CN106638918A - Construction method for sponge city rainwater collection system - Google Patents

Construction method for sponge city rainwater collection system Download PDF

Info

Publication number
CN106638918A
CN106638918A CN201611097668.8A CN201611097668A CN106638918A CN 106638918 A CN106638918 A CN 106638918A CN 201611097668 A CN201611097668 A CN 201611097668A CN 106638918 A CN106638918 A CN 106638918A
Authority
CN
China
Prior art keywords
water
retaining
well
tank
clarifier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611097668.8A
Other languages
Chinese (zh)
Other versions
CN106638918B (en
Inventor
吴明桦
沈玫吟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NINGBO SHUNXING GARDEN CONSTRUCTION CO., LTD.
Original Assignee
Zhejiang Xin Xin Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Xin Xin Construction Co Ltd filed Critical Zhejiang Xin Xin Construction Co Ltd
Priority to CN201611097668.8A priority Critical patent/CN106638918B/en
Publication of CN106638918A publication Critical patent/CN106638918A/en
Application granted granted Critical
Publication of CN106638918B publication Critical patent/CN106638918B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • E03F5/101Dedicated additional structures, interposed or parallel to the sewer system
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/14Devices for separating liquid or solid substances from sewage, e.g. sand or sludge traps, rakes or grates

Abstract

The invention discloses a construction method for a sponge city rainwater collection system. The system comprises the steps of a, excavation of foundation pit; b, base treatment; c, water purification pool building; d, water storage tank being in place; e, water seepage base course paving; f, watering and maintenance. According to the construction method for the sponge city rainwater collection system, the construction is easy, the difficulty is low, the construction quality is easy to control, the construction cost is low, the referred construction equipment is little, the permeation effect is good, the water-holding capacity is strong, collected rainwater is purified and put into secondary use, the resource utilization efficiency of the rainwater is greatly improved, waste is turned into wealth, and the problem of scanty water resources is relieved.

Description

A kind of construction method of sponge urban rainwater collection system
Technical field
The invention belongs to sponge city water resource utilizes field, more particularly to a kind of sponge urban rainwater collection system is applied Work method.
Background technology
With the propulsion of Urbanization Construction, increasing for hardened ground changes original water regime, causes rainfall runoff Increase, the frequent ponding in road surface, the normal large area ponding of urban Jing, while rain flood peak value becomes big, soil moisture content is reduced, underground Water level decreasing phenomenon aggravation etc..In addition, China's Urban Water Shortage Problem of Cities is increasingly serious, and northern area resource-type water shortage, southern area Water quality type water shortage.In such a case, government puts forward the target for building " sponge city ", gives in each side such as policy, finances To support.
Sponge city, as the term suggests, city is such as sponge, in duration of raining, can quickly absorb, accumulate, permeating, Purifying rainwater, reduces rainwater and forms runoff, recharge of groundwater;Simultaneously when not raining, by a series for the treatment of measures and supporting Pipe network facilities, the water of accumulation is used, so as to allow rainwater resource to be preferably dissolved in the supply and drain water system in city.Make Rational sponge urban water system, can both be effectively protected the original ecosystem in city, it is also possible to slowly recover original The destroyed ecosystem, simultaneously for the Development control area of whole urbanization impact drop to it is lower.
Traditional sponge urban construction pattern, is everywhere hard surface.Whenever heavy rain, " the ash such as pipe duct, pumping plant is relied primarily on Color " facility carrys out draining, and with " quick to exclude " and " end concentration " main planning and design concept is controlled to, and rainwater mainly passes through draining Facility is drained, it is impossible to penetrate into underground, is often resulted in and is met rain flooded, and drought and waterlogging racing does not meet the requirement of sponge urban construction.
The content of the invention
Present invention aim at solving above-mentioned technical problem present in prior art, there is provided a kind of sponge urban rainwater is received The construction method of collecting system, construction is simple, and difficulty is low, and construction quality is easily controllable, and construction cost is low, the construction equipment being related to Few, osmotic effect is good, and water-holding capacity is strong, by the rainwater purification collected, and puts into the secondary money for using, substantially increasing rainwater Source utilization ratio, turns waste into wealth, and alleviates the problem of water resources shortage.
In order to solve above-mentioned technical problem, the present invention is adopted the following technical scheme that:
A kind of construction method of sponge urban rainwater collection system, it is characterised in that comprise the steps:
(a) excavation of foundation pit:According to design working drawing, coordinated by the way of artificial grooving using excavator, excavation pit is to setting Meter absolute altitude, clears up bottom of foundation ditch, and then the bullet line of ink marker is levelling, keeps the gradient of bottom of foundation ditch 2%~3%, controls foundation pit side-wall Perpendicularity be respectively less than 1%, and do support protection, in the case where bottom of foundation ditch is made, grey wire tag, marks retaining clarifier-tank construction area, Ensure foundation ditch flatness and perpendicularity, prevent foundation ditch from occurring subsiding, the generation of the phenomenon that come down, so as to ensure construction quality, construct Region division clearly, improves efficiency of construction;
(b) base treatment:Waterproofing geomembrane is laid in the grey coil of mark, is fixed with cement nail every 5~8m, Then the original soil of 150~200mm is backfilled on waterproofing geomembrane, and rolls compacting back and forth, then compacted density > 92% is layered Casting concrete bed course, total height is 250~300mm, reserved 100 between concrete cushion edge and waterproofing geomembrane~ The lap of splice of 150mm, every the reserved ventilating grooves of 10~15m on concrete cushion, and lays from below to up in ventilating groove 100~150mm thickness ventilation anti-seepage sand and 100~150mm thick pervious concrete, every layer of uniform compaction, concrete cushion is poured After the completion of, surface wooden float rubs flat with the hands, and is covered in 12h, conserves 7~8 days, it is ensured that the structure of concrete cushion is strong Degree, permeability and heat endurance, support baseboard based on concrete cushion, bearing capacity has to comply with design requirement, coagulation Soil padding also acts as buffer action, prevents ground surface environment from affecting foundation ditch foundation structure;
C () retaining clarifier-tank is built by laying bricks or stones:After concrete cushion acceptance(check), retaining clarifier-tank is built by laying bricks or stones, building the pond body phase by laying bricks or stones Between, water string is attached separately on water inlet and delivery port, then hammering compacting is arranged on collector pipe on water inlet, will Drainpipe is arranged on delivery port, and is enclosed in interface winding 2~3 with waterstop, and according to positioning convex the side of locating slot is directed at Formula loads water filtration separator in retaining well, then injects cement mortar into locating slot, while the slurries for overflowing locating slot are cleared up, from Pond body side starts to lay retaining well, and brushing cement mortar in each outside wall surface of retaining well, adjacent retaining well is brought into close contact, retaining After well laying is finished, cover plate and liquid level well are poured successively, liquid level well bassets 50~100mm, then lays on the cover board anti- Water geomembrane, by waterproofing geomembrane whole cover plate is paved with, and evens up fixation, and reserves the lap of splice of 100~150mm, then tightly Waterproofing geomembrane is enclosed in patch pond body outer wall laying one, then by the waterproofing geomembrane under the circle waterproofing geomembrane and concrete cushion, Waterproofing geomembrane on cover plate completes overlap joint process, and retaining clarifier-tank gets up rain water-harvesting, no as the container for collecting rainwater Ground space is occupied, filters synchronous with purification, antiseepage is with vaporization prevention simultaneously, net by concrete cushion, retaining with waterproofing geomembrane In change pond and cover plate are wrapped in, prevent original soil around from invading, the squeezing action of surrounding original soil will not be subject to, play structural defence work With;
D () water tank is in place:Water tank and suction pump are separately fixed on ground, the water side connection retaining of suction pump Tank, each road drainpipe is assembled on many siphunculus, then the water side of many siphunculus is connected into the water inlet end of suction pump, and suction pump will store The rainwater collected in water purifying tank is pumped into water tank and stores, for pouring crops, the daily water consumption of landscape plant, washing Parking lot water, road rinse, flush the toilet and some other non-domestic water purposes, substantially increase the recycling effect of rainwater Rate, turns waste into wealth, and alleviates the problem of water resources shortage, reduces soil erosion, to building the ecological agriculture, ecocity, protection Environment all has very great meaning;
The laying of (e) infiltration basic unit:Retaining clarifier-tank and cover plate are buried with original soil backfill, is often filled out 200~300mm and is entered pedestrian Work is tamped, then the laying infiltration basic unit on earthing face, the basic unit that seeps water be followed successively by from the bottom to top the thick coarse sands layers of 100~150mm, The thick metalling of 200~250mm thick gravel layer and 100~150mm, coarse sands layer buries collector pipe, has laid rear vibration tamp, Then screed-coat is laid on metalling, the screed-coat levelling compacting of sand is middle to both sides slope 1~1.5%, finally levelling Water-permeable brick is staggeredly laid on layer, after water-permeable brick laying is finished, compacting is smooth, and rainwater permeates downwards, enters Infiltration water basic unit, in infiltration Migrate in basic unit, can only downwards be permeated by hole, flow velocity is slow, and the time of staying is long, and coarse sands layer, gravel layer and metalling are all There is adsorption capacity, the nitrogen in rainwater, phosphorus solid particle are adsorbed, dropped by the anaerobe of infiltration basic unit growth Solution, purifying rainwater;Water-permeable brick has good gas permeability, water penetration, and rainwater can be enable rapidly to penetrate into underground, supplements ground The soil moisture of table water and underground water, while with the effect for absorbing moisture and heat, so as to adjust the temperature of earth's surface local space Humidity, and the tropical island effect in city is effectively solved, the pressure of municipal drainage and flood control, the dirt to preventing public waters can be alleviated Dye and process sewage have good effect;
(f) water seasoning:After construction is finished, water-permeable brick, and water seasoning are covered with stack of rice straw, curing time is little more than 24 When, stack of rice straw moistening is ensured during maintenance, and forbid idler to trample, water seasoning can ensure the intensity of water-permeable brick, prevent Crack, keeps the water penetration of water-permeable brick.
Further, abandoned stream screened well is buried in the range of foundation ditch periphery 2m in step (d), the water side of many siphunculus is accessed The water inlet end of abandoned stream screened well, the water side of abandoned stream screened well connects the water inlet end of suction pump, from the rain that retaining clarifier-tank is collected Water Jing drainpipes are entered in abandoned stream screened well, and the suspended particulate and rubbish thing remained in rainwater is eliminated by absorption so that rainwater Effectively purified, improve the quality of rainwater, be pumped into water tank by drawing water, come into operation.
Further, in step (c) before the laying of retaining well, by retaining well unification water saturates, penetration period is 5~ 6min, retaining well is piled up by hacking and is formed, and prevents retaining well from absorbing the moisture in cement mortar, causes cement not produce aquation mistake Journey just solidifies in advance, substantially reduces mortar strength, with water saturates retaining well can be made to reach saturation state, prevents sending out for water suction phenomenon It is raw.
Further, the specific practice of concrete cushion maintenance is to use covered rearing with plastic film concrete cushion in step (b), and Water seasoning, ensures covering material moistening during maintenance, and forbids idler to trample or continue to construct thereon,
A kind of retaining clarifier-tank of the construction method for sponge urban rainwater collection system, it is characterised in that:Including pond Body, retaining well, cover plate and water filtration separator, on retaining well, retaining well is evenly distributed in pond body cover plate, and water filtration separator is located at In retaining well, treatment hole is evenly distributed with water filtration separator, positioning convex is symmetrically distributed with water filtration separator, it is symmetrical in retaining well Locating slot is distributed with, locating slot matches with positioning convex, the side of retaining well is equipped with water-flowing trough, and the both sides of pond body set respectively There are water inlet and delivery port;Retaining clarifier-tank easy construction, the efficiency high, as the container for collecting rainwater, rain water-harvesting are risen Come, filter synchronous with purification, with vaporization prevention simultaneously, Stability Analysis of Structures is safe and reliable, prevents take up ground space, the rain of purification for antiseepage Water can be used for various aspects, substantially increase the resource utilization efficiency of rainwater, turn waste into wealth, and alleviate asking for water resources shortage Topic.
Further, annular protrusion is provided with the top of retaining well, between adjacent annular projection drainage channel, adjacent retaining is formed Drainage channel between well is interconnected so that the moisture fallen on retaining well falls into the bottom of pond body along drainage channel, gathers Collection gets up.
Further, cover plate is provided with liquid level well, and liquid level well penetrates cover plate, and liquid level well is connected with retaining well, is set on liquid level well There is well lid, well lid is provided with leaking hole, and liquid level well facilitates the retaining situation that staff's timing is checked in retaining clarifier-tank, liquid level It is too high, need to be drawn water, the setting of leaking hole facilitates the downward seepage of ground rainwater, reduces land drainage pressure.
Further, water inlet is provided with water string, and delivery port is provided with water string, and the water string is using flexible anti- Jacket pipe, improves the water resistance inside and outside water inlet and inside and outside delivery port, and prevention collector pipe and drainpipe are subjected to displacement deformation.
Further, retaining well is in regular hexagon shape, and retaining gang of wells body forms alveolate texture, stablizes safe and reliable, do not account for According to ground space, filter synchronous with purification, antiseepage is with vaporization prevention simultaneously.
The present invention has the advantages that as a result of above-mentioned technical proposal:
Construct in the present invention simple, difficulty is low, and construction quality is easily controllable, and construction cost is low, and the construction equipment being related to is few, Osmotic effect is good, and water-holding capacity is strong, by the rainwater purification collected, reduces the secondary pollution of rainwater;Water-permeable brick is staggeredly laid, Rainwater is permeated downwards rapidly, enter Infiltration water basic unit, migrate in infiltration basic unit, can only downwards be permeated by hole, Flow velocity is slow, and the time of staying is long, and coarse sands layer, gravel layer and metalling have adsorption capacity, and the nitrogen in rainwater, phosphorus solid particle are entered Row absorption, is degraded by the anaerobe of infiltration basic unit growth, purifying rainwater, the rainwater Jing coarse sands layers bottom after purification Collector pipe flows into retaining clarifier-tank, and retaining clarifier-tank gets up rain water-harvesting as the container for collecting rainwater, prevents take up ground empty Between, filtering synchronous with purification, the rainwater of collection simultaneously, is pumped into water tank and is stored by antiseepage with vaporization prevention by suction pump Come, rinse, flush the toilet and some other non-lives for pouring crops, the daily water consumption of landscape plant, washing bay water, road Water purposes is used, urban pavement discharge pressure is reduced, and by the rainwater purification collected, input is secondary to be used, and is substantially increased The resource utilization efficiency of rainwater, turns waste into wealth, and alleviates the problem of water resources shortage.
The easy construction of retaining clarifier-tank, efficiency high in the present invention, only locating slot need to be directed at during construction according to positioning convex Mode loads water filtration separator in retaining well, then injects cement mortar into locating slot so that water filtration separator is bonded and fixed at storage It is reliable and stable in well, simple to operate, quick effective, the reduction of erection time;Water filtration separator plays a part of to block rainwater, and rainwater is only Infiltration can downwards be continued by treatment hole, the fixed particle remained in rainwater is stopped on water filtration separator surface, it is impossible to fallen, point From impurity;Retaining clarifier-tank as collect rainwater container, rain water-harvesting is got up, filter synchronous with purification, antiseepage with prevent Simultaneously, Stability Analysis of Structures is safe and reliable, prevents take up ground space for evaporation.
Description of the drawings
Below in conjunction with the accompanying drawings the invention will be further described:
Fig. 1 is the structural representation of retaining clarifier-tank in the present invention;
Fig. 2 is the structural representation after retaining well is piled up in the present invention;
Fig. 3 is retaining well and the structural representation of water filtration separator connection in the present invention;
Fig. 4 is the structural representation of pond body in the present invention;
Fig. 5 is a kind of schematic flow sheet of the construction method of sponge urban rainwater collection system of the invention.
In figure:1- pond bodies;2- retaining wells;3- cover plates;4- water filtration separators;5- treatment holes;6- positioning convex;7- locating slots; 8- water-flowing troughs;9- water inlets;10- delivery ports;11- water strings;12- annular protrusions;13- drainage channels;14- liquid level wells;15- Well lid;16- leaking holes.
Specific embodiment
As shown in Figures 1 to 5, it is a kind of construction method of sponge urban rainwater collection system of the invention, including following step Suddenly:
(a) excavation of foundation pit:According to design working drawing, coordinated by the way of artificial grooving using excavator, excavation pit is to setting Meter absolute altitude, clears up bottom of foundation ditch, and then the bullet line of ink marker is levelling, keeps the gradient of bottom of foundation ditch 2%~3%, controls foundation pit side-wall Perpendicularity be respectively less than 1%, and do support protection, in the case where bottom of foundation ditch is made, grey wire tag, marks retaining clarifier-tank construction area, Ensure foundation ditch flatness and perpendicularity, prevent foundation ditch from occurring subsiding, the generation of the phenomenon that come down, so as to ensure construction quality, construct Region division clearly, improves efficiency of construction.
(b) base treatment:Waterproofing geomembrane is laid in the grey coil of mark, is fixed with cement nail every 5~8m, Then the original soil of 150~200mm is backfilled on waterproofing geomembrane, and rolls compacting back and forth, then compacted density > 92% is layered Casting concrete bed course, total height is 250~300mm, reserved 100 between concrete cushion edge and waterproofing geomembrane~ The lap of splice of 150mm, every the reserved ventilating grooves of 10~15m on concrete cushion, and lays from below to up in ventilating groove 100~150mm thickness ventilation anti-seepage sand and 100~150mm thick pervious concrete, every layer of uniform compaction, concrete cushion is poured After the completion of, surface wooden float rubs flat with the hands, and is covered in 12h, conserves 7~8 days, the specific practice of concrete cushion maintenance It is to use covered rearing with plastic film concrete cushion, and water seasoning, covering material moistening is ensured during maintenance, and forbid idler to trample Or continue to construct thereon, it is ensured that the structural strength of concrete cushion, permeability and heat endurance, concrete cushion is used as base Plinth support baseboard, bearing capacity has to comply with design requirement, and concrete cushion also acts as buffer action, prevents ground surface environment from affecting base Hole foundation structure.
C () retaining clarifier-tank is built by laying bricks or stones:After concrete cushion acceptance(check), retaining clarifier-tank, retaining clarifier-tank bag are built by laying bricks or stones Pond body 1, retaining well 2, cover plate 3 and water filtration separator 4 are included, on retaining well 2, retaining well 2 is evenly distributed in pond body 1 cover plate 3, Retaining well 2 is in regular hexagon shape, forms alveolate texture, stablizes safe and reliable.Water filtration separator 4 in the retaining well 2, drainage every Be evenly distributed with treatment hole 5 on plate 4, water filtration separator 4 plays a part of to block rainwater, rainwater can only by treatment hole 5 downwards after Continuous infiltration, the fixed particle of rainwater residual is being stopped on the surface of water filtration separator 4, it is impossible to is fallen, has been separated impurity.
Be symmetrically distributed with positioning convex 6 on water filtration separator 4, be symmetrically distributed with locating slot 7 in retaining well 2, locating slot 7 with it is fixed Position raised 6 matches, and water filtration separator 4 is loaded retaining well 2 by the mode that only need to be directed at locating slot 7 according to positioning convex 6 during construction Interior, simple to operate, easy construction, efficiency high are quick effective.The side of retaining well 2 is equipped with water-flowing trough 8, adjacent retaining well 2 it Between water-flowing trough 8 be mutually communicated, expand the flow range of rainwater, keep activity.Pond body 1 is respectively provided on two sides with water inlet 9 With delivery port 10, water string 11 is equipped with water inlet 9 and delivery port 10, the water string 11 adopts soft waterproof casing, The water resistance inside and outside water inlet 9 and inside and outside delivery port 10 is improved, prevention pipeline is subjected to displacement deformation.The top of retaining well 2 sets There is annular protrusion 12, drainage channel 13 is formed between adjacent annular projection 12, the drainage channel 13 between adjacent retaining well 2 is mutual Connection so that the moisture fallen on retaining well 2 falls into the bottom of pond body 1 along drainage channel 13, gathers together.Set on cover plate 3 There is liquid level well 14, liquid level well 14 penetrates cover plate 3, and liquid level well 14 is connected with retaining well 2, and liquid level well 14 is provided with well lid 15, well lid 15 are provided with leaking hole 16, and liquid level well 14 facilitates the retaining situation that staff's timing is checked in retaining clarifier-tank, and liquid level is too high Then need to be drawn water, the setting of leaking hole 16 facilitates the downward seepage of ground rainwater, reduces land drainage pressure.
During pond body 1 is built by laying bricks or stones, water string 11 is attached separately on water inlet 9 and delivery port 10, hammering compacting, then Collector pipe is arranged on water inlet 9, drainpipe is arranged on delivery port 10, and 2~3 are wound in interface with waterstop Circle, loads water filtration separator 4 in retaining well 2 according to the mode that positioning convex 6 is directed at locating slot 7, then injects into locating slot 7 Cement mortar, while clearing up the slurries for overflowing locating slot 7, starts to lay retaining well 2 from the side of pond body 1, before retaining well 2 is laid, It is 5~6min by the unification water saturates of retaining well 2, penetration period, retaining well 2 is piled up by hacking and formed, and prevents retaining well 2 from absorbing Moisture in cement mortar, causes cement not produce hydration process and just solidifies in advance, substantially reduces mortar strength, uses water saturates energy Make retaining well 2 reach saturation state, prevent the generation of water suction phenomenon.Brushing cement mortar in each outside wall surface of retaining well 2 is adjacent Retaining well 2 is brought into close contact, and after the laying of retaining well 2 is finished, pours cover plate 3 and liquid level well 14 successively, and liquid level well 14 bassets 50 ~100mm, then sets waterproofing geomembrane on the upper berth of cover plate 3, and waterproofing geomembrane is paved with into whole cover plate 3, evens up fixation, and reserves The lap of splice of 100~150mm, is then close to the outer wall of pond body 1 laying one and encloses waterproofing geomembrane, then by the circle waterproofing geomembrane Overlap joint is completed with the waterproofing geomembrane on the waterproofing geomembrane under concrete cushion, cover plate 3 to process, retaining clarifier-tank is used as collection The container of rainwater, rain water-harvesting is got up, and prevents take up ground space, filters synchronous with purification, and antiseepage with vaporization prevention simultaneously, uses anti- In water geomembrane is wrapped in concrete cushion, retaining clarifier-tank and cover plate 3, prevent original soil around from invading, surrounding will not be subject to The squeezing action of original soil, plays structural defence effect.
D () water tank is in place:Water tank and suction pump are separately fixed on ground, the water side connection retaining of suction pump Tank, each road drainpipe is assembled on many siphunculus, abandoned stream screened well is buried in the range of foundation ditch periphery 2m, by the water outlet of many siphunculus The water inlet end into abandoned stream screened well is terminated, the water side of abandoned stream screened well connects the water inlet end of suction pump, receives from retaining clarifier-tank The rainwater Jing drainpipes of collection are entered in abandoned stream screened well, and the suspended particulate and rubbish thing remained in rainwater is eliminated by absorption, is made Obtain rainwater effectively to be purified, improve the quality of rainwater, be pumped into water tank by drawing water and stored, for pouring agriculture Crop, the daily water consumption of landscape plant, washing bay water, road rinse, flush the toilet and some other non-domestic water purposes, significantly The resource utilization efficiency of rainwater is improve, is turned waste into wealth, alleviate the problem of water resources shortage, soil erosion is reduced, to building If the ecological agriculture, ecocity, environmental protection all have very great meaning.
The laying of (e) infiltration basic unit:Retaining clarifier-tank and cover plate 3 are buried with original soil backfill, often filling out 200~300mm is carried out Hand compaction, then lays infiltration basic unit on earthing face, and the basic unit that seeps water is followed successively by from the bottom to top the thick coarse sands of 100~150mm The thick metalling of layer, 200~250mm thick gravel layer and 100~150mm, coarse sands layer buries collector pipe, has laid rear vibro-rammer It is real, screed-coat is then laid on metalling, the screed-coat levelling compacting of sand, centre finally exists to both sides slope 1~1.5% Water-permeable brick is staggeredly laid on screed-coat, after water-permeable brick laying is finished, compacting is smooth, and rainwater permeates downwards, enters Infiltration water basic unit, Migrate in infiltration basic unit, can only downwards be permeated by hole, flow velocity is slow, and the time of staying is long, coarse sands layer, gravel layer and rubble Layer has adsorption capacity, and the nitrogen in rainwater, phosphorus solid particle are adsorbed, and is carried out by the anaerobe of infiltration basic unit growth Degraded, purifying rainwater;Water-permeable brick has good gas permeability, water penetration, and rainwater can be enable rapidly to penetrate into underground, supplements The soil moisture of surface water and groundwater, while with the effect for absorbing moisture and heat, so as to adjust earth's surface local space Humiture, and the tropical island effect in city is effectively solved, the pressure of municipal drainage and flood control can be alleviated, to preventing public waters Pollution and process sewage have good effect.
(f) water seasoning:After construction is finished, water-permeable brick, and water seasoning are covered with stack of rice straw, curing time is little more than 24 When, stack of rice straw moistening is ensured during maintenance, and forbid idler to trample, water seasoning can ensure the intensity of water-permeable brick, prevent Crack, keeps the water penetration of water-permeable brick.
Construct in the present invention simple, difficulty is low, and construction quality is easily controllable, and construction cost is low, and the construction equipment being related to is few, Osmotic effect is good, and water-holding capacity is strong, by the rainwater purification collected, reduces the secondary pollution of rainwater;Water-permeable brick is staggeredly laid, Rainwater is permeated downwards rapidly, enter Infiltration water basic unit, migrate in infiltration basic unit, can only downwards be permeated by hole, Flow velocity is slow, and the time of staying is long, and coarse sands layer, gravel layer and metalling have adsorption capacity, and the nitrogen in rainwater, phosphorus solid particle are entered Row absorption, is degraded by the anaerobe of infiltration basic unit growth, purifying rainwater, the rainwater Jing coarse sands layers bottom after purification Collector pipe flows into retaining clarifier-tank, and retaining clarifier-tank gets up rain water-harvesting as the container for collecting rainwater, prevents take up ground empty Between, filtering synchronous with purification, the rainwater of collection simultaneously, is pumped into water tank and is stored by antiseepage with vaporization prevention by suction pump Come, rinse, flush the toilet and some other non-lives for pouring crops, the daily water consumption of landscape plant, washing bay water, road Water purposes is used, urban pavement discharge pressure is reduced, and by the rainwater purification collected, input is secondary to be used, and is substantially increased The resource utilization efficiency of rainwater, turns waste into wealth, and alleviates the problem of water resources shortage.
The easy construction of retaining clarifier-tank, efficiency high in the present invention, only locating slot 7 need to be directed at during construction according to positioning convex 6 Mode water filtration separator 4 is loaded in retaining well 2, then inject cement mortar into locating slot 7 so that the bonding of water filtration separator 4 is solid It is scheduled in retaining well 2, reliable and stable, simple to operate, quick effective, the reduction of erection time;Water filtration separator 4 plays the work of retardance rainwater With, rainwater can only downwards continue to permeate by treatment hole 5, and the fixed particle remained in rainwater is stopped on the surface of water filtration separator 4, Cannot fall, separate impurity;Retaining clarifier-tank gets up rain water-harvesting as the container for collecting rainwater, filters same with purification Step, with vaporization prevention simultaneously, Stability Analysis of Structures is safe and reliable, prevents take up ground space for antiseepage.
The specific embodiment of the present invention is these are only, but the technical characteristic of the present invention is not limited thereto.It is any with this It is to solve essentially identical technical problem based on bright, realizes essentially identical technique effect, done simple change, etc. With replacement or modification etc., all it is covered by among protection scope of the present invention.

Claims (9)

1. a kind of construction method of sponge urban rainwater collection system, it is characterised in that comprise the steps:
(a) excavation of foundation pit:According to design working drawing, coordinated by the way of artificial grooving using excavator, excavation pit is to designing mark Height, clears up bottom of foundation ditch, and then the bullet line of ink marker is levelling, keeps the gradient of bottom of foundation ditch 2%~3%, controls hanging down for foundation pit side-wall Straight degree is respectively less than 1%, and does support protection, and in the case where bottom of foundation ditch is made, grey wire tag, marks retaining clarifier-tank construction area;
(b) base treatment:Waterproofing geomembrane is laid in the grey coil of mark, is fixed with cement nail every 5~8m, then The original soil of 150~200mm is backfilled on waterproofing geomembrane, and compacting is rolled back and forth, compacted density > 92%, then placement layer by layer Concrete cushion, total height is 250~300mm, reserves 100~150mm's between concrete cushion edge and waterproofing geomembrane The lap of splice, every the reserved ventilating grooves of 10~15m on concrete cushion, and lay 100 from below to up in ventilating groove~ 150mm thickness ventilation anti-seepage sand and 100~150mm thick pervious concrete, every layer of uniform compaction, concrete cushion is poured and completed Afterwards, surface wooden float rubs flat with the hands, and is covered in 12h, conserves 7~8 days;
C () retaining clarifier-tank is built by laying bricks or stones:After concrete cushion acceptance(check), retaining clarifier-tank is built by laying bricks or stones, during pond body is built by laying bricks or stones, will Water string is attached separately on water inlet and delivery port, hammering compacting, and then collector pipe is arranged on water inlet, by drainpipe On delivery port, and enclosed in interface winding 2~3 with waterstop, will be filtered according to the mode that positioning convex is directed at locating slot Water dividing plate loads in retaining well, then injects cement mortar into locating slot, while the slurries for overflowing locating slot are cleared up, from pond body one Side starts to lay retaining well, and brushing cement mortar in each outside wall surface of retaining well, adjacent retaining well is brought into close contact, the laying of retaining well After finishing, cover plate and liquid level well are poured successively, liquid level well bassets 50~100mm, and waterproof geotechnique is then laid on the cover board Film, by waterproofing geomembrane whole cover plate is paved with, and evens up fixation, and reserves the lap of splice of 100~150mm, is then close to pond body Waterproofing geomembrane is enclosed in outer wall laying one, then by the waterproofing geomembrane under the circle waterproofing geomembrane and concrete cushion, cover plate Waterproofing geomembrane complete overlap joint process;
D () water tank is in place:Water tank and suction pump are separately fixed on ground, the water side connection water tank of suction pump, Each road drainpipe is assembled on many siphunculus, then the water side of many siphunculus is connected into the water inlet end of suction pump;
The laying of (e) infiltration basic unit:Retaining clarifier-tank and cover plate are buried with original soil backfill, is often filled out 200~300mm and is manually rammed It is real, the then laying infiltration basic unit on earthing face, the basic unit that seeps water be followed successively by from the bottom to top the thick coarse sands layers of 100~150mm, 200 The thick metalling of~250mm thick gravel layer and 100~150mm, coarse sands layer buries collector pipe, has laid rear vibration tamp, so Lay screed-coat on metalling afterwards, the screed-coat levelling compacting of sand is middle to both sides slope 1~1.5%, finally in screed-coat Upper staggeredly laying water-permeable brick, after water-permeable brick laying is finished, tamps smooth;
(f) water seasoning:After construction is finished, water-permeable brick, and water seasoning are covered with stack of rice straw, curing time is more than 24 hours, Ensure stack of rice straw moistening during maintenance, and forbid idler to trample.
2. the construction method of a kind of sponge urban rainwater collection system according to claim 1, it is characterised in that:Step Abandoned stream screened well is buried in the range of foundation ditch periphery 2m in (d), the water inlet end of abandoned stream screened well is accessed in the water side of many siphunculus, The water side of abandoned stream screened well connects the water inlet end of suction pump.
3. the construction method of a kind of sponge urban rainwater collection system according to claim 1, it is characterised in that:Step C in () before the laying of retaining well, by retaining well unification water saturates, penetration period is 5~6min.
4. the construction method of a kind of sponge urban rainwater collection system according to claim 1, it is characterised in that:Step B the specific practice of concrete cushion maintenance is to use covered rearing with plastic film concrete cushion in (), and water seasoning, is protected during maintenance Card covering material moistening, and forbid idler to trample or continue to construct thereon.
5. a kind of retaining clarifier-tank of the construction method for sponge urban rainwater collection system as claimed in claim 1, its It is characterised by:Including pond body, retaining well, cover plate and water filtration separator, the cover plate is on the retaining well, and the retaining well is equal Even to be distributed in the pond body, the water filtration separator is evenly distributed with drainage in the retaining well on the water filtration separator Hole, is symmetrically distributed with positioning convex on the water filtration separator, be symmetrically distributed with locating slot in the retaining well, the locating slot with The positioning convex matches, the side of the retaining well is equipped with water-flowing trough, and the pond body is respectively provided on two sides with water inlet And delivery port.
6. the retaining clarifier-tank of a kind of construction method for sponge urban rainwater collection system according to claim 5, It is characterized in that:Annular protrusion is provided with the top of the retaining well, between the adjacent annular protrusion drainage channel is formed.
7. the retaining clarifier-tank of a kind of construction method for sponge urban rainwater collection system according to claim 5, It is characterized in that:The cover plate is provided with liquid level well, and the liquid level well penetrates the cover plate, the liquid level well and the retaining well Connection, the liquid level well is provided with well lid, and the well lid is provided with leaking hole.
8. the retaining clarifier-tank of a kind of construction method for sponge urban rainwater collection system according to claim 5, It is characterized in that:The water inlet is provided with water string, and the delivery port is provided with the water string.
9. the retaining clarifier-tank of a kind of construction method for sponge urban rainwater collection system according to claim 5, It is characterized in that:The retaining well is in regular hexagon shape.
CN201611097668.8A 2016-12-02 2016-12-02 Construction method of sponge urban rainwater collection system Active CN106638918B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611097668.8A CN106638918B (en) 2016-12-02 2016-12-02 Construction method of sponge urban rainwater collection system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611097668.8A CN106638918B (en) 2016-12-02 2016-12-02 Construction method of sponge urban rainwater collection system

Publications (2)

Publication Number Publication Date
CN106638918A true CN106638918A (en) 2017-05-10
CN106638918B CN106638918B (en) 2019-12-20

Family

ID=58818245

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611097668.8A Active CN106638918B (en) 2016-12-02 2016-12-02 Construction method of sponge urban rainwater collection system

Country Status (1)

Country Link
CN (1) CN106638918B (en)

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107740326A (en) * 2017-10-13 2018-02-27 重庆工商职业学院 A kind of bridge-type infiltration water backwater square structure
CN107859155A (en) * 2017-12-20 2018-03-30 苏州市清泽环境技术有限公司 High intensity modular combination storage pond
CN107989153A (en) * 2017-12-08 2018-05-04 芜湖德司节能科技有限公司 A kind of novel construction method for building sponge city
CN108560677A (en) * 2018-05-31 2018-09-21 浙江建设职业技术学院 Rain water collecting system
CN108560678A (en) * 2018-05-31 2018-09-21 浙江建设职业技术学院 Hexagon honeycomb structure rainwater-collecting nature diacolation pond
CN108867242A (en) * 2018-08-02 2018-11-23 南京吉欧地下空间科技有限公司 A kind of urban road draining brick and water discharge method
CN109122245A (en) * 2018-09-12 2019-01-04 汤文健 The stone filter-type rainwater-collecting irrigation rig of sponge urban lawn vegetation plantation
CN109385982A (en) * 2018-12-18 2019-02-26 毅康科技有限公司 A kind of ecological dam body with filtering water purification function
CN109989474A (en) * 2017-12-29 2019-07-09 江苏森洋环境建设集团有限公司 A kind of construction method of rain water collecting system
CN110344471A (en) * 2019-07-06 2019-10-18 李厅 A kind of garden paving and the integrated construction method of rainwater-collecting
CN110847328A (en) * 2019-11-19 2020-02-28 春涛国际建筑有限公司 Construction process of sewage collecting well
CN110886378A (en) * 2019-12-04 2020-03-17 北京林业大学 Construction method of water storage vibration reduction device installed under greening road and sidewalk
CN110905062A (en) * 2019-12-04 2020-03-24 北京林业大学 Installation method of honeycomb-shaped water storage, irrigation and vibration reduction periodic structure for city
CN110905071A (en) * 2019-12-04 2020-03-24 北京林业大学 Method for installing square water storage, irrigation and vibration reduction periodic structure for city
CN110924512A (en) * 2019-12-04 2020-03-27 北京林业大学 Square water storage, irrigation and vibration reduction periodic structure for city
CN110984350A (en) * 2019-12-04 2020-04-10 北京林业大学 Water storage system with water storage, vibration reduction and irrigation functions
CN111218878A (en) * 2019-12-04 2020-06-02 北京林业大学 Application of honeycomb-shaped water storage, irrigation and vibration reduction periodic structure for city
CN112095711A (en) * 2020-09-07 2020-12-18 苏州胜景泰园林环境建设有限公司 Rainwater collection and recovery construction method applied to sponge city
CN113404150A (en) * 2021-06-17 2021-09-17 浙江同济科技职业学院 Construction method of rainwater and sewage diversion integrated recovery system
CN114482196A (en) * 2021-12-24 2022-05-13 河北省水文工程地质勘查院(河北省遥感中心、河北省地矿局科技信息中心) Underground seepage water collection and storage regulation system and method
CN114994272A (en) * 2022-05-05 2022-09-02 南京大学 Underground water plug-in type composite monitoring well

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892702A (en) * 2010-08-05 2010-11-24 上海交通大学 Onsite processing device for discarding initial rainwater in heavy rain without occupying area and processing method thereof
CN205475428U (en) * 2016-01-15 2016-08-17 桂平市华鸿污水处理有限公司 Sponge urban rainwater synthesizes collecting system
CN106088124A (en) * 2016-07-28 2016-11-09 中国建筑第四工程局有限公司 A kind of deep basal pit base plate exterior wall blind drainage secondary utilization method and structure
CN106088289A (en) * 2016-07-14 2016-11-09 浙江水利水电学院 A kind of water storage system for sponge Front river course road and construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892702A (en) * 2010-08-05 2010-11-24 上海交通大学 Onsite processing device for discarding initial rainwater in heavy rain without occupying area and processing method thereof
CN205475428U (en) * 2016-01-15 2016-08-17 桂平市华鸿污水处理有限公司 Sponge urban rainwater synthesizes collecting system
CN106088289A (en) * 2016-07-14 2016-11-09 浙江水利水电学院 A kind of water storage system for sponge Front river course road and construction method
CN106088124A (en) * 2016-07-28 2016-11-09 中国建筑第四工程局有限公司 A kind of deep basal pit base plate exterior wall blind drainage secondary utilization method and structure

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107740326B (en) * 2017-10-13 2020-05-26 重庆建工住宅建设有限公司 Bridge type water seepage and water retention square structure
CN107740326A (en) * 2017-10-13 2018-02-27 重庆工商职业学院 A kind of bridge-type infiltration water backwater square structure
CN107989153A (en) * 2017-12-08 2018-05-04 芜湖德司节能科技有限公司 A kind of novel construction method for building sponge city
CN107859155A (en) * 2017-12-20 2018-03-30 苏州市清泽环境技术有限公司 High intensity modular combination storage pond
CN109989474B (en) * 2017-12-29 2020-09-04 江苏森洋环境建设集团有限公司 Construction method of rainwater collection system
CN109989474A (en) * 2017-12-29 2019-07-09 江苏森洋环境建设集团有限公司 A kind of construction method of rain water collecting system
CN108560677A (en) * 2018-05-31 2018-09-21 浙江建设职业技术学院 Rain water collecting system
CN108560678A (en) * 2018-05-31 2018-09-21 浙江建设职业技术学院 Hexagon honeycomb structure rainwater-collecting nature diacolation pond
CN108867242A (en) * 2018-08-02 2018-11-23 南京吉欧地下空间科技有限公司 A kind of urban road draining brick and water discharge method
CN109122245A (en) * 2018-09-12 2019-01-04 汤文健 The stone filter-type rainwater-collecting irrigation rig of sponge urban lawn vegetation plantation
CN109385982A (en) * 2018-12-18 2019-02-26 毅康科技有限公司 A kind of ecological dam body with filtering water purification function
CN110344471A (en) * 2019-07-06 2019-10-18 李厅 A kind of garden paving and the integrated construction method of rainwater-collecting
CN110847328A (en) * 2019-11-19 2020-02-28 春涛国际建筑有限公司 Construction process of sewage collecting well
CN110905071A (en) * 2019-12-04 2020-03-24 北京林业大学 Method for installing square water storage, irrigation and vibration reduction periodic structure for city
CN110924512A (en) * 2019-12-04 2020-03-27 北京林业大学 Square water storage, irrigation and vibration reduction periodic structure for city
CN110984350A (en) * 2019-12-04 2020-04-10 北京林业大学 Water storage system with water storage, vibration reduction and irrigation functions
CN110905062A (en) * 2019-12-04 2020-03-24 北京林业大学 Installation method of honeycomb-shaped water storage, irrigation and vibration reduction periodic structure for city
CN111218878A (en) * 2019-12-04 2020-06-02 北京林业大学 Application of honeycomb-shaped water storage, irrigation and vibration reduction periodic structure for city
CN110886378A (en) * 2019-12-04 2020-03-17 北京林业大学 Construction method of water storage vibration reduction device installed under greening road and sidewalk
CN112095711A (en) * 2020-09-07 2020-12-18 苏州胜景泰园林环境建设有限公司 Rainwater collection and recovery construction method applied to sponge city
CN113404150A (en) * 2021-06-17 2021-09-17 浙江同济科技职业学院 Construction method of rainwater and sewage diversion integrated recovery system
CN113404150B (en) * 2021-06-17 2023-12-08 浙江同济科技职业学院 Construction method of rain and sewage diversion integrated recovery system
CN114482196A (en) * 2021-12-24 2022-05-13 河北省水文工程地质勘查院(河北省遥感中心、河北省地矿局科技信息中心) Underground seepage water collection and storage regulation system and method
CN114482196B (en) * 2021-12-24 2024-02-27 河北省水文工程地质勘查院(河北省遥感中心、河北省地矿局科技信息中心) Underground water seepage collection and regulation system and regulation method thereof
CN114994272A (en) * 2022-05-05 2022-09-02 南京大学 Underground water plug-in type composite monitoring well

Also Published As

Publication number Publication date
CN106638918B (en) 2019-12-20

Similar Documents

Publication Publication Date Title
CN106638918A (en) Construction method for sponge city rainwater collection system
CN106759825B (en) Construction method of sponge urban green land water storage system
CN204959952U (en) Recessed formula greenery patches rainwater regulation dispatch pond and distributed rainwater regulation dispatch pond system
CN206752614U (en) A kind of sponge-type road sinks formula afforests dividing strip Rainwater collection system
CN105089142A (en) Low elevation greenbelt rainwater regulation scheduling pool and distributed rainwater regulation scheduling pool system
CN106193261B (en) A kind of Collapsible Loess District rain flood harvests step man-made lake system and design method
CN110016886B (en) Riverway near natural ecological embankment
CN106917522B (en) A kind of Outdoor Parking position system based on sponge the idea of the city
CN106193245B (en) A kind of paddy field underground reservoir and its construction method for sponge city
CN206571217U (en) Outdoor Parking position system based on sponge the idea of the city
CN112391997B (en) Ecological river bank structure for sponge city construction
CN107989153A (en) A kind of novel construction method for building sponge city
CN202627166U (en) Novel water-discharging ecological zone for town road
CN208105449U (en) A kind of ecostagnation pond
CN207228292U (en) One kind omits water system in printing slowly after first catchmenting
CN108086459A (en) A kind of construction method of sponge urban green space water storage system
CN210684945U (en) Rainwater collecting pool
CN208501715U (en) A kind of Rain Garden
CN207727719U (en) Ooze storage row's rainwater piping lane
CN214301528U (en) Sponge transformation system for urban river retaining wall
CN107558587A (en) One kind omits water system in printing slowly after first catchmenting
CN213358503U (en) Natural bank slope protective structure based on sponge city idea
JP7429922B2 (en) storage system
CN105350637B (en) Urban green space subsurface stormwater is regulated and stored device
CN210916868U (en) Novel municipal administration permeable pavement road drainage structures

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20191125

Address after: 315000 room M103, building 1, Lane 60, siyanqi street, Yinzhou District, Ningbo City, Zhejiang Province

Applicant after: NINGBO SHUNXING GARDEN CONSTRUCTION CO., LTD.

Address before: 323800 Songyuan New Road, Qingyuan County, Lishui City, Zhejiang Province, 17

Applicant before: Zhejiang Xin Xin Construction Co., Ltd.

TA01 Transfer of patent application right
GR01 Patent grant