It cuts;
(2) preparation of construction: according to decorating scheme, crossing on metope, and the distance between the line drawn and floor are skirting board
Fitting limit reserve the mounting height on floor and during scribing line;
(3) metope is cleared up: metope being located at dashed part pulverized limestone brush layer below and is scalped, skirt wire casing is formed, cuts wall in shovel
Trim lines are shoveled during face and want smooth, and shovel polishes to the metope shoveled out until exposing masonry, then with sand paper;
(4) skirting board is installed: the installation needs of skirting board carry out after floor is completed, during installation, first in the wall shoveled
Then skirting board is packed into skirt wire casing and ajusts, puts jail, and skirting board is made to fit with floor by spreading glue on face;
(5) metope is whitewashed, and is filled repairing to the gap between skirting board and wall plaster layer.
2. a kind of wall decoration technique according to claim 1, it is characterised in that: in step (1) scribing line when and floor
The distance between need to increase by 1 ~ 2cm.
3. a kind of wall decoration technique according to claim 1, it is characterised in that: step is beaten in (3) to metope
After mill, it is also necessary to be cleaned to metope, clean method are as follows: using the length of 50cm or so as primary wiping trip segment, then
It is applied in skirt wire casing with wet towel, and is pressed along the direction perpendicular to metope to wet towel with hand, later at this
Metope is wiped repeatedly 3 ~ 5 times along same direction in the trip segment of 50cm or so, in the stroke for having wiped all skirt wire casings
Duan Hou, then dried up the moisture in skirt wire casing with hair dryer, and also need with hairbrush during drying to skirting
Slot is cleaned, and needs standing 30min or more that can carry out next-step operation after completing drying operation.
4. a kind of wall decoration technique according to claim 1, it is characterised in that: the smearing step of glue in step (4)
Are as follows: one layer of structure glue is brushed first on wall, one layer of screen cloth is then sticked, brushes one layer of structure glue again on screen cloth later, is tied
Structure glue needs completely to soak screen cloth, then pastes one layer of filter cloth again, could finally incite somebody to action after filter cloth surface brushes one layer of structure glue again
Skirting board is packed into skirt wire casing.
5. a kind of wall decoration technique according to claim 4, it is characterised in that: glue uses iron nail after the completion of smearing
The pit of three rows or more is stabbed out in the form of spot distribution on the surface of glue, and during stabbing pit, paying attention to cannot
Involve filter cloth.
6. a kind of wall decoration technique according to claim 4, it is characterised in that: the smearing overall thickness of the structure glue is
3~5mm。
7. a kind of wall decoration technique according to claim 4, it is characterised in that: skirting board is fitting it with structure glue
Before, it needs first to carry out hot baking to structure glue with air-heater, air-heater must be moved back and forth when heat is dried, keep structure glue heated equal
It is even, until structure glue again sticks skirting board when being in leather hard, and gently it is compacted.
8. a kind of wall decoration technique according to claim 7, it is characterised in that: the skirting board need after mounting with
It is separated by the filling irrigating sealant for being formed with 1 ~ 2cm between pulverized limestone brush layer.
9. a kind of wall decoration technique according to claim 8, it is characterised in that: after structure glue solidifies completely, then use
Lime fills the gap between skirting board and pulverized limestone brush layer, and the lime newly filled is smoothed out, and makes skirting board and wall plaster
Lateral surface flush between layer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910086585.6A CN109826404A (en) | 2019-01-29 | 2019-01-29 | A kind of wall decoration technique |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910086585.6A CN109826404A (en) | 2019-01-29 | 2019-01-29 | A kind of wall decoration technique |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109826404A true CN109826404A (en) | 2019-05-31 |
Family
ID=66862849
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910086585.6A Pending CN109826404A (en) | 2019-01-29 | 2019-01-29 | A kind of wall decoration technique |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109826404A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110512833A (en) * | 2019-09-04 | 2019-11-29 | 谭士虎 | A kind of wall decoration technique |
CN114165025A (en) * | 2021-12-27 | 2022-03-11 | 王聚业 | Novel skirting line and mounting method thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107152145A (en) * | 2017-06-07 | 2017-09-12 | 天津市源泉市政工程有限公司 | A kind of stone material flooring construction method |
CN107780627A (en) * | 2016-08-30 | 2018-03-09 | 陈春来 | A kind of exterior wall heat-insulating paint construction method |
CN108049603A (en) * | 2017-12-12 | 2018-05-18 | 安徽大富装饰股份有限公司 | A kind of indoor wall space convenient decoration |
CN108166719A (en) * | 2017-12-26 | 2018-06-15 | 南通远洋船舶配套有限公司 | PVC floor directly lays processing mounting process of the upper wall as skirting from ground |
CN108797943A (en) * | 2018-05-30 | 2018-11-13 | 湖州汇德集团有限公司 | A kind of laying process of solid wooden floor board |
-
2019
- 2019-01-29 CN CN201910086585.6A patent/CN109826404A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107780627A (en) * | 2016-08-30 | 2018-03-09 | 陈春来 | A kind of exterior wall heat-insulating paint construction method |
CN107152145A (en) * | 2017-06-07 | 2017-09-12 | 天津市源泉市政工程有限公司 | A kind of stone material flooring construction method |
CN108049603A (en) * | 2017-12-12 | 2018-05-18 | 安徽大富装饰股份有限公司 | A kind of indoor wall space convenient decoration |
CN108166719A (en) * | 2017-12-26 | 2018-06-15 | 南通远洋船舶配套有限公司 | PVC floor directly lays processing mounting process of the upper wall as skirting from ground |
CN108797943A (en) * | 2018-05-30 | 2018-11-13 | 湖州汇德集团有限公司 | A kind of laying process of solid wooden floor board |
Non-Patent Citations (1)
Title |
---|
马冬: "《建筑装饰材料与施工工艺》", 31 July 2017, 中国矿业大学出版社 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110512833A (en) * | 2019-09-04 | 2019-11-29 | 谭士虎 | A kind of wall decoration technique |
CN114165025A (en) * | 2021-12-27 | 2022-03-11 | 王聚业 | Novel skirting line and mounting method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102505831B (en) | Construction method for paving plasters on ground and manmade stone | |
CN104612261A (en) | Method for external insulation construction of polystyrene board thin plastered surface in cold and windy area | |
CN103938822A (en) | Inorganic thermal insulation decorative sheet and installation method thereof | |
CN109826404A (en) | A kind of wall decoration technique | |
CN107338967A (en) | A kind of new technology and new material of aging blocks outdoor tile facing renewal and reform | |
CN109750758A (en) | The construction method that prefabricated sandwich heat preservation shear wall exterior wall is laterally stitched and vertically stitched | |
CN107237409A (en) | Exterior wall heat-insulating paint construction method | |
CN107780627A (en) | A kind of exterior wall heat-insulating paint construction method | |
CN112575979A (en) | Construction method of plastering waterproof mortar for building exterior wall | |
CN110273490A (en) | A kind of embedded lightweight wall plate steel building construction and construction method | |
CN103088985A (en) | Method of bonding and jointing of exterior wall tiles | |
CN101649624B (en) | Construction method for governing basement leakage | |
CN108179858A (en) | A kind of artificial stone paving structure and its laying method | |
CN206205167U (en) | A kind of indoor toilets threshold stone water proof structure | |
CN209509431U (en) | A kind of facing paving structure of wet area | |
CN105888084A (en) | Whole outer wall internal thermal insulation system construction method by using enhanced composite thermal insulation material | |
CN101173549A (en) | Novel material integrating decoration, anti-crack, water-proof and heat preserving function, and its producing method | |
CN100368641C (en) | Spraying of heat preservating decorating polyurethane wall body and its construction method | |
CN206205168U (en) | A kind of bathroom door pin waterproof treatment structure | |
CN206143550U (en) | Concrete mat formation piece or structure of mating formation on stone material road surface | |
CN206591722U (en) | A kind of moistureproof cement light partition wall board of crack resistence for connecting wall | |
CN109736539A (en) | Ceramic tile close joint paving ground structure and laying method | |
CN103089112A (en) | Face brick facing door/window side anti-leakage structure and construction method thereof | |
CN109853889A (en) | A kind of construction method of kervit microbead insulated sand slurry | |
CN204983447U (en) | Building external tile face structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190531 |
|
RJ01 | Rejection of invention patent application after publication |